Upload
engr-piagola
View
217
Download
0
Embed Size (px)
Citation preview
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 1/13
Project Approach
Project
Reliabi l i ty
Approach
Ronald SchopSr. Reliability Engineer
www.weibull.nl
November 2003
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 2/13
Project Approach2
Act iv i t ies
Historical InformationField Performance
Targets / Baseline
Risk Analysis
Focus on “HOT” Items
Reliability Growth
FRACAS
Reliability Forecast
PAST
NOW
GOAL
RISKS
FOCUS
CONTROL
CORRECT
FORECAST
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 3/13
Project Approach3
His tor ical In form at ion
Gather Information of Previous Designs:• Field Problems Solved
• Quality Problems from the Past
• Failures discovered at Testing
• Production Problems
BEST POSSIBLE Risk Analysis Input
Avoid BOOBY TRAPS from the past.
If there is no Previous Design available, use the data from a similar
Component or System … ...
Lessons Learned … ...
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 4/13
Project Approach4
Field Perfo rmance
Warranty
Reliability
Durability
R&M Costs
Where are we Now … ...
Gather Performance Indicators of Current Design:
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 5/13
Project Approach5
Targets / Basel ine
Decide if a LOAD CYCLE DIAGRAM
measurement / definition is required.
Where to GO to … ...
Define the specific System / ComponentRELIABILITY TARGET and WARRANTY
TARGET
Create a System / Component BASELINE,including Targets and clear User Profiles
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 6/13
Project Approach6
S y s t e m
F a i l u r e R A T E
Time
System Bathtub Curve
Warranty and Reliab i l i ty Targets
Warranty Reliability Durability
R&M Costs
Show the Difference ...
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 7/13Project Approach7
Sample Combined Target Plo t Combined Warranty & Reliability Target
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 8/13Project Approach8
Risk Analys is
General Risk Prediction Analysis Simultaneous Engineering Teams
Identify all Risks
Define Activities
Assign Risk Reduction Values per Activity
FMEA on Design & Process Detailed Risk Analysis where required
FTA - Fault Tree Analysis For Safety Issues and Complex Systems
What are the RISKS … ...
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 9/13Project Approach9
Focus on “HOT” Items
FMEA’s will give additional focus.
RVP (Reliability Validation Plan)
– Objective % Confidence gained per planned Activity.
– Shows “Uncovered Failure-Modes” & “Overkill’s”
– Shows contribution (%C) per Activity. – Cost Effective Testing / Activity Plan.
Derive the “HOT” Items from GRPA Use “Gut Feeling” too … ... !
Objectivity and Focus ...
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 10/13Project Approach10
Rel iab i l ity Grow th
General Risk Reduction Plan
– Keep track of ALL Risks identified
Crow-AMSAA Validation Testing Monitoring
– Development Process Monitoring
– Reliability Growth and Tracking – Forecast Reliability Performance
RVP’s Realisation in Time
– Milestone settings / Checkpoints
Weibayes for significant Components
Weibull “IF” Failures occur… ...
Control Growth-Process … ...
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 11/13Project Approach11
FRACAS
ALL failures to report to the
Failure Review Board (FRB)
FRB to address each issue to appropriate
Person / Department.
FRB makes sure that proposed change is indeed
an improvement / solution.
Correct and Control … ...
Failure Report And Corrective Action System
There are no INCIDENTS!
Each Failure is the beginning of a Trend... The “I - Word” … …
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 12/13Project Approach12
Single Failure-Modes
With Failures: OLD / NEW Testing Results: Weibull Analysis
Field Failure Forecast
No Failures: RVP or Weibayes Analysis
Minimal Field Failure Forecast
Reliab i l i ty Forecas t
Systems
Crow-AMSAA Analysis Forecast System Reliability using Instantaneous
mode.
Forecast … ...
7/27/2019 Project Approach.pptx
http://slidepdf.com/reader/full/project-approachpptx 13/13Project Approach13
SUMMARY
We have the medicine,we just have to take it !
We have the DATAPrevious problems
We have the TOOLS
GRPA; FMEA; FTA; RVP; etc.
We have the METHODS
FRB; Weibull; Crow-AMSAA
PAST
NOW
GOAL
RISKS
FOCUS
CONTROL
CORRECT
FORECAST