PROJECT NO. 8141707 117 Lake Street - TML Library Electrical Atrium Upgrades PROJECT COMPLETION December 2013 PROJECT DESIGNER BC Capital Projects Management PROJECT TYPE / FUNDING A&R Academic Allowance TOTAL PROJECT COST $40,000 AREA CONTRACTOR DEPARTMENT PROJECT DESCRIPTION: Library Services requested electrical improvements for the atrium space and one classroom at 117 Lake Street Library. The project consisted of replacing the existing floor in the atrium, that once was a fountain, and providing electrical outlets for general use. Perimeter wiremold electrical and data outlets were installed to Classroom 112. The gravel opening underneath the staircase was in-filled as part of the scope of work. New lounge furniture was provided for by the requesting Department. BEFORE: AFTER: FLOOR PLAN: PROJECT COST $/SF $14 / S.F. 2,840 S.F. BC Special Projects Group Library Services

Project Card - 2013

Embed Size (px)

Citation preview

Page 1: Project Card - 2013

PROJECT NO. 8141707117 Lake Street - TML Library

Electrical Atrium Upgrades

PROJECT COMPLETION December 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING A&R Academic Allowance

TOTAL PROJECT COST $40,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Library Services requested electrical improvements for the atrium space and one classroom at 117 Lake Street Library. The project consisted of replacing the existing floor in the atrium, that once was a fountain, and providing electrical outlets for general use. Perimeter wiremold electrical and data outlets were installed to Classroom 112. The gravel opening underneath the staircase was in-filled as part of the scope of work. New lounge furniture was provided for by the requesting Department.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $14 / S.F.

2,840 S.F.

BC Special Projects Group

Library Services

Page 2: Project Card - 2013

PROJECT NO. 8141203Bapst / Burns Library

Burns Interior Upgrades

PROJECT COMPLETION August 2013

PROJECT DESIGNER McGinley Kalsow & Associates

PROJECT TYPE / FUNDING R&R Academic & Administrative

TOTAL PROJECT COST $145,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

This project in the Trustee Meeting Room entailed historial reconstruction of cast stone and plaster elements. A conservator was partnered with a restoration contractor to properly treat the original features of this room where plaster was originally used to create a detailed wood appearance.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $73 / S.F.

2,000 S.F.

Haven Restoration, Inc.

President's Office

Page 3: Project Card - 2013

PROJECT NO. 8141402Connolly Faculty Center

Connolly Faculty Center Greenhouse Connector - Phase 2

PROJECT COMPLETION November 2013

PROJECT DESIGNER BC Capital Projects Management / Daigle Engineers

PROJECT TYPE / FUNDING A&R Academic & Administrative

TOTAL PROJECT COST $130,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

The project involved a continuation of a previous renovation of the greenhouse attached to the Connolly Faculty Center. This work specifically targeted the restoration of the historic conservatory. Included in the scope of the project was the structural reconstruction of the roof of the conservatory.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $481 / S.F.

270 S.F.

BC Special Projects Group

Office of the Provost

Page 4: Project Card - 2013

PROJECT NO. 8141404Conte Forum

4th Floor Renovations - Suite 412

PROJECT COMPLETION August 2013

PROJECT DESIGNER Oudens Ello Architecture

PROJECT TYPE / FUNDING A&R Academic & Administrative

TOTAL PROJECT COST $265,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

This project involved renovating an existing open office area on the fourth floor of Conte Forum into six new enclosed offices for the Olympic Sports Coaching Staff. Included in the work was the creation of a new copier alcove and a receptionist area.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $60 / S.F.

4,410 S.F.

Consigli

Athletics

Page 5: Project Card - 2013

PROJECT NO. 8141406Corcoran Commons

2nd Floor Flooring Upgrades & Bureau of Conferences Space Upgrades

PROJECT COMPLETION August 2013

PROJECT DESIGNER Perkins & Will

PROJECT TYPE / FUNDING A&R Academic & Administrative

TOTAL PROJECT COST $127,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Auxiliary services requested that the 2nd floor spaces of Corcoran Commons be upgraded with new flooring and overall improvements to the B.O.C. Heights, Newton, and Boston Function Rooms. Included in the scope of work was replacement of the existing carpet, paint, addition of acoustic panels, and replacement & refurbishment of wood side service door.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $21 / S.F.

5,915 S.F.

BWK Construction

Auxiliary Services

Page 6: Project Card - 2013

PROJECT NO. 8131709Devlin Hall

Kruckenberg Lab - Room 316

PROJECT COMPLETION April 2013

PROJECT DESIGNER DiMella Shaffer

PROJECT TYPE / FUNDING A&R Academic Allowance

TOTAL PROJECT COST $115,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Earth and Environmental Sciences requested a renovation of lab 316 in Devlin Hall, to accommodate new faculty member Dr. Seth Kruckenberg. The scope of work created a new room for a SEM Microscope, that also required large double doors that can be opened into the general lab for teaching purposes. The rest o fhte lab space was reconfigured with the existing counters which were modified for the new reconfiguration.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $170 / S.F.

678 S.F.

BC Special Projects Group

Earth & Environmental Sciences

Page 7: Project Card - 2013

PROJECT NO. 8141552Flanagan House

Living Room Renovation

PROJECT COMPLETION October 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING Other

TOTAL PROJECT COST $13,500

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Flanagan House Living Room, used by the Philosophy Department as a visiting scholars residence and as a meeting/function room, needed to have light fixtures installed on the walls and ceiling to adequately light surfaces for weekly meetings. Before the upgrade, the room was to dark and un-inviting. Project included painted walls, trim and new furniture purchased (by requesting dept.) to seat 10-12 people and arranged with both living and meetings in mind.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $40 / S.F.

330 S.F.

BC Special Projects Group

Philosophy

Page 8: Project Card - 2013

PROJECT NO. 8131556Flynn RecPlex Center

CT 5 to Spin Room

PROJECT COMPLETION March 2013

PROJECT DESIGNER S3 Design

PROJECT TYPE / FUNDING R&R Academic & Administrative

TOTAL PROJECT COST $135,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

The project involved the conversion of an existing raquetball court in the Flyn Rec Plex into a spin classroom. The room was designed to accommodate upwards of 20 cycling stations and included one small enclosed office.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $87 / S.F.

1,560 S.F.

BWK Construction

Athletics

Page 9: Project Card - 2013

PROJECT NO. 8141210Flynn RecPlex Center

Pool Refurbishment

PROJECT COMPLETION June 2014

PROJECT DESIGNER Counselman/Hunsaker

PROJECT TYPE / FUNDING R&R Academic & Administrative

TOTAL PROJECT COST $240,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

This project was to refinish the pool interior by chipping off top layer of finish and replastering the surface. New pool tile was installed, along with new starting blocks.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF N.A. / S.F.

N.A.

South Shore Gunite

Athletics

Page 10: Project Card - 2013

PROJECT NO. 8121706Fulton Hall

Office Suite 254

PROJECT COMPLETION January 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING A&R Academic Allowance

TOTAL PROJECT COST $25,500

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Renovate existing office suite and convert room 254E (previously used as a storage room) into office space by installing a new glazed door and typical Fulton office pendant lighting. New 2x2 lighting in rooms 254 only. New carpet and paint entire suite. Room 254E meets all HVAC requirements to be an office. Provide air and water balancing at all existing fan coil units, clean coils and confirm all HVAC is working properly.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $25 / S.F.

1,000 S.F.

BC Special Projects Group

Carroll School of Management

Page 11: Project Card - 2013

PROJECT NO. 8141407Fulton Hall

Student Lounge Upgrades

PROJECT COMPLETION August 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING A&R Academic & Administrative

TOTAL PROJECT COST $105,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

CPM Redesigned the Graduate Student Lounge in Fulton Hall for GCSOM, rooms 124, 124A & B to be more functional and aesthetically pleasing. Included in the renovation was the addition of one private meeting space with access or the main corridor, an enlarged Kitchen space with full size refrigerator and microwave. We also opened up the general space to make it more conducive to socializing and or quiet study area with a large monitor on the wall. To accomplish this we introduced smaller square tables with four chairs for each with no arms that would be extremely flexible to reconfigure, we purposely eliminated sofas and soft seating to encourage integration. We also designed a more applicable storage closet for their variety of needs.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $142 / S.F.

740 S.F.

BC Special Projects Group

Carroll School of Management

Page 12: Project Card - 2013

PROJECT NO. 8143401General Campus

Landscape - Academic Quad

PROJECT COMPLETION August 2013

PROJECT DESIGNER Stephen Stimson Associates

PROJECT TYPE / FUNDING Major

TOTAL PROJECT COST $3,000,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

This project consisted of a continuation of landscape improvements outlined in our master plan for creating linked quadrangles on our campus. The academic courtyard in front of Gasson Hall was re-worked to include new green space and addressing ADA improvements.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $86 / S.F.

34,580 S.F.

McCourt

Other

Page 13: Project Card - 2013

PROJECT NO. 8083821Higgins Hall

Lab 120 Renovation - Dr. He

PROJECT COMPLETION June 2013

PROJECT DESIGNER isGenuity

PROJECT TYPE / FUNDING Major - Higgins Master Plan

TOTAL PROJECT COST $152,500

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

The Physics Department submitted A&R 8302912 for new Physics faculty hire, Dr. Ruihua He. The scope of work to accommodate Professor He is for the accommodation of a new 6’ fume hood in Lab 120, replacing an existing 4’ hood, and the relocation of an existing sink. Associated work will also include countertops and cabinets reconfiguration to accommodate the new hood. The reorganization of the support space in 120C will include new casework, shelving, finishes and furniture.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $147 / S.F.

1,040 S.F.

CE Floyd

Physics

Page 14: Project Card - 2013

PROJECT NO. 8083822Higgins Hall

Labs 400/410 & 420 Renovation - Dr. Van Opijnen

PROJECT COMPLETION June 2013

PROJECT DESIGNER isGenuity

PROJECT TYPE / FUNDING Major - Higgins Master Plan

TOTAL PROJECT COST $240,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

The Biology Department submitted A&R 2733112 for new Biology faculty hire, Dr. Tim van Opijnen. The scope of work to accommodate Professor van Opijnen is for the accommodation of a new chemical storage room replacing an existing dark room, and removal of a sink in Lab 400. Associated with this A&R is also the elimination of the wall between labs 400 and 410, creating one large sized lab to which individual bench space can be assigned to a PI, consistent with one of the goals identified in the Master Plan. Work will also include providing a new lab bench and other changes needed as a result of eliminating the wall between the two labs. Work in Bio-informatics space 420 is limited to adding a door with a sidelight, and providing new open shelving in lieu of cabinets.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $246 / S.F.

975 S.F.

CE Floyd

Biology

Page 15: Project Card - 2013

PROJECT NO. 8121571Kenny Cottle Library

Institute for Scientific Research - Phase 2

PROJECT COMPLETION April 2013

PROJECT DESIGNER Marguilles Perruzzi

PROJECT TYPE / FUNDING Other

TOTAL PROJECT COST $875,500

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

This project consisted of the renovation of a portion of the second floor of Kenny Cottle Library on Boston College’s Newton Campus, in order to accommodate the relocation and consolidation of staff for the Institute for Scientific Research (ISR), following up on a first phase of work completed in 2011. The scope of work included new wall construction as needed to create individual office space, a conference room and support spaces.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $124 / S.F.

7,080 S.F.

Acella

Institute for Scientific Research

Page 16: Project Card - 2013

PROJECT NO. 8131563Maloney Hall

BCPD Kitchen Report Room

PROJECT COMPLETION July 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING A&R Undesignated

TOTAL PROJECT COST $47,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Capital Projects Management created a separate report writing room for the BCPD in their Maloney Hall suite. The report room had been sharing space with the new Dispatch manager’s office in 112A Maloney. We relocated computers to new report room 106 which formally housed the lockers for security staff of which we relocated the lockers to the locker rooms 126B and 130A. We extended the report room 106 by opening up existing corridor wall and adding a door to the back corridor and putting one way glass on the door from the kitchen, gaining needed space.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $104 / S.F.

450 S.F.

BC Special Projects Group

Boston College Police Department

Page 17: Project Card - 2013

PROJECT NO. 8131557Maloney Hall

BCPD Office - Detective Bureau Conference Room

PROJECT COMPLETION March 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING A&R Undesignated

TOTAL PROJECT COST $32,500

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

The project was about the relocation of the Detectives Bureau to accommodate a large conference room. This new space also has additional audio/visual/internet capabilities to act as an emergency operations center, if need be. Also included in the work was the conversion of two small bunk rooms into office space.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $62 / S.F.

525 S.F.

BC Special Projects Group

Boston College Police Department

Page 18: Project Card - 2013

PROJECT NO. 8141409Maloney Hall

Hillside Café Flooring Upgrades

PROJECT COMPLETION August 2013

PROJECT DESIGNER Perkins & Will

PROJECT TYPE / FUNDING A&R Academic & Administrative

TOTAL PROJECT COST $100,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

The project consisted of removing the existing vinyl flooring from the dining room and servery area and replacing it with new terrazzo tile flooring. Some modest millwork replacement is needed as well at existing millwork stations.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $42 / S.F.

2,365 S.F.

BWK Construction

Auxiliary Services

Page 19: Project Card - 2013

PROJECT NO. 8141410McElroy Commons

Lobby Finish Upgrades

PROJECT COMPLETION August 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING A&R Academic & Administrative

TOTAL PROJECT COST $115,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

The existing McElroy Lobby was last renovated in the 80’s and with the newly completed Stokes Hall next door, looked tired and out of date. The existing vending machines structure was removed and the vending machines were relocated to a nearby corridor. All new wood panel half height walls (to compliment the bookstore interior/cabinets) were constructed and new lobby furniture with tablet arms were purchased.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $136 / S.F.

850 S.F.

BC Special Projects Group

General Campus

Page 20: Project Card - 2013

PROJECT NO. 8083315Merkert Chemistry Center

Undergraduate General Teaching Labs

PROJECT COMPLETION August 2013

PROJECT DESIGNER Payette Associates

PROJECT TYPE / FUNDING Major - Merkert Master Plan

TOTAL PROJECT COST $4,410,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Due to the increased student population of undergraduates majoring in Chemistry, the Chemistry Department renovated three general purpose undergraduate teaching labs (Labs 113, 116 and 120) to increase the student count of their current labs of 18 students per lab to possibly 22 stations per lab. The labs were updated to provide a more functional layout for their teaching, in keeping with today’s standards for instruction, allowing for clear sight lines, better student and instructor focus, and open circulation. In addition, all support rooms associated with these labs were renovated and reconfigured as required.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $617 / S.F.

7,150 S.F.

Wise Construction

Chemistry

Page 21: Project Card - 2013

PROJECT NO. 8133602Rubenstein Hall

Rubenstein Upgrades - Res Life Lounge

PROJECT COMPLETION August 2013

PROJECT DESIGNER Cannon Design

PROJECT TYPE / FUNDING Major - Residential Life

TOTAL PROJECT COST $725,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

As part of larger infrastructure improvements to Rubenstein Hall to provide fire protection and upgrading the fire alarm system, a component project was the creation of new lounge space for the building’s community. Consistent with other similar lounge renovations that have occurred in previous summers, the Rubenstein Lounge is made up of three spaces: social, study and spiritual. The scope of work included a new entrance and modest ADA improvements, as well as interfacing with adjacent administrative space.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $308 / S.F.

2,350 S.F.

Shawmut Design & Construction

Residential Life

Page 22: Project Card - 2013

PROJECT NO. 8141551Southwell Career Center

Career Center Renovations - Phase I

PROJECT COMPLETION August 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING A&R Undesignated

TOTAL PROJECT COST $37,500

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Due to a recent retirement within the Career Center- space on the first floor of Southwell Hall has become available. CPM facilitated a plan that helped the Career Center re-shuffle staff, graduate students and work studies within the basement of Southwell Hall and the first floor. This required furniture/staff relocation and evaluation of power and data. We cleaned & painted the entire interior of the basement and first floor. We also replaced the carpet on the first floor.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $7 / S.F.

5,200 S.F.

BC Special Projects Group

Student Affairs

Page 23: Project Card - 2013

PROJECT NO. 8141412Stuart House

Adjunct Faculty Office Renovation

PROJECT COMPLETION August 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING A&R Academic & Administrative

TOTAL PROJECT COST $10,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

This project was to renovate and upgrade the Shared Adjunct Professor's Office of the Law School. The project work included new finshes to all walls, a new ceiling, a new carpet, new window sills and new window treatments. The existing solid door was replaced with a fully glazed door. The project also included upgrades to the power, data and lighting.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $31 / S.F.

320 S.F.

BC Special Projects Group

Law School

Page 24: Project Card - 2013

PROJECT NO. 8141411Stuart House

Office Suite for Associate Dean

PROJECT COMPLETION August 2013

PROJECT DESIGNER BC Capital Projects Management

PROJECT TYPE / FUNDING A&R Academic & Administrative

TOTAL PROJECT COST $10,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

This project was to relocate an Associate Dean of the Law School into a newly renovated office. The work involved the construction of a new partition to create the office. The project work included also new finshes, a new ceiling, new carpet, and new built-in bookcases. The project also included upgrades to the power, data, new lighting and a new wall mounted air conditioner. Additional work involved renovating existing storage areas to relocate existing files from new office area and repainting the Associate Dean's former office.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $11 / S.F.

900 S.F.

BC Special Projects Group

Law School

Page 25: Project Card - 2013

PROJECT NO. 8141414Upper Campus

UC Renovate Res Hall Bathrooms (Triples to Quads)

PROJECT COMPLETION August 2013

PROJECT DESIGNER Lavallee Brensinger Associates

PROJECT TYPE / FUNDING Major - Residential Life

TOTAL PROJECT COST $575,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Student Affairs requested the creation of 20 new freshman quads with the conversion of existing triples with bathrooms, by eliminating the bathrooms and adding the fourth bed to each room. The work was completed in five residence halls on Upper Campus: Cheverus, Fitzpatrick, Gonzaga, Loyola, and Xavier. The scope of work included removing all plumbing fixtures, ceramic tiles, etc, and creating a new layout to accommodate four beds, along with associated other res life furnishings.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $144 / S.F.

4,000 S.F.

Chapman Construction

Residential Life

Page 26: Project Card - 2013

PROJECT NO. 8113655Williams Hall

Lounge Upgrades

PROJECT COMPLETION August 2013

PROJECT DESIGNER CBT Architects

PROJECT TYPE / FUNDING Major - Residential Life

TOTAL PROJECT COST $850,000

AREA

CONTRACTOR

DEPARTMENT

PROJECT DESCRIPTION:

Following the renovations of the lounge/library/study areas in the first year residence halls, Williams Hall is the first project for second-year halls. Roncalli Hall & Welch Hall, due to the grouping of all three Res Halls, considered "one community", will be renovated in 2014.

BEFORE:

AFTER:

FLOOR PLAN:

PROJECT COST $/SF $230 / S.F.

3,695 S.F.

JK Blackstone

Residential Life