Ardustat Project Checklist SyRs – Completed SDS – In progress Project- GUI Cleanup – In progress Hardware Replacement - Completed Actual Testing – In Progress (Still trying to find assistance) Final Report – N/A

Project Checklist ◦ SyRs – Completed ◦ SDS – In progress ◦ Project- GUI Cleanup – In progress Hardware Replacement - Completed Actual Testing – In

Embed Size (px)

Citation preview

Page 1: Project Checklist ◦ SyRs – Completed ◦ SDS – In progress ◦ Project-  GUI Cleanup – In progress  Hardware Replacement - Completed  Actual Testing – In

ArdustatProject Checklist◦ SyRs – Completed◦ SDS – In progress◦ Project-

GUI Cleanup – In progress Hardware Replacement - Completed Actual Testing – In Progress (Still

trying to find assistance)◦ Final Report – N/A

Page 2: Project Checklist ◦ SyRs – Completed ◦ SDS – In progress ◦ Project-  GUI Cleanup – In progress  Hardware Replacement - Completed  Actual Testing – In

PCB built by Doug Programmer and missing resistor received SDS in progress

Cheapstat Status

Page 3: Project Checklist ◦ SyRs – Completed ◦ SDS – In progress ◦ Project-  GUI Cleanup – In progress  Hardware Replacement - Completed  Actual Testing – In

Order qty 2 PCB from PCB express◦ Kyle meet with Tom Carroll

Receive parts order for two Cstat prototypes Assemble D. Jackson’s board with parts in

hand Contact Dr. Waters for test supplies Complete 1st draft SDS