PPrroojjeecctt CClloossuurree RReeppoorrtt
Version 1.0 Updated on: July 11, 2009
Project Closure Report Template Page 2 of 11
Overview What is a Project Closure Report? A Project Closure Report is a document which formalizes the closure of the project. It provides confirmation that the criteria for customer acceptance have been met and requests sign-off from the Project Sponsor to close the project.
A Project Closure Report includes:
• A formal list of completion criteria • Confirmation that each completion criterion has been met • A list of outstanding business activities, risks and issues • A set of closure actions (to hand over project deliverables / documentation, terminate
suppliers, release resources and undertake closure communication) • A request for project closure approval.
When to use a Project Closure Report A Project Closure Report is undertaken at the start of the Project Closure phase (i.e. after the end of the Project Execution phase). The document is usually prepared by the Project Manager and presented to the Project Sponsor for sign-off. Following sign-off, a suite of closure activities is undertaken to formally close the project. After these activities have been completed, a Post Implementation Review is undertaken to measure the success of the project and identify lessons learnt for future projects.
Introduction
Project Description / Background
Project Initiation Document.>
Project Executive Summary
Project Executive Summary
<Please provide an executive summary of the contents in the report. This section should be written last. >
Project Team Structure
Project Team Structure
<Please provide a comprehensive list of the project team members. - Include internal, external, and 3rd parties (vendors, etc.)>
Project Closure Report Template Page 3 of 11
Project Performance This section identifies the criteria required to complete the project and any outstanding items which still need to be undertaken even though the project may be ready for completion.
Completion Criteria (i.e. Project Scope) In the table below, list the criteria which must be met to confirm that the project is completed. For each criteria listed, assess whether or not it has been achieved to the satisfaction of the customer.
Completion Criteria
Performance Criteria Satisfaction Level Comments
Objectives:
• All project objectives have been achieved (as defined in the C.A.R. and Project Initiation documents)
Exceeded
Met
Did Not Meet
Deliverables:
• All deliverables have been completed (as defined in the C.A.R. and Project Initiation documents)
Exceeded
Met
Did Not Meet
Deliverables:
• All deliverables have been accepted by the customer (as defined in the C.A.R. and Project Initiation documents)
Exceeded
Met
Did Not Meet
Outstanding Items In the table below, list any outstanding items which still need to be undertaken even though the project has satisfied the above completion criteria. For each item, list the actions required to be undertaken and the Owner responsible for undertaking the action.
Outstanding Items
Item Action Owner
Activities <List all activities or tasks which have not yet been completed (as defined in the Project Plan) If none, please mark as ‘none.’>
<Name>
Risks <List all business risks which have not yet been fully mitigated> <Name>
Issues <List any current issues which are impacting on the business and have not yet been fully resolved>
<Name>
Project Closure Report Template Page 4 of 11
Project Budget / Cost In the table below, reflect the budget / cost performance of the project. This table may also be copied into Excel for more dynamic execution and calculations.
Project Budget / Cost
Line Item Budget Actuals (Over) / Under Budget
Hardware: $ $ $( ) / $
Software: $ $ $( ) / $
Contractual Services: $ $ $( ) / $
Other: $ $ $( ) / $
Totals: $ $ $( ) / $
Performance Criterion
Project Cost Exceeded Met Did Not Meet
Project Quality In the table below, please fill in the key deliverables and describe, according to the Quality Plan, Measurements, and Customer Satisfaction Survey, if each deliverable Exceeded, Met, or Did Not Meet the customer’s expectation.
Project Quality
<Enter Key Deliverable> Exceeded Met Did Not Meet
<Enter Key Deliverable> Exceeded Met Did Not Meet
<Enter Key Deliverable> Exceeded Met Did Not Meet
<Enter Key Deliverable> Exceeded Met Did Not Meet
<Enter Key Deliverable> Exceeded Met Did Not Meet
<Enter Key Deliverable> Exceeded Met Did Not Meet
<Enter Key Deliverable> Exceeded Met Did Not Meet
<Enter Key Deliverable> Exceeded Met Did Not Meet
<Enter Key Deliverable> Exceeded Met Did Not Meet
<Enter Key Deliverable> Exceeded Met Did Not Meet
Project Closure Report Template Page 5 of 11
Lessons Learned and Best Practices This section summarizes the project close lessons learned and identifies key best practices.
Lessons Learned In the table below, briefly summarize Lessons Learned or refer to the project document PMO - Project Lessons Learned Methodology.
Lessons Learned
<Lessons Learned>
Best Practices In the table below, briefly summarize best practices observed and/or utilized for this project.
Best Practices
<Best Practices>
Project Conclusion In the table below, please provide a brief concluding statement for the report.
Project Conclusion
<Concluding Statement>
Project Closure Report Template Page 6 of 11
Project Closure Transition This section outlines the next steps required to finalize the closure of the project.
This includes (but may not be limited to):
1. Hand-off of deliverables and documentation to the customer
2. The termination of supplier contracts
3. The release of project resources back to the business (or the marketplace)
4. The communication to all stakeholders that the project is now formally closed.
Deliverables Develop a hand-off plan for the release of all project deliverables to the customer. An example format is included below. This table may also be copied into Excel for more dynamic execution:
Deliverable Current New© Hand-over Plan Type Owner Location Owner Location Activities Date Owner HR / General Ledger System Modules
Name Ex. FTL, DFB
Name Ex. FTL, DFB
• Handover system maintenance
• Handover operational support
• Handover system documentation
Date Name
Project Closure Report Template Page 7 of 11
Documentation Develop a hand-off plan for the release of all project documentation to the customer. An example format is included below. This table may also be copied into Excel for more dynamic execution:
Documentation Current New© Hand-over Plan Type Owner Division Owner Division Activities Date Owner Project Initiation:
• Project Initiation Document • Project Scope Deliverables
Document • Business Requirements
Name Ex. FTL, DFB
Name Ex. FTL, DFB
Activity
Date Name
Project Planning
• Project Plan (if necessary) • Resource Plan • Financial Plan • Quality Plan • Acceptance Plan • Training Manuals • Reference Guides • User Manuals • Communication Collateral (if
any)
Name Ex. FTL, DFB
Name Ex. FTL, DFB
Activity
Date Name
Project Execution
• Change Control Process • Change Form • Change Register • Risk Register (if requested by
customer)
Name Ex. FTL, DFB
Name Ex. FTL, DFB
Activity
Date Name
Project Close-Out
• Lessons Learn Document • Results from Customer
Satisfaction Surveys (Quality) • Service Level Agreement • Best Practices
Project Closure Report Template Page 8 of 11
Suppliers Develop a hand-off plan for the termination of project supplier contracts. An example format is included below. This table may also be copied into Excel for more dynamic execution:
Supplier Name
Contract Reference
Termination Activity© Release Date Activity Owner
Supplier Name Contract (SOW) Ref. No.
• Notify supplier of termination • Release supplier resources • Return supplier assets • Pay supplier invoices
Date activity to be completed by
Name of person responsible for activity
Resources Develop a hand-off plan for the release of all project resources (including staff and equipment). An example format is included below. This table may also be copied into Excel for more dynamic execution:
Resource Name
Current Designation
Release Activity Release Date Activity Owner
Staff Name Project Role • Notify staff member of release • Release staff member • Return staff assets • Pay final staff salary
Date staff member released
Name of person responsible for activity
Equipment Type Equipment Purpose
• Identify new owner • Undertake equipment sale • Release equipment • Update General Ledger
Date equipment released
Name of person responsible for activity
Equipment Develop a plan to identify, decommission, dispose, store, or reassign any related hardware that is being replaced. An example format is included below. This table may also be copied into Excel for more dynamic execution: Equipment Name
Current Designation
Release Activity Release Date Activity Owner
Equipment Type Equipment Purpose
• Identify new owner • Undertake equipment sale • Release equipment • Update General Ledger • Decommission equipment
Date equipment released, decommissioned, reassigned, etc.
Name of person responsible for activity
Project Closure Report Template Page 9 of 11
Communication Develop a plan to communicate the project closure to all stakeholders and interested parties. An example format is included below. This table may also be copied into Excel for more dynamic execution:
Target Audience
Intended
Message
Method Used©
Dispatch Date
Dispatch Owner
Recipient Names or Groups for receipt of messages
• Project has been successfully completed and is now closed
• Benefits realized due to success of the project
• Lessons learned from project
• Email and formal letter for each recipient
• Special Board presentation on benefits realized
• Undertake ‘Post Implementation Review’ and email to key stakeholders
Date when communication should be released
Name of the person responsible for communication
Supporting Documentation Attach any documentation that is relevant to the Project Closure Report. Examples include:
• Project documentation generated to date (Project Initiation, Project Plan, Resource Plan, Financial Plan, Quality Plan or Acceptance Plan) which relates to the project closure criteria specified.
• Other relevant information or correspondence.
Project Closure Report Template Page 10 of 11
Document Approvals
Role Name Signature© Date Technology Project Management Office, Closure Review Sponsor
Technology Executive Sponsor, VP/CTO
Business Executive Sponsor, Director/VP
Technology Project Manager
Project Closure Report Template Page 11 of 11
Version Control Version Control: 1.0 Revision Date: Change: Revision Made By: