Upload
buixuyen
View
223
Download
0
Embed Size (px)
Citation preview
1
PROJECT CONTROL
PRINCIPLESBernd Madauss
International Space University
Strasbourg [email protected]
2010
2
PPerformance Dependence of
Parameters
SSchedule
CCosts
Optimization of Project Parameters:Performance (P), Schedule (S) and Cost (C)
Project Control Principles
3
Project Management & Control
• Status Control• Technical Achievements• Critical Areas• Documentation• Engineering Changes• Schedule (Actual vs. Plan, Critical Path)• Actions• Financial Status• Contractual
• Status vs. Planning• Deviations to Plan• Corrective Actions & Resolutions
Project Control Principles
4
Project Management & Control
• Analysis• Impact to entire Project• Consequences to Project Goal• Decisions to be taken
• Management Decisions• Change of Project Baseline
• Technical Requirements• Schedule Restraints• Financial• Contractual
• Change of Project Plans
Project Control Principles
5
Integrated Project Control Process(Project Feedback Solution)
PROJECT
BASELINE
PROJECT
PLANS
ANALYSIS
FORECAST
PM
DECISIONS
PROJECT
ATP
STATUS
REVIEW
TASK
PERFORMANCE
COMPARE
TO PLAN
P
S
C
At CTR AwardR&D, Organization
AIV, Test, Operations
Total Project, Dedicated
WP’s, Subcos & Supplier
Status ReviewDeviation AnalysisPropose
Corrective Actions
• Actions,
• Changes,
• Redirection
ATP = Authority to Proceed
Project Control Principles
6
Work Breakdown Structure
Subdivision into Smaller Increments
• Level 1: Total Project
• Level 2: Systems of the Project
• Level 3: Subsystems of the Project
• Level 4: Units/Equipments
• Level 5: Work Packages or Components
Project Control Principles
7
Work Breakdown Structure(sample only)
1st Stage
Contractor "D"
Russia
2nd Stage
Contractor "E"
Ukrain
Fairing
Contractor "I"
Switzerland
Launch Campaign
Contractor "K"
Kasakstan
Supply of
Launch Vehicle
Contractor "A"
USA
Payload
Contractor "H"
USA
Bus
Contractor "G"
France
Propulsion
Contractor "H"
Germany
Interface
Contractor "F"
Japan
Supply of
Satellite
Contrctor "B"
France
TT&C Station
Contractor "L"
Italy
Up-Link
Contractor "M"
Spain
Data Processing
Contractor "N"
Belgium
Telemetry
Contractor "O"
UK
Supply of
Ground Station
Contrctor "C"
UK
Tracking
Company "P"
Germany
Monitoring
Company "D"
Holland
Evaluation
Company "Q"
Ireland
Relay
Company "R"
China
Satellite
Operations
Contractor "D"
Holland
Satellite
System
Customer
Luxembourg
Project Control Principles
8
Work Breakdown Structure (WBS)A Key to Successful Project Management !!!The WBS serves several important Purposes, such as:
• Subdivision of Work
• Identification of Project Levels
• Work Sharing between Companies
• Economic Geographical Distribution of Funds
• Implementation of WBS Numbering System (Code) – applicable to the entire Project
• Definition of Cost Account Structure
• Allocation of Funds
• Implementation of Project Control in line with the WBS Code
• Assignment of Responsibilities to Companies & Individual Managers
• Identification of Interfaces at all Levels
• Implementation of Documentation Numbers related to WBS Code
• Identification of Work Packages
Project Control Principles
9
Content of Work Package Description
• Work Package (WP) Identification• Title• Identification of the WP in the WBS (WP Number)• Date of the Start and End of the WP
• Company or Entity in charge of the WP Performance
• Assign Work Package Manager
• Description of WP Tasks to be Performed
• Tasks Explicitly Excluded
• WP Inputs (Documents, Hardware, Software)
• WP Outputs (Products: Hardware, Software, Documents)
Project Control Principles
10
Project Milestones
• Identify Project Milestones
• Major Milestones
• Payment Milestones
• Other Milestones
• Planned Achievements
• Important Key Events for Control
Project Control Principles
11
1. Establish Schedule Baseline
project task
time
Input * Output **
* Objective, requirements,
mission plan, etc.
** Deliverables (HW, SW,
documentation
Project Control Principles
12
Specification
Design
Production
Test
1. Establish Schedule Baseline (Sequence of Events)
Activity
Dummy Activity
Project Control Principles
13
1. Establish Schedule Baseline (Sequence of Events and Durations)
Specification
Design
Production
Test
4 w
8 w
6 w
2 wto + 20
to
Project Control Principles
14
Baseline Milestone ScheduleA INSTALLATION
B APPROVAL RESPONSiBILITY
C ACCOMPLISHMENT
RESPONSiBILITY
H SCHEDULE TITLE
J CONTRACTOR
G PROJECT
I SCHEDULE NO.
(LEAVE BLANK)
D ORIG. SCHEDULE APPR.
E LAST SCHEDULE CHANGE
F STATUS AS OF
K LEVEL
MILESTONES
L KEY MILESTONES
M INTERNAL MILESTONES
N INTERFACES
O NOTES
TIME SCALE
(DATE)
Project Control Principles
16
1. Establish Schedule Baseline (Critical Path Analysis)
Specification
Design
Production
Test
4 w
8 w
6 w
2 wto + 26
to
Material
20 w
Critical Path of Project
Positive Slack
Project Control Principles
17
Specification
Design
Product.
Test
2. Establish Schedule Targets (Definition of Milestones)
Activity
Dummy Activity
Complete
Complete
Complete
Complete
Project Control Principles
18
• Identify Project Milestones
• Major Milestones
• Payment Milestones
• Other Milestones
• Describe Planned Achievements
• Perform Control
2. Establish Schedule Targets (Definition of Milestones)
Project Control Principles
19
• Baseline Planning
• Measurement of Achievements
• Comparison of Planned and Actual
• Deviations to Plan
• Corrective Actions
4. Provide Schedule Control (Status Monitoring)
Project Control Principles
20
A ufgaben
K onstruktion
Fertigung
Zusam m enbau
und Test
1 2 3 4 5 6 7 8 9 121110
-2
- 4
+2
4. Provide Schedule Control (Status Monitoring)
Project Control Principles
21
1
2
3
4
5
6
7
8
9
10
14
13
12
11
0 1 2 3 4 5 6 7 8 9 10 14131211
3
4
1
5
2Ge
pla
nte
r T
erm
in *
Berichterstattung *
Berichterstattung
für 3 bis 5 nicht
realistisch
Problem -
Erkennung
Terminverzüge von
1 bis 3 haben voll
auf 4 und 5 durch-
geschlagen
* Monate nach
Projektbeginn (0)
4. Provide Schedule Control (Schedule Trend Charts)
Project Control Principles
22
5. Identify Schedule Problem Areas
Activities and/or Milestones are not
Completed in Time
Progress Information not Available
Work Forecast Shows Delay of Deliverables
Critical Path Analysis not Performed
Project Control Principles
23
6. Implement Corrective Actions
Requesting Additional resources to Complete
Activities and/or Milestones on the
Critical Path
Provide Constantly Progress Information
Introduce Work Around Solutions
Perform Critical Path Analysis
Project Control Principles
24
7. Implement Schedule Reporting
Activities and Milestones Completed
Work Forecast of Activities to be Completed
including Time to Completion (TTC)
Schedule Problem Areas and Solutions
Results of Critical Path Analysis
Project Control Principles
25
Project Cost Plans
• Cost Account Structure
• Manpower & Cost Plan
• Travel & Subsistence
• Overall Cost Summary
Project Control Principles
26
Planning Of Project Resources
Manpower Requirements
Material Requirement
Requirements for Machines
Facility Requirements
Travel Requirements
Others (TBD)
Project Control Principles
27
RESOURCE TIME LINE(Month or Quarter)
TOTAL
Manpower (hrs)
100 150 200 250 200 150 100 50 1 200
Costs (T-Euro):
o Manpower
o Travel
o Material
o Equipment
o Contractors
o Others
10 15 20 25 20 15 10 5 120
Grand Total
Manpower and Cost Plan
Project Control Principles
28
RESOURCE MANPOPWER & COST STATUS REPORT
Manpower and Cost Elements
a. Budget b. Actual c. PO d. CTC e. Forec
ast(b + c + d)
f. Variance(e – a)
Manpower (Hours)
1 200 900 0 400 1 300 - 100
Costs (Euro):o Manpowero Travelo Materialo Equipmento Supplierso Others
120152535
90580
001329
401130
130162429
- 10- 1+ 1+ 6
Grand Total 195 103 42 54 199 - 4
Manpower and Cost Control
Project Control Principles
29
Earned Value Methodology
e:\pmt\seminare\s_10\s_10gf02.cdr Fo-03
100
500
300
700Statuskontrolle ( 01.07.XX )
Akkumulierte Kosten (TDM)
Plankosten ( PK )
Zeitplan
Kostenplan
Akk. Kosten
Ist-Kosten
Akk. Ist-Kosten
Terminplan
Ist-Kosten ( IK )
Cost to Completion ( CTC )
Arbeitswert ( AW )200
600
400
1 10 115 153 1372 126 164 148 9
20 45 45 70 70 75 65 65 40 --65 40 --40 -- --65 110 180 250 325 390 520 600 --455 560 --640 -- --
15 40 40 45 50 6055 95 140 190 250
Accumulated
Costs
Time Now (TN)
BCWS
BCWP
ACWP
Cost Plan
Actual Costs
Time Schedule
ACWP – Actual Cost Work Performed
BCWP – Budgeted Cost Work Performed
BCWS – Budgeted Cost Work Scheduled
Cost at Completion (CAC)
Project Control Principles
30
Recommended Project Management Literature
• Kerzner, Project Management & Study Guide, 8th Edition
• Madauss, Projektmanagement, 6th Edition, 2000, German
• Verzuh, The Fast Forward MBA in Project Management, 1999
• Terry, Principles of Management, 7th Edition• ESA, Space Project Management, ECSS-M
Project Control Principles