38
Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Embed Size (px)

Citation preview

Page 1: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Project Managementat CERNPierre BonnalEngineering Department

RIGI Meeting @ CERN

Page 2: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 2

Outline

• PRAM in the Sixties

• Web-based tools of the Nineties

• Project Control 2.0 in the years 2000s

• in the years 2010s

• Will Project Planning & Scheduling 2.0 be next?

Contributions from CERN to Project Management

2015-03-06

Page 3: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 32015-03-06

Page 4: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 4

PRAM in the Sixties

2015-03-06

Page 5: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 52015-03-06

PRAM in the Sixties

CERN PS 56-59

CPM in 1959

PERT in 1959

PDM in 1960-68

PRAM in 1966

RCPS in mid-60s

CERN ISR 67-71

Page 6: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 62015-03-06

PRAM in the Sixties

Page 7: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 7

Web-based tools in the Nineties

2015-03-06

Page 8: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 82015-03-06

Web-based tools of the Nineties

Page 9: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 9

Project Control 2.0 in the years 2000s(EVM LSM RSM)

2015-03-06

Page 10: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 10

Project Control 2.0

Large Hadron Collider 1995-2008

Multi-billion-CHF project very large scaleMany contributors, several sources of funding

Highly technological project several challengesSufficient room for creativity and innovation

Performance-driven project it must work!Even if it takes more time and more resources

Highly distributed project really worldwide!

Public-funded project public auditors

2015-03-06

Page 11: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 11

Project Control 2.0 (cont’d)

In 1994 “Must Win” project, under-funded and under-resourced!

All CERN’s departments involved in some ways

LHC Project Leader appointed as a director

Budgeting and cost control Project Administrator

Planning and scheduling Technical Co-ordinator

No link between the cost control system and the scheduling system!

2015-03-06

Page 12: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 12

Project Control 2.0 (cont’d)

Technical Co-ord. “the project is behind schedule”

Project Admin. “the project is under-running”

The LHC Project Management Team was not in capacity to demonstrate that EAC < TAB

Member States asked CERN Management to set up an appropriate Project Control System

2015-03-06

Page 13: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 13

Project Control 2.0 (cont’d)

Multi-level planning and scheduling3 levels master, co-ordination and detailed

Earned Value Management-based

Interfaced to accounting system Actual Costs

Interfaced to contract management system

Interfaced to human resource management system

In-kind contributions

Collaborative and web-based obvious!

Lean planning + reporting by Project Engineers2015-03-06

Page 14: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 14

Project Control 2.0 (cont’d)

But how to get rid of the 90%-syndrome?

Activitycompleted?

Progress still 95%!

Activitycompleted?

Progress 90%!

An activity of the project

Activitynot startedProgress 0%

Activityhalf-way

Progress 50%

Activityalmost doneProgress 90%

Deliverable-oriented PM System

2015-03-06

Page 15: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 15

Project Control 2.0 (cont’d)

Transparency of the physical progress reportingA “10 magnets out of 20” physical progress statementis more informative than a “50% complete” statement!

Payment milestones of result-oriented contracts refer to effective deliveriesFinish dates of contract activities are always known!

Finally, a trend in project management practices (ref. Patrick A. Howard. Deliverable-oriented project management. ProjectWorld’98 Proceedings, 1998)

2015-03-06

Page 16: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 16

Project Control 2.0 (cont’d)

2015-03-06

Page 17: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 172015-03-06

Project Control 2.0 (cont’d)

4 types of activities

Page 18: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 18

LHC Project EVMS | Weak points

Introduced while AC = CHF 1 billion!!

Granularity between contract breakdown structure,co-ordination schedule, codes of accounts…

Too many activities 12’000+ activities

Varying granularity of activities: from a few kCHF to several MCHF from a few weeks to several months

Project Engineers planned too optimistically

Weak integration with schedule networks

2015-03-06

Page 19: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 19

LHC Project EVMS | Lessons learned

Number of planned activities < 500Work Package vs. Planned Package features

Constrain the size of the activities so that:

80% of the activities in range 0.2% – 2% BAC

Duration < 10% project duration and 3 months

No. of level-of-effort activities in range 1 – 1%

Unambiguous responsibility only one per activity

Systematics in breaking down to ease taking over

2015-03-06

Page 20: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 202015-03-06

LHC Project EVMS | Strong points

Deliverable-orientation collaborative framework

Strong Project Leader support essential!

Microsoft® Excel® sheets to interact with DBs

Strongly integrated with corporate databases

Planned (baseline) vs. expected (trend) figures

“AC = EV rule” for in-kind contributions

One repository of activities for all groups(eliminate overlap, detect holes…)

Contributed to cost consciousness at all levels

Regain confidence of CERN’s Member States

Page 21: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Improvements

Embed a resource-constrained critical path scheduling engine

Page 22: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 222015-03-06

Improvements (cont’d)

Embed a resource-constrained critical path scheduling engine

Embed repetitive & linear scheduling methods functionalities

Page 23: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 23

Improvements (cont’d)

Embed a resource-constrained critical path scheduling engine

Embed repetitive & linear scheduling methods functionalities

Manage better the Project Management Reservein synchronization with change records

Consider a Planning & Scheduling 2.0 approach

2015-03-06

Page 24: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 24

in the Years 2010s

2015-03-06

Page 25: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 25

GSI FAIR (Germany)

CERN (Switzerland)

TUT (Finland)

UPM (Spain)

KIT (Germany)

Sensetrix (Finland)

bgator (Finland)

Oxford Technology (UK)

The research leading to this framework has received funding from the European Commission under the FP7

ITN project PURESAFE, grant agreement no. 264336.

A&M ParisTech (France)

U. de Savoie (France)

= 15 early-stage researchers

ESS (Sweden)

ECP (France)

LASS (France)

2015-03-06

Page 26: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

The need:A systems engineering (SE) framework suited to scientific facilities and systems that are subject to ionizing radiations

The preferred solution:Participative-basedevery project/systems engineer contributes actively to managerial tasks

Lean thinking-basedenhance outcome value while limiting waste

Open source-basedcreative common license

2015-03-06

Page 27: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 27

Editorial Content

Guidelines, Standards,Specifications, SW, etc.

Improvement of the editorial content

2015-03-06

Page 28: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

cern.ch/openSE Not yet openSE.org

Page 29: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN
Page 30: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 302015-03-06

Lifecycle

A common understanding of a facility or system lifecycle

Page 31: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 31

Processes

A common understanding of key processes

• Systems Engineering processes:gathering needs and defining requirements,systems architecting and modelling, verifying & validating, managing product risks, managing configuration & quality

• Project Management processes:scoping, planning and scheduling, costing, managing project risks, supplying components

• Design and Engineering processes:DfS, DfE, DfMA, DfP, DfC, DfO, DfR, DfA, DfM, DfT/DfRH** Design for Telerobotics / Design for Remote Handling

2015-03-06

Page 32: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 32

Roles

A common understanding of roles and responsibilities

2015-03-06

Page 33: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 33

Results

A common understanding of the expected results

• The systems or the facility indeed

• The means for “ORAMS’ing” them

• Information, documentation

2015-03-06

Page 34: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 34

Will Project Planning & Scheduling 2.0 (PDM 2.0) be next?

2015-03-06

Page 35: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 352015-03-06

Page 36: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 36

Planning & Scheduling 2.0

Mathieu Baudin’s PhD thesis (A&M ParisTech)

Algorithms developed and prototype working

Algorithms tested at GSI FAIR Darmstadt

Will they be embedded in IMPACT?

Will they be embedded in commercial packages?

2015-03-06

Page 37: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Pierre Bonnal - Design Society @ CERN 37

CERN has always been on the cutting edge in matterof particle physics

CERN has always beenon the cutting edge in matterof technologies

CERN has also always been on the cutting edge in matterof project management

2015-03-06

Page 38: Project Management at CERN Pierre Bonnal Engineering Department RIGI Meeting @ CERN

Thanks.