25
MICHAEL SMURFIT GRADUATE SCHOOL OF BUSINESS The Large Hadron Collider Project Analysis and Recommendations Laura Halpin. 12252990 Wed 21st Aug 2013 MiM. BMGT44210. Sem. 3 "I confirm that the work submitted here is entirely my own work, and that any work of others which is included has been properly referenced and acknowledged according to normal academic guidelines."

Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

Embed Size (px)

Citation preview

Page 1: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

MICHAEL SMURFIT GRADUATE SCHOOL OF BUSINESS

The Large Hadron Collider Project

Analysis and Recommendations

Laura Halpin. 12252990

Wed 21st Aug 2013

MiM. BMGT44210. Sem. 3

"I confirm that the work submitted here is entirely my own work, and that any work of others which is included has been properly referenced and acknowledged according to normal academic

guidelines."

Page 2: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

TABLE OF CONTENTS

PAGE

Executive Summary 1

Introduction 2

Risk Management 3

Risk Types and Approach to Risk 3

Critical Analysis 4

Planning 6

CERN's Project Planning Steps 6

Implementation 9

Start-up Confusion 9

More Delays and Problems 10

Causes of Poor Implementation 10

1. Conflict of interest of Project Leader and Others 11

2. Project Nature and Globally-Dispersed Management 11

3. Optimism Bias in Planning 12

Conclusion 13

References 15

Bibliography 18

Appendices 19

Page 3: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

1

EXECUTIVE SUMMARY

This report contains details on the planning, implementation and risk management of the

large-scale project involving the construction and initial operation of the Large Hadron

Collider (hereafter referred to as the LHC) at CERN (Conseil Européen pour la Recherche

Nucléaire) in Geneva, Switzerland.

An executive decision has been taken by this consultant to define the temporal scope of the

project within certain limits for the purpose of this report; in reality, that scope was at best ill-

defined for the LHC project - an issue of concern, and of relevance in an educational capacity

in the conclusion of this report. Here, the project timeframe is said to be from 1994 (the

official approval of the project by CERN) to 2009 (the beginning of prolonged LHC

operation without fault). Specific information is drawn from official CERN documentation,

as well as firsthand accounts from engineers/scientists/managers who worked on the project,

and numerous other journal articles and media sources.

The introduction explains who CERN are, and what the project entailed - its scope, purpose,

and the nature of the project.

Risk management is assessed first, with the aim of emphasizing its importance throughout

each phase of the project. Various risks and their complexity are identified, as well as a brief

outline of CERN's techniques in approaching risk and critical analysis of this approach.

Planning, the foundation of any project, is explored in the following section, and CERN's

planning and scheduling techniques laid out. Critical insight into the planning phase of the

LHC is mentioned briefly, and investigated in more detail in conjunction with the

implementation phase - where plans are tested and their efficacy appears most clearly.

Implementation is the final section, in which we delve into problems which arose, as well as

analyze the implementation in the context of the project as a whole.

The concluding section draws together learnings from the report to create an advisory

guideline to ensure the effective and safe management of future large-scale, LHC-type

projects at CERN.

Page 4: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

2

INTRODUCTION

Founded in 1954, CERN is an international organization dedicated to pioneering work in the

field of particle physics. It is composed of 20 member, and 7 observer states, all of which

contribute to funding and other investments in its operations.

On 16 December 1994, after over ten years of technical feasibility studies and R&D, the

CERN Council approved the construction of the LHC. The accelerator was to be built by

CERN and a close partner division Fermilab, under the project leadership of scientist Lyn

Evans. It would be built within an existing infrastructure - that constructed from 1984-1989

for CERN's Large Electron-Positron machine (LEP), another particle accelerator. The new

accelerator would thus be 26.7km in circumference, and between 50m and 175m

underground - the tunnel being sloped "for reasons of cost".1

The machine's primary objective was to "provide proton-proton collisions with a centre of

mass energy of 7 TeV and an unprecedented luminosity of lO34 cmm2 s-l."2 In layman's

terms: to smash protons into one another, producing energy on collision as a result of

acceleration at almost the speed of light, with a luminosity (a measurement of how well the

particles can be detected) high enough for the potential discovery of new or previously

unobservable particles. The challenge, according to Steve Myers, CERN's director of

accelerators and technology, would be similar to "firing needles across the Atlantic and

getting them to collide half way."3 The primary goal of the project was, put simply, "to build

a working accelerator on time".4

Around the primary objective floated other goals which arose as their respective experiments

were given the go-ahead by the CERN council. As the project progressed, a total of 6

experiments were approved - ATLAS, CMS, ALICE and LHC-b between 1996 and 1998,

and two smaller ones after that - TOTEM and LHCf. These experiments each required

specific detection activities, carried out by large detector machines at different points in the

collider's rings. Operation would be carried out at -271.3°C, the machine cooled to this

temperature by liquid helium. An overall view of the LHC's structure can be seen in

Appendix A.

The LHC was a long-term megascience project. This meant that although it was subject to

many of the same conventions as other projects in project management, its large scale and

technical complexity presented additional risks and difficulties for management.

Page 5: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

3

RISK MANAGEMENT

With a project of the scale and scope of the LHC, the primary approach to risk must be

complete prevention. The nature of the experiments to be carried out by the machine involve

speeds and energies so high that any slight errors in design or implementation could be

catastrophic. In order to do this, quality management is the most essential tool, and

communication its inarguable prerequisite. In a complex, long-term project, uncertainty is

magnified. The longer the project runs and the more complexity it entails, the more

uncertainty it involves. One of the greatest risks is change in the project environment over

time, and in order to mitigate this overall risk, the project must place enormous emphasis on

the temporal-scope and prioritization of risk. Usually, the risks with the highest impact will

gain high prioritization for mitigation. In the case of the LHC, the risks in this category fell

into the domain of hysteria-risks, and scientific impossibilities (according to the scientists at

CERN). Still, to maximize chances of success, these risk had to be dealt with - even if this

meant simply disproving/dispelling the theories, often physicist to physicist.

Risk Types and Approach to Risk

The three most severe risks identified with the LHC experiments involved the potential

destruction of matter, and the earth itself - inarguably the most serious risk imaginable.

These potential risks were:

1. The creation of a black hole, or micro black holes - phenomena which would cause all

matter to collapse into a point of infinite density, resulting in the destruction of the earth.

2. Strangelets - material with a gravitational force so strong it would, if it was created,

destroy all life

3. Monopoles - theoretical particles which could be created by the machine's operations and

which would rip matter asunder.5

The interesting thing about these ultimate risks with the LHC, was that they existed largely in

the minds of a minority of physicists, and, due to the unfortunate nature of public tendency

towards hysteria in the face of unknown concepts (particularly in this highly specialised field

of particle physics), in the media. In reality, these risks, along with others which had been

Page 6: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

4

raised, were thrown out in 2003 by a safety study conducted at CERN, which concluded that

there was "no basis for any conceivable threat" of this kind.6 (In fact, a later account related

CERN's registration at Lloyds of London for the world's first 'Global Destruction with Black

Hole Indemnity' policy,7 but this source is unconfirmed, and likely to have been a hoax )

This disconfirmation of the extreme risks, however, did not render the construction and

operation project risk-free by any means. Other risks to be considered were:

- Risk of faulty design

- Risk of incorrect implementation of good design

- Risk of poor quality components/materials

- Risk of miscommunication among those working on the project, either at a temporal point,

or between those working on the project at different points in time (i.e.: poor

information/knowledge management)

- Risk of public fear causing internal/external sabotage

- Risk of over-running on budget or time

- Risk of injury to/loss of key personnel

- Risk of damage to components over time

The list is by no means exhaustive, and with these, and other risks, in mind, CERN's

approach to risk was comprehensive - accounting for both external and internal risks - and of

a twofold nature:

1. Qualitative - involving Monte Carlo simulations

2. Qualitative - involving risk identification at each stage of the project with the help of a

work breakdown structure, and subsequent risk assessment using what-if analyses.8

Critical Analysis

From all of the above it is clear to see that the risks involved with the LHC project included

PR management, for external risks, and quality management for internal, technical risks.

What has yet to be considered, however, is the overall risk which comes with changes over

time. For example, the length of this project meant that during its life-cycle, incredible

technological advances occurred. Floricel and Miller propose a view on risk in large-scale

Page 7: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

5

engineering projects which explores the need for robustness and flexibility in mega projects.

They contend that in order to achieve these essential elements of managing environmental

turbulence and risk, an organization's structure must be comprised of concrete strategic

systems complemented by institutional anchoring measures, all held together by the shared

vision of the project - returning once again to the importance of clear communication.9 The

attitude to risk management in a global organization like CERN is complicated. This idea of

flexibility within a robust system is crucial for risk response in a long-term, constantly

changing project, and as we will see in the later Implementation section, was impaired by

both quality issues, and cognitive biases.

Some of these involved an important element of risk management, namely

testing/prototyping. Although test and prototypes were scheduled into the LHC project, they

were incomplete and occasionally, dangerously so. In response to the 2008 quench incident

(detailed later), James Gillies, a spokesperson for the CERN laboratory, admitted "this thing

is its own prototype".10

Extensive testing was carried out on the machine, but it later proved

inadequate, with even internal personnel sceptical of the quality assurance levels at the

facility. Director general of accelerators and technology at CERN, Steve Myers, even

referred to the team's response to the 2008 incident as "playing musical chairs with helium".11

The message to take from the risk management of the LHC project is a cautionary one.

When it comes to risk, management is vital. It is no use waiting for the explosion to happen

in order to develop a plan. No matter how long-term the project scope, risk management

must be extended throughout the planning, implementation and control stages, and any and

all risks must be prepared for. Failing that, a robust, flexible system must be securely in

place to readjust the approach when unanticipated risks occur. If this is impossible, it is

worth considering whether the scope of the project itself may be the critical failure factor.

Page 8: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

6

PLANNING

The first thing to be taken into account when planning a project are constraints. The LHC

construction project initially had a budget constraint of about 4.6m Swiss Francs, and, based

on the decision to construct the LHC within the existing LEP tunnel, a serious space

constraint.

These constraints were the reasons behind many of the early decisions in the LHC planning

process. One of these decisions was to re-use as much of the LEP's infrastructure as possible

(although additional caverns had to be created for several of the collider's detectors)12

in

order to take advantage of previous investments.

With this in mind, we begin examination of the LHC project planning process.

CERN's Project Planning Steps

A project of this size, complexity and globally managed nature, meant tremendous

coordination was needed, which in turn meant the need for a holistic outlook by the

management, and efficient flows of information across the whole project. Thus the planning

process for the LHC followed a number of well-defined and detailed steps - these are laid out

by Bachy, Bonnal and Tarrant in CERN's LHC Note.355.13

1. Creation of an action plan, the highest level definition of the project, contributed to by all

interested parties (physicists, CERN Council etc.) and including a summary of the entire

project and its purpose.

2. Detailed PBSs (Product Breakdown Structure), including manufacturing and quality

control information, design rules, and detailing of each technical component - Some of

the most critical components necessary to reach this objective were superconducting

dipole magnets - these create a linear magnetic field to guide beams of ionized particles

on their circular path, in opposite directions, within the machine's giant rings.14

Detailed ABSs (Assembly Breakdown Structures), including the sequence of activities

for assembly of the project and how best to use the LEP infrastructure. These were

drawn up for each of the main construction sites and major machine parts, and assisted in

Page 9: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

7

defining and controlling exactly what needed to be done/produced, and how. (See

Appendix B for samples). These PBSs/ABSs, along with an OBS (Organizational

Breakdown Structure), were then cross-referenced and merged to create the WBS (Work

Breakdown Structure). This WBS is a matrix structure made up of work packages, and

includes definition of specific tasks to be completed, which work groups are to complete

them, and cost estimates. It serves to provide guidance to all those involved, as well as

to enable management of risk (in the LHC case, carried out with the use of risk flotation

reserves between co-ordination schedules), and to track performance against these stated

intentions of necessary task activities.

3. In a long-term, complex project like the LHC, changes are inevitable over time. Thus the

planning system was based on multi-level hierarchy style planning, where the work

packages of the WBS were decoupled - meaning that changes impacted only the work

package involved, not the entire planning system. The top level of this hierarchy was a

Master Production Schedule, which covers the whole duration of the project, and

functions as the management overview segment of planning. The middle level was a

series of co-ordination schedules, and the lower level comprised various detailed

schedules drawn up and overseen by technical work units. These detailed schedules

ensure resources were available, and that the specific tasks, in their decomposed states,

were feasible within the temporal constraints of the project. (See Appendix C)

4. Employment of planning hardware and software.

Software for planning the LHC was chosen based on its ability to process the

complexities of the project, and user-friendly nature. CERN chose Microsoft Project,

version 4.0 for Windows 3.1.15

5. Planning co-ordination meetings were held regularly to facilitate updates and

adjustments, attended by the planning co-ordinators and planning leaders for various

technical groups, as well as progress reports published at project milestones.

A CERN publication entitled ' A Deliverable-Oriented EVM System Suited to a Large-Scale

Project' outlined the importance of developing frameworks for adjustment of plans within a

long-term project. This systematic approach means that newcomers, as well as current

Page 10: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

8

contributors, to the project are clear on how to approach the management of their section, and

reduces the risk of omission or duplication of information.16

We can see from CERN documentation that the planning and scheduling system of the LHC

was carried out meticulously. But it is necessary to call to mind that old project management

adage: 'the proof of the planning is in the…implementation'. To fully understand the

planning process and its contribution to the success/failure of the LHC, we must view it

within the context of the project as a whole - in particular, its implementation, and the

problems which arose therein.

Page 11: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

9

IMPLEMENTATION

After consideration of the risk management and planning aspects of the LHC project, we turn

to its implementation phase. Although the scope of the LHC construction project does not

include the experiments to be run, it does include the construction of a working accelerator.

Thus the implementation segment of this report focuses on the final construction phase and

the initial attempts at operating the machine.

Start-up Confusion

This is where we see cracks in the walls beginning to occur (both figuratively and literally).

Originally, the machine was scheduled to begin operations in 2007, according to project

manager Lyn Evans, who claimed:

“[O]ur commitment is still firmly behind the objective of colliding beams in the summer of

2007,” ".17

However, according to the CERN outreach website, this was not the case - it claims, instead,

that the planned completion date was 2008.18

Other sources say the machine was scheduled

to run as early as early as 2005, with Physics World claiming it was "Originally slated for

2005 start-up",19

and a Report of the US ATLAS Pixel Baseline Review Committee

mentioning: "the LHC 7/1/2005-startup date".20

These various sources - a sample range of those available - indicate two possibilities for the

discrepancies in projected start-up date:

1. Nobody knew when the LHC was supposed to start, or

2. Some people knew, but communication structures - both internal and external to the

immediate project team - were ineffective in conveying the information clearly

The first possibility indicates lack of clear definition of objectives, and the second possibility

would mean poor communication by the project coordinators. In a project of this magnitude

and public nature, both of those options are simply unacceptable.

Page 12: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

10

More Delays and Problems

Aside from the start date issue, the project's implementation was fraught with delays and

setbacks.

In 2002, overrunning on cost resulted in a long delay.

In 2004, 3 kilometres of equipment had to be replaced following a manufacturing error.21

In 2007, the machine "suffered a serious setback when a support structure for key magnets

failed during routine tests".22

According to Fermilab, the reason for this error is traceable

back to tests carried out of the magnets between 1998/2002 - "none of which appear to have

addressed the asymmetric loads. The only tests on the magnets while they were still at

Fermilab were performed on single magnets, which would never develop such loads."23

By the planned startup date in 2008, the machine had already "been delayed several years and

[was] significantly over budget.24

Even when the machine began functioning in September 2008, the delays continued. Just

nine days after its initial start-up - after a host of media fanfare celebrating its success, (along

with semi-serious relief that the world continued to exist), a massive magnet quench caused it

to shut down. This meant a number of magnets were damaged when a faulty electrical

connection caused the freezing liquid helium to escape into the tunnel. The damage to the

dipole magnets was so great that repairs would take months - a delay which, in reality, turned

into a year.

Causes of Poor Implementation

These delays are representative of the many others which appeared to plague the LHC. The

question is: why did so many occur?

And the answer, I believe, consists of three elements:

1. Conflict of interest of the project leader. This leads to the bias where the person

managing the project (Lyn Evans) identifies primarily with the stakeholder group who

will use the product, not with that which builds it. This feeds into the vast media and

industry pressures to complete the machine and begin its operations.

2. The nature of the project and its globally dispersed management, and

3. Optimism bias in planning.

Page 13: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

11

In an endeavour to understand these causes for application in and improvement of future

projects, let us explore each one in more detail.

1. Conflict of interest of the project leader, and media/industry pressures to complete the

machine and begin its operations.

Lyn Evans was, by profession, a scientist. His motivation in building the LHC was to

achieve the results of particle physics experiment which had previously been impossible to

obtain. This was compounded by the huge community of physicists who waited so eagerly

for the same, or similar results, and the media frenzy over the so-called 'doomsday machine'.

The result of these various pressures meant the LHC was built in an atmosphere of fraught

anticipation. And although this should not have meant any aspect of project management

was neglected, the myriad delays, faults, errors and setbacks indicate that they were.

Quality management, although well-documented by CERN and in evidence throughout, fell

short of that required for such a huge project. Critically, the machine suffered from one of

the most dangerous features of human functioning: assumption. In fact, following the 2008

quench incident, Jim Strait, and accelerator physicist, admitted that the tolerances of the

valves in place for relief in case of incident "were based on "incorrect assumptions" about

how much helium might escape in an accident. "The total amount of helium released was

larger than the valves were designed to handle...You could call it a design error".25

2. The nature of the project and its globally dispersed management.

A 1997 article by Ari-Pekka Hameri, a scientist involved with configuration/communication

management at CERN during the LHC project, classifies the project as a "long-term and

global one-of-a-kind project".26

The paper consolidates various research results into a list of

fundamental reasons for failure in this type of undertaking, which include inconsistent

understanding of the project's objectives among its management and users, rigid planning

structures, poor response to sudden changes in the environment, and unforeseen risks

associated with technical complexity.27

From the analysis of the LHC thus far, all of these

problems are clearly present.

Although the planning mechanisms and procedures put in place by CERN were extensive, the

documents contain little room for manoeuvre - they are rigid and inflexible. As discussed,

Page 14: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

12

there are large discrepancies regarding schedule-related objectives and various different

groups hoping for different outcomes on completion of the project. Changes in the

environment and technical complexity, manifesting here as technical faults and changing

public attitudes to the safety and usefulness of the machine, are met with slow response and

poorly communicated progress. The communication problem is one which stems from the

project's global nature and dispersed management, with contributing member states from all

over the world.

3. Optimism bias in planning.

The main difficulty with optimism bias is that it is, by nature, almost (if not completely)

impossible to perceive at the time of planning. It is only when a project runs overtime/over-

budget that hindsight allows us to see how optimistic, rather than realistic, our estimates

were. An article titled 'Performers, Trackers, Lemmings and the Lost: Sustained False

Optimism in Forecasting Project Outcomes' explores this topic, identifying two factors which

come into play with optimism bias in a project management setting: "over-optimism in

estimates, and overconfidence in the reliability of those estimates."28

The article details

contributing factors to this optimism bias - among them motivated reasoning, outcome

attribution, and the paradox of dispositional optimism. 29

The significance of these

psychological biases reaches full gravity on realisation that the immense power of accelerator

physics lies in the hands of the project team - real people with real cognitive biases.

Crucially, the article explores the tendency of optimism bias to extend throughout the life-

cycle of the project. Accounts of management reaction to setbacks during implementation

are peppered with the evidence of this extension: the massive quench in 2008 was dismissed

as "teething problems" in a CERN press release four days after the incident, the same

document stating a scheduled re-start in Spring 2009.30

In Spring 2009, that date was pushed

back to late Summer31

and the re-start did not actually occur until later that year. This is one

of many similar examples throughout the LHC project lifecycle.

Page 15: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

13

CONCLUSION

The LHC project overran both budget and time constraints, with delays and repairs to the

machine needing almost constant capital injection from member countries. Despite a

substantial amount of documentation by CERN on the planning, scheduling, safety and

implementation procedures, as well as technicalities of the machine's dimensions and

capabilities in terms of groundbreaking research in particle physics, a clear list of objectives

or critical success factors for the project is nowhere to be found. This leads to the ultimate

conclusion that the project was viewed, by its primary users and management team, as more

of a long-awaited scientific experiment than as an engineering, or project management feat.

Although this summary is reductive to the extreme, I believe the findings detailed in this

report provide ample guidance for the improvement of future projects, not least with respect

to the opportunities offered by advances in project management literature in the 20 years

since the project's official start.

The following guidelines for the effective management of future projects of this scale are thus

recommended:

- Clearly defined and communicated objectives

- A shared vision of the outcome and critical success factors of the project

- Complete and accurate quality management, testing and prototyping in all critical functions

- Clearly defined and communicated safety features for public peace of mind

- Standardization of all planning procedures, as well as clear guidelines on how to manage

planning and implementation within all management and technical divisions involved. These

standardized frameworks should include robustness and flexibility to deal with the inevitable

uncertainty in a long-term project.

- Awareness of biases in the process - conflicts of interest should be noted and, if their impact

is considered severe enough on the potential success of the project, removed. Cognitive

biases should be researched and mitigated where possible.

Page 16: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

14

Two final points must be considered by CERN in undertaking LHC-like projects in the

future.

1. It is worth noting that the technology used in the construction and operation of these

groundbreaking scientific devices, and the highly theoretical particle physics for which

they are produced, are two very different fields. Although CERN operates within a highly

specialized area, the project management discipline is constantly evolving and new tools

and techniques are produced constantly. CERN is thus advised that greater cross-

functional teaming and external advice should be sought on construction/operation

projects such as this.

2. It is vitally important that the planning and implementation processes in any project are

suited to the project type. Thus a megascience project should be properly researched, and

due regard given to its extreme size and international stakeholders. Criteria outside of the

iron triangle's cost, time and scope should be taken into account,32

and all aspects of the

project should contribute to the learning process for future projects.

Thus I conclude with a quotation from Jim Strait, who commented on the LHC project: "In

Italian we say, Chi non fa, non sbaglia: 'He who doesn't work makes no mistakes'. What we

have to do is learn from our mistakes and make it better."33

Page 17: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

15

REFERENCES

1. CERN Communications Group (2009) 'CERN faq - The LHC Guide'. Available at:

http://cds.cern.ch/record/1165534/files/CERN-Brochure-2009-003-Eng.pdf (Accessed 10

Aug 2013)

2. Evans, L.R. (1994) 'Advanced Technology Issues in the LHC Project'. 4th European

Particle Accelerator Conference, London, UK, 27 Jun-1 Jul 1994 : p.429

3. The Telegraph (2010) 'Large Hadron Collider Hits Problems as Scientists Bid to Start

High-Energy Collisions'. Available at: http://www.telegraph.co.uk/science/large-hadron-

collider/7537355/Large-Hadron-Collider-hits-problems-as-scientists-bid-to-start-high-

energy-collisions.html (Accessed 15 Aug 2013)

4. Foraz, K., Gaillard, H., Lari, L., Weisz, S. (2004) 'Scheduling the Installation of the Large

Hadron Collider'. Proceedings of EPAC (European Particle Accelerator Conference) 2004,

CERN, Geneva, Switzerland : p.1924

5. CERN Press Office (2011). 'The Safety of the LHC'. Available at:

http://press.web.cern.ch/backgrounders/safety-lhc (Accessed 13 Aug 2013)

6. Blaizot, J., Iliopoulos, J., Madsen, J., Ross, G.G., Sonderegger, P., Specht, H. (2003)

'Study of Potentially Dangerous Events During Heacy-Ion Collisions at the LHC: Report of

the LHC Safety Study Group'. CERN Scientific Information Service. CERN, Geneva.

Available at: http://www.uslhc.us/What_is_the_LHC/LHC_Safety (Accessed 14 Aug 2013)

: p.iii

7. Walid (?) 'Large Hadron Collider Buys Black Hole Insurance Policy'. Available at:

ununconfirmedsources.com/?itemid=3241> (Accessed 18 Aug 2013)

8. Bachy, G., Bonnal, P, Tarrant, M (1995) A Planning & Scheduling System for the LHC

Project [CERN MT/95-09 (DI); LHC Note 355] Available at:

https://cds.cern.ch/record/294011/holdings?ln=en (Accessed 11 Aug 2013) : p.4

9. Floricel, S., Miller, R. (2001) 'Strategizing for Anticipated Risks and Turbulence in Large-

Scale Engineering Projects'. International Journal of Project Management, 19(8) : pp.445-

455

10. Brumfiel, G. (2008) 'Eight-Month Delay for LHC'. Available at:

http://www.nature.com/news/2008/081017/full/4551015a.html (Accessed 13 Aug 2013)

11. Brumfiel, G., (2009) 'LHC Faces Further Delay'. Available at:

http://www.nature.com/news/2009/090209/full/news.2009.90.html (Accessed 13 Aug 2013)

12. CERN Technical Support Department (2006) 'LHC Project: Scope.' Available at:

http://ts-dep.web.cern.ch/ts-dep/groups/ce/ce-LHC.htm (Accessed 9 Aug 2013)

13. . Bachy, G., Bonnal, P, Tarrant, M (1995) A Planning & Scheduling System for the

LHC Project [CERN MT/95-09 (DI); LHC Note 355] Available at:

https://cds.cern.ch/record/294011/holdings?ln=en (Accessed 11 Aug 2013)

Page 18: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

16

14. CNET (2010) 'The Heart of the LHC: A Dipole Magnet'. Available at:

http://news.cnet.com/2300-11386_3-10003996.html (Accessed 10 Aug 2013)

15. CERN Document Server (1996) LHC Project Progress Report 01: Planning and

Scheduling [Doc. No.LHC-QAP-402]. Available at:

http://cds.cern.ch/record/307862/files/lhc-project-report-01.pdf (Accessed 11 Aug 2013)

16. Bonnal, P., De Jonghe, J., Ferguson, J (2006) 'A Deliverable-Oriented EVM System

Suited to a Large-Scale Project'. Project Management Journal, 37(1) : pp.67-80

17. Madrigal, A. (2009) ' LHC Suffers More Leaks, and Delays'. Available at:

http://www.wired.com/wiredscience/2009/07/lhc-suffers-more-leaks-and-delays/ (Accessed

13 Aug 2013)

18. CERN (1995) 'LHC Machine Outreach: LHC - Vital Statistics'. Available at: http://lhc-

machine-outreach.web.cern.ch/lhc-machine-outreach/lhc-vital-statistics.htm (Accessed 15

Aug 2013)

19. Physicsworld.com (2007) 'Large Hadron Collider Faces Delay'. Available at:

http://physicsworld.com/cws/article/news/2007/mar/30/large-hadron-collider-faces-delay

(Accessed 13 Aug 2013)

20. Bercovitz, J., Derylo, G., Haller, G., Kane, S., Lipton, R., O'Connor, P., Premisler, L

(2000) 'Report of the US ATLAS Pixel Baseline Review by the Review Committee'.

Available at: file:///C:\Users\Laura\Downloads\FinalPixelBaselineReviewReport.doc>

21. Brumfiel, G. (2008) 'LHC Switches On'. Available at:

http://www.nature.com/news/2008/080910/full/news.2008.1098.html (Accessed 13 Aug

2013)

22. Ananthaswamy, A. (2007) 'Large Hadron Collider Suffers Serious Setback'. Available

at: http://www.newscientist.com/article/dn11519-large-hadron-collider-suffers-serious-

setback.html#.UhNkF5LYeNN (Accessed 14 Aug 2013)

23. Physicsworld.com (2007) 'Large Hadron Collider Faces Delay'. Available at:

http://physicsworld.com/cws/article/news/2007/mar/30/large-hadron-collider-faces-delay

(Accessed 13 Aug 2013)

24. Harrell, E. (2008) 'Why the Large Hadron Collider is Already on the Fritz'. Available

at: http://www.time.com/time/health/article/0,8599,1843296,00.html (Accessed 16 Aug

2013)

25. , G. (2008) 'Eight-Month Delay for LHC'. Available at:

http://www.nature.com/news/2008/081017/full/4551015a.html (Accessed 13 Aug 2013)

26. Hameri, A. (1997) 'Project Management in a Long-term and Global One-of-a-Kind

Project'. International Journal of Project Management, 15(3) : pp.151-157

27. Ibid

28. Kutsch, E., Maylor, H., Weyer, B., Lupson, J., (2011) 'Performers, Trackers, Lemmings

and the Lost: Sustained False Optimism in Forecasting Project Outcomes - Evidence from a

Quasi-Experiment'. International Journal of Project Management, 29(8) : p.1073

Page 19: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

17

29. Ibid

30. CERN Press Office (2008) 'LHC Re-start Scheduled for 2009'. Available at:

http://press.web.cern.ch/press-releases/2008/09/lhc-re-start-scheduled-2009 (Accessed 16

Aug 2013)

31. Meyer, D. (2008) 'LHC Restart Gets Reset to June'. Available at:

http://news.cnet.com/8301-11386_3-10101366-76.html (Accessed 16 Aug 2013)

32. Toor, S., Ogunlana, S. (2010) 'Beyond the ‘iron triangle’: Stakeholder Perception of Key

Performance Indicators (KPIs) for Large-scale Public Sector Development Projects'.

International Journal of Project Management, 28 (3) : pp. 228-236

33. Brumfiel, G. (2010) 'Did Design Flaws Doom the LHC?' Available at:

http://www.nature.com/news/2010/100223/full/4631008a.html (Accessed 17 Aug 2013)

34. Appendix A and C images from:

Bachy, G., Bonnal, P, Tarrant, M (1995) A Planning & Scheduling System for the LHC

Project [CERN MT/95-09 (DI); LHC Note 355] Available at:

https://cds.cern.ch/record/294011/holdings?ln=en (Accessed 11 Aug 2013)

Page 20: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

18

BIBLIOGRAPHY

Atkinson, R., Crawford, L., Ward, S (2006) 'Fundamental Uncertainties in Projects and the

Scope of Project Management'. International Journal of Project Management, 24(8) : pp.

687-698

Bachy, G., Hameri, A. (1997) 'What to Be Implemented at the Early Stage of a Large Scale

Project.' International Journal of Project Management, 15(4) : pp.211-218

Brianti, G., (2004) 'The Large Hadron Collider Project: Historical Account'. Physics Reports,

403-404 : pp.349-364

CERN Technical Support Department (2006) 'LHC Project: Scope.' Available at: http://ts-

dep.web.cern.ch/ts-dep/groups/ce/ce-LHC.htm (Accessed 9 Aug 2013)

CERN (2013). Atlas Experiment. Available at: http://atlas.ch/ (Accessed 12 Aug 2013)

CERN (2012). Compact Muon Solenoid's Experiment at CERN's LHC. Available at:

http://cms.web.cern.ch/ (Accessed 12 Aug 2013)

CERN/ALICE Collaboration (2012). ALICE: A large Ion Collider Experiment. Available

at: http://aliceinfo.cern.ch/ (Accessed 12 Aug 2013)

CERN (2013). Large Hadron Collider Beauty Experiment. Available at: http://lhcb-

public.web.cern.ch/lhcb-public/ (Accessed 12 Aug 2013)

CERN (2011) The TOTEM Experiment. Available at: http://totem-

experiment.web.cern.ch/totem-experiment/ (Accessed 12 Aug 2013)

CERN (2012) Experiments - LHCf. Available at:

http://home.web.cern.ch/about/experiments/lhcf (Accessed 12 Aug 2013)

CERN Document Server (1996) LHC Project Progress Report 02: Design Process and

Control [Doc. No. LHC-QAP-301]. Available at: http://cds.cern.ch/record/307864/files/lhc-

project-report-02.pdf (Accessed 11 Aug 2013)

Hameri, A., Nitter, P. (2002) 'Engineering Data Management Through Different Breakdown

Structures in a Large-Scale Project'. International Journal of Project Management, 20(5) :

pp.375-384

Lebrun, P (2000) The Large Hadron Collider: A Megascience Project. [LHC Project Report

374] In: 38th INFN Eloisatron Project Workshop : Superconducting Materials for High

Energy Colliders "Ettore Majorana", Italy, pp. 11-20.

Maiani, L. (1999) 'The Large Hadron Collider Project'. Fusion Engineering and Design,

46(2-4) : pp.433-447

Petter, S. (2008) 'Managing User Expectations on Software Projects: Lessons from the

Trenches'. International Journal of Project Management, 26(7) : pp.700-712

Page 21: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

19

APPENDIX A34

Page 22: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

20

APPENDIX B

Page 23: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

21

Page 24: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

22

Page 25: Project Management Individual Report - Large Hadron Collider Analysis and Recommendations

23

APPENDIX C