CVE 4091 - DESIGN 1Project Management
Requirements
Project Phases Design 1 – Prepare proposal
Purpose is to win the designProposal must state why your team is bestMust include a Project Management Plan in the proposalMust include your proposed fee for design
Design 2 – Design the projectVerify the proposal @ 5% stageDesign phases @ 15, 50, 95,100%Develop engineering details & construction drawingsManage & report on status@15, 50, 95,100%Integrate all design elements into unified projectPrepare display for Design Showcase in AprilEstimate cost of construction @ 15, 50, 95,100%Written report is graded at each stage
Proposal Contents-11. Title Page – follow instructions
2. Letter of Transmittal – transmits your fee/price; PM signs
3. Table of Contents – separate tab for each section
4. Introduction Project Background – focus the reader Scope of Work – what’s included & what’s not Project Site Map – where is it Team Organization – who will do it
5. Project Management Plan Project Flow Diagram – flow of tasks over time Work Breakdown Structure – who will do each task Design Budget (fee) – what will each task cost Design Schedule (MS Project) – when will each task be completed Conceptual cost of construction – cost to actually build the project
Proposal Contents-26. Project Layout & Base Map
Base Map shows data on boundaries and major features Layout adds “proposed” location and size of engineering features: roads,
piping systems, retention ponds, etc. All team members should participate in this drawing
7. Preliminary Design Investigation - each engineer Written Technical Report – consult with engineering advisor Include such items as:
• Engineering problem(s) to be solved in the design• Logic of location & size of engineering features• Design options considered; cite the pros & cons of each• Applicable codes, ordinances or criteria that will control the design• Cite all technical information to be used in the design• Design decision – what engineering design method will be used and why• Constraints – cite any political, environmental or physical limitations
8. Global, Societal and Professional Issues
9. Appendices & List of References
Project Management Tools =Your Project Dashboard
They enable you to be proactive rather than reactive…
Project Management Tools Project Flow Diagram
your road map/GPS
Project Schedule
your speedometer
Project Budget
your fuel gauge
Project Design Flow Diagram
Time2 4 6 8 10 12 14 16
General Design
Planning Preparation Construct Core
Trim Exterior
Demobilize
Interior Design Room Const Interior Finishes
Bury Pharoah
Structure
Site Selection
Master Plan
Open Quarry Cut Blocks Cut Trim
Workforce
Train Train Train
Build Camp
DemobCamp
FinalInsp
Flow Diagram-2
Work Breakdown Structure
Work Breakdown Structure
Don’t forgetTo update durationAt each % stage!!!WBS
Design Budget
Don’t forgetTo show totalsAt each % stage!!!
Don’t forgetTo update durationAt each % stage!!!
Budget
Design Schedule – MS Project
Conceptual Cost Estimate
Preliminary Construction Cost Based on historical data Itemize components: W&WW, Structure, Roads, etc. Base on similar project Use cost per SF or similar data Be sure to update for location & timing
Example: construct a 300-bed college dorm @ FIT
Base: 2008 UCF example @ $25,000/bed (Const data or RS Means)
Location: Melbourne vs. Orlando = 0.83 (RS Means)
Timing: Inflation = 10% 2008-2014 (Internet)
Conceptual cost = $7,500,000 x .83 x 1.1 = $6,847,500
Questions????