Upload
jennyrosesison
View
18
Download
1
Tags:
Embed Size (px)
DESCRIPTION
Project Scheduling
Citation preview
Project Project ManagementManagement
Project ManagementProject Management
The on-going process of directing and coordinating all the steps in the development of an information system
Goal to produce an IS that is acceptable to its end-user
developed within the specified time frame and budget
Project Management...Project Management...
Rolerecognize such factors and to eliminate/minimize their negative effects
Playersmanages a project to develop an ISdefines a project’s activities and events
estimates the time and cost necessary to complete each activity
Project Management...Project Management...
Players (cont...)schedules and assigns the activities to specific members of the project team
coordinates activitiesmonitors eventsevaluates and reports on the progress of the activities and events
Project SchedulingProject Scheduling
determining the order in which activities will be performed, setting start and end times for each activity, and assigning specific tasks to team members
SCHEDULING TOOLS◦GANTT Charts◦PERT/ CPM Charts
GANTT ChartsGANTT Charts
GANTT Charts◦developed by Henry L. Gantt ◦a horizontal bar that graphically illustrates a
schedule◦horizontal axis : time◦vertical axis : activity◦length of the bar indicates duration of the
activity
GANTT Charts...GANTT Charts...
GANTT Charts (cont...)◦positioning of the bar shows the start and end
of the activity◦useful for tracking and reporting progress◦graphically displays a schedule◦often used to report progress because they
present an easily understood picture of project status
GANTT Charts...GANTT Charts...
1. The completed portion of each bar is shaded.
GANTT Charts...GANTT Charts...
current date
2. A triangle or arrowhead indicator is used.
GANTT Charts...GANTT Charts...
3. A second bar shows the completed work.
GANTT Charts...GANTT Charts...
Problems◦no indication of activity dependencies◦how an activity which is behind schedule can
influence the entire project◦no. of hours per day required to complete an
activity is not shown◦no. of people assigned is also not shown◦it can not determine how far ahead/behind
schedule a project is
Create a Gantt Chart◦Task 1 – Jan. 14 – Feb 10◦Task 2 – Feb 19 – Mar 18◦Task 3 – Mar 16 – Apr. 24◦Task 4 – May 4 – May 31◦Task 5 – Mar 19 – Apr 14◦Task 6 – Apr 16 – Jun 6◦ Task 7 – May 16 – July 14
PERT/ CPM ChartsPERT/ CPM Charts
PERT (Program Evaluation Review Technique)◦developed by the Navy Special Projects Office
in 1950’s to control the development of the Polaris submarine missile program(Three point estimate)
CPM (Critical Path Method)◦developed by the private industry at the same
time as PERT to meet similar project management needs (Single point estimate)
PERT/ CPM Charts...PERT/ CPM Charts...
Charting Conventions◦Activity
- Describes each task Shown as vectors -Line with an Event Represented as branches (lines)
-Identified by letters
- Start/end of an activity
PERT/ CPM Charts...PERT/ CPM Charts...
Event◦displayed graphically as nodes, circle or
rectangle◦identified as node in the network
Path◦sequence of activities leading from the
beginning node to the final node
PERT/ CPM Charts...PERT/ CPM Charts...
Dummy Activities◦indicated by dotted lines◦no labeled process description/time◦used to ensure continuity
Simultaneous activity◦serial arrangement means one after the other◦parallel format shows overlapping activities
PERT/ CPM Charts...PERT/ CPM Charts...Concepts:
◦Optimistic time estimate – completion time expected if everything went exactly as planned
◦Pessimistic time estimate – completion time expected if everything possible went wrong
◦Most likely time estimate – only if normal problems are encountered
◦Critical Path – defines the most sensitive part of the chart that may affect the schedule of the whole project (longest time to complete)
◦Slack – extra time to do an activity without affecting project schedules
Getting the Estimated Time and Slack
ET = Optimistic + 4 x Most Likely + Pessimistic / 6
Slack/Float = Earliest Finish – Latest Finish
PERT/ CPM Charts...PERT/ CPM Charts...
Rules in PERT/CPM NetworksEach activity must be represented by its
own branch on the chart.Direction of time flows is indicated by
arrows. An activity line meeting an event node indicates activity completion. The length of an activity branch is not representative of the time the activity will take.
PERT/ CPM Charts...PERT/ CPM Charts...
Relationship between activities are determined by the sequence of the branches.
If several activities terminate at one node, no activities starting at that node may begin until all entering activities are completed.
For analysis reason, no two activities are allowed to both start and end at the same nodes. If the project network would seem to require this, a dummy activity must be inserted.
A dummy activity has no time, it merely preserves the proper sequencing in the network design.
PERT/ CPM Charts...PERT/ CPM Charts...
Steps included:1. determine the activities needed to
complete the project 2. sequential relationship of these activities
(try to establish as many simultaneous activities as possible
3. estimate the completion time for each activity
4. draw the PERT/CPM network, showing the relationship activities as determined in STEP 2
PERT/ CPM Charts...PERT/ CPM Charts...
Steps included:5. starting with the beginning node of the
network, use the earliest start – earliest finish relationships to determine the project completion time (Forward Pass)
6. moving to the end node of the network, use the latest start – latest finish relationships to determine the activities on the critical path and the float for activities not on the critical path
PERT/ CPM Charts...PERT/ CPM Charts...
7. use the earliest time - earliest finish relationships in STEP 5 and the latest start – latest finish relationships in STEP 6 to develop an activity time table for the project
Network Diagram The most common information shown is:The activity name The normal duration time The early start time (ES) The early finish time (EF) The late start time (LS) The late finish time (LF) The slack