PROJECTS photovoltaic power plants in the FBiH. PV E planned installed capacity of 1.0 MWp in the Federation with the approved building permit. PV E JELAH 1, JELAH-TEŠANJ. BACKGROUND. Installed capacity: 1 MW Location: Jelah Project Owner: KEBEX d.o.o. Obtained DOCUMENTATION: - PowerPoint PPT Presentation
Citation preview
EPBIH
• Generation, distribution & supply of electricity
• Established in 1946
• Share Capital 1.144 billion EUR (90 % state & 10 % private share)
• Operates with 2 TPPs, 3 HPPs & 8 small HPPs
• The biggest company in B&H
Company profile
TPP Tuzla
• 90% state • 10% private
Generation Distribution & Supply
TPP Kakanj
HPP on Neretva
ED Bihac
ED Tuzla
ED Zenica
ED Sarajevo
ED Mostar
Company structure
2014Current facts
Description Dec. 31, 2014
Dec. 31, 2013
Dec. 31, 2012
Shareholders capital 1,144 1,144 1,144 mil. €
Operational revenues 482,6 497,3 454.0 mil. €
Operational expenditures 396,1 392,5 378.3 mil. €
EBITDA 86,5 104,8 75.7 mil. €
Profit/Loss 1,6 18,9 3.6 mil. €
Production 7,404 7,473 6,509 GWh
Installed capacity 1,682 1,682 1,682 MW
Number of customers 733.600 724.607 715.411
Number of employees 4.855 4.848 4.873
Company’s key indicators
0
200
400
600
800
1000
1200
1400
1600
1800
2000
Assets Equity & Liabilities
Short term liabilities
Long term liabilities
Equity
Current assets
Fixed assets
Balance Sheet 2014
(€ million)
*excluding coal mines
Financial results 2014(€ million)
0,00
100,00
200,00
300,00
400,00
500,00
600,00
Revenues Costs Depreciation Profit
Fees
Coal transport
Other costs
Maintenance
Transmission
Wages
Material for gen.
other revenues
financing
services
heat
electricity
01.0002.000
3.000
4.000
5.000
6.000
7.000
8.000
2007200820092010 2011 20122013 2014
Thermal
Hydro Thermal
Production indicators
010002000300040005000600070008000
92 93 94 95 96 97 98 99 '00 '01 '02 '03 '04 '05 '06 '07 '08 '09 '10 `11 `12 `13 `14
G Wh
GWh 2013 2014 %
Production 7,473 7,404 - 0,9%
Thermal 5,550 5,787 +4,3%
Hydro 1,923 1,617 -15,9%
Hydro % 26% 22%
End users (Gross)
4,980 4,953 -0,5%
Production and coal supply
01000200030004000500060007000
'99 '00 '01 '02 '03 '04 '05 '06 '07 '08 '09 '10 `11 `12 `13 `14
000 t
Coal purchase in 20145,536 thousand tons+ 4,9% compared to 2013
• Thermal power generation is dominant and is participating in total production between 70 – 80%
• Hydro power generation is inferior and is participating in total production between 20 – 30%
• EPBiH is 100% owner of seven coal mines within FBiH
• More than 85% of the total coal is produced within own coal mines
• Price of coal is defined by the FBiH Government (90% owner of EPBiH)
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
3,488 3,409 4,087 4,306 4,606 4,622 4,985 5,139 5,73 5,657 5,362 6,192 6,232 5,536 5,809
Average electricity market sales price
0
10
20
30
40
50
60
70
2006 2007 2008 2009 2010 2011 2012 2013 2014
Average price (€/MWh)
Year 2006 2007 2008 2009 2010 2011 2012 2013 2014
Average price (€/MWh) 35.4 47.0 56.3 64.9 44.9 51.1 53.3 51.1 44.8
NEW CAPITAL INVESTMENTS IN EPBiH
Background of the opportunity
Bosnia and Herzegovina is the country with the highest energy potential in Southeastern Europe:
• Bosnia and Herzegovina is a net exporter of electric power• 8.1% of Bosnia’s total exports is related to electric power• Total currently installed and operating capacity - 3.400 MW• Energy production capacities are not fully exploited.• The total estimated hydro potential in BIH is estimated of 23,395 GWh/per year (of which only approx. 25% are being utilized)• BIH has significant reserves of coal (3.7 billion tons of lignite and 2.2 billion tons of brown coal)
which allow development of new thermal power plants.• The Government of the Federation of BIH announced a series of projects in the energy sector in
the total value of € 5 billion as a major building block of the economic strategy of the country
Investment environment
• Reliable energy supplier in
the country and region;
• Meet the requirements of EU
& increase of generation
from renewable energy
sources;
• Massive investments needed
in energy sector
• Increasing demand for
energy
• Volatility in energy prices
DRIVERS
What will we do?
> Uptake new technologies
> Significantly reduce CO2 emissions
> Increase the efficiency of existing thermal power plants (replacement project)
> Diversify the energy portfolio and increase the reliability
> Improve distribution network
> Jobs creation• Frequent outages
• Resource endowment
• Technical Capacity
Projects are based on Strategic plan and program of development of energy sector inFederation of B&H and Government decisions
• WF Podveležje • WF Vlašić
Thermal PP
• TPP Kakanj, Unit 8• TPP Bugojno, Unit 1• TPP Tuzla, Unit 7 in tendering stage
Renewable Energy PP - Hydro
• HPP Vranduk in tendering stage• HPP Una Kostela• HPP Janici • HPP Kovanici• HPP Babino Selo• HPP Krusevo & Zeleni vir• HPP Ustikolina• SHPP on Neretvica river
List of ongoing projects
Renewable Energy PP - Wind
• WF Vlasic• WF Podvelezje in tendering stage
Thermal power plants - planned projects (Investors/strategic partner/JV)
TPP KAKANJ, UNIT 8
Investment ready
TPP & COAL MINE BUGOJNO, UNIT 1
Planning phase
TPP TUZLA, UNIT 7
In tendering phase
Replacing cogeneration unit at the existing location450 MW /2.756 GWh
Investment: 842 mill. €
Replacing cogeneration unit at the existing location300 MW / 1.755 GWh
Investment: 626 mill. €
The new cogeneration unit and coal mine 300 MW / 1.755 GWh Investment: 681 mill. €
Hydro power plants - planned projects I
HPP VRANDUK
In tendering phase
Run-of-river, diversion plant20 MW /96 GWh
Investment: 64,6 mill. €
HPP USTIKOLNA
Investment ready
Run-of-river, plant inside dam60 MW / 247 GWh
Investment: 123 mill. €
SHPP’s ON NERETVICA RIVERPlanning phase
Investment: 49,7 mill. €
15 plants to be constructed in 3 phases26,1 MW / 102 GWh
HPP KRUSEVO & ZELENI VIR
Planning phase
Kruševo: Accumulation,Zeleni Vir: Run-of-river, plant inside dam9,7+2,1 MW / 21,7+8,4 GWh
Investment: 46,6 mill. €
Hydro power plants - planned projects II
HPP KOVANIĆI
Planning phase
HPP UNA KOSTELA
Planning phase
run-of derivation power plant6.46 MW / 21.42 GWh
Investment: 10 mill. €
HPP JANJIĆI
Planning phase Investment: 35 mill. €
run of dam power plant13.3 MW / 68 GWh
HPP BABINO SELO
Planning phase
run-of derivation power plant11,5 MW / 59,5 GWh
Investment: 35 mill. €
run of dam power plant13.3 MW / 68 GWh
Wind farm - planned projects
WF Podveležje
In tendering phase
New project on new location46 MW /93 GWh
Investment: 64 mill. €
WF Vlašić
Planning phase
New project on new location48 MW / 98 GWh Investment: 64 mill. €
Project description TPP Kakanj
History of the plant & new project
• The TPP «Kakanj» is located in the center of Bosnia, 40 km from Sarajevo. • The first units of the TPP were completed in 1956. • The current installed power amounts to 578 MW with an annual output of 2.300 GWh. • Yearly consumption of coal amounts to 1,8 million tons.• The planned construction of the new TPP Unit will provide replacement capacities for the part of
the existing units which will be shut down.• All the required infrastructure for the construction of the replacement TPP Unit is available• Connection to a 400 kV grid (currently under - loaded) is secured.• Long-term supply of coal for the duration of the project and beyond is secured.• The new Unit will be designed as a cogeneration unit to provide long term supply of heating
energy to the nearby towns.
Environmental impacts
• Increased energy efficiency and accordingly reduced emission of greenhouse gases • The new Unit is designed in compliance with technologies, which assures the emission of all
pollutants to be below the permissible limit values and in accordance with the EU legislation
Project description TPP Kakanj – current statusProject preparation progress as of today
Requireddecisions by the Government
CompletedStudies &Preparation
Permitsobtained &documents inpreparation
• Completed
• Preliminary design of the plant• Investment study• Environmental study
•Enviromental permit obtained•Land permit obtained•Grid connection permit obtained
Planned activities
Tender forthe investitors
Joint projectpreparation
Start ofconstruction& operations
•Closing of the financial structure•Decision on equipment supplier •Issuance of the construction permit
•Start of civil works •Start of commercial production
•Issuance of the tender•Application deadline •Decision on the investitors
Project description TPP Kakanj - summaryBasic project data
Items Values
Installed power 300 MW
Production (based on 6.500 hours of production) 1.755 GWh
Efficiency in condensing mode 39%
Efficiency in co generation mode‐ > 70%
Coal consumption 1,3 million tons/year
Emission SO2 < 150 mg/Nm3
Emission Nox < 200 mg/Nm3
Emission Dust < 10 mg/Nm3Total Investment
Items Values
Estimated total investment costs
€ 529 millionProject development timelines
Items Values
Call for expresesion for interest June 2014
Selection of project partner May 2015
Closing of partnership aggreement December 2015
Project implementation January 2016
Issuance of the construction permit May 2016
Start of civil works for the main power building (MPB) May 2016
Start of commercial production September 2020
Project description TPP Kakanj - Heating pipelineBasic project data
Items Values
Lenght from Kakanj to Zenica 33 km
Heat Capacity 200MW th
Estimated total investment cost € 61,6 milion
EPBiH interest
• Efficiency increasing of existing and future units• Assure market for heating energy in long term period• Revenue increasing• Meet the requirements of EU and Reducing of
emissions
Local community interest
• Stable heating sistem• Less polution• Energy efficiency• Job creation
Items Values
Lenght from Kakanj to Sarajevo 40 km
Heat Capacity 450MWth
Estimated total investment cost € 61,6 milion
HPP Ustikolina Project description
Overview
• The HPP «Ustikolina» is located on the Drina river• 4 HPP already exist on river Drina• HPP «Ustikolina» is run-of-river power plant• Connection to a grid is enabled on existing 110 kV OHL
Positive & Enviromental impacts
• Independent energy production source for the region• Production of energy from renewable energy sources• Waterflow control system improvement • Economical benefit to local communities• Development of local infrastructure • Local tourism development
HPP Ustikolina project description – current status
Project preparation progress as of today
Requireddecisions by the Government
CompletedStudies &Preparation
Permitsobtained &documents inpreparation
• Completed
• Prefeasibility study • Preliminary design & Environmental impact assessment study
• Preliminary water approval • Certification for connection on transmission grid• Environmental permit
Planned activities
Projectpreparation
Start ofconstruction& operations
• Urban permit Concession agreement• Issuance of the construction permit
• Start of construction• Start of commercial production
• Closing of the financial structureLoan agreement
Urban permit for investigation works
• Ongoing activities
Project description HPP Ustikolina - summary
Basic project data
Items Values
Installed power 60,48 MW
Annual production 237 GWh
Total InvestmentItems Values
Estimated total investment costs € 139 million
Project development timelines
Items Values
Preliminary designEnvironmental permit
December 2013 February 2014
Urban permit December 2015
Ensuring of financial sources June 2016
Issuance of the pre-construction permit December 2016
EPC tender completness February 2017
Start of HPP construction September2017
Start of commercial production 2022
Project description HPP Kruševo & Zeleni Vir
Overview
• HPP Kruševo & HPP Zeleni Vir is located on the Bioštica river, Olovo Municipality• HPP kruševo is peak HPP; HPP Zeleni Vir is compensation HPP• Connection to a grid is enabled on existing 110 kV & 35kV network
Positive & Enviromental impacts
• Production of energy from renewable energy sources• Increasing of energy production in Electro energetic system• Waterflow control system improvement • Economical benefit to local communities• Development of local infrastructure
Project description HPP Kruševo & HPP Zeleni Vir – current status
Project preparation progress as of today
Requireddecisions by the Government
CompletedStudies &Preparation
Permitsobtained &documents inpreparation
• Completed
• Prefeasibility study • Preliminary environmental impact assessment
• Mine clearance certification obtained
Planned activities
Projectpreparation
Start ofconstruction& operations
• Urban permit• Concession agreement• Issuance of the construction permit
•Start of construction•Start of commercial production
•Closing of the financial structureLoan agreement
WBIF funds approved
•Environmental impact assessment &Preliminary design
Project description HPP Kruševo & HPP Zeleni Vir - summary
Basic project data
Items Values
Installed power 10,97 MW & 2,36 MW
Annual production 30,76 GWh & 9,64 GWh
Total InvestmentItems Values
Estimated total investment costs 33,75 mil € & 9.63 mil. €
Project development timelines
Items Values
Preliminary design & Envoronmental studyEnvironmental permit
May 2015August 2015
Urban permit September 2015
Ensuring of financial sources October 2015
Issuance of the pre-construction permit December 2015
EPC tender completness april 2016
Start of HPP construction December 2016
Start of commercial production 2020