8/17/2019 Proposal & Report - Additional Return AR Room
1/9
Additional Grill in AR Room AR
March, 2016
8/17/2019 Proposal & Report - Additional Return AR Room
2/9
2
PT. Vision-Ease Asia - VEA-FR-MPRP-EPRO-02 Form Proposal Project Rev. 0a Tgl. 18 Feb 14 1/1
Catatan : Setiap copy dokumen internal tanpa tanda “Controlled Copy” dianggap sebagai dokumen tidak terkendali. Adalah tanggung jawab setiap pengguna untuk memastikan isi dokumen
yang digunakannya sebagai yang terbaru dan berlaku serta memusnahkan dokum
1. Currently particle count is very high (out of spec) in some spot places.
2. There is only 1 return (grill) in AR room, it causes flow not laminar.
3. Existing return grill is big with dimension 1240x640mm (1 for all station).
Proposal Name : Additional Return AR Room
Date : March, 2016
Background :
1. Reduce particle count in AR room.2. Make flow in AR room becomes laminar by adding some new return in some spot with high
particle counting.
3. Adopt coating room with laminar flow into AR room.
Purpose :
1. Particle counting (in spec).
2. Laminar flow in AR room.
Target :
1. Dimension2. Particle counting
3. Laminar flow
Checking Item :
1. Dimension grill return 600x100mm
2. Additional return for 6 position in AR room.Other Information :
Initiated By Prepared By
Checked By Approved By
Eng. Project Eng. AR Senior Manager
Angga Istia Fadilah Maryatin Zulkarnain Ikin Santosa T
8/17/2019 Proposal & Report - Additional Return AR Room
3/9
3
8/17/2019 Proposal & Report - Additional Return AR Room
4/9
Existing AR Return
Currently there is only 1 (big size)
return in AR coating room coveredall stages.
1240mm
640mm
8/17/2019 Proposal & Report - Additional Return AR Room
5/9
Layout
Note:
• Resize existing return from 1240x640mm to 600x100mm
• Add new return 600x100mm
• Total return in AR Room: 6 position
Actual Plan
Existing: 1240x640mm
2
3
4
5
6
1
8/17/2019 Proposal & Report - Additional Return AR Room
6/9
Particle Count
8/17/2019 Proposal & Report - Additional Return AR Room
7/9
Plan
Needed additional Return, for Laminar Flow. Like as Hard Coating Room and Pre-
cure Room. It’s able to reduce particle.
Especially on Machine, loading, and oven area.
8/17/2019 Proposal & Report - Additional Return AR Room
8/9
Measurement
Measurement of particulate in AR Room is not stable.
And each area difference result.
Higher particulate at Oven area, machine area, and loading area
HEPA AreaScan
HEPA AreaTengah
HEPA AreaConveyor
DepanKonveyor
Coater#1 Coater#2 Loading#1 Loading#2 Area AntarCoater
Oven#1 Oven#2
24-Feb-16 124 4 7 0 0 0 0 0 0 0
25-Feb-16 66 2 0 10 762 3877 11 383 383 383
26-Feb-16 60 657 9 677 266 296 34 34 34
1-Mar-16 1 0 0 146 857 386 68 355 1178
2-Mar-16 3 4 0 6 37 674 239 19 435 990 2241
3-Mar-16 0 6 1 6 96 1554 50 639 206 748 1733
4-Mar-16 21 23 5 83 1009 3354 367 69 995 1779 3893
5-Mar-16 91 0 5 0 85 979 49 75 631 749 9637-Mar-16 1 3 6 3 59 183 30 30 66 193 602
8-Mar-16 1 55 167 1238 37 26 340 1262 1419
9-Mar-16 53 3 3 220 226 934 71 448 183 460 862
10-Mar-16 2 1 0 31 252 803 366 691 665 2257 2896
11-Mar-16 11 93 191 697 146 22 57 677 1135
14-Mar-16 7 0 0 1 286 482 185 520 482 1721 9041
15-Mar-16 1 17 0 1 61 679 136 35 195 2013 3598
16-Mar-16 87 20 6 45 86 752 250 76 176 2531 3652
17-Mar-16 0 2 0 0 68 1492 228 272 2005 1257 1357
18-Mar-16 5 0 1 0 13 1395 374 651 2287 1879 1870
19-Mar-16 1 2 6 13 39 848 151 137 384 1029
21-Mar-16 27 10 0 15 49 651 258 179 737 821 2635
22-Mar-16 0 0 2 2 109 149 181 259 235 697 378
23-Mar-16 0 0 102 51 460 269 88 979 1243 5
24-Mar-16 1238
0.5 (µm)
Tanggal
8/17/2019 Proposal & Report - Additional Return AR Room
9/9
Air Flow
Current condition AR Air Flow is not Laminar Flow
Only one return from 4 supply.
It is able make a turbulence air
Not Laminar Flow in AR Coater