    US 29 / 15/ 17 Interchange StudyFauquier County, Virginia

    March 8, 2013

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    2/28

    PROJECT HISTORYUS 29 / 15 / 17 Interchang

    Page 1

    This interchange study explores the feasibility of

    constructing an interchange at the existing at-grade

    intersection of Route 29/15/17 with Business Route29/15/17 & Lord Fairfax Road just at the southern edge

    of the Town of Warrenton in Fauquier County.

    Route 29 is a major north-south route in Virginia

    spanning 248 miles from the North Carolina State Line in

    Danville to the Key Bridge in Washington D.C. The

    portion from Danville to Warrenton is known as the

    Seminole Trail. Through the project areas, US 29 is co-located with US Route 15 and US Route 17.

    Route 29 is a principal arterial. South of the project

    intersection, Route 29 is four-lane highway with at-grade

    intersections. North of the project intersection, Route

    29 is a limited access bypass of Warrenton with grade

    separations. Business Route 29 is classified as a minorarterial while Lord Fairfax Way is not federally classified

    and thus a local road.

    Existing Intersection

    Project

    Area

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    3/28

    PROJECT HISTORYUS 29 / 15 / 17 Interchang

    Page 2

    When the Route 29 Bypass was constructed in the early

    1980s, an interchange was explored at this intersection.

    Several designs were considered including a full

    cloverleaf and Route 29 on new alignment.

    However, ultimately a trumpet interchange design was

    chosen and limited access right-of-way was acquired in

    the 1990s.

    1980s Original Interchange

    Concepts

    1980s Design Plans for a Trumpet

    Interchange

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    4/28

    PROJECT HISTORYPREVIOUS ALTERNATIVESUS 29 / 15 / 17 Interchang

    Page 3

    Recently VDOT explored several preliminary interchange alternatives for this

    intersection utilizing the existing right-of-way as much as possible. Four distinct

    alternatives were developed and compared.

    Alternative 1 Alternative 2

    Alternative 3

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    5/28

    PROJECT HISTORYPREVIOUS ALTERNATIVESUS 29 / 15 / 17 Interchang

    Page 4

    Comparison

    MatrixAlternative 4

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    6/28

    EXISTING 2009 TRAFFIC CONDITIONSUS 29 / 15 / 17 Interchang

    Page 5

    21

    1198

    470

    10

    17

    5

    39

    45

    860

    41

    165

    27

    AM PEAK HOUR N

    1689

    C

    32

    944

    23314

    895

    293

    39

    44

    16

    60

    73

    1413

    77

    637

    40

    1202

    E

    1546

    754

    PM PEAK HOUR

    James Madison Hwy

    Easte

    rnBypass

    JamesMa

    disonHwy

    Lord Fairfax Rd (Route 880) James Madison Hwy

    Easte

    rnBypass

    JamesMa

    disonHwy

    Lord Fairfax Rd

    F

    F EC

    D BC

    C

    E

    E

    F

    E

    D

    D

    D

    D

    D

    D

    D

    D BC

    C

    E

    E

    D

    D

    DB C

    C

    Business Business

    LEGEND: Volume Level of Service233 C

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    7/28

    Traffic volumes for design year 2040 were developed by

    applying historic trend growth rates to existing counts and

    adding additional traffic associated with the planned ArringtonProperty Development.

    FUTURE GROWTHUS 29 / 15 / 17 Interchang

    Page 6

    Route 2010VPD

    2040VPD

    %Trucks

    US 15-17-29 43,400 74,100 9%

    US 15-17-29 Bypass 39,700 68,100 9%

    Bus 15-17-29 10,500 15,700 2%

    Route 880 3,100 19,300 6%

    2040 Design Year Volumes

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    8/28

    FUTURE 2040 NO-BUILD TRAFFIC CONDITIONSUS 29 / 15 / 17 Interchang

    Page 7

    192

    1838

    721

    35

    95

    50366

    80

    1527

    66

    267

    251

    2751

    F

    180

    1973

    584

    James Madison Hwy

    Easte

    rnBypass

    JamesMa

    disonHwy

    Lord Fairfax Rd (Route 880)

    AM PEAK HOUR N

    41

    1373

    449

    150

    315

    258190

    130

    2509

    124

    1029

    120

    F

    1863

    F

    1546

    1273

    PM PEAK HOU

    James Madison Hwy

    JamesMa

    disonHwy

    Lord Fairfax Rd

    F

    F

    F

    F

    F

    F

    E D B

    FFC

    D

    F

    F

    FF

    EF F B

    F

    D

    D

    E E

    FFC

    F

    Business Business

    LEGEND: Volume Level of Service233 C

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    9/28

    PRELIMINARY ALTERNATIVES ELIMINATEDUS 29 / 15 / 17 Interchang

    Page 8

    Based on the previous VDOT developed alternatives and consideration for the future traffic demand, Baker devel

    five preliminary interchange concepts for the project.

    Three of the five alternatives were eliminated from further consideration and two advanced for further study.

    three eliminated include:

    1. Mainline Bridges Alternative

    Eliminated from further study

    Left hand exit does not meet driver

    expectations and could result in safety issues.

    Most expensive alternative

    Requires significant amount of retaining walls

    Requires design exception for vertical grades

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    10/28

    PRELIMINARY ALTERNATIVES ELIMINATEDUS 29 / 15 / 17 Interchang

    Page 9

    2. Partial Cloverleaf Alternative

    ( loops to the South)

    Eliminated from further study

    Least amount of storage for heaviest turn

    movement (NB to WB left)

    Still requires a traffic signal

    Requires most right-of-way

    Tight SB loop off-ramp < 25 mph

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    11/28

    PRELIMINARY ALTERNATIVES ELIMINATEDUS 29 / 15 / 17 Interchang

    Page 10

    3. Partial Cloverleaf Alternative

    ( loops to the North)

    Eliminated from further study

    NB to EB movement could block loop ramp

    which carries the heaviest turn movement (NB

    to WB left)

    Still requires a traffic signal

    Tight NB loop off-ramp < 25 mph

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    12/28

    Page 11

    PRELIMINARY ALTERNATIVES CARRIED FORWARDUS 29 / 15 / 17 Interchang

    Diamond Interchange Alternative

    This Interchange Study carried two alternatives forward for further study. For each alternative concept

    geometric layout, operational functionality, right-of-way impacts, constructability, and costs were analyzed.

    The concepts were re-designed to carry the 2040 forecast traffic volumes for the project area. The cross-streeta design speed of >=40 mph and the ramps a design speed of >= 25 mph.

    The two preliminary alternatives carried forward are:

    Roundabout Interchange Alternative

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    13/28

    DIAMOND INTERCHANGE CONCEPTUS 29 / 15 / 17 Interchang

    Page 12

    The Diamond Interchan

    Concept consists of:

    Removing the existinggrade signalized inter

    Carrying Lord Fairfax

    over Route 29 Bypass

    six-lane bridge.

    Four ramps with RoutBypass.

    Signalized intersectio

    either side of the cro

    bridge at the ramp te

    5-foot sidewalk on no

    of interchange.

    2011 Project Costs

    PE:

    RW:

    CONST:

    TOTAL:

    2,000,000

    100,000

    24,000,000

    26,100,000

    Diamond Interchange

    Concept

    Curb and gutter

    Landscaped Median

    Bridge

    Road Improvements

    Existing ROW

    ROW Acquisition

    Sidewalk

    Potential SWM Pond

    Legend

    Pavement Demolition

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    14/28

    DIAMOND INTERCHANGE CONCEPTUS 29 / 15 / 17 Interchang

    Page 13

    The Diamond Interchange Concept

    the following operational character

    Ramp termini will need to be sign

    by opening day.

    The western Ramp termini inters

    is expected to operate at LOS B o

    better for both AM and PM peak

    The eastern Ramp Termini Intersis expected to operate at LOS C o

    better for both AM and PM peak

    Ramp junctions with Route 29 By

    expected expected to operate at

    or better for AM peak hour and L

    or better for PM peak hour with design volumes.

    Diamond Interchange

    Concept

    Curb and gutter

    Landscaped Median

    Bridge

    Road Improvements

    Existing ROW

    ROW Acquisition

    Sidewalk

    Potential SWM Pond

    Guardrail

    Legend

    Pavement Demolition

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    15/28

    DIAMOND INTERCHANGE - RIGHT OF WAY NEEDSUS 29 / 15 / 17 Interchang

    Page 14

    The Diamond Interchan

    Concept requires 1.98 aright-of-way:

    Right-of-way based on

    Fauquier County GIS d

    Retaining walls may b

    to reduce acquisition

    Construction easemen

    could be used instead

    ROW acquisition for d

    roads during construcDiamond Interchange

    ConceptExisting ROW

    ROW Acquisition

    Legend

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    16/28

    ElevationLooking North

    DIAMOND INTERCHANGEBRIDGE DETAILSUS 29 / 15 / 17 Interchang

    Page 15

    Typical Section - Looking East

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    17/28

    DIAMOND INTERCHANGE - CONSTRUCTABILITYUS 29 / 15 / 17 Interchang

    Page 16

    Bridge Construction

    Road Construction

    SWM Pond Construction

    Legend

    Temporary Pavement Phase 1

    Construction

    Phase 1 Construction:

    Maintain all traffic movements at existing signalized intersection.

    Divert WB Business Route 29/15/17 traffic to EB Business Route 29/15/17.

    Construct Bridge & SWM Ponds. Construct Westbound Lord Fairfax Road and WB Business Route 29/15/17.

    Construct SB off-ramp & NB on-ramp and a portion of the NB off-ramp & SB on-ramp.

    Lord Fairfax Rd.

    James Madison Hwy

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    18/28

    DIAMOND INTERCHANGE - CONSTRUCTABILITYUS 29 / 15 / 17 Interchang

    Page 17

    Road Construction

    SWM Pond Construction

    Legend

    Phase 1 Construction

    Temporary Pavement

    Phase 2Construction

    Phase 2 Construction:

    Divert EB Business Route 29/15/17 traffic to WB Business Route 29/15/17.

    Divert EB Lord Fairfax Rd traffic to WB Lord Fairfax Road & utilize SB off-ramp & NB on-ramp

    Maintain WB to SB left turn movement at existing signalized intersection.

    Detour NB to WB and NB to EB traffic onto Lord Fairfax Rd prior to project area.

    Detour SB on-ramp traffic using temporary pavement.

    Construct SB on-ramp and a portion of EB Business Route 29/15/17.

    Lord Fairfax Rd.

    James Madison Hwy

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    19/28

    DIAMOND INTERCHANGE - CONSTRUCTABILITYUS 29 / 15 / 17 Interchang

    Page 18

    Road Construction

    SWM Pond Construction

    Legend

    Phase 1 & 2 Construction

    Temporary PavementPhase 3

    Construction

    Phase 3 Construction:

    Divert EB Business Route 29/15/17 traffic to WB Business Route 29/15/17.

    Divert EB Lord Fairfax Rd traffic to WB Lord Fairfax Road &

    utilize SB off-ramp, NB on-ramp & SB on-ramp

    Detour NB to WB and NB to EB traffic onto Lord Fairfax Rd prior to project area. Construct final portion of NB off-ramp and a portion of EB Business Route 29/15/17.

    Enlarge SWM pond.

    Lord Fairfax Rd.

    James Madison Hwy

    DIAMOND INTERCHANGE COST ESTIMATE

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    20/28

    DIAMOND INTERCHANGECOST ESTIMATEUS 29 / 15 / 17 Interchang

    Page 19

    Assumptions

    VDOT Culpepper District Average Unit Costs 2009-20

    Bridge Costs = $250 SF

    Pavement Section: 2.0 Surface Coarse + 4.0

    Intermediate Coarse + 7.0 Base Mix + 8.0 Subbase

    Aggregate.

    Miscellaneous 20%

    Contingency 10%

    ROW Costs = 140% of assessed land value +$15,000

    admin fees per parcel.

    Utility Adjustments minimal project passes over w

    line and gas line easement as does the existing road

    Cost Estimate

    Roadway & Drainage Costs: $ 9,500,000

    Bridge Costs: $ 4,800,000

    Miscellaneous (20%): $ 2,850,000

    Contingency (10%): $ 1,450,000

    Mobilization/Survey/MOT: $ 2,400,000

    Base Estimate for Construction: $ 21,000,000

    Right-of-way/Utilities: $ 200,000

    Construction Engineering (15.5%): $ 2,900,000

    Preliminary Engineering: $ 2,000,000

    TOTAL PROJECT COSTS: $ 26,100,000

    ROUNDABOUT INTERCHANGE CONCEPT

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    21/28

    ROUNDABOUT INTERCHANGE CONCEPTUS 29 / 15 / 17 Interchang

    Page 20

    The Roundabout Interc

    Concept consists of:

    Removing the existinggrade signalized inter

    Carrying Lord Fairfax

    over Route 29 Bypass

    three-lane bridge.

    Four ramps with Rout

    Bypass.

    Roundabouts on eith

    of the cross street br

    the ramp termini.

    Multi-use Path on no

    of interchange.

    2011 Project Costs

    PE:

    RW:

    CONST:

    TOTAL:

    2,000,000

    100,000

    22,500,000

    24,600,000

    Roundabout InterchangeConcept

    Curb and gutter

    Landscaped Median

    Bridge

    Road Improvements

    Existing ROW

    ROW Acquisition

    Sidewalk

    Potential SWM Pond

    Guardrail

    Legend

    Pavement Demolition

    ROUNDABOUT INTERCHANGE CONCEPT

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    22/28

    ROUNDABOUT INTERCHANGE CONCEPTUS 29 / 15 / 17 Interchang

    Page 21

    Roundabout InterchangeConcept

    Curb and gutter

    Landscaped Median

    Bridge

    Road Improvements

    Existing ROW

    ROW Acquisition

    Sidewalk

    Potential SWM Pond

    Guardrail

    Legend

    Pavement Demolition

    The Roundabout Interch

    Concept has the followin

    operational characteristi

    Ramp termini intersec

    expected to operate at

    or better for AM peak

    and LOS C or better fo

    peak hour with 2040 d

    volumes.

    Ramp junctions with R

    29 Bypass expected ex

    to operate at LOS C or

    for AM peak hour and

    or better for PM peak

    with 2040 design volum

    ROUNDABOUT INTERCHANGE RIGHT OF WAY NEEDS

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    23/28

    ROUNDABOUT INTERCHANGE RIGHT OF WAY NEEDSUS 29 / 15 / 17 Interchang

    Page 22

    The Roundabout Interch

    Concept requires 1.98 aright-of-way:

    Right-of-way based on

    Fauquier County GIS d

    Retaining walls may b

    to reduce acquisition

    Construction easemen

    could be used instead

    ROW acquisition for d

    roads during construcRoundabout Interchange

    ConceptExisting ROW

    ROW Acquisition

    Legend

    ROUNDABOUT INTERCHANGE BRIDGE DETAILS

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    24/28

    ROUNDABOUT INTERCHANGEBRIDGE DETAILSUS 29 / 15 / 17 Interchang

    Page 23

    ElevationLooking North

    Typical Section - Looking East

    ROUNDABOUT INTERCHANGE CONSTRUCTABILITY

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    25/28

    ROUNDABOUT INTERCHANGE - CONSTRUCTABILITYUS 29 / 15 / 17 Interchang

    Page 24

    Bridge Construction

    Road Construction

    SWM Pond Construction

    Legend

    Temporary PavementPhase 1

    Construction

    Phase 1 Construction:

    Maintain all traffic movements at existing signalized intersection.

    Divert WB Business Route 29/15/17 traffic to EB Business Route 29/15/17.

    Construct Bridge & SWM Ponds.

    Construct Westbound Lord Fairfax Road and WB Business Route 29/15/17.

    Construct SB off-ramp & NB on-ramp and a portion of the NB off-ramp & SB on-ramp.

    Construct north half of both roundabouts

    James Madison Hwy

    Lord Fairfax Rd.

    ROUNDABOUT INTERCHANGE CONSTRUCTABILITY

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    26/28

    ROUNDABOUT INTERCHANGE - CONSTRUCTABILITYUS 29 / 15 / 17 Interchang

    Page 25

    Road Construction

    SWM Pond Construction

    Legend

    Phase 1 Construction

    Temporary Pavement

    Phase 2Construction

    Phase 2 Construction:

    Divert EB Business Route 29/15/17 traffic to WB Business Route 29/15/17.

    Divert EB Lord Fairfax Rd traffic to WB Lord Fairfax Road & utilize north side of roundabouts

    Maintain WB to SB left turn movement at existing signalized intersection.

    Detour NB to WB and NB to EB traffic onto Lord Fairfax Rd prior to project area.

    Detour SB on-ramp traffic using temporary pavement & utilize NB on-ramp and SB off-ramp.

    Construct SB on-ramp, a portion of EB Business Route 29/15/17 including finishing west roundabout.

    James Madison Hwy

    Lord Fairfax Rd.

    ROUNDABOUT INTERCHANGE - CONSTRUCTABILITY

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    27/28

    ROUNDABOUT INTERCHANGE - CONSTRUCTABILITYUS 29 / 15 / 17 Interchang

    Page 26

    Road Construction

    SWM Pond Construction

    Legend

    Phase 1 & 2 Construction

    Temporary PavementPhase 3

    Construction

    Phase 3 Construction:

    Divert EB Business Route 29/15/17 traffic to WB Business Route 29/15/17.

    Divert EB Lord Fairfax Rd traffic to WB Lord Fairfax Road & utilize SB off-ramp, NB on-ramp & SB on-

    ramp.

    Detour NB to WB and NB to EB traffic onto Lord Fairfax Rd prior to project area. Construct final portion of NB off-ramp including finishing east side roundabout and a portion of EB

    Business Route 29/15/17. Enlarge SWM pond.

    James Madison Hwy

    Lord Fairfax Rd.

    ROUNDABOUT INTERCHANGE COST ESTIMATE

  • 7/28/2019 Proposed interchange at Rt. 29 and Lord Fairfax Dr.

    28/28

    ROUNDABOUT INTERCHANGE COST ESTIMATEUS 29 / 15 / 17 Interchang

    Page 27

    Assumptions

    VDOT Culpepper District Average Unit Costs 2009-20

    Bridge Costs = $250 SF

    Pavement Section: 2.0 Surface Coarse + 4.0

    Intermediate Coarse + 7.0 Base Mix + 8.0 Subbase

    Aggregate.

    Miscellaneous 20%

    Contingency 10%

    ROW Costs = 140% of assessed land value +$15,000

    admin fees per parcel.

    Utility Adjustments minimal project passes over w

    line and gas line easement as does the existing road

    Cost Estimate

    Roadway & Drainage Costs: $ 9,500,000

    Bridge Costs: $ 3,800,000

    Miscellaneous (20%): $ 2,650,000

    Contingency (10%): $ 1,350,000

    Mobilization/Survey/MOT: $ 2,400,000

    Base Estimate for Construction: $ 19,700,000

    Right-of-way/Utilities: $ 200,000

    Construction Engineering (15.5%): $ 2,700,000

    Preliminary Engineering: $ 2,000,000

    TOTAL PROJECT COSTS: $ 24,600,000