F. Pedrosa EN-ACE
PS LS2 Planning overview with LIU
focus
• Organisation
• LS2 Master and restrictions
• LS2 LIU Main Activities
• Critical Paths
• Documentation Status
• Summary
Content
Fernando Pedrosa EN-ACE 2/20
Organisation
Fernando Pedrosa EN-ACE 3/20
Activity Technical
Coordinator
B269 Activities Stephane Reignier
B355 EPC Activities Frederic Daligault
B365 TE-EPC ActivitiesNicolas David
Main Units refurbishment Aniello Russo
New BTP lineMike Hourican
LINAC4 connection Simon Mataguez
New F61 line Sebastien Evrard
Facility Coordinators
Fernando Pedrosa David Hay (Deputy)
Site Coordination
Nicolas Mornand
EROS
Jordi Bossy
Integration
Jean-Pierre Corso
Antoine Kosmicki
Configuration / Layout DB
Thomas Birtwistle
Blanca Vazquez de
Prada
Master schedule and restrictions
Fernando Pedrosa EN-ACE 4/20
Periods with
possible access
restrictions
Periods with access
restrictions
Cooling works
Fernando Pedrosa EN-ACE 5/20
• Modification of the 10 MHz
water cooling circuit(SS36, SS46, SS51, SS56, SS66,
SS76, SS81, SS86, SS91, SS96)
• New
demineralized
water system
• Actual status
• Ongoing works in gallery 1,
PS SWY, B.255 and B.355
• Difficulties:
• Asbestos
• Lead surveys
• Integration issues
Key DatesPS cooling
• Baseline start date:
• Nov. 2018
• Baseline end date:
• Nov. 2019
10MHz cooling
• Baseline start date:
• Jan. 2019
• Baseline end date:
• Mar. 2019
Accelerating and stabilizing elements
Fernando Pedrosa EN-ACE 6/20
• Modification of the 10 MHz water cooling
circuit(SS36, SS46, SS51, SS56, SS66, SS76, SS81,
SS86, SS91, SS96)
• New feedback amplifiers for the 40/80
MHz
• Upgrade of the 10 MHz feedback
amplifiers
(SS36, SS46, SS51, SS56, SS66, SS76, SS81,
SS86, SS91, SS96)
• New 80 MHz fast tuner (SS88 and SS08)
• Upgrade of Finemet RF system (coupled-bunch
feedback) (SS02)
• Actual status
• 10MHz final amplifiers
removed from the machine
and under test in B.359
• Fast tuner removed
• Electronics on the SS02
Damper removed and
cabling ongoing
Key DatesDamper
• Installation:
• Nov. 2019
New amplifiers
• Installation:
• Jan./Feb. 2020
New fast tuners
• Installation:
• Dec. 2019 / Jan.
2020
New injection and bending elements
Fernando Pedrosa EN-ACE 7/20
• Replace injection extra
kicker (KFA45)
• New injection bumpers(40, 41, 43, 44)
New injection septum +
bumper SMH42:
• New SEMGrid (MU42)
• New bumper (SS42)
• New low-beta injection quadrupoles (SS33, SS49)
• Remove kick enhancement
quadrupoles(SS25 and SS73)
• Replace F16.BHZ377
and F16.BHZ378
• Actual status
• Old KFA45 tested
and removed from
the machine
• Old SMH42 and
power transformer
removed
• Difficulties:
• Some logistical
problems
encountered
Key DatesKFA45
• Installation:
• Feb. 2020
BTP
• Installation:
• Up to Aug. 2019
SMH42
• Installation:
• Feb. 2020
BHZ377 + BHZ378
• Installation:
• Mar. + Apr. 2020
New low-beta
• Installation:
• May + Jun. 2019
• New BTP line
New beam intercepting devices
Fernando Pedrosa EN-ACE 8/20
• New ralentisseurs (SS12)
• New internal beam dumps (SS47 and SS48)
• Consolidation of the beam stoppers(F16.STP512, F16.STP176)
Key DatesInternal dumps
• Installation:
• Apr. 2020
Rallentisseur
• Installation:
• Jan. 2020
Stoppers
• Installation:
• Jan. + Feb. 2020
• Actual status
• Old ralentisseur removed
• Internal dumps removed
New beam instrumentation
Fernando Pedrosa EN-ACE 9/20
• New beam wire scanners(SS64, SS65, SS68, SS85)
• New vertical beam gas ionization
profile monitor(SS84)
• Actual status
• De-cabling done
• Cabling ongoing
Key DatesWire Scanners
• Installation:
• Jul. 2019
Vertical BGI
• Installation:
• Apr. 2020
BTP line
Fernando Pedrosa EN-ACE 10/20
After LS2After LS2
Before LS2
• Actual status
• Disconnection - ongoing
• Vacuum equipment - removed
• Beam instrumentation devices - removed
LIU activities in the machine - overview
Fernando Pedrosa EN-ACE 11/20
• Replace injection extra kicker (KFA45)
• New injection bumpers (40, 41, 43, 44)
New injection septum + bumper SMH42:
• New SEMGrid (MU42)
• New bumper (SS42)
• New ralentisseurs(SS12)
• Modification of the 10 MHz water cooling circuit(SS36, SS46, SS51, SS56, SS66, SS76, SS81, SS86, SS91, SS96)
• New feedback amplifiers for the 40/80 MHz
• Upgrade of the 10 MHz feedback amplifiers
(SS36, SS46, SS51, SS56, SS66, SS76, SS81, SS86, SS91, SS96)
• New 80 MHz fast tuner(SS88 and SS08)
• New beam wire scanners(SS64, SS65, SS68, SS85)• New internal beam dumps (SS47 and SS48)
• New vertical beam gas ionization
profile monitor(SS84)
• Consolidation of the beam stoppers(F16.STP512, F16.STP176)
• New low-beta injection quadrupoles(SS33, SS49)
• Upgrade of Finemet RF system
(coupled-bunch feedback)(SS02)
• Remove kick enhancement
quadrupoles(SS25 and SS73)
• LINAC4 connection
• New BTP line
• New demineralized water system
• Replace F16.BHZ377 and F16.BHZ378
B.365 (LIU + Consolidation)
Fernando Pedrosa EN-ACE 12/20
Before LS2
After LS2Ground floor
1st floor
Today• Actual status
• Power converters disconnection ongoing
• KFA45 equipment dismantling ongoing
B.355 (LIU + Consolidation)
Fernando Pedrosa EN-ACE 13/20
Today• Actual status
• Power converters disconnection - done
• Cooling works ongoing
Organisation
Fernando Pedrosa EN-ACE 14/20
PS LIU installations in the surface buildings
351
New power converters
• Injection septum + bumper(PI.SMH42, PI.BSM42)
• Injection low beta quadrupoles
• Injection bumpers
Renovation of the TT2 power converters
• Removal of old equipment
• Reconditioning of the building
• Installation of new cooling/ventilation equipment
• Installation of electrical distribution
• Installation of data gateway/FGC gateway
• WIC machine protection
Note: B.269 is treated in a specific presentation
from V. Montabonnet
New power converters
• Magnets of the vertical beam gas
ionization profile monitor
Transverse feedback
• Modification of the PS and TT2 demineralized
water cooling circuit
• Modify the copper secondary cooling circuit
New LLRF digital beam control
Renovation of the electrical power distribution
Critical path/paths
Fernando Pedrosa EN-ACE 15/20
Critical paths:
• F61 (PS to East
Area) line (EN-EA)
• LV consolidation
project (EN-EL)
• POPS (TE-EPC)
Note:
• Any delay on the
Main Units
consolidation, LV
consolidation or
cabling will shift all
other activities and
we may have
other critical paths
PS Documentation Status (Engineering Change Request status)
Fernando Pedrosa EN-ACE
Reference Title Group Contact Status
New feedback amplifiers for the 40 and 80 MHz cavities BE-RF Carlo Rossi NEEDED
PS-ACC10-EC-
0002
Upgrade of the RF Amplifier and Installation of a New Water
Distribution for the 10MHz Cavities of the PS RingBE-RF Valentin Desquiens IN WORK
Table: LIU-PS Scope ECRs currently In Work or Needed
Chart and table excludes LT, LTB and BTP lines, as they are considered part of the LIU-PSB project scope
16/20Courtesy of: Thomas Birtwistle
There 3 ECRs that are approved, that cannot
yet be released because the differential
drawings are missing
PS Documentation Status (Integration status)
Fernando Pedrosa EN-ACE 17/20Courtesy of: Yvon Muttoni
The completion of all the ECR and Integration study
processes (Life Cycle) depend on the input and quality
of information provided by the design offices in each
Group.
Documentation Status (Work Package Analysis status)
Fernando Pedrosa EN-ACE
13 WPAs (9 of which are for LIU works)
LIU related18/20
Summary
Fernando Pedrosa EN-ACE 19/20
• Most of the equipment that will be replaced by LIU equipment has been already removed from the machine
• Planning for consolidation is tight and any delay may have consequences in the LIU equipment installation
• Some of the new LIU equipment are ready only in 2020
• There is still a considerable amount of ECRs under approval and one is still needed. There 3 ECRs that are approved, that cannot yet be released because the differential drawings are missing
• 37% of the integration studies are still in progress
• None of the LIU installations is in the critical path
Thank you Q’s