PUBLIC CONSULTATION
Venue :Bacolod City
Date and Time :Tentative April 16, 2018@ 2:00PM
Barangays 27, 41 and Villamonte, Bacolod City, Negros Occidental
Public Scoping Presentation THE UPPER EAST Page 1 of 58
1. Company Profile
2. What is ECC?
3. Project Description and Components
4. Project Rationale
5. Environmental Impacts and Mitigation Plan
a.Pre-Construction Phaseb.Construction Phasec.Operationald.Abandonment
OUTLINE OF TOPICS
Public Scoping Presentation THE UPPER EAST Page 2 of 58
Public Scoping Presentation THE UPPER EAST Page 3 of 58
• Captained by real estate mogul and businessmanextraordinaire, Dr. Andrew L. Tan, the company startedthe Live-Work-Play-Learn-Shop philosophy in all of thetownship projects that are being developed underMegaworld.
• The company aspires to guarantee your highestsatisfaction through topnotch quality products andservices conceived in the spirit of improvement andborn out of relentless pursuit of innovation anddevelopment.
• Gives high importance to the continuous advancementof the knowledge and skills of all company personnel,especially its key people, so that they can provide youthe service of the highest quality.
Public Scoping Presentation THE UPPER EAST Page 4 of 58
Public Scoping Presentation THE UPPER EAST Page 5 of 58
MCKINLEY HILL
Public Scoping Presentation THE UPPER EAST Page 6 of 58
EASTWOOD CITY
Public Scoping Presentation THE UPPER EAST Page 7 of 58
MCKINLEY WEST
Public Scoping Presentation THE UPPER EAST Page 8 of 58
UPTOWN BONIFACIO
Public Scoping Presentation THE UPPER EAST Page 9 of 58
Public Scoping Presentation THE UPPER EAST Page 10 of 58
The Environmental Impact Assessment (EIA) System inthe Philippines, officially referred to as the PhilippineEnvironmental Impact Statement System (PEIS System),was established under PD 1586 on 11 June 1978.
Section 4 of PD 1586 provides that no person, partnershipor corporation shall undertake or operate any suchdeclared environmentally critical project (ECP) orenvironmentally critical area (ECA) without first securingan Environmental Compliance Certificate (ECC).
Public Scoping Presentation THE UPPER EAST Page 11 of 58
PRESIDENTIAL DECREE No. 1151 section 4Environmental Impact Statement (EIS)
Before an environmental impact statement is issued by alead agency, all agencies having jurisdiction over, or specialexpertise on, the subject matter involved shall comment onthe draft environmental impact statement made by the leadagency within thirty (30) days from receipt of the same.
Public Scoping Presentation THE UPPER EAST Page 12 of 58
An Environmental Compliance Certificate (ECC) is adocument that may be issued after thorough review of theEIA Report.
It certifies that the proposed project has complied with therequirements of the EIS System and that the proponent hascommitted to implement its approved EnvironmentalManagement Plan (EMP) to address the environmentalimpacts and to operate within the best environmentalpractice.
Public Scoping Presentation THE UPPER EAST Page 13 of 58
Public Scoping Presentation THE UPPER EAST Page 14 of 58
VICINITY MAP
BRGY. 41
BACOLOD CITY GOVERNMENT
CENTER
TO BREDCO PORT
TO TACULING
TO BACOLOD –SILAY AIRPORT
LOPUE’S EAST CENTER
BACOLOD CITY SOUTH TERMINAL
TO MANDALAGAN
TO GRANADA
SM SAVEMORE
EAST
PHILIPPINE STATISTICS AUTHORITY
BRGY. 27
BRGY.VILLAMONTE
PUBLIC CEMETERY
Public Scoping Presentation THE UPPER EAST Page 15 of 58
SITE PHOTOS
Public Scoping Presentation THE UPPER EAST Page 16 of 58
MASTER DEVELOPMENT PLAN
Public Scoping Presentation THE UPPER EAST Page 17 of 58
PROJECT COMPONENTS
Lot Area : 344,055.00 square metersTotal Open Space : 120,301.00 square meters
a) Roads and Alleys : 103,280.00 square meters
b) Amenity / Landscape : 15,167.00 square meters
c) Utility : 1,854.00 square meters
Total Saleable Area : 223,754.00 square meters
Project Duration : 2 years and 6 months development period (tentatively construction to commence on January 2019)
Estimated Project Cost : Php2,109,057,150.00
Public Scoping Presentation THE UPPER EAST Page 18 of 58
TOPOGRAPHIC PLAN
Public Scoping Presentation THE UPPER EAST Page 19 of 58
LIST OF CONSULTANTS
Trade Consultants
Land Development Consultancy Design Services RMDC Corporation
Soil Investigation (Factual Report) Technotest, Inc
Getechnical Assessment Brian B. Tan
Hydrographic Survey AAG Land Surveying
Hydrology and Flood Study AMH Philippines
EGGAR Ecobase Consultancy Services
Public Scoping Presentation THE UPPER EAST Page 20 of 58
Public Scoping Presentation THE UPPER EAST Page 21 of 58
Megaworld is re-shaping the Bacolod City skyline and raisingstandards for commercial, residential and officedevelopment in the Philippines to promote a high-levelstandard in terms of quality, innovativeness andresponsiveness to consumer's needs.
Uplifting Bacolod City's infrastructures and facilities Opening job opportunities To create a unique synergy and be a special place to live,
work and play. To encourage national economic performance that attract foreign
investors and other multinational companies To provide employment and To contribute to the economic growth of the area.
PROJECT RATIONALE
Public Scoping Presentation THE UPPER EAST Page 22 of 58
Public Scoping Presentation THE UPPER EAST Page 23 of 58
PRE-CONSTRUCTION
CONSTRUCTION
ABANDONMENT
OPERATIONAL
PROJECT PHASES / STAGES
Public Scoping Presentation THE UPPER EAST Page 24 of 58
I. THE LANDII. THE WATERIII. THE AIRIV. THE PEOPLE
ENVIRONMENTAL ASPECTS
Public Scoping Presentation THE UPPER EAST Page 25 of 58
Environmental Studies
Preparation of Development Plan
Acquisition of required development permits, e.g. ECC, locational clearance, etc.;
Right of way clearing and fencing
PRE-CONSTRUCTION PHASE
Public Scoping Presentation THE UPPER EAST Page 26 of 58
ENGINEERING GEOLOGICAL AND
GEOHAZARD ASSESSMENT
REPORT(EGGAR)
ENVIRONMENTAL STUDIES
Public Scoping Presentation THE UPPER EAST Page 27 of 58
SOIL INVESTIGATION REPORT
ENVIRONMENTAL STUDIES
Public Scoping Presentation THE UPPER EAST Page 28 of 58
ENVIRONMENTAL STUDIES
PHIVOLCSCERTIFICATION
Public Scoping Presentation THE UPPER EAST Page 29 of 58
ZONING CERTIFICATION
ENVIRONMENTAL STUDIES
Public Scoping Presentation THE UPPER EAST Page 30 of 58
Major activities of this project include landdevelopment/ clearing, installation of basic features suchas drainage system, water supply, power,telecommunication, and the construction of the facilitiesand utilities.
CONSTRUCTION PHASE
Public Scoping Presentation THE UPPER EAST Page 31 of 58
CONSTRUCTION PHASE
The LandIssues and Mitigation
Public Scoping Presentation THE UPPER EAST Page 32 of 58
SOLID WASTEEnvironmental Impacts
Options for Prevention or Mitigation or Enhancement
• Generation of solid construction wastes • Strict implementation of Solid Waste Management Act which include waste segregation, re-use and recycling and waste audit along construction waste streams.
• Contractors shall remove and dispose properly all debris and excess material.
Public Scoping Presentation THE UPPER EAST Page 33 of 58
Environmental ImpactsOptions for Prevention or Mitigation or
Enhancement• Accumulation of domestic solid waste in the
form of used paper, cans, bottles and food refuse• Contractors must provide Material Recovery
Facility to utilize proper sanitation and goodhousekeeping.
• Contractors shall formulate guidelines ongarbage disposal and impose penalty to anyworkers who dispose solid wasteindiscriminately.
• Provision of proper storage for raw materials.• Proper coordination with the City garbage
collection system for prompt removal of garbagefrom site.
• Daily ocular inspection of the garbage bins.
SOLID WASTE
Public Scoping Presentation THE UPPER EAST Page 34 of 58
Environmental ImpactsOptions for Prevention or Mitigation or
Enhancement• Generation of special wastes or household
hazardous wastes • Generation of used oil and grease from the
equipment and vehicles• Oil and grease spills from heavy equipment and
vehicles
• Provide hazardous waste storage room for properhandling and disposal of hazardous wastematerials in accordance with RA 6969
• Hazardous wastes will be collected in containersfor protection from spillage during storage andtransport while an open top metal drum will beused for other types of hazardous wastes.
• Labeled containers/ drums will be brought to aqualified waste facility for proper disposal orrecycling accredited by DENR.
• Collection of oil and grease during maintenanceworks
HAZARDOUS WASTE
Public Scoping Presentation THE UPPER EAST Page 35 of 58
The WaterIssues and Mitigation
CONSTRUCTION PHASE
Public Scoping Presentation THE UPPER EAST Page 36 of 58
Environmental Impacts Options for Prevention or Mitigation or Enhancement
• Increased water demand • Implement water conservation by educating the workers
• Possible contamination (i.e. coliform level) of nearest water body to domestic wastes
• Provide/ build temporary/ portable toilet facilities with septic tank for workers and implement proper waste disposal procedures
• Provide grease trap/ oil and water separator for food wastes
WATER QUANTITY AND QUALITY
Public Scoping Presentation THE UPPER EAST Page 37 of 58
Environmental ImpactsOptions for Prevention or Mitigation or
Enhancement
• Siltation and turbidity of receiving drainage line and water body
• Drainage system will be provided with silt trap sothat construction debris/ waste that will begenerated in the construction site will not clog upthat might cause flooding in the area. Silt trapminimizes siltation.
• Installation of perimeter fence to avoid surfacerun-off along the street.
• To avoid scattering of mud there should be adesignated wash bay area for vehicle.
• Stockpile aggregates properly• Regular cleaning of canals.• Earthwork activities would also be scheduled
during low precipitation periods. Proper workscheduling to hasten excavation works.
• Exposed surfaces will be cemented or landscapedto stabilize the soil.
FLOODING/SILTATION
Public Scoping Presentation THE UPPER EAST Page 38 of 58
The AirIssues and Mitigation
CONSTRUCTION PHASE
Public Scoping Presentation THE UPPER EAST Page 39 of 58
Environmental ImpactsOptions for Prevention or Mitigation or
Enhancement• Generation of dust/ debris• Increased in TSP level
• Regular watering of on-site construction area are expected to limit fugitive dust levels to acceptable levels.
• Constructing perimeter fences around the construction site to serve as windbreakers or barriers.
• Proper work scheduling of cut-and-fill of the ground to hasten this activity and lessen the exposure of the earth materials to wind and rainfall.
• Use of canvass covers for delivery trucks.• Ensure that the transport vehicles moving around
the construction site are regulated to minimum.
DUST GENERATION
Public Scoping Presentation THE UPPER EAST Page 40 of 58
Environmental ImpactsOptions for Prevention or Mitigation or
Enhancement• Increase of TSP, NOx, SOx levels at the
construction site• The equipment that will be brought to and used
in the construction site has to be in good working condition.
• Proper maintenance of genset and other equipment should be implemented to help reduce the level of SOx and NOx emission and reduce fuel consumption.
• Limit the movement of vehicles in the area through the assistance of traffic enforcer.
• Schedule delivery of construction materials during non-peak hours.
• Assign unloading and loading area for deliveries.
AIR QUALITY
Public Scoping Presentation THE UPPER EAST Page 41 of 58
Environmental ImpactsOptions for Prevention or Mitigation or
Enhancement• Possible excessive noise generation • Construct temporary fence to acts as barriers and
to confine noise within the project area.• Equipment should be properly maintained to
minimize noise emissions.• Use of mufflers on equipment mounts to lessen
the noise produce.• Proper scheduling of works to avoid the elevated
cumulative noise impact.
NOISE QUALITY
Public Scoping Presentation THE UPPER EAST Page 42 of 58
The PeopleIssues and Mitigation
CONSTRUCTION PHASE
Public Scoping Presentation THE UPPER EAST Page 43 of 58
Environmental Impacts Options for Prevention or Mitigation or Enhancement
• Safety of workers and passersby • Strict implementation of construction Safety Rules and Regulations.
• Appointment of Safety Engineers and Project Nurse.• Provide first aid center, medical and emergency kits
within the job site.• Provision of Personal Protective Equipment (PPE) to
the workers.• Post warning and safety reminders signs at strategic
areas.• Provide fire extinguishers and safety nets at job site.• Conduct seminars on environmental management
and monitoring.• Provision of construction fence with lighted canopy
and safety net around the project site for the falling debris.
HEALTH AND SAFETY
Public Scoping Presentation THE UPPER EAST Page 44 of 58
HEALTH AND SAFETY
Public Scoping Presentation THE UPPER EAST Page 45 of 58
Environmental ImpactsOptions for Prevention or Mitigation or
Enhancement• Probable disturbance of peace and order • Strict implementation of No gambling and
drinking policy• Assign roving guards at night.• Imposed disciplinary measures• Coordination with barangay and police
PEACE AND ORDER
Public Scoping Presentation THE UPPER EAST Page 46 of 58
Environmental Impacts Options for Prevention or Mitigation or Enhancement
• Increase in traffic volume • Traffic Management Plan will be implemented to have a smooth flow of traffic.
• Delivery of construction materials will be schedule during off-peak hours to minimize impact
• Hauling of cut soil and construction waste by dump trucks would be scheduled to minimize impact on vehicular flow.
• Coordination with local authorities on traffic management.
• Traffic control devices such as barricades, cones, blinkers shall be used to guide or channel traffic.
• The arrangement of traffic control devices used to stop or channel traffic (barricades, cones, blinkers) shall be periodically inspected to ensure that the devices are in good condition.
• Caution, warning and construction information warning signs will be displayed as appropriate to warn or inform vehicle traffic passing along the roadways near the construction site.
TRAFFIC
Public Scoping Presentation THE UPPER EAST Page 47 of 58
Environmental ImpactsOptions for Prevention or Mitigation or
Enhancement• Increase in Job and Business Opportunities• Additional Income and Benefit to the Local
Government
• Qualified skilled worker from the affected community will be given priority to be hired
• Purchased construction materials, which can be supplied by business enterprises in Bacolod City and adjacent cities
• Secure and pay necessary business permits and clearances to the LGU. LGU shall directly benefit from the project due to the additional fees that would be collected from taxes and additional revenues from licenses and permits from various commercial establishments within the project site.
• Attract new investors and expected to create more new businesses to be developed in the area resulting to increase in property value.
SOCIO-ECONOMIC
Public Scoping Presentation THE UPPER EAST Page 48 of 58
The proposed project will be turned over to the Estateadministration after construction. Maintenance offacilities and amenities will be handled/ managed bythem.
OPERATIONAL PHASE
Public Scoping Presentation THE UPPER EAST Page 49 of 58
There will be daily monitoring of the solid waste by the assignedmaintenance personnel to check whether the segregated wastesare brought to their designated containers
SOLID WASTE GENERATION
Public Scoping Presentation THE UPPER EAST Page 50 of 58
WEAR AND TEAR OF LANDSCAPE
Continuing maintenance and development of green areas, and landscaped areas.
Public Scoping Presentation THE UPPER EAST Page 51 of 58
INCREASE DEMAND FOR WATER SUPPLY
• Provision of domestic water tank, fire water reserved and an underground water tank
• The tenants shall be encouraged to conserve water
Public Scoping Presentation THE UPPER EAST Page 52 of 58
GENERATION OF DOMESTIC WASTEWATER
• Provide grease trap/ oil and water separator for food wastes
• Provision for centralized sewage treatment facility to cater the locators of The Upper East
Public Scoping Presentation THE UPPER EAST Page 53 of 58
EMISSION OF CO, SO2, NO2 FROM USE OF GENSET
• Regular monitoring and maintenance of the generator set shall be implemented by the administration personnel
• Secure Permit to Operate for Genset.
Public Scoping Presentation THE UPPER EAST Page 54 of 58
INCREASE OF TRAFFIC AND POSSIBLE PROBLEM
• Tenants would be provided enough parking spaces for their vehicles
• Traffic will be manned by traffic enforcer
Public Scoping Presentation THE UPPER EAST Page 55 of 58
NATURAL HAZARDS, POSSIBLE BOMB THREATS AND OTHER CRIMINAL ACTIVITIES
Public Scoping Presentation THE UPPER EAST Page 56 of 58
ABANDONMENT PHASE
After the completion of the land development,abandonment is not foreseen for this type of projectexcept for the abandonment of the temporary facilitiesused during construction.
The General Contractor will free the site fromconstruction debris and temporary structures such asbunk houses, stockrooms, toilets, etc.
Public Scoping Presentation THE UPPER EAST Page 57 of 58
THANK YOU
Public Scoping Presentation THE UPPER EAST Page 58 of 58