28
Final Punchlist for M&M Formulation Plant,Anklehwer Points observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC) Sr no Observations EC Plant 1 Final Internal Painting to the wall. 2 Rolling shutter final painting rectification and painting the frame of it internally. 3 Solvent bridge sheeting cutout covering. 4 Platform structure foundation bolts to be provided with double nuts. 5 Greasing of foundation bolts of platform structure for final handover. 6 Platform structure staricase anchor fastening pending to its base plates. 7 Windows frame gaps filling with sealent and some windows needs holes to the frames. 8 Cleaning of PEB columns final time. 9 One number of Emergency door handle broken, needs to be repaired. 10 Gaps in frame of emergency door to be filled up with the sealent. 11 Joint filling in stair case marble. Both stair cases. 12 Spout to be addidtional provieded in the sump from floor to the sump of 100mm dia pvc pipe. 13 Hounch to be done at the bottom of the sump and top surface of sump needs to a smooth surface. 14 Floor patch found in 2 areas of floor.Needs to to repaired. 15 Cladding found spots of some paints , needs to get removed. 16 One window of HEC behind electric panel to be fixed gently so that it cannot be operated due to electrica 17 One coulums edge finishfound broken due to shifting of electric panel.Needs to get repaired. 18 Ramp angle nosing to be painted black.A point raised later by client. 19 Purlin above the lintel beam needs to get clean. 20 Lintel of emergency door needs a good finsh outer plaster. 21 Precast slab for the passage of stairecase and road of HEC need plaster finish. 22 Flushing needs to get clean from paint patches. 23 Chajja of 1 number obsered a hair crack. Needs to get rectified . 24 Some concrete needed to done to complete a small 300 mm long pilnth protection gap with staircase at back 25 26 Chequer plate final painting and fixing work. 27 Few chajja needs to get bottom plaster rectified with proper finish. 28 Outer plaster needs to get properly finish in some areas. 29 Outer plaster rectification and painting. Plaster and brick masonry found fully broken due to huge holes for small pipes and cables done by electrical contractor. Needs to get repaired.

Punch List Final-dates

Embed Size (px)

DESCRIPTION

vbcb

Citation preview

HECFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateEC Plant1Final Internal Painting to the wall.7/7/152Rolling shutter final painting rectification and painting the frame of it internally.7/7/153Solvent bridge sheeting cutout covering.7/7/154Platform structure foundation bolts to be provided with double nuts.7/7/155Greasing of foundation bolts of platform structure for final handover.7/7/156Platform structure staricase anchor fastening pending to its base plates.7/7/157Windows frame gaps filling with sealent and some windows needs holes to the frames.7/7/158Cleaning of PEB columns final time.7/7/159One number of Emergency door handle broken, needs to be repaired.7/7/1510Gaps in frame of emergency door to be filled up with the sealent.7/8/1511Joint filling in stair case marble. Both stair cases.7/8/1512Spout to be addidtional provieded in the sump from floor to the sump of 100mm dia pvc pipe.7/8/1513Hounch to be done at the bottom of the sump and top surface of sump needs to a smooth surface.7/8/1514Floor patch found in 2 areas of floor.Needs to to repaired.7/8/1515Cladding found spots of some paints , needs to get removed.7/9/1516One window of HEC behind electric panel to be fixed gently so that it cannot be operated due to electrical concern.7/9/1517One coulums edge finishfound broken due to shifting of electric panel.Needs to get repaired.7/9/1518Ramp angle nosing to be painted black.A point raised later by client.7/9/1519Purlin above the lintel beam needs to get clean.7/9/1520Lintel of emergency door needs a good finsh outer plaster.7/10/1521Precast slab for the passage of stairecase and road of HEC need plaster finish.7/10/1522Flushing needs to get clean from paint patches.7/10/1523Chajja of 1 number obsered a hair crack. Needs to get rectified .7/10/1524Some concrete needed to done to complete a small 300 mm long pilnth protection gap with staircase at backside.7/11/1525Plaster and brick masonry found fully broken due to huge holes for small pipes and cables done by electrical contractor. Needs to get repaired.7/11/1526Chequer plate final painting and fixing work.7/11/1527Few chajja needs to get bottom plaster rectified with proper finish.7/11/1528Outer plaster needs to get properly finish in some areas.7/11/1529Outer plaster rectification and painting.7/11/1530Floor washing.7/11/15

ECFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateHEC Plant1Final Internal Painting to the wall.7/12/152Rolling shutter final painting rectification and painting the frame of it internally.7/12/153Solvent bridge sheeting cutout covering.7/12/154Platform structure foundation bolts to be provided with double nuts.7/12/155Greasing of foundation bolts of platform structure for final handover.7/12/156Platform structure staricase anchor fastening pending to its base plates.7/12/157Windows frame gaps filling with sealent and some windows needs holes to the frames.7/12/158Cleaning of PEB columns final time.7/13/159Gaps in frame of emergency door to be filled up with the sealent.7/13/1510Joint filling in stair case marble. Both stair cases.7/13/1511Spout to be addidtional provieded in the sump from floor to the sump of 100mm dia pvc pipe.7/13/1512Hounch to be done at the bottom of the sump and top surface of sump needs to a smooth surface.7/13/1513Debris cleaning outside near plant at back side.7/13/1514Plaster and brick masonry found fully broken due to huge holes for small pipes and cables done by electrical contractor. Needs to get repaired.7/14/1515Floor patch of 1 number needs to get repaired.7/14/1516Cladding found spots of some paints , needs to get removed.7/14/1517Purlin above the lintel beam needs to get clean.7/14/1518Excess marble needs to get mould or cut.7/14/1519Chequer plate final painting and fixing work.7/14/1520Minor hair crack develop near emergency door.7/14/1521Ramp angle nosing to be painted black.A point raised later by client.7/15/1522Floor washing.7/15/1523Outer plaster rectification and painting.7/15/15

SCFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateSC Plant1Final Internal Painting to the wall.7/13/152Rolling shutter final painting rectification and painting the frame of it internally.7/16/153Platform structure foundation bolts to be provided with double nuts.7/16/154Greasing of foundation bolts of platform structure for final handover.7/16/155Platform structure staricase anchor fastening pending to its base plates.7/16/156Windows frame gaps filling with sealent and some windows needs holes to the frames.7/16/157Cleaning of PEB columns final time.7/16/158Gaps in frame of emergency door to be filled up with the sealent.7/16/159Joint filling in stair case marble. Both stair cases.7/17/1510Spout to be addidtional provieded in the sump from floor to the sump of 100mm dia pvc pipe.7/17/1511Hounch to be done at the bottom of the sump and top surface of sump needs to a smooth surface.7/17/1512Plaster and brick masonry found fully broken due to huge holes for small pipes and cables done by electrical contractor. Needs to get repaired.7/17/1513Floor patch of 1 number needs to get repaired.7/17/1514Cladding found spots of some paints , needs to get removed.7/18/1515Purlin above the lintel beam needs to get clean.7/18/1516Window cill needs to get edge finish as an edge has broken.7/18/1517Chequer plate final painting and fixing work.7/18/1518Ramp angle nosing to be painted black.A point raised later by client.7/18/1519Elbow fixing at the railinf of staircase.7/18/1520Outer plaster rectification and painting.7/18/1521Floor washing.7/18/15

StoresFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateSTORES1Final Internal Painting to the wall.7/14/152Rolling shutter final painting rectification and painting the frame of it internally.7/19/153Solvent bridge sheeting cutout covering.7/19/154Platform structure foundation bolts to be provided with double nuts.7/19/155Greasing of foundation bolts of platform structure for final handover.7/19/156Platform structure staricase anchor fastening pending to its base plates.7/19/157Windows frame gaps filling with sealent and some windows needs holes to the frames.7/19/158Cleaning of PEB columns final time nd at some place painting needs to be done if cleaning in not proper.7/19/159Groove filling near OTTA rolling shutter needed to get filled with bitumen.Around 5m filling.7/19/1510Gaps in frame of emergency door to be filled up with the sealent.7/20/1511Joint filling in stair case marble. Both stair cases.7/20/1512Plaster and brick masonry found fully broken due to huge holes for small pipes and cables done by electrical contractor. Needs to get repaired.7/20/1513Floor patch of 1 number needs to get repaired.7/20/1514Cladding found spots of some paints , needs to get removed.7/20/1515Purlin above the lintel beam needs to get clean.7/20/1516OTTA plaster needs to gets properly finished at side near road WP.7/20/1517Front staircase sponch finshing required.7/20/1518Sponch finsh at two winow cill along raod R8.7/20/1519OTTA angle nosing needs application of black paint.7/20/1520Outer paint final.7/20/1521Pipe cleaning PVC of OTTA and cleaning of rain water pipe near rolling shutter.7/20/1522Floor washing.7/20/15

Admin,QC and ExtensionFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateADMIN,QC and EXTENSION1Damage floor tile replacement.Completed2Skirting groove filling.Completed3Ventilation of toilet block needs a tile framing.7/10/154SS Sink bottom gap filling in pantry.7/10/155Wash basin bottom pipe cleaning and finishing gaps with white cement in Ladies toilet.7/10/156Urinal Sprader needs to adjust the excess spreading problem- 1nos.7/10/157Some groove filling in dado tiles to be rectified and finished.7/10/158Jet-spray stand to get fixed in gents and ladied toilet.7/10/159Bolwer cleaning of windows frame.7/10/1510Sealent filling in some window frame gaps.7/10/1511Damaged granite needs to get replaced and its joint filling needs to get done.7/12/1512OTTA plaster edge plaster finish requierd.7/12/1513Outer plaster at some points needs to get rectified and get sponch plaster.7/12/1514Window cill excees at backside of Admin needs to get cut of mould.7/12/1515Dip moulding required in the plaster of admin building.7/14/1516Rain water pipe needs get placed near toilet block.7/15/1517Louvers cleaning and repair of one frame near pantry.7/15/15181 nos of ventilation pending in electrical room .7/15/1519Extension toliet cleaning.7/15/1520Four holes by elec contrator needs to get filled and finished.7/15/1521Septic tank outer porttion cleaning.7/15/1522Manhole cover of soak pit needs a frame to it.7/15/1523Paint cleaning from doors of elec room and QC lab and OTTA at back side of QC lab.7/15/1524Extra sink in QC lab needs to closed by client requirement and sahould be closed by granite cover and the sink cock shall handover to the cleint.7/15/1525Floor tiles tape removal in some area.7/15/1526Sump hounch finishing anf top portion finish.7/15/15

HT YardFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateHT YARD1Wicket gate not closing properly. Needs to get rectified.7/9/152Cahinlink fencing to be rectified and needful should be done for tighten.7/10/1538mm rod placed on behalf of 6mm GI road needs to get painted.7/10/15

Security cabin and Main GateFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateSECURITY CABIN & MAIN GATE1Gate column, beam needs a proper plaster finish.7/7/152Pully in the main gate to be changed.7/7/153Wicket gate painting in main gate.7/7/154Circular column painting with weather coat.7/7/155Chajja and wall flushing need to be rectified and needs to get finished properly.7/8/156Window sill in cabin needs a filling of minor cracks in plaster.7/9/157Granite sills which is excess should get moulded.7/9/158Cleaning of paint patches in building.7/9/159Window frame gaps sealent filling.7/10/15

Tank FarmFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateTANK FARM1Main gate closing problem.7/11/152Base plate of gate foundation needs to get painted.7/11/153Painting of all chainlink fencing angles and rod at top.7/11/15420mm metal filling in small patch near road and main gate of solvent area.7/12/155Refilling of holes which was done by Alfa for solvent pipe conceal. Needs to get repaired.7/13/156Sump plaster inside of it is pending.7/15/157Final painting outer.7/15/158A spout needed to floor of tank farm for rainwater removal.7/15/159A samll patch of chainlink fencing needs to get complete.7/12/15

Road and DrainFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateROAD & DRAIN1Few patches found near canteen road needs to get repaired.5/15/152Few edges to get repaired in R1 & R2 road.5/15/153Drain near HEC and Stores OTTA need to get completion of plaster.5/15/154Precast slabs at the road curvatures needs get fine finished.5/15/155Edges of drain plaster near WP Plant and near SC plants needs to get repaired.5/15/156Two 300 mm dia pipe at drain outlet near HEC.5/15/157Aggregates near WP Plant road where portacabin was placed needs to get removed.5/15/158Cleaning of drains.5/15/159Cleaning of roads.5/15/1510Few edges to get repaired in R8 and R9 road.5/15/15

Canteen buildingFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateCANTEEN1Damage floor tile replacement, one wall tile, 2 sink wall tile.7/9/152SS Sink bottom gap filling in Sink area and wash basin area.7/9/153Wash basin bottom pipe cleaning and finishing gaps with white cement in Ladies toilet.7/9/154Urinal Sprader needs to adjust the excess spreading problem- 1nos.7/9/155Bolwer cleaning of windows frame.7/10/156Sealent filling in some window frame gaps.7/13/157Staircase marble joint filling.7/10/158Staircase marble crack observed near wash area entrance.Needs to get replaced.7/10/159Septic tank outer porttion cleaning.7/13/1510Manhole cover of soak pit needs a frame to it.7/15/1511Floor tiles tape removal in some area.7/15/1512One marble fitting needs to get placed in on tread and rise near wash area.7/10/1513Cleaning of windows.7/15/1514Cleaning of ventilations in canteen and toilet area.7/15/1515Water tank foundations needs to get painted. 2-numbers7/15/1516Water tank structure painting left.7/15/1517Water tank of sintex manhole cover fixing pending.7/15/1518Outside plaster rectification. Needs to get sponch finish.7/15/1519Outside painting rectification.7/15/15

PCC DG RoomFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DatePCC DG ROOM1Rollin shutter painting rectification.7/12/152Internal painting of the rolling shutter frame.7/12/153Louvers to get clean from paint marks.7/12/154Moulding of staircase marble pending.7/12/155Joint filling of the marble left.7/12/156Gap between riser and rolling shutter observed, need get solved.7/12/157Chamber for electric cable needs to get paint.7/12/158Manhole cover to get painted.7/12/159Outside plaster rectificaion.7/15/1510Outside painting rectification.7/15/1511Trafo fencing rectification.7/15/1512Painting of the angles of the chainlink fencing.7/15/15138mm rod fixed at top needs to get painted.7/15/15

Water tank and Pump houseFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateWATER TANK & PUMP HOUSE1Water tank top plaster finish to be repaired, was broken due to erction of the steel column for solvent pipe.7/11/152Manhole cover needs to get framed and fixed. 3 nos7/11/153Flange opening inside the tank-1.7/11/154Pump house staircase needs to get painted.7/11/155Internal painting of pump house to be done-suggested by client.7/15/156Cleaning of plaster mortar from floor of pump house.7/13/157Removal of scaffolding from pump house.7/15/158Cover plastic to get removed from ventilation of the pump house.7/11/159Front portion sheet clading rectification 7/12/15

WP PlantFinal Punchlist for M&M Formulation Plant,AnklehwerPoints observation done by: Mustak Patel(PMC) and Krishan Pandya(MEPC)7/3/15Sr noObservationsOutlook DateComplition DateWP Plant1Final Internal Painting to the wall.7/15/152Rolling shutter final painting rectification and painting the frame of it internally.7/12/153Platform structure foundation bolts to be provided with double nuts.7/11/154Greasing of foundation bolts of platform structure for final handover.7/11/155Platform structure staricase anchor fastening pending to its base plates.7/13/156Windows frame gaps filling with sealent and some windows needs holes to the frames & Cleaning 7/13/157Cleaning of PEB columns final time.7/13/158Gaps in frame of emergency door to be filled up with the sealent.7/13/159Joint filling in stair case marble. Both stair cases.7/13/1510Spout to be addidtional provieded in the sump from floor to the sump of 100mm dia pvc pipe.7/13/1511Hounch to be done at the bottom of the sump and top surface of sump needs to a smooth surface.7/13/1512Plaster and brick masonry found fully broken due to huge holes for small pipes and cables done by electrical contractor. Needs to get repaired.7/13/1513Floor patch of 1 number needs to get repaired.7/13/1514Cladding found spots of some paints , needs to get removed.7/13/1515Purlin above the lintel beam needs to get clean.7/14/1516Window cill needs to get edge finish as an edge has broken.7/14/1517Chequer plate final painting and fixing work.7/14/1518Ramp angle nosing to be painted black.A point raised later by client.7/15/1519Elbow fixing at the railing of staircase.7/15/1520Outer plaster rectification and painting.7/15/1521Floor washing.7/15/1522Lift pit portion Cleanning & inside painting 7/15/15