qbModCon Tiwi Islands Construction Crew Tiwi Islands 2009 qbModCon Modular House

qbModCon Leah Nguiu Tiwi Islands 2009

Embed Size (px)

Citation preview

Page 1: qbModCon Leah Nguiu Tiwi Islands 2009

qbModConTiwi Islands Construction Crew

Tiwi Islands 2009 qbModCon Modular House

Page 2: qbModCon Leah Nguiu Tiwi Islands 2009

Tiwi IslandsDay One Site Preparation for footings

Page 3: qbModCon Leah Nguiu Tiwi Islands 2009

Floor Frame Complete

Modular Floor Frame Set Out The Concrete Footings

Day two Floor Frame Completed with Concrete Footings

Page 4: qbModCon Leah Nguiu Tiwi Islands 2009

Installing The Flooring and Structural Extrusions

Day 3 Install Viva Board Flooring and qbModCon Structural Extrusions

Page 5: qbModCon Leah Nguiu Tiwi Islands 2009

The Exterior Walls and WindowsDay 4 Set-out External Walls with qbModCon Structural Extrusions

Page 6: qbModCon Leah Nguiu Tiwi Islands 2009

The Local Fella’s Working Hard

Page 7: qbModCon Leah Nguiu Tiwi Islands 2009

Installing the Ring Beam & TrussesDay 5 Complete External Walls and Tighten Down Ring Beam for Truss Installation

Page 8: qbModCon Leah Nguiu Tiwi Islands 2009

Installing the Trusses , Ridge and Hip beams

Day 6 Continue Truss Installation -with Ridge and Hip Beam Extrusions

Installing Internal Walls prior to roof panels

Hip Beam Installation

Page 9: qbModCon Leah Nguiu Tiwi Islands 2009

Up Go the Roof Panels

Day Seven-With the Truss Sections and qbModCon Ridge Beams in Place Install the Roof Panels

Page 10: qbModCon Leah Nguiu Tiwi Islands 2009

Internal Walls

Day 8 Finishing of Internal Walls

Page 11: qbModCon Leah Nguiu Tiwi Islands 2009

•Trim-Deck Roof Sheets •Available in Various colours•Powder coated Aluminium rails •Composite Decking•Heat Insulated Walls•R-Value 3.78•Cool in Summer•Warm in Winter•Eco Friendly•Cyclone Proof•Virtually Maintenance free

Day Nine Install the Roof Sheets and all Flashings.Continue with the finishing touches on the exterior

Page 12: qbModCon Leah Nguiu Tiwi Islands 2009

The Internal Fit Out

The Internal Fit Out•Acrylic rendered walls•Tiled Floors•Melamine Kitchen•Combination Upright stove•Double Stainless Sink•Cathedral Ceilings•Large Open plan•Kitchen Lounge and Dinning

Page 13: qbModCon Leah Nguiu Tiwi Islands 2009

110 sqm 3 Bedroom Modular House

Page 14: qbModCon Leah Nguiu Tiwi Islands 2009

Sustainable Housing By qbModCon

Exposed Trusses Cool and Spacious

Page 15: qbModCon Leah Nguiu Tiwi Islands 2009

The Finished Product

Tiled Bathroom Full Kitchen

Page 16: qbModCon Leah Nguiu Tiwi Islands 2009

The Local Construction Crew

Tiwi IslandsLocal Construction Crew

•Guiseppe Tipiloura

•Russell Yunupingu

•Stephen O Keeffe

•Ben Bokkerink

•Zachary Bloor

•Rodney Coleman

•Malcolm Blair

qbModCon3 Bedroom 110 sqm House with 18 sqm deckNguiu 2009

Page 17: qbModCon Leah Nguiu Tiwi Islands 2009

Tiwi Islands 2009

We would like to personally thank Leah Kerinauia all of the Friendly local Indigenous workers from Nguiu and Melville Island the locals at Tiwi Barge ,Brian Clancy from Tiwi Island Land Council, Bernard & Lynette(TLO) ,The Tiwi Collage ,The Licensed Contractors from MiBT and all the people who made this project successful

RegardsDavid Holmes