I. LEARNING CURVE A particular manufacturing job is subject to an estimated 80% experience curve. The first unit required 20 labor hours to complete. Required: a. What is the cumulative average time per unit after four units are completed? b. What is the total time required to produce 2 units? c. How many hours are required to produce the second unit? II. PROBABILITY ANALYSIS Sports Club sells cold sodas at FEU’s home basketball games. In the year 2014, the frequency of distribution of the demand for cups of sodas per day is presented below: Sales volume in cups Frequency 2000 48 days 5000 80 days 6000 144 days 8000 32 days 10000 16 days 360 days Determine the 2015’s estimated daily demand for sodas at FEU’s home game using: a. Deterministic Approach (based on most likely event) b. Expected value approach I. LEARNING CURVE A particular manufacturing job is subject to an estimated 80% experience curve. The first unit required 20 labor hours to complete. Required: a. What is the cumulative average time per unit after four units are completed? b. What is the total time required to produce 2 units? c. How many hours are required to produce the second unit? II. PROBABILITY ANALYSIS Sports Club sells cold sodas at FEU’s home basketball games. In the year 2014, the frequency of distribution of the demand for cups of sodas per day is presented below: Sales volume in Frequency

Quantitative Techniques - LC,PA,PERT,GT

Embed Size (px)

DESCRIPTION

Learning Curve, Probability, PERT

Citation preview

Page 1: Quantitative Techniques - LC,PA,PERT,GT

I. LEARNING CURVEA particular manufacturing job is subject to an estimated 80% experience curve. The first unit required 20 labor hours to complete.Required:a. What is the cumulative average time per unit after four units are completed?b. What is the total time required to produce 2 units?c. How many hours are required to produce the second unit?

II. PROBABILITY ANALYSISSports Club sells cold sodas at FEU’s home basketball games. In the year 2014, the frequency of distribution of the demand for cups of sodas per day is presented below:

Sales volume in cups Frequency2000 48 days5000 80 days6000 144 days8000 32 days

10000 16 days360 days

Determine the 2015’s estimated daily demand for sodas at FEU’s home game using:a. Deterministic Approach (based on most likely event)b. Expected value approach

I. LEARNING CURVEA particular manufacturing job is subject to an estimated 80% experience curve. The first unit required 20 labor hours to complete.Required:a. What is the cumulative average time per unit after four units are completed?b. What is the total time required to produce 2 units?c. How many hours are required to produce the second unit?

II. PROBABILITY ANALYSISSports Club sells cold sodas at FEU’s home basketball games. In the year 2014, the frequency of distribution of the demand for cups of sodas per day is presented below:

Sales volume in cups Frequency2000 48 days5000 80 days6000 144 days8000 32 days

10000 16 days360 days

Determine the 2015’s estimated daily demand for sodas at FEU’s home game using:a. Deterministic Approach (based on most likely event)b. Expected value approach

Page 2: Quantitative Techniques - LC,PA,PERT,GT

III. GANTT CHART

SEP OCT NOV DEC

a. Which task is the longest in completion time?b. All task are being performed in what month?

IV. PERTThe construction firm schedule of activities and related expectation completion time are as follows:

Activities Description Estimated Time (in weeks)A-B Obtain on site work permits 2B-E Repair damages by vandals 8B-C Inspect const. materials 1C-E Order & receive materials 2C-D Apply for waiver 3D-E Obtain waiver 1E-F Perform electric work 5F-G Complete interior partitions 4

Required:a. Prepare the PERT Network for the projectb. Identify the critical path and its expected timec. Identify the shortest path and its slack time in weeks

III. GANTT CHART

SEP OCT NOV DEC

a. Which task is the longest in completion time?b. All task are being performed in what month?

IV. PERTThe construction firm schedule of activities and related expectation completion time are as follows:

Activities Description Estimated Time (in weeks)A-B Obtain on site work permits 2B-E Repair damages by vandals 8B-C Inspect const. materials 1C-E Order & receive materials 2C-D Apply for waiver 3D-E Obtain waiver 1E-F Perform electric work 5F-G Complete interior partitions 4

Required:a. Prepare the PERT Network for the projectb. Identify the critical path and its expected time

A

B

C

D

TASK

A

B

C

D

TASK

Page 3: Quantitative Techniques - LC,PA,PERT,GT

c. Identify the shortest path and its slack time in weeks