    KEGIATAN : LANJUTAN PEMBANGUNAN SEKOLAH TERPADU

    PROYEK : LANJUTAN PEMBANGUNAN SMPN 1 DAN SMAN 1 SAMARINDA

    LOKASI : SAMARINDA

    TAHUN : 2011

    NO SUB JUMLAH JUMLAH

    1 PEKERJAAN PENDAHULUAN UMUM Sub Jumlah 810,189,843.60Rp

    810,189,8Rp

    2. LANJUTAN LABORATORIUM SMA 9,100,244,945.19Rp

    9,100,244,9Rp

    3 LANJUTAN RUANG KELAS EDUKASI B SMP 8,515,530,165.42Rp

    8,515,530,1Rp

    4 PEKERJAAN ELEKTRIKAN & MEKANIKAL KAWASAN 1,140,178,269.32Rp1,140,178,2Rp

    5 PEKERJAAN AIR BERSIH KAWASAN 300,855,055.24Rp

    300,855,0Rp

    6 LAPANGAN BASKET SMAN 1 212,522,442.60Rp

    212,522,4Rp

    7 LAPANGAN UPACARA EDUKASI SMA 505,425,808.11Rp

    505,425,8Rp

    8 SALURAN DRAINASE KAWASAN 420,846,412.70Rp

    420,846,4Rp

    9 GROUND TANK 514,793,905.39Rp

    514,793,9Rp

    10 ROOF TANK 359,912,451.53Rp

    359,912,4Rp

    11 PEKERJAAN SOUND SYSTEM MASJID 86,906,460.00Rp

    86,906,4Rp

    12 GEDUNG EDUKASI SMAN 1 19,683,209.63Rp

    19,683,2Rp

    13 GEDUNG PERPUSTAKAAN SMA 41,507,431.87Rp41,507,4Rp

    14 GEDUNG KEGIATAN SMP 230,896,605.00Rp

    230,896,6Rp

    15 GEDUNG ADMINISTRASI SMP 39,317,280.00Rp

    39,317,2Rp

    16 GEDUNG EDUKASI C SMP 150,546,762.00Rp

    150,546,7Rp

    17 R. GENSET 1,346,368,055.40Rp

    1,346,368,0Rp

    REKAPITULASI HARGA

    ITEM PEKERJAAN

  • 7/29/2019 Rab Sma & Smp

    2/411

    A JUMLAH = 23,795,7Rp

    B PPN. 10 % X A = 2,379,5Rp

    C JUMLAH (A+B) = 26,175,2Rp

    DIBULATKAN = 26,175,2Rp

    Samarinda,...........................

    Dibuat oleh

    PT/CV.......................

    ( Nama)

    Jabatan

    Terbilang :

  • 7/29/2019 Rab Sma & Smp

    3/411

    Pagu Dana SMP 1 dan SMA 1

    14,475,399,400.00

    9,719,800,000.00

    24,195,199,400.00

  • 7/29/2019 Rab Sma & Smp

    4/411

    KEGIATA : LANJUTAN PEMBANGUNAN SEKOLAH TERPADU

    PROYEK : LANJUTAN PEMBANGUNAN SMPN 1 DAN SMAN 1 SAMARINDA

    LOKASI : SAMARINDA

    TAHUN : 2011

    1 3

    I PEKERJAAN PENDAHULUAN UMUM

    1 Pek. Pembuatan Direksi Keet, M2 8

    2 Pek. Pembuatan Gudang dan Barak Pekerja M2 10

    3 Pagar Pengaman M' 30

    4 Penyediaan air kerja BLN 25 Penyediaan listrik kerja BLN 2

    6 Pek. Pembuatan Papan Nama Proyek Ls

    7 Quality Control Ls

    8 Administrasi Teknis Ls

    9 Pembersihan lokasi dan pengukuran Ls### Mobilisasi Alat Ls

    II LANJUTAN LABORATORIUM SMA

    2.1 PEKERJAAN STRUKTUR

    1 Pelat Lantai tebal 10 cm

    Beton cor readymix dengan mutu K 225 M3

    Besi Polos Kg 1,78

    Begisting M2 6

    2 Pelat Tangga Tebal 15 cm

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 1,20Bekisting Plat/Dak M2 3

    3 Plat Selasar tebal 8 cmBeton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 16Bekisting Plat/Dak M2 3

    4 Plat kanopi tebal 8 cm

    Beton cor readymix dengan mutu K 225 M3 1

    Pembesian Polos Kg 49Bekisting Plat/Dak M2 13

    5 Beton Anak Tangga

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 45

    6 Meja Wastafel

    Beton cor readymix dengan mutu K 225 M3Pembesian Polos kg 10

    Bekisting Plat/Dak M2 1

    7 Balok 8/12

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Polos kg 5

    Bekisting balok M2

    8 Kolom 10/10

    Beton cor readymix dengan mutu K 225 M3 2

    Pembesian Polos kg 8,81

    Bekisting Kolom M2 46

    2.2 PEKERJAAN LANTAI

    1 Pasang Keramik Lantai 40/40 M2 2,422 Pasang Keramik Lantai 40/40 unpolished M2 67

    3 Pasang Keramik Lantai 20/20 M2 44 Pasang Keramik Dinding 20/25 M2 42

    RAB ( RENCANA ANGGARAN BIAYA)

    2

    NO. URAIAN PEKERJAAN SAT. VOLU

  • 7/29/2019 Rab Sma & Smp

    5/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    5 Fasade 1

    Nat 2 Cm M' 2

    Nat 12.5 Cm M' 176 Fasade 2

    List Ukuran 7+7.5+7 cm M' 9List Ukuran 8+8+8 cm, (Laboratorium SMA) M' 5

    List Ukuran 3+3+3 cm (rooster) M' 12

    Pasang Batu Alam Tempel M2 17 Fasade 3

    List Ukuran 7+7.5+7 cm M' 9List Ukuran 8+8+8 cm, (Laboratorium SMA) M' 4

    List Ukuran 3+3+3 cm M' 9

    Pasang Batu Alam Tempel M2 38 Fasade 4

    List Ukuran 7+7.5+7 cm M' 16

    Nat 12.5 Cm M' 309 Railing Tangga Laboratorium SMA M' 4

    10 Pasang Plang Nama " LABORATORIUM SMA NEGERI 1" Bh

    12 Benangan Kolom Expose dan Balok sunshading M' 12,63

    13 Pekerjaan Alkaplas M2 10,39

    2.4 PEKERJAAN PLAFOND

    1 Pekerjaan Plafond Gyptile M2 2,422 Pekerjaan Plafond Kalsiboard M2 83

    2.5 PEKERJAAN ATAP

    1 Pasang Gording Canal 150.65.20.3,2 Kg 7,932 Pasang Ikatan Angin 16 M' 343 Pasang Trekstang 12 M' 234 Pasang WF 200.150.6.9 Kg5 Pasang WF 200.100.5,5.8 Kg 7,996 Pasang Atap Zincalume 0.35 mm M2 1,187 Pasang Listplank Zincalume 0.35 mm M2 61

    Pasang Canal 125.50.20.2,3 Kg 1,13Besi siku 10x10 kg 288 Baut span screw Bh 119 Baut dan mur Bh 7,52

    10 Angkur 16 mm L = 600 mm Bh 5411 Plat T = 6 mm kg 612 Plat T = 8 mm kg 3913 Plat T = 12 mm kg 16

    14 14 Grouting m2

    2.6 PEKERJAAN KUSEN, PINTU & JENDELA

    1 J1 22

    Kusen aluminium M' 4,69

    Pasang Kaca 5 mm M2 26

    Silicon sealant M' 6,79Kait Angin Jendela Bh 1,77

    Grendel jendela Bh 88Handel jendela Bh 88

    Engsel Jendela 3" Bh 1,77

    Benangan M1 2,79

    2 P1 1

    Kusen Kayu Bengkirai M' 14

    Daun Pintu Panil Plywood Megateak M2 5Pasang Kaca 5 mm M2 1

    Engsel Pintu 4" Bh 10

    Kunci Pintu Bh 3

    Handle Pintu Bh 3

    Melamic Kusen M' 14Melamic Daun Pintu M2 10

    Benangan M' 22

    3 P2

    Kusen Kayu Bengkirai M' 1Daun Pintu Panil Plywood Megateak M2

    Pasang Kaca 5 mm M2

    Engsel Pintu 4" Bh 1

  • 7/29/2019 Rab Sma & Smp

    6/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    2.7 PEKERJAAN SANITAIR & DRAINASE

    1 Pasang Klosed jongkok lengkap Assesories Bh 2

    2 Pasang Kran Air Biasa Bh 2

    3 Pasang Wastafel lengkap assesories Bh

    4 Floor drain Bh 25 Instalasi air bersih Ttk 3

    6 Instalasi air kotor dia. 4" Ttk 2

    7 Instalasi air kotor dia. 3" Ttk 3

    8 Instalasi air kotor dia. 1 1/2" Ttk 39 Pasang Urinoir lengkap lengkap assesories Bh 1

    10 Bak mandi lapis keramik Bh 2

    11 Roof drain lengkap pipa saluran air hujan Bh 2

    12 Clean Out Bh 1

    13 Septic Tank

    Pekerjaan Tanah

    Galian Tanah M3 4

    Urugan Tanah Kembali M3Urugan Pasir M3

    Lantai kerja M3Sloof (13x20)

    Beton cor readymix dengan mutu K 225 M3Pembesian Polos Kg 6

    Bekisting Sloof/Tie Beam M2

    Plat Lantai Dasar Tebal 10 cm

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 8Kolom Praktis (13x13)

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 8

    Bekisting Kolom M2

    DindingBeton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 40

    Bekisting Dinding M2 7

    Balok Praktis (13x20)Beton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 6

    Bekisting Balok M2

    Plat Lantai Tebal 12 cmBeton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 19

    Bekisting Plat/Dak M2 1

    Penutup septicktank

    Beton cor readymix dengan mutu K 225 M3Pembesian Polos Kg

    Bekisting Plat/Dak M2

    Plesteran 1 : 2 M2 4

    Pipa Ventilasi Septictank unit

    14 Pekerjaan ResapanGalian Tanah M3 2

    Urugan Tanah M3

    Urugan Pasir M3Lapisan Ijuk M3

    Urugan batu gunung M3

    Urugan Koral M3

    Pasang Pipa Resapan M' 3

    15 Parit Keliling Bangunan U 40

    BETON PRECASE

    Galian M3 6Urugan tanah Kembali M3 2

    Beton M3 3

    Besi polos Kg 3,53

    Begesting M2 43Plesteran M2 19

    Pekerjaan Alkaplas M2 19

  • 7/29/2019 Rab Sma & Smp

    7/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    Kunci Pintu Lemari Bh 3

    Melamic Daun Pintu Bh 1

  • 7/29/2019 Rab Sma & Smp

    8/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    Pasang Keramik 10/10 M2 2

    2 Meja Kerja R. Fisika 1 (Samping)

    Pelat Beton Meja Kerja Tebal 10 cm M3

    Besi Polos Kg 28Begisting M2 3

    Plesteran 1:4 M2 3

    Pekerjaan Alkaplas M2 3

    Daun Pintu Lemari Panil Plywood Megateak M2 2

    Engsel Pintu lemari Bh 10Kunci Pintu Lemari Bh 5

    Melamic Daun Pintu M2 2

    Pasang Keramik 10/10 M2 3

    3 Meja Kerja R. Fisika 2 (Tengah)

    Pelat Beton Meja Kerja Tebal 10 cm M3

    Besi Polos Kg 20

    Begisting M2 2Plesteran 1:4 M2 2

    Pekerjaan Alkaplas M2 2Daun Pintu Lemari Panil Plywood Megateak M2 1

    Engsel Pintu lemari Bh 6

    Kunci Pintu Lemari Bh 3Melamic Daun Pintu M2 1

    Pasang Keramik 10/10 M2 2

    4 Meja Kerja R. Fisika 2 (Samping)

    Pelat Beton Meja Kerja Tebal 10 cm M3Besi Polos Kg 27

    Begisting M2 3

    Plesteran 1:4 M2 3

    Pekerjaan Alkaplas M2 3Daun Pintu Lemari Panil Plywood Megateak M2 2

    Engsel Pintu lemari Bh 10

    Kunci Pintu Lemari Bh 5

    Melamic Daun Pintu M2 2Pasang Keramik 10/10 M2 3

    5 Meja Kerja R. Kimia 1 (Tengah)

    Pelat Beton Meja Kerja Tebal 10 cm M3

    Besi Polos Kg 20Begisting M2 2

    Plesteran 1:4 M2 2

    Pekerjaan Alkaplas M2 2

    Daun Pintu Lemari Panil Plywood Megateak M2 1Engsel Pintu lemari Bh 6

    Kunci Pintu Lemari Bh 3

    Melamic Daun Pintu M2 1

    Pasang Keramik 10/10 M2 2

    6 Meja Kerja R. Kimia 1 (Samping)Pelat Beton Meja Kerja Tebal 10 cm M3

    Besi Polos Kg 28

    Begisting M2 3

    Plesteran 1:4 M2 3Pekerjaan Alkaplas M2 3

    Daun Pintu Lemari Panil Plywood Megateak M2 2

    Engsel Pintu lemari Bh 10

    Kunci Pintu Lemari Bh 5Melamic Daun Pintu M2 2

    Pasang Keramik 10/10 M2 3

    7 Meja Kerja R. Kimia 2 (Tengah)Pelat Beton Meja Kerja Tebal 10 cm M3

    Besi Polos Kg 20

    Begisting M2 2

    Plesteran 1:4 M2 2

    Pekerjaan Alkaplas M2 2Daun Pintu Lemari Panil Plywood Megateak M2 1

  • 7/29/2019 Rab Sma & Smp

    9/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    Engsel Pintu lemari Bh 6

    Kunci Pintu Lemari Bh 3

  • 7/29/2019 Rab Sma & Smp

    10/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    Melamic Daun Pintu M2 1

    Pasang Keramik 10/10 M2 2

    10 Meja Kerja R. Biologi 1 (Samping)

    Pelat Beton Meja Kerja Tebal 10 cm M3Besi Polos Kg 40

    Begisting M2 4

    Plesteran 1:4 M2 4

    Pekerjaan Alkaplas M2 4

    Daun Pintu Lemari Panil Plywood Megateak M2 2Engsel Pintu lemari Bh 10

    Kunci Pintu Lemari Bh 5

    Melamic Daun Pintu M2 2

    Pasang Keramik 10/10 M2 4

    11 Meja Kerja R. Biologi 2 (Tengah)

    Pelat Beton Meja Kerja Tebal 10 cm M3

    Besi Polos Kg 20Begisting M2 2

    Plesteran 1:4 M2 2Pekerjaan Alkaplas M2 2

    Daun Pintu Lemari Panil Plywood Megateak M2 1

    Engsel Pintu lemari Bh 6Kunci Pintu Lemari Bh 3

    Melamic Daun Pintu M2 1

    Pasang Keramik 10/10 M2 2

    12 Meja Kerja R. Biologi 2 (Samping)Pelat Beton Meja Kerja Tebal 10 cm M3

    Besi Polos Kg 27

    Begisting M2 3

    Plesteran 1:4 M2 3Pekerjaan Alkaplas M2 3

    Daun Pintu Lemari Panil Plywood Megateak M2 2

    Engsel Pintu lemari Bh 10

    Kunci Pintu Lemari Bh 5Melamic Daun Pintu M2 2Pasang Keramik 10/10 M2 3

    III LANJUTAN RUANG KELAS EDUKASI B SMP

    LANJUTAN EDUKASI B

    3.1 PEKERJAAN STRUKTUR

    1 Balok 15/30

    - Beton Ready Mix K-225 M3 1

    - Besi Polos Kg 17

    - Begisting M2 1

    2 Balok 20/30

    - Beton Ready Mix K-225 M3 7

    - Besi Polos Kg 14,32

    - Begisting M2 793 Balok 20/40

    - Beton Ready Mix K-225 M3 1- Besi Polos Kg 2,32

    - Begisting M2 10

    4 Balok 30/60

    - Beton Ready Mix K-225 M3 6- Besi Polos Kg 13,97

    - Begisting M2 42

    5 Balok 13/13

    - Beton Ready Mix K-225 M3 1

    - Besi Polos Kg 3,81

    - Begisting M2 226 Pelat Lantai Tebal 12 cm

    - Beton Ready Mix K-225 M3 25

    - Besi Polos Kg 26,54- Begisting M2 2,28

    7 Pelat Lantai Tebal 15 cm

    Beton Ready Mix K 225 M3 1

  • 7/29/2019 Rab Sma & Smp

    11/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    - Beton Ready Mix K-225 M3

    - Besi Polos Kg 50

    - Begisting M2 4

    3.2 PEKERJAAN LANTAI

    1 Pasang Keramik Lantai 40/40 Polish M2 1,462 Pasang Keramik lantai 30/30 Unpolish M2 76

    3 Pasang Keramik Lantai 20/20 Unpolish M2 4

    4 Pasang Keramik Dinding 20/25 Polish M2 54

  • 7/29/2019 Rab Sma & Smp

    12/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    5 Pasang Keramik Tangga 30/30 Unpolish M2 12

    6 Waterproofing M2 47

    7 Screeding ( Plesteran + Aci) M2 57

    3.3 PEKERJAAN DINDING

    1 Pasangan bata 1 : 4 M2 3,16

    2 Plesteran 1 : 4 M2 5,67

    3 Alkaplast dinding M2 7,51

    4 Pengecatan dinding interior, ex Cendana M2 4,095 Pengecatan dinding exterior, ex Mowilex Weathercoat M2 3,92

    6 Railing Tangga Edukasi SMP M' 10

    7 Pasang Plang Nama " GEDUNG EDUKASI B " Bh

    8 Plesteran Beton ExposePlesteran 1:2 M2 1,79

    11 Stopper Plafond

    Plesteran 1:2 M2 65

    12 Plesteran Lubang Rooster

    Plesteran 1:4 M2 313 List 10 Cm/Ban-Banan M' 33

    3.4 PEKERJAAN PLAFOND

    1 Pasang Plafond Calsyboard 4.5 mm, Rangka tee-cross tee 60 x 120 + rod M2 82

    2 Pasang Plafond gyptile 9 mm, pre- painted Rangka tee-cross tee 60 x 120 + rod M2 1,46

    3.5 PEKERJAAN ATAP

    1 Pasang Atap Zincalume 0.35 mm M2 76

    2 Baut Ropping bh 3,83

    3 Sealant Baut Ropping ttk 3,83

    4 Pasang WF 200.100.5,5.8 kg 4,575 Kolom Besar kg 89

    6 Kolom Kecil kg 22

    7 Voute kg 1,05

    8 Pasang Gording Canal 100.50.20.3,2 Kg 3,189 T.Beam CNP 2 x 100 x 50 x 20 x 3.2 mm kg 69

    10 Pasang Ikatan Angin 16 M' 38

    11 Pasang Trekstang 12 M' 21

    12 Anchor 5/8 " x L 640 mm Bh 1713 Baut HTB M16 L= 2 " Bh 70

    14 Baut Trekstang 3/8 " Bh 33

    15 Baut Gordeng 3/8 " Bh 59

    16 Baut T.Beam 3/8 " Bh 1717 Base Plate 12 mm Kg 12

    18 Joint Plat 10 mm Kg 23

    19 Stifner 6 mm Kg 6

    20 Siku 70 x 70 x 7 mm dudukan Gordeng Kg 10

    3.6 PEKERJAAN KUSEN, PINTU & JENDELA

    1 J1 99

    Kusen Alumunium (natural anodized) M' 71

    Pasang Kaca 5 mm M2 12Kait Angin Jendela Bh 19

    Grendel jendela Bh 9

    Handel jendela Bh 9

    Engsel Jendela 3" Bh 19Sealent M' 2,23

    Benangan Kusen M' 52

    2 BV1 45

    Kusen Alumunium (natural anodized) M' 10Pasang Kaca 5 mm M2 1

    Sealent M' 43

    Benangan Kusen M' 11

    5 P1 21

    Kusen Kayu Bengkirai M' 18Rangka Bengkirai Daun Jendela Kaca M' 7

    Daun Pintu Panil Plywood Megateak t= 3mm M2 7Pasang Kaca 5 mm M2

  • 7/29/2019 Rab Sma & Smp

    13/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    6 P2 38

    Kusen Kayu Bengkirai M' 19

    Daun Pintu Panil Plywood Megateak t= 3mm M2 6

    Engsel Pintu 4" Bh 11

    Kunci Pintu Bh 3Handle Pintu Bh 3

    Melamic Kusen M' 19

    Melamic Daun Pintu M2 12

    Benangan Kusen M' 38

    7 P3 4

    Kusen Kayu Bengkirai M' 1

    Daun Pintu Panil Plywood Megateak t= 3mm M2Engsel Pintu 4" Bh

    Kunci Pintu Bh

    Handle Pintu Bh

    Melamic Kusen M' 1

    Melamic Daun Pintu M2Benangan Kusen M' 2

    8 Sunshading

    Pasang Sunshading M' 3,78

    3.7 PEKERJAAN SANITAIR

    1 Pasang Klosed jongkok lengkap Assesories Bh 32 Pasang Kran Air Biasa Bh 3

    3 Pasang Urinoir lengkap lengkap assesories Bh 14 Wastafel lengkap Assesories Bh 1

    5 Kaca cermin rangka all. 600 x 900 mm Bh 1

    6 Floor drain Bh 3

    7 Instalasi air bersih Bh 38 Instalasi air kotor dia. 4" Bh 3

    9 Instalasi air kotor dia. 3" Bh 4

    10 Instalasi air kotor dia. 1 1/2" Bh 1

    11 Instalasi air kotor dia. 2" Bh 112 Bak mandi lapis keramik Bh 3

    13 Roof drain lengkap pipa saluran air hujan Ttk 1

    14 Clean out Ttk

    15 Septic Tank

    Galian Tanah M3 2Urugan Tanah Kembali M3

    Urugan Pasir M3

    Lantai kerja M3

    Kolom 13/13- Beton Ready Mix K-225 M3

    - Besi beton Kg 9

    - Begisting M2

    Sloof 13/20- Beton Ready Mix K-225 M3

    - Besi beton Kg 8

    - Begisting M2Balok 13/20

    - Beton Ready Mix K-225 M3- Besi beton Kg 10

    - Begisting M2 1

    Pelat Lantai Tebal 10 cm

    - Beton Ready Mix K-225 M3

    - Besi beton Kg 9Pelat Dinding Tebal 12 cm

    - Beton Ready Mix K-225 M3

    - Besi beton Kg 21

    - Begisting M2 2Pelat Atas Tebal 12 cm

    - Beton Ready Mix K-225 M3

    - Besi beton Kg 11

    - Begisting M2Pelat Penutup Tebal 5 cm

    - Beton Ready Mix K-225 M3

    - Besi beton Kg 1

  • 7/29/2019 Rab Sma & Smp

    14/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    3.8 PEKERJAAN ELEKTRIKAL

    1 Panel Sub Distribusi Ttk

    2 Instalasi Lampu Recessed Mounted Flourrescent Light, 2xTL 36W Ttk 10

    3 Instalasi Lampu Recessed Mounted Flourrescent Light, 2xTL 18W Ttk 6

    4 Instalasi Lampu Recessed Mounted Flourrescent Light, Acrylic Cover 2xTL 18W Ttk5 Instalasi Lampu Recessed Mounted Down Light, PLE-T 20W Ttk 3

    6 Instalasi Grid Switch Ttk 2

    7 Instalasi Saklar Tunggal Ttk

    8 Instalasi Saklar ganda Ttk 29 Instalasi Stop Kontak Ttk 2

    10 Penangkal petir lengkap Ttk

    11 Kabel Penyalur Petir M' 10

    12 Bak Kontrol Test Point Ttk

    IV PEKERJAAN ELEKTRIKAN & MEKANIKAL KAWASAN

    4.1 Pekerjaan Elektrikal Kawasan

    1 Pasang Kabel Daya NYFGbY 4 X 70 mm M' 872 Pasang Kabel Daya NYFGbY 4 X 25 mm M' 253 Pasang Kabel Daya NYFGbY 4 X 10 mm M' 2,86

    V PEKERJAAN AIR BERSIH KAWASAN

    5.1 Instalasi Pipa PDAM Ke Tandon Bawah

    1 Pipa Galvanis 50 mm m' 122 Fitting ls

    3 Material Bantu ls

    4 Floating valve 50 mm bh

    5 Gate valve 50 mm bh

    6 Meteran air bh

    5.2 Instalasi Tranfer Air Bersih dari Pompa Ke roof tank Atas:

    1 Pipa Galvanis 50 mm m' 22

    2 Pipa Galvanis 40 mm m' 233 Pipa Galvanis 25 mm m' 9

    4 Fitting ls

    5 Material bantu ls6 Gate valve 50 mm bh

    7 Gate valve 40 mm bh 28 Gate valve 25 mm bh

    9 Flexible Joint 50 mm bh

    10 Flexible Joint 40 mm bh

    11 Strainer 50 mm bh12 Foot valve 50 mm bh

    13 Pompa kap. 275 lt/mnt - head 40 m' unit

    14 Water level control set

    15 Presure gauge bh16 Presure switch bh

    5.3 Instalasi Air Bersih dari roof tank ke Pemakaian :

    1 Pipa PVC 40 mm m' 132 Pipa PVC 32 mm m' 4

    3 Fitting PVC bh 14 Material Bantu ls

    5 Gate valve 32 mm bh 1

    6 Gate valve 25 mm bh 1

    5.4 Biaya Penyambungan PDAM

    1 Biaya Penyambungan PDAM Unit

    VI LAPANGAN BASKET SMAN 1

    6.1 PEKERJAAN PENDAHULUUAN

    1 Pengukuran & Pasang Bouwplank M' 10

    6.2 PEKERJAAN TANAH

    1 Urugan pasir M3 52 Galian tanah M3 5

    6.3 PEKERJAAN STRUKTUR

    1 Rabat Beton Tebal 10 cm M3 52 Fl h d M2 54

  • 7/29/2019 Rab Sma & Smp

    15/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    7.2 PEKERJAAN TAMAN

    1 Pasang kanstin m' 11

    2 Grill besi diatas saluran m' 2

    3 Tanah Top Soil m3 84 Penanaman rumput embun m2 41

    5 Penanaman pohon :

    a. Dadap merah bh 1

    b. Anggrek tanah bh 1,16c. Soka bh 2

    7.3 SALURAN PEMBUANGAN

    1 Bobokan Jalur Gorong-gorong m' 22 Pasang gorong-gorong dia.60 cm dan bak kontrol M' 2

    3 Pasir urug m3 1

    4 Rekondisi bongkaran m' 2

    VIII SALURAN DRAINASE KAWASAN

    SALURAN 2000X1000 MM DEPAN GEDUNG EDUKASI SMAN1

    8.1 PEKERJAAN PENDAHULUAN :1 Pengukuran & Pasang Bouwplank M' 12

    8.2 PEKERJAAN TANAH

    1 Galian Tanah M3 33

    2 Urugan Pasir M3 3

    3 Lantai Kerja M3 3

    4 Urugan Tanah M3 5

    8.3 PEKERJAAN STRUKTUR

    1 BETON SALURAN

    Beton cor readymix dengan mutu K - 225 M3 8Pembesian Polos KG 4,23

    Bekisting Dinding M2 57

    2 BALOK PRAKTIS 130x130

    Beton cor readymix dengan mutu K - 225 M2Pembesian Polos KG 31

    Bekisting balok M2 3

    IX GROUND TANK

    9.1 PEKERJAAN PENDAHULUAN

    1 Pengukuran & Pasang Bouwplank M' 5

    9.2 PEKERJAAN TANAH

    1 Galian Tanah M3 22 Urugan Tanah Kembali M3

    4 Pemadatan Tanah M3

    5 Urugan pasir M3 1

    9.3 PEKERJAAN PONDASI

    1 Pancang ulin 10/10 - 400cm Ttk 9

    9.4 PEKERJAAN STRUKTUR

    1 Pelat Groundtank tebal 30 cm, (Groundtank) M3 4

    1 Pembesian Polos Kg 5,25

    9.5 PEKERJAAN TANDON FIBER ( 5 m x 6 m x 2 m )

    1 Pasang rangkaian tandon fiber kapasitas 60 m3 Unit

    2 Tangga Monyet Unit

    3 Rumah pompa Unit

    9.6 PEKERJAAN SANITAIR

    1 Parit Keliling U 30 Pasangan bata M' 6

    9.7 PEKERJAAN ELEKTRIKAL

    1 Panel Penerangan dan pompa Unit

    2 Instalasi Lampu Surface Mounted Square Glass Light "Baret Persegi" PL 20W Ttk3 Instalasi Saklar tunggal Ttk4 Instalasi Stop Kontak Ttk

  • 7/29/2019 Rab Sma & Smp

    16/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    10.6 PEKERJAAN ELEKTRIKAL

    1 Panel Penerangan dan pompa Unit

    2 Instalasi Lampu Surface Mounted Square Glass Light "Baret Persegi" PL 20W Ttk

    3 Instalasi Saklar tunggal Ttk

    4 Instalasi Stop Kontak Ttk5 Pasang Pompa BOSTER Unit

    XI GEDUNG MASJID SMA

    PEKERJAAN SOUND SYSTEM MASJID SMA

    11.1 PERALATAN UTAMA

    1 Mixer Amplifier 120 Watt Unit2 Microphone bh

    3 Microphone Wireless bh

    4 Nicad Battery bh

    5 Material Bantu lot11.2 INSTALASI SOUND SYSTEM

    1 Columb/Wall Speaker 15 W bh

    2 Horn Speaker 15 W bh

    3 Instalasi Columb Speaker ttk

    4 Instalasi Horn Speaker ttk5 Test Commisioning Ls

    XII GEDUNG EDUKASI SMAN 1

    12 PEKERJAAN KUSEN, PINTU & JENDELA

    12.1 P2A (4 UNIT)

    Frame allumunium m' 2Pintu allumunium unit

    Engsel Pintu 4" Bh 1

    Kunci Pintu Bh

    Handle Pintu Bh

    Kaca es m2Sealent m' 11

    Benangan Kusen M' 3

    XIII GEDUNG PERPUSTAKAAN SMA

    13 PEKERJAAN SANITAIR DAN DRAINASE

    1 Pipa Saluran air hujan (air tampias) BH 12 Clean Out (Co) BH

    XIV GEDUNG KEGIATAN SMP

    14 PEKERJAAN KUSEN PINTU DAN JENDELA

    1 SunshadingPasang Sunshading M' 1,52

    XV GEDUNG ADMINISTRASI SMP

    15 PEKERJAAN KUSEN PINTU DAN JENDELA

    1 Sunshading

    Pasang Sunshading M' 25

    XVI GEDUNG EDUKASI C SMP

    16 PEKERJAAN KUSEN PINTU DAN JENDELA

    1 Sunshading

    Pasang Sunshading M' 99

    XVII R. GENSET

    17.1 PEKERJAAN PENDAHULUAN

    1 Pengukuran & Pasang Bouwplank M' 5

    17.2 PEKERJAAN TANAH

    1 Galian Tanah M3 3

  • 7/29/2019 Rab Sma & Smp

    17/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Ulir Kg 8

  • 7/29/2019 Rab Sma & Smp

    18/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    Bekisting Footplate/Pile Cap M2 1

    5 Sloof 15/30

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Ulir Kg 15

    Pembesian Polos Kg 6Bekisting Sloof/Tie Beam M2 1

    5 Sloof 20/30

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Ulir Kg 27

    Pembesian Polos Kg 9Bekisting Sloof/Tie Beam M2 1

    9 Balok 15/30

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Ulir Kg 27Pembesian Polos Kg 11

    Bekisting Balok M2 3

    10 Balok 20/30

    Beton cor readymix dengan mutu K 225 M3Pembesian Ulir Kg 27

    Pembesian Polos Kg 9Bekisting Balok M2 3

    11 Balok 8/12

    Beton cor readymix dengan mutu K 225 M3Pembesian Polos Kg 6

    Bekisting Balok M2

    12 Pelat Lantai tebal 10 cm

    Beton cor readymix dengan mutu K 225 M3Pembesian Polos Kg 1,21

    Bekisting Plat/Dak M2 8

    13 Duct CabelBeton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 9

    Bekisting Dinding M2 6

    14 Pelat Lantai dasar tebal 12 cmBeton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 86

    15 Kolom 30/30Beton cor readymix dengan mutu K 225 M3

    Pembesian Ulir Kg 57

    Pembesian Polos Kg 21

    Bekisting Kolom M2 4

  • 7/29/2019 Rab Sma & Smp

    19/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    16 Kolom 10X10

    Beton cor readymix dengan mutu K 225 M3

    Pembesian Polos Kg 13

    Bekisting Kolom M2 1

    17.5 PEKERJAAN LANTAI

    1 Waterproofing M2 8

    2 Sterofom/delatasi lantai M' 1

    17.6 PEKERJAAN DINDING

    1 Pasangan bata 1 : 4 M2 11

    2 Plesteran 1 : 4 M2 303 Pengecatan dinding interior, ex Cendana M2 20

    4 Pengecatan dinding exterior, ex Mowilex Weathercoat M2 15

    5 Pekerjaan Akaplas M2 36

    17.7 PEKERJAAN KUSEN, PINTU DAN JENDELA

    1 P1 Bh

    2 BV.1 Bh

    17.8 PEKERJAAN SANITAIR

    1 Roof drain lengkap pipa saluran air hujan Bh

    2 Parit Keliling Bangunan U 30 (Precast)Galian tanah M3 1

    Urugan Tanah Kembali M3

    Beton M3

    Besi Polos Kg 79

    Begisting M2 9

    Pemasangan ls3 Pemasangan Grill Besi m' 7

    17.9 Pengadaan Daya 150.000VA PL

    9.1 PEKERJAAN TRAFO DAN JARINGAN 20 KV

    1 Pemasangan Jaringan dan Konstruksi 2 Gawang

    - Jaringan Gawang

    - Serandang Trafo 2 Tiang Unit

    - Tiang Jaringan & accessories Unit2 Pengadaan dan Pemasangan PT & CT

    - Penadaan PT & CT PL

    - Serandang PT & CT Unit

    - KWH Meter PLN PL

    - Fuse Cut Out Unit

    - Lighting arester Buah

    3 Pengadaan dan Pemasangan Trafo 3 Phasa 150 kVA. Unit

    - Trafo Jenis Hemetic oil Immersed Type Out Door- Garansi 1 Tahun dari PT. Alstom / Unindo Indonesia

    - Certificat , Tes Uji trafo.4 Upah Pemasangan Ls

    9.2 PEKERJAAN PANEL MDP

    1 Panel MDP Set

    9.4 KABEL FEDEER

    - Kabel NYFGBY 4 x 150 mm2 dari Trafo ke MDP Meter 3

    - Material bantu & acceories Ls

    9.5 PEKERJAAN ELEKTRIKAL

    1 Panel Penerangan Ruang Genset Unit

  • 7/29/2019 Rab Sma & Smp

    20/411

    NO. URAIAN PEKERJAAN SAT. VOLU

    2 Instalasi Lampu TL 2x36 W TK0 Ttk

    3 Instalasi Saklar Ganda Ttk

    4 Instalasi Stop Kontak Ttk

  • 7/29/2019 Rab Sma & Smp

    21/411

    PEKERJAAN PENDAHULUAN1 M2 1.00 Membuat serobong kerja

    1.00 0.0450 0.0450 M3 Kayu meranti 6/12

    1.00 0.0450 0.0450 M3 Kayu meranti 5/7

    1.00 0.4098 0.4098 Lbr Plywood 3mm

    1.00 0.4837 0.4837 Lbr Plywood 9mm

    1.00 1.2000 1.2000 Lbr Atap Asbes Gelombang ( 1.8

    1.00 0.3000 0.3000 Bh Nok Atap Asbes

    1.00 0.0333 0.0333 M3 Papan Meranti

    1.00 0.4000 0.4000 Kg Paku biasa 1" - 3,5"

    1.00 0.2000 0.2000 Zak Semen PC

    1.00 0.0600 0.0600 M3 Pasir Pasang

    1.00 0.0600 0.0600 Bh Kran Air Biasa

    1.00 0.0600 0.0600 Bh Kunci Pintu

    1.00 3.0000 3.0000 Bh Engsel pintu 4"

    1.00 0.0600 0.0600 Bh Gerendel Pintu

    1.00 0.0417 0.0417 Ls Instalasi listrik

    1.00 1.0000 1.0000 M2 Upah kerja

    1 M' Pengukuran & pasang bouwplank

    1.00 0.0120 0.0120 M3 Kayu meranti 5/7

    1.00 0.0044 0.0044 M3 Papan Meranti

    1.00 0.0200 0.0200 Kg Paku biasa 1" - 3,5"

    1.00 0.0750 0.0750 Oh Tukang Kayu

    1.00 0.0750 0.0750 Oh Pekerja

    1.00 0.0075 0.0075 Oh Kepala Tukang

    1.00 0.0038 0.0038 Oh Mandor

    1.00 0.0075 0.0075 Oh Surveyor/Juru ukur

    1 M' Pagar Pengaman

    1.00 0.0105 0.0105 M3 Kayu Meranti

    1.00 0.0085 0.0085 M3 Kayu Ulin1.00 1.1500 1.1500 Lbr Seng Gelombang BJLs 20

    1.00 0.0200 0.0200 Kg Paku Payung

    1.00 0.0300 0.0300 Kg Paku biasa 1" - 3,5"

    1.00 0.4000 0.4000 Oh Pekerja

    1.00 0.2000 0.2000 Oh Tukang Kayu

    1.00 0.0200 0.0200 Oh Kepala Tukang

    1.00 0.0020 0.0020 Oh Mandor

    DAFTA

    URAIAN PEKERJAAN

  • 7/29/2019 Rab Sma & Smp

    22/411

    PEKERJAAN TANAH1 M3 Galian Tanah

    1.00 0.5000 0.5000 Oh Tukang Gali/Urug

    1.00 0.0500 0.0500 Oh Mandor

    1 M3 Urugan Tanah Kembali

    1.00 0.2920 0.2920 Oh Tukang Gali/Urug

    1.00 0.0292 0.0292 Oh Mandor

    1 M3 Urugan Tanah

    1.00 1.2000 1.2000 M3 Tanah Urug Pilihan

    1.00 0.3000 0.3000 Oh Tukang Gali/Urug

    1.00 0.0100 0.0100 Oh Mandor

    1 M3 Urugan Pasir

    1.00 1.2000 1.2000 M3 Pasir urug

    1.00 0.3000 0.3000 Oh Tukang Gali/Urug

    1.00 0.0100 0.0100 Oh Mandor

    1 M3 Urugan Koral

    1.00 1.0500 1.0500 M3 Koral

    1.00 0.3000 0.3000 Oh Tukang Gali/Urug

    1.00 0.0100 0.0100 Oh Mandor

    1 M3 Urugan batu gunung

    1.00 1.0500 1.0500 M3 batu gunung

    1.00 0.3000 0.3000 Oh Tukang Gali/Urug

    1.00 0.0100 0.0100 Oh Mandor

    1 m3 Buangan tanah

    1.00 0.2750 0.2750 oh Pekerja

    1.00 0.0107 0.0107 oh Mandor 1 M3 Pemadatan Tanah

    1.00 0.5000 0.5000 Oh Pekerja

    1.00 0.0500 0.0500 Oh Mandor

    1 M3 Urugan Tanah Top soil

    1.00 1.2000 1.2000 M3 Tanah Top Soil

    1.00 0.3000 0.3000 Oh Tukang Gali/Urug

    1.00 0.0100 0.0100 Oh Mandor

    PEKERJAAN KAYU KASAR1 M3 Pekerjaan Kayu Kasar

    1.00 1.1000 1.1000 M3 Kayu Ulin

    1.00 3.0000 3.0000 Kg Paku Ulin

    1.00 5.0000 5.0000 Oh Pekerja

    1.00 15.0000 15.0000 Oh Tukang Kayu

    1.00 1.5000 1.5000 Oh Kepala Tukang

    1.00 0.2500 0.2500 Oh Mandor

    PEKERJAAN KAYU HALUS1 M3 Kayu Kusen, Rangka Bangunan dan Kuda-Kuda ya

    1.00 1.2000 1.2000 M3 Kayu Ulin

    1.00 0.2000 0.2000 Kg Paku Ulin

  • 7/29/2019 Rab Sma & Smp

    23/411

    1.00 20.0000 20.0000 Oh Pekerja

    1.00 30.0000 30.0000 Oh Tukang Kayu

    1.00 3.0000 3.0000 Oh Kepala Tukang

    1.00 0.5000 0.5000 Oh Mandor

    1 M3 Kayu Kusen, Rangka Bangunan dan Kuda-Kuda ya

    1.00 1.2000 1.2000 M3 Kayu Bengkirai

    1.00 0.2000 0.2000 Kg Paku biasa 1" - 3,5"

    1.00 20.0000 20.0000 Oh Pekerja

    1.00 30.0000 30.0000 Oh Tukang Kayu

    1.00 3.0000 3.0000 Oh Kepala Tukang

    1.00 0.5000 0.5000 Oh Mandor

    PAPAN1 M2 0.0250 /M3 Papan kayu untuk tritisan, lantai dll. diketam halus t

    1.00 1.3000 0.0325 M3 Papan Ulin

    1.00 2.0000 0.0500 Kg Paku Ulin

    1.00 10.0000 0.2500 Oh Pekerja

    1.00 30.0000 0.7500 Oh Tukang Kayu

    1.00 3.0000 0.0750 Oh Kepala Tukang

    1.00 0.5000 0.0125 Oh Mandor

    1 M2 0.0250 /M3 Papan kayu untuk tritisan, lantai dll. diketam halus t

    1.00 1.3000 0.0325 M3 Papan Bengkirai

    1.00 0.2000 0.0050 Kg Paku biasa 1" - 3,5"

    1.00 10.0000 0.2500 Oh Pekerja

    1.00 30.0000 0.7500 Oh Tukang Kayu

    1.00 3.0000 0.0750 Oh Kepala Tukang

    1.00 0.5000 0.0125 Oh Mandor

    PEKERJAAN PONDASI DAN PERKERASAN1 M3 Pasangan Batu Gunung

    1.00 1.1000 1.1000 M3 Batu gunung

    1.00 163.0000 163.0000 Kg Semen Portland

    1.00 0.5200 0.5200 M3 Pasir Pasang

    1.00 1.5000 1.5000 Oh Pekerja

    1.00 0.6000 0.6000 Oh Tukang Batu

    1.00 0.0600 0.0600 Oh Kepala Tukang

    1.00 0.0750 0.0750 Oh Mandor

    1 M' Pancang Mini Pile 32.32.32

    1.00 1.0000 1.0000 M' Mini Pile 32.32.32

    1.00 1.0000 1.0000 Ls Peralatan Pancang

    1.00 0.6500 0.6500 Oh Pekerja

    1.00 1.3000 1.3000 Oh Tukang Kayu

    1.00 0.1625 0.1625 Oh Kepala Tukang1.00 0.3250 0.3250 Oh Mandor

    1 Ttk Pemancangan Kayu Ulin 10/10 - 400cm

    1.00 0.0400 0.0400 M3 Kayu Ulin 10/10 - 4 m

    1.00 1.0000 1.0000 Ls Peralatan Pancang

    1.00 0.0650 0.0650 Oh Pekerja

    1.00 0.1625 0.1625 Oh Tukang Kayu

    1.00 0.0163 0.0163 Oh Kepala Tukang

    1.00 0.0325 0.0325 Oh Mandor

  • 7/29/2019 Rab Sma & Smp

    24/411

    1 Ttk Pemancangan Kayu Ulin 10/10 - 200cm

    1.00 0.0200 0.0200 M3 Kayu Ulin 10/10 - 4 m

    1.00 1.0000 1.0000 Ls Peralatan Pancang

    1.00 0.0650 0.0650 Oh Pekerja

    1.00 0.1625 0.1625 Oh Tukang Kayu

    1.00 0.0163 0.0163 Oh Kepala Tukang

    1.00 0.0325 0.0325 Oh Mandor

    1 Ttk Pemancangan Kayu Ulin 10/10 - 150cm

    1.00 0.0150 0.0150 M3 Kayu Ulin 10/10 - 4 m

    1.00 1.0000 1.0000 Ls Peralatan Pancang

    1.00 0.0650 0.0650 Oh Pekerja

    1.00 0.1625 0.1625 Oh Tukang Kayu

    1.00 0.0163 0.0163 Oh Kepala Tukang

    1.00 0.0325 0.0325 Oh Mandor

    1 Ttk Pemancangan Kayu Ulin 10/10 - 100cm

    1.00 0.0100 0.0100 M3 Kayu Ulin 10/10 - 4 m

    1.00 1.0000 1.0000 Ls Peralatan Pancang

    1.00 0.0650 0.0650 Oh Pekerja

    1.00 0.1625 0.1625 Oh Tukang Kayu

    1.00 0.0163 0.0163 Oh Kepala Tukang

    1.00 0.0325 0.0325 Oh Mandor

    1 Ttk Pancang Ulin 10/10 - 400cm

    Pekerjaan

    1.00 1.0000 1.0000 Ttk Pemancangan Kayu Ulin 10/1

    1 Ttk Pancang ulin 10/10 - 200 cm

    Pekerjaan

    1.00 2.2500 2.2500 Ttk Pemancangan Kayu Ulin 10/1

    1 Ttk Pancang Ulin 10/10 - 150 cmPekerjaan

    1.00 1.0000 1.0000 Ttk Pemancangan Kayu Ulin 10/1

    1 Ttk Pancang Ulin 10/10 - 100cm

    Pekerjaan

    1.00 1.0000 1.0000 Ttk Pemancangan Kayu Ulin 10/1

    1 Ttk 0.0025 /Ttk Sunduk Ulin 5/10 - 50cm

    Pekerjaan

    1.00 1.0000 0.0025 M3 Pekerjaan Kayu Kasar

    1 Ttk 0.0015 /Ttk Sunduk Ulin 5/10 - 30cm

    Pekerjaan1.00 1.0000 0.0015 M3 Pekerjaan Kayu Kasar

    1 M' 0.0120 /M' Sepatu Ulin 3/20 x 2 Bh

    Pekerjaan

    1.00 1.0000 0.0120 M3 Pekerjaan Kayu Kasar

    1 M' 0.0100 /M' Sepatu Ulin 5/10 x 2 Bh

    Pekerjaan

  • 7/29/2019 Rab Sma & Smp

    25/411

    1.00 1.0000 0.0100 M3 Pekerjaan Kayu Kasar

    1 M' Subdrain Pipa PVC AW 1 1/2"

    1.00 0.0360 0.0360 Oh Pekerja

    1.00 0.0600 0.0600 Oh Tukang

    1.00 0.0060 0.0060 Oh Kepala Tukang

    1.00 0.0018 0.0018 Oh Mandor

    1.00 1.2000 1.2000 M' Pipa PVC 1 1/2" class AW

    1.00 1.0000 1.0000 Ls Perlengkapan

    1 M3 Sub Base

    1.00 1.2400 1.2400 m3 Batu Belah (15/20 cm)

    1.00 0.9300 0.9300 m3 Batu Gunung

    1.00 0.3100 0.3100 M3 Agregat Klas B

    1.00 2.0000 2.0000 oh Pekerja tak trampil

    1.00 0.1250 0.1250 oh Mandor

    1.00 1.0000 1.0000 Ls. Alat Bantu

    1 M3 Lapis Agregat Pondasi Klas B

    1.000.2835

    0.2835 jam Pekerja tak trampil

    1.00 0.0405 0.0405 jam Mandor

    1.00 1.2000 1.2000 m3 Agregat Klas B

    1.00 0.0405 0.0405 jam Wheel Loader

    1.00 0.1570 0.1570 jam Dump Truck

    1.00 0.0080 0.0080 jam Motor Grader

    1.00 0.0080 0.0080 jam Vibrator Roller

    1.00 0.0115 0.0115 jam Pneumatic Tyre Roller

    1.00 0.0211 0.0211 jam Water Tanker

    1.00 1.0000 1.0000 ls Alat bantu

    PEKERJAAN BETONKOMPONEN BESI1 Kg Pembesian Polos

    1.00 1.0000 1.0000 Kg Besi Beton Polos

    1.00 0.0150 0.0150 Kg Kawat Beton/ Bendrat

    1.00 0.0070 0.0070 Oh Pekerja

    1.00 0.0070 0.0070 Oh Tukang besi

    1.00 0.0025 0.0025 Oh Kepala Tukang

    1.00 0.0003 0.0003 Oh Mandor

    1 Kg Pembesian Ulir

    1.00 1.0000 1.0000 Kg Besi Beton Ulir

    1.00 0.0150 0.0150 Kg Kawat Beton/ Bendrat

    1.00 0.0070 0.0070 Oh Pekerja

    1.00 0.0070 0.0070 Oh Tukang besi1.00 0.0025 0.0025 Oh Kepala Tukang

    1.00 0.0003 0.0003 Oh Mandor

    KOMPONEN BETON1 M3 Beton cor manual dengan mutu K-175

    1.00 250.0000 250.0000 Kg Semen Portland

    1.00 0.6250 0.6250 M3 Pasir beton

    1.00 0.8700 0.8700 M3 Koral beton

    1.00 3.0000 3.0000 Oh Pekerja

  • 7/29/2019 Rab Sma & Smp

    26/411

    1.00 1.0000 1.0000 Oh Tukang batu

    1.00 0.1000 0.1000 Oh Kepala Tukang

    1.00 0.3000 0.3000 Oh Mandor

    1 M3 Beton cor manual dengan mutu K 225

    1.00 390.0000 390.0000 Kg Semen Portland

    1.00 0.6500 0.6500 M3 Pasir beton

    1.00 0.6500 0.6500 M3 Koral beton

    1.00 3.0000 3.0000 Oh Pekerja

    1.00 1.0000 1.0000 Oh Tukang batu

    1.00 0.1000 0.1000 Oh Kepala Tukang

    1.00 0.3000 0.3000 Oh Mandor

    1 M3 Beton cor readymix dengan mutu K 175

    1.00 1.0250 1.0250 M3 Beton readymix K-175

    1.00 0.5400 0.5400 Oh Pekerja

    1.00 0.3000 0.3000 Oh Tukang batu

    1.00 0.0900 0.0900 Oh Kepala Tukang

    1.00 0.0270 0.0270 Oh Mandor

    1.00 1.0250 1.0250 M3 Concrete Pump

    1.00 0.0100 0.0100 hr Vibrator

    1.00 0.1500 0.1500 ltr Bensin

    1 M3 Beton cor readymix dengan mutu K 225

    1.00 1.0250 1.0250 M3 Beton readymix K-225

    1.00 0.6300 0.6300 Oh Pekerja

    1.00 0.3000 0.3000 Oh Tukang batu

    1.00 0.0900 0.0900 Oh Kepala Tukang

    1.00 0.0270 0.0270 Oh Mandor

    1.00 1.0250 1.0250 M3 Concrete Pump

    1.00 0.0100 0.0100 hr Vibrator

    1.00 0.1500 0.1500 ltr Bensin

    1 M3 Beton cor readymix dengan mutu K 3001.00 1.0250 1.0250 M3 Beton readymix K-300

    1.00 0.6300 0.6300 Oh Pekerja

    1.00 0.3000 0.3000 Oh Tukang batu

    1.00 0.0900 0.0900 Oh Kepala Tukang

    1.00 0.0270 0.0270 Oh Mandor

    1.00 1.0250 1.0250 M3 Concrete Pump

    1.00 0.0100 0.0100 hr Vibrator

    1.00 0.1500 0.1500 ltr Bensin

    1 M2 Plastik cor

    1.00 0.0167 0.0167 roll Plastik cor

    1.00 0.0833 0.0833 Oh Pekerja

    1 M' Nat asphalt + pasir

    1.00 0.0040 0.0040 M3 Pasir pasang1.00 0.6345 0.6345 kg Aspal1.00 1.0000 1.0000 ls Perlengkapan1.00 0.1600 0.1600 Oh Pekerja1.00 0.0160 0.0160 Oh Tukang1.00 0.0016 0.0016 Oh Kepala tukang

    1.00 0.0008 0.0008 Oh Mandor 1 M2 Grooving

    1.00 1.0000 1.0000 ls Perlengkapan1.00 0.3600 0.3600 Oh Pekerja

  • 7/29/2019 Rab Sma & Smp

    27/411

    1.00 0.0360 0.0360 Oh Tukang1.00 0.0036 0.0036 Oh Kepala tukang1.00 0.0018 0.0018 Oh Mandor

    1 bh Selang dowel

    1.00 0.6000 0.6000 m' Selang 3/4 plastik

    1.00 0.0900 0.0900 Oh Pekerja1.00 1.0000 1.0000 ls Alat bantu

    1 unit Precast Saluran

    1.00 0.2016 0.2016 m3 Beton readymix K-225

    1.00 8.3210 8.3210 kg Pembesian Polos

    1.00 1.3800 1.3800 m2 Bekisting saluran

    1 unit Precast tutup Saluran

    1.00 0.0744 0.0744 m3 Beton readymix K-225

    1.00 5.7778 5.7778 kg Pembesian Polos

    1.00 0.7400 0.7400 m2 Bekisting tutup saluran

    KOMPONEN BEKISTING1 M2 1.00 M2 Bekisting Footplate/Pile Cap

    1.00 0.0280 0.0280 M3 Papan Meranti

    1.00 0.2000 0.2000 Kg Paku biasa 1" - 3,5"1.00 0.1000 0.1000 Ltr Minyak begesting

    1.00 0.2600 0.2600 Oh Tukang Kayu

    1.00 0.0260 0.0260 Oh Kepala Tukang

    1.00 0.3000 0.3000 Oh Pekerja

    1.00 0.0050 0.0050 Oh Mandor

    1 M2 1.00 M2 Bekisting Sloof/Tie Beam

    1.00 0.0300 0.0300 M3 Papan Meranti

    1.00 0.2000 0.2000 Kg Paku biasa 1" - 3,5"

    1.00 0.1000 0.1000 Ltr Minyak begesting

    1.00 0.2600 0.2600 Oh Tukang Kayu

    1.00 0.0260 0.0260 Oh Kepala Tukang

    1.00 0.3000 0.3000 Oh Pekerja1.00 0.0050 0.0050 Oh Mandor

    1 M2 1.00 M2 Bekisting Kolom

    1.00 0.0854 0.0854 Lbr Plywood 9mm

    1.00 0.0200 0.0200 M3 Papan Meranti

    1.00 0.0075 0.0075 M3 Kayu meranti

    1.00 2.0000 2.0000 Btg Dolken kayu galam dia. 8 - 10

    1.00 0.3000 0.3000 Kg Paku biasa 1" - 3,5"

    1.00 0.2000 0.2000 Ltr Minyak begesting

    1.00 0.3300 0.3300 Oh Tukang Kayu

    1.00 0.0330 0.0330 Oh Kepala Tukang

    1.00 0.3000 0.3000 Oh Pekerja

    1.00 0.0060 0.0060 Oh Mandor

    1 M2 1.00 M2 Bekisting Plat/Dak

    1.00 0.0854 0.0854 Lbr Plywood 9mm

    1.00 0.0200 0.0200 M3 Papan Meranti

    1.00 0.0075 0.0075 M3 Kayu meranti

    1.00 2.0000 2.0000 Btg Dolken kayu galam dia. 8 - 10

    1.00 0.3000 0.3000 Kg Paku biasa 1" - 3,5"

    1.00 0.2000 0.2000 Ltr Minyak begesting

  • 7/29/2019 Rab Sma & Smp

    28/411

    1.00 0.3300 0.3300 Oh Tukang Kayu

    1.00 0.0330 0.0330 Oh Kepala Tukang

    1.00 0.3000 0.3000 Oh Pekerja

    1.00 0.0060 0.0060 Oh Mandor

    1 M2 1.00 M2 Bekisting Balok

    1.00 0.0854 0.0854 Lbr Plywood 9mm

    1.00 0.0200 0.0200 M3 Papan Meranti

    1.00 0.0110 0.0110 M3 Kayu meranti

    1.00 2.0000 2.0000 Btg Dolken kayu galam dia. 8 - 10

    1.00 0.3000 0.3000 Kg Paku biasa 1" - 3,5"

    1.00 0.2000 0.2000 Ltr Minyak begesting

    1.00 0.3300 0.3300 Oh Tukang Kayu

    1.00 0.0330 0.0330 Oh Kepala Tukang

    1.00 0.3000 0.3000 Oh Pekerja

    1.00 0.0060 0.0060 Oh Mandor

    1 M2 1.00 M2 Bekisting Dinding

    1.00 0.0854 0.0854 Lbr Plywood 9mm

    1.00 0.0200 0.0200 M3 Papan Meranti

    1.00 0.0075 0.0075 M3 Kayu meranti

    1.00 2.0000 2.0000 Btg Dolken kayu galam dia. 8 - 10

    1.00 0.3000 0.3000 Kg Paku biasa 1" - 3,5"

    1.00 0.2000 0.2000 Ltr Minyak begesting

    1.00 0.3300 0.3300 Oh Tukang Kayu

    1.00 0.0330 0.0330 Oh Kepala Tukang

    1.00 0.3000 0.3000 Oh Pekerja

    1.00 0.0060 0.0060 Oh Mandor

    1 m' Delatasi Dinding

    1.00 0.1540 0.1540 lbr Steroform

    1.00 0.1760 0.1760 oh Pekerja

    RABAT & PELAT LANTAI1 M3 Lantai kerja tebal 5 cm

    Pekerjaan

    1.00 1.0000 1.0000 Beton cor manual dengan m

    BOX CULVERT1 unit Box Culvert

    1.00 0.7133 0.7133 M3 Beton cor readymix dengan

    1.00 41.0370 41.0370 Kg Pembesian Polos

    1.00 57.1721 57.1721 kg Pembesian Ulir

    1.00 6.79 6.7920 M2 Bekisting Sloof/Tie Beam

    PLAT GROUNDTANK

    1 M3 Pelat Groundtank tebal 30 cm, (Groundtank)1.00 1.0000 1.0000 M3 Beton cor readymix dengan

    1.00 118.7870 118.7870 Kg Pembesian Polos

    1 M3 Shear Wall tebal 20 cm, (Groundtank)

    1.00 1.0000 1.0000 M3 Beton cor readymix dengan

    1.00 89.0902 89.0902 Kg Pembesian Polos

    1.00 10.0000 10.0000 M2 Bekisting Dinding

    1 M3 Pelat Lantai tebal 15 cm, (Groundtank)

  • 7/29/2019 Rab Sma & Smp

    29/411

    1.00 1.0000 1.0000 M3 Beton cor readymix dengan

    1.00 118.7870 118.7870 Kg Pembesian Polos

    1 M3 Pelat Atap tebal 10 cm, (Groundtank)

    1.00 1.0000 1.0000 M3 Beton cor readymix dengan

    1.00 178.1804 178.1804 Kg Pembesian Polos

    1.00 10.00 10.0000 M2 Bekisting Plat/Dak

    PEKERJAAN BAJA1 Kg Pasang WF 400.300.10.16

    1.00 1.0500 1.0500 Kg WF 400.300.10.16

    1.00 0.0800 0.0800 Kg Meni Primer Zinchromate ex N

    1.00 0.0200 0.0200 Kg Thinner A

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0060 0.0060 Oh Tukang Besi

    1.00 0.0060 0.0060 Oh Kepala Tukang Besi

    1.00 0.0003 0.0003 Oh Mandor

    1 Kg Pasang WF 350.250.8.12

    1.00 1.0500 1.0500 Kg WF 350.250.8.12

    1.00 0.0800 0.0800 Kg Meni Primer Zinchromate ex N1.00 0.0200 0.0200 Kg Thinner A

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0060 0.0060 Oh Tukang Besi

    1.00 0.0060 0.0060 Oh Kepala Tukang Besi

    1.00 0.0003 0.0003 Oh Mandor

    1 Kg Pasang WF 250.175.7.11

    1.00 1.0500 1.0500 Kg WF 250.175.7.11

    1.00 0.0800 0.0800 Kg Meni Primer Zinchromate ex N

    1.00 0.0200 0.0200 Kg Thinner A

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0060 0.0060 Oh Tukang Besi

    1.00 0.0060 0.0060 Oh Kepala Tukang Besi1.00 0.0003 0.0003 Oh Mandor

    1 Kg Pasang WF 200.150.6.9

    1.00 1.0500 1.0500 Kg WF 200.150.6.9

    1.00 0.0800 0.0800 Kg Meni Primer Zinchromate ex N

    1.00 0.0200 0.0200 Kg Thinner A

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0060 0.0060 Oh Tukang Besi

    1.00 0.0060 0.0060 Oh Kepala Tukang Besi

    1.00 0.0003 0.0003 Oh Mandor

    1 Kg Pasang WF 200.100.5,5.8

    1.00 1.0500 1.0500 Kg WF 200.100.5,5.8

    1.00 0.0800 0.0800 Kg Meni Primer Zinchromate ex N

    1.00 0.0200 0.0200 Kg Thinner A

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0060 0.0060 Oh Tukang Besi

    1.00 0.0060 0.0060 Oh Kepala Tukang Besi

    1.00 0.0003 0.0003 Oh Mandor

    1 Kg Pasang Gording Canal 150.65.20.3,2

  • 7/29/2019 Rab Sma & Smp

    30/411

    1.00 1.0500 1.0500 Kg Canal 150.65.20.3,2

    1.00 0.0800 0.0800 Kg Meni Primer Zinchromate ex N

    1.00 0.0200 0.0200 Kg Thinner A

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0060 0.0060 Oh Kepala Tukang Besi

    1.00 0.0060 0.0060 Oh Kepala Tukang

    1.00 0.0003 0.0003 Oh Mandor

    1 Kg Pasang Gording Canal 100.50.20.3,2

    1.00 1.0500 1.0500 Kg Canal 100.50.20.3,2

    1.00 0.0800 0.0800 Kg Meni Primer Zinchromate ex N

    1.00 0.0200 0.0200 Kg Thinner A

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0060 0.0060 Oh Tukang Besi

    1.00 0.0060 0.0060 Oh Kepala Tukang Besi

    1.00 0.0003 0.0003 Oh Mandor

    1 Kg Pasang Siku 50.50.5

    1.00 1.0500 1.0500 Kg 50.50.5

    1.00 0.0800 0.0800 Kg Meni Primer Zinchromate ex N

    1.00 0.0200 0.0200 Kg Thinner A

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0060 0.0060 Oh Tukang Besi

    1.00 0.0060 0.0060 Oh Kepala Tukang Besi

    1.00 0.0003 0.0003 Oh Mandor

    1 M' Pasang Ikatan Angin 16

    1.00 1.5147 1.5147 Kg Besi Beton Polos

    1.00 0.1212 0.1212 Kg Meni Primer Zinchromate ex N

    1.00 0.0303 0.0303 Kg Thinner A

    1.00 0.1212 0.1212 Oh Pekerja

    1.00 0.0091 0.0091 Oh Tukang Besi

    1.00 0.0091 0.0091 Oh Kepala Tukang Besi

    1.00 0.0005 0.0005 Oh Mandor

    1 M' Pasang Trekstang 12

    1.00 0.9765 0.9765 Kg Besi Beton Polos

    1.00 0.0781 0.0781 Kg Meni Primer Zinchromate ex N

    1.00 0.0195 0.0195 Kg Thinner A

    1.00 0.0781 0.0781 Oh Pekerja

    1.00 0.0059 0.0059 Oh Tukang Besi

    1.00 0.0059 0.0059 Oh Kepala Tukang Besi

    1.00 0.0003 0.0003 Oh Mandor

    PEKERJAAN DINDING1 M3 Pasangan Rolag 1 : 2

    1M3 Pasangan bata 1 : 2

    1 M2 Pasangan bata 1 : 2

    1.00 70.0000 70.0000 Bh Batu Bata

    1.00 18.9500 18.9500 Kg Semen Portland

    1.00 0.0380 0.0380 M3 Pasir Pasang

    1.00 0.3300 0.3300 Oh Pekerja

    1.00 0.1000 0.1000 Oh Tukang Batu

    1.00 0.0100 0.0100 Oh Kepala Tukang

    1.00 0.0150 0.0150 Oh Mandor

  • 7/29/2019 Rab Sma & Smp

    31/411

    1 M3 Pasangan Rolag 1 : 4

    1M3 Pasangan bata 1 : 4

    1 M2 Pasangan bata 1 : 4

    1.00 70.0000 70.0000 Bh Batu Bata

    1.00 11.5000 11.5000 Kg Semen Portland

    1.00 0.0430 0.0430 M3 Pasir Pasang

    1.00 0.3300 0.3300 Oh Pekerja

    1.00 0.1000 0.1000 Oh Tukang Batu

    1.00 0.0100 0.0100 Oh Kepala Tukang

    1.00 0.0150 0.0150 Oh Mandor

    1 M2 Plesteran 1 : 2

    1.00 12.5000 12.5000 Kg Semen Portland

    1.00 0.0170 0.0170 M3 Pasir Pasang

    1.00 0.3000 0.3000 Oh Pekerja

    1.00 0.1500 0.1500 Oh Tukang Batu

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0100 0.0100 Oh Mandor

    1 M2 Plesteran 1 : 4

    1.00 10.0000 10.0000 Kg Semen Portland

    1.00 0.0200 0.0200 M3 Pasir Pasang

    1.00 0.3000 0.3000 Oh Pekerja

    1.00 0.1500 0.1500 Oh Tukang Batu

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0100 0.0100 Oh Mandor

    1 M2 Plesteran Kamprot

    1.00 10.0000 10.0000 Kg Semen Portland

    1.00 0.0200 0.0200 M3 Pasir Pasang

    1.00 0.2000 0.2000 Oh Pekerja

    1.00 0.1500 0.1500 Oh Tukang Batu

    1.00 0.0150 0.0150 Oh Kepala Tukang1.00 0.0100 0.0100 Oh Mandor

    1 M2 Pekerjaan Alkaplas

    1.00 3.2813 3.2813 Kg Semen Instant Acian @ 25 Kg

    1.00 0.0500 0.0500 Oh Pekerja

    1.00 0.1000 0.1000 Oh Tukang Batu

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0100 0.0100 Oh Mandor

    1 M2 Pasang Ornamen GRC Masjid

    1.00 1.0500 1.0500 M2 Ornamen GRC

    1 M' Pasang Batu Alam Tempel1.00 1.0500 1.0500 M2 Batu Alam Tempel

    1.00 11.7500 11.7500 Kg Semen Portland

    1.00 0.0350 0.0350 M3 pasir pasang

    1.00 0.6200 0.6200 Oh Pekerja

    1.00 0.3500 0.3500 Oh Tukang batu

    1.00 0.0350 0.0350 Oh Kepala Tukang

    1.00 0.0300 0.0300 Oh Mandor

    1 M2 Pasang Kawat Harmonika

  • 7/29/2019 Rab Sma & Smp

    32/411

    1.00 1.1000 1.1000 M2 Kawat Harmonika

    1.00 0.0200 0.0200 Kg Paku biasa 1" - 3,5"

    1.00 0.0018 0.0018 M3 Kayu Kusen, Rangka Bangun

    1.00 0.1000 0.1000 Oh Pekerja

    1.00 0.1000 0.1000 Oh Tukang Kayu

    1.00 0.0100 0.0100 Oh Kepala Tukang

    1 M' 1.00 Nat 2 cm

    1.00 1.1250 1.1250 Kg Semen Portland

    1.00 0.1370 0.1370 M3 Pekerja

    1.00 0.0685 0.0685 Oh Tukang Batu

    1.00 0.0066 0.0066 Oh Kepala Tukang

    1.00 0.0066 0.0066 Oh Mandor

    1 M' Nat 12.5 Cm

    0.1600 M2 tembok + acian

    1.00 1.0000 0.1600 M2 Plesteran 1 : 4

    4.0000 Bh Lining

    1.00 0.0685 0.2739 Oh Pekerja

    1.00 0.0342 0.1370 Oh Tukang Batu

    1.00 0.0033 0.0132 Oh Kepala Tukang

    1.00 0.0033 0.0132 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' List Ukuran 12 cm

    0.0300 M3 Pekerjaan Beton

    1.00 1.0000 0.0300 M3 Beton cor readymix dengan

    1.00 96.9878 2.9096 Kg Pembesian Polos

    0.4900 M2 tembok + acian

    1.00 1.0000 0.4900 M2 Plesteran 1 : 4

    3.0000 Bh Lining

    1.00 0.0685 0.2054 Oh Pekerja

    1.00 0.0342 0.1027 Oh Tukang Batu

    1.00 0.0033 0.0099 Oh Kepala Tukang1.00 0.0033 0.0099 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' List Ukuran 8+8+8 cm, (Laboratorium SMA)

    0.0168 M3 rjaan Beton

    1.00 1.0000 0.0168 M3 Beton cor readymix dengan

    1.00 115.9252 1.9475 Kg Pembesian Polos

    0.2400 M2 tembok + acian

    1.00 1.0000 0.2400 M2 Plesteran 1 : 4

    4.0000 Bh Lining

    1.00 0.0685 0.2739 Oh Pekerja

    1.00 0.0342 0.1370 Oh Tukang Batu

    1.00 0.0033 0.0132 Oh Kepala Tukang1.00 0.0033 0.0132 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' List Ukuran 7+7.5+7 cm

    0.0150 M3 rjaan Beton

    1.00 1.0000 0.0150 M3 Beton cor readymix dengan

    1.00 115.9252 1.7389 Kg Pembesian Polos

    0.2150 M2 tembok + acian

    1.00 1.0000 0.2150 M2 Plesteran 1 : 4

  • 7/29/2019 Rab Sma & Smp

    33/411

    4.0000 Bh Lining

    1.00 0.0685 0.2739 Oh Pekerja

    1.00 0.0342 0.1370 Oh Tukang Batu

    1.00 0.0033 0.0132 Oh Kepala Tukang

    1.00 0.0033 0.0132 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' List Ukuran 5+12.5+5 cm

    0.2250 M2 tembok + acian

    1.00 1.0000 0.2250 M2 Plesteran 1 : 4

    4.0000 Bh Lining

    1.00 0.0685 0.2739 Oh Pekerja

    1.00 0.0342 0.1370 Oh Tukang Batu

    1.00 0.0033 0.0132 Oh Kepala Tukang

    1.00 0.0033 0.0132 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' List Ukuran 5+15+5 cm

    0.2500 M2 tembok + acian

    1.00 1.0000 0.2500 M2 Plesteran 1 : 4

    4.0000 Bh Lining

    1.00 0.0685 0.2739 Oh Pekerja

    1.00 0.0342 0.1370 Oh Tukang Batu

    1.00 0.0033 0.0132 Oh Kepala Tukang

    1.00 0.0033 0.0132 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' List Ukuran 5+5+5 cm

    0.1500 M2 tembok + acian

    1.00 1.0000 0.1500 M2 Plesteran 1 : 4

    4.0000 Bh Lining

    1.00 0.0685 0.2739 Oh Pekerja

    1.00 0.0342 0.1370 Oh Tukang Batu

    1.00 0.0033 0.0132 Oh Kepala Tukang1.00 0.0033 0.0132 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' List Ukuran 3+3+3 cm

    0.0900 M2 tembok + acian

    1.00 1.0000 0.0900 M2 Plesteran 1 : 4

    3.0000 Bh Lining

    1.00 0.0685 0.2054 Oh Pekerja

    1.00 0.0342 0.1027 Oh Tukang Batu

    1.00 0.0033 0.0099 Oh Kepala Tukang

    1.00 0.0033 0.0099 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' List Ukuran 6.5 cm

    0.1250 M2 tembok + acian

    1.00 1.0000 0.1250 M2 Plesteran 1 : 4

    4.0000 Bh Lining

    1.00 0.0685 0.2739 Oh Pekerja

    1.00 0.0342 0.1370 Oh Tukang Batu

    1.00 0.0033 0.0132 Oh Kepala Tukang

    1.00 0.0033 0.0132 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

  • 7/29/2019 Rab Sma & Smp

    34/411

    1 M' Listplank Ukuran 5 x 25 cm, (Edukasi SMA)

    0.0125 M3 Pekerjaan Beton

    1.00 1.0000 0.0125 M3 Beton cor readymix dengan

    1.00 232.7707 2.9096 Kg Pembesian Polos

    1.00 0.5500 0.5500 M2 Bekisting Balok

    0.4500 M2 tembok + acian

    1.00 1.0000 0.4500 M2 Plesteran 1 : 4

    4.0000 Bh Lining

    1.00 0.0685 0.2739 Oh Pekerja

    1.00 0.0342 0.1370 Oh Tukang Batu

    1.00 0.0033 0.0132 Oh Kepala Tukang

    1.00 0.0033 0.0132 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' Benangan Janggutan Void Tangga, (R. Kegiatan S

    0.8000 M2 tembok + acian

    1.00 1.0000 0.8000 M2 Plesteran 1 : 4

    2.0000 Bh Lining

    1.00 0.0685 0.1370 Oh Pekerja

    1.00 0.0342 0.0685 Oh Tukang Batu

    1.00 0.0033 0.0066 Oh Kepala Tukang

    1.00 0.0033 0.0066 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' Benangan Beton Ekspose J3, (Perpustakaan SMA)

    0.5900 Plesteran tembok + acian

    1.00 1.0000 0.5900 M2 Plesteran 1 : 4

    2.0000 Lining

    1.00 0.0685 0.1370 Oh Pekerja

    1.00 0.0342 0.0685 Oh Tukang Batu

    1.00 0.0033 0.0066 Oh Kepala Tukang

    1.00 0.0033 0.0066 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' Plesteran + Benangan Listplank R. Genset

    1.0500 Plesteran tembok + acian

    1.00 1.0000 1.0500 M2 Plesteran 1 : 4

    9.0000 Lining

    1.00 0.0685 0.6163 Oh Pekerja

    1.00 0.0342 0.3081 Oh Tukang Batu

    1.00 0.0033 0.0297 Oh Kepala Tukang

    1.00 0.0033 0.0297 Oh Mandor

    1.00 1.0000 1.0000 Ls Alat Bantu

    1 M' Benangan sudut

    1.00 3.0800 3.0800 Kg Semen Portland1.00 0.0086 0.0086 m3 Pasir Pasang

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.1200 0.1200 Oh Tukang Batu

    1.00 0.0120 0.0120 Oh Kepala Tukang

    1.00 0.0060 0.0060 Oh Mandor

    1 M3 Kolom Ekspose Kantor SMA

  • 7/29/2019 Rab Sma & Smp

    35/411

    Pekerjaan Beton

    1.00 1.0000 1.0000 M3 Beton cor readymix dengan

    1.00 116.3853 116.3853 Kg Pembesian Polos

    1.00 20.0000 20.0000 M2 Bekisting Kolom

    1 Unit Pasang Ornamen Gable Rumah Adat Dayak

    1.00 1.0000 1.0000 Bh Ornamen Gable Rumah Adat

    1 Unit Pasang Ornamen Jengger Atap Rumah Adat Daya

    1.00 1.0000 1.0000 Bh Ornamen Jengger Atap Rum

    1 Unit Pasang Ornamen Ukiran Tiang Lamin

    1.00 1.0000 1.0000 Bh Ornamen Ukiran Tiang Lamin

    1 Unit Pasang Patung Burung Enggang

    1.00 1.0000 1.0000 Bh Patung Burung Enggang

    1 M2 Waterproofing Coating

    1.00 0.6667 0.6667 Kg Waterproofing cementbase

    1.00 0.0300 0.0300 Oh Tukang Cat

    1.00 0.0250 0.0250 Oh Kepala Tukang1.00 0.1500 0.1500 Oh Pekerja

    1.00 0.0080 0.0080 Oh Mandor

    RAILLING,

    1 M' Pasang Pipa Galvanis 1 "

    1.00 1.2000 1.2000 M' Pipa Galvanis 1 "

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.1080 0.1080 Oh Pekerja

    1.00 0.1800 0.1800 Oh Tukang

    1.00 0.0180 0.0180 Oh Kepala Tukang

    1.00 0.0054 0.0054 Oh Mandor

    1 M' Pasang Pipa Galvanis 1 1/2"1.00 1.2000 1.2000 M' Pipa Galvanis 1 1/2"

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.1080 0.1080 Oh Pekerja

    1.00 0.1800 0.1800 Oh Tukang

    1.00 0.0180 0.0180 Oh Kepala Tukang

    1.00 0.0054 0.0054 Oh Mandor

    1 M' Pasang Pipa Galvanis 2"

    1.00 1.2000 1.2000 M' Pipa Galvanis 2"

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.1080 0.1080 Oh Pekerja

    1.00 0.1800 0.1800 Oh Tukang

    1.00 0.0180 0.0180 Oh Kepala Tukang1.00 0.0054 0.0054 Oh Mandor

    1 M' Pasang Pipa Galvanis 2.5"

    1.00 1.2000 1.2000 M' Pipa Galvanis 2.5"

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.1080 0.1080 Oh Pekerja

    1.00 0.1800 0.1800 Oh Tukang

    1.00 0.0180 0.0180 Oh Kepala Tukang

  • 7/29/2019 Rab Sma & Smp

    36/411

    1.00 0.0054 0.0054 Oh Mandor

    1 M' Pasang Pipa Galvanis 3"

    1.00 1.2000 1.2000 M' Pipa Galvanis 3"

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.1350 0.1350 Oh Pekerja

    1.00 0.2250 0.2250 Oh Tukang

    1.00 0.0225 0.0225 Oh Kepala Tukang

    1.00 0.0068 0.0068 Oh Mandor

    1 M' Pasang Pipa Galvanis 4"

    1.00 1.2000 1.2000 M' Pipa Galvanis 4"

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.1350 0.1350 Oh Pekerja

    1.00 0.2250 0.2250 Oh Tukang

    1.00 0.0225 0.0225 Oh Kepala Tukang

    1.00 0.0068 0.0068 Oh Mandor

    1 M' Pasang Pipa Hitam 1"

    1.00 1.2000 1.2000 M' Pipa Hitam 1"

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.1080 0.1080 Oh Pekerja

    1.00 0.1800 0.1800 Oh Tukang

    1.00 0.0180 0.0180 Oh Kepala Tukang

    1.00 0.0054 0.0054 Oh Mandor

    1 M' Pasang Pipa Hitam 2"

    1.00 1.2000 1.2000 M' Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.1080 0.1080 Oh Pekerja1.00 0.1800 0.1800 Oh Tukang

    1.00 0.0180 0.0180 Oh Kepala Tukang

    1.00 0.0054 0.0054 Oh Mandor

    1 M' Pasang Besi Hitam 4x4cm

    1.00 1.2000 1.2000 M' Besi Hitam 4x4cm

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.1080 0.1080 Oh Pekerja

    1.00 0.1800 0.1800 Oh Tukang

    1.00 0.0180 0.0180 Oh Kepala Tukang

    1.00 0.0054 0.0054 Oh Mandor

    1 M' Railing Tangga Kantor SMP

    M' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"

    1.05 2.0000 2.1000 M' Pasang Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

  • 7/29/2019 Rab Sma & Smp

    37/411

    1 M' Railing Tangga Edukasi SMP

    M' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"

    1.05 1.0000 1.0500 M' Pasang Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Railing Tangga R. Guru SMP

    M' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"

    1.05 1.0000 1.0500 M' Pasang Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Railing Tangga Laboratorium SMP

    M' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"1.05 1.0000 1.0500 M' Pasang Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Railing Tangga Perpustakaan SMP

    M' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"

    1.05 2.0000 2.1000 M' Pasang Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Railing Balkon Kantor SMA

    M' Pekerjaan

    1.05 0.6667 0.7000 M' Pasang Pipa Hitam 2"

    1.05 9.0000 9.4500 M' Pasang Besi Hitam 4x4cm

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Railing Tangga Edukasi SMA

    M' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"

    1.05 2.0000 2.1000 M' Pasang Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Railing Tangga R. Kegiatan SMA

    M' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"

    1.05 2.0000 2.1000 M' Pasang Pipa Hitam 2"

  • 7/29/2019 Rab Sma & Smp

    38/411

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Railing Tangga Laboratorium SMA

    M' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"

    1.05 2.0000 2.1000 M' Pasang Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Railing Tangga Perpustakaan SMA

    M' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"

    1.05 2.0000 2.1000 M' Pasang Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M3 Railing Tangga OutdoorM' Pekerjaan

    1.05 6.0000 6.3000 M' Pasang Pipa Hitam 1"

    1.05 2.0000 2.1000 M' Pasang Pipa Hitam 2"

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Pagar Railing Besi Hitam Tinggi 80 cm

    M' Pekerjaan

    1.05 6.8000 7.1400 M' Pasang Besi Hitam 4x4cm

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Pengecatan Semi Duco

    1 M' Railing Pagar Bangkirai 6/12

    Pekerjaan

    1.00 0.0072 0.0072 M3 Kayu kusen, rangka banguna

    1.00 0.2400 0.2400 M2 Pekerjaan Melamic

    1.00 1.0000 1.0000 Ls Acesoris, angkur, dll

    1.00 1.0000 1.0000 Ls Upah pemasangan

    PEKERJAAN LANTAI1 M2 Pasang Keramik Lantai 60/601.00 1.1000 1.1000 M2 keramik 60x60 cm

    1.00 8.8000 8.8000 Kg Semen portland

    1.00 0.0215 0.0215 M3 Pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna

    1.00 0.3400 0.3400 Oh Pekerja

    1.00 0.1700 0.1700 Oh Tukang batu

  • 7/29/2019 Rab Sma & Smp

    39/411

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0150 0.0150 Oh Mandor

    1 M2 Pasang Keramik Lantai 40/40

    1.00 1.1000 1.1000 M2 keramik 40x40 cm

    1.00 8.8000 8.8000 Kg Semen portland

    1.00 0.0215 0.0215 M3 Pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna

    1.00 0.3400 0.3400 Oh Pekerja

    1.00 0.1700 0.1700 Oh Tukang batu

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0150 0.0150 Oh Mandor

    1 M2 Pasang Keramik Lantai 40/40 Unpolished

    1.00 1.1000 1.1000 M2 Keramik 40x40 cm Unpolished

    1.00 8.8000 8.8000 Kg Semen portland

    1.00 0.0215 0.0215 M3 Pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna1.00 0.3400 0.3400 Oh Pekerja

    1.00 0.1700 0.1700 Oh Tukang batu

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0150 0.0150 Oh Mandor

    1 M2 Pasang Keramik Lantai 33/33

    1.00 1.1000 1.1000 M2 Keramik 33x33 cm

    1.00 8.8000 8.8000 Kg Semen portland

    1.00 0.0215 0.0215 M3 Pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna

    1.00 0.3400 0.3400 Oh Pekerja

    1.00 0.1700 0.1700 Oh Tukang batu

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0150 0.0150 Oh Mandor

    1 M2 Pasang Keramik Lantai 30/30

    1.00 1.1000 1.1000 M2 Keramik 30x30 cm

    1.00 8.8000 8.8000 Kg Semen portland

    1.00 0.0215 0.0215 M3 Pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna

    1.00 0.3400 0.3400 Oh Pekerja1.00 0.1700 0.1700 Oh Tukang batu

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0150 0.0150 Oh Mandor

    1 M2 Pasang Keramik Lantai 30/30 Unpolished

    1.00 1.1000 1.1000 M2 Keramik 30x30 cm Unpolished

    1.00 8.8000 8.8000 Kg Semen portland

  • 7/29/2019 Rab Sma & Smp

    40/411

    1.00 0.0215 0.0215 M3 Pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna

    1.00 0.3400 0.3400 Oh Pekerja

    1.00 0.1700 0.1700 Oh Tukang batu

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0150 0.0150 Oh Mandor

    1 M2 Pasang Keramik Lantai 20/20 Unpolished

    1.00 1.1000 1.1000 M2 Keramik 20x20 cm Unpolished

    1.00 8.8000 8.8000 Kg Semen Portland

    1.00 0.0215 0.0215 M3 pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna

    1.00 0.3400 0.3400 Oh Pekerja

    1.00 0.1700 0.1700 Oh Tukang batu

    1.00 0.0150 0.0150 Oh Kepala Tukang

    1.00 0.0150 0.0150 Oh Mandor

    1 M2 Pasang Keramik 10/101.00 1.1000 1.1000 M2 Keramik 10x10 cm

    1.00 8.8000 8.8000 Kg Semen Portland

    1.00 0.0215 0.0215 M3 pasir pasang

    1.00 1.5000 1.5000 Kg Semen warna

    1.00 0.3500 0.3500 Oh Pekerja

    1.00 0.2500 0.3000 Oh Tukang batu

    1.00 0.1000 0.1000 Oh Kepala Tukang

    1.00 0.1000 0.1000 Oh Mandor

    1 M2 Pasang Keramik Dinding 30/30

    1.00 1.1000 1.1000 M2 Keramik 30x30 cm

    1.00 9.3000 9.3000 Kg Semen Portland

    1.00 0.0180 0.0180 M3 pasir pasang

    1.00 1.5000 1.5000 Kg Semen warna

    1.00 0.3000 0.3000 Oh Pekerja

    1.00 0.3000 0.3000 Oh Tukang batu

    1.00 0.0250 0.0250 Oh Kepala Tukang

    1.00 0.0250 0.0250 Oh Mandor

    1 M2 Pasang Keramik Dinding 20/25

    1.00 1.1000 1.1000 M2 Keramik 20x25 cm1.00 9.3000 9.3000 Kg Semen Portland

    1.00 0.0180 0.0180 M3 pasir pasang

    1.00 1.5000 1.5000 Kg Semen warna

    1.00 0.3000 0.3000 Oh Pekerja

    1.00 0.3000 0.3000 Oh Tukang batu

    1.00 0.0250 0.0250 Oh Kepala Tukang

    1.00 0.0250 0.0250 Oh Mandor

  • 7/29/2019 Rab Sma & Smp

    41/411

    1 M2 Pasang Keramik Tangga 40/40

    1.00 1.4000 1.4000 M2 Keramik 40x40 cm

    1.00 8.8000 8.8000 Kg Semen portland

    1.00 0.0215 0.0215 M3 Pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna

    1.00 0.4000 0.4000 Oh Pekerja

    1.00 0.5500 0.5500 Oh Tukang batu

    1.00 0.0500 0.0500 Oh Kepala Tukang

    1.00 0.0500 0.0500 Oh Mandor

    1 M2 Pasang Keramik Tangga 33/33

    1.00 1.2100 1.2100 M2 Keramik 33x33 cm

    1.00 8.8000 8.8000 Kg Semen portland

    1.00 0.0215 0.0215 M3 Pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna

    1.00 0.4000 0.4000 Oh Pekerja

    1.00 0.5500 0.5500 Oh Tukang batu1.00 0.0500 0.0500 Oh Kepala Tukang

    1.00 0.0500 0.0500 Oh Mandor

    1 M2 Pasang Keramik Tangga 30/30

    1.00 1.2100 1.2100 M2 Keramik 30x30 cm

    1.00 8.8000 8.8000 Kg Semen portland

    1.00 0.0215 0.0215 M3 Pasir pasang

    1.00 1.3000 1.3000 Kg Semen warna

    1.00 0.4000 0.4000 Oh Pekerja

    1.00 0.5500 0.5500 Oh Tukang batu

    1.00 0.0500 0.0500 Oh Kepala Tukang

    1.00 0.0500 0.0500 Oh Mandor

    1 M2 Pasang Koral Sikat

    1.00 0.6286 0.6286 Krg Koral Sikat

    1.00 12.0000 12.0000 Kg Semen Portland

    1.00 0.0275 0.0275 M3 pasir pasang

    1.00 0.2290 0.2290 Kg Semen warna

    1.00 1.0000 1.0000 M2 Upah Pasang Koral Sikat

    PEKERJAAN PLAFOND1 M2 Plafond lumbersiring rangka kayu meranti

    1.00 5.5000 5.5000 kpg Lumbersiring lebar 5cm

    1.00 0.2200 0.2200 Kg Paku biasa 1" - 3,5"

    1.00 0.1500 0.1500 Kg Paku triplek

    1.00 0.0252 0.0252 M3 Kayu Meranti

  • 7/29/2019 Rab Sma & Smp

    42/411

    1.00 0.3750 0.3750 Oh Tukang Kayu

    1.00 0.0750 0.0750 Oh Kepala Tukang

    1.00 0.1500 0.1500 Oh Pekerja

    1.00 0.0135 0.0135 Oh Mandor

    1 M2 Pasang Plafond Gyptile 9 mm Prepainted 60x120 M

    1.00 1.0000 1.0000 M2 Rangka Main Tee Cross Tee 6

    1.00 1.0000 1.0000 M2 Panel gyptile 9mm pre-painte

    1 M2 Pasang Plafond Kalsiboard 4,5 mm, dengan rangk

    1.00 1.0000 1.0000 M2 Rangka Metal + rod

    1.00 1.0000 1.0000 M2 Panel Kalsiboard 4,5mm

    1.00 1.0000 1.0000 M2 Pengecatan Plafond Kalsiboa

    1 M2 Pasang Plafond Gypsum t=9 mm, dengan rangka

    1.00 1.0000 1.0000 M2 Rangka Metal + rod

    1.00 1.0000 1.0000 M2 Panel Kalsiboard 4,5mm

    1.00 1.0000 1.0000 M2 Pengecatan Plafond Gypsum

    1 M2 Pasang Panel Plafond CaLsiboard

    1.00 0.3640 0.3640 Lbr CaLsyboard 9 mm

    1.00 0.1100 0.1100 Kg Paku gypsum

    1.00 0.0500 0.0500 Oh Tukang

    1.00 0.0050 0.0050 Oh Kepala Tukang

    1.00 0.1000 0.1000 Oh Pekerja

    1.00 0.0050 0.0050 Oh Mandor

    1 M2 Pasang Panel Plafond Gypsum board

    1.00 0.3640 0.3640 Lbr Gypsum board (120x240x9) m

    1.00 0.1100 0.1100 Kg Paku gypsum

    1.00 0.0500 0.0500 Oh Tukang

    1.00 0.0050 0.0050 Oh Kepala Tukang

    1.00 0.1000 0.1000 Oh Pekerja

    1.00 0.0050 0.0050 Oh Mandor

    1 M2 Pasang List Plafond Gypsum

    1.00 1.0000 1.0000 M' List Gypsum

    1.00 0.0434 0.0434 Kg Compound UB20

    1.00 0.0100 0.0100 Kg Paku biasa 1" - 3,5"

    1.00 0.0300 0.0300 Oh Pekerja1.00 0.0300 0.0300 Oh Tukang kayu

    1.00 0.0030 0.0030 Oh Kepala Tukang

    1.00 0.0016 0.0016 Oh Mandor

    1 M2 Pasang Rangka Plafond 60x120 Main Tee-Cross Tee

    1.00 3.0900 3.0900 M' Rangka Main Tee Cross Tee 6

    1.00 1.2360 1.2360 M' Penggantung / Rod

  • 7/29/2019 Rab Sma & Smp

    43/411

    1.00 1.0000 1.0000 LS Material Bantu

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0600 0.0600 Oh Tukang kayu

    1.00 0.0060 0.0060 Oh Kepala Tukang

    1.00 0.0030 0.0030 Oh Mandor

    1 M2 Pasang Rangka Plafond Metal + Rod1.00 3.0900 3.0900 M' Rangka Plafond Metal

    1.00 1.2360 1.2360 M' Penggantung / Rod

    1.00 1.0000 1.0000 LS Material Bantu

    1.00 0.0600 0.0600 Oh Pekerja

    1.00 0.0600 0.0600 Oh Tukang kayu

    1.00 0.0060 0.0060 Oh Kepala Tukang

    1.00 0.0030 0.0030 Oh Mandor

    PEKERJAAN ATAPPENUTUP ATAP

    1 M2 Pasang Atap Zincalume 0.35 mm

    1.00 1.0500 1.0500 M2 Atap Zincalume 0.35 mm

    1.00 4.0000 4.0000 Pcs Hex Washer Flange

    1.00 0.0750 0.0750 Oh Pekerja

    1.00 0.3750 0.3750 Oh Tukang Besi

    1.00 0.0040 0.0040 Oh Kepala Tukang

    1.00 0.0030 0.0030 Oh Mandor

    1 M2 Pasang Atap Genteng Metal, ex Multi Roof

    1.00 2.6000 2.6000 Lbr Genteng Metal, ex Multi Roof

    1.00 0.0200 0.0200 Kg Paku genteng metal

    1.00 0.2000 0.2000 Oh Pekerja

    1.00 0.1000 0.1000 Oh Tukang Besi

    1.00 0.0100 0.0100 Oh Kepala Tukang

    1.00 0.0100 0.0100 Oh Mandor

    1 M2 Pasang Atap Polycarbonat 6 mm

    1.00 1.0500 1.0500 M2 Atap Polycarbonat 6 mm

    1.00 6.0000 6.0000 Bh Paku sekrup 2'

    1.00 0.1400 0.1400 Oh Pekerja

    1.00 0.0700 0.0700 Oh Tukang Besi

    1.00 0.0070 0.0070 Oh Kepala Tukang1.00 0.0070 0.0070 Oh Mandor

    BUBUNGAN1 M' Pasang Bubungan Atap Zincalume 0.35 mm

    Pekerjaan

    1.00 0.5000 0.5000 M2 Pasang Atap Zincalume 0.35

  • 7/29/2019 Rab Sma & Smp

    44/411

    1 M' Pasang Bubungan Genteng Metal, ex Multi Roof

    1.00 0.9091 0.9091 Bh Bubungan Genteng Metal, ex

    1.00 0.0200 0.0200 Kg Paku genteng metal

    1.00 0.2000 0.2000 Oh Pekerja

    1.00 0.1000 0.1000 Oh Tukang Besi

    1.00 0.0100 0.0100 Oh Kepala Tukang

    1.00 0.0100 0.0100 Oh Mandor

    RANGKA ATAP1 M3 Pasang Kuda-Kuda Kayu Bengkirai 6/12, diketam h

    Pekerjaan

    1.00 1.0000 1.0000 M3 Kayu kusen, rangka banguna

    1 M2 0.0178 Pasang Rangka Atap, diketam halus

    Pekerjaan

    1.00 1.0000 0.0178 M3 Kayu kusen, rangka banguna

    LISTPLANK1 M' Pasang Listplank Zincalume 0.35 mm

    Pekerjaan

    1.00 0.3000 0.3000 M2 Pasang Atap Zincalume 0.35

    1 M' Pasang Listplank Bengkirai 2.5/20, diketam halus

    Pekerjaan

    1.00 0.2000 0.2000 M2 Papan kayu untuk tritisan, lant

    PEKERJAAN PENGECATAN1 M2 Pengecatan dinding interior, ex Cendana

    1.00 0.2500 0.2500 Kg Plamir Tembok

    1.00 0.2000 0.2000 Kg Cat Tembok, ex Cendana

    1.00 1.0000 1.0000 Lbr Amplas

    1.00 0.0100 0.0100 Oh Pekerja

    1.00 0.0200 0.0200 Oh Tukang Cat

    1.00 0.0400 0.0400 Oh Kepala Tukang

    1.00 0.0020 0.0020 Oh Mandor

    1 M2 Pengecatan Dinding Exterior, ex Mowilex Weatherc

    1.00 0.2000 0.2000 Ltr Cat Tembok, ex Mowilex Wea1.00 0.1500 0.1500 Kg Alkali undercoat

    1.00 1.0000 1.0000 Lbr Amplas

    1.00 0.0100 0.0100 Oh Pekerja

    1.00 0.0200 0.0200 Oh Tukang Cat

    1.00 0.0400 0.0400 Oh Kepala Tukang

    1.00 0.0020 0.0020 Oh Mandor

  • 7/29/2019 Rab Sma & Smp

    45/411

    1 M2 Pengecatan Plafond Gypsum

    1.00 1.0000 1.0000 M2 Pengecatan dinding interior,

    1 M' Pengecatan List Plafond Gypsum

    1.00 0.0278 0.0278 Kg Cat Tembok, ex Cendana

    1.00 0.0215 0.0215 Kg Cat Tembok, ex Cendana

    1.00 0.1500 0.1500 Lbr Amplas

    1.00 0.0100 0.0100 Oh Tukang Cat

    1.00 0.0083 0.0083 Oh Kepala Tukang

    1.00 0.0500 0.0500 Oh Pekerja

    1.00 0.0027 0.0027 Oh Mandor

    1 M' Melamic plafond lumbersiring

    1.00 0.6928 0.6928 Kg Melamin

    1.00 0.0600 0.0600 Kg Pewarna

    1.00 0.0480 0.0480 Kg Dempul kayu

    1.00 0.0516 0.0516 Kg Sanding

    1.00 0.0360 0.0360 Ltr Thinner A

    1.00 0.3600 0.3600 Lbr Amplas

    1.00 0.3838 0.3838 Oh Tukang Cat

    1.00 0.0339 0.0339 Oh Kepala Tukang

    1.00 0.2258 0.2258 Oh Pekerja

    1.00 0.0113 0.0113 Oh Mandor

    1 M2 Pekerjaan Melamic

    1.00 0.6928 0.6928 Kg Melamin

    1.00 0.0600 0.0600 Kg Pewarna

    1.00 0.0480 0.0480 Kg Dempul kayu

    1.00 0.0516 0.0516 Kg Sanding1.00 0.0360 0.0360 Ltr Thinner A

    1.00 0.3600 0.3600 Lbr Amplas

    1.00 0.3838 0.3838 Oh Tukang Cat

    1.00 0.0339 0.0339 Oh Kepala Tukang

    1.00 0.2258 0.2258 Oh Pekerja

    1.00 0.0113 0.0113 Oh Mandor

    1 M' Melamic Kusen

    Pekerjaan

    1.00 0.2400 0.2400 M2 Pekerjaan Melamic

    1 M2 Melamic Daun Jendela

    Pekerjaan

    1.00 1.0000 1.0000 M2 Pekerjaan Melamic

    1 M2 Melamic Daun Pintu

    Pekerjaan

    1.00 1.0000 1.0000 M2 Pekerjaan Melamic

  • 7/29/2019 Rab Sma & Smp

    46/411

    1 M' Pengecatan (Pipa Galvanis 2.5")

    1.00 1.0000 1.0000 M' Pengecatan (Pipa Galvanis 2.

    PEKERJAAN KUSEN / PINTU / JENDELA1 M' Kusen aluminium

    1.00 1.0000 1.0000 M' Kusen aluminium 4"

    1 M' Kusen kayu ulin

    1.00 1.0500 1.0500 M' Kusen kayu ulin 5/13

    1.00 1.0000 1.0000 M' Upah pasang kusen kayu

    1 M' Kusen Kayu Bengkirai

    1.00 1.0500 1.0500 M' Kusen kayu bengkirai 5/13

    1.00 1.0000 1.0000 M' Upah pasang kusen kayu

    1 M2 0.07 Daun Pintu Panil Bengkirai

    Pekerjaan

    1.00 1.0000 0.0650 M3 Kayu kusen, rangka banguna

    1.00 1.0000 1.0000 Ls Material Bantu

    1 M2 0.07 Daun Pintu Panil Ulin

    Pekerjaan

    1.00 1.0000 0.0650 M3 Kayu kusen, rangka banguna

    1.00 1.0000 1.0000 Ls Material Bantu

    1 M2 Daun Pintu Panil Plywood

    1.00 0.8000 0.8000 M2 Plywood 3mm

    1.00 1.0000 1.0000 Ls Material Bantu

    Pekerjaan

    1.00 0.0200 0.0200 M3 Kayu kusen, rangka banguna

    1 M2 Daun Pintu Panil Plywood Megateak

    1.00 1.0000 1.0000 M2 Plywood Megateak 3mm

    1.00 1.0000 1.0000 Ls Material Bantu

    Pekerjaan

    1.00 0.0200 0.0200 M3 Kayu kusen, rangka banguna

    1 M2 Daun Pintu Panil Plywood Lapis Aluminium Foil

    1.00 1.0000 1.0000 M2 Plywood Lapis Aluminium Foil

    1.00 1.0000 1.0000 Ls Material Bantu

    Pekerjaan

    1.00 0.0200 0.0200 M3 Kayu kusen, rangka banguna

    1 M2 Daun Pintu Panil Plywood & Plywood Lapis Aluminiu

    Pekerjaan

    1.00 1.0000 1.0000 M2 Daun Pintu Panil Plywood

    1.00 0.5000 0.5000 M2 Daun Pintu Panil Plywood Lap

    1.00 0.0200 0.0200 M3 Kayu kusen, rangka banguna

  • 7/29/2019 Rab Sma & Smp

    47/411

    1 M2 Daun Pintu Panil Plywood Megateak & Plywood Lap

    Pekerjaan

    1.00 1.0000 1.0000 M2 Daun Pintu Panil Plywood Me

    1.00 0.5000 0.5000 M2 Daun Pintu Panil Plywood Lap

    1.00 0.0200 0.0200 M3 Kayu kusen, rangka banguna

    1 M2 Daun Pintu Lemari Panil Plywood Megateak

    1.00 1.0000 1.0000 M2 Plywood Megateak 3mm

    Pekerjaan

    1.00 0.0042 0.0042 M3 Kayu kusen, rangka banguna

    1 M2 0.0050 Rangka Bengkirai Daun Jendela Kaca

    Pekerjaan

    1.00 1.2500 0.0063 M3 Kayu kusen, rangka banguna

    1 M2 0.0050 Rangka Bengkirai Daun Pintu Kaca

    Pekerjaan

    1.00 1.2500 0.0063 M3 Kayu kusen, rangka banguna

    1 M2 Pasang Kaca 5 mm

    1.00 1.0000 1.0000 M2 Kaca bening 5mm

    1 M2 Pasang Kaca 8 mm

    1.00 1.0000 1.0000 M2 Kaca bening 8mm

    1 M2 Pasang Kaca es 5mm

    1.00 1.0000 1.0000 M2 Kaca es 5mm

    1 Bh Pasang Pintu kaca Tempered Glass 12mm ex Asahi1.00 1.0000 1.0000 btl Pintu kaca Tempered Glass 1

    1 M' Silicon sealant

    1.00 1.0000 1.0000 btl Sil icon sealant

    PEKERJAAN PENGUNCI & PENGGANTUNG1 Bh Engsel Jendela 3"

    1.00 1.0000 1.0000 Bh Engsel Jendela 3"

    1 Bh Engsel pintu 4"

    1.00 1.0000 1.0000 Bh Engsel pintu 4"

    1 Bh Engsel Pintu lemari

    1.00 1.0000 1.0000 Bh Engsel Pintu Lemari

    1 Bh Grendel jendela

    1.00 1.0000 1.0000 Bh Gerendel jendela

    1 Bh Grendel pintu

  • 7/29/2019 Rab Sma & Smp

    48/411

    1.00 1.0000 1.0000 Bh Gerendel pintu

    1 Bh Kait Angin Jendela

    1.00 1.0000 1.0000 Bh Kait angin jendela

    1 Bh Handel jendela

    1.00 1.0000 1.0000 Bh Handel jendela

    1 Bh Kunci pintu

    1.00 1.0000 1.0000 Bh Kunci pintu

    1 Bh Kunci Pintu Lemari

    1.00 1.0000 1.0000 Bh Kunci Pintu Lemari

    PEKERJAAN SANITAIR1 Bh Pasang Klosed Jongkok lengkap Assesories

    1.00 0.1600 0.1600 Oh Mandor

    1.00 1.5000 1.5000 Oh Tukang

    1.00 0.1500 0.1500 Oh Kepala Tukang

    1.00 1.0000 1.0000 Oh Pekerja

    1.00 1.0000 1.0000 Bh Kloset Jongkok

    1.00 6.0000 6.0000 Kg Semen Portland

    1.00 0.0100 0.0100 M3 Pasir Pasang

    1 Bh Pasang Wastafel lengkap assesories

    1.00 0.1000 0.1000 Oh Mandor

    1.00 1.4500 1.4500 Oh Tukang

    1.00 0.1500 0.1500 Oh Kepala Tukang

    1.00 1.2000 1.2000 Oh Pekerja1.00 1.0000 1.0000 Bh Wastafel

    1.00 0.0100 0.0100 M3 Pasir Pasang

    1.00 6.0000 6.0000 Kg Semen Portland

    1 Ttk Pasang Urinoir lengkap lengkap assesories

    1.00 0.1000 0.1000 Oh Mandor

    1.00 1.0000 1.0000 Oh Tukang

    1.00 1.0000 1.0000 Oh Pekerja

    1.00 0.1000 0.1000 Oh Kepala Tukang

    1.00 1.0000 1.0000 Bh Urinoir

    1.00 0.0100 0.0100 M3 Pasir Pasang

    1.00 6.0000 6.0000 Kg Semen Portland

    1 Bh Bak mandi lapis keramik

    1.00 1.1680 1.1680 M2 Pasangan bata 1 : 4

    1.00 1.1680 1.1680 M2 Pasang Keramik Dinding 20/2

    1.00 1.0000 1.0000 M2 Pasang Keramik Lantai 20/20

    1.00 1.0000 1.0000 Bh Lubang kuras PVC bak mandi

  • 7/29/2019 Rab Sma & Smp

    49/411

    1.00 1.1680 1.1680 m2 Waterproofing Coating

    1.00 1.0000 1.0000 ls Acesoris, dll

    1 1 M' Pasang Pipa PVC 1/2" class AW

    1.00 1.2000 1.2000 M' Pipa PVC 1/2" class AW

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.0018 0.0018 Oh Mandor

    1.00 0.0600 0.0600 Oh Tukang

    1.00 0.0360 0.0360 Oh Pekerja

    1.00 0.0060 0.0060 Oh Kepala Tukang

    1 M' Pasang Pipa PVC 3/4" class AW

    1.00 1.2000 1.2000 M' Pipa PVC 3/4" class AW

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.0018 0.0018 Oh Mandor

    1.00 0.0600 0.0600 Oh Tukang

    1.00 0.0360 0.0360 Oh Pekerja

    1.00 0.0060 0.0060 Oh Kepala Tukang

    1 M' Pasang Pipa PVC 1 1/2" class AW

    1.00 1.2000 1.2000 M' Pipa PVC 1 1/2" class AW

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.0360 0.0360 Oh Pekerja

    1.00 0.0600 0.0600 Oh Tukang

    1.00 0.0060 0.0060 Oh Kepala Tukang

    1.00 0.0018 0.0018 Oh Mandor

    1 M' Subdrain Pipa PVC AW 2 "

    1.00 0.0360 0.0360 Oh Pekerja

    1.00 0.0600 0.0600 Oh Tukang

    1.00 0.0060 0.0060 Oh Kepala Tukang

    1.00 0.0018 0.0018 Oh Mandor

    1.00 1.2000 1.2000 M' Pipa PVC 2" class aw

    1.00 1.0000 1.0000 Ls Perlengkapan

    1 M' Pasang Pipa PVC 3" class AW

    1.00 1.2000 1.2000 M' Pipa PVC 3" class AW

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.0810 0.0810 Oh Pekerja

    1.00 0.1350 0.1350 Oh Tukang1.00 0.1350 0.1350 Oh Kepala Tukang

    1.00 0.0041 0.0041 Oh Mandor

    1 M' Pasang Pipa PVC 4" class AW

    1.00 1.2000 1.2000 M' Pipa PVC 4" class AW

    1.00 1.0000 1.0000 Ls Perlengkapan

    1.00 0.0810 0.0810 Oh Pekerja

  • 7/29/2019 Rab Sma & Smp

    50/411

    1.00 0.1350 0.1350 Oh Tukang

    1.00 0.1350 0.1350 Oh Kepala Tukang

    1.00 0.0041 0.0041 Oh Mandor

    1 Ttk 6.00 Instalasi air bersih

    Pekerjaan

    1.00 1.0000 6.0000 M' Pasang Pipa PVC 1/2" class A

    1.00 1.0000 6.0000 M' Pasang Pipa PVC 3/4" class A

    1 Ttk 4.00 Instalasi air kotor dia. 1 1/2"

    Pekerjaan

    1.00 1.0000 4.0000 M' Pasang Pipa PVC 1 1/2" class

    1 Ttk 4.00 Instalasi air kotor dia. 3"

    Pekerjaan

    1.00 1.0000 4.0000 M' Pasang Pipa PVC 3" class AW

    1 Ttk 4.00 Instalasi air kotor dia. 4"

    Pekerjaan1.00 1.0000 4.0000 M' Pasang Pipa PVC 4" class AW

    1 Bh Pasang Kran Air Biasa

    1.00 1.0000 1.0000 Bh Kran Air Biasa

    1.00 0.1000 0.0800 Oh Tukang

    1.00 0.0100 0.1350 Oh Kepala Tukang

    1 Unit Pipa Ventilasi Septictank

    Pekerjaan

    1.00 2.0000 2.0000 M' Pasang Pipa Galvanis 1 1/2"

    1 M' Pasang Pipa Resapan

    Pekerjaan

    1.00 1.0000 1.0000 M' Pasang Pipa PVC 4" class AW

    1 M3 Lapisan Ijuk

    1.00 1.0000 1.0000 M3 Ijuk

    1 Bh Pasang Kitchen Sink

    1.00 1.0000 1.0000 Unit Kitchen Sink

    1 Bh Floor drain

    1.00 0.1000 0.1000 Oh Tukang

    1.00 0.0100 0.0100 Oh Kepala Tukang

    1.00 1.0000 1.0000 Bh Floordrain plastik

    1 Ttk 8.00 Roof drain lengkap pipa saluran air hujan

    1.00 1.0000 1.0000 Bh Roofdrain

    Pekerjaan

    1.00 1.0000 8.0000 M' Pasang Pipa PVC 3" class AW

  • 7/29/2019 Rab Sma & Smp

    51/411

    PEKERJAAN INSTALASI LISTRIK1 Ttk Panel Sub Distribusi

    1 Unit Panel Penerangan, (Ground Tank)

    1.00 1.0000 1.0000 Bh Box Panel Plat

    1.00 3.0000 3.0000 Bh MCB 4A

    1.00 6.0000 6.0000 Bh MCB 6A

    1.00 1.0000 1.0000 Bh MCCB 16A

    1.00 4.0000 4.0000 Bh Tembaga Sisi r

    1.00 1.0000 1.0000 Bh Ampere meter

    1.00 1.0000 1.0000 Bh Volt meter

    1.00 1.0000 1.0000 Bh Ampere - voltage Selector

    1.00 1.0000 1.0000 Bh Pilot lamp

    1.00 1.0000 1.0000 Bh Pilot Lamp Fuse

    1.00 1.0000 1.0000 Bh Rel MCB

    1.00 1.0000 1.0000 Bh Terminal Block

    1.00 2.0000 2.0000 M' Kabel Arde BC 6 mm2

    1.00 1.0000 1.0000 Ls Busbar

    1.00 1.0000 1.0000 Ls Assesories panel (Isolator, Sek

    1.00 1.0000 1.0000 Oh Pelaksana ME

    1.00 2.2500 2.2500 Oh Tukang listrik

    1.00 2.2500 2.2500 Oh Pekerja

    1 Unit Panel Penerangan, (Auditorium)

    1.00 1.0000 1.0000 Bh Box Panel Plat

    1.00 1.0000 1.0000 Bh MCB 25A 3P

    1.00 8.0000 8.0000 Bh MCB 10A

    1.00 5.0000 5.0000 Bh MCB 6A

    1.00 4.0000 4.0000 Bh Tembaga Sisi r

    1.00 1.0000 1.0000 Bh Ampere meter

    1.00 1.0000 1.0000 Bh Volt meter

    1.00 1.0000 1.0000 Bh Ampere - voltage Selector

    1.00 3.0000 3.0000 Bh Pilot lamp

    1.00 3.0000 3.0000 Bh Pilot Lamp Fuse

    1.00 3.0000 3.0000 Bh Rel MCB

    1.00 1.0000 1.0000 Bh Terminal Block

    1.00 2.0000 2.0000 M' Kabel Arde BC 6 mM2

    1.00 1.0000 1.0000 Ls Busbar

    1.00 1.0000 1.0000 Ls Assesories panel (Isolator, Sek

    1.00 1.0000 1.0000 Oh Pelaksana ME

    1.00 2.2500 2.2500 Oh Tukang listrik

    1.00 2.2500 2.2500 Oh Pekerja

    1 Ttk Instalasi Stop Kontak

    1.00 1.0000 1.0000 Bh Stop kontak 500 watt

  • 7/29/2019 Rab Sma & Smp

    52/411

    1.00 1.0000 1.0000 Bh Inbouw Doos

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mm2 ex su

    1.00 3.0000 3.0000 Bh Sok Counduit

    1.00 4.0000 4.0000 M' Fleksibel Pipa conduit1.00 10.0000 10.0000 Bh Klem Pipa

    1.00 0.5500 0.5500 Bh Isolasi

    1.00 0.0040 0.0040 Oh Pelaksana ME

    1.00 0.4330 0.4330 Oh Tukang listrik

    1.00 0.1520 0.1520 Oh Pekerja

    1 Ttk Instalasi Stop kontak AC

    1.00 1.0000 1.0000 Bh Stop kontak 1000 watt

    1.00 1.0000 1.0000 Bh Inbouw Doos

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mM2 ex su

    1.00 3.0000 3.0000 Bh Sok Counduit

    1.00 4.0000 4.0000 M' Fleksibel Pipa conduit

    1.00 10.0000 10.0000 Bh Klem Pipa

    1.00 0.5500 0.5500 Bh Isolasi

    1.00 0.0040 0.0040 Oh Pelaksana ME

    1.00 0.4330 0.4330 Oh Tukang listrik

    1.00 0.1520 0.1520 Oh Pekerja

    1 Ttk Instalasi Saklar Tunggal

    1.00 1.0000 1.0000 Bh Saklar Tunggal

    1.00 1.0000 1.0000 Bh Inbouw Doos

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mM2 ex su

    1.00 3.0000 3.0000 Bh Sok Counduit

    1.00 4.0000 4.0000 M' Fleksibel Pipa conduit

    1.00 10.0000 10.0000 Bh Klem Pipa

    1.00 0.5500 0.5500 Bh Isolasi

    1.00 0.0040 0.0040 Oh Pelaksana ME

    1.00 0.4330 0.4330 Oh Tukang listrik

    1.00 0.1520 0.1520 Oh Pekerja

    1 Ttk Instalasi Saklar Ganda

    1.00 1.0000 1.0000 Bh Saklar Ganda

    1.00 1.0000 1.0000 Bh Inbouw Doos

  • 7/29/2019 Rab Sma & Smp

    53/411

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mM2 ex su

    1.00 3.0000 3.0000 Bh Sok Counduit

    1.00 4.0000 4.0000 M' Fleksibel Pipa conduit

    1.00 10.0000 10.0000 Bh Klem Pipa1.00 0.5500 0.5500 Bh Isolasi

    1.00 0.0040 0.0040 Oh Pelaksana ME

    1.00 0.4330 0.4330 Oh Tukang listrik

    1.00 0.1520 0.1520 Oh Pekerja

    1 Ttk Instalasi Handle Switch

    1.00 1.0000 1.0000 Bh Saklar Handle

    1.00 1.0000 1.0000 Bh Inbouw Doos

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mM2 ex su

    1.00 3.0000 3.0000 Bh Sok Counduit

    1.00 4.0000 4.0000 M' Fleksibel Pipa conduit

    1.00 10.0000 10.0000 Bh Klem Pipa

    1.00 0.5500 0.5500 Bh Isolasi

    1.00 0.0040 0.0040 Oh Pelaksana ME

    1.00 0.4330 0.4330 Oh Tukang listrik

    1.00 0.1520 0.1520 Oh Pekerja

    1 Ttk Instalasi Grid Switch

    1.00 1.0000 1.0000 Bh Grid Switch

    1.00 1.0000 1.0000 Bh Inbouw Doos

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mM2 ex su

    1.00 3.0000 3.0000 Bh Sok Counduit

    1.00 4.0000 4.0000 M' Fleksibel Pipa conduit

    1.00 10.0000 10.0000 Bh Klem Pipa

    1.00 0.5500 0.5500 Bh Isolasi

    1.00 0.0040 0.0040 Oh Pelaksana ME

    1.00 0.4330 0.4330 Oh Tukang listrik

    1.00 0.1520 0.1520 Oh Pekerja

    1 Ttk Instalasi Lampu Recessed Mounted Flourrescent Lig

    1.00 1.0000 1.0000 Bh Lampu Recessed Mounted Fl

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

  • 7/29/2019 Rab Sma & Smp

    54/411

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mM2 ex su

    1.00 3.0000 3.0000 Bh Sok Counduit

    1.00 4.0000 4.0000 M' Fleksibel Pipa conduit

    1.00 10.0000 10.0000 Bh Klem Pipa

    1.00 0.5500 0.5500 Bh Isolasi

    1.00 0.0040 0.0040 Oh Pelaksana ME

    1.00 0.4330 0.4330 Oh Tukang listrik

    1.00 0.1520 0.1520 Oh Pekerja

    1 Ttk Instalasi Lampu Recessed Mounted Flourrescent Lig

    1.00 1.0000 1.0000 Bh Lampu Recessed Mounted Fl

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mM2 ex su

    1.00 3.0000 3.0000 Bh Sok Counduit

    1.00 4.0000 4.0000 M' Fleksibel Pipa conduit

    1.00 10.0000 10.0000 Bh Klem Pipa

    1.00 0.5500 0.5500 Bh Isolasi

    1.00 0.0040 0.0040 Oh Pelaksana ME

    1.00 0.4330 0.4330 Oh Tukang listrik

    1.00 0.1520 0.1520 Oh Pekerja

    1 Ttk Instalasi Lampu Recessed Mounted Flourrescent Lig

    1.00 1.0000 1.0000 Bh Lampu Recessed Mounted Fl

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mM2 ex su

    1.00 3.0000 3.0000 Bh Sok Counduit

    1.00 4.0000 4.0000 M' Fleksibel Pipa conduit

    1.00 10.0000 10.0000 Bh Klem Pipa

    1.00 0.5500 0.5500 Bh Isolasi

    1.00 0.0040 0.0040 Oh Pelaksana ME1.00 0.4330 0.4330 Oh Tukang listrik

    1.00 0.1520 0.1520 Oh Pekerja

    1 Ttk Instalasi Lampu Recessed Mounted Down Light, PLE

    1.00 1.0000 1.0000 Bh Lampu Recessed Mounted D

    1.00 10.0000 10.0000 M' Pipa PVC 3/4" protector kabel

    1.00 1.0000 1.0000 Bh Tee Doos 3 Lubang

    1.00 1.0000 1.0000 Bh Tee Doos 4 Lubang

    1.00 10.0000 10.0000 M' Kabel NYM 3 x 2,5 mM2 ex su

    1.00 3.0000 3.