The Rail Baltic Project in EstoniaState of play

Ado LõhmusDeputy Secretary General

28.09.2015

Page 2: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Some important facts (1)

• A north-south railway route – connecting linkbetween Scandinavia and Western Europe.

• Double-track railway, European standardgauge 1,435 mm, trains powered byelectricity.

• The project is carried out in cooperation withLatvia and Lithuania – joint venture RB Rail.

• Finland and Poland are also involved aspartners.

• Time of completion: 2022-2025.

Page 3: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Some important facts (2)

• Total length of the route – ca. 700kilometres, including ca. 200 in Estonia.

• In Estonia, the route runs through HarjuCounty, Rapla County and Pärnu County.

• Trains take less than an hour to travel fromTallinn to Pärnu and less than two hours toRiga.

• Total cost – 3.6 billion euros, the Estonianpart – ca. 1,1 billion.

Page 4: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Fundamental route choice

• The route – running from Tallinn viaPärnu – has been provided in theResolution of the Government of theRepublic (22.09.2011), approving theNational Plan Estonia 2030+.

• The resolution was preceded by publicdebate and consultations with relatedparties and experts.

Page 5: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Elaboration of route options (1)

Location with regard to:

• inhabited areas (a buffer zone of at least500 metres);

• Natura 2000 areas, protected areas andthe habitats of protected species;

• cemeteries, heritage conservation areasand objects protected under heritageconservation;

Page 6: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Elaboration of route options (2)

• technical suitability of the route;

• expenses and socio-economic impact;

On the basis of the assessment criteria,route options were chosen in case ofwhich the negative impact was thesmallest for all the assessed impacts.

Page 7: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Socio-economic aspects

• Cost-benefit analysis;• Construction costs;• Operational costs;• Maintenance costs• Time-saving (travelers, cargo

transport);• Job creation;• Positive externalities (e.g. reduction of

emissions);• etc.

Page 8: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway
Page 9: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

SEA of county-wide plans

• The preparation of the county-wide plansof Harju, Rapla and Pärnu County wasinitiated by the order of the Governmentof the Republic in 2012.

• SEAs were initiated by each countygoverner.

• Three spatial plans – one comprehensiveSEA.

Page 10: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Parties of the SEA procedure

• Contracting authority (developer):• Ministry of Economics and Communication;• Estonian Technical Surveillance Authority.

• Planning authorities: countygovernments.

• SEA supervisor: Ministry of theEnvironment.

• Planning consultant, SEA expertsgroup, interested groups (municipalities,NGOs governmental agencies etc)

Page 11: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Transboundary SEA

• Estonia as Party of Origin (MoE) sentnotifications (together with the SEAprogramme in English) in August 2013to:• Latvia, Lithuania, Poland and

Finland.

• Latvia indicated its wish to participate inthe SEA procedure.

• Estonia as Affected Party – notificationfrom Latvia

Page 12: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Additional surveys

• Geotechnical study;

• Settlement structure baseline study;

• Cultural heritage study;

• Archeological heritage study;

• Nature surveys;

• Analysis of compensation possibilitiesof potential negative effects to landowners.

Page 13: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Findings – examples

• Historical and archaeologicalmonuments,• e.g. flint age settlements.

• Protected species and habitats,• e.g. capercaillie.

• Elaboration of additional principles ofcompensating the negative effects oflarge-scale national infrastuctureprojects (MoE).

Page 14: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Experiences

• Protected areas – creation of theNabala-Tuhala nature conservationareas.

Page 15: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Nabala 2013 and Nabala 2015

Page 16: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Mitigation measures

• People, e.g.:• noise barriers, exchange of windows;• landscaping;• assuring movement options.

• Important species and habitats:• mitigation measures (e.g. ecoducts,

tunnels, culverts);• compensation measures (e.g. re-plantation

of flora).

Page 17: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway
Page 18: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Compensation measures

• Property, e.g.:• buildings in the neighbouring environment;• value of land plots – dwelling land;

–> compensation (if necessary) pursuantto applicable law.

• Acquisition of land to state – transferand expropriation.

• Analysis of compensation possibilitiesof potential negative effects to theowners of the immovables (Sorainen).

Page 19: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway
Page 20: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Prospective (1)

Timetable ActionJune 2014 Approval of the SEA programme

September 2015

Public displays of the sketches of thespatial plans

October 2015 Approval of spatial plans

December2015

Acceptance of spatial plans

Page 21: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Prospective (2)

Timetable2016

Action

January / february

Publication of the spatial plans and SEA report, including transboundarydocumentation to Latvia

March Supervision of the SEA report (MoE)

March /may

Supervision over preparation of spatialplans

June Adoption of spatial plans

Page 22: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Construction works

• Could begin in 2017-2018 at theearliest.

• The objective is to finish most of thework by 2022.

Page 23: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Rail Baltic 2013

Page 24: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Rail Baltic 2015

Page 25: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Sources used

• The Rail Baltic project web pagehttp://www.railbaltic.info/en/

• The Scoping Report for the Rail BalticSEA (06.06.2014)

• Rail Baltic Feasibility Study (2011)http://tja.ee/rail-baltica-tasuvusanaluusi-tulemused/?highlight=aecom

• Maps – Ministry of Economic Affairsand Communications

Page 26: Rail Baltic Estonia - UNECE · The Rail Baltic Project in Estonia State of play Ado Lõhmus Deputy Secretary General 28.09.2015. Some important facts (1) • A north-south railway

Thank you!