Upload
trantuyen
View
213
Download
0
Embed Size (px)
Citation preview
Real Time Contingency Analysis Practice at the Ontario Grid
Control Centre
Yinhua Guo Jeff Penrice Vivian Cheuk
Ontario Grid Control Centre
Hydro One
1
Hydro One Power System
• Major Transmission Company in Ontario
– 97% of Ontario transmission network, 29,000km high voltage circuits
– Interconnect with New York, Michigan, Minnesota, Manitoba, and Quebec (asynchronous)
• Largest Distribution Utility in Ontario
– 123,000km low voltage distribution network
– Serving 1.3 million rural customers
– Extensive distributed generation (wind & solar)
2
3
Courtesy of WorldAtlas
Hydro One Real Time CA Sequence
• State Estimation (SE): every 30sec.
• Thermal Limit Calculation: limited time ratings
• SPS Basecase: arming status, tripped modules
• Contingency Analysis (CA): every 3min
– Contingency case redefinition (over 4100 ctgs)
– Extensive SPS simulation
– Contingency case screening (down to ~50 ctgs)
– Full processing for selected ctgs
4
CA Redefinition
• Dynamically Expand CA Outages at CB Level
• Simulating Protective Relay Actions
– Interlock bypass switches considered
• Transfer Trip for LEO Protection
• SPS Remedial Actions Incorporated
• Cascading Outages: iterative simulations for interactions among SPS, LEO, overload, 59/27 voltage relays
5
CA Redefinition
- Example of interlock bypassing & cascading
6
SPS in Ontario Power System
• Rely Heavily on Special Protection Systems
– Stability concern, thermal limit, voltage violation
– ~400 modules, ~600 signals, ~3600 control actions
• SPS Remedial Action Examples
– Generation/load rejection
– Generation/HVDC runback
– Breaker (group) trip/close
– Equipment (group) rejection
– Capacitor/reactor switching
7
SPS Simulation in CA
• SPS Contingency Detection Logic
– Status/topology based
– Analog value based
– Protective relay trip signals
• Arming and Conditional Arming
– Selection and blocking switches
– Trip supervision (voltage, status)
– Staged tripping
– Arming from OGCC and from IESO
– Selection from plant/station
8
Transformer 2pu Protection
– Over current based: I > 2*I_rated
– Staged tripping of loads in 4.5”, 7.5”, 9.5”
9
Line Backup Protection
– Not the classic zone 3 remote backup relay
– Loss of transfer trip communication on DESN
– Transformer back feeding
10
CA Limits & Monitoring
• CA Branch Limit Violations
– Transformer/overhead line/cable thermal limits calculation in real time: IEEE standard based and expanded
– 15min or 2hr LTR used for CA monitoring
• CA Voltage Violations
• Transformer Back-feeding Condition
• CA Causing Islands
11
Control Action Cancellation
• Manual Control Actions Developed
– Control action type CTG pre-defined for target CTG: with control actions reverted
– Enabled when target CTG cause violation
– Cancel control action when violations disappear for control action type CTG
• SPS Arming/Disarming Decision
– Target CTG cause violations -> arm SPS
– Control action type CTG with SPS disabled, when no more violations -> disarm SPS
12
Detailed CA Post Flow
• CA Post Contingency Detailed Solution
– CA reports ctg violations/warnings only
– Postflow shows full CA solution for specified ctg
– Results shown on both tabular and one-lines
– Run in STNET, access from RTCA, STNET, STCA
• Different from Applying Ctg to Basecase
– Monitored limits: norm vs. emer, cont. vs. 15min
– Post ctg protective relay and SPS actions
13
14
CA Solution Validation
• Verification of CA Solutions
– SE solution against SCADA measured values
– CA solution against SE/power flow solution
– Pre-outage CA solution against post-outage system state (real time or DTS Replay)
• CA Case Coverage
– Missing CA case definition? => monthly check
– Screen masking? =>periodical comparison of CA results with/without screening (off-line)
15
16
CA Setup & Maintenance
• Solution Algorithms & Options
– Full Newton method (auto-enable)
– Fast Decoupled (default)
– MW only solution
– Separate control options for base and ctg cases
• Tuning & Trouble Shooting
– Model & solution must match system response
– Application parameters tuning
– Identifying ctg case causing crashing
17
Performance Monitoring
• CA Solution Quality and Availability
– Invalid basecase
– Solution with extreme voltage (too high/low)
– Unsolved contingency cases
– Run every 3 minutes
• Monitoring Procedures and Tools
– Shift control engineer/officer (7x24), issuing tickets
– Application staff, 2nd level support
– Watchdog application, running in real time
18
19