Upload
vuongnhan
View
219
Download
0
Embed Size (px)
Citation preview
remote projects
remoteprojects
REMOTE PROJECTS CAPABILITY2
coNstrUctIoNoF tWo WAtertANKsoNsLoW, WA
REMOTE PROJECTS CAPABILITY 3
A large number of projects each year are completed outside of capital cities in remote locations throughout Australia as well as overseas. SRG are well equipped to undertake projects wherever the location - our proven track record and experience in remote areas, as well as our focus on safety, quality and environment ensures SRG are the right people for the job.
We highly value the relationships we build with our clients and we seek to deliver first class results to all of our projects - no matter where they are located. The repeat business we receive is a testament to the value, performance and quality we deliver. We like to work closely with local suppliers and contractors near to the project location. We source local labour wherever possible.
safety, quality, environment
Safety, Quality and the Environment are paramount to SRG. We believe that responsible health and safety management as well as superior health and safety performance is integral to an efficient and successful project. Being a customer focused organisation with an intense desire to be the best in
our field, SRG operates and complies with the requirements of the following Quality Management, Environmental Management and Occupational Health & Safety Management Systems.
services
Post-tensioning
Ground anchors
Dam strengthening
Bridge construction
Slipform construction
Heavy lifting and load handling
Retaining walls
Civil contracting
Remedial works
Drill and Blast
Geotechnical
occupational Health & safety management system
AS/NZS 4801:2001
OHSAS 18001
quality management system
ISO 9001:2008
environmental management system
AS/NZS ISO 14001:2004
We focus on delivering high quality work in a safe and sustainable manner to the benefit of the project, client and community. SRG has gained Federal Safety Commission accreditation and is also a founding member of the Post-Tensioning Institute of Australia (PTIA).
SRG is a well established professional engineering and
contracting operation with over 50 years experience.
We are currently operating from offices throughout
Australia as well as Hong Kong and the Middle East.
REMOTE PROJECTS CAPABILITY4
Warramboo Bridge & tunnel Project
remote projecteXperIeNce
SRG were contracted to undertake the construction of a new bridge and concrete arch structure on the North West Coastal Highway at the Mesa A Mine Site, which is situated approximately 1,140km north of Perth in Western Australia.
Mobilising to this remote site required a great deal of organisation to ensure the works could commence on time. SRG’s experience in this field ensured the mobilisation was completed smoothly. Extra support from head office was utilised during the initial stages to ensure the project commenced as planned. Detailed and realistic programming of the works was essential for the success of this project.
Personnel from Perth and Sydney were utilised on a FIFO basis. The process to get personnel inducted and mobilised to site took approximately three weeks due to inductions, training, VOC’s etc. Managing a FIFO project in a mine site environment is extremely demanding.
Safety is always the number one priority for SRG. Site based inspections, ‘Take Five’s’ and a strong focus on the pre-starts and tool box talks, were all paramount on this site.
Numerous local suppliers were utilised from nearby Karratha for this project including personnel for scaffolding, specialist cutting and also crane hire.
location: MESA A Mine, Pannawonica, Western Australia
client: Rio Tinto Iron Ore
year: 2011 - 2012
scope: Construction of a new 3 span bridge and separate arch structure
5REMOTE PROJECTS CAPABILITY
Wellington Dam is located approximately 200kms south of Perth. SRG formed part of the Wellington Dam Alliance and completed the remedial works on this project to strengthen the existing concrete gravity structure with high capacity ground anchors. The anchors were up to 91 strands and equal the current world record capacity of 25,389kN (2,588t) breaking load. To accommodate access for long term monitoring an access bridge was constructed across the crest of the dam.
Site works were carried out from January 2009 until June 2011. SRG’s experienced team of Project Managers, Site Engineers, Superintendent and Leading Hands were all relocated to nearby Bunbury. SRG utilised some of their experienced labourers but also sourced local labour from nearby Bunbury to work on the project. Numerous local suppliers were also utilised for the project.
The Alliance was nominated for a Worksafe Safety Award for the engineering of a strand cutting module. A strong focus was placed on the site inductions and the philosophy of “working above the line” in relation to the hierarchy of control.
location: Collie, Western Australia
client: Water Corporation of Western Australia
year: 2010 - 2011
scope: Design, Spillway Bridge Construction, Roadworks, Drilling, Fabricate and Install Permanent Ground Anchors, Gallery Drainage Works
Wellington Dam strengthening Works
REMOTE PROJECTS CAPABILITY6
catagunya Dam restoration
remote projecteXperIeNce
Catagunya Dam is owned and operated by Hydro Tasmania and is located in central Tasmania, approximately 100 km’s northwest from Hobart.
The works incorporated 92 No. 91 strand vertical anchors up to 77.8m long, embedded up to 30m into hard dolerite rock below the dam. The 53 spillway anchors are located 8.5m below the crest on the 56 degree slope and the remaining 39 in the abutments.
The anchoring works commenced in January 2009 and were completed in June 2010. SRG’s experienced team of Project Managers, Site Engineers, Superintendent and Leading Hands were all relocated to New Norfolk, over an hours drive from site. SRG utilised some of their experienced labourers as well as locally sourced labour from the surrounding areas to work on the project. Numerous local suppliers were utilised for the project.
The Catagunya site team aimed to raise the bar from the high standard they had set at the previous dam project. The Catagunya team focused on the areas of skills and training of personnel.
Training was conducted during toolbox talks at regular intervals on site for all employees, covering each aspect of the project from mobilisation, fabrication, installation, stressing, grouting, demobilisation and first aid.
The site team also created a safe system of racking inside the shipping containers, ensuring that each piece of equipment was secured and could not move during transportation. This reduced the hazard of equipment damage and streamlined the mobilisation process, as each item was easily removed without the risk of injuries to employees.
location: Central Tasmania
client: Hydro Tasmania
year: 2009 - 2010
scope: Manufacture and installation of the world’s highest capacity ground anchors, with breaking loads exceeding 25,389kN (2,588t)
7REMOTE PROJECTS CAPABILITY
SRG were contracted to undertake the strengthening of the Tinaroo Falls Dam by anchoring the existing concrete gravity structure into the foundation bedrock using BBR VT CONA CMG technology.
Tinaroo Falls Dam is owned and operated by SunWater Limited and is located in far north Queensland on the Baron River, approximately 1 hour drive inland from Cairns.
SRG’s experience and organisation ensured mobilisation was completed smoothly and works could commence on time. Detailed and realistic programming of the works was essential for the success of this project.
In a first for SRG, at the request of the client, SRG tendered and was awarded the role of main contractor for the project. In addition to the anchoring works the scope included the provision of a bridge access system over the spillway, concrete coring and insitu
concrete works for the 1,250mm diameter anchor head blocks and pits, and drilling works for the anchors.
The project was successfully completed in 2010, with the SRG and SunWater team extremely satisfied with the project and the safety, budget and programme goals all being achieved.
location: Tinaroo, Queensland
client: SunWater Limited
year: 2009 - 2010
scope: Design, manufacture and installatin of permanent ground anchors. Construction of a 70m long bridge access system over the spillway. Concrete coring and insitu concrete construction works for the anchor head blocks and pits.
tinaroo falls Dam
REMOTE PROJECTS CAPABILITY8
capel river Bridge
remote projecteXperIeNce
SRG were contracted to fully construct a new bridge over the Capel River. The 6 span, 72m long Mallokup Road bridge is located approximately 200km’s south of Perth and spans over the Capel River.
The project commenced in November 2007 and was completed in June 2008. SRG utilised some of their experienced labourers and also sourced local labour from the surrounding areas to work on the project. Local suppliers for backfill, rock pitching and concrete were also utilised for the project.
The specialist piling equipment and machinery was mobilised from Perth to site and set up in approximately three days ready for the commencement of piling works.
Separate office, storage containers and amenities were set up within a compound close to the site for the project team and subcontractors.
location: Capel, Western Australia
client: Main Roads Western Australia
year: 2007 - 2008
scope: Construction of a new bridge over the Capel River
9REMOTE PROJECTS CAPABILITY
SRG were engaged to provide heavy lifting services for the erection of a Prilling Skirt as part of the construction of a new ammonium nitrate plant. The new plant is part of an expansion program by asset owner Dyno Nobel Asia Pacific and is located in Moranbah Queensland, which is inland between Rockhampton and Mackay in northern Queensland.
The project’s construction team, an Alliance Joint Venture between United Group Ltd, Bilfinger Berger Services and BGC Contracting, planned the construction of the tower and skirt utilising the SRG’s strand lifting technology.
The complex lifting and Prill Skirt assembly process was completed over a period of approximately four months and deemed a highly successful operation, with the project’s Construction Superintendent Mr John Roberts commenting “I want to thank you (SRG) for your help and input with the planning of the Prill
Skirt assembly into the Prill Tower. This was a very complex and critical part of our project. It was essential that the erection of the skirt was completed without delays, with no safety concerns and that the 160 tonnes of suspended material was fully controlled at all times, with a large safety factor allowed for on all the lifting and lowering procedures. ..... it has been a very successful operation for the project and we will use SRG again in future when the need arises.”
location: Moranbah, Queensland
client: Dyno Nobel Asia Pacific
year: 2011
scope: Heavy Lifting of a 160 tonne Prill Skirt, 70m high
Prill toWer Heavy lift
REMOTE PROJECTS CAPABILITY10
roseires Dam Heightening Project
remote projecteXperIeNce
Roseires Dam is in the Republic of Sudan, in the Blue Nile State on the Blue Nile River, near the town of Ad Damazin, 550km south east of Khartoum, seven hours by car.
The upgrade heightened the dam by 10 metres which stretches the embankments by a total of 11.6km. On completion the dam capacity has increased from 3.0 billion cubic metres to 7.40 billion cubic metres.
SRG were subcontracted by a Chinese Joint Venture, CCMDJV, to supply and install the dam anchors for the project.
With the dam height raised from 68 to 78 metres and the spillway buttress widened, anchors were installed to strengthen the dam so that it can cope with the additional load due to increased dam capacity.
SRG mobilised their project team as well as all equipment required to perform the works within one month. The crew was made up of Project Management, Engineers
and Supervisors from the Australian operations, post-tensioning technicians from SRG’s Middle East branch as well as local Sudanese labourers.
Undaunted by the remoteness and political instability, the site team worked an eight week on, two week off roster over seven months in a testing environment to deliver another successful project for SRG.
location: Ad Damazin, Republic of Sudan
client: Republic of Sudan Dams Implementation Unit
year: 2012
scope: Manufacture, transport, install, grout, stress, monitor and cap 5506, 1206 and 806 permanent anchors
11REMOTE PROJECTS CAPABILITY
SRG were contracted to strengthen four bridges (Beebingarra, Petemarer, Tabba Tabba and Pardoo Creeks) on the Great Northern Highway, up to 110km north of Port Hedland.
The bridges range from 64.5m to 102m in length and are approximately 40 years old. The bridges were showing signs of fatigue cracking and failed approach slabs due to the high proportion of road trains and oversized loads using the bridges.
They were completed one-half at a time to allow the traffic to continue to travel on the major highway during the construction period. Challenges faced included the management of the heavy/oversized traffic on site, tropical cyclones, availability and management of subcontractors in a remote location, significant concrete logistical challenges (large deck pours were poured at night with large travel times) and an over friendly local fly population.
The nine month project commenced in July 2013 and was completed one month ahead of schedule.
location: Pilbara, Western Australia
client: Main Roads Western Australia
year: 2013-2014
scope: Bridge strengthening; concrete deck overlay (250mm), new approach slabs, expansion joints, guardrail and earthworks to tie the existing road surface in with the raised bridge level.
Pilbara Bridges
REMOTE PROJECTS CAPABILITY12
mid-West Bridge
remote projecteXperIeNce
SRG were engaged by Main Roads Western Australia to refurbish four bridges for safety and maintenance cost reasons. These were located in close proximity to the townships of Geraldton, Coorow and Eneabba in the Mid West region.
The existing guardrail was upgraded and significantly extended with X Tension 350 end terminals installed to provide impact protection to the public. Abutment extensions were added to accommodate the new approach slabs. These were installed to ensure a smooth transition onto the bridges and to save significant costs in maintaining these approaches.
The two bridges near Eneabba were located on the busy Northwest Coastal Highway (NWCH) and had to be
installed in halves, with a temporary steel safety barrier used to provide protection to the public and workers on site.
location: Mid West Region Western Australia
client: Main Roads Western Australia
year: 2013
scope: Bridge refurbishment, new abutments, approach slabs and guardrail replacement
13REMOTE PROJECTS CAPABILITY
SRG were engaged by the Water Corporation of WA for the design and construction of two 5 mega litre water storage tanks as part of the Onslow town water scheme.
This project included the full management of the design and design review process including managing all consultants.
SRG were also responsible for all site earthworks including temporary and permanent roads, sourcing, placing and compacting 12,000m3 of select fill and placement and subsequent removal of 30,000m3 of material for preloading to achieve compaction.
Other responsibilites on this project included:
• Construction of complex reinforced
(post-tensioned) concrete tanks• Construction of approximately
4.5km of access roads and hard stands
• Traffic management• Management of community
relations• Management of subcontractors and
suppliers• Earthworks settlement monitoring
systems
location: Onslow, Western Australia
client: Water Corporation Western Australia
year: 2014-2015
scope: Design and construction of two 5 mega litre water storage tanks.
onslow Water tanks
REMOTE PROJECTS CAPABILITY14
location Laanecoorie, Victoria
client Goulburn-Murray Water
year 2008 - 2009
scope Manufacture and installation of permanent ground anchors
laanecoorie Dam training Wall
location Nagambie, Victoria
client Goulburn-Murray Water
year 2008
scope Replacement of defective anchors including drilling and permanent anchor installation
goulBurn Weir ancHor rePlacement
location Harvey, Western Australia
client Leighton Contractors
year 2001
scope Design, supply & operation of heavy lifting system
location Nhulanbuy, Northern Territory
client Nabalco
year 2000
scope Slipform construction of Silo
gove siloPaDDington golD navajo unDerPass
location Kalgoorlie, Western Australia
client Goldfields Creative Concreting
year 2010
scope Post-tensioning services
location Cadia, New South Wales
client Universal Cranes
year 2011
scope PT Bars for stockpile conveyor
compLeted projects
Harvey Dam Heavy lift
caDia east unDergrounD mine
location Darwin, Northern Territory
client Thiess
year 2003 - 2006
scope Multistrand post-tensioning to LNG tank
DarWin lng tank
location Katherine, Northern Territory
client BJB Joint Venture
year 2012
scope Bridge jacking, epoxy injection crack repairs and carbon fibre strengthening
eDitH river rail BriDge rePairs
location Gove, Northern Territory
client Macmahon Contractors
year 2006
scope Ground anchor installation
location Newman, Western Australia
client Barclay Mowlem Construction
year 2003
scope Construction of composite deck bridge
yanDicoogina creek BriDge
rail DuPlication Project
location Karratha, Western Australia
client Macmahon Contractors
year 2005
scope Installation of ground anchors
location Nullagine, Western Australia
client DTMT Constructions
year 2007
scope Ground anchor installation
gove grounD ancHors
clouDBreak mine site
15REMOTE PROJECTS CAPABILITY
location Dampier, Western Australia
client John Holland Pty Ltd
year 2002
scope Drilling and installation of passive pile anchors
DamPier salt jetty
location Wyndham, Western Australia
client Department of Transport
year 2000 - 2001
scope Refurbishment and coating of the wharf substructure
WynDHam jetty refurBisHment
location Bridgetown, Western Australia
client Main Roads WA
year 2004
scope Timber bridge refurbishment & maintenance works
BlackWooD river BriDge
location Geraldton, Western Australia
client Main Roads Western Australia
year 2004
scope Upgrading guardrailing construction of reinforced concrete approach slabs
geralDton BriDges Balley Balley Brook BriDge
location Greenhills, Western Australia
client Main Roads Western Australia
year 2009
scope Reinforced concrete overlay
location Collie and Harvey, WA
client Main Roads Western Australia
year 2009
scope Reinforced concrete overlay, approach slabs, expansion joints & guardrail upgrade
BriDges 3850 anD 4827a
location Narambeen, Western Australia
client Main Roads WA
year 2006
scope Bridge demolition, wingwall & headwall construction, & guardrailing
BriDge 4076 rePlacement
location Newman, Western Australia
client BHP Billiton Iron Ore
year 2010
scope Supply, installation and stressing of cable stays
rgP4 neWman HuB conveyor stays
location Port Hedland, Western Australia
client Cargil Salt / Main Roads WA
year 1997
scope Earthworks and soil nailing
reDBank BriDge
location Esperance, Western Australia
client Main Roads WA
year 1997
scope Bridge strengthening works
lort river BriDge strengtHening
Hamersley iron soil staBilisation
location Dampier, Western Australia
client Hamersley Iron
year 1997
scope Soil stabilisation
location Broome, Western Australia
client John Holland Pty Ltd
year 2006
scope Design, drilling, supply & installation of ground anchors
Broome jetty extension ancHors
Issu
e 2
015
/07
AboUtUs We are an Australian complex services company. We solve the challenging and difficult problems that others can’t. Our vision is to make the complex simple for our customers.
We have people working across Australia and the world bringing our unique blend of innovation, precision, technical excellence and safety to every mining and infrastructure project we touch.
Since 1961, we have worked on many of the iconic stadiums, skyscrapers, bridges, dams, structures and mining projects, both here in Australia, and overseas.
That’s because we’re not afraid to challenge what is considered possible.
srglimiteD.com.au
call 1300 775 477 +61 8 9267 5400
Get to KNoW Us At srGLImIted.com.AU
australia / africa / miDDle east / asia Pacific / Hong kong