Renovation, Modernization and Life Time Extension Measures on Steam Turbines

Embed Size (px)

Citation preview

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    1/31

    Siemens AG 2012. All rights reserved.

    Power-Gen India & Central Asia 2012

    Renovation, Modernization and Life TimeExtension Measures on Steam Turbines

    Thorsten Strunk, Siemens Energy &Subrata Kumar Kundu, Siemens Power Engineering Pvt Ltd.

    Siemens AG 2010. All rights reserved.

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    2/31

    Siemens AG 2012. All rights reserved.

    Page 2 April 2012 Power-Gen India & Central Asia 2012

    Content of Presentation

    Contents

    Introduction

    Lifetime Extension Methode

    Modernization Technology

    Upgrade ProductsUpgrade References

    Turbine St ress Limits

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    3/31

    Siemens AG 2012. All rights reserved.

    Page 3 April 2012 Power-Gen India & Central Asia 2012

    Coal

    GasNuclear

    Hydro

    Oil

    Renewable

    2010 12 th PlanSource: Siemens AG

    Installed Capacity(rounded)

    R&M & LE are imperative in order to accommodate

    power demand

    Additional Capacity

    R&M, LEor

    shut down

    160 GW

    160 GW

    94 GW

    94 GW

    68 GW

    68 GW

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    4/31

    Siemens AG 2012. All rights reserved.

    Page 4 April 2012 Power-Gen India & Central Asia 2012

    Improve competitiveness of your plant -Production costs and life cycle costs

    Environmental regulations/Climate change

    Increasing share of renewables

    Ageing fleet Lifetime extension

    Availability and reliability

    Need for more capacity (MW)

    Unstable political boundaries for new powerplant projects

    Steam Plant Modernization

    Main Market Drivers

    2008 2030

    20,300 TWh

    33,000 TWh

    Fossilenergy

    sources

    54%68%

    Gas20%

    Hydro15%

    Hydro15%

    Nuclear15%

    Nuclear15%

    Coal32%

    Coal32%

    Oil2%

    17%17%

    21%

    16%

    13%

    41%

    3%

    6%

    2.3% per year 2)

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    5/31

    Siemens AG 2012. All rights reserved.

    Page 5 April 2012 Power-Gen India & Central Asia 2012

    Content of Presentation

    Contents

    Introduction

    Lifetime Extension Methode

    Modernization Technology

    Upgrade ProductsUpgrade References

    Turbine St ress Limits

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    6/31

    Siemens AG 2012. All rights reserved.

    Page 6 April 2012 Power-Gen India & Central Asia 2012

    Service concept for Turbine Components

    Design Service (NDE, RLA)

    Real Life Time of Component Up To Failure

    OperationalHours

    ComponentFailureProbability

    NDE Non-Destructive Examination

    RLA - Remaining Life Analysis

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    7/31

    Siemens AG 2012. All rights reserved.

    Page 7 April 2012 Power-Gen India & Central Asia 2012

    Lifetime evaluation

    Life Time Assessment by NDTat major outages

    Life Time Extension by Lifetime Assessment (LTA) Operational data evaluation Future operational Scenario Remaining Lifetime Analysis (RLA)

    Extended LifetimeLifetime

    ExtensionDesign Lifetime

    Lifetime Assessment by NDTat major outages

    Repair /Replace

    Components

    OperationalRestriction,

    Limitation

    Modernizationand

    upgradation

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    8/31

    Siemens AG 2012. All rights reserved.

    Page 8 April 2012 Power-Gen India & Central Asia 2012

    Fatigue of major steam turbine components

    HP and IP turbine casings and rotorsLow cycle fatigue due to starts and shutdowns

    Creep damage due to stationary operation

    LP turbine rotor Low cycle fatigue due

    to starts and shutdowns

    IP/LP bypass valve casings Low cycle fatigue due

    to bypass operation

    Main Steam and Reheat turbine valve casingsLow cycle fatigue due to starts and shutdowns

    Creep damage due to stationary operation

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    9/31

    Siemens AG 2012. All rights reserved.

    Page 9 April 2012 Power-Gen India & Central Asia 2012

    Life Time Extension of steam turbine components

    Damage reduction DD and component release forthe further operations based on:

    Updated computational conditions

    Local repair Transient and steady state operational

    conditions adjustmentEvaluation Repair vs. Replace by three steps

    ComponentDamage D

    (Creep + LCF)

    OperationalTime

    Warning Time Point(Outage required)

    D

    Step 1: Lifetimeassessment by NDT

    Step 2: Evaluation ofoperational history

    Step 3: Remaininglifetime analysis

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    10/31

    Siemens AG 2012. All rights reserved.

    Page 10 April 2012 Power-Gen India & Central Asia 2012

    I n v e s t m

    e n

    t

    ReliabilityReliability

    Lifetime

    Reliability

    EfficiencyCapacityFlexibility

    Lifetime

    V a

    l u e

    t o C u s

    t o m e r Inspection/

    Repair

    Component

    Exchange

    Upgrade

    Steam Plant Modernization

    Service Differentiation

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    11/31

    Siemens AG 2012. All rights reserved.

    Page 11 April 2012 Power-Gen India & Central Asia 2012

    -

    Upgrade solutions for fossil and nuclearsteam turbines

    All power output ranges (200-1400 MW)

    HP, IP, LP turbines

    Condenser, Generator and I&C upgrades

    Siemens (incl. KWU), Parsons andWestinghouse designs (incl. license ST)

    Other OEM products

    Continuous R&D investment for technologyimprovements and product range

    enlargementLarge list of references

    > 25 years of experience. More than 270fossil units modernized (64 O-OEM)

    Steam Plant Modernization

    Product Portfolio

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    12/31

    Siemens AG 2012. All rights reserved.

    Page 12 April 2012 Power-Gen India & Central Asia 2012

    Content of Presentation

    Contents

    Introduction

    Lifetime Extension Methode

    Modernization Technology

    Upgrade ProductsUpgrade References

    Turbine St ress Limits

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    13/31

    Siemens AG 2012. All rights reserved.

    Page 13 April 2012 Power-Gen India & Central Asia 2012

    Overview of Key Technologies for Efficiency

    Improvements for Modernization Projects

    State-of-the-art 3DS TM Drum Stage Blading

    3D Blading

    EarlierBlading

    Modern3D

    Blade

    Stage Load

    E f f i c i e n c y

    + 2 %Customer Benefits

    World-class performance

    Wide range of applicationSpecific design for each applicationwithin short delivery timesLong life & high reliability

    Stationary Blades Rotating Blades

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    14/31

    Siemens AG 2012. All rights reserved.

    Page 14 April 2012 Power-Gen India & Central Asia 2012

    Overview of Key Technologies for Efficiency

    Improvements for Modernization Projects

    LP Blading Design Features

    State-of-the-art fully 3D design by

    means of advanced computationalmethodsOptimized last stage blade sizeOptimized LP exhaust areaNew Shrouded L-2, L-1 and

    Freestanding or Shrouded Last StageBlade with Trans- and Supersonic TipSections, 3D-Flow Design

    Customer BenefitsImproved blade efficiency byadvanced 3D blade design

    Increased efficiency by shroudedrotating blades

    Reduced exhaust losses

    LA-0L-0R

    LE-0L-0C

    p1p

    1

    p1p2

    -LA-0L-2R

    LA-0L-1R

    LE-0L-1CLE-0L-2C

    Standardized Stage Package

    CustomizedDesign

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    15/31

    Siemens AG 2012. All rights reserved.

    Page 15 April 2012 Power-Gen India & Central Asia 2012

    Overview of Key Technologies

    LP-Blading Reliability Features

    Customer BenefitsIncreased Reliability and Service Life dueto Reduced Stress Levels and effectiveErosion Protection MeasuresReduction of Maintenance Costs

    Suction of the water filminto interior of guide blade

    Suction of the boundary-flowwater into blade-carrier ring

    Highly effective Erosion ProtectionMeasures based on extensiveExperience and Use of High AlloyMaterials

    Fir Tree Root Design for improvedStrength and Reliability by ResidualStress Application and Control

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    16/31

    Siemens AG 2012. All rights reserved.Page 16 April 2012 Power-Gen India & Central Asia 2012

    Overview of Key Technologies for Efficiency

    Improvements for Modernization Projects

    Optimized Sealing Concept

    Brush Seals inBladepath & Shaft Sealing

    Abradable Coatings inShaft Sealing

    Spring-Backed SealSegments

    Customer BenefitsMinimization of clearancelosses for higher efficiency

    Brush Sealsin BladepathAbradable

    Coatings

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    17/31

    Siemens AG 2012. All rights reserved.Page 17 April 2012 Power-Gen India & Central Asia 2012

    Concepts for Efficiency Improvement

    Technologies

    Blading Technology

    Protection via coatingRetrieve original roughnessApplication of shroudedL-1 standard stageReblading 3DS

    Sealing Technology(Shaft & Blading)

    Improved seal stripsAdvanced segment designAbradable coatingBrush seals

    TE GEIP

    1

    2

    3 4 5 6

    HP LP

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    18/31

    Siemens AG 2012. All rights reserved.Page 18 April 2012 Power-Gen India & Central Asia 2012

    Content of Presentation

    Contents

    Introduction

    Lifetime Extension Methode

    Modernization Technology

    Upgrade Products

    Upgrade References

    Turbine St ress Limits

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    19/31

    Siemens AG 2012. All rights reserved.Page 19 April 2012 Power-Gen India & Central Asia 2012

    Steam Plant Modernization

    Typical Upgrade Scope

    Modernization of HP, IP and LP Turbines, Condenser

    Exchange of bladepath components: Rotor, blading, inner casing

    Newest blading and sealing technology

    Outer casing, auxiliary systems, interfaces to foundation etc remainunchanged

    For Other OEM an upgrade study with adaptation measurement ismandatory

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    20/31

    Siemens AG 2012. All rights reserved.Page 20 April 2012 Power-Gen India & Central Asia 2012

    LP

    IP

    HP

    LP

    IP

    HP

    LP

    IP

    HP

    Turbine

    N30-2x10m

    M30-50

    M30-63

    H30-63

    H30-100

    N30-2x5m

    M30-25

    H30-25

    N30-2x5m

    K-200 IP

    K-200 HP

    KWU 500 MW

    KWU 200 / 210 MW

    LMZ 200 / 210 MW

    Frame

    Products for Mods&Ups Market in India

    principle example

    principle example

    principle example

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    21/31

    Siemens AG 2012. All rights reserved.Page 21 April 2012 Power-Gen India & Central Asia 2012

    Content of Presentation

    Contents

    Introduction

    Lifetime Extension Methode

    Modernization Technology

    Upgrade Products

    Upgrade References

    Turbine St ress Limits

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    22/31

    Siemens AG 2012. All rights reserved.Page 22 April 2012 Power-Gen India & Central Asia 2012

    Upgrade References

    Ibbenbren (Germany) Upgrade of fossil OEM-Turbines & Condensers

    Hard coal-fired HP-IP-LP-LP configuration with approx. 838 MW (after Retrofit)

    Extended upgrade scope: all turbine sections + condenser + bearing

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    23/31

    Siemens AG 2012. All rights reserved.Page 23 April 2012 Power-Gen India & Central Asia 2012

    Upgrade References

    Overview Total Scope

    Offset-halves bearings

    HP IP LP1 LP2

    Reinforced connectionbearing pedestal to foundation

    Condenser 1 Condenser 2

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    24/31

    Siemens AG 2012. All rights reserved.Page 24 April 2012 Power-Gen India & Central Asia 2012

    Performance increase of 86MW(43 green MW due to increased thermal efficiency)

    Up to 260.000t CO 2 reduction p.a.

    All requirements fulfilled for characteristics such as Heat rate

    Swallowing capacity Rotor & Bearing Vibrations Start up and shutdown times Noise Emissions

    Total retrofit time 72 days

    Commissioning without any obstacles and delays

    Upgrade Reference

    Conclusions

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    25/31

    Siemens AG 2012. All rights reserved.Page 25 April 2012 Power-Gen India & Central Asia 2012

    Experiences with Fossil Turbine Modernizations

    Fossil Fleet

    Siemens

    GE

    Alstom

    MHI

    LMZ

    Skoda

    Chinese

    No. of Units Rating (MW)

    278 104GW

    214

    2

    24

    32

    1

    23

    88250

    1200

    6501700

    7120

    120

    4950

    includes Westinghouse and Parsons Steam Turbines

    *

    *

    Experiences with fossil turbine modernizations over the last 20 years

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    26/31

    Siemens AG 2012. All rights reserved.Page 26 April 2012 Power-Gen India & Central Asia 2012

    Upgrade ReferencesKardia, Greece 300 MW LMZ Steam Turbine Upgrade

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    27/31

    Siemens AG 2012. All rights reserved.Page 27 April 2012 Power-Gen India & Central Asia 2012

    Upgrade ReferencesSyrdarinskaya, Uzbekistan 300 MW LMZ Steam Turbine Upgrade

    Scope of the upgrade :

    IP/LP Cylinder: IP section: Installation of a rotor

    cooling system

    LP section: Renewal of the shrunk-on

    disks, including rotating blades and

    diaphragms

    LP Cylinder:

    New rotor, inner casing and blading.

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    28/31

    Siemens AG 2012. All rights reserved.Page 28 April 2012 Power-Gen India & Central Asia 2012

    Upgrade ReferencesLoy Yang Power , Australia 500 MW SIEMENS / KWU Steam Turbine Upgrade

    Awards celebration

    The outage has set an international benchmarkfor outage management and sustainable plantenhancement and has been therefore citedwith two Engineering Excellence Awards.

    Ausindustry Excellence Award for

    Industrial Development

    Victorian Workcover Excellence Award

    for Workplace Practice.

    Customer benefits

    Increased power output by almost 10%to more than 545 MW

    Improved efficiency.

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    29/31

    Siemens AG 2012. All rights reserved.Page 29 April 2012 Power-Gen India & Central Asia 2012

    Improvement of turbine efficiencyHigher load output, GREEN MW

    Lower CO 2 emissionsLower production costs

    Improved profitability

    Improvement of total plant efficiency

    Through boiler and condenser upgradeIncreased mass flow, steam parameters

    Lifetime Extension ageing fleetReduced maintenance costs

    Improvement of availability and reliability

    Improved Operational Flexibility Flex PowerFaster start up/load changes

    Flexible use of lifetime

    Improvement of turbine efficiencyHigher load output, GREEN MW

    Lower CO2

    emissions

    Lower production costs

    Improved profitability

    Improvement of total plant efficiencyThrough boiler and condenser upgrade

    Increased mass flow, steam parameters

    Lifetime Extension ageing fleetReduced maintenance costs

    Improvement of availability and reliability

    Improved Operational Flexibility Flex PowerFaster start up/load changes

    Flexible use of lifetime

    Steam Plant Modernization Fossil Plants

    Customer Benefits

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    30/31

    Siemens AG 2012. All rights reserved.Page 30 April 2012 Power-Gen India & Central Asia 2012

    Siemens AG 2010. All rights reserved.

    Power-Gen India & Central Asia 2012

    Thank Youfor Your Attention!

  • 8/11/2019 Renovation, Modernization and Life Time Extension Measures on Steam Turbines

    31/31

    Siemens AG 2012. All rights reserved.Page 31 April 2012 Power-Gen India & Central Asia 2012

    Disclaimer

    This document contains forward-looking statements and information that is, statements related tofuture, not past, events. These statements may be identified either orally or in writing by words asexpects, anticipates, intends, plans, believes, seeks, estimates, will or words of similarmeaning. Such statements are based on our current expectations and certain assumptions, and are,therefore, subject to certain risks and uncertainties. A variety of factors, many of which are beyondSiemens control, affect its operations, performance, business strategy and results and could causethe actual results, performance or achievements of Siemens worldwide to be materially different fromany future results, performance or achievements that may be expressed or implied by such forward-looking statements. For us, particular uncertainties arise, among others, from changes in generaleconomic and business conditions, changes in currency exchange rates and interest rates,

    introduction of competing products or technologies by other companies, lack of acceptance of newproducts or services by customers targeted by Siemens worldwide, changes in business strategy andvarious other factors. More detailed information about certain of these factors is contained inSiemens filings with the SEC, which are available on the Siemens website, www.siemens.com andon the SECs website, www.sec.gov . Should one or more of these risks or uncertainties materialize,or should underlying assumptions prove incorrect, actual results may vary materially from those

    described in the relevant forward-looking statement as anticipated, believed, estimated, expected,intended, planned or projected. Siemens does not intend or assume any obligation to update or revisethese forward-looking statements in light of developments which differ from those anticipated.

    Trademarks mentioned in this document are the property of Siemens AG, it's affiliates or theirrespective owners.