Restart NSW Regional Water and Waste Water Backlog Program

Briefing of Shortlisted Applicants

16 March 2016

Page 2: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Page 2

Jenny Davis, Executive Director Infrastructure NSW

Glenn George, A/Senior Manager, DPI Water

Sam Samra, Senior Manager, DPI Water

Peter Fragiacomo, Principal Analyst, Department of Industry

Introduction

Page 3: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Probity Adviser

Page 3

Integrity and fairness in the process - all meetings are conducted in the presence of the Probity Advisor.

Any issues of a probity nature arising may be raised directly with the Probity Advisor.

Kevin Williams, OCM

Email [email protected]

Page 4: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Today’s Meeting

The purpose of today’s meeting is to better inform you of the assessment process

To better describe the material required

The objective is to contribute to the quality of detailed submissions

Today is not part of the assessment process

We ask everyone to keep discussions at today’s meeting confidential

Page 4

Page 5: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Background

Funding of up to $110 million is available

… only if the applications meet assessment criteria

71 Projects eligible

45 projects shortlisted

Page 5

Page 6: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Assessment - Project Criteria

Criteria in the Guidelines are unchanged in the Detailed Application Stage:

1. Strategic Assessment

Country Towns Water Supply and Sewerage Scheme.

Demonstrated Council priorities.

2. Economic Assessment

Spreadsheets: Typical Residential Bill Calculator, CBA Toolkit to calculate the Benefit Cost Ratio and a User Guide have been circulated

3. Affordability

4. Project Delivery

Page 7: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Focus in the Detailed Applications

1. Subsidy Limits

2. Positive economic benefits – benefit-cost ratio (BCR) of at least 1 is required, together with a positive net present value (NPV) - Demonstrates good use of Restart funding and value for money

3. Affordability – all life-cycle costs considered

4. Deliverability - risk assessment and management plans, project plans, procurement plan is sound

Page 7

Page 8: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

1. Subsidy Limits

Applying the CTWSS rules: ■ Only 1996 Backlog Infrastructure is eligible, including 10% infill and

10% non-residential demand [Note 5 of page 21 of User Guide]

■ Grant funding based on 50% of Capital cost to serve the lower of the 1996 ETs and the Required ET capacity [Item 16 of page 21]

■ Grant funding limited to 50% of $45,000/ET [Note 8 of page 21]

■ For augmentation of existing systems, large LWUs (ie. 2014-15 water & sewerage revenue exceeds $15M) are only eligible for 20% grant funding for the 1996 backlog component [Note 8 of page 21]

Page 9: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

2. Positive Net Economic Benefit

Key Inputs to the TRB Calculator:

Required ET capacity [optional – Item 9A on page 21]

Capital cost [optional - Item 11A on page 21]

LWU funds used [optional – reduces the required TRB, Item 12A on page 21]

Key Outputs: ■ Required TRB [Typical Residential Bill $ per ET] [Item 21, page 21]

■ Approx. Government grant and % Subsidy [Items 17, 18 on page 21]

Page 10: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

2. Positive Net Economic Benefit

Key Inputs to CBA Toolkit [optional, blue items page 17]: TRB [$ per ET]

Project Capacity [ETs]

Population

% Subsidy

Additional Benefits identified

Key Outputs: ■ Benefit Cost Ratio (BCR) – Total Cost

■ Net Present Value (NPV) – Total Cost

Page 11: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

2. Tips for Economic Appraisal A well developed description of project outcomes is required outside

the spreadsheets

As noted on pages 10 to 12 of the User Guide, the LWU may identify additional benefits for:

Productivity Savings, reduced Epidemic Risk, reduced Environmental Damage, Economic Benefits & Social Benefits

Do not double count benefits that have been estimated by the Cost Benefit Analysis Toolkit. Refer to page 10 of User Guide.

Provide a brief statement of how each of the additional benefits was determined with your Detailed Application [page 10 of User Guide].

Page 12: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

3. Affordability – Reliable Estimates and Timing Source of the cost estimate is critical

Asset management plans are important

Is the new infrastructure viable in the future – eg. sufficient user income, is it resilient to changes in demand or technology

The ability to meet ongoing operation, maintenance and renewal costs

Provide evidence that your organisation has the ability to fund and operate the asset over its life, including renewal eg. are you achieving full cost recovery for water supply and sewerage infrastructure – refer to Item 2a of your TBL Performance Reports from DPI Water

Page 12

Page 13: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Project Delivery Plans

Is the project “investment ready” or “construction ready”?

Delivery approach – innovative, efficient

Do you have all the agreements, land, approvals etc. in place?

Provide detailed Project Delivery Plans – target delivery within 5 to 7 years

Provide detailed Risk Assessment and management plans

Page 14: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

More Questions?

DPI Water and INSW will accept questions which must be raised in writing: Please identify questions that you consider unique to your proposal and should remain confidential

Answers to questions will be in writing

Answers (other than confidential project information) will be shared with all applications

Please check that we are using the correct email address

Page 14

Page 15: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Confidential Information

All information provided in the application may be distributed to other parties

Identify any information contained in the application which you consider confidential and provide reasons

Any request made under the Government Information (Public Access) Act 2009 for access to an application, including information marked ‘confidential’, will be determined in accordance with the Act

Page 15

Page 16: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Process Next steps

Detailed applications close 28 April 2016

Regional Independent Assessment panel undertakes a review of all application material and makes recommendations to Infrastructure NSW

Infrastructure NSW submits its recommendations to the Government

Funding decisions are made by the Government

Page 16

Page 17: Restart NSW Regional Water and Waste Water Backlog Program · 2016-03-22 · Restart NSW Regional Water and Waste Water Backlog Program ... Grant funding based on 50% of Capital cost

Contact Details

Everything must be submitted (cc) to [email protected]

DPI Water contact is Glenn George on 0411 449 745 [email protected]

Page 17