ADDENDUM NO. 1
ISSUE DATE: 7/8/2019
This Addendum shall become and form a part of the RFQ for:
RFQ 484-072319 – Bridge Bundle #1 - 2019 Engineering Design Service
NOTE: PLEASE REVIEW CAREFULLY! THERE MAYBE CHANGES TO THE INFORMATION TO BE PROVIDED. FAILURE TO ADHERE TO ANY CHANGES ADDRESSED IN THIS ADDENDUM MAY RESULT IN
DISQUALIFICATION.
In the event of a conflict between previously released information and the information contained herein, the latter shall control. NOTE: A signed acknowledgment of this addendum (this page) MUST be attached to your SUBMITTAL for Phase I. Firm Name Signature Date Typed Name and Title
Georgia Department of Transportation (GDOT) Office of Transportation Services Procurement
One Georgia Center 600 West Peachtree Street, NW
19th Floor Atlanta, Georgia 30308
This Addendum, including all questions and answers, shall become and form a part of the original RFQ package and shall be taken into account when preparing your proposal.
I. Written Questions and Answers
Questions Answers
1.
Can the submittal date be extended?
See Addendum below.
2. Would the Department consider allowing the 4.01 area classes to be utilized by a subconsultant, rather than a prime requirement?
No. The Prime must be prequalified in 3.01 and 4.01a or 4.01b.
3. Where individual projects within the bundle state “In House Road and Bridge”, which services within the scope defined by section 6A through 6J of each contract will the successful consultant be providing?
See Addendum below
4. It is our understanding PI 0016532, 0016533 and 0016530 in Contract 2 are part of the SR 17 Grip corridor project. How does the department intend to deliver the projects under this bridge contract?
The bridge replacement projects PI 0016532, 0016533 and 0016530, are scoped to replace the existing bridges per those project’s justifications statements. Projects programmed as bridge replacement are used to replace bridges in-kind.
Addendum No. 1
RFQ 484- 072319
Page 2 of 24
II. RFQ Section III-Schedule of Events will be deleted and replaced by the attached Schedule of Events.
III. RFQ Exhibit I -1; I -2; I -3; I -5 and 1- 8 are DELETED and REPLACED by the attached Exhibit I -1; I -2; I -3; I -5 and 1- 8
EXHIBIT I-1
Project/Contract
1. Project Number(s): N/A
2. PI Number: 3. County: 4. Description:
0016516 Franklin SR 106 @ MIDDLE FORK BROAD RIVER 2.3 MI S OF CARNESVILLE
0016517 Franklin SR 328 @ GUMLOG CREEK 3.8 MI N OF LAVONIA
0016519 Gwinnett SR 8 @ JACKSON CREEK IN LILBURN
0016523 Jackson I-85 @ CR 229/VALENTINE INDUSTRIAL PKWY NW OF JEFFERSON (IN HOUSE ROAD AND BRIDGE)
0016526 Madison SR 106 @ HUDSON RIVER 3.8 MI N OF POCATALICO
5. Required Area Classes:
Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.
A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:
Number Area Class
3.01 Two-Lane or Multi-lane Rural Roadway Design
PHASE I DATE TIME
a. GDOT issues public advertisement of RFQ-484-072319 6/20/2019 ----------
b. Deadline for submission of written questions and requests for clarification 7/8/2019 2:00 PM
c. Deadline for submission of Statements of Qualifications
8/26/2019 2:00 PM
d. GDOT completes evaluation and issues notification and other information to
finalist firms TBD
PHASE II
e. Deadline for submission of written questions from finalists TBD 2:00 PM
f. Phase II Response of Finalist firms due TBD TBA
Addendum No. 1
RFQ 484- 072319
Page 3 of 24
4.01(a) Minor Bridge Design
or
4.01(b) Minor Bridge Design - CONDITIONAL
B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be
prequalified by GDOT in the area classes listed below:
Number Area Class
1.06(a) NEPA
1.06(b) History
1.06(c) Air Quality
1.06(d) Noise
1.06(e) Ecology
1.06(f) Archaeology
1.06(g) Freshwater Aquatic Surveys
1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)
1.10 Traffic Analysis
3.12 Hydraulic and Hydrological Studies (Roadway)
4.04 Hydraulic and Hydrological Studies (Bridges)
5.01 Land Surveying
5.02 Engineering Surveying
5.08 Overhead/Subsurface Utility Engineering (SUE)
6.01(a) Soil Survey Studies
6.01(b) Geological and Geophysical Studies
6.02 Bridge Foundation Studies
6.05 Hazardous Waste Site Assessment Studies
9.01 Erosion, Sedimentation, and Pollution Control Plan
6. Scope:
The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual.
A. Complete Field Surveys:
1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.
B. Concept Report:
1) Traffic Studies. 2) Cost Estimates. 3) Initial Concept Meeting Preparation and Attendance. 4) PAR Activities. 5) Concept Meeting Preparation and Attendance. 6) Approved Concept Report.
Addendum No. 1
RFQ 484- 072319
Page 4 of 24
7) Concept Design Data Book. 8) Public Involvement Plan (for GDOT’s approval).
C. Environmental Document:
1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History,
Ecology, and Archaeology). 2) NEPA documents.
a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.
3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance. 7) Preparation of a Vegetative Buffer application. 8) Public Involvement (1 possible detour/PIOH). 9) Prepare for and attend the PFPR and FFPR.
D. Preliminary Design:
1) Complete Preliminary Roadway Plans, including but not limited to:
a) Preliminary Bridge Plans. b) Preliminary Signing and Marking Plans. c) Preliminary ESPCP. d) Preliminary Utility Plans. e) Preliminary Staging Plans. f) Drainage Design including MS4, if applicable.
2) Bridge Hydraulic Study. 3) BFI Report. 4) Pavement Evaluation/UST/Soil Survey. 5) Constructability Meeting participation. 6) Cost Estimation with annual updates. 7) Location and Design Report. 8) PFPR participation, report, and responses (all plans sets and other information requested by Engineering
Services).
E. Right-of-Way (ROW) Plans: 1) Prepare ROW plans and coordinate ROW staking. 2) Right of Way revisions during acquisition, as needed.
F. Utilities:
Subsurface Utility Engineering.
G. Final Design:
1) Complete Final Roadway Plans, including but not limited to:
Addendum No. 1
RFQ 484- 072319
Page 5 of 24
a) Final Bridge Plans (LRFD). b) Final Signing and Marking Plans. c) Final ESPCP. d) Final Utility Plans. e) Final Staging Plans. f) Final Drainage Design including MS4, if applicable.
2) FFPR participation, report, and responses(all plans sets and other information requested by Engineering
Services). 3) Corrected FFPR Plans. 4) CES Final cost estimate. 5) Final PS&E Package. 6) Amendments & Revisions.
H. Construction:
1) Use on Construction Revisions. 2) Review Shop Drawings.
I. Quality Control/Quality Assurance Reviews for all deliverables.
J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings
may be required to resolve major project issues).
K. For PI 0016523 (Jackson County), I-85 @ CR 229/VALENTINE INDUSTRIAL PKWY, NW OF (IN HOUSE ROAD AND BRIDGE) the Consultant shall provide the following: A. Complete Field Surveys:
1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.
B. Environmental Document:
1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).
2) NEPA documents.
a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.
3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance.
C. Utilities:
Subsurface Utility Engineering. D. Quality Control/Quality Assurance Reviews for all deliverables. E. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional
meetings may be required to resolve major project issues).
Addendum No. 1
RFQ 484- 072319
Page 6 of 24
7. Related Key Team Leaders for Exhibit I-1 Contract 1:
A. Roadway Design. B. Bridge Design. C. NEPA Lead.
8. The following milestone dates are proposed: PI-0016516, PI-0016523, & PI-0016526
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Limited Concept report submittal – Q1 FY 21 (about 4 months duration). C. PFPR – Q3 FY 21 D. FFPR – Q1 FY 22. E. Let Contract – Q2 FY 22. PI-0016517 & PI-0016519
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.
Addendum No. 1
RFQ 484- 072319
Page 7 of 24
EXHIBIT I-2
Project/Contract 2
1. Project Number(s): N/A
2. PI Number: 3. County: 4. Description:
0016524 Lincoln SR 43 @ LLOYD CREEK 7 MI SW OF LINCOLNTON
0016525 Lincoln SR 220 @ SOAP CREEK 5 MI E OF LINCOLNTON
0016532 Wilkes SR 17 @ ROCK CREEK 2.3 MI N OF WASHINGTON
0016533 Wilkes SR 17 @ BROAD RIVER OVERFLOW 7.3 MI N OF TIGNALL (IN HOUSE ROAD AND BRIDGE)
0016530 Elbert/Wilkes SR 17 @ BROAD RIVER 7.5 MI N OF TIGNALL (IN HOUSE ROAD AND BRIDGE)
5. Required Area Classes:
Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.
A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:
Number Area Class
3.01 Two-Lane or Multi-lane Rural Roadway Design
4.01(a) Minor Bridge Design
or
4.01(b) Minor Bridge Design - CONDITIONAL
B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be prequalified by GDOT in the area classes listed below:
Number Area Class
1.06(a) NEPA
1.06(b) History
1.06(c) Air Quality
1.06(d) Noise
1.06(e) Ecology
1.06(f) Archaeology
1.06(g) Freshwater Aquatic Surveys
1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)
1.10 Traffic Analysis
3.12 Hydraulic and Hydrological Studies (Roadway)
4.04 Hydraulic and Hydrological Studies (Bridges)
5.01 Land Surveying
5.02 Engineering Surveying
5.08 Overhead/Subsurface Utility Engineering (SUE)
6.01(a) Soil Survey Studies
6.01(b) Geological and Geophysical Studies
6.02 Bridge Foundation Studies
Addendum No. 1
RFQ 484- 072319
Page 8 of 24
6.05 Hazardous Waste Site Assessment Studies
9.01 Erosion, Sedimentation, and Pollution Control Plan
6. Scope:
The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual. A. Complete Field Surveys:
1) Provide Survey Control Package.
2) Provide Inroads Survey Database.
3) Staking for Bridge Site Inspection.
4) Staking for ROW acquisition.
B. Concept Report:
1) Traffic Studies.
2) Cost Estimates.
3) Initial Concept Meeting Preparation and Attendance.
4) PAR Activities.
5) Concept Meeting Preparation and Attendance.
6) Approved Concept Report.
7) Concept Design Data Book.
8) Public Involvement Plan (for GDOT’s approval).
C. Environmental Document:
1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History,
Ecology, and Archaeology). 2) NEPA documents.
1) Categorical Exclusion.
2) EA/FONSI.
3) Section 4f coordination.
4) One NEPA document reevaluation for Construction.
3) Preparation of a Section 404 Permit application.
4) Section 408 Coordination.
5) Aquatic Survey.
6) Stream Buffer Variance.
7) Preparation of a Vegetative Buffer application.
8) Public Involvement (1 possible detour/PIOH).
9) Prepare for and attend the PFPR and FFPR.
D. Preliminary Design:
Addendum No. 1
RFQ 484- 072319
Page 9 of 24
1) Complete Preliminary Roadway Plans, including but not limited to:
2) Preliminary Bridge Plans.
3) Preliminary Signing and Marking Plans.
4) Preliminary ESPCP.
5) Preliminary Utility Plans.
6) Preliminary Staging Plans.
7) Drainage Design including MS4, if applicable.
8) Bridge Hydraulic Study.
9) BFI Report.
10) Pavement Evaluation/UST/Soil Survey.
11) Constructability Meeting participation.
12) Cost Estimation with annual updates.
13) Location and Design Report.
14) PFPR participation, report, and responses (all plans sets and other information requested by Engineering
Services).
E. Right-of-Way (ROW) Plans:
1) Prepare ROW plans and coordinate ROW staking.
2) Right of Way revisions during acquisition, as needed.
F. Utilities:
Subsurface Utility Engineering.
G. Final Design:
1) Complete Final Roadway Plans, including but not limited to:
1) Final Bridge Plans (LRFD).
2) Final Signing and Marking Plans.
3) Final ESPCP.
4) Final Utility Plans.
5) Final Staging Plans.
6) Final Drainage Design including MS4, if applicable.
2) FFPR participation , report, and responses(all plans sets and other information requested by Engineering
Services).
3) Corrected FFPR Plans.
4) CES Final cost estimate.
5) Final PS&E Package.
6) Amendments & Revisions.
H. Construction:
1) Use on Construction Revisions.
2) Review Shop Drawings.
I. Quality Control/Quality Assurance Reviews for all deliverables.
Addendum No. 1
RFQ 484- 072319
Page 10 of 24
J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings
may be required to resolve major project issues).
K. For PI numbers 0016533 and 0016530 (Wilkesand Elbert/Wilkes County), SR 17 @ BROAD RIVER OVERFLOW
7.3 MI N OF TIGNALL (IN HOUSE ROAD AND BRIDGE) and SR 17 @ BROAD RIVER 7.5 MI N OF TIGNALL
(IN HOUSE ROAD AND BRIDGE) the Consultant shall provide the following:
A. Complete Field Surveys:
1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.
B. Environmental Document:
1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).
2) NEPA documents.
a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.
3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance.
C. Utilities:
Subsurface Utility Engineering. D. Quality Control/Quality Assurance Reviews for all deliverables. E. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional
meetings may be required to resolve major project issues).
7. Related Key Team Leaders per Exhibit I-2, Contract 2:
A. Roadway Design. B. Bridge Design. C. NEPA Lead.
8. The following milestone dates are proposed:
PI-0016524
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Limited Concept report submittal – Q1 FY 21 (about 4 months duration). C. PFPR – Q3 FY 21. D. FFPR – Q1 FY 22. E. Let Contract – Q2 FY 22.
PI-0016530, PI-0016532, & PI-0016533
Addendum No. 1
RFQ 484- 072319
Page 11 of 24
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.
PI-0016525
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q1 FY 22. C. PFPR – Q3 FY 22. D. FFPR – Q4 FY 23. E. Let Contract – Q1 FY 24.
Addendum No. 1
RFQ 484- 072319
Page 12 of 24
EXHIBIT I-3
Project/Contract
1. Project Number(s): N/A
2. PI Number: 3. County: 4. Description:
0016504 Atkinson SR 31 @ RED BLUFF CREEK TRIB 9 MI S OF PEARSON
0016505 Atkinson SR 31 @ RED BLUFF CREEK 8 MI S OF PEARSON
0016510 Clinch SR 89/US 441 @ CYPRESS CREEK 1.6 MI S OF FARGO
0016514 Echols SR 89/US 441 @ LITTLE SUWANNEE CREEK 8 MIL S OF FARGO
0016531 Turner CR 26/ BETHEL ROAD @ HAT CREEK 6.7 MI SE OF SYCAMORE (IN HOUSE BRIDGE)
5. Required Area Classes:
Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.
A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:
Number Area Class
3.01 Two-Lane or Multi-lane Rural Roadway Design
4.01(a) Minor Bridge Design
or
4.01(b) Minor Bridge Design - CONDITIONAL
B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be
prequalified by GDOT in the area classes listed below:
Number Area Class
1.06(a) NEPA
1.06(b) History
1.06(c) Air Quality
1.06(d) Noise
1.06(e) Ecology
1.06(f) Archaeology
1.06(g) Freshwater Aquatic Surveys
1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)
1.10 Traffic Analysis
3.12 Hydraulic and Hydrological Studies (Roadway)
4.04 Hydraulic and Hydrological Studies (Bridges)
5.01 Land Surveying
5.02 Engineering Surveying
5.08 Overhead/Subsurface Utility Engineering (SUE)
6.01(a) Soil Survey Studies
6.01(b) Geological and Geophysical Studies
6.02 Bridge Foundation Studies
6.05 Hazardous Waste Site Assessment Studies
9.01 Erosion, Sedimentation, and Pollution Control Plan
Addendum No. 1
RFQ 484- 072319
Page 13 of 24
6. Scope:
The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual.
A. Complete Field Surveys:
1) Provide Survey Control Package.
2) Provide Inroads Survey Database.
3) Staking for Bridge Site Inspection.
4) Staking for ROW acquisition.
B. Concept Report:
1) Traffic Studies.
2) Cost Estimates.
3) Initial Concept Meeting Preparation and Attendance.
4) PAR Activities.
5) Concept Meeting Preparation and Attendance.
6) Approved Concept Report.
7) Concept Design Data Book.
8) Public Involvement Plan (for GDOT’s approval).
C. Environmental Document:
1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).
2) NEPA documents.
a) Categorical Exclusion.
b) EA/FONSI.
c) Section 4f coordination.
d) One NEPA document reevaluation for Construction.
3) Preparation of a Section 404 Permit application.
4) Section 408 Coordination.
5) Aquatic Survey.
6) Stream Buffer Variance.
7) Preparation of a Vegetative Buffer application.
8) Public Involvement (1 possible detour/PIOH).
9) Prepare for and attend the PFPR and FFPR.
D. Preliminary Design:
Addendum No. 1
RFQ 484- 072319
Page 14 of 24
1) Complete Preliminary Roadway Plans, including but not limited to:
a) Preliminary Bridge Plans.
b) Preliminary Signing and Marking Plans.
c) Preliminary ESPCP.
d) Preliminary Utility Plans.
e) Preliminary Staging Plans.
f) Drainage Design including MS4, if applicable.
2) Bridge Hydraulic Study.
3) BFI Report.
4) Pavement Evaluation/UST/Soil Survey.
5) Constructability Meeting participation.
6) Cost Estimation with annual updates.
7) Location and Design Report.
8) PFPR participation, report, and responses (all plans sets and other information requested by Engineering
Services).
E. Right-of-Way (ROW) Plans:
1) Prepare ROW plans and coordinate ROW staking.
2) Right of Way revisions during acquisition, as needed.
F. Utilities:
Subsurface Utility Engineering.
G. Final Design:
1) Complete Final Roadway Plans, including but not limited to:
a) Final Bridge Plans (LRFD).
b) Final Signing and Marking Plans.
c) Final ESPCP.
d) Final Utility Plans.
e) Final Staging Plans.
f) Final Drainage Design including MS4, if applicable.
2) FFPR participation , report, and responses(all plans sets and other information requested by Engineering
Services).
3) Corrected FFPR Plans.
4) CES Final cost estimate.
5) Final PS&E Package.
6) Amendments & Revisions.
H. Construction:
1) Use on Construction Revisions.
2) Review Shop Drawings.
I. Quality Control/Quality Assurance Reviews for all deliverables.
Addendum No. 1
RFQ 484- 072319
Page 15 of 24
J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings
may be required to resolve major project issues).
K. For PI 0016531 (Turner County), CR 26/ BETHEL ROAD @ HAT CREEK 6.7 MI SE OF SYCAMORE (IN HOUSE
BRIDGE) the Consultant will provide all the scope A – J listed above except for the following:
1) Preliminary Bridge Plans 2) Bridge Hydraulic Study. 3) BFI Report. 4) Final Bridge Plans (LRFD). 5) Review Shop Drawings.
7. Related Key Team Leaders per Exhibit I-3, Contract 3:
A. Roadway Design. B. Bridge Design. C. NEPA Lead.
8. The following milestone dates are proposed:
PI-0016531
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Limited Concept report submittal – Q1 FY 21 (about 4 months duration). C. PFPR – Q3 FY 21. D. FFPR – Q1 FY 22. E. Let Contract – Q2 FY 22.
PI-0016504, PI-0016505, PI-0016510, & PI-0016514 A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.
Addendum No. 1
RFQ 484- 072319
Page 16 of 24
EXHIBIT I-5
Project/Contract
1. Project Number(s): N/A
2. PI Number: 3. County: 4. Description:
0016506 Bartow I-75 @ CR 179/CEDAR CREEK ROAD 5.2 MI NW OF WHITE
0016528 Murray SR 2/SR 61 @ SUMAC CREEK 1.6 MI N OF CRANDALL
0016529 Murray SR 61 @ PERRY CREEK 6.3 MI N OF CRANDALL
0016509 Cherokee SR 108 @ SHOAL CREEK 4.5 MI SW OF WALESKA (IN HOUSE ROAD AND BRIDGE)
5. Required Area Classes:
Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.
A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:
Number Area Class
3.01 Two-Lane or Multi-lane Rural Roadway Design
4.01(a) Minor Bridge Design
or
4.01(b) Minor Bridge Design - CONDITIONAL
B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be
prequalified by GDOT in the area classes listed below:
Number Area Class
1.06(a) NEPA
1.06(b) History
1.06(c) Air Quality
1.06(d) Noise
1.06(e) Ecology
1.06(f) Archaeology
1.06(g) Freshwater Aquatic Surveys
1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)
1.10 Traffic Analysis
3.12 Hydraulic and Hydrological Studies (Roadway)
4.04 Hydraulic and Hydrological Studies (Bridges)
5.01 Land Surveying
5.02 Engineering Surveying
5.08 Overhead/Subsurface Utility Engineering (SUE)
6.01(a) Soil Survey Studies
6.01(b) Geological and Geophysical Studies
6.02 Bridge Foundation Studies
6.05 Hazardous Waste Site Assessment Studies
9.01 Erosion, Sedimentation, and Pollution Control Plan
Addendum No. 1
RFQ 484- 072319
Page 17 of 24
6. Scope: The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual.
A. Complete Field Surveys:
1) Provide Survey Control Package.
2) Provide Inroads Survey Database.
3) Staking for Bridge Site Inspection.
4) Staking for ROW acquisition.
B. Concept Report:
1) Traffic Studies.
2) Cost Estimates.
3) Initial Concept Meeting Preparation and Attendance.
4) PAR Activities.
5) Concept Meeting Preparation and Attendance.
6) Approved Concept Report.
7) Concept Design Data Book.
8) Public Involvement Plan (for GDOT’s approval).
C. Environmental Document:
1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History,
Ecology, and Archaeology). 2) NEPA documents.
a) Categorical Exclusion.
b) EA/FONSI.
c) Section 4f coordination.
d) One NEPA document reevaluation for Construction.
3) Preparation of a Section 404 Permit application.
4) Section 408 Coordination.
5) Aquatic Survey.
6) Stream Buffer Variance.
7) Preparation of a Vegetative Buffer application.
8) Public Involvement (1 possible detour/PIOH).
9) Prepare for and attend the PFPR and FFPR.
D. Preliminary Design:
1) Complete Preliminary Roadway Plans, including but not limited to:
a) Preliminary Bridge Plans.
b) Preliminary Signing and Marking Plans.
Addendum No. 1
RFQ 484- 072319
Page 18 of 24
c) Preliminary ESPCP.
d) Preliminary Utility Plans.
e) Preliminary Staging Plans.
f) Drainage Design including MS4, if applicable.
2) Bridge Hydraulic Study.
3) BFI Report.
4) Pavement Evaluation/UST/Soil Survey.
5) Constructability Meeting participation.
6) Cost Estimation with annual updates.
7) Location and Design Report.
8) PFPR participation, report, and responses (all plans sets and other information requested by Engineering
Services).
E. Right-of-Way (ROW) Plans:
1) Prepare ROW plans and coordinate ROW staking.
2) Right of Way revisions during acquisition, as needed.
F. Utilities:
Subsurface Utility Engineering.
G. Final Design:
1) Complete Final Roadway Plans, including but not limited to:
a) Final Bridge Plans (LRFD).
b) Final Signing and Marking Plans.
c) Final ESPCP.
d) Final Utility Plans.
e) Final Staging Plans.
f) Final Drainage Design including MS4, if applicable.
2) FFPR participation , report, and responses(all plans sets and other information requested by Engineering
Services).
3) Corrected FFPR Plans.
4) CES Final cost estimate.
5) Final PS&E Package.
6) Amendments & Revisions.
H. Construction:
1) Use on Construction Revisions.
2) Review Shop Drawings.
I. Quality Control/Quality Assurance Reviews for all deliverables.
J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings
may be required to resolve major project issues).
K. For PI 0016509 (Cherokee County), SR 108 @ SHOAL CREEK 4.5 MI SW OF WALESKA (IN HOUSE ROAD
AND BRIDGE) the Consultant shall provide the following:
A. Complete Field Surveys:
Addendum No. 1
RFQ 484- 072319
Page 19 of 24
1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.
B. Environmental Document:
1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).
2) NEPA documents.
a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.
3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance.
C. Utilities:
Subsurface Utility Engineering. D. Quality Control/Quality Assurance Reviews for all deliverables. E. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional
meetings may be required to resolve major project issues).
7. Related Key Team Leaders per Exhibit I-5, Contract 5:
A. Roadway Design. B. Bridge Design. C. NEPA Lead.
8. The following milestone dates are proposed:
PI-0016529
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Limited Concept report submittal – Q1 FY 21 (about 4 months duration) . C. PFPR – Q3 FY 21. D. FFPR – Q1 FY 22. E. Let Contract – Q2 FY 22. PI-0016509 & PI-0016528
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.
PI-0016506
Addendum No. 1
RFQ 484- 072319
Page 20 of 24
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q1 FY 22. C. PFPR – Q3 FY 22. D. FFPR – Q4 FY 23. E. Let Contract – Q1 FY 24.
Addendum No. 1
RFQ 484- 072319
Page 21 of 24
EXHIBIT I-8
Project/Contract
1. Project Number(s): N/A
2. PI Number: 3. County: 4. Description:
0016508 Chattahoochee SR 520/US 27 @ FIRST DIVISION ROAD 7.5 MI NW OF CUSSETA
0016520 Harris SR 103 @ MOUNTAIN OAK CREEK 5.5 MI SW OF WHITESVILLE (IN HOUSE ROAD AND BRIDGE)
0016521 Harris SR 103 @ HOUSE CREEK 6.5 MI SE OF WEST POINT (IN HOUSE ROAD AND BRIDGE)
0016522 Harris SR 103 @ SAND CREEK 5.5 MI SE OF WEST POINT (IN HOUSE ROAD AND BRIDGE)
0016527 Meriwether SR 362 @ RED OAK CREEK 6 MI NE OF GREENVILLE (IN HOUSE ROAD AND BRIDGE)
5. Required Area Classes:
Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.
A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:
Number Area Class
3.01 Two-Lane or Multi-lane Rural Roadway Design
4.01(a) Minor Bridge Design
or
4.01(b) Minor Bridge Design - CONDITIONAL
B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be
prequalified by GDOT in the area classes listed below:
Number Area Class
1.06(a) NEPA
1.06(b) History
1.06(c) Air Quality
1.06(d) Noise
1.06(e) Ecology
1.06(f) Archaeology
1.06(g) Freshwater Aquatic Surveys
1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)
1.10 Traffic Analysis
3.12 Hydraulic and Hydrological Studies (Roadway)
4.04 Hydraulic and Hydrological Studies (Bridges)
5.01 Land Surveying
5.02 Engineering Surveying
5.08 Overhead/Subsurface Utility Engineering (SUE)
6.01(a) Soil Survey Studies
6.01(b) Geological and Geophysical Studies
Addendum No. 1
RFQ 484- 072319
Page 22 of 24
6.02 Bridge Foundation Studies
6.05 Hazardous Waste Site Assessment Studies
9.01 Erosion, Sedimentation, and Pollution Control Plan
6. Scope:
The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual.
A. Complete Field Surveys:
1) Provide Survey Control Package.
2) Provide Inroads Survey Database.
3) Staking for Bridge Site Inspection.
4) Staking for ROW acquisition.
B. Concept Report:
1) Traffic Studies.
2) Cost Estimates.
3) Initial Concept Meeting Preparation and Attendance.
4) PAR Activities.
5) Concept Meeting Preparation and Attendance.
6) Approved Concept Report.
7) Concept Design Data Book.
8) Public Involvement Plan (for GDOT’s approval).
C. Environmental Document:
1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History,
Ecology, and Archaeology). 2) NEPA documents.
a) Categorical Exclusion.
b) EA/FONSI.
c) Section 4f coordination.
d) One NEPA document reevaluation for Construction.
3) Preparation of a Section 404 Permit application.
4) Section 408 Coordination.
5) Aquatic Survey.
6) Stream Buffer Variance.
7) Preparation of a Vegetative Buffer application.
8) Public Involvement (1 possible detour/PIOH).
9) Prepare for and attend the PFPR and FFPR.
D. Preliminary Design:
Addendum No. 1
RFQ 484- 072319
Page 23 of 24
1) Complete Preliminary Roadway Plans, including but not limited to:
a) Preliminary Bridge Plans.
b) Preliminary Signing and Marking Plans.
c) Preliminary ESPCP.
d) Preliminary Utility Plans.
e) Preliminary Staging Plans.
f) Drainage Design including MS4, if applicable.
2) Bridge Hydraulic Study.
3) BFI Report.
4) Pavement Evaluation/UST/Soil Survey.
5) Constructability Meeting participation.
6) Cost Estimation with annual updates.
7) Location and Design Report.
8) PFPR participation, report, and responses (all plans sets and other information requested by Engineering
Services).
E. Right-of-Way (ROW) Plans:
1) Prepare ROW plans and coordinate ROW staking.
2) Right of Way revisions during acquisition, as needed.
F. Utilities:
Subsurface Utility Engineering.
G. Final Design:
1) Complete Final Roadway Plans, including but not limited to:
a) Final Bridge Plans (LRFD).
b) Final Signing and Marking Plans.
c) Final ESPCP.
d) Final Utility Plans.
e) Final Staging Plans.
f) Final Drainage Design including MS4, if applicable.
2) FFPR participation , report, and responses(all plans sets and other information requested by Engineering
Services).
3) Corrected FFPR Plans.
4) CES Final cost estimate.
5) Final PS&E Package.
6) Amendments & Revisions.
H. Construction:
1) Use on Construction Revisions.
2) Review Shop Drawings.
I. Quality Control/Quality Assurance Reviews for all deliverables.
Addendum No. 1
RFQ 484- 072319
Page 24 of 24
J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings
may be required to resolve major project issues).
K. For PI numbers 0016521; 0016522, and 0016527 (Harris, and Meriwether County), SR 103 @ HOUSE CREEK
6.5 MI SE OF WEST POINT (IN HOUSE ROAD AND BRIDGE); SR 103 @ SAND CREEK 5.5 MI SE OF WEST
POINT (IN HOUSE ROAD AND BRIDGE) and SR 362 @ RED OAK CREEK 6 MI NE OF GREENVILLE (IN
HOUSE ROAD AND BRIDGE) the Consultant shall provide the following:
A. Complete Field Surveys:
1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.
B. Environmental Document:
1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).
2) NEPA documents.
a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.
3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance.
C. Utilities:
Subsurface Utility Engineering. D. Quality Control/Quality Assurance Reviews for all deliverables. E. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional
meetings may be required to resolve major project issues).
7. Related Key Team Leaders per Exhibit I-8, Contract 8:
A. Roadway Design. B. Bridge Design. C. NEPA Lead.
8. The following milestone dates are proposed PI #’s 0016508, 0016520, 0016521, 0016522 & 0016527:
A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.