Upload
rohit-thakur
View
218
Download
0
Embed Size (px)
Citation preview
7/28/2019 Risk and Uncertainty in Project Management
1/24
RISK AND UNCERTAINTY IN
PROJECT MANAGEMENT
7/28/2019 Risk and Uncertainty in Project Management
2/24
That is, the probability that the expected
result will not be achieved.
From conception or identification to
implementation, risks issues arise and do
affect the project in a number of ways.
risks may be due to environmental or
managerial factors
7/28/2019 Risk and Uncertainty in Project Management
3/24
Types of Risk
Completion Risks
Permitting Risks
Price Risks Resource Risks
Operating Risks
Casualty Risks Technology Risks
7/28/2019 Risk and Uncertainty in Project Management
4/24
Classification of risks
Measurable Risks
Immeasurable Risks
Manageable Risks Insurable Risks
Investment Risks
7/28/2019 Risk and Uncertainty in Project Management
5/24
Risk Management Plan
Risk Identification
Risks Quantification
Risk Response Risk Monitoring and Control
7/28/2019 Risk and Uncertainty in Project Management
6/24
Risk Identification
Risk identification determines what might
happen that could affect the objectives of
the project, and how those things might
happen.
identification process must be
comprehensive
7/28/2019 Risk and Uncertainty in Project Management
7/24
The process should be structured using
the key elements to examine risks
systematically, in each area of the project
to be addressed
Techniques
brainstorming
7/28/2019 Risk and Uncertainty in Project Management
8/24
Info for Risk Identification
Historical Data,
Theoretical Analysis,
Empirical Data And Analysis, Informed Opinions Of The Project Team
And Other Experts, And The Concerns Of
Stakeholders To identify and name the risks
7/28/2019 Risk and Uncertainty in Project Management
9/24
Risk Quantification
Risk need to be quantified in two
dimensions
7/28/2019 Risk and Uncertainty in Project Management
10/24
7/28/2019 Risk and Uncertainty in Project Management
11/24
Economic
condition
Cash flow
()
Probability
Boom 100,000,000 20% or 0.20
Normal 50,000,000 50% or 0.50
Recession -10,000,000 30% or 0.30
7/28/2019 Risk and Uncertainty in Project Management
12/24
The Range
The Standard Deviation
7/28/2019 Risk and Uncertainty in Project Management
13/24
7/28/2019 Risk and Uncertainty in Project Management
14/24
Expected
cashflow for A0.20 x 100,000,000 +
0.5
0x
50,000,0
00+
0.3
0x
-10,000,0
00
Expected
cashflow for A 20,000,000
25,000,0
00
-
3,000,000
Expected
cashflow for A42,000,000
7/28/2019 Risk and Uncertainty in Project Management
15/24
( )xCoefficient of Variation
E x
7/28/2019 Risk and Uncertainty in Project Management
16/24
Economic Cashflow
Cashflow
times Deviation Squared Weighted Squared
Condition
s
Probabi
lity Probability Deviation Deviation
Boom
100,000,00
0 0.20 20,000,000 56,500,000
3,192,250 x
10^9 638,450 x 10^9
Normal 50,000,000 0.50 25,000,000 6,500,000 42,250 x 10^9 21,125 x 10^9
Recession -10,000,000 0.30 -3,000,000 -52,000,000
2,704,000 x
10^9 811,200 x 10^9
E(x) 43,500,000 sigma squared 1,516,000 x 10^9
sigma 38,935,845
7/28/2019 Risk and Uncertainty in Project Management
17/24
Sensitivity Analysis
scenario analysis or simulation analysis
examination of possible cash flows and
returns on an investment when one uncertain
element is altered
"what if?" analysis
Sensitivity analysis illustrates the effects ofchanges in assumptions
7/28/2019 Risk and Uncertainty in Project Management
18/24
Sensitivity Analysis
can be used to get an idea of a project's
possible future cash flows and their risk.
7/28/2019 Risk and Uncertainty in Project Management
19/24
Sales
Cost of goods sold and gross profit
Operating expenses
Interest rates
Accounts receivable days
Inventory days
Accounts payable days on hand
Major fixed asset purchases or reductions
Acquisitions or closings
7/28/2019 Risk and Uncertainty in Project Management
20/24
Risk Response
Strategies
Avoid the risk.
Do something to remove it.
Use another supplier for example.
Transfer the risk.
Make someone else responsible.
Perhaps a supplier can be made responsible for aparticularly risky part of the project.
7/28/2019 Risk and Uncertainty in Project Management
21/24
Mitigate the risk.
Take actions to lessen the impact or chance of the
risk occurring.
If the risk relates to availability of resources, drawup an agreement and get sign-off for the resource
to be available.
Accept the risk.
The risk might be so small the effort to do anythingis not worth while.
7/28/2019 Risk and Uncertainty in Project Management
22/24
A risk response plan
Strategy
action items to address the strategy.
what needs to be done,
who is doing it,
when it should be completed.
7/28/2019 Risk and Uncertainty in Project Management
23/24
Risk Control
continually monitor risks to identify any
change in the status, or if they turn into an
issue.
best to hold regular risk reviews to :
identify actions outstanding,
identify risk probability and impact,
remove risks that have passed,
new risks.
7/28/2019 Risk and Uncertainty in Project Management
24/24
Incorporating Risk into Discount
Rate
The discount rate itself has an element of
risk
To take account of additional risk; increase
the discount rate Refer to theories guiding choice of discount
rate