Risk and Uncertainty in Project Management

Embed Size (px)

Citation preview

  • 7/28/2019 Risk and Uncertainty in Project Management

    1/24

    RISK AND UNCERTAINTY IN

    PROJECT MANAGEMENT

  • 7/28/2019 Risk and Uncertainty in Project Management

    2/24

    That is, the probability that the expected

    result will not be achieved.

    From conception or identification to

    implementation, risks issues arise and do

    affect the project in a number of ways.

    risks may be due to environmental or

    managerial factors

  • 7/28/2019 Risk and Uncertainty in Project Management

    3/24

    Types of Risk

    Completion Risks

    Permitting Risks

    Price Risks Resource Risks

    Operating Risks

    Casualty Risks Technology Risks

  • 7/28/2019 Risk and Uncertainty in Project Management

    4/24

    Classification of risks

    Measurable Risks

    Immeasurable Risks

    Manageable Risks Insurable Risks

    Investment Risks

  • 7/28/2019 Risk and Uncertainty in Project Management

    5/24

    Risk Management Plan

    Risk Identification

    Risks Quantification

    Risk Response Risk Monitoring and Control

  • 7/28/2019 Risk and Uncertainty in Project Management

    6/24

    Risk Identification

    Risk identification determines what might

    happen that could affect the objectives of

    the project, and how those things might

    happen.

    identification process must be

    comprehensive

  • 7/28/2019 Risk and Uncertainty in Project Management

    7/24

    The process should be structured using

    the key elements to examine risks

    systematically, in each area of the project

    to be addressed

    Techniques

    brainstorming

  • 7/28/2019 Risk and Uncertainty in Project Management

    8/24

    Info for Risk Identification

    Historical Data,

    Theoretical Analysis,

    Empirical Data And Analysis, Informed Opinions Of The Project Team

    And Other Experts, And The Concerns Of

    Stakeholders To identify and name the risks

  • 7/28/2019 Risk and Uncertainty in Project Management

    9/24

    Risk Quantification

    Risk need to be quantified in two

    dimensions

  • 7/28/2019 Risk and Uncertainty in Project Management

    10/24

  • 7/28/2019 Risk and Uncertainty in Project Management

    11/24

    Economic

    condition

    Cash flow

    ()

    Probability

    Boom 100,000,000 20% or 0.20

    Normal 50,000,000 50% or 0.50

    Recession -10,000,000 30% or 0.30

  • 7/28/2019 Risk and Uncertainty in Project Management

    12/24

    The Range

    The Standard Deviation

  • 7/28/2019 Risk and Uncertainty in Project Management

    13/24

  • 7/28/2019 Risk and Uncertainty in Project Management

    14/24

    Expected

    cashflow for A0.20 x 100,000,000 +

    0.5

    0x

    50,000,0

    00+

    0.3

    0x

    -10,000,0

    00

    Expected

    cashflow for A 20,000,000

    25,000,0

    00

    -

    3,000,000

    Expected

    cashflow for A42,000,000

  • 7/28/2019 Risk and Uncertainty in Project Management

    15/24

    ( )xCoefficient of Variation

    E x

  • 7/28/2019 Risk and Uncertainty in Project Management

    16/24

    Economic Cashflow

    Cashflow

    times Deviation Squared Weighted Squared

    Condition

    s

    Probabi

    lity Probability Deviation Deviation

    Boom

    100,000,00

    0 0.20 20,000,000 56,500,000

    3,192,250 x

    10^9 638,450 x 10^9

    Normal 50,000,000 0.50 25,000,000 6,500,000 42,250 x 10^9 21,125 x 10^9

    Recession -10,000,000 0.30 -3,000,000 -52,000,000

    2,704,000 x

    10^9 811,200 x 10^9

    E(x) 43,500,000 sigma squared 1,516,000 x 10^9

    sigma 38,935,845

  • 7/28/2019 Risk and Uncertainty in Project Management

    17/24

    Sensitivity Analysis

    scenario analysis or simulation analysis

    examination of possible cash flows and

    returns on an investment when one uncertain

    element is altered

    "what if?" analysis

    Sensitivity analysis illustrates the effects ofchanges in assumptions

  • 7/28/2019 Risk and Uncertainty in Project Management

    18/24

    Sensitivity Analysis

    can be used to get an idea of a project's

    possible future cash flows and their risk.

  • 7/28/2019 Risk and Uncertainty in Project Management

    19/24

    Sales

    Cost of goods sold and gross profit

    Operating expenses

    Interest rates

    Accounts receivable days

    Inventory days

    Accounts payable days on hand

    Major fixed asset purchases or reductions

    Acquisitions or closings

  • 7/28/2019 Risk and Uncertainty in Project Management

    20/24

    Risk Response

    Strategies

    Avoid the risk.

    Do something to remove it.

    Use another supplier for example.

    Transfer the risk.

    Make someone else responsible.

    Perhaps a supplier can be made responsible for aparticularly risky part of the project.

  • 7/28/2019 Risk and Uncertainty in Project Management

    21/24

    Mitigate the risk.

    Take actions to lessen the impact or chance of the

    risk occurring.

    If the risk relates to availability of resources, drawup an agreement and get sign-off for the resource

    to be available.

    Accept the risk.

    The risk might be so small the effort to do anythingis not worth while.

  • 7/28/2019 Risk and Uncertainty in Project Management

    22/24

    A risk response plan

    Strategy

    action items to address the strategy.

    what needs to be done,

    who is doing it,

    when it should be completed.

  • 7/28/2019 Risk and Uncertainty in Project Management

    23/24

    Risk Control

    continually monitor risks to identify any

    change in the status, or if they turn into an

    issue.

    best to hold regular risk reviews to :

    identify actions outstanding,

    identify risk probability and impact,

    remove risks that have passed,

    new risks.

  • 7/28/2019 Risk and Uncertainty in Project Management

    24/24

    Incorporating Risk into Discount

    Rate

    The discount rate itself has an element of

    risk

    To take account of additional risk; increase

    the discount rate Refer to theories guiding choice of discount

    rate