Upload
njenns
View
232
Download
0
Embed Size (px)
Citation preview
8/13/2019 Risk Assessment of Subsea Pipelines
1/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 1
Inspection Maintenance and Repair of Deepwater Pipelines
DNV RP-F113
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
2/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines
Introduction
2
Requirements for pipeline inspection: what, when and how Pipeline maintenance and routine inspection Pipeline damage during installation and operation in
deepwater, causes and effects Understanding the risks and potential need for repair Repair systems & tools
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
3/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 3
Requirements for pipelineinspection: what, when and how
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
4/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines
All inspection, maintenance and
repair is performed remotely
4
Water depths are beyond diver limits and all activity (IMR) is remote Wall thickness are typically high } Materials, Welding, buckling Operating pressures are typically very high or very low Ambient external pressures are high, commonly similar to internal operational
pressures } Coating and Insulation Degradation High levels of Insulation are commonly required } Insulation Degradation Waters are typically cold approx 4 C- 6 C } CP, Flow Assurance, Materials Pipelines tend not to be protected by a concrete coating } Damage Geohazards can be significant } Spanning, Buckling, Damage, Bend Stability,
Turbitity and Debris flows Slugging within produced fluids is common } Spanning, Fatigue Greater tolerances Survey inaccuracy, installation accuracy
Metocean and environmental conditions tend to be benign } Stability Seabed mobility is less dominant } Scour, Spanning Corrosion coatings tend to be of very high quality } Corrosion, Damage
Typical Characteristics of Deepwater Pipelines
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
5/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 5
The ongoing assessment of inspection findings will involve comparison of datawith that recorded during previous inspection campaigns.
This will allow trends to be extrapolated and judgments made regarding theurgency of remedial action.
This process necessarily commences with the acquisition of the measurement ofinternally and externally taken values at the commencement of pipeline service,known as a Baseline Survey .
BASELINE SURVEY
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
6/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 6
Planned inspection campaigns are an integral part of the IMR strategy , thepurpose of the inspections being: to monitor pipeline system integrity over time monitor the impact of the subsea and production environments on the
pipeline. Understanding and confirming design assumptions
Routine inspections may indicate a requirement for more specific investigationsinvolving detailed or specialist techniques.
The normal physical inspection tasks undertaken on the Deepwater Pipelinescan be split into locations internal and external to the pipeline.
Internal and External locations are typically periodically inspected by Pigging and Remote Vehicle methods respectively.
Permanent monitoring methods also exist and are becoming morecommonplace.
INSPECTION STRATEGY (Monitoring)
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
7/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 7
It is essential that in developing an inspection regime that the deign is
understood and must include interaction with the designers: deepwater lateral buckling and walking issues will have been solved with
reference to the anticipatedpipeline operation response. Is that what reallyhappened?
If your system is anticipated to have multiple start up and shut downscenarios you will need to understand what the designers anticipatedhappening and how to monitor it.
there may be need to reconfirm what has actually happened once thepipeline is in operation.
INSPECTION STRATEGY (Understanding the Design)
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
8/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines
Location Method Technique Defects
8
Inspection
Internal
Pigging
Magnetic Flux
Ultrasonic
Visual
Calliper
Geometry (XYZ)
PermanentMonitoring
CorrosionProbe/SpoolSand Probe
External
ROV
Visual
Geometry XYZ
Burial
Acoustic
CP Probe
Weld Scanner Tomography
ScanningSide Scan
AUV
Visual
Geometry (XYZ)Sidescan
PermanentMonitoring
Vibration
Strain
Spanning/Burial
Corrosion
Dents
Gouges
leak
CP Failure
Coating Damage
Hydrate
Movement
Buckle
Vibration
Cracking
Fatigue
Protection Integrity (mattresses/Rock/Covers)
INSPECTION METHODS
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
9/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 9
Location Method Technique
Defect
S p a n n i n g /
B u r i a
l / S c o u r
C o
r r o s i o n
D e n t s
G
o u g e s
l e a k
E r o s i o n
C P
F a i l u r e
C o a t i n g
D a m a g e
H y d r a t e
M o v e m e n t
B u c k
l e
V i b r a t i o n
P r o t e c t i o n
I n t e g r i t y
C r a c k i n g
Internal
Pigging
Magnetic FluxUltrasonic
VisualCalliper
Geometry(XYZ)
Permanent
Monitoring
CorrosionProbe
Sand Probe
External
ROV
VisualAcousticCP Probe
Weld Scanner
Tomography
Side Scan
AUV
Visual
AcousticSidescan
PermanentMonitoring
VibrationStrain
INSPECTION DEFECT MATRIX
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
10/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 10
Risk Based Inspection Concept
IdentifyThreats/Hazards
to Pipeline
AssessInspection
History
Susceptibilityto Threat
MitigationMeasure to
reducesusceptibility
Likelihood ofFailure
Failure Mode
Consequenceof Failure
Risk Factor
RemainingLife or
InspectionGrade
InspectionScheme
DNV RP-F116 (Sec H1)
The risk assessment comprises the following maintasks;
a) Establish equipment scope
b) Identify threats
c) Data gathering
d) Data quality review
e) Estimate probability of failure (PoF) f) Estimate consequences of failure (CoF)
g) Determine risk
h) Identify risk mitigating measures
i) All equipment threats have considered
j) Determine aggregated risk
k) Planning of inspection, monitoring and testingactivities
RiskOK?
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
11/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 11
Defectselected
RecordResults
Determinemost likely
location
Reviewdesign
Reviewprevious
inspections
Prepare &PerformTargeted Inspection
Defectobserved?
I n s p e c
t i o n
R e c o r
d s
DesignDossier
No
Stop
Yes
Defect Type 2
Defect Type 3
Defect Type 4
Defect Type 5
Defect Type 6
Defect Type1
Assess Defect &Determine Correction
CodeRequirements
Targeted Inspections
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
12/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 12
Pig Inspection of offshore pipelines tends to look for internal problems .
Generally running pigs in offshore pipelines is very similar to running in onshorelines, after the wall thickness and higher pressures are taken in to consideration.
The most favoured inspection methods are either ultrasonic or magnetic flux inspection.
Magnetic flux is limited by magnet strength , ie get enough magnetism in the wall
of the pipe to enable good results to be obtained.Ultrasonic can inspect very thick wall pipe but Ultrasonic's have to be run in aliquid medium .
The main difference between offshore and onshore is the length of run betweenpig traps, as Offshore pipelines tend not to have intermediate compressionstations with conveniently located pig traps. The pig must not get stuck in thepipeline as retrieving it will be much more expensive than from an onshorepipeline. The pig must stay alive and recording data (battery duration may be anissue)
Deepwater Pig Inspection
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
13/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 13
Traditionally, external inspection, of deepwater pipelines is performed usingwork ROVs deployed from DP ROV support vessels .These vessels are expensive , and they may not be available when they areneeded most.
In deep waters, ROVs become heavy to handle from these vessels, becauseof long umbilicals ; and they become prone to breakdowns .
ROV inspections of long transmission lines can be very slow and may takemany months to complete end to end
Weather downtime is also an issue for ROV support vessels when workingin harsh and hostile environments
Deepwater ROV Inspection
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
14/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines
AUV based Inspection
14
AUV-based Inspection in deepwater fields may provide dramatic improvements incost, performance, safety and reliability. Large DPII vessels with high-end ROV spreads would no longer be required for
simple inspection. AUVs have demonstrated solid performance requiring simple autonomy for
missions such as bathymetric survey and high resolution sonar imaging AUVs can be deployed from small utility vessels , be capable of operations in
higher seas , without the operational limitations and equipment hazards imposedby umbilical and tether management systems. In the future AUVs would become field resident , residing in the subsea field for
periods of months.
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
15/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 15
Pipeline routine inspection and maintenance
O i i i f R i /S h d l d I i
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
16/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 16
Optimisation of Routine/Scheduled Inspection
An optimum IMR plan aims to strike an appropriate balance between the
following objectives: maximising the availability of the pipeline system during its operating life by
maintaining and preserving its integrity, thus maximising revenue; minimising inspection, intervention and rectification measures through the
life of the pipeline system, thus minimising through-life IMR related costs . reducing to as low as is reasonably practicable all risks to people, the
environment and assets , in accordance with legislative, societal and businessrequirements, thus minimising the costs of failures.
When and What do we inspect?
O i i i f R i I i M
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
17/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 17
Optimisation of Routine Inspection Measures
Phase 1
Phase 2
Phase 3
Time
F a
i l u r e
r a t e
The typical variation of failure rate in anoperating system with time, takes the shapeof the classic ' bath-tub ' curve, and can bedivided into three phases: Phase 1, early failures or damage, due to
defects in materials, incorrect installation,incorrect operation, unexpectedenvironmental effects (Scouring etc)
Phase 2, random failures or damage, dueto earthquakes, impacts (dropped objects,fishing, anchors), etc
Phase 3, wear out failures or damage, dueto corrosion, fatigue, internal erosion,anode depletion, coating breakdown etc
C d R i t DNV OS F101
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
18/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 18
Code Requirements DNV OS-F101
1. Define equipment scope ( i.e. All equipment that can lead to a failure) (DNV- OS-F101, Sec. 11, D304)
2. For each equipment, identify all threats which can lead to a failure (DNV-OS- F101, Sec. 11, D201)
3. For each threat; estimate risk (DNV-OS-F101, Sec. 11, D202) Consequence of failure (CoF) Probability of failure (PoF)
Propose plans for: Inspection, monitoring and testing (IMT) (DNV-OS-F101, Sec. 11, D103) Mitigation, intervention and repair (MIR) (DNV-OS-F101, Sec. 11, D700) Integrity assessment (IA) (DNV-OS-F101, Sec. 11, D600)
I ti Pl i g
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
19/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 19
Inspection Planning
Inspection Planning
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
20/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 20
Inspection Planning
APPENDIX G
EXAMPLE - RISK ASSESSMENT AND IM PLANNING
E mple Process from RP F116
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
21/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 21
Example Process from RP-F116Inspection Interval
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
22/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 22
Example Process from RP-F116Schedule Planning
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
23/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 23
1) Reduction in annual inspection applies to remote subsea pipelines only 2) Acoustic side scan sonar is not always cost effective especially indeepwater or where there are strong currents. An ROV survey with reduced scope could be considered 3) the third phase may not occur withinnormal project lifetimes, i.e. the Phase 2 (plateau phase) extends for several decades with well designed, operated and maintained facilities.
Type of Inspection
Years
s t s -
i l t
r
s l i
r
P h a s e 1
" E a r
l y F a i l u r e
"
Phase 2 1)
"Random Failure"Phase 3 3)
"Wear-Out Failure"
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Intelligent Pig
Visual including CPand Side Scan
Towed Acoustic SideScan Sonar 2)
Targeted Special
Events ? ? ?
Pipeline Maintenance
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
24/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 24
Preventive maintenanceBecause of the high cost and potential delays associated with intervention,preventive maintenance should be eliminated at the design stage , wherever
possible.Routine maintenanceRoutine maintenance tasks are required where the elimination of specificintervention is uneconomic or technically problematic . Normally suchmaintenance would be undertaken during repair activity, or combined withplanned inspection campaigns.
Corrective MaintenanceIntervention to rectify breakdown or degradation (Corrective Maintenance) isreferred to as Repair.
Normally Subsea Facilities shall possess sufficient reliability to ensureavailability throughout the field life.
Subsea equipment that is susceptible to failure should be designed tominimize the effort /cost required for replacement of the failed assembly.
Pipeline Maintenance
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
25/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 25
Pipeline damage during installation andoperation in deepwater, causes and effects
Installation Damage Scenarios
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
26/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 26
Installation Damage Scenarios
The potential causes and effects of damage during installation Phase of the pipeline(s) are summarized as follows:
rd PartyObjects Dropped from Ships Material and Construction Defects
InstallationTension failure Station Keeping
Geohazards Slope Stability
Route Features
Rock Outcrops, Cement Soil, Shell and Coral Banks.Pockmarks
Coating Damage (Corrosion and Weight coating):
Lost & Damaged weight coating Damaged corrosion coating Lost & Damaged insulation coating
Anode Damage:Lost anode Disconnected anode
Damage to pipeline geometry and/or pipe wall:
Gouges, Grooves and Notches.Dents Wet and Dry Buckles.Overstressing or Excessive Bending.Fatigue Damage.Bend Pull Out
Operational Damage Scenarios
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
27/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 27
Operational Damage Scenarios
The potential causes of damage during operational Phase of the pipeline(s) are summarized as follows:
GeohazardsEarthquakes Seismic Fault movement Submarine Landslides Mass Gravity Flows Turbidity Currents Sub-marine Volcanoes Liquefaction Tsunamis
Route FeaturesRock Outcrops, Cement Soil, Shell and Coral Banks.Shallow Gas and Seepage of Gas and Fluids Pockmarks Mud Diapirs and Mud Volcanoes Slope Instability Mass Movements
rd PartyTrawling Anchoring Objects Dropped from Ships Ship sinking
Ship Grounding Shipwrecks and Debris Material and Construction Defects Sabotage Military Action
Environmantal
Wind, Waves and Currents Scour Seabed Morphodynamics
Operational Damage Scenarios (effects)
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
28/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 28
Operational Damage Scenarios (effects)
The effect of damage that could occur during the operational phase of the pipeline(s) are summarized as follows:
Coating Damage (Corrosion and Weight coating):
Lost & Damaged weight coating Damaged corrosion coating Lost & Damaged insulation coating
Anode Damage: Lost anode Disconnected anode Over consumption Anode pasivity
Hydrate Formation: Pinhole Leak.Lost & Damaged insulation coating Incorrect operation
Damage to pipeline geometry and/or pipe wall:
Rupture.Internal Corrosion.External Corrosion.Pinhole Leak.
Gouges, Grooves and Notches.Cracks and Fracture Propagation.Dents and Buckles.Overstressing or Excessive Bending.Fatigue Damage.
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
29/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 29
Based on the damage scenarios and risk assessment it is clear that: The pipeline installation contractor should have fully developed procedures
and all necessary equipment mobilised and ready for implementation in the event of dry or wet buckles, prior to the start of deepwater pipelay operations.
The operator should have fully developed procedures and all necessary
equipment ready for implementation prior to the start of operations, to cater for the following scenarios:
Hydrate formation.Localised damage (i.e. dent or pinhole leak).Local Rupture.Rupture over extensive pipeline length.
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
30/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 30
Understanding the risks and potential need forrepair
MEIDP Example
MEIDP Example (3500m WD)
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
31/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 31
MEIDP Example (3500m WD)
Intervention Zones
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
32/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 32
Based on this preliminary information, the route has been divided into five differentintervention requirement zones.
1) Shallow Water Zone (0 to 150m WD)
2) Continental Slope Zone (150m to 2500m WD)3) Deep Water Section (2500m to 3500m WD)
4) Remote Seamount Section (300m to 3000m WD)
5) Indus Fan Section (2500m to 3000m WD)
Upper Indus FanMiddle Indus Fan AbyssalPlain
S o u t
h M u r r a y
R i d g e
N o r t h
M u r r a y
R i d g e
D a
l r y m p
l e
T r o u g
h
A b y s s a
l
P l a i nAbyssal
PlainQualhat Seamou
nt R i s eRise
S l o p e
S l o p e Shelf
1 1
45
3
33
2 2
Intervention Zones
Typical QRA for Deepwater Pipelines
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
33/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 33
yp p p
MEIDP QRA Risk Contributors and % contribution Ship sinking (40.24%) Objects dropped from ships (19.91%) Ship grounding (14.07%) Material and construction defects (11.17%) External corrosion (10.62%) Anchoring (3.23%) Internal corrosion (0.63%) Trawling (0.12%)
Typical QRA for Deepwater Pipelines
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
34/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 34
Trawling Anchoring
Dropped objectsInternal corrosion
External corrosionMaterial and construction defects
0.00E+00
5.00E-04
1.00E-03
1.50E-03
2.00E-03
2.50E-03
3.00E-03
Trawling Anchoring
Dropped objectsShip sinking
Ship groundingInternal corrosionExternal corrosionMaterial and construction defects
0.00E+00
1.00E-03
2.00E-03
3.00E-03
4.00E-03
5.00E-03
6.00E-03
Most likelylocation forIntervention is thedeepest water
Upper Indus FanMiddle Indus Fan AbyssalPlain
S o u t
h
M u r r a y
R i d g e
N o r t h
M u r r a y
R i d g e
D a l r y m p
l e
T r o u g
h
A b y s s a
l
P l a
i nAbyssalPlain
Qualhat Seamou
nt
R i s eRise S l o p e S l o p e Shelf
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
35/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 35
Repair systems & tools
Help is at Hand
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
36/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 36
This Recommended Practice (RP) is intended to provide criteria and guidelines for the qualification offittings and systems used for pipeline subsea repair and/or modifications and tie-ins.
Help is at Hand
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
37/42
Why Tooling is Needed
http://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
38/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines
Why Tooling is Needed
38
Equipment PurposePipeline CoatingRemoval Tool
Removal of external pipeline coatings in the vicinity of any section that hasbeen cut (by the Pipeline Cutting Tool). Required in the event that the PipelineRecovery Tool grips the pipeline on its external steel surface.
External Weld BeadRemoval Tool
Removal of external longitudinal weld seam (SAW linepipe) to preventinterference on connector seal.
End Preparation Tool Machining of the end face of the pipeline to prevent interference on connectorseal.
Pipeline RecoveryTool
Tool connected to the end of the cut pipeline to allow recovery to surface.Designed to allow the pipeline be dewatered and isolated prior to recovery.
Pipeline RepairClamp
Permanent clamp installed around the pipeline in the vicinity of minor damage(i.e. dent) for the purpose of ensuring the structural integrity of the pipelinewithout the need for cutting out and replacing an entire section of pipe.
Subsea PipelineConnectors
Connector assembly and modular system used for the installation andconnection of a new section of pipeline.
Replacement Spoolpiece
New section of pipeline used to replace area of damage.
Hydrate BlockageRemoval Spread
Accidental ingress of moisture into the pipeline can cause formation of ahydrate plug. Hydrate removal is possible by various passive methods but may
ultimately require a deepwater hot-tap operation at actual location of thehydrate where the spread taps a hole into the pipeline and injects hydrateremoval chemicals.
Summary of Inspection for Deepwater Pipelines
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
39/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines
Su a y o spect o o eepwate pe es
Intelligent pigging is the primary form of internal inspection
ROV are the primary tool for performing external inspection
The development of AUVs for flypast inspections may give benefits deepwater byisolating the vehicle from surface influences
Risk Based methods have been established for determining Inspection regimes (DnV
RP116)
39
Summary of Repair for Deepwater PipelinesI ll i Ph
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
40/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines
Installation Phase
Damage scenarios during installations and operation pose differing levels of risk.
The most significant potential damage scenarios during the installation phase aredry and wet buckles.
The technology and methodologies required for rectification of installation phasedamage (i.e. buckles) are a direct extension of techniques used for similar events inshallow water, and currently exists with installation contractors and specialistequipment suppliers.
40
Summary of Repair for Deepwater PipelinesO ti l Ph
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
41/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines
Operational Phase
Several potential damage scenarios exist during the operational phase. The most
significant are where a damaged section of pipeline needs to be reinforced, replacedor cleared of a hydrate blockage.Where a replacement pipeline section is required, the length could vary significantlydepending on the nature of the event causing the damage (a few meters to severalkilometres in the event of a geohazard (i.e. slope instability).There is a wide range of qualified or nearly qualified equipment for the subsearepair, both currently available and under continual development. The equipmentexists both as individual components (equipment, tools and fittings) and fullsystems.Some repair systems are owned and operated on a club basis, by a group orconsortia of pipeline operators. The clubs at present operate in specificgeographical locations.The need to access the pipeline at both ends for the purpose of re-commissioning
(i.e. flooding, cleaning, dewatering, etc.), is inherent in many of the repair scenarios.Access facilities and the provision of adequate space for equipment (particularlydewatering) are significant.
41
References
http://www.informaglobalevents.com/event/deeppipeshttp://www.informaglobalevents.com/event/deeppipes8/13/2019 Risk Assessment of Subsea Pipelines
42/42
Deep and Ultra-deepwater Pipelines Co nference
27 - 28 September 2011, Novotel Paris Les Halles
Ian Nash
Inspection Maintenance and Repair ofDeepwater Pipelines 42
I Nash & P Roberts OPT 2011, MEIDP The Deepwater Gas Route to India, February23-24,I Nash & P Roberts DUDPC 2011, Case Study: MEIDP Installation, intervention andRepair, Sept 27-28 Peritus International, 18001.01-REP-IIDP-Y-0014 MEIDP, Emergency Pipeline RepairSystems, Aug 2011Peritus International, 18001.01-REP-IIDP-Y-0007 MEIDP Quantified Risk
Assessment Update, Dec 2010 Dan McLeod, Emerging Capabilities for Autonomous Inspection Repair andMaintenance, OCEANS 2010 (ART) DNV RP-F116 Integrity Management of Submarine Pipeline Systems DNV RP-F113 Subsea Pipeline Repair
http://www.informaglobalevents.com/event/deeppipes