Upload
rod-cavicchioni
View
230
Download
8
Embed Size (px)
DESCRIPTION
rope works risk assesment
Citation preview
Risk Assessment for Rope change at MGD Sentosa Iland – Mt. Faber ( Singapore)
Step Description of the step Possible hazards Controls / precautions1 Set-up of the equipment as shown in
attachment General public accessing rigging areas
Oil leaking from the winches
Manual pushing of heavy equipment components
Cuts and grazes
Punches and blows to the head Falling, slipping, stumbling
Fence around the winch and the area to be equipped on the west side
Warning signs to prevent persons from trespassing the area
Entombment package nearby the winches
Observe entombment plan specific to the location
Employees qualified by training in handling of heavy components
Use shoes with steel toe cap Always wear shirts with short
sleeves and trousers Compulsory wearing of a helmet Working area must be kept clean Works on the ground acc. to
Doppelmayr instructions2 Installation of anchors, bottom roll, deflection
roll Failure of the anchor or rigging points
respectively Install double anchor or rigging
points for high forces. Anchor calculated with a safety factor of 3 to max. Acting load.
Helmet / stepping aside As few people as possible Keep working area clean / secure
with guy ropes Visual check the anchor
3 Working with ropes and slings Endangerment third parties During pulling work no persons are allowed to stay under the
Tear of ropes/ slings
Fall down from assembly material and slings/ropes
Incorrect serving of winches, and machines
Slip of clamping plate and ropes
Uncontrolled unreeling from ropes
ropes. Walk ways and traffic road have to be secured. The lateral safety margin between people and the rope is to be adapted to the local conditions and should at least 10 meter.
The maximum rope and anchorage forces must be admit . Slings and ropes must be selected with a security from at least 2,5 to the minimum breaking load. The condition of ropes and Slings are to be visually examined before use. Defective material has to to be removed.
Rope, assembly aids and tools for the work are to be secured against falling down.
Only trained personal to allowed to operate winches and machines.
For the rope attachments use only anchorage material which is appropriate for the selected kind of anchorage and the arising forces . Clamping plate diameter must correspond with the rope diameter. Screws (e.g. of clamping plates) are to be tightened with torque wrench.
Rope drums are to be secured against uncontrolled unreeling. Nobody is allowed to stay inside loosely rope rings. Likewise
Hang up at construction works and structures
critical rope angles from guide rollers are to be avoided.
During the pulling work the rope is to be controlled on the critical places and/or accompanied during pulling. It has to be considered that changing the rope tension means changing also the rope position.
4 Fixing 29 mm Hauling Rope at Sentosa Station by installation of Attachment slings.
Falling of parts from certain height Slipping of clamping plate Tear of attachment slings Tear of anchors
See point 3
5 Fixing 29 mm hauling rope at Mount Faber by installation of attachments slings on one side and 5 To Winch and 16 To tackle block on the other side.
Falling of parts from certain height Slipping of clamping plate Tear of attachment slings Tear of anchors
See point 3
6 Pull with 5 To Winch until 29 mm Rope at Mt. Faber is loose.Cut 29 mm rope at Mt. Faber.Release 29 mm Rope until the tension weight at Sentosa is placed on the ground.
Sparks and fire
Injuries caused by the falling or releasing rope and by falling parts
Loss of the rope Sparks and fire
Twisted ropes
Protect surrounding area against sparks. Place fire extinguisher.
Only trained operators on winches and machines
Clean area below counterweight at Sentosa
Ensure that the tension of the rope has been released before cutting it.
Use tension holder against twist of tackle block and rope
7 Fixing 29 mm Hauling Rope at Sentosa Station by installation of Attachment slings with 16 to tackle block an Tirfor. Same side as winch.Cut 29 mm rope at Sentosa
Falling of parts from certain height Slipping of clamping plate Tear of attachment slings Tear of anchors Sparks and fire
See point 3
Protect surrounding area against
sparks. Place fire extinguisher.
8 Pull 29 mm Hauling Rope trough 25 to winch at Sentosa and roll up on Hasp winch. At Mt. Faber, connect the 29 mm hauling rope to 14 mm winch rope by means of splice connection.
Twisted ropes Incorrect serving of winches, and
machines Falling of parts from certain height Slipping of clamping plate Tear of rope splice connection
See point 3
Splice connection to be done only by special trained Garaventa people.
9 Pulling out 29 mm Hauling Rope with 25 to winch over the spilling ring and roll on to hasp winch. Continue release with 5 to winch until 14 mm winch rope has reached Sentosa
Endangerment third parties Loss of the rope Loss of communication Loss of winch control
See point 3 Limit winches to breaking load of
rope Ensure adequate communication Check radio equipment before
using it Back-up radio for the operator of
the winches Headset for operator of winches One person to regulate the winch
speed Limiting to the tensioning values
indicated by the Engineering Dept.
10 Fix 14 mm winch rope at Sentosa and Mt. Faber. Cut 14 mm rope between winch an fixation at Mt. Faber
Falling of parts from certain height Slipping of clamping plate Tear of attachment slings Tear of anchors Sparks and fire
See point 3
Protect surrounding area against sparks. Place fire extinguisher.
11 Change Winches in both Stations to the opposite Side and pull out 29 mm hauling rope as described in point 8 and 9.The 14 mm winch rope remain placed.
Clamping fingers and feet Personal falling over slings and tools
Wear hand cloves and safety shoes
Clean up working tools and equipment
12 Install 40 to tackle block to Track rope at Mt. Falling of parts from certain height See point 3
Faber and release Track rope until counter weight is placed on the ground.
Slipping of clamping plate Tear of attachment slings Tear of anchors
13 Install chain hasp in the parking area at Faber.
Endangerment third parties Fall down from assembly material and
slings/ropes Loss control of mobile crane
See point 3
Use only trained machinist on mobile crane
14 Install Liner hoist at Mt. Faber and feed the 42mm track rope through the liner hoist to the chain hasp
Twisted ropes Incorrect serving of winches, and
machines Clamping fingers and feet Personal falling over slings and tools
Wear hand cloves and safety shoes
Clean up working tools and equipment
15 Fix the 29 mm rope at Sentosa coming through the spilling ring of the 25 to winch to the track rope by means of casting head
Twisted ropes Incorrect serving of winches, and
machines Clamping fingers and feet Personal falling over slings and tools Sparks and fire
Wear hand cloves and safety shoes
Clean up working tools and equipment
Casting head to be installed only by special traind Garaventa people
16 While pulling with the liner hoist, releasing with the 25 to winch the 29 mm rope. Pull 42mm track rope on to the chain hasp until 29 mm rope has reached Mt. Faber.
Endangerment third parties Loss of the rope Loss of communication Loss of winch control
See point 3 Limit winches to breaking load of
rope Ensure adequate communication Check radio equipment before
using it Back-up radio for the operator of
the winches Headset for operator of winches One person to regulate the winch
speed
Limiting to the tensioning values indicated by the Engineering Dept.
17 Fix 29 mm rope at Sentosa and Mt. Faber.Cut of casting head. The 29 mm rope remain in place.
Sparks and fire
Injuries caused by the falling or releasing rope and by falling parts
Loss of the rope Sparks and fire
Twisted ropes
Protect surrounding area against sparks. Place fire extinguisher.
Only trained operators on winches and machines
Clean area below counterweight at Sentosa
Ensure that the tension of the rope has been released before cutting it.
Use tension holder against twist of tackle block and rope
18 Move linear hoist an winches to the opposite side.
Clamping fingers and feet Personal falling over slings and tools
Wear hand cloves and safety shoes
Clean up working tools and equipment
19 Repeat point 12 to 16.