Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Risk Management and
Job Safety Planning
Code
The primary code of practice for Hazard Recognition, Evaluation
and Control at Newfoundland Power
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 2 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
1.0 Purpose
The purpose of this Code is to manage the hazards associated with high risk activities at
Newfoundland Power. In essence, the purpose of job planning is:
To reduce the risk of serious incidents.
To provide a better opportunity to recognize, evaluate and control hazards before the
work begins.
To improve the quality of construction drawings and integrate safety into the design phase.
To improve communication between engineering, planners, supervisors, and crew
members.
To more effectively manage changes that occur during a project or job.
To be prepared for emergencies.
2.0 Scope
This Code applies to all Newfoundland Power Electrical Line Operations, Engineering and
Construction, Electrical and Mechanical Maintenance, Vehicle Service Center Mechanics, Power
Plant Staff, Meter Technicians, Meter Readers, Collectors and associated contractors. Where
contractors have their own specific hazard assessment and control processes (including forms),
these processes may be acceptable to Newfoundland Power upon review. Any revision or
modification of the principles outlined in this code of practice shall require the approval of the
Manager of Corporate Safety.
3.0 General
Risk Management and Job Safety Planning is an integral element of Newfoundland Power’s
Health and Safety Management System. Given the variety and complexity of the types of work
performed at Newfoundland Power, different jobs require different levels of planning. It is
recognized that large projects involving multiple disciplines or multiple crews require more
detailed planning than day-to-day jobs carried out by individual crews. For any job, hazards
must be identified, evaluated based on risk and the appropriate controls or barriers put in place so
that the work can proceed safely. In addition, it is critical that all involved in the work
participate in the job planning process at some level. The level of participation will vary
depending on the nature and scope of the work. A review of the hazards associated with the
work, how they were evaluated and the barriers to be put in place, must be communicated to the
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 3 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
front line. Safe work relies on effective job planning, good hazard assessment skills, teamwork,
the recognition of a worker-in-charge and open and effective communication. At Newfoundland
Power, no task is more important than ensuring that the job is properly planned and performed
safely.
Effective job safety planning starts with recognizing that any task can result in an accident if
hazards are not identified and effectively controlled. The intent of this Code of Practice is to
provide the foundation and tools necessary for employees to be able to properly identify and
control major hazards through effective risk management and job safety planning and to
communicate these hazards and controls to all other workers at the work site.
Hazard Identification
When analyzed, any accident can be defined as resulting from an unintended or uncontrolled
release of energy. The more powerful this energy is, the more likely it will result in serious
injury to a worker or workers. It is therefore important to be able to identify the energy forms
present in the workplace that are typically involved in these accidents. These energy forms are
listed below:
Electrical Biological
Radiant Gravity
Kinetic Water
Noise Mechanical
Pressure/Tension Body Mechanics
Thermal Chemical
Determining whether these energy forms are present during the work process is an important first
step in identifying the specific hazards, risk level and barriers required to control these hazards.
Risk Assessment
Once energies and their associated hazards have been identified the level of risk associated with
each identified hazard must be determined with the objective of focusing on the powerful
energies that could result in a serious injury to a worker or workers. The following definitions
are used to determine the level of risk related to a given hazard:
1. High Risk Hazard – Could result in fatality or serious injury (i.e. permanent disability).
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 4 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
2. Medium Risk Hazard – Could result in temporary disability (i.e. lost time injury).
3. Low Risk Hazard – Could result in minor injury (i.e. medical-aid or first-aid injury).
Where either High or Medium Risk hazards are identified, specific barriers (controls) must also
be determined and documented.
Low Risk hazards do not require specific documented controls as they are managed through
employee awareness, general caution and by following basic safety practices.
Accident Causation – Unwanted Energy Release
Understanding how the unwanted or unintended release of energy can result in worker injury can
be graphically illustrated by using an energy flow diagram. For example, consider Diagram 1
which shows the three stages of an accident involving a worker who is struck by a falling tool.
As can be seen from the diagram, the accident chain starts with the tool falling from a height.
This is the first step in the process and is known as the energy Release phase. In this case, the
energy form released, or no longer controlled, is gravity.
Once the energy is released, the energy flow moves along to the second stage which is the
Contact phase. Here, the falling tool makes contact with a worker below. When the tool makes
contact with a worker, the incident moves into what is known as the Injury phase. This is
simply the phase where an unprotected worker could suffer substantial injury, especially if the
contact was made to a vulnerable body part such as the head.
It is important to note that there has to be a sequence of events to occur before an accident can
result in an injury and that it always starts with an unwanted release of energy. Recognizing that
it is the unwanted release of various energy forms that start the accident chain, then one is better
equipped to prevent an unwanted release from occurring, and therefore, better equipped to
prevent an injury.
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 5 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
Diagram 1 - Unwanted Energy Flow
In assessing any job, it is critical that workers consider which forms of energy (hazards) are
present for the task about to be performed and then to determine what the level of risk is for a
particular hazard.
For any particular job or task there may be several different energy forms involved. What the
worker is expected to do in these cases is to review the list and identify any major hazards
associated with each energy form that may present itself. Once the major hazards have been
identified through their various energy forms, the worker can then proceed to evaluate those
hazards and put a plan in place to control them.
Accident Prevention - Hazard Controls (Barriers)
Once the high and medium risk hazards have been identified a specified plan must be put in
place to determine how these hazards are to be controlled. This involves the implementation of
barriers (or controls). There are many types of barriers that can be put in place to minimize the
danger associated with hazards. A list of barriers, in their order of effectiveness (1 being the
most effective and 10 being the least effective), is given below:
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 6 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
1. Eliminate the Hazard 6. Minimize Error Potential
2. Minimize Energy to Safe Levels 7. Use Written Procedures
3. Install Physical Barriers 8. Provide Training
4. Wear Protective Equipment 9. Provide Supervision
5. Install Warning Devices 10. Identify Hazards Only
By referring to Diagram 2, it can be seen that there are a number of opportunities to place barriers
along the energy flow path thereby interrupting the energy flow:
Diagram 2 – Unwanted Energy Flow with Barriers
Barriers that prevent the release of energy are the most effective. Using the above example, this
can be effectively accomplished by tying off the tool (barrier #3) which is a physical barrier that
prevents the tool from falling. Barriers placed on the source that prevent the release of energy
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 7 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
are referred to as “Control Barriers”.
Any barrier can fail (in this case ropes can break) so thorough job planning must be prepared for
this eventuality. In the event of failure of the first barrier, the objective must be to prevent
contact from occurring. Even if the tool falls, no injury will result if the falling tool does not
contact the worker. In this case, the contact is prevented by roping off the area (barrier #5) and
including it in the tailboard discussion (barrier #6) so that all workers are aware to stay out of the
contact zone. Placing barriers along the energy flow at a point between the energy source and
the target will prevent an injury should the control barrier fail. Barriers placed along the
unwanted energy flow, once the energy has been released, are referred to as “Safety Barriers”.
Some barriers do not impede or interrupt the flow of energy but are necessary to improve the
overall effectiveness of control and safety barriers. Safety training, safe work procedures and
providing supervision are all examples of this type of barrier. These barriers are referred to as
“Support Barriers” and, while in and of themselves, they are not as effective as control or
safety barriers, they are no less important.
It should be clear from Diagram #2 that every effort must be taken to put barriers in place that
will prevent the energy flow from moving from one phase to the next and that there are a number
of things which can be done (by placing barriers at all possible points along the energy flow
path) to prevent an injury from occurring. As discussed above, the most effective barrier is the
one that prevents the energy from being released. However, as previously noted, as many
barriers as possible must be in place in case the primary (control) barrier fails. It is important
therefore to ensure that two key principles of Risk Management & Job Safety planning be
applied consistently.
Barrier Effectiveness Principle
Some barriers are more effective than others. The first three barriers on the barrier effective list
above focus on preventing the release of energy. Once these barriers are placed they are
independent of the human factor in that they do not rely on human performance to work. Moving
down through the list, the barriers tend to be more reliant on human performance which makes
them prone to errors. The more a barrier relies upon a person to respond in a certain way, the less
effective it is. In short, the higher the barrier appears on the list above, the more effective it is in
preventing accidents in the workplace. This becomes especially important when high risk (fatal)
hazards exist while performing any task that a principle known as the Barrier Effectiveness
Principle apply. This principle states that:
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 8 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
For any High-Risk hazard (i.e., with potentially fatal consequences), there should be at least
One Control Barrier in place to provide the primary protection from the hazard: i.e. Eliminate
the Hazard, Minimize Energy to Safe Levels or install Physical Barriers
It should be noted that assessing the effectiveness or quality of a barrier is just as important as
implementing the barrier itself. For example, using a hot stick that is overdue on retest or not
wiped down, is not an example of an effective barrier, and therefore it should not be used. In
order for the Hot Stick to be effective, it has to be tested and clean so that it can do the job for
which it was intended. Any tool or piece of equipment used for the purpose of implementing a
barrier (especially with respect to high voltage lines) must be confirmed rated, tested and capable
for the job it is about to be used for.
Multiple Barrier Principle
Because one barrier may be more effective than another does not mean that it should be the only
barrier used. In fact, because no barrier is 100% effective (barriers fail sometimes), fatal hazards
require multiple barriers in case the primary barrier fails. The more barriers that are in place to
interrupt the unwanted energy flow, the lower the chances are that an injury will occur. This
concept is known as the Multiple Barrier Principle and is comprised of two different
components:
The Multiple Barrier Principle (1)
For any High-Risk Hazard (i.e., with potentially fatal consequences), there must be a
Secondary Control Barrier or Safety Barrier in place to provide secondary protection in the
event that the primary barrier fails.
The Multiple Barrier Principle (2)
If it is not possible to apply an effective Control Barrier for High-Risk Hazards, there must be
Multiple Effective Safety and Support Barriers in place to reduce the risk to an acceptable level.
Communication
Though effective hazard recognition, evaluation and control are critical in preventing workplace
accidents, the issue of communication is of no less importance. Hazard assessments can be
extremely well done with effective barriers identified, but unless the hazards and required
barriers have been discussed and communicated with all involved, then the risk assessment and
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 9 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
job safety planning process has not been fully completed. ALL workers must have the
opportunity to participate in the risk assessment process, and provide feedback with respect to
how these major hazards are controlled. The Worker in Charge holds a unique responsibility to
enable this participation by leading the discussion and asking for feedback and confirmation of
understanding (especially from new workers) during the hazard recognition, evaluation and
control process and for documenting the discussions on the tailboard conference form.
4.0 Responsibilities
4.1 Directors shall:
Ensure that the Risk Management and Job Safety Planning Code and associated
training is implemented, where required, within their Region/Department.
Ensure that supervisors are held accountable to monitor the quality and effectiveness
of Risk Management and Job Safety Planning within his/her Region/Department.
Assess the quality of Risk Management and Job Safety Planning during safe work
observations.
4.2 Managers shall:
Coordinate Risk Management and Job Safety Planning Code training.
Provide resources and sufficient lead-time for quality risk assessment and job safety
planning for larger projects.
Review and sign off on all Steps and Conditions Plans.
Ensure engineering drawings as well as permits, approvals or other documents
required for safe conduct of the work are provided to workers.
Ensure that a system of monitoring and coaching by the supervisors is implemented that
includes a formal review of Job Safety Planning documents and that there is a process of
on-going monitoring during field visits and safe work observations.
Assess the quality of Risk Management and Job Safety Planning during safe work
observations.
Provide feedback and coaching to supervisors and crews related to Risk Management and
Job Safety Planning Code compliance.
4.3 Supervisors shall:
Be responsible for the ongoing (day-to-day) management of the Risk Management/
Job Safety Planning process.
Regularly monitor compliance to the Risk Management and Job Safety Planning
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 10 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
process, by reviewing planning documents (tailboard conference plans, steps and
conditions plans, etc.).
Provide feedback and coaching to Lead Hands and crews related to Risk Management and
Job Safety Planning Code compliance on an ongoing basis while in the field and during
formal safe work observations.
4.4 Lead Hands shall:
Ensure that Tailboard Conference Plans are completed as required by this code.
Ensure that all crew members and/or contractors working on the site participate in the
discussion and development of the Tailboard Conference Plan.
4.5 Work Crews shall:
Actively participate in the preparation of the Tailboard Conference Plan.
Indicate that he/she participated and understands the plan by signing the Tailboard
Conference Plan form.
4.6 Manager of Corporate Safety shall:
Be responsible for on-going review and revision of the Risk Management and Job Safety
Planning Code.
Be responsible for identifying the position training requirements on the Safety Training
Matrix and in the Safe Work Management System (SWMS).
Be responsible for the development of the Risk Management & Job Safety Planning Code
training program.
5.0 Procedure
5.1 Training is mandatory for all employees that are covered under the scope of this code of
practice. Specific training requirements for each job classification group are contained in
the safety training matrix. Those required to attend training shall be scheduled to do so
through Safe Work Management System (SWMS) which will automatically set training
requirements by job title. Refer to OPR500.15 – Identification and Assessment of
Training, Awareness and Competency.
5.2 Prior to the start of the job, a Risk Assessment and associated Job Safety Plan must be
conducted as outlined in this procedure. The complexity of the risk assessment and job
planning process will depend on a number of factors including the scope of the work and
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 11 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
the number of workers involved.
5.3 Daily Job Safety Planning
Prior to the commencement of work, a job safety plan must be created by the work crew
and/or worker and documented using Form 85A - Tailboard Conference Plan (Line
Operations) or Form 85B - Tailboard Conference Plan (Electrical/Generation) . The
overall purpose of the daily job safety job safety plan is to:
a) reduce the risk of serious accidents;
b) improve the quality of job briefings and on-site meetings;
c) provide an opportunity to identify and control hazards prior to the commencement
of work;
d) conduct an assessment on the effectiveness of the barriers.
The daily job safety plan should be prepared by the work crew and/or worker at the job
site. Where high risk work is undertaken by the crew prior to arrival at the job site (e.g.
loading heavy materials, attachment of wire reels or trailers, etc.) the daily job safety plan
should be started to include this portion of the work and completed upon arrival at the job
site.
The Worker in Charge is responsible to ensure that job safety plan is created and
documented using Form 85A - Tailboard Conference Plan (Line Operations) or Form
85B - Tailboard Conference Plan (Electrical/Generation). The form shall also identify
the Worker in Charge.
Daily job safety plans need not be too detailed and normally require between five to ten
written steps as a general rule of thumb. A daily job safety plan would normally not
require more than fifteen minutes to properly prepare.
Each job safety plan must identify and document the job steps in sequence, rate the
hazard associated with each step and identify the appropriate barriers. Also, barriers
shall be categorized as being Control, Safety or Support barriers. When documenting the
hazards and barriers, specific detail should be used to describe each.
All workers (including contractors) shall actively participate in the discussion
surrounding the creation of the daily job safety plan and shall sign off on the form as an
indication of their participation and understanding of the plan.
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 12 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
It is recognized that some job classifications within Newfoundland Power perform a
variety of tasks ranging from low to high risk. Low risk work does not require the
completion of a job safety plan. It is important therefore that each employee understand
the tasks which require the creation of a job safety plan. These requirements should be
defined and communicated by the Regional Directors in consultation with the Director
responsible for Corporate Safety.
While a minimum of one Tailboard Conference Plan form must be completed each day
by each work crew or work unit, the following guidelines apply to working at multiple
locations during the day, repetitive work and/or working alone:
Working at multiple locations during the day:
For work crews performing routine tasks at multiple locations, (e.g. maintenance crews
and/or service crews in the line operations) the same written Form 85A - Tailboard
Conference Plan (Line Operations) or Form 85B - Tailboard Conference Plan
(Electrical/Generation) may be used for other jobs performed throughout the day in lieu
of creating another document. In these situations, when tasks and/or locations change,
they must be identified on the Form 85A - Tailboard Conference Plan (Line Operations)
or Form 85B - Tailboard Conference Plan (Electrical/Generation) along with the hazards
associated with the new task and the barriers required to control them.
Repetitive work on successive days at the same specific location:
For work crews performing routine and/or repetitive tasks at the same specific location
on successive days (e.g. breaker maintenance or control wiring in a substation) the same
written Form 85A - Tailboard Conference Plan (Line Operations) or Form 85B -
Tailboard Conference Plan (Electrical/Generation) may be used on each successive day
up to a maximum of five days. In these situations a job safety planning meeting is held
with all workers and the hazards and barriers discussed. Any new hazards and barriers,
not previously identified shall be documented. All workers must sign off on the job
safety plan with the new date noted on the form:
Daily Job Safety Plans While Working Alone:
When working alone, prior to performing work, employees are required to assess the
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 13 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
hazards associated with the work, evaluate the risk and ensure appropriate barriers have
been put in place so that the work can safely proceed. This is best accomplished by
documenting the hazards on an appropriate tailboard conference form, reviewing them
and implementing effective barriers for the hazards identified.
In all cases, particular attention must be given to emergency response requirements, call-
back protocol, etc. Employees, and supervisors of employees, who work alone must refer
to OPR300.03 – Working Alone for details on working alone protocols.
The following requirements have been defined for the creation of daily job safety plans
while working alone:
a) For workers performing routine tasks by themselves such as multiple substation
inspections a daily Form 85B - Tailboard Conference Plan (Electrical/Generation)
may be used throughout the day in lieu of creating another document. Location
changes and any newly identified hazards and barriers shall be documented.
b) For conducting daily inspections in power plants a single form per day may be
used throughout the day in lieu of creating another document. Alternatively, a
weekly form by specific location (e.g. Petty Hr. Plant) may be used up to a
maximum of 5 days. In each case the form must be reviewed and hazards
assessed prior to commencement of work.
c) For removing and installing meters by Meter Readers and/or Collectors at
multiple locations, a single tailboard may be used throughout the day in lieu of
creating another document. Location changes and any newly identified hazards
and barriers shall be documented.
Completed Tailboard Conference Plans (Form 85A - Tailboard Conference Plan (Line
Operations) and/or Form 85B - Tailboard Conference Plan (Electrical/Generation) shall
be forwarded to Area or Departmental SWMS Coordinators for filing and retention as per
the Master Health and Safety Records List (MHSRL).
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 14 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
5.4 Project Safety Planning - for Large or Complex Jobs
For large or complex jobs, the Risk Management & Job Safety Planning process requires
the creation of a Steps and Conditions Planning Chart which is documented using Form
84 - Steps and Conditions Planning Chart.
Determining whether a Form 84 - Steps and Conditions Planning Chart is required for a
particular job/project shall be based on an assessment of several factors including the
duration, scope and complexity of the job/project based on the number of different
disciplines and /or work groups involved (including contractors). Using these criteria, the
person responsible for the overall project shall determine whether a Form 84 - Steps and
Conditions Planning Chart is required.
Jobs that normally require a Steps and Conditions Planning Chart include long term jobs
(greater than one week as a general rule of thumb), large scale jobs, such as capital
construction and/or maintenance associated with plants, substations, buildings and
distribution or transmission lines and isolation grounding.
It should be noted that some jobs that are greater than one week or that involve multiple
crews may not necessarily be overly complex (i.e. don’t have multiple steps) and
therefore may not require the creation of a Steps and Conditions Planning Chart.
Examples of this type of project are:
a. A power transformer maintenance project in a substation lasting longer than a
week.
b. A planned outage for a distribution feeder upgrade where a large number of crews
are participating but are all essentially performing the same work at different
structures (e.g. replacing insulators).
Alternatively, some shorter projects (i.e. less than one week) may require the completion
of a Steps & Conditions Planning Chart due the complex nature of the work and/or the
involvement of multiple crews or disciplines, including contractors. Examples of this
type of project are:
a. The replacement of several damaged structures and conductor on a 138kV
transmission line.
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 15 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
b. Planned transmission line work that will be conducted if the transmission line is
to remain energized during the work.
c. The installation of a mobile generation unit at a substation.
It is the responsibility of the overall project supervisor to create, or designate a person
responsible to create, the Steps & Conditions Planning Chart. In doing so all relevant
documentation must be gathered and a meeting held with an individual, or individuals,
representing the relevant technical groups, work disciplines and contractors responsible
for the design and execution of the work. Attendance at the meeting by a representative
(s) from the appropriate hands-on work group, while not always practical, is strongly
recommended.
The Steps & Conditions Planning Chart shall break the job down into its major steps and
will identify the major hazards and required barriers associated with each hazard. The
plan shall also identify and document the conditions (or requirements) necessary to
ensure that each identified step can be completed safely and efficiently.
The Manager responsible for the overall planning of the project shall review and sign off
on the Steps and Conditions Planning Chart.
The Manager responsible for the overall planning of the project shall determine if the
project requires the use of Form 88 - Daily Project Safety Plan.
Upon approval of the Steps and Conditions Planning Chart, it is the responsibility of the
project site supervisor to ensure a Form 88 - Daily Project Safety Plan is held each day
with all Workers in Charge and individual employee working independently involved in
the execution of the work. The overall purpose of the Form 88 - Daily Project Safety
Plan is to review the overall planned project work for that day with careful emphasis on
highlighting the major hazards and the barriers that will be used to control them. The
Form 88 - Daily Project Safety Plan also documents who the Workers in Charge are,
what workers form part of each crew and any individual workers working independently
without a Worker in Charge.
Once the Form 88 - Daily Project Safety Plan meeting has been conducted, it shall be the
responsibility of each Worker in Charge or individual employee working independently
to conduct and document a tailboard conference at the worksite to reinforce
understanding of the overall plan as well as to assess the worksite for any specific
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 16 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
hazards that may be present for that particular employee or crew. Tailboard conferences
shall be conducted and documented on a daily basis using Form 85A - Tailboard
Conference Plan (Line Operations) and/or Form 85B - Tailboard Conference Plan
(Electrical/Generation) and/or an approved contractors hazard assessment form
(Tailboard) and shall include all workers present at the site, including contractors.
Completed Form 88 - Daily Project Safety Plan shall be forwarded to Area or
Departmental SWMS Coordinators for filing and retention as per the Master Health and
Safety Records List (MHSRL).
Procedural Checklist for Projects:
a. Prepare Engineering drawings, obtain permits and approvals.
b. Prepare Form 84 - Steps and Conditions Planning Chart – with input from the
relevant technical groups, work disciplines and contractors.
c. Indicate major hazards and controls on Form 84 - Steps and Conditions Planning
Chart.
d. Manager review and sign-off of the Steps and Conditions Planning Chart.
e. Manger to determine if this project requires the use of Form 88 - Daily Project
Safety Plan.
f. Provide drawings, permits and approvals to workers.
g. Conduct chalkboard meeting, communicate the plan.
h. Communicate requirement for tailboard meetings.
i. Monitor job progress.
5.5 Emergency Preparedness
Every job with major hazards associated with the work must be properly planned to
ensure that if an emergency occurs, there will be quick and appropriate action to mitigate
(to the extent that is reasonably practicable) any injuries which may occur on the site.
This emergency preparedness must be included as part of the tailboard discussions and
documented on the tailboard conference plan and must reference the following:
Who is responsible for initiating help in case of an emergency?
Detailed location of the worksite.
What the appropriate emergency contact numbers are for the location?
How will contact be made with emergency personnel (cell phone, radio, etc.)?
Availability and location of First Aid equipment.
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 17 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
Any other relevant information helpful in case of an emergency.
Posting of the emergency plan for larger projects.
When workers are working alone they should also consider the need to initiate a call-
back plan for the duration of the work they are about to perform.
5.6 Changes to the Job or Task
Whenever the scope of a job (with major hazards associated) changes, or when new
crews or workers are added to a job in progress, it is a requirement for the Worker in
Charge to brief the new crew or workers on the hazards and associated barriers as
outlined above. Should the scope of the work change, the job must stop and a re-
assessment of the hazards performed with all workers at the site so that appropriate
barriers can be implemented.
5.7 Power Restoration
When restoring power after a major outage, the requirement for effective communication
and risk management/job planning is integral to completing the work safely. Due to the
additional complexity of these emergency restoration projects, where many crews and
company personnel are on site for extended periods, extra caution and attention to detail
is required. Immediately after such projects the Director may request a post mortem
review to determine the effectiveness of the Risk Management and Job Safety Planning
process.
5.8 Monitoring the Risk Management and Job Safety Planning Program
In order to maintain the quality of the Risk Management and Job Safety Planning
Program, management is responsible for on-going monitoring of processes and providing
feedback and coaching to Lead Hands and work crews by:
a. Having all tailboard forms returned to the immediate supervisor at the end of
each day for review prior to forwarding to the HSMS Records Officer for filing.
b. Having supervisors assess each tailboard for the following key indicators:
Location adequately described
Emergency Plan information documented
Worker In Charge identified
Date Issued: 2009 08 31
Date Revised: 2020 06 16
Date Reviewed: 2020 06 16
Page 18 of 18
Risk Management and Job Safety Planning Code
Created By: B. Fitzgerald Reviewed By: R. Murdoch
Revised By: R. Murdoch Approved By: J. Curran
Adequate number of job steps identified for the scope of work
Hazards properly identified with specifics
Hazards properly classified (H,M,L)
Control, Safety and Support Barriers identified with specifics
Barrier Effectiveness Principle applied
Multiple Barrier Principle applied
Crew sign off
c. Having supervisors assess the tailboards (using same indicators above) while in
the field during visits to the job site and/or during formal Work Observations.
d. Providing positive feedback and recognition to Lead Hands where high quality
planning is evident and also providing coaching and direction when job planning
has not met an acceptable standard.
e. Reviewing tailboard forms at safety meetings especially to recognize tailboards
of high quality meeting all of the requirements of the Risk Management and Job
Safety Planning Code
f. Ensuring that Managers review (sign off) on Steps and Conditions Planning
Charts and provide the necessary feedback and coaching as required.