Handout 6.1.1 Risk Management Planning Workbook Unit 6
Handout 6.1.1 Risk Management Planning Workbook
This handout supports study and skills application in BSBRSK501A Manage Risk.
The handout is a complete workbook. It will form the basis for working through a formal risk management process.
By completing each Tool you will build all the components required for a basic Risk Management Plan. While Risk Management Plans may vary in
terms of focus and content across different organisations and operational areas, this workbook includes standard tools and templates. In
discussions with your facilitator or assessor you may choose to substitute tools in this workbook with alternatives, for instance ones you may use
in your organisation.
If you are being formally assessed for BSBRSK501A Manage Risk the submission of this workbook will provide evidence as to your competence.
There are ten tools and templates in this workbook.
Tool 1 - Goal and purpose and the alignment of risk categories and criteria......................................................................................................2
Tool 2 - Stakeholder identification and ranking template....................................................................................................................................... 3
Tool 3 - Risk register template.................................................................................................................................................................................. 4
Tool 4 - Task Analysis and Risk Identification Tool................................................................................................................................................ 5
Tool 5 - SWOT Analysis............................................................................................................................................................................................. 8
Tool 6 - PEST Analysis.............................................................................................................................................................................................. 9
Tool 7 - Identifying and Analysing Risks............................................................................................................................................................... 11
Tool 8 - Risk Assessment Matrix............................................................................................................................................................................ 12
Tool 9 - Risk Treatment Schedule and Action Plan.............................................................................................................................................. 13
Tool 10 – Risk Management Plan Request Form.................................................................................................................................................. 14
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 1 - Goal and purpose and the alignment of risk categories and criteria
Targeting Statements or description
Vision & Values
Including vision statement and any supporting values that the risk will impact.Goals
Including strategy, products, services, profitability, etc. likely to be impacted by the risk.
Describe the risk
Including how leaders are measuring goals (KPI) or impact.
Risk Category
List the risk category or elements of operations the risk will impact.
Criteria
Determine the likely impact of this level of risk if it is not treated.
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 2 - Stakeholder identification and ranking template
Team/Project/Operational Area:
Description of risk in brief:
Stakeholder Power* Interest*
Date Issued: Version:Responsible officer Contact:
* Use the Power and Influence Grid provided in your study guide to rank each stakeholder.
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 3 - Risk register template
Organisation:
Area: Date Issued:
Compiled by: Contact details:
Ris
k
Refe
ren
ce
The risk What can happen?
(event or type)
How can it
happen?
(source)
What can happen?
(impact)
Existing
controls?
Y = Yes
N = No
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 4 - Task Analysis and Risk Identification Tool
Company Name:
Position:
Job Identification:
Function/ Department:
Job Classification:
Assessor/Reviewer: Date of analysis:
Competency or Role:
Description: This role refers to the preparation and firing of shot in an open cut mining operation.
Job Steps Risk Possible impact
H=High
M=Moderate
L=Low
Notes on risk (ie. Affects safety, process, people, customers, etc.)
1.
2.
3.
4.
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Example:The following job has five major technical competencies/roles (1. Site preparation; 2. Shot firing; 3. Dangerous goods handling and transportation; 4. Safety; 5. Documentation and reporting). The Shot firing role has been examined by job steps for risks. Note: This is only an example.
Greater Eagle Mining
Position: Mining shot firer (Open Cut)
Job Identification: MIN233
Function/ Department: NT Mineral extraction
Job Classification: Grade 5
Assessor/Reviewer: Peter Bloggs Date of analysis: 11/10/2010
Competency or Role: 2. Shot firing – open cut
Description: This role refers to the preparation and firing of shot in an open cut mining operation.
Job Steps Risk Possible importance
H=High
M=Moderate
L=Low
Notes on risk (ie. Ability to address and possible impact - safety, process, people, customers, etc.)
1. Check drill holes Drill holes are not deep enough H Affect efficiency and success of firing
Drill holes have obstructions M May affect efficiency and success of firing
Drill holes are not placed correctly H Affect efficiency and success of firing
Size of holes is incorrect H Affect positioning of the shot
2. Check and place shot Shots have not been watered before scaling H Affect efficiency and success of firing
Incorrect loading H Affect efficiency and success of firing
Incorrect placement of loads in shot holes H Affect efficiency and success of firing
Issues affecting scaling are incorrectly determined H Affect efficiency and success of firing, may cause safety concerns for personnel (placement from shot)
3. Prepare safety equipment Incorrect personal protective equipment worn M Affects personal safety
Confirm all on site personnel correctly equipped H Affects safety of personnel
Personnel inappropriately equipped to deal with possible exposure to carbon monoxide and oxides of nitrogen
H Affects safety of personnel and can cause death
Duration or delay in firing may cause personnel to have longer exposure to the sun
L-M Affects safety of personnel
4. Check equipment and prepare for firing Shot lines are not all checked H Affect efficiency and success of firing
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Sequence of firing is incorrect H Affect efficiency and success of firing
Lines are exposed to elements that may affect signal M Affect efficiency and success of firing
5. Undertake warning and shot firing
communication to site and compliance
requirements
Communications devices are not working H Affect efficiency of firing and safety of personnel
Warning not done in adequate time H Affects safety of personnel and can cause death
Not all relevant personnel are aware of shot firing H Affects safety of personnel and can cause death
Hazard communication is not understood by personnel on site
M Affect efficiency of firing and safety of personnel
6. Fire shot Signal is not received by detonators H Affect efficiency and success of firing
Signal is triggered early or late H Affect efficiency of firing and safety of personnel
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 5 - SWOT Analysis
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 6 - PEST Analysis
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Example: The following is a ‘sanitised’ example of a PEST analysis completed by an Australian public health care organisation in mid 2009. The organisation supports public health services in a number of Australian states and in New Zealand.
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 7 - Identifying and Analysing Risks
Organisation: Compiled by: Date:
Function/Activity: Reviewed by: Date:
Ris
k R
efe
ren
ce
The RiskWhat Can Happen?
SourceHow can this Happen?
ImpactWhat will happen/
consequences?
Current control
Strategiesand their
effectiveness
(A) –Adequate(M) –
Moderate(I) –
Indadequate
Risk Analysis Risk Priority
Acc
epta
bili
ty (
A/U
)
Lik
elih
ood
Con
seq
uen
ce
Ris
k L
evel
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 8 - Risk Assessment Matrix
Category ↓ Consequence →→→
PeopleInjuries or ailments not
requiring medical treatment.
Minor injury or First Aid Treatment Case.
Serious injury causing hospitalisation or multiple medical treatment cases.
Life threatening injury or multiple serious
injuries causing hospitalisation.
Death or multiple life threatening injuries.
Reputation Internal Review
Scrutiny required by internal committees or
internal audit to prevent escalation.
Scrutiny required by external committees or ACT Auditor General’s Office, or inquest, etc.
Intense public, political and media scrutiny. Eg:
front page headlines, TV, etc.
Assembly inquiry or Commission of inquiry
or adverse national media.
Business Process & Systems
Minor errors in systems or processes requiring
corrective action, or minor delay without impact on overall
schedule.
Policy procedural rule occasionally not met or
services do not fully meet needs.
One or more key accountability
requirements not met. Inconvenient but not
client welfare threatening.
Strategies not consistent with
Government’s agenda. Trends show service is
degraded.
Critical system failure, bad policy advice or
ongoing non-compliance. Business
severely affected.
ComplianceLow-level breach with
limited follow up and no legal action
Breach with report required by
compliance body and possibility of later legal
action
Serious breach with investigation, report by compliance body and
possibility of legal sanctions
Major breach with penalty and possible
litigation
Serious breach, litigation occurs, and
investigation by professional, regulatory
or legislative body
Safety No injuryMinor injury requiring
treatmentMajor injury requiring
first aid treatment Major injury requiring
hospital treatment Death or major injury
Financial 1% of Budget or <$5K
2.5% of Budget or <$50K
> 5% of Budget or <$500K
> 10% of Budget or <$5M
>25% of Budget or >$5M
Minor Moderate Major Significant Catastrophic
Probability: Historical: 1 2 3 4 5
Lik
elih
oo
d →
→→
>1 in 10Is expected to occur in most circumstances
5 Very likely M H H E E
1 in 10 - 100Will probably occur
4 Likely L M H H E
1 in 100 – 1,000Might occur at some time in the future
3 Possible L M M H H
1 in 1,000 – 10,000Could occur but doubtful 2 Unlikely L L M M H
1 in 10,000 – 100,000
May occur but only in exceptional circumstances
1 Highly unlikely L L L L M(Adapted from Standards Australia Risk Management AS/NZS 4360: 2004)
E – Extreme risk – detailed action plan requiredH - High risk – needs senior management attentionM – Medium risk – specify management responsibilityL – Low risk – manage by routine procedures
High or Extreme risks must be reported to Senior Management and require detailed treatment plans to reduce the risk to Low or Medium.
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 9 - Risk Treatment Schedule and Action Plan
Organisation: Compiled by: Date:
Function/Activity: Reviewed by: Date:
Ris
k R
efe
ren
ce
Possible Treatment Options Result of cost-benefit
analysisA: acceptB: reject
Is the Treatment to be
Implemented
(Y/N)
Risk Analysis
Responsible Person TimetableFor implementation, Start – Finish date
Lik
elih
ood
Con
seq
uen
ce
Cu
rren
t
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Tool 10 – Risk Management Plan Request Form
Organisation: Operational Area- Context:
Risk Reference: Risk Title:
Level of Risk Low Risk Moderate Risks High Risk Extreme Risk
Proposed By:
Reviewed By:
Date Received: Allocate Request Number:
Proposed Treatment Description:
Risk Category:
People [ ] Safety [ ] Business process & systems [ ] Compliance [ ]
Procedural [ ] Finance [ ] Other [ ] specify:
Consequences if risk not treated:{Notes on how issue will impact context}
Treatment Objectives :{Notes on outcomes treatment and control will bring to the organisation or operational area}1.2.3.4.5.6.
Review:
Reviewer comments: {Notes by reviewer of this treatment}
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Recommendations: {Reviewer’s recommendations}
Date review completed: {MM/DD/YYYY}Analysis:
Risk assessment completed? No [ ] Yes [ ]
Cost: Benefit Analysis completed? No [ ] Yes [ ]
Supporting documents attached? No [ ] Yes [ ]
Planned Milestones for Monitoring and Review
List any milestones that are late as well as deliverables that can be monitored in the planned timeframe.
Milestone Approved Schedule{dd/mm/yyyy}
Actual{dd/mm/yyyy}
Current Forecast{dd/mm/yyyy}
Status*
* Status indicator:{Used to report monitor and review of treatment progress}
Green(Controlled)
Yellow (Caution)
Red(Critical)
Estimate of Additional Effort: (insert rows as needed)
Resources Required Work Days/Costs
Handout 6.1.1 Risk Management Planning Workbook Unit 6
Management Action:
{Senior management approval required for High and Extreme level risks}
Recommendation status:Accept [ ]Reject [ ]Defer [ ]
Approved Commencement Date: {MM/DD/YYYY}Planned Completion Date: {MM/DD/YYYY}
Assigned to:
Name Title Date(MM/DD/YYYY)
Comment
Approving Manager:
Signed….
I have reviewed the information contained in this Risk Management Plan Request and agree.
Date: _____/_______/______