12
River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008

River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment

  • Upload
    katoka

  • View
    54

  • Download
    2

Embed Size (px)

DESCRIPTION

River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment. Ray Spain Local Authorities Workshop, 3 rd December 2008. What is SEA?. Purpose to ensure that the environmental consequences are assessed during preparation and prior to adoption of RBMP - PowerPoint PPT Presentation

Citation preview

Page 1: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

River Basin Management Plans

& Strategic Environmental Assessment &

Appropriate Assessment

Ray Spain

Local Authorities Workshop, 3rd December 2008

Page 2: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

What is SEA?

Purpose • to ensure that the environmental

consequences are assessed during preparation and prior to adoption of RBMP

• to ensure the RBMP & POMs are as robust as possible in the context of the wider environment

Page 3: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

What is the Process?

• Screening – Is an SEA needed?

• Scoping – What should it include?

• Environmental Assessment and Report – Alternatives

• SEA Statement

Page 4: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

SEA Screening

• The statutory bodies responsible for SEA in Ireland and

Northern Ireland are

• DEHLG

• EPA

• DCENR

• Northern Ireland Environment Agency (formerly EHS)

The statutory bodies concluded that SEA is required for RBMPs

and POMs (2007) at a RBD level – 8 SEAs for the island of

Ireland

Page 5: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

SEA SCOPING• What should it include?

• Scoping ran in parallel, and fed into, the Water Matters (SWMI) Report

• Scoping is complete! for each of the 8 RBD’s.

• Scoping Documentis available for download atwww.serbd.com

Page 6: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

SEA Environmental Assessment Report

• ALL legislative requirements of Schedule 2 of the SEA Regulations (1 - 10)

– Information on the current state of the environment and likely evolution in the absence of the Plan (business as usual)

– Environmental protection objectives relevant to the plan

– Reasons for selecting the alternatives (supplementary measures)

– Likely significant effects on the environment

– Mitigation and monitoring measures

Page 7: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

SEA PROCESS

Screening

Overall MethodologyRBMP PROCESS

Initial Characterisation

ScopingSignificant Issues

Alternatives

Status / Risk / Possible Measures

Set Objectives

Action Programme

Objectives / Indicators / Targets

Environmental ReportDraft RBMP

Final RBMP SEA Statement

Consultation

Implementation & review cycle - 2nd RBMP

Page 8: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

Habitats Directive Assessment

(Appropriate Assessment)

– Habitats Directive, Article 6 (92/43/EEC)

– SACs, SPAs (Natura 2000 sites), and Ramsar Sites

– Narrow focus - maintaining integrity and conservation objectives of the site

– Protection led

– Precautionary

Four main steps

Screening

Appropriate assessment (avoidance first, then mitigation)

Assessment of alternative solutions

Assessment where no alternatives exist (compensatory measures)

Page 9: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

Appropriate Assessment

SEA PROCESS

Screening

Scoping

Alternatives

SEA Statement

Potential Impacts to

SAC / SPA

HABITATS DIRECTIVE ASSESSMENT

Assessment of Alternatives

Assessment Where No Alternatives Exist

Screening

Appropriate Assessment

Page 10: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

Role of SEA & HDA

• SEA in decision making

– Provides for high level of protection of the environment

– Informs decision making

– Assist in making more environmentally sustainable decisions

• HDA in decision making – more focused

– Maintains the integrity of site and its features

– Influences decision making

– Prevents development that could harm sites

Page 11: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

Integration with RBMP

• RBMP must show how this was done

• SEA– RBMP must have regard to SEA

• HDA – mitigation measures must be included in RBMP

Page 12: River Basin Management Plans &  Strategic Environmental Assessment & Appropriate Assessment

Timetable

Phase I: Environmental Assessment & Report (Jul – Dec 2008)

Phase II: Public Consultation (Jan – Jun 2009)

Phase III: Preparation of Submission Reports (Jul –Aug 2009)

Phase IV: Preparation of SEA Statements (Jul - Sep 2009)

Fixed Milestones: Draft RBMP 22 December 2008

Final RBMP 16 October 2009