RPC project status report
RPC IB meeting29 march 2011
Pigi Paolucci
RPC IB meeting - Pigi Paolucci 2
Agenda Approval: Agenda and minutes of the December
meeting
Organization chart endorsement
Resource manager proposal
Upgrade structure
M&O-B and MoA
2011 budget and manpower (RM)
TC-RC report
DPG Upgrade report
29/03/11
RPC IB meeting - Pigi Paolucci 3
Organization chart 2011-2012 organization chart was already
approved but not the upgrade structure
Let’s discuss the upgrade proposal and eventually endorse it. It is focused on the RE4 design and production
(2011-2012) We have time to improve the part related to the installation and commissioning (2013-2014)
In the next future we will come back to discuss about the “future upgrade” (2017-2018) organization.
29/03/11
RPC IB meeting - Pigi Paolucci 4
Project Manager P. Paolucci
M. Tytgat & G. Pugliese
Run Coordinator L. BenussiH. Shahzad
N. Zaganidis
DPG D. PiccoloK. Bunkowski
C. Carillo
Upgrade G. IaselliA. Sharma
S. Buontempo
Institution BoardL. Litov
Resource manager A. Colaleo
Steering committeeW. Van Doninck, M. Maggi
H. Hoorani, A. Colaleo,A. Sharma
(PM+DPM+RC+TC+DPG)
29/03/11
Tech. CoordinationS. Buontempo
A. Dimitrov
Conference Committee
S. Park, B. Pavlov
Editorial boardS. Qian, M. Abbrescia
S. Bianco
RPC IB meeting - Pigi Paolucci 5
Organization chart Main institutions have member in the organization
chart
All the RPC senior physicists have been contacted and most of them have now a clear position in the chart
Upgrade positions have to be assigned in the next months
Thanks everybody for the contribution given in the discussion and to who accepted to be part of the game
29/03/11
RPC IB meeting - Pigi Paolucci 6
Institution Board Leander Litov is the chairman of the Institution Board
since today.
RPC MB will closely work with him in all the aspect related to the Institution Board (see CMS constitution) Editorial Board, Conference Committee, new
institutions..
Next IB meeting will be managed by Leander
Editorial board and conference committee have to begin to work as soon as possible. We suggest to rotate the chairman every year and to choose the chair by yourself.
29/03/11
RPC IB meeting - Pigi Paolucci
Steering Committee
29/03/117
Chairman: Hafeez HooraniMembers: A. Colaleo, M. Maggi, A. Sharma,
W. Van Doninck
The RPC management board will consult the SC to get help on very urgent and crucial tasks and to solve delicate scientific issues.
The experience of the 5 senior physicists members is a guarantee for the RPC project and will help us a lot in the future.
RPC IB meeting - Pigi Paolucci 8
DPG D. Piccolo
K. Bunkowsk C. Carillo
Run Coordinator L. Benussi
H. Shahzad N. Zaganidis
SoftwareValidation/Data Certification
J. Gho
Detector perfomance
C. Calabria
OnlineK. Bunkowski
OfflineD. Piccolo
Detector & trigger analysisC. Carillo
Phys Valid ToolS. Costantini
Detector impact on
triggerResp.
Calibration Streams M. Maggi
WBMU. Berzano
Run QualityTae Jeong
Noise tools S. Costantini
DQM A. Cimmino
Skims S. Tupputi
Simulation B. Pavlov
Local RecoC. Carrillo
DataBase M. Maggi
Trigger DBM Szlepper
Configuration K. Bunkowski
DCS software
Detector DB
Manpower needed
Not covered
Covered
29/03/11
Non event data
P. Petkov
DPG-POG Min Suk Kim
UpgradeResp.
RPC IB meeting - Pigi Paolucci 929/03/11
Technical CoordinationS. Buontempo
A. Dimitrov
Mainten. & repair. (RE,RE)
Dimitrov & Shahzad
UpgradeG. Iaselli
A. Sharma S. Buontempo
Bakelite HPL
CERN test standCERN
Gap production
Chambermechanics
Ghent siteM. Tytgat
India siteL. Pant
CERN siteCERN
Chamber QC at CERN
Chamber design
Off-detectorelectronic
CoolingJ. Crotty
GasBenussi
TriggerWarsaw
DocumentationDimitrov
Equipment DBD. Uzunova
ElectronicsF. Loddo
DCS hardware
Resp.
Test beamNicolas
R&DN. Zaganidis
GIF activity
Power system
Power cable
Signal cableChamber
production
High eta
Chamber instal.
Cable instal.
Commissioning at P5RE1/1 at P5
Run coordination & Upgrade
Manpower needed
Not covered
Covered
RPC IB meeting - Pigi Paolucci 10
Critical task
• We still have few important tasks not covered:– Online Database (Warsaw is looking for a student)– Detector Control System (none)– Power system (temporary solution)– Offline Database (Bari group)– WMB (none from July 2011)
29/03/11
RPC IB meeting - Pigi Paolucci 11
Resource manager
• It is now time to assign the position of the resource manager (myself in the 2010)
• Resource manager is designed by the project manager and endorsed by the IB
• After having discussed with Gabriella and Michael, with some institution leaders and colleagues I would like to submit to you the name of Anna Colaleo
• She knows perfectly the RPC project and is now the national Italian representative (resource manager of the RPC Italian budget)
• Please to send me comments in the next 10 days and let us endorse the position via email
29/03/11
RPC IB meeting - Pigi Paolucci 12
News and goals HV scan and efficiency studies and FEB configuration
Very good collaboration with steering committee, RC/TC/DPG groups and CMS experts
It was a clear example of cross-coordination and coherent work
This is the way our collaboration should work and to do this we need: Task force group for special issue
Manpower flexibility
Usage of external experts from CMS and/or Institutions
Some budget; as usual
29/03/11
RPC IB meeting - Pigi Paolucci 13
Next issues Important issues to work on in the next month:
WBM deployment at CAF/P5 !!! manpower needed
DQM efficiencies and DB
Noise and DB
CMS center instructions for shifters – test pilot needed
Upgrade schedule and milestones
Upgrade money matrix
29/03/11
PVT
RPC IB meeting - Pigi Paolucci 14
Construction and docDB
29/03/11
I would like to remind you we have hired a DB expert (Daniela) to work for 3 months on the construction DB.
She is doing a very good job but is now stuck for lack of information and collaboration.
Question: if the construction DB is not on top of our list of priority I will close to task
Anton is supervising both the construction DB and docDB
RPC docDB is almost ready. We need to clean our twiki page
http://dev-cms.web.cern.ch/
RPC IB meeting - Pigi Paolucci 1529/03/11
field items FTE cost (K€) cost (KCHF)MANPOWER Detector reparation 0,50 16,8 25,2Electronic (TTU+FEB+CB) reparation 0,08 2,8 4,2HV-LV repar. And maint. 0,17 5,6 8,4HV-LV firmware upgrade 0,17 5,6 8,4
DCS - DQM - DB software upgrade 0,50 16,8 25,2DCS - DQM machine maint. 0,17 5,6 8,4
Sensors upgrade endcap upgrade endcap 0,17 5,6 8,4Gas gas test and reparation 0,33 11,2 16,8
Gas Monitoring repair and maint. 0,17 5,6 8,4Cooling repar. and maint. 0,17 5,6 8,4TOTAL 2,42 81,2 121,8MATERIALS
chamber maintenance detector 6,67 10
Server (5 DCS + 3 DQM + 3 GGM) upgrade (every 2-3 years) 3,33 5,0FE electronics spare and maintenance 16,67 25,0HV-LV spares 0,00 0,0HV-LV-ADC CAEN maintenance 21,33 32,0HV-LV-ADC cable, connect. distrib 5,33 8,0Areas P5 lab - ISR- GIF - 904 infrastr. 16,67 25,0
Gas Monitoring materials 10,00 15,0
Gas Monitoring spares 3,33 5,0
Electronic Pool - CERN store 12,67 19,0
Communication telephone for shifters and experts 2,00 3
TOTAL (maintenance and reparation) 91,3 147,0
Grand Total 172,5 268,8
M&O-B table 2011
RPC IB meeting - Pigi Paolucci 16
M&O-B 2011 - sharing
29/03/11
M&O 2010 # ESPAmount due
KCHF Manpower Cash Approved
Peking univ 2 6,4 3,2 3,2
SKK Univ (Korea) 2 6,4 38,4 Korea
Korea Univ (Korea) 10 32,0
Chonnam (Korea) 0 0,0
Mumbai-Barc (India) 1 3,2 3,2
Chandigarh (India) 3 9,6 1,5 8,1
Ghent (Belgium) 9 28,8 28,8
Brussel Univ (Blgium) 1 3,2 3,2
Uniandes 2 6,4 6,4
Pakistan 6 19,2 9,6 9,6
Asrt-Enhep (Egypt) 3 9,6 5,1 4,8
CERN 4 12,8 12,8
Bari 12 38,4
LNF 5 16,0
Napoli 9 28,8 92,8 Italy YES
Pavia 3 9,6
Sofia Univ 6 19,2 9,6 9,6
Sofia INRE 6 19,2 9,6 9,6
RPC TOTAL 84 KCHF 268,8 KCHF 38,6 KCHF 230,5
RPC IB meeting - Pigi Paolucci 17
M&O-B trend 2010-2015
29/03/11
2010 2011 2012 2013 2014 20150
50
100
150
200
250
300
350
400
450
500
TotalHired ManpowerSpares
RPC IB meeting - Pigi Paolucci 18
2011 manpower status
• Mircho 3 monthsMay
• Umberto 3 months (+ 3 from CERN) June• Anton 12 months
Dec• Alaa 3 months (+ 3 from Egypt)
Aug• Cimmino 2 months
Feb• Uzunova 3 months
May• Tech 2
Jan/Feb-------------------------------------------
Total 28 months 120 KCHF + ?
29/03/11
RPC IB meeting - Pigi Paolucci 19
2011-2012 manpower positions
• We have two very critical position to assure for the next two year:– Detector expert– Trigger and DAQ expert
• Since the last years the positions are covered in the best way by Anton and Karol
• Karol fellow finish in Sept 2011• Anton contract finish in June 2011
29/03/11
RPC IB meeting - Pigi Paolucci 20
2011-2012 manpower positions
• I would like to submit to you the following proposal:
Detector Expert - Anton• Extend the Project Associate to the December
2011 - 6 monthsTrigger and DAQ expert - Karol• Support the fellow extension of 6 months• Prepare a PA until the end of 2012 (shared with
CMS trigger project) – 8-10 months29/03/11
RPC IB meeting - Pigi Paolucci 21
2011 Budget status
• Material cost (march 2011) 8.5 KCHF• Material cost estimate
40.0 KCHF• Manpower present cost 120.0
KCHF• Manpower estimate 60.0
KCHF• Varie
10.0 KCHF• Total
238.5 KCHF
• 2011 contribution230.0 KCHF
29/03/11
RPC IB meeting - Pigi Paolucci 22
2010 budget carry over
• 2010 Cash contribution 269 KCHF -• 2010 expenditure (2009 debt included) 213 KCHF
--------------------------• 2010 carry over = 56 KCHF -• Jan/Mar 2011 expenditure 55
KCHF------------------------------Present budget = 1 KCHF
• We need to open the 2011 contributions
29/03/11
RPC IB meeting - Pigi Paolucci 23
ESP 2011
• ESP 2011 are now in production• Few bugs have been fixed today• 2010 pledges were not well done !! Be careful this year• Pledge will be closed in 2 weeks from now:
– Shift are automatically linked to the ESP (we don’t have to pledge shifts)
– We don’t have to exceed the needed FTE– MB will check the pledges and will approve only the work really done
and certified by the coordinators– Please contact coordinators and MB for any question or doubt before
inserting any pledge.
• Data and Operation Manager are at 50% CMS central shift29/03/11
RPC IB meeting - Pigi Paolucci 24
Project Activity Task Needed (months) Fte Total x cat.
Muon-RPC Detector Hardware Technical coordinator 6,00 0,50Muon-RPC Detector Hardware Chamber 10,00 0,83Muon-RPC Detector Hardware Electronics 3,00 0,25Muon-RPC Detector Hardware Services 3,00 0,25
Muon-RPC Electronics and DAQ Power System 3,00 0,25Muon-RPC Electronics and DAQ DCS-DSS 3,00 0,25Muon-RPC Electronics and DAQ Electronic configuration 10,00 0,83Muon-RPC Electronics and DAQ Gas Gain Monitor 3,00 0,25Muon-RPC Electronics and DAQ DAQ and online DB 4,00 0,33
45,00Muon-RPC Software and DQM DPG coordinator 6,00 0,50Muon-RPC Software and DQM DQM 12,00 1,00Muon-RPC Software and DQM DCS & WBM 12,00 1,00Muon-RPC Software and DQM PVT 6,00 0,50Muon-RPC Software and DQM Simulation 4,00 0,33Muon-RPC Software and DQM Database 10,00 0,83Muon-RPC Software and DQM Prompt Analysis 36,00 3,00
86,00Muon-RPC Operation Run coordinator 6,00 0,50Muon-RPC Operation Operation Manager shift* 11,00 0,92Muon-RPC Operation CAF shift* 11,00 0,92Muon-RPC Operation Data Manage shiftr* 11,00 0,92
39,00Muon-RPC Operation Upgrade coordinator 6,00 0,50Muon-RPC Upgrade Software 4,00 0,33Muon-RPC Upgrade Bakelite production and test 3,00 0,25Muon-RPC Upgrade Gap production 8,00 0,25Muon-RPC Upgrade Chamber design 2,00 0,25Muon-RPC Upgrade Chamber construction 24,00 2,00Muon-RPC Upgrade Chamber test at 904 7,00 0,58Muon-RPC Upgrade Front-end electronic 3,00 0,25Muon-RPC Upgrade Trigger electronic 7,00 0,58Muon-RPC Upgrade Services 4,00 0,33Muon-RPC Upgrade R&D at high eta 2,00 0,17Muon-RPC Upgrade Simulation at high eta 2,00 0,17
72,00Muon-RPC Management LV3 24,00 2,00Muon-RPC Management LV2 IB - CC - EB chairman 3,00 0,25Muon-RPC Management LV2 steering committee 3,00 0,25
272,00 21,33
29/03/11
RPC IB meeting - Pigi Paolucci 25
ESP – short instructions
• Before pledging anyone please contact the coordinator and the MB to discuss about the number of months.
• Example: – LV3 management is 1 month max– Steering committee is 3 months / 5 people– LV2 IB - CC - EB chairman is 3 months/ 6 people– LV3s can also pledge work on the specific item– LV1 is not an ESP – no pledge– Shifts cannot be pledged
29/03/11
RPC IB meeting - Pigi Paolucci
2011 Agenda
29/03/1126
General Meeting: Thursday at 9:30 (1 per month)DPG/RC: Thursday at 9:30 (3 per month)Tech coordination: Monday at 9:00 (weekly)Upgrade: Tuesday at 9:00 (weekly)Management: Wed at 10:00 (weekly) restricted ISR meeting: Monday 14:00 (weekly) technical
904 meeting: Wed 10:00 (weekly) technical
GEM meeting: Tuesday 14:00 (weekly) technical
Upgrade RE4 Workshop to be decidedUpgrade High Eta Workshop to be decided
Let me ask the 4 coordinators and deputies to actively participate to the 3 weekly meetings. Unique project
RPC IB meeting - Pigi Paolucci 27
RPC “social” dinner tonight at 20:30
29/03/11
La Villa du Lac – Divonne Les Bains
It is just in front le lake
Sorry but not more than the 34 people already registered
From Highway:
1. after the “douane” go straight
2. turn right at the second roundabout
3. After 400 meter there is a roundabout, go straight
4. The Hotel is on the left
From GEX:
1. Follow “highway to Geneve” indication.
2. Then indication to “promenade” or “Villa du Lac”
RPC IB meeting - Pigi Paolucci 28
Conclusion Project is in good shape and many improvements
have been done during the 2010-2011 shut-down
ESP pledge letters deadline is in 2 weeks.
Manpower: DCS – WBM – Online experts – detector expert
2010 expenditure were in line with our budget 269 KCHF
2011-2012: we have to cover 2 critical tasks
2011 budget is necessary – contribution request in few days
29/03/11