4
RPC UK Limited 1 The Courtyard, Hawksworth Est., Thorpe Lane, Guiseley, Leeds, LS20 8LG t. f. e. w. 01943 222 001 0870 432 8424 [email protected] www.rpc.uk.com Page 1 of 4 Dave’s Tips 25: Future Period Bucket Planning (Primavera P6.x, P6 v7, P6 Rel 8.x) INTRODUCTION Future Period Bucket Planning allows a Planner/Scheduler to enter a custom distribution, or spread, per resource or role assignment, to model resource requirements in a way that truly reflects how the work is planned and performed. When staffing a project, most people staff their project by the day, week or month. Future Period Bucket Planning allows a resource assignment to start and stop anytime over the duration of the activity. Future Period Bucket Planning also allows changes to be made to resource assignments to ensure that resources are not over- or under-allocated for a specific time period. HOW When you specify an activity's total budgeted or planned units, the budgeted or planned units for an assignment to that activity are spread evenly across the duration of the activity, in the timescale increment you choose. In this example the Plumber has been assigned to work 8 hours per day for 10 days. Fig 1.0 Note the “Curve” column is empty (see Fig 1.0). However, your projects may contain activities for which you know work will be performed sporadically and at varying levels of effort. For these activities, you can do either of the following to more accurately capture when you plan for work to be performed on an activity: Assign a curve to a resource or role assignment. Manually enter future period assignment values (bucket planning) While assigning a resource curve to the resource/role assignment will yield more accurate results than spreading units evenly across the duration of an activity, the work you plan to perform per period on an activity may not be fully reflected by the curve. As a result, performance against the project plan cannot be accurately measured.

RPCTIP25 - Future Bucket Planning

Embed Size (px)

DESCRIPTION

Bucket Planning

Citation preview

Page 1: RPCTIP25 - Future Bucket Planning

RPC UK Limited

1 The Courtyard,

Hawksworth Est., Thorpe Lane,

Guiseley, Leeds, LS20 8LG

t.

f.

e.

w.

01943 222 001

0870 432 8424

[email protected]

www.rpc.uk.com

P a g e 1 o f 4

Dave’s Tips 25: Future Period Bucket Planning

(Primavera P6.x, P6 v7, P6 Rel 8.x)

INTRODUCTION

Future Period Bucket Planning allows a Planner/Scheduler to enter a custom distribution, or

spread, per resource or role assignment, to model resource requirements in a way that truly

reflects how the work is planned and performed. When staffing a project, most people staff their

project by the day, week or month. Future Period Bucket Planning allows a resource assignment

to start and stop anytime over the duration of the activity. Future Period Bucket Planning also

allows changes to be made to resource assignments to ensure that resources are not over- or

under-allocated for a specific time period.

HOW

When you specify an activity's total budgeted or planned units, the budgeted or planned units for

an assignment to that activity are spread evenly across the duration of the activity, in the

timescale increment you choose.

In this example the Plumber has been assigned to work 8 hours per day for 10 days.

Fig 1.0

Note the “Curve” column is empty (see Fig 1.0).

However, your projects may contain activities for which you know work will be performed

sporadically and at varying levels of effort. For these activities, you can do either of the following

to more accurately capture when you plan for work to be performed on an activity:

• Assign a curve to a resource or role assignment.

• Manually enter future period assignment values (bucket planning)

While assigning a resource curve to the resource/role assignment will yield more accurate results

than spreading units evenly across the duration of an activity, the work you plan to perform per

period on an activity may not be fully reflected by the curve. As a result, performance against the

project plan cannot be accurately measured.

Page 2: RPCTIP25 - Future Bucket Planning

RPC UK Limited

1 The Courtyard,

Hawksworth Est., Thorpe Lane,

Guiseley, Leeds, LS20 8LG

t.

f.

e.

w.

01943 222 001

0870 432 8424

[email protected]

www.rpc.uk.com

P a g e 2 o f 4

For example, the “Bell Shaped Curve” has been assigned to this resource and this is reflected in

the spreading of the units (See Fig 1.1).

Fig 1.1

To achieve the most precise resource/role distribution plan, you can manually enter the budgeted

or planned resource/role allocation per assignment in the timescale unit you choose (days,

weeks, months, quarters, years, or financial periods). For example, assume an activity has an

original or planned duration of 10 days and budgeted or planned units of 80 hours. For this

activity, you know that the actual work will not be spread evenly across the duration of the

activity; rather, the budgeted or planned units will be spread as follows:

Fig 1.2

Note how the curve is set to “Manual” indicating the manual loading of units (See Fig 1.2).

The other feature of bucket planning is that if you change the budgeted units of the activity, the

spread will be pro-rated according to the last spread.

Fig 1.3

In the example above (Fig 1.3), not how the budgeted units has been

changed to 120 and the spread is prorated to the original allocation.

Page 3: RPCTIP25 - Future Bucket Planning

RPC UK Limited

1 The Courtyard,

Hawksworth Est., Thorpe Lane,

Guiseley, Leeds, LS20 8LG

t.

f.

e.

w.

01943 222 001

0870 432 8424

[email protected]

www.rpc.uk.com

P a g e 3 o f 4

By manually entering the planned resource/role distribution in future period assignment buckets,

you can create an accurate baseline plan to measure against current project progress. As the

current project schedule progresses and you apply actuals, you can track how the project is

performing against plan by comparing the project’s budgeted or planned future periods to the

current project’s actuals.

If work on an activity is not proceeding according to plan, you can manually update the remaining

units for an assignment's future periods, enabling you to measure the remaining work for an

assignment without changing the original plan. Alternatively, if you choose to re-estimate future

work based on changes to the project schedule, you can edit an assignment's future period

budgeted or planned units while the activity is in progress; if many assignment's require re-

estimation, you can establish a new baseline plan based on your changes.

TIPS

You can compare the planned future period resource distribution to actual units and costs in the

Resource Usage Profile, Resource Usage Spreadsheet, Activity Usage Profile, Activity Usage

Spreadsheet, time-distributed reports, and the Tracking window. If you plan your project work in

defined financial periods, after you store period performance, you can compare the resource

distribution you planned to the project's past period actuals. See Store Period Performance.

Activity costs, including earned value and planned value, are calculated using the planned future

period resource distribution you define for activity assignments.

Note - You must have the 'Edit Future Periods' project privilege to manually enter future period

data.

RPCuk Knowledge Zone

In keeping with our philosophy of adding value, we want our clients, partners and explorers of

our web site and newsletter subscribers to view their interaction with RPCuk as a rewarding

experience.

We believe that knowledge transfer is an integral part of any relationship and, over the years, we

have acquired a wealth of experiences and learned - usually the hard way! - some useful tips and

tricks which we are more than happy to share.

We will regularly be publishing briefings on a variety of project management and planning topics

that may be of interest. In addition, we intend to offer useful tools and links to other resources

through our RPCuk Tips and Tricks Section.

Page 4: RPCTIP25 - Future Bucket Planning

RPC UK Limited

1 The Courtyard,

Hawksworth Est., Thorpe Lane,

Guiseley, Leeds, LS20 8LG

t.

f.

e.

w.

01943 222 001

0870 432 8424

[email protected]

www.rpc.uk.com

P a g e 4 o f 4

If you have not already done so, sign up to the RPCuk electronic newsletter and keep checking the

Knowledge Zone for more Oracle Primavera P6 hints, tips and shortcuts.

We hope you find the knowledge zone useful and informative. If you would like to contribute to

the knowledge zone or indeed have any topics / suggestions please feel free to contact us on

01943 222001 or by emailing [email protected] – any feedback would be most

welcome.