35
RWA, 15/6/2007 1 R. Assmann, AB R. Assmann, AB LHC MAC LHC MAC June 15 June 15 th th , 2007 , 2007 Collimation System Collimation System Update Update

RWA, 15/6/2007 1 R. Assmann, AB LHC MAC June 15 th, 2007 Collimation System Update

Embed Size (px)

Citation preview

RWA, 15/6/2007 1

R. Assmann, ABR. Assmann, AB

LHC MACLHC MAC

June 15June 15thth, 2007, 2007

Collimation System UpdateCollimation System Update

RWA, 15/6/2007 2

The LHC Collimation System

• System is powerful but complex:

– 160 locations160 locations in the ring.

– 28 locations28 locations in the transfer line.

– 8 types of collimators8 types of collimators plus various types of masks and absorbers.

– A path is defined from initial to nominal and ultimate intensities (upgradesupgrades).

– Different interfacesDifferent interfaces depending on neighboring equipment and on level of induced radioactivity.

Phase # elements

Initial 9494

Upgrade 1 4444 (all prepared)

Upgrade 2 22

RWA, 15/6/2007 3

System Overview

MomentumCleaning

BetatronCleaning

“Phase 1”

“Final” system: Layount is 100% frozen!

RWA, 15/6/2007 4

Functional Description

• Two-stage cleaning (robust CFC primary and secondary collimators).

• Catching the cleaning-induced showers (Cu/W collimators).

• Protecting the warm magnets against heat and radiation (passive absorbers).

• Local cleaning and protection at triplets (Cu/W collimators).

• Catching the p-p induced showers (Cu collimators).

• Intercepting mis-injected beam (TCDI, TDI, TCLI).

• Intercepting dumped beam (TCDQ, TCS.TCDQ).

• Scraping and halo diagnostics (primary collimators and thin scrapers).

RWA, 15/6/2007 5

The LHC “TCSG” Collimator

360 MJ proton beam360 MJ proton beam

1.2 m1.2 m

3 mm beam passage with RF contacts for guiding image currents

Designed for maximum robustness:

Advanced CC jaws with water cooling!Advanced CC jaws with water cooling!

Other types: Mostly with different jaw Mostly with different jaw materials. Some very different with 2 materials. Some very different with 2 beams!beams!

For design see TS seminar A. Bertarelli.

RWA, 15/6/2007 6

Hardware Procurement...

Major contracts:Major contracts:

Collimators (FR)Collimators (FR)

Motors and sensors (D)Motors and sensors (D)

Position sensors (FR/China)Position sensors (FR/China)

CFC (J)CFC (J)

Supports (Bulgaria)Supports (Bulgaria)

Vacuum pumping ports (Italy)Vacuum pumping ports (Italy)

Material/screws (Switzerland)Material/screws (Switzerland)

Glidcop material (US)Glidcop material (US)

PXI low level controls (H/US)PXI low level controls (H/US)

Motor drivers + supplies (Italy)

RWA, 15/6/2007 7

Status of Collimator Procurement

• The 118 collimators and absorbers for the initial phase must be procured:

• Series production ongoing for the initial phase:

– Industry: 108 in total (including 6 upgrade collimators)

80 ring collimators (+12 spares) and 14 transfer line collimators (+ 2 spares).

– CERN: 32 in total (including 8 collimators taken over from

CERCA)

18 ring collimators/absorbers (+ 4 spares) and 10 transfer line masks

Phase # elements

Initial 94 (ring) + 24 (TL)94 (ring) + 24 (TL)

Upgrade 1 4444 (all prepared)

Upgrade 2 22

(including 2 TCDD, 2 TCLIM, 8 TCAP)

(including 4 TCLP, 8 TCHS, 2 TCLA)

RWA, 15/6/2007 8

Industrial Production

0

2

4

6

8

10

12

De

liv

ere

d C

oll

ima

tors

Time

Planning

Delivered (TL)

Delivered bad (ring)

Delivered good (ring)

Production has just reached its peak rate of 12 collimators per month!

The production crisis during the second half of 2006 has been overcome!

RWA, 15/6/2007 9

Industrial Production (Integrated)

0

20

40

60

80

100

120

Date

# co

llim

ato

rs

We have received 1/3 of the collimators1/3 of the collimators from industry.

October 2007October 2007: All collimators for installation can be available, if no other crisis!

There was a production crisis from July to December 2006!

spares

Crisis

RWA, 15/6/2007 10

Problem Collection I

Brazing

Ni-Cu coating RF fingersVacuum feedthroughs

Coating

TS/MME analysis of problems

RWA, 15/6/2007 11

Production Collection 2TCS010 after bake-out (8 Sep 2006)

0.00E+00

1.00E-08

2.00E-08

3.00E-08

4.00E-08

5.00E-08

6.00E-08

7.00E-08

8.00E-08

9.00E-08

1.00E-07

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105

Mass

Pa

rtia

l Pre

ss

ure

[u

nc

alib

rate

d]

Oil Pollution

Welding

RF fingers

AT/VAC and TS/MME analysis of problems

RWA, 15/6/2007 12

Overcoming the Crisis...

• Production of conform collimators stopped in August 2006 due to severe quality problems in the production company. Main problems:

– Machining of UHV parts with oil-based cooling fluids.

– Insufficient UHV cleaning.

– Non-conform surface coating and brazing problems.

– Lack of quality control from contractor.

• Problems appeared when production rate was supposed to go up.

• Status August 2006: 14 collimators produced, 8 only acceptable.

• Strong TS involvement starting in September 2006 to correct situation together with AB and AT:

– Review, documentation and transfer of all detailed CERN procedures, as used for construction of prototype collimators in TS.

– Some critical production steps done at CERN while contractor corrects problems.

– TS/MME leading production control on site of contractor and sub-contractors.

– AT/VAC program to establish UHV: 15 tests of collimators components made between 6/11/06 and 6/12/06 + assistance in Romans to CERCA. 

• Quite some effort required: 1600 TS staff hours from Oct-Dec 2006 plus important AB/AT resources. TS/MME and AT/VAC presence at CERCA during Christmas holidays.

RWA, 15/6/2007 13

Achievements

• All technical issues solved and production was restarted.

• Collimator quality acceptable but not perfect for first 2007 collimators (e.g. only partial tank cooling for some collimators) handled without impact on collimation performance (e.g. locating first collimators at low power locations or repairing at CERN).

• Peak production rate of 12 collimators in 1 month was achieved in May.

• Collimator production is in industrial mode.

• The full minimal system is at CERN (basic two-stage betatron and momentum cleaning) ready for originally foreseen 450 GeV run and up to ~15 nominal bunches at 7 TeV.

• Production now focuses on W collimators. In September 2007:

– cleaning performance reach at ~20% of nominal intensity.

– triplet protection collimators available.

RWA, 15/6/2007 14

Production Process

TanksJaw supports

BellowsCleaning

Parts

Pressure tests

Company has built a stock of pre-assembled parts. Procedures in place.

RWA, 15/6/2007 15

Production Process

Jaw assembly

Assembled collimator Mechanical table

Brazing controlAlignment & calibration

Collimators are handled in parallel at their different stages higher rate!

RWA, 15/6/2007 16

Production Process

EB welding

Vacuum & bakeout

Packed & ready for shipment

RWA, 15/6/2007 17

WorkflowW

ork

flo

w

RWA, 15/6/2007 18

Completion Other Components I

• Supports and quick plug-ins:

– All phase 1 standard supports installed. Allmost all completed with plug-in: final work in LSS7R ongoing (waiting for completion of warm magnet tests).

– Alignment campaign planned (next week LSS1 then LSS7).

– Phase 2 base supports are at CERN but installation to be completed.

– Cabling electrical plug-in: 100 out of 112 are ready.

– Cooling water: All tappings with valves installed. Special flexibles are at CERN, standard flexibles from TS/CV. Connection, adjustment, final pressure test to be done.

• Radiation hard stepping motors and resolvers (50 MGy):

– All ~550 at CERN. Rejection for ~50, due to insufficient insulation of resolvers.

• Position sensors LVDT‘s:

– 750/750 produced and tested. 5 rejected. Ready for mounting.

• Microswitches:

– 1500/1500 produced and tested.

RWA, 15/6/2007 19

Completion Other Components II

• Cabling:

– Long cables all ordered in standard campaign. All installed except LSS2.

– Final ~5 m cable connections (radiation hard) all ordered by TS/EL. Installed in LSS3 and few other positions (LSS8 and TI8).

– Cables of interconnection among racks (interlocks, triggers, timing, ...) all ordered (TS/EL) but not installed yet.

• Racks:

– Racks all installed in the 7 IR‘s with collimators.

• Stepping motor drivers:

– 10/510 ready. 100 more will arrive next Tuesday. Not critical (all there in September)

– Delay due to EM emission and long cable required modifications. Now fixed.

• PXI low level controls:

– All delivered by NI.

Outside of m

ain tunnel

RWA, 15/6/2007 20

Other Procurement

First series production of stepping motors with 50 MGy radiation-hardness. High

numbers now available for mounting on collimators.

Design based on ITER R&D and early prototyping. Solution was adapted to CERN

needs and transformed into industrial process (9 month effort AB/ATB + industry).

RWA, 15/6/2007 21

Cooling Water Issues

• Manifolds for water connection at collimator support were found to have bad welding: No issue for the early years but we must replace them to avoid problems in some years. Try to do it before 2008 startup but not required..

• Cooling water in the collimator must be regulated with an accuracy of about 10%:

– Water velocity must be high enough to handle heat loads from the beam (up to 7kW – is a function of beam intensity and loss rates).

– Water velocity must be lower than 3 m/s to avoid erosion/corrosion.

– Water loads will change after any change in collimator complement (upgrade).

• Prototype tests for radiation-hard regulation valves are ongoing. Procurement in August - October and installation in October/November (no impact on vacuum integrity).

• No showstopper (can always implement a temporary solution) but we are watching this carefully…

RWA, 15/6/2007 22

Final Assembly at CERN

Final assembly restarted with full speed end of April.Final assembly restarted with full speed end of April. Major effort AB/ATB group.

Collimators can be installed after leaving the final assembly hall in B.252!

So far 10 collimators installed10 collimators installed!

0

20

40

60

80

100

120

Date

# c

oll

ima

tors

spares

Final assembly completed!

Industrial production

RWA, 15/6/2007 23

Acceptance at CERN

RWA, 15/6/2007 24

Example: Criteria

RWA, 15/6/2007 25

Support & Plug-In Installation

LSS5

Almost all ready in the 7 IR‘s with collimators.

Survey and alignment done with quick-plugin supports and without collimator (precise reference from plug-in and alignment tool).

RWA, 15/6/2007 26

Collimator Installation Preparation

Delroux et al

RWA, 15/6/2007 27

Collimator Installation

Quick plug-in support (10 min installation)

RWA, 15/6/2007 28

Ring Collimators Installed in IR6

IR6 collimators are part of the dump protection system of the LHC.

Special installationSpecial installation due to space constraints with the dump line.

These 2 like some others with only partial tank coolingpartial tank cooling (welding problem on tank: predicted to be no problem as low heat load expected).

RWA, 15/6/2007 29

Collimator Transport Vehicle

Start of training for collimator installation with upgraded vehicle (K. Kershaw et al).

RWA, 15/6/2007 30

Collimator Installation

• All required installation tools are operational.

• Collimators are being produced at higher rate now. May was a very important milestone. Most difficult collimator design (8 two-beam collimators) likely transferred to CERN production.

• A detailed production planning up to the end will be provided by the company by mid-June (difficult). Somehow mixed with contractual negotiations.

• Planning for not-completed in-house production is being established with TS (depends on decisions with CERCA).

• Optimized collimator installation planning is being worked out with the LHC installation planning group:

– Install the collimators we receive up to January 2008 to have complete collimation system for 2008 run. Compatibility with production progress.

– Minimize interference with other work: group by vacuum sectors, synchronize with vacuum workflow, synchronize with alignment, HWC constraints, ….

RWA, 15/6/2007 31

Production Priorities Draft ICERCA -> Bld 252TCP TCS G/M TCLIB TCT H/VA TCLA TCL TCDI TCTVB TCLIA

10 82 2 12 20 4 24 4 2PHASE I (1st run 7TeV) 8 32 2 12 18 4 24 4 2Upgrade 1 30 2Upgrade 2 2 20

InstalledTCSG.4L6.B2 TCTH.4L8.B1 ?TCSG.4R6.B1 TCTH.4R8.B2

AVAILABILITY FOR THE TRANSPORTTCSG.A5L3.B2

TCSG.4L3.B2

TCP.B6R7.B2 TCSG.4R3.B1

TCP.C6R7.B2 TCSG.A5R3.B1

TCSG.A4L7.B1

TCSG.A4R7.B1

TCSG.A4L7.B2

TCP.D6R7.B2

TCSG.A4R7.B2

TCP.D6L7.B1

TCSG.A6R7.B2

TCSG.6L7.B2

TCSG.A5R7.B2

TCP.C6L7.B1

TCSG.5R3.B2

TCSG.B5R3.B1

TCSG.5L3.B1

TCSG.6R7.B1

TCP.B6L7.B1 TCSG.A6L7.B1

TCSG.A5L7.B1

TCP.6R3.B2

TCP.6L3.B1

TCTVA.4R5.B2

TCTH.4R5.B2

TCTVA.4L5.B1

TCTH.4L5.B1TCDI.TCDI.

1st target --> mid-July : the first 30 collimators must be ready to be installed

under approval

29

CERCA -> TS-MME

30

28

27

26

25

24

A4L3

A4R3

B5L3

B5R3

A5R3

A5L7

A6L7

B5L7

B5R7

A5R7

A6R7

Test of the Warm

Magnets Point7

IP7

B4L5

B4R5

sectors with chamber supports which could be closed :

A4L1A4L2A7L3B4L5A7L7A4L8A4R1A4R2A7R3B4R5A4L7A4R8A5R1A6R2________A4R7____

IN WORK...JUN

EJU

LY

J. Coupard et al

RWA, 15/6/2007 32

Production Priorities Draft IICERCA -> Bld 252TCP TCS G/M TCLIB TCT H/VA TCLA TCL TCDI

TCTVA.4R5.B2

TCTH.4R5.B2

TCTVA.4L5.B1

TCTH.4L5.B1TCDI.TCDI.TCDI.TCDI.TCDI.TCDI.

TCLA.A7L7.B2

TCLA.A7R7.B1

TCLA.D6L7.B2

TCLA.C6L7.B2

TCLA.B6L7.B2

TCLA.A6L7.B2

TCLA.A6R7.B1

TCLA.B6R7.B1

TCLA.C6R7.B1

TCLA.D6R7.B1

TCSG.D4L7.B1

TCSG.D4R7.B2

TCSG.B4L7.B1

TCSG.B4R7.B2

TCSG.E5L7.B2

TCSG.D5L7.B2

TCSG.B5L7.B1

TCSG.B5L7.B2

TCSG.E5R7.B1

TCSG.D5R7.B1

32

33

34

35

1st target --> mid-July : the first 30 collimators must be ready to be installed

2nd target --> mid-September : 6 TCDI and 14 TCT/TCLA must be ready to be installed

36

37

38

29

30

31

A7L7

A7R7

A4L7

A4R7

IP7

A5L7

B4L5

B4R5 IN WORK...

JULY

AUG

UST

SEPT

EMBE

R

J. Coupard et al

RWA, 15/6/2007 33

Draft Sequence: Optimized Installation-Readiness

TI2/LSS8(May - Jul 06)

LSS6(Feb 07)

LSS3/7(Jan - Jun 07)

LSS3/7(Aug - Oct 07)

LSS5(Jul 07)

TI8(Jul - Aug 07)

LSS2/8(Oct 07)

LSS1(Oct - Nov 07)

LSS2(Nov 07)

LSS5(Nov 07)

LSS1(Nov 07)

LSS2(Nov 07)

LSS8(Nov - Dec 07)

LSS3/7(Jan 08)

January 2008: Goal is full phase 1 completion. Ready for high activation, high luminosity, non-standard *.

Present status:The minimal system is there.

Ready for high intensities but not high activation.Planning quite uncertain: detailed planning from CERCA needed, including material status.

Ongoing work. Being optimized further… Sequence of vacuum sectors exists.

RWA, 15/6/2007 34

Conclusion I

• The collimator production crisis has been overcome. Production reached a peak value of 12

per month. Must work hard to keep it there…

• Procurement of extensive auxiliary equipment (sensors, motors, local infrastructure, …) is in

good shape.

• Increased pressure on CERN work: Final assembly at CERN has restarted and is going full

speed for 3 collimators per week (~8 persons full time).

• Full minimal system is at CERN and is being prepared for installation (ready for up to 15

nominal bunches at 7 TeV). 8 collimators stored for installation (IR3 and IR7).

• All quick-plugin supports available/installed (final LSS7R ongoing).

• Collimator alignment campaign will start next week in LSS1 and then move to LSS7.

• High rate collimator installation is being prepared (installation training). 10 already installed.

IR7 installation starts in July…

RWA, 15/6/2007 35

Conclusion II

• Many tests without and with beam show that LHC collimators are robust, reliable (20,000

cycles) and precisely controllable. The 118 initial LHC collimators/absorbers should advance

the state-of-the-art by ~2 orders of magnitude.

• Goals: Have almost the full phase 1 system ready for the 2008 run.

Full passive protection, high cleaning efficiency (> 99.99%) will then be there.

Last collimators for installation ready in January 2008.

• These goals are achievable if we can keep the present pace. We still have a way to go and

there are always risks… We will work hard to make these goals.

• Requires some effort to integrate late collimator installation with other activities.

• Optimized installation planning is being worked out with the LHC installation planning group.

Detailed schedules still in flux (negotiations affect schedule and in-house work).

• Ongoing work in other areas not discussed here: hardware commissioning, controls system,

preparation for beam commissioning and operation, accelerator physics studies, radiation

tests, cascade modeling, preparations for upgrades (performance, remote handling, …).