54
SA port terminals: capacity and utilisation review 2014/15

SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

Embed Size (px)

Citation preview

Page 1: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

SA port terminals: capacity and utilisation review

2014/15

Page 2: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

1. INTRODUCTION ....................................................................................................................................... 1

2. TOWARDS MEASURING PORT CAPACITY AND UTILISATION .................................................................... 2

3. PURPOSE OF THE REVIEW ........................................................................................................................ 8

4. CAPACITY OF SOUTH AFRICAN PORT TERMINALS .................................................................................... 9

4.1. THE NPA’S LONG TERM PORT DEVELOPMENT FRAMEWORK .............................................................................. 12

4.1.1. Land use ............................................................................................................................................. 13

4.2. TERMINALS AND BERTHS ........................................................................................................................... 16

4.2.1. Container terminals .................................................................................................................... 18

4.2.2. Automotives ............................................................................................................................... 23

4.2.3. Dry bulk, Break Bulk and Liquid Bulk .......................................................................................... 28

4.3. TERMINAL UTILISATION PER PORT ................................................................................................................ 35

4.3.1. Port of Durban ............................................................................................................................ 35

4.3.2. Port of Richards Bay ................................................................................................................... 36

4.3.3. Port of East London .................................................................................................................... 37

4.3.4. Port of Ngqurha .......................................................................................................................... 38

4.3.5. Port of Port Elizabeth .................................................................................................................. 39

4.3.6. Port of Cape Town ...................................................................................................................... 40

4.3.7. Port of Saldahna ......................................................................................................................... 41

5. SUMMARY ............................................................................................................................................. 42

6. WAY FORWARD ..................................................................................................................................... 46

7. CONCLUSION ......................................................................................................................................... 49

8. BIBLIOGRAPHY ...................................................................................................................................... 50

Page 3: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

iii

FIGURE 1: DEPICTION OF A PROCESS FLOW AT PORTS REPRESENTING KEY POINTS FOR PERFOMANCE MEASUREMENT ....................... 4

FIGURE 2: TERMINAL OPERATOR PERFORMANCE STANDARD (TOPS): SYSTEMATIC PORT PERFORMANCE MODEL ........................... 5

FIGURE 3: PROGRESSION FOR PORT CAPACITY UTILISATION: PRODUCTIVITY, EFFICIENCY TO CAPACITY EXPANSION ............................ 7

FIGURE 4: LAND USE (HA) FOR CARGO AND NON-CARGO FUNCTIONS ACROSS THE 8 COMMERCIAL PORTS (2012) ........................ 13

FIGURE 5: PROJECTED GROWTH IN LAND AREA ACROSS THE VARIOUS CARGO WORKING CATEGORIES .......................................... 15

FIGURE 6: BERTH PRODUCTIVITY - CONTAINER TERMINALS................................................................................................. 20

FIGURE 7: TEUS PER BERTH METRE BASED ON DESIGN, INSTALLED CAPACITY AND 2013/14 THROUGHPUT ................................. 21

FIGURE 8: TEUS PER TERMINAL AREA (HA) ..................................................................................................................... 22

FIGURE 9: TOPS PERFORMANCE FOR CONTAINER TERMINALS............................................................................................. 22

FIGURE 10: ANNUAL RO-RO UNITS PER METRE OF BERTH .................................................................................................. 25

FIGURE 11: ANNUAL RO-RO UNITS PER HA OF TERMINAL AREA .......................................................................................... 25

FIGURE 12: RO-RO TERMINAL PRODUCTIVITY IN RELATION TO DESIGN AND INSTALLED CAPACITY AND 2013/14 PERFORMANCE ...... 26

FIGURE 13: TOPS AUTOMOTIVE SECTOR PERFORMANCE 2013/14 .................................................................................... 27

FIGURE 14: DRY BULK TERMINAL PRODUCTIVITY .............................................................................................................. 32

FIGURE 15: BREAK BULK THROUGHPUT PER METRE BERTH AND PER TERMINAL AREA (2013) .................................................... 33

FIGURE 16: LIQUID BULK THROUGHPUT PER M/BERTH AND PER HA 34

FIGURE 17: TERMINAL PRODUCTIVITY IN THE PORT OF DURBAN ......................................................................................... 36

FIGURE 18: TERMINAL PRODUCTIVITY IN THE PORT OF RICHARDS BAY ................................................................................. 37

FIGURE 19: TERMINAL PRODUCTIVITY IN THE PORT OF EAST LONDON .................................................................................. 38

FIGURE 20: TERMINAL PRODUCTIVITY AT THE PORT OF NGQURHA ...................................................................................... 39

FIGURE 21: TERMINAL PRODUCTIVITY AT THE PORT OF PORT ELIZABETH .............................................................................. 40

FIGURE 22: TERMINAL PRODUCTIVITY IN THE PORT OF CAPE TOWN .................................................................................... 40

FIGURE 23: TERMINAL PRODUCTIVITY AT THE PORT OF SALDAHNA ...................................................................................... 41

TABLES

TABLE 1: LAND USE ACROSS THE DIFFERENT PORT FUNCTIONS 2012 TO 2040+ ..................................................................... 14

TABLE 2: WATERSIDE CAPACITY OF SOUTH AFRICAN TERMINALS ......................................................................................... 16

TABLE 3: LATENT CAPACITY ACROSS THE MAIN COMMODITY TYPES HANDLED IN SOUTH AFRICAN PORTS ..................................... 17

TABLE 4: CONTAINER TERMINAL CAPACITY ACROSS THE SYSTEM AS PER LTPDF (2013) .......................................................... 18

TABLE 5: CONTAINER TERMINALS THROUGHPUT (2013/14) VS. DESIGN AND INSTALLED CAPACITY ............................................ 19

TABLE 6: TOPS ACROSS THE SHIP RATE FOR CONTAINERS ................................................................................................. 23

TABLE 7: RO-RO TERMINAL CAPACITY ACROSS THE SYSTEM ................................................................................................ 23

TABLE 8: RO-RO TERMINAL CAPACITY BASED ON THROUGHPUT AGAINST DESIGN AND INSTALLED CAPACITY ................................. 24

TABLE 9: TOPS REPORTED PERFORMANCE FOR RO-RO ..................................................................................................... 27

TABLE 10: BULK TERMINALS ACROSS THE SYSTEM (CONTINUES ON NEXT PAGE) ...................................................................... 28

TABLE 11: THROUGHPUT AGAINST DESIGN CAPACITY FOR DRY BULK (2013) ......................................................................... 30

TABLE 12: THROUGHPUT AGAINST DESIGN CAPACITY FOR BREAK BULK (2013) ...................................................................... 30

TABLE 13: THROUGHPUT AGAINST DESIGN AND INSTALLED CAPACITY FOR LIQUID BULK (2013) ................................................ 31

TABLE 14: SUMMARY OF TERMINAL USE BY CARGO TYPE AND PORT ..................................................................................... 43

TABLE 15: BERTH UTILISATION FACTOR ......................................................................................................................... 48

TABLE 16: EXAMPLE OF POSSIBLE OPTIMAL BERTH UTILISATION AND ATS FOR SA TERMINALS .................................................. 49

Page 4: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

1. Introduction

1. Ports have an essential role to play in facilitation of trade, which is a key driver of economic

growth. As a result there is generally keen interest in how ports and port terminals perform

in facilitating effective movement of goods and people. Although container traffic accounts

for less than half world trade by volume, containerized cargo globally accounts for more than

two thirds of the value of goods traded. Accordingly, there has been a bias toward measuring

and improving the performance of container terminals.

2. In 1987, a process of defining common indicators against which the performance of a port

can be measured gained momentum with the publication of the United Nations Conference

on Trade and Development (UNCTAD:1987) monogram. Notwithstanding literature that

abounds prior and after the UNCTAD process, the monogram represented the first attempt to

document, for port managers and practitioners in developing countries, common

performance indicators for calculating port productivity, identifying data requirements

including who should collect and how such data should systematically be collected which

informs system designs to date.

3. Practitioners have continued to influence the determination of port performance measures

(see various papers delivered at the UN Ad Hoc Expert Meeting on Assessing Port

Performance, Geneva 2012); or Research groups tasked with recommending the best

strategies for improving port performance at country or regional levels (See Tioga Research

Report on North American container terminals 2010; the Infrastructure Development Bank

funded study on Latin American and Caribbean Ports (LAP) and the annual publication of port

statistics for Australian ports in the Waterline Reports).

4. Various academics have also weighed- in on the matter with research on various aspects of

port performance which ranges from establishing common methodologies in defining

technical efficiencies of ports against which ports can be measured, to applying variations of

either the Stochastic Frontier Assessments (SFA) or the Data Envelopment Analysis or a

combination (see for example Cullinane: 2010; Gonzales & Trujillo (2004), Tally (2007), Merk

and Dang (2012)) in measuring technical efficiency of ports. Annual publications which

provide global comparisons and analyse trends and improvements in the performance of

global ports, such as the JOC White Paper on Port Productivity amongst others, contribute to

the wealth of knowledge and approaches on port productivity.

5. Most literature shows that port performance measurement is affected by complex interplays

between various players and factors in the port system where no two ports are alike, save for

Page 5: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

2

the functions they perform i.e. facilitating the transfer of goods from the sea-side to the land-

side and vice versa. Each of the distinct groups of port users try to weigh in and influence

measures. Shipping lines, road transport companies, and cargo owners each focus on and

require different levels of service and would thus be keen on different measures in the

performance of container terminals. As an example, cargo owners, concerned about the time

that cargo stays in a terminal making it important therefore that appropriate standards be set

for cargo dwell times.

6. Shipping lines are driven by the need to transport cargo on time at the lowest cost and

hence, are concerned about capacity, transit time, and reliability of service, costs and

productivity levels at a port which often is translated through a demand for the right

equipment at terminal. In turn this informs the measures they would be interested in and

support in ports.

7. Merk and Dang (2012) research on Efficiency of world ports in container and bulk cargo (oil,

coal, ores and grains), even though limited to the case-study methodology which makes it

difficult to replicate in other contexts, nonetheless lays a good base for calculating port

efficiency in the non-container sector and takes previous studies on Stochastic Frontier

Analysis (SFA) and Data Envelopment Assessments (DEA) forward in both container and non-

container sector.

8. The most recent study by Salminen (2013) measures port capacity in containers, dry bulks,

break bulk, liquid bulk terminals making a link between capacity assessments and investment

strategies in uncertain investment contexts. Similar assessment will be useful in the

Regulator’s next iteration of the capacity and utilisation reviews.

9. Whilst noting these global developments in port capacity and utilisation as well as

measurement of port productivity and efficiency, this review report will provide a basic snap

shot and base-line from which future reviews can conduct further analysis including

efficiencies in the South African system.

2. Towards measuring port capacity and utilisation

10. The ability of a port to handle cargo and/or vessels timeously and/or economically as well as

the ability of a port to manage the expectations and requirement of various grouping of port

users, in the various stages depicted above, determines in part whether vessels and cargo are

attracted to a port, the other part being market factors. Where alternative to a port exists,

Page 6: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

3

then effective utilisation of facility expressed in the overall vessel turnaround time becomes

important.

11. The existence or provision of port capacity and utilisation thereof in the various stages in the

movement of vessels and goods i.e. anchorage, terminals (berths and yard) and intermodal

links (road and rail) are thus an important part of measuring port performance. In this regard,

this review presents a status quo of existing capacities in the various South African terminals

that handle containers, automotives, dry bulk, break bulk and liquid bulk commodities.

12. Measuring port productivity and defining the right measures is important in that, even with

varying and different levels of endowments in ports, ports are essentially there to provide

services to/for vessels (bringing or carrying cargo), cargo (including some storage thereof for

defined periods of time) and the interface with cargo transportation inland (road or rail

haulage).

13. Figure 1 tracks the movement of a vessel from the time it arrives at anchorage, to berthing

and operations and sailing out of the port. Using vessel turnaround time as a proxy for how

well the port or terminal or berth is operating, the figure also highlights key points in the

journey where performance is measured through time indicators.

14. The item marked (A) shows that generally the time a vessel spends in anchorage is measured

as it indicates how vessels queue before berthing. However, given time spent in anchorage

may be caused by a myriad of reasons, including: weather, waiting for orders, early arrival, or

terminal/berth readiness or availability of marine services, only those reasons related to

terminal readiness and/or availability of marine services are considered, as these are within

the control of port management.

15. From anchorage, a vessel will be readied for actual berthing, including the carrying out of

marines services to bring vessel to berth, this is considered as transit time (B) the treatment

of which also affects berth productivity. If this transit time is included in the calculation of

berth utilisation it may reflect unproductive use since this time is not accounted for the in the

movement of cargo across the ship. The practice is thus for transit time to be measured but

excluded from the measurements of berth utilisation. Stevedoring and related functions must

be carried out before the vessel can be worked or operation can commence. This is also

considered as vessel non-working time depicted as (C1).

Page 7: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

4

Figure 1: Depiction of a process flow at ports representing key points for perfomance measurement

Source: Report on Study of Indian Ports

16. Vessel working time is the time between the commencement of operation and completion of

operation i.e. working time. Idle time (C2) includes latching and rope untying time in

preparation for departure. Lastly, vessel sailing from berth from the last rope being dropped

is considered non- working time.

17. Figure 1 assist in visually summarizing the steps and key points in the handling of a vessel

where key performance indicators and measures of port performance are defined. The more

commonly measured benchmarks on productivity, each with their own indicators and data

inputs, can be categorized into those that cover:

Berth productivity (TEU/metre of berth length),

Quay crane productivity, (TEU/crane/hour),

Yard productivity (TEU/hectare of yard), and

Workforce productivity (TEU/employee/year).

Page 8: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

5

18. The Terminal Operator Performance Standards (TOPS) of the NPA, introduced in December

2013, follows the same logic and identifies key performance measures in a systematic port

performance model as outlined in Figure 2.

Figure 2: Terminal Operator Performance Standard (TOPS): systematic port performance model

19. The NPA has started a process of measuring port performance in four key points depicted in

Figure 2, namely;

a. At anchorage – measuring berthing delays

b. At berth - measuring berth occupancy, berth utilisation, gross crane moves per hour

and ship working hour;

c. At terminal – the measure is throughput and dwell times;

d. Point of intermodal exchange of cargo – measures truck turnaround time, truck

waiting time, rail turnaround time and trains departing on time.

20. Ports are contested spaces where players want to maximize the benefits that can be derived

from the system whilst minimizing their direct cost as much as they can. Benefits from the

system are not always mutually inclusive e.g. port pricing of South African ports is done at

system level through the Required Revenue method which is a “zero sum” system i.e. all port

users must contribute in varying degrees to the total CAPEX and maintenance of port

infrastructure. When segments of port users require investment to be made to expand

capacity and reduce congestion in ports, they equally should be responsive to shared

increases in port charges to achieve the objective.

Page 9: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

6

21. In addition, Cullinane (2010) also posits that increasing port efficiencies may temporally

result in higher rather than lower port costs in the short term(e.g. where it is achieved

through deployment of more resources). Creation of capacity often displaces existing

capacity for a period of time which, notwithstanding proper planning, and it is often

unavoidable, resulting in less throughput which is a key indicator in most measures of port

productivity and efficiency. Deployment of additional capacity, e.g. equipment, tends to

affect the throughput during the period of adjustment making the investment not cost

effective during such periods. As an example, in the expansion of container terminal at Pier1

in the Port of Durban in 2013, the total TEU throughput reduced resulting in the Durban

Container terminal losing two places in the Top 100 Container Terminals of the world.

22. The nature and character of port infrastructure i.e. long lead times and expansive capital

outlays, makes it imperative that optimal use of current infrastructure is encouraged to make

the most of existing infrastructure. In the short term, capacity of a port can only be increased

by adding cranes, improving efficiency or optimising container yards, often focusing on

increasing stacking density and operating hours.

23. Medium to longer term strategies to address capacity may include adding more

infrastructure in the form of expanding or building new quay walls, dredging and deepening

of berths, building new terminals. Overall, terminal capacity establishes a terminal’s limit and

may point to areas where terminal productivity and efficiencies can be increased in the port

development. It is not static, as it can be changed over time either through optimization of

the system or through expansion.

24. The capacity of a port is usually defined as the maximum traffic it can handle within given

parameters and is informed by fixed and variable factors. Fixed port factors include maritime

channels, berths, terminals, storage facilities and other transport linkages. Variable factors

included cranes, carriers, IT systems, labor as well as marine equipment and services.

25. In assessing port performance, a distinction is also made between design (theoretical)

capacity and installed (operational) capacity of terminals. Design capacity is the maximum

throughput that can be achieved in a terminal as designed whilst installed capacity, also

called operational capacity, refers to optimal amount of throughput achievable given

resources deployed in terminal at a given time.

Page 10: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

7

Figure 3: Progression for port capacity utilisation: productivity, efficiency to capacity expansion

26. Figure 3 graphically illustrates the progression of port development from start up, to the

stage of system optimization and capacity expansion. Generally, low-utilisation and low cost

operations characterise ports or terminals at the start. Port or terminal performance and

productivity at this stage is measured simply by assessing throughput against installed

capacity. Financial and labor measures can be added if cost effectiveness dimensions of port

capacity are to be addressed.

27. As port operations become more complex and involve more players, ports tend to make

system and technology improvements that allow them to take full advantage of land, capital

and labor. The objective is to reach the limit of the system with full deployment of land,

capital and labor.

28. When limits of expansion are reached, investment in capital equipment to minimize labor

costs is often then the route taken, exhausting throughput capability of the system,

technology, land, and capital equipment. Measures of congestion such as dwell times, berth

occupancy become important at this stage as they indicate the extent to which port or

terminal infrastructure can handle more throughput or whether these should be expanded.

29. Utilisation indicators measure how intensely port facilities/capacity is used i.e. percentage of

actual use of resources and maximum possible use of those resources over time. The most

collected utilisation measures are berth occupancy (the ratio of time a berth is occupied by a

vessel to the total time available in that period) and storage utilisation. High berth occupancy

rates i.e. above 65 – 70% have been accepted to be a sign of congestion. Berth and terminal

Stage 1:

Port or Terminal Start up

Low utilisation

Low cost operation

Capacity against throughput

Stage 2: System Optimisation

System and technology

improvements

Full deployment of land, capital and

labour

Terminal throughput per crane, yard, hectare, labour,

Dwell times, berth occupancy, Road/Rail Turnaround time etc

Stage 3: Capacity Investments

Expand existing capacity

Create new capacity

Installed capacity vs. throughput

Financial measures

Labour

Ch

arac

teri

stic

s M

easu

res

Page 11: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

8

utilisation are better indicators than just berth occupancy as they measure the time that a

berth or terminal is productively utilized rather than just the time a vessel is alongside the

berth.

30. For the purpose of this review, the terminal capacity expressed in terms of number and

length of berths dedicated to handling particular cargo type, the size of the terminal in

hectares as well as design and installed capacities as extrapolated from the NPAs LTPDF are

used to paint a picture of the extent to which existing capacity is being used.

31. In line with the National Ports Act, Act 12 of 2005, the Ports Regulator (the Regulator) must,

through economic regulation of the South African port system ensure that the National Ports

Authority (the NPA) effectively manages South Africa’s port system in a manner that enables

the objects of the Act to be met, one being the development of an efficient port system

supporting the country’s economic development.

32. The optimal and efficient use of existing capacity, i.e. sweating of assets, by the NPA is an

important indicator for the Regulator and is reflected in the current tariff setting

methodology which highlights an intention to include efficiency measures in future tariff

determinations.

3. Purpose of the review

33. The purpose of this PRSA review of the NPAs’ capacity and utilisation is to begin to identify

and analyse existing terminal capacity including terminal area, berth capacity, design and

installed capacity, and based on 2013 throughput, to assess the extent to which capacity is

utilised across cargo types and port terminals.

34. The review of the NPAs port capacity and utilization will be an ongoing process and it is

important that a baseline be set as a start. This is especially so where the Regulator has had

to collate for the first time information on South African port terminals and their capacities.

35. This first review of the NPAs capacity and utilisation thus simply intends to lay a baseline on

existing port infrastructure and the extent of its utilisation. The review does look at some

productivity measured in terms of terminal throughput against design and installed capacity

based on the NPAs data/information collated from the Long Term Port Development

Framework and the 2013 throughput data for terminals.

36. It is intended that the review process will, in the short term serve to create dialogue on how

the Regulator should encourage improvements in the use of port infrastructure. It is

envisaged that ultimately there will be common definitions and monitoring of the

Page 12: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

9

performance of South Africa’s port terminals, alongside the Operator Performance Standards

of the NPA and indications of where further analysis is required in subsequent reviews are

given.

37. Efficiency and comparisons against international benchmarks will be done in a separate

Benchmarking report which takes the utilisation and productivity statistics reported herein

and compares them against reported performance of other terminals internationally.

4. Capacity of South African port terminals

38. Empowered by the National Ports Act, the NPA develops both operational and long term port

development plans that guides and directs how South African ports will grow. It has

developed the Long Term Port Development Framework (LTPDF) which provides a long-term

vision for the development of South Africa’s 8 of 9 the commercial ports namely Ports of

Richards Bay, Durban, East London, Ngqurha, Port Elizabeth, Mossel Bay, Cape Town and

Saldahna Bay.

39. The LTPDF is consulted with and supported by port users as required by the Act and

Regulations, with the current LTPDF consulted with stakeholders in May 2014. The LTPDF

provides a long term vision and direction of the NPAs CAPEX programme, as well as

engenders support for the CAPEX programme especially from port users from whom tariffs

are raised to provide, sustain and expand capacity. Before delving into the provisions of the

LTPDF, a brief overview of the various ports and their development over time is provided in

the items that follow.

40. As noted in the report of the Development Bank of Southern Africa and Presidency (DPME:

2012), each port in South Africa has its own history and origins. In the case of Cape Town, its

trading history goes back to the formal Dutch settlement at the Cape in 1652. But before

this, ports such as Saldanha Bay, Mossel Bay, Durban and several other locations were visited

by Portuguese and then Dutch traders stopping for shelter, water or even small-scale trading.

The modern commercial era of South Africa’s ports commenced with the unification of the

country geographically and politically at the beginning of the twentieth century, following the

1899-1902 Anglo-Boer War.

Port of Durban

41. History traces the development of the Port of Durban to the appointment of the first harbor

master for Durban around 1840, although the use of the Bluff to shelter ships is recorded as

Page 13: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

10

far back as 1497. In the 1930s to the 1950s the Bayhead area in the Port of Durban was used

as a base for flying boats. Over the years Durban became the busiest general cargo port and

the largest and busiest container terminal in the Southern Hemisphere. It services its own

industrial and commercial region in addition to the rest of South Africa’s hinterland through

Gauteng as well as regional traffic. To accommodate growth, the port has grown its container

handling capacity with second container terminal at Pier One become operational in 2007.

Plans exist to extend Pier 1 Container terminal through the infilling of Salisbury Island (which

belongs to the South African Navy). The Port channel has been widened (222m at its

narrowest point) and deepened (16,5m in the inner channel) to allow bigger vessels to be

accommodated.

42. The main commodity categories handled at Durban are: containers, vehicles, grains (rice,

maize), forestry products (including woodchip), liquid bulks (crude oil, petroleum products

and chemicals), coal, fertilizer, steel, fruit, sugar, and passengers (including cruise vessels).

Although the whole port is owned by Transnet through the NPA, a number of terminals are

operated by private companies.

Port of Richards Bay

43. The Port of Richards Bay was developed between 1972 and 1976 in response to the demand

for additional rail-linked port infrastructure to service export potential from the (now)

KwaZulu-Natal and Mpumalanga coalfields. A deepwater facility was needed because of the

development internationally of very large bulk carriers. Richards Bay was chosen because of

the large lagoon; the ease of dredging; direct links with the national rail network, an adjacent

town, Empangeni, to stimulate initial development; and an ample supply of fresh water.

44. The port is now South Africa’s premier dry bulk port, handling an increasing variety of bulk

and neo-bulk commodities in addition to break-bulk. The coal terminal, single bulk liquids

berth and bulk liquid storage and phosphoric acid loading facility are operated by private

companies.

Port of East London

45. The Port of East London is South Africa’s only river port situated at the mouth of the Buffalo

River. As a common user port, it boasts the largest grain elevator in South Africa, a car

terminal on the west bank which includes a four story parking facility connect by dedicated

road to Mercedes Benz factory. The Port also has a multipurpose terminal on the East Bank

which handles containers, a dry dock, a repair quay, pilot and fishing jetty, the Latimer’s

Landing Water frontage as well as bunkering with fuel oil and marine gas oil.

Page 14: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

11

Port of Port Elizabeth

46. Although services started in 1836 (a surfboat for handling cargo and passengers) and the first

jetty was constructed in 1837, the Port of Port Elizabeth was established as a proper harbour

in 1933 with the construction of the Charl Malan Quay (now used as the container and car

terminals) which for the first time offered protection from open seas.

47. Agriculture and farming – deciduous and citrus fruits and wool crop – played an important

role in the development of the Port of Port Elizabeth, prior to the growth of containers and

motor industry in prominence in this port. The fishing industry and passenger ships

(accommodated at the fruit terminal berths when calling at the Port) are important players in

the Port. Other products handled in this port include Manganese ore (which by 2017/18 will

be relocated to the Port of Ngqurha) and petroleum form other South African ports. The Port

of Port Elizabeth will be losing some of its commercial activities to the new and deeper Port

of Ngqurha.

Port of Ngqurha

48. The Port of Ngqurha is South Africa’s 8th and latest commercial port development. It is a

deepwater port capable of handling post-Panamax dry and liquid bulkers as well as 6,500 TEU

cellular container vessels. The port’s main breakwater is the longest in South Africa. At a

construction cost of R10b, the port of Ngqurha was to have an aluminium smelter as its

anchor tenant with a required expenditure of about R1, 8b by Eskom. With the energy crisis

in 2008, the aluminium smelter became unlikely against the pressures for Eskom to provide

adequate and inexpensive energy on a national basis. This brought about a change in focus

for the Port of Ngqurha from a deep-water bulk port to container handling with operations

on the container terminal commencing in 2009. The Coega Industrial Development Zone (IDZ)

as well as the Nelson Mandela Bay Strategy all aim to optimize the existence of the two ports

in this undeveloped region.

Port of Cape Town

49. The Port of Cape Town, established in 1652 as a station for ships of the Dutch East India

Company, has evolved to the two docks – Ben Schoeman Dock and Duncan Dock respectively

housing container and the multipurpose, fruit terminal, dry dock, repair quay and tanker

basin. The port has ship repair facilities – the Sturrock Dock, Robinson Dry Dock, a

synchrolift, a repair quay in the Duncan Dock and Berth A where ship repair is done by a

private company.

Port of Mossel Bay

50. The Port of Mossel Bay is the smallest commercial harbor in the South African system. It

caters for the developing oil industry which began with Mossgas in the late 1980’s as well as

Page 15: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

12

small but significant fishing industry in the region. The Port has not grown other significant

commercial activity over the years.

Port of Saldahna Bay

51. The Port of Saldahna Bay was developed from a need to facilitate export of iron ore from the

Northern Cape. Until the late 1970s the Port of Saldanha was a small fishing village. The

opportunity to export iron ore from Sishen in the Northern Cape led to the construction of a

800km railway line, together with storage and loading facilities for the largest dry bulk

carriers in the world. The first vessel loaded with ore left Saldanha in September 1976. The

construction of the Saldanha Steel Mill near the port led to export of steel manufactured

from more iron ore which is railed from Sishen directly to the mill.

52. It is supported by more than 800kms of rail line connecting the port to mines at Sishen in the

Northern Cape. The rail line was originally built by Iscor (now Acelor Mittal) before being

taken over by Transnet Freight Rail. As one of the deeper harbours in the South African port

system, the Port of Saldahna accepts vessels up to 20.5m draught with the harbor master

conditionally accepting vessels up to 21.5m.

4.1. The NPA’s long term port development framework

53. The Long Term Port Development Framework (2013) provides a picture of NPAs CAPEX plans

for the short term (2012 – 2018), medium term (2018 – 2040) and long term (2041 and

beyond) with provision/expansion of port capacity for the five main commodity classes i.e:

containers; dry bulk (coal, iron ore, manganese, sugar, chrome ore, copper, lead, woodchips);

Liquid bulk (petroleum products, chemicals, vegetable oils); Break-bulk (fruit, steel, scrap

metals, Ferro alloys, pig iron, fish & fish products); and Automotive at the various ports.

54. The NPA uses a Freight Demand Model to project the possible extent of future traffic growth

in cargo handled at each of the ports. The model is developed at a broader transport level by

Transnet with a dedicated section for ports. Combined with the LTPDF is the port component

of the Transnet Market Demand Strategy (MDS) which provides traffic and demand forecasts

for which the NPA develops strategies to maintain/sustain or expand infrastructure and

capacity in the short, medium and long term.

55. It should be noted that the long term port development framework is not a set or

prescriptive plan, but rather an indication of the direction that the NPA believes port

development will go based on current capacity, assumptions and projected demand. The plan

is therefore flexible and should accommodate changes where assumptions and projections

Page 16: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

13

change. The LTPDF’s periodisation has short term being the period 2012 – 2017, medium

terms is 2018 – 2040 and long term is 2040 and beyond.

4.1.1. Land use

56. Figure 4 summarises land side capacity in terms of available land for uses in cargo working

and non-cargo working areas in the South African port system.

Figure 4: Land use (ha) for cargo and non-cargo functions across the 8 commercial ports (2012)

57. The status quo as summarised in Figure 5 has total port land of 5 226 hectares. More than

half (3 562ha) of land available to the NPA is categorized as open space or NPA other i.e. land

which is currently not productively used. Open land alone is 1 625ha, which suggests

availability of land to support the NPA Capex expansion programme into the future. What is

not obtainable from the LTPDF are the port specifics that informs how much of this land is

usable, must remain open land, and how much is available for further developments in the

future.

3562ha, (68%)

535

419

367

145

97

66 18 17

1664 ha, (32%)

Open space/NPA other Dry Bulk Liquid Bulk Container Commercial Logistics Ship Repair Vehicles Fishing

Page 17: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

14

58. The remaining 1 664 ha covers both cargo and non-cargo working land uses. A significant

portion of this is currently used for Dry Bulk (535 ha), Liquid Bulk (419ha) and container

terminals (367ha). Automotives account for the least size of land at 66 ha.

59. On non-cargo working land uses, Commercial logistics at 145 ha accounts for the next most

significant land use parcel in the system. Remaining land uses are shared amongst Ship-repair

(whose prominence in the system is anticipated to increase owing to Operation Phakisa),

fishing, vehicles and maritime commercial.

60. Plans for land use in the medium to long term are depicted in Table 1. According to the NPAs

port planning principles, South African ports must increasingly play a supportive role for

economic growth and trade by facilitating back of port developments. This is evidenced in the

projected growth in maritime commercial and commercial logistics land uses from 162ha

(145 +17) in 2012 to 309ha by 2019 and 522ha beyond 2040. This reflects a 260% growth in

commercial logistics land and similarly a 253% growth in maritime commercial land in the

next 27 years.

Table 1: Land use across the different port functions 2012 to 2040+

Land Use Current (2012)

(hectares)

2018 – 2040 Medium Term (hectares)

2040+ Long Term (hectares)

Hectares % growth (on current ha)

hectares % growth (on current ha)

Containers 367 812 121% 1 100 200%

Vehicles 66 94 42% 107 62%

Dry Bulk 535 916 71% 819 53%

Liquid Bulk 419 833 99% 884 111%

Ship Repair 97 140 44% 117 21%

Commercial Logistics

145 249 72% 522 260%

Fishing 18 29 61% 28 55%

Maritime commercial

17 60 253% 60 253%

TNPA other 1 937 2 380 23% 3 750 94%

Open Space 1 625 1163 -28% 1 506 -7%

Total 5 445 6 991 9 218

Compiled from Long Term Port Development Framework (NPA) 2013

61. For cargo working land, container terminals with 367ha of land area in 2012 grows to 1 100ha

by 2040 and beyond, a planned 200% growth. Dry bulk land area which currently is the

biggest at 535ha is anticipated to grow to 819ha, a 53% growth by 2040+, whilst land area for

liquid bulk which currently is the second largest land area is anticipated to have grown by

111% to 884ha in the long term. Bucking the global containerization trends where most

Page 18: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

15

commodities are being containerized, the LTPDF anticipates growing the dry bulk land use by

71% in the medium term and by an overall 53% over the long term which will take the

current 535ha to 819ha by 2040 and beyond.

62. In the context of Operation Phakisa, current LTPDF only anticipated to grow land use for ship

repair by a modest 44% in the medium term and overall 21% in the long term i.e. from 97 ha

currently to 140 ha in the medium term and reducing to 117ha in the long term.

63. Figure 5 graphically shows the trend in the planned growth for the various land uses in the

system.

Figure 5: Projected growth in land area across the various cargo working categories

64. Dry bulk, Liquid Bulk and Containers account for the most land area currently and in the

future. Vehicles and ship repair facility accounts for the least land area currently and in the

future growing to just above 100hectares.

65. The land use part of the LTPDF estimates the requirement for land for port development

based on long term volume projections which are more difficult to project than short term.

The Regulator will thus, in subsequent reviews, interrogate more rigorously the modeling,

data and modeling that informs the reported land use in Table 1.

Page 19: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

16

4.2. Terminals and Berths

66. The terminal capacity details in this review are from the NPA’s Long Term Ports Development

Framework LTPDF (2013) which provides the extent of port terminal area in hectares,

numbers of berths including a distinction between usable berths and unusable berths, berth

length as well as the design and installed capacities of the various terminals. This terminal

capacity indicates how much a port is able to handle in terms of cargo-throughput. The

physical attributes of a port or terminal also determines the size of vessels that can call.

Table 2: Waterside capacity of South African terminals

Terminal Total Berths

Usable berths Berth Length(m) Installed capacity

Design capacity

Containers 18 17 5 590 4 790 043 8 013 000

Vehicles 7 5 2 050 681 041 850 000

Dry Bulk 30 25 8 081 187 666 802 229 084 000

Break Bulk 40 37 6 476 17 344 903 32 513 153

Liquid Bulk 18 17 3 715 26 141 684 66 451 207

Total 113 101 25 912

Compiled from Long Term Port Development Framework (NPA) 2013

67. As depicted in Table 2, South African terminals total a berth length of about 26kms, with 113

berths and 1 618 hectares of terminal areas for cargo handling. Out of the total berths

available in the system 101 are reported as usable. Reasons for berths not being used

include, berths used for lay-bye, or temporary decommissioning due to dredging or where

cargo is not handled due to superstructure not installed i.e. terminal not operating for

example, 2 berths out of 4 in the Port of Ngqurha.

68. Dry and break bulk terminals account for a combined total of 14 557m of berth length and a

total of 62 usable berths out of 70. Liquid bulks are handled at 17 out of 18 usable berths,

with 3 715 m of berth length. Container cargo is handled in 17 of 18 berths with 5 590m of

berth length and a total of 367 hectares. Vehicles are handled in the three ports of Durban,

Port Elizabeth and East London which have a combined total of 5 berths (from a total of 7).

The automotive sector is served by 2 050m of berth length and 66 hectares of available land

area.

69. With regards to terminal capacity, the container terminals in the South African system are

designed to handle up to 8 013 000 TEUs per annum. Just over half of this is available as

installed capacity. This suggests that there is significant capacity for container handling in the

system before additional capacity can be laid down.

Page 20: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

17

70. The system has to date handled 681 041 units of vehicles in a year against the design capacity

of 850 000 units a year again suggesting that there is excess capacity in the system. The same

trend applies to dry, break and liquid bulk where installed capacity is lower than design

capacity.

71. In terms of the LTPDF, deep water berths at the Ports of Richards Bay (14m to 19m),

Saldahna (up to 23m) and Ngqurha (16.5m to 18m) account for 6kms of berth length. The

remainder of the terminals have berth depth which is medium to shallow i.e. 12m and below.

72. The NPA in the LTPDF plans to expand the system to 57 000m (57km) where 50% of the

berths will be 16m and deeper to accommodate global trends in bigger vessels requiring

deeper berths. In the long term (by 2042), the berth length across all ports is anticipated to

grow to 92kms with about 66% of this made up of deep water berths.

The next section reports on the latent capacity in the South African port system which is

arrived at by taking the difference between design and installed capacities. It points to

additional capacity that can be made available to handle cargo. As highlighted before, design

capacity is the maximum throughput that a terminal can handle per annum based on

infrastructure that has been put down and all things being equal. Installed capacity refers to

the maximum throughput that a terminal can handle per annum, taking other performance

factors into account i.e. installed superstructure, the appropriate and capable labour and

systems as prevailing market conditions.

Table 3: Latent capacity across the main commodity types handled in South African ports

All Installed capacity Design Capacity Latent

Containers (TEUs pa) 4 790 043 8 013 000 3 222 957

Vehicles (units pa) 681 041 850 000 168 959

Dry Bulk (mtpa) 173 666 802 155 884 000 (17 782 802)

Break Bulk (mtpa) 17 344 903 32 513 153 15 168 250

Liquid Bulk(klpa) 26 141 684 66 451 207 40 309 523

Compiled from Long Term Port Development Framework (NPA) 2013

73. In Table 3 latent capacity in the terminals handling the various commodity or cargo types is

calculated. This was arrived at simply by calculating the difference between installed or

operational capacity from design capacity. A more through assessment would take into

account the factors outlined above i.e. superstructure and labour. Accordingly, the outcomes

here are cautiously interpreted as indicative of what may be happening in the terminals. The

results shows that most of the terminals are either reaching their design capacity levels or

have latent capacity.

Page 21: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

18

74. The review also looks at productive use of the terminal in terms of throughput per metre of

berth and throughput per hectare of terminal area based on the 2013/14 throughput figures.

This is only a snap shot of berth and terminal area productivity. A better picture on

productivity will be attained when the comparisons are with historical and projected

throughput, which will be a focus of the next iteration of the review. The next iteration will

also analyse productivity of the berths and terminal area in relation to vessels callings in each

of the berths and terminals based on the recently acquired Vessel Tracking System data. The

next section reports on the breakdown and analysis per cargo handling terminal.

4.2.1. Container terminals

75. Container traffic is handled through dedicated terminals in the Ports of Durban, Ngqurha, and

Cape Town. However, the Port of East London does not have a dedicated terminal, containers

are handled at the break-bulk terminal and berths instead. Container traffic that is also

handled at the Port of Richards Bay and the Port of Saldahna break-bulk terminals is not

included herein.

76. Having established that there is latent capacity of about 3,2million TEUs in the system, we

review how capacity is spread across the terminals handling container cargo.

Table 4: Container terminal capacity across the system as per LTPDF (2013)

Container terminals

Installed Capacity (TEUs pa)

Design Capacity (TEUs pa)

Installed capacity as a percent of design capacity

Durban 3 020 000 3 020 000 0%

Port Elizabeth 325 211 600 000 54%

Ngqurha 491 442 2 800 000 18%

East London 53 390 93 000 57%

Cape Town 900 000 1 500 000 60%

Total 4 790 043 8 013 000 60%

Compiled from Long Term Port Development Framework (NPA) 2013

77. Table 4 shows that, overall, installed capacity at South Africa’s container terminal stands at

60% of design capacity. Reportedly, only in the Port of Durban’s container terminals does the

installed capacity match the design capacity, which shows full utilisation of design capacity.

The Port of Ngqurha, on the other hand, has design capacity of 2,8m TEUs per annum with

installed capacity for only 491 442 TEUs meaning that only 18% of its design capacity is being

used. The Ports of East London and Port Elizabeth are operating at just above half their

design capacity at 57% and 54% respectively. The container terminal at the Port of Cape

Town is operating at 60% of the terminal’s design capacity.

Page 22: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

19

78. Container throughput in the system in 2013 is summarized in the second column of Table 5.

Based on 2013 throughput levels, with throughput of 4,6million TEUs through the system,

overall container terminals are operating at 58% of their design capacity which suggests

sufficient capacity in the terminal. This contrasts with the same throughput measured against

installed capacity where the terminals are operating at 96% of installed capacity. Rather than

an indicator of terminals running out of capacity, this high figure reflects the existence of

latent capacity and the extent to which improvements can be made in installed capacity to

handle more throughput in the system.

Table 5: Container terminals throughput (2013/14) vs. design and installed capacity

Container terminals

13/14 Total TEUs Throughput against

design (%) Throughput against installed

capacity (%)

Durban 2 660 144 88% 88%

Cape Town 907 796 61% 101%

Ngqurha 713 306 25% 145%

Port Elizabeth 291 233 49% 90%

East London 41 080 44% 77%

Total 4 613 559 58% 96%

Compiled from Long Term Port Development Framework (NPA) 2013

79. The averages also hide the situation in the individual ports. The Durban container terminal,

based on 2013 throughput against design capacity is operating at 88% of its design capacity.

The least used container terminal when considering throughput against design capacity is the

Port of Ngqurha with only a quarter (25%) of its design capacity reportedly being used.

Because the terminal is designed as a four berth operation, but in 2013 was operating with

installed capacity of a two berth terminal, this registers the Port of Ngqurha’s container

terminal as using 145% of its installed capacity. The same trend applies with the Port of Port

Elizabeth which is only utilizing 49% of its design capacity but throughput against installed

capacity reflects a higher rate of 90%. This points to the need for further analysis of all the

factors around installed capacities in the terminals to determine the extent to which the

design capacity can be optimized before terminals are said to have run out of capacity as

suggested by this reported figures.

80. Berth productivity indicates how productively a berth is used by dividing the number of units

over the metre of berth length per annum only for vessels that are able to call a port. It is

calculated as throughput per berth length.

Page 23: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

20

Figure 6: Berth Productivity - container terminals

81. Figure 6 shows the number of containers moved per metre of berth in each of the terminals.

The average performance across the system was 818 TEUs per metre of berth. With 1032

TEU/m the Port of Durban moves the highest number of TEUs per metre of berth. This is

followed by the Port of Ngqurha at 991 TEUs per metre of berth. Both the Ports of Cape Town

and Port Elizabeth performed below South African container terminal average. Although the

averages allow for comparisons to be done per terminal, as done in international studies (see

Drewry: 2014), regard should be paid to how the terminals are performing in relation to their

design capacity – an indicator of what is possible based on infrastructure already provided –

as well as the installed capacity – an indicator of what is feasible based on investment in

superstructure and operational standards for the terminals.

82. Figure 7 provides a more comprehensive picture of berth productivity based on design

capacity, installed capacity and 2013/14 through for each of the terminals. The difference

between current throughput and maximum throughput based on design and installed

capacity highlights where additional throughput is possible by addressing installed capacity

issues. It is assumed that design and installed capacity account for the effects of terminal

layout, the alongside depth and vessels sizes accommodated at each port, as well as

superstructure and port operating systems in each of the terminals.

83. The Port of Durban’s Container terminals, which handled 1032 TEUs per metre of berth, were

39 TEUs short of the number of TEUs that they can handle in terms of design and installed

capacity. The challenge is with the Port of Ngqurha, which based on design capacity, has the

potential to handle 3 889 TEUs per metre of berth against the 991 TEUs per metre of berth

that the port achieved in 2013/14.The productivity of its installed capacity is 683 TEUs per

1032 991

789

459

818

0

200

400

600

800

1000

1200

Durban Ngqurha Cape Town Port Elizabeth Average

Annual TEU/berth(m)

Annual TEU/berth m

Page 24: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

21

metre of berth which is 570% of installed capacity. In simple terms this points to significant

latent capacity in the Port of Ngqurha and raises questions about installed capacity as well as

total volumes and projected growth of containers handled by the Port.

Figure 7: TEUs per berth metre based on design, installed capacity and 2013/14 throughput

84. The Port of Cape Town whose throughput in 2013/14 was 789 TEUs, and is operating at its

optimal berth productivity levels in terms of installed capacity. However, this is only half of

the design capacity, pointing to possibility of more throughput if installed capacity is

increased to be closer to the design capacity.

85. Figure 8 averages terminal productivity in terms of annual TEUs per hectare of terminal area

to an annual count of 11 222 TEUs per hectare. The terminals in the Ports of Durban (14 379

TEUs/ha) and Cape Town (13 156TEU/ha) handle more TEUs per/ha in the system.

Respectively the two terminals have 185ha and 69 ha, making the Port of Cape Town the

more productive of the two.

1171

3889

1303

945 1171

683 782

512

1032 991 789

459

0

500

1000

1500

2000

2500

3000

3500

4000

4500

Durban Ngqurha Cape Town Port Elizabeth

TEU

s p

er

be

rth

me

tre

TEUs per berth meter: design vs installed vs 2013/14 throughput

Teus per berth metre on design capacity TEUs per berth metre on installed capacity

2013/14 TEUs per berth metre

Page 25: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

22

Figure 8: TEUs per terminal area (ha)

86. With 77ha and 36ha respectively and accounting for an annual 9 264TEUs/ha and

8090TEUs/ha, the Ports of Ngqurha and Port Elizabeth are performing below the average of

the country’s four container terminals. Other factors measures that affect terminal and berth

productivity must be assessed. This includes cargo dwell times, ship turnaround times,

container handled per ship working time, etc.

Figure 9: TOPS performance for container terminals

87. Some of these are measured in TOPS and are reported in Figure 9 which shows Cargo dwell

times (import, export and transshipment) as well as rail/truck turnaround time in terminals

and ship working hours. Across the system, import cargo dwell time is reported to be 4 days,

for export containers it was 6 days whilst transshipment boxes could stay for up to 13 days

from the previous year’s 17 days. Further analysis of this reported performance against

throughput in the terminals will be a focus of the next iteration of the review taking into

14 379 13 156

9 264 8 090

11 222

0

2000

4000

6000

8000

10000

12000

14000

16000

Durban Cape Town Ngqurha Port Elizabeth Average

Annual TEUs/hectare

Annual TEUs/hectare

3.9

3 6

8

4

28

49

11

3.3

5 5

17

4

31

48

8

4.0

4 6

13

4

35

49

13

Annual Throughput

(Million TEU's)

Cargo Dwell Time Import

(days)

Cargo Dwell Time Exp (days)

Cargo Dwell Time Trans

(days)

Rail Turn Around Time

Truck Turn Around Time

Ship Working Hour

Terminal Berthing Delays

CONTAINER SECTOR

Baseline 2012/13 Actual Y1 TOPS Y1

Page 26: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

23

account installed superstructure etc., size of storage, and terminal stacking policy all of

which affects the time it takes for boxes to be handled across at the berth/quay and in the

terminal area.

Table 6: TOPS Across the Ship Rate for containers

Container terminals 13/14 Total TEUs TOPS performance (ship working rate per hour)

Durban 2 660 144 49

Cape Town 907 796 55

Ngqurha 713 306 54

Port Elizabeth 291 233 40

88. According to the Terminal Operator Performance Standards (TOPS) phase 1 performance

report, the Ports of Cape Town and Ngqurha handled 55 and 54 containers per ship working

hour which indicates high productivity of installed capacity in the terminals. An observed

general trend in terms of setting of terminal performance standards was/is based on previous

performance rather any optimal measure. Whilst it is practical starting point, it does not

allow for definition of efficient measure, rather perpetuating or slightly improving on

previous performance.

4.2.2. Automotives

89. Imports and exports of vehicles in South Africa is through the Roll-On, Roll-Off (Ro-Ro)

terminals in the Ports of Durban, Port Elizabeth and East London which collectively have a

design capacity of 850 000 units per annum. In Table 7 a summary of the endowments of the

terminals is provided. There is a total of 7 berth with 5 being used, 2 050m of berth length

and 69ha of terminal area across the system for handling automotive traffic. The maximum

throughput that has been handled in the three ports, based on installed capacity to date has

been 681 000 units.

Table 7: Ro-Ro terminal capacity across the system

Automotives Terminal area(ha)

Total Berths

Usable berths

Berth Length

(m)

Operational Capacity

(Units per annum)

Design Capacity

(units per annum)

Design capacity/oper

ational capacity

Durban RoRo 39 3 3 1149 480 000 520 000 92%

Port Elizabeth 21 2 1 342 133 552 200 000 67%

East London 9 2 1 559 67 489 130 000 52%

Sub-total 69 7 5 2050 681041 850 000 80%

Compiled from Long Term Port Development Framework (NPA) 2013

Page 27: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

24

90. Table 7 shows the operational capacity as a proportion of design capacity to give an

indication of the extent to which the terminals are used as designed. The Ro-Ro Terminal in

the Port of Durban shows operational capacity to be at 92% of design capacity, the Port of

Port Elizabeth at 67% and Port of East London at 52%. This suggests that the Port of Durban’s

Ro-Ro terminal is closer to running out of capacity than the other two terminals. However,

capacity at Ro-Ro terminal is not only determined by the throughput that is handled per

metre of berth, but also by the storage capacity (parking space, cargo dwell times etc),

factors that are not included in this review at this stage.

Table 8: Ro-Ro terminal capacity based on throughput against design and installed capacity

Ro-Ro Terminal

Design Capacity (units per annum)

Operational capacity

(units per annum)

2013/14 Throughput

(TEUs)

Throughput against design capacity (%)

Throughput against operational capacity

(%)

Durban 520 000 480 000 501 456 96% 104%

Port Elizabeth

200 000 133 552 133 194 67% 100%

East London

130 000 67 489 56 193 43% 83%

Total 850 000 681 041 81% 101%

Compiled from Long Term Port Development Framework (NPA) 2013

91. Table 8 shows that with 2013 throughput figures, the Ro-Ro terminals in the three ports used

81% percent of the installed capacity. The Port of Durban (96%) recording the highest,

followed by Port of Port Elizabeth (67%) and Port of East London. The extent to which the

terminal are utilised against installed/operational capacity shows the Durban (104% and Port

Elizabeth (100%) terminals operating at full installed capacities. The Port of East London is

utilizing 83% of its installed capacity. When measuring throughput against operational

capacity, the Ro-Ro terminals come through as operating beyond their capacity. As indicated

above, further analysis looking at factors such as cargo dwell times, parking space, as an

example are necessary before concluding that additional capacity should be deployed in this

sector.

92. Calculating the productivity of the Ro-Ro Terminal in terms of the number of units handled

per metre of berth annually and the number of units handled per hectare annually provides

the following picture.

Page 28: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

25

Figure 10: Annual Ro-Ro units per metre of berth

93. The total throughput of 681 041 units per annum over 2 050m of berth gives an average

throughput of 309 units per metre of berth. The Port of Durban and Port Elizabeth had the

higher throughput per berth metre at 436 and 389 units per metre of berth respectively.

With the second largest berth metres for handling vehicles at 559m, the Port of East London’s

101 units per metre of berth is below the average and reflects on the lower annual

throughput handled at this Port.

94. Terminal utilisation in terms of throughput per total terminal area (in hectares) is presented

in Figure 11. On average the system handles 8 481 Units per terminal area per annum.

Figure 11: Annual Ro-Ro Units per ha of terminal area

436

389

101

309

0

50

100

150

200

250

300

350

400

450

500

Durban Port Elizabeth East London Average

Ro-Ro Units per annum /metre of berth

12858

6343 6244

8481

0

2000

4000

6000

8000

10000

12000

14000

Durban Port Elizabeth East London Average

Ro-Ro Units pa/ha terminal area

Units pa/ha terminal area

Page 29: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

26

95. The Durban Ro-Ro terminal handles 12 858 units per hectare. Both the Ports of Port Elizabeth

(6 343) and East London (6 244) handled similar number of units per hectare. The Port of East

London’s terminal utilisation rate is higher than its berth utilisation rates. This shows higher

utilisation of its 9 hectares of terminal area for Ro-Ros. The Port of East London’s berth and

terminal utilisation rates indicate the productive use of terminal area and availability of

capacity to handle more throughput at berth.

96. An assessment of berth utilisation in relation to design and installed capacity provides as

sense of the level to which available capacity is utilised, other things constant.

Figure 12: Ro-ro terminal productivity in relation to design and installed capacity and 2013/14 performance

97. Figure 12 illustrates what the annual throughput per Ro-ro terminal should be based on

design capacity, installed capacity and in relation to the reported number of units handled in

2013/14.

98. The Durban Ro-ro terminal throughput per meter of berth, overall, is in line with the number

of units that the terminal should handled as per design and installed capacity. With 389 units

per metre of berth, the berth productivity for the port of Port of Port Elizabeth for 2013/14 is

in line with that calculated from its installed capacity (391 units per metre of berth).

However, with design capacity at 585 units per metre of berth, there is extra handling

capacity that can be availed through adjustments in installed capacity.

453 418 436

585

391 389

233

121 101

0

100

200

300

400

500

600

700

Units per berth metre/ design capacity

Units per berth metre/installed capacity

Units per berth meter 2013/14

Un

its

pe

r m

etr

e o

f b

ert

h

Ro-ro terminal productivity in relation to design & installed capacity vs. 2013/14 performance

Durban Port Elizabeth East London

Page 30: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

27

99. With 101 units per metre of berth, the berth productivity of the Port of East London is close

to its installed capacity of 121 units. This however, is only half of its design capacity, again

pointing to additional capacity that can be gained in the system through adjustments in

installed capacity.

Table 9: TOPS reported performance for Ro-Ro

Container terminals 13/14 Total TEUs

TOPS performance (ship working rate per hour)

Durban 501 456 136

Port Elizabeth 133 194 172

East London 56 193 172

100. Actual operational hours for Ro-Ro terminal as reflected in the number of vessels calling

within these terminals not just port hours, may yield different outcomes and will be further

investigated.

Figure 13: TOPS Automotive sector performance 2013/14

101. Figure 13 reflects the TOPS outcomes for 2013/14 according to which ship working hour for

automotive sector is on average 150 hours. Cargo dwell times of 5 days for import vehicles,

11 days for Export vehicles and similarly 10 days for transshipped vehicles.

102. The next phase of the review can assess capacity utilisation by applying these TOPS

outcomes at berth and terminal levels to further refine our understanding of the factors and

determine the extent to which what has been reported as latent capacity in these berths and

terminals can be further utilised.

596

5 13

10

40

162

565

7 14

12

45

146

553

5 11

10

45

150

Annual Throughput (Thousand)

Cargo Dwell Time Import (days)

Cargo Dwell Time Exp (days)

Cargo Dwell Time Trans (days)

Truck Turn Around Time

Ship Working Hour

RO-RO SECTOR

Baseline 2012/13 Actual Y1 TOPS Y1

Page 31: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

28

4.2.3. Dry bulk, Break Bulk and Liquid Bulk

103. Bulk products are handled at all of the South African ports with terminal capacities as

summarised in Table 10. The bulk products are handled either at the dry bulk terminals

(dominated by coal, iron ore and manganese), or break-bulk terminals (dominated by

agricultural products, grains, project cargo etc) or liquid bulk terminals (edible and non-edible

oils including petroleum) terminals.

104. There are 25 usable dry bulk berths (out of 30) in the system with 8 081m of berth length

and terminal area of 525ha, the largest cargo working space in the system. Breakbulk has 37

usable berths (out of 40), 6 476m of berth length and 230.6 ha terminal area. Liquid bulk

terminal comprise 17 usable berths (out of 18), 3 715m berth length and 276,5 ha terminal

area.

Table 10: Bulk terminals across the system (continues on next page)

Dry bulk Terminal area(ha)

Total Berths

Usable berths

Berth Length(m)

Installed Capacity

(mtpa)

Design Capacity

Installed capacity/

Design Capacity

Saldahna 73 2 2 1260 50 736 955 58 000 000 87%

Cape Town 7 3 2 569 1 400 000 2 100 000 67%

Port Elizabeth 18 1 1 360 4 459 369 5 000 000 89%

Durban 59 9 7 1581 11 000 000 11 000 000 100%

Richards Bay (coal)

280 6 6 2060 91 000 000 110 000 000 83%

Richards Bay 85 8 6 1863 14 600 000 21 000 000 70%

East London 3 1 1 388 470 478 984 000 48%

Sub-total 525 30 25 8081 173 666 802 155 884 000 111%

Break-bulk Terminal area(ha)

Total Berths

Usable berths

Berth Length

Installed Capacity

(mtpa)

Design Capacity

Installed capacity/

Design Capacity

Durban 81 14 14 871 4 000 000 4 000 000 100%

Mossel Bay 3,6 1 1 274 30 084 53 000 57%

Cape Town 22 7 6 1368 4 000 000 10 877 071 37%

Saldahna 20 6 3 874 1 708 047 3 300 000 52%

Richards Bay 81 6 6 1244 7 200 000 9 935 915 72%

East London 10 2 2 492 3 096 166 667 2%

Ngqura 5 1 1 316 0 3 000 000 0%

Port Elizabeth 8 3 4 1037 403 676 1 180 500 34%

Sub-total 230,6 40 37 6476 17 344 903 32 513 153 53%

Page 32: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

29

Liquid Bulk Terminal area(ha)

Total Berths

Usable berths

Berth Length

Installed Capacity

(mtpa)

Design Capacity

Installed capacity/

Design Capacity

Saldahna 0,5 1 1 360 6 946 229 25 000 000 28%

Cape Town 11 2 2 489 3 400 000 3 400 000 100%

Port Elizabeth 16 1 1 242 972 208 2 926 829 33%

Durban 157 9 8 1765 11 000 000 21 000 000 52%

Richards Bay 73 2 2 600 1 011 432 3 152 778 32%

East London 19 1 1 259 918 688 3 000 000 31%

Mossel Bay 0 2 2 0 1 893 127 7 971 600 24%

Sub-total 276,5 18 17 3715 26 141 684 66 451 207 39%

Compiled from Long Term Port Development Framework (NPA) 2013

105. Table 10 shows the operational capacity at 100% of design capacity at the Liquid Bulk

terminal in Cape Town Port, and Break and Dry-Bulk terminals in the Port of Durban.

Indicating that operations at these terminals have reached operational capacity.

106. Overall, Dry Bulk terminals are operating at 111% of their design capacity. However, this

belies the range where at the low end is the Port of East London with operational capacity at

only 48% of design capacity against terminals in the Port of Durban that on average have

operational capacity at 100% of installed capacity.

107. Operational capacity at Break Bulk terminal overall, is 53% of installed capacity. Next to the

Port of Durban at 100%, is the Port of Richards Bay whose operational capacity is at 72% of

design capacity. Port of East London stands at only 2% of operational capacity against its

design capacity, indicating significant underutilization of bulk terminals capacity in this port.

108. In liquid bulk terminals across the system, operational capacity is only 39% of design

capacity suggesting significant latent capacity overall. Only in Durban is operational or

installed capacity at half (52%) of design capacity.

109. The throughput for break, dry and liquid bulks are captured in Table 11 together with an

indication of what that throughput represents in terms of utilisation of the terminal in 2013.

110. It shows overall utilisation of Dry Bulk terminal in 2013 at 70% of design capacity overall. At

the level of terminals, the Port of Port Elizabeth’s Dry Bulk terminals are handling more than

their design and operational capacity at 122% and 137% respectively. This is followed by

terminals in the Port of Durban and Saldahna both with utilisation rates of 95% of the design

capacity (which for the terminal in Durban is the same as operational capacity). The data

suggests that the Port of Durban’s terminals have reached capacity and would experience

more congestion levels which would be characterized by vessels waiting for long periods of

time for berths.

Page 33: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

30

Table 11: Throughput against design capacity for dry bulk (2013)

Dry bulk

Design

Capacity

(units per

annum)

Operational

Capacity (Units

per annum)

2013/14

Throughput(mtpa)

Throughput against

design (%)

Throughput

against installed

(%)

Durban 11 000 000 11 000 000 10 443 977 95% 95%

Cape Town

2 100 000 1 400 000 646 659 31% 46%

Saldanha 58 000 000 50 736 955 55 051 928 95% 109%

Richards Bay

131 000 000 105 000 000 87 116 278 67% 83%

East London

984 000 470 478 105 637 11% 22%

Port Elizabeth

5 000 000 4 459 369 6 099 605 122% 137%

Total 173 666 802 159 464 084 70% 85%

111. The next dry bulk terminals with high utilisation rates are the Port of Richards Bay dry bulk

terminals (including RBCT) with throughput representing a utilisation of 67% of the terminal’s

design capacity. The Port of East London has the least utilisation of its design capacity at 11%,

followed by the Port of Cape Town at 31%. This trend continues when throughput is

considered against operational/installed capacity.

Table 12: Throughput against design capacity for break bulk (2013)

Break-bulk Design Capacity

(units per annum)

Operational capacity (units

per annum)

2013/14 Throughput

(mtpa)

Throughput against design

capacity (%)

Throughput against

installed capacity (%)

Durban 4 000 000 4 000 000 3 460 865 87% 87%

Mossel Bay 53 000 30 084 57 664 109% 192%

Cape Town 10 877 071 4 000 000 449 244 4% 11%

Saldanha 3 300 000 1 708 047 873 803 26% 51%

Richards Bay 9 935 915 7 200 000 3 383 847 34% 47%

East London 166 667 3 096 93 748 56% 3028%

Ngqurha 3 000 000 0 80 031 3% N/A

Port Elizabeth 1 180 500 403 676 316 714 27% 78%

Total 8 715 916 27% 50%

112. Due to non-homogeneity of cargo handled at breakbulk terminals within those terminals

annually and across the ports, breakbulk terminals demonstrate large variations in capacity

utilisation. Performance of breakbulk terminals is depicted in Table 12 in terms of throughput

against design and installed capacity. Overall, only 27% of Break-Bulk terminals are utilizing

their design capacities in South African ports. In 2013 the Port of East London and Mossel

Bay’s throughput puts their performance at way above installed capacity. It is possible that

installed capacity in this case is understated resulting in such significant performance.

Page 34: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

31

113. Table 13 provides the summaries for liquid bulk terminals throughput against design and

installed capacity of the terminals in the respective ports. The 39,2million kiloliter of

throughput in the system in 2013 represents utilisation of 59% of the design capacity of the

liquid bulk terminals across the country. However, assessing the same throughput against

installed capacity shows some strains in the system with an average of 150% utilisation.

Table 13: Throughput against design and installed capacity for liquid bulk (2013)

Liquid Bulk

Port

Design

Capacity (units

per annum)

Installed capacity

(units per annum)

2013/14

Throughput

(klpa)

Throughput

against design

capacity (%)

Throughput

against installed

capacity (%)

Durban 21 000 000 11 000 000 26 790 888 128% 244%

Mossel Bay 7 971 600 1 893 127 2 118 992 27% 112%

Cape Town 3 400 000 3 400 000 2 605 900 77% 77%

Saldanha 25 000 000 6 946 229 4 260 761 17% 61%

Richards Bay 3 152 778 1 011 432 1 777 610 56% 176%

East London 3 000 000 918 688 836 843 28% 91%

Port Elizabeth

2 926 829 972 208 887 466

30% 91%

Total 66451207 26 141 684 39 278 460 59% 150%

114. Terminal productivity for dry bulk, break bulk and liquid bulk terminals was assessed in

terms of throughput per berth and terminal area. It should be noted that with liquid bulks,

some of the product not handled at the berths, but through SBM, may be included in the

total throughput. This makes attribution of throughput to berths and to terminal area to be

imprecise requiring further work in data capturing and reporting in the next review phase.

What is presented is based on assessment of existing data.

Page 35: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

32

754136

338867

311130

177017

92380

35212

284790

0

100000

200000

300000

400000

500000

600000

700000

800000

mtpa/hectare

Dry Bulk. Mtpa/ha terminal area

Saldanha Port Elizabeth Richards Bay Durban

Cape Town East London Average

4369242289

16943

6606

1136

18490

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

50000

mtpa/berth length

Dry Bulk. mtpa/m berth

Saldanha Richards Bay Port Elizabeth Durban

Cape Town East London Average

272

Figure 14: Dry Bulk terminal productivity

115. Figure 14 highlights productivity figures in the dry bulk terminals in terms of annual

throughput per metre of berth and annual throughput per hectare of terminal area available

at each port handling dry bulk cargo. On average the system handles 18 490 million tons of

throughput per annum (mtpa) on a metre of berth. The Ports of Saldahna and Richards Bay

performs above this average handling 43 692mtpa and 42 289 per metre of berth. They are

followed by the Port of Port Elizabeth which handled 16 943mtpa, the next highest tonnage

per metre of berth, though below average. These three ports which handle coal, manganese

and iron ore, collectively account for the highest dry bulk throughput in the South African

port system.

116. Handling 338 867mtpa per hectare the Port of Port Elizabeth performs slightly higher than

the Port of Richards Bay on this measure with the latter handling 311 130mtpa per hectare.

The Port of Saldahna handled 754 136mtpa per hectare which set the average at a very high

284 790mtpa per hectare.

Page 36: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

33

3973

2720

1000

328 305 253 210 191

1 073

0

500

1000

1500

2000

2500

3000

3500

4000

4500

mtpa/m berth

Break bulk mtpa/m berth

Durban Richards Bay Saldanha

Cape Town Port Elizabeth Ngqura

Mossel Bay East London Average

4369042727

41776

39589

20420

16018 16006

9375

22067

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

50000

mtpa/hectare

Break bulk mtpa/hectare

Saldanha Durban Richards Bay

Port Elizabeth Cape Town Mossel Bay

Ngqura East London Average

Figure 15: Break bulk throughput per metre berth and per terminal area (2013)

117. Terminal and berth productivity for break bulk terminals, also measured in terms of through

put per metre of berth and per terminal area in hectares is presented in Figure 15. The

system handled break bulk cargo at an average of 1 073mtpa per metre of berth in 2013. The

Port of Durban recorded the highest number of break bulk tons per metre of berth at

3 973mtpa per metre, followed by the Port of Richards Bay which handled 2 720mtpa per

metre of berth. The rest of the Ports were below the average line.

118. Average performance on terminal area productivity, which is calculated in terms of annual

throughput per hectare, is 22 067mtpa per hectare. The four ports of Saldahna (43 690mtpa),

Durban (42 727mtpa), Richards Bay (41 776mtpa) and Port Elizabeth (39 589mtpa) performed

above the average with the remainder below the average.

Page 37: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

34

236900

170643

5546744044

24351

84509

0

50000

100000

150000

200000

250000

Cape Town

Durban Port Elizabeth

East London

Richards Bay

Average

Liquid Bulk, klpa/ha

kilolitres pa/hectare

15179

11835

5329

36673231 2963

2038

0

2000

4000

6000

8000

10000

12000

14000

16000

Durban Saldanha Cape Town

Port Elizabeth

East London

Richards Bay

Average

Liquid Bulk (klpa)/ m berth

kilolitres pa/m berth

Figure 16: Liquid bulk throughput per m/berth and per ha

119. Figure 16 summarises the productivity of the liquid bulk terminals measured by annual

throughput against berth length and hectares of land available. As mentioned previously, the

total throughput figures includes the liquid bulk cargo that would have been handled through

the Single Buoy Mooring (SBM) which is not accounted for by the given berth length. A result

of this is the absence of numbers for the Port of Mossel Bay and the Ngqurha. Figure 16 is thus

presented only as indicative. In the next review data issues with liquid bulk terminals will be

resolved with the NPA.

120. Overall, the Port of Durban accounts for high utilisation of berth i.e. above average

throughput per berth metre in Container, automotive, Break Bulk and Liquid Bulk sectors,

whilst the Port of Saldahna accounts for high throughput per metre of berth in the Dry Bulk

sector. The Port of Port Elizabeth accounts for the lowest throughput per berth metre in

containers, whilst the Port of East London accounts for the lowest throughput per berth in

the Automotive, Dry Bulk and Break Bulk sector and the Port of Richards Bay’s Liquid Bulk

Terminal accounts for the lowest throughput per berth metre for liquid bulk.

121. With regard to throughput per hectare, Durban’s container and Automotive terminals

registered the highest throughput per hectare, whilst the Port of Saldahna accounts for the

highest throughput in the Dry and Breakbulk sectors with the Port of Cape Towns’ Liquid bulk

terminal’s throughput being the highest. The Port of East London’s Automotive, Dry Bulk and

Breakbulk sectors account for the least throughput per hectare in the system, followed by

Page 38: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

35

Port Elizabeth in the container sector and Richards Bay in Liquid Bulk. A summary across the

system is provided at the end, in section 5.

4.3. Terminal utilisation per port

122. In this section terminal performance is consolidated and reported per port with some port

level comparisons given for productivity measures per commodity type handled. In order to

compare like with like, the throughput per cargo type was converted into metric tons using

the following conversion rates:

Containers: 1 TEU = 21tons (as per Global Port Pricing Comparator Study assumption)

subject to confirmation of ration between full and empty

Auto: 1 metre = 2 tons (as per tariff book) and average length of 2.5m per unit (as per

GPPCS assumptions).

Liquid bulk: due to different density per cargo, individual calculations must be done

based on TOPS data to establish a conversion factor for liquid bulk. For the purpose

of the review, the given kiloliters per annum were used without conversion.

4.3.1. Port of Durban

123. Comparing productivity across the terminals in the Port of Durban as captured in Figure 17

shows more throughput per metre of berth in the liquid bulk terminals relative to the other

terminals. This is followed by productivity in the container terminals which handles 12 384

tons per metre of berth.

Page 39: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

36

15179

12384

6606

3973

2180

0

2000

4000

6000

8000

10000

12000

14000

16000

Liquid Bulk Containers Dry bulk Breakbulk Automotive

Port of Durban

tonspa/m berth

42727

64290

170643

172548

177017

0 50000 100000 150000 200000

Breakbulk

Automotive

Liquid Bulk

Containers

Dry bulk

Port of Durban

(tons)pa/ha

Figure 17: Terminal productivity in the Port of Durban

124. Containers (185ha) and liquid bulk (157ha) accounts for the most hectares of terminal area

in the Port of Durban. However, the productivity levels in Figure 17 show that the Dry Bulk

terminals have handled slightly more tons per annum per hectare, relative to containers and

liquid bulk.

4.3.2. Port of Richards Bay

125. The Dry Bulk terminal handled the most throughput per metre of berth as well as per

hectare in the Port of Richards Bay.

Page 40: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

37

24351

41776

311130

0 50000 100000 150000 200000 250000 300000 350000

Liquid Bulk(klpa)

Breakbulk(mtpa)

Dry bulk(mtpa)

Port of Richards Bay

annual unit/ ha

42289kl

2963kl 2720mt

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

Dry bulk Liquid Bulk Breakbulk

Port of Richards Bay

annual unit pa/m berth

Figure 18: Terminal productivity in the Port of Richards Bay

126. The terminal accounts for both the most land area (385ha compared to Break Bulk (81ha)

and Liquid Bulk (73ha). Breakbulk terminal is more productive in terms of throughput per

metre of berth. The productivity of the liquid and breakbulk terminals are similar where

throughput per hectare is concerned.

4.3.3. Port of East London

127. Figure 19 shows the most productive terminal by metre of berth in the Port of East London is

the Liquid bulk terminal which handled 3 231mtpa per metre of berth. The terminal is also

the most productive in the port in relation to throughput per terminal area(ha) with

44 044klpa processed per hectare.

Page 41: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

38

3231

505

272191

0

500

1000

1500

2000

2500

3000

3500

Liquid Bulk Automotive Dry bulk Breakbulk

Port of East London

mtpa/m berth

9375

31220

35212

44044

0 10000 20000 30000 40000 50000

Breakbulk

Automotive

Dry bulk

Liquid Bulk

Port of East London

mtpa/ha

Figure 19: Terminal productivity in the Port of East London

128. The next productive terminal is the automotive terminal handling 505mtpa per metre of

berth. However, the Dry Bulk terminal is the second most productive terminal in terms of

throughput per hectare having handled 35 212mtpa per hectare; which is followed closely

the automotive terminals 31 2200mtpa per hectare. The break bulk terminal performance

per metres of berth is only 191mtpa per metre and slightly higher per hectare, attesting to

the low installed capacity and volumes in this terminal.

4.3.4. Port of Ngqurha

129. Figure 20 shows productivity at the Port of Ngqurha defaulting to the container terminal

since the Port currently only handles significant volumes of containers.

Page 42: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

39

11892

253

0

2000

4000

6000

8000

10000

12000

14000

Container Breakbulk

Port of Ngqurha

mtpa/m berth

16006

111168

0 20000 40000 60000 80000 100000 120000

Breakbulk

Container

Port of Ngqurha

mtpa/ha

Figure 20: Terminal productivity at the Port of Ngqurha

130. As reported earlier, comparing the berth and terminal productivity for the Port of Ngqurha

container terminal to that of Durban, Port Elizabeth and Cape Town places the Port of

Ngqurha ahead second to Durban on berth productivity and second to the Port of Cape Town

on terminal productivity.

4.3.5. Port of Port Elizabeth

131. Terminal productivity as reported in Figure 18 shows the Dry Bulk Terminal in the Port of

Port Elizabeth accounting for the highest tons per metre of berth and per terminal area. This

is due to Manganese which is moved in the terminal and whose throughput is same as the

installed capacity.

Page 43: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

40

31715

39589

55467

97080

338867

0 100000 200000 300000 400000

Automotive

Breakbulk

Liquid Bulk

Containers

Dry Bulk

Port of Port Elizabeth

mtpa/ha

16943

5508

3667

1945

305

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

Dry bulk Containers Liquid Bulk Automotive Breakbulk

Port of Port Elizabeth

mtpa/m berth

Figure 21: Terminal productivity at the Port of Port Elizabeth

132. The container (5 508mtpa/berth metre) and liquid bulk (3 667mtpa/berth metre) terminals

are the next two terminals with high throughput per berth metre and terminal area. Break

bulk only handled 305mtpa per berth metre whilst automotive terminals handled 31 715

mtpa per hectare at the bottom end of the productivity rates in this Port.

4.3.6. Port of Cape Town

133. The productivity levels in the Port of Cape Town shows the container terminal performing

higher than the other terminal with a throughput of 9 468mtpa per metre of berth. In terms

of terminal area, liquid bulk had the highest throughput per hectare, handling 236 900mtpa

per hectare.

9468

5329

1136

328

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

Containers Liquid Bulk Dry bulk Breakbulk

Port of Cape Town

unitpa/m berth

20420

92380

157872

236900

0 50000 100000 150000 200000 250000

Breakbulk

Drybulk

Container

Liquid bulk

Port of Cape Town

mtpa/ha

Figure 22: Terminal productivity in the Port of Cape Town

Page 44: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

41

134. Breakbulk terminal recorded the lowest throughput per berth metre and per hectare in the

Port of Cape Town.

4.3.7. Port of Saldahna

135. The Port of Saldahna handles liquid, dry and break bulk. The reported terminal area for

Liquid Bulk is 3.6hectares which translates into a significantly high productivity rate of

8 521 511kilolitres per annum per hectare.

43690

754136

8521522

0 2000000 4000000 6000000 8000000 10000000

Breakbulk(mtpa)

Dry bulk(mtpa)

Liquid Bulk(klpa)

Port of Saldahna

unitpa/ha

1000mt

11835kl

43692mt

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

50000

Breakbulk Liquid Bulk Dry bulk

Port of Saldahna

unitpa/m berth

Figure 23: Terminal productivity at the Port of Saldahna

136. However, productivity measured at throughput per berth metre, shows the dry bulk

terminal to be more productive. 43 672mt per annum per berth metres are handled. The

berth area for liquid bulk in the Port of Saldahna is given as only 500 metres which accounts

for the significantly high throughput per berth metre. Dry bulk (which handles mainly iron ore

and manganese ore) accounts for the highest throughput per hectare in the Port of Saldahna.

Very limited break bulk cargo is handled at the Port of Saldahna with the terminal accounting

for low productivity per metre of berth and terminal area.

Page 45: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

42

5. Summary

137. Table 14 below provides a snap shot on the status quo of the levels of utilisation of South

African terminals per commodity type and per port. It summarises current port terminal use

using reported NPAs 2013/14 throughput per terminal in relation to design and then installed

capacity in the terminal. Full capacity is defined as a terminal operating at 100% of design or

installed capacity.

138. The table also summarises terminal performance in terms of throughput per metre of berth

and per terminal area for each of the commodity types as reported. Averages were

determined for each of the commodity types and that average is used to indicate if the

reported performance of a terminal is within the average of all terminals handling the same

cargo types. For container and Ro-ros, the table also reflects performance against design and

installed capacity.

Page 46: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

Table 14: Summary of terminal use by cargo type and port

Richards Bay

Durban East London

Port Elizabeth

Ngqurha Mossel Bay

Cape Town

Saldahna

Throughput in relation to design capacity: compared against capacity of 100%

Containers N/A Close to capacity

(88%)

Below capacity

(44%)

Below capacity

(49%)

Below capacity

(25%)

N/A Below capacity

(61%)

N/A

Ro-Ro N/A Close to capacity

(96%)

Below capacity

(43%)

Below capacity

(67%)

N/A N/A N/A N/A

Dry Bulk Below capacity

(67%)

Close to capacity

(95%)

Below capacity

(11%)

Above capacity

(122%)

N/A N/A Below capacity

(31%)

Close to capacity

(95%)

Break Bulk Below capacity

(34%)

Close to capacity

(87%)

Below capacity

(56%)

Below capacity

(27%)

Below capacity

(3%)

Above capacity

(109%)

Below capacity

(4%)

Below capacity

(26%)

Liquid Bulk Below capacity

(56%)

Above capacity

(128%)

Below capacity

(28%)

Below capacity

(30%)

N/A Below capacity

(27%)

Close to capacity

(77%)

Below capacity

(17%)

Port level summary analysis

Below capacity

Close to and

above capacity

Below capacity

Mainly below

capacity

Significantly below Capacity

Breakbulk

above, Liquid Bulk

below capacity

Mainly Below

capacity

Mainly below

capacity

Throughput in relation to installed capacity: compared to capacity of 100%

Containers N/A Close to capacity

(88%)

Close to capacity

(77%)

Close to capacity

(90%)

Above capacity

(145%) ***

N/A At capacity (101%)

N/A

Ro-Ro N/A Above capacity

(104%)

Close to capacity

(83%)

At capacity (100%)

N/A N/A N/A N/A

Dry Bulk Close to capacity

(83%)

Close to capacity

(95%)

Below capacity

(22%)

Above capacity

(137%)

N/A N/A Below capacity

(46%)

Above capacity

(109%)

Break Bulk Below capacity

(47%)

Close to capacity

(87%)

Above (3 028%)

Close to capacity

(78%)

N/A Above capacity

(192%)

Below capacity

(11%)

Below capacity

(51%)

Liquid Bulk Above capacity

(176%)

Above capacity

(244%)

Close to capacity

(91%)

Close to capacity

(91%)

N/A Above capacity

(112%)

Close to capacity

(77%)

Below capacity

(61%)

Port level summary

analysis

Mainly close to

and above

capacity

Mainly close to

and above

capacity

Mainly close to

and above

capacity

Mainly close to and

above capacity

Above capacity

Above capacity for two of four berths

Mainly below

capacity

Mainly Below

capacity and above

on Dry bulk

Throughput per berth metre: compared against average

Containers (Ave: 818)

N/A Above ave

(1 032)

N/A Below ave (459)

Above Ave

(991)

N/A Below Ave (789)

N/A

Ro-Ro (Ave:309)

N/A Above ave (436)

Below ave (101)

Above ave (389)

N/A N/A N/A N/A

Dry Bulk (Ave:18 490)

Above ave (42289)

Below ave (6 606)

Below ave (272)

Below ave (16 943)

N/A N/A Below Ave ( 1 136)

Above ave (43 692)

Break Bulk (Ave:1 073)

Above ave ( 2 720)

Above ave (3 973)

Below ave (191)

Below ave (305)

Below Ave (253)

Below Ave

(16 018)

Below Ave (328)

Below Average

(1000)

Liquid Bulk Above ave Above Above Above ave N/A N/A** Above ave Above ave

Page 47: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

44

(Ave:2 038) (2 963) ave* (15 179)

Ave (3 231)

(3 667) (5 329) (2 038)

Port level summary analysis

Above average

Mainly Above average

Below average

Mainly Below average

Average Below average

Mainly Below Average

Mainly above Average

Throughput per berth metre compared against design and installed capacity: Containers (Reported figures based on 2013/14 throughput)

Design capacity

N/A (1032) 1 171

N/A (459) 945 (991) 3 889

N/A (789) 1 303

N/A

Installed capacity

N/A (1032) 1 171

N/A (459) 512 (991) 683 N/A (789) 782 N/A

Port level summary analysis (reported throughput vs design and installed capacity)

N/A Terminal operating at full capacity

N/A Terminal operating close to installed capacity and at half of design capacity

Terminal operating above installed capacity but significantly below design capacity

N/A Terminal operating above installed capacity with some design capacity still available

N/A

Throughput per berth metre compared against design and installed capacity: Ro-ro( reported figures based on 2013/14 throughput )

Design capacity

N/A (436)453 (101)233 (389) 585 N/A N/A N/A N/A

Installed capacity

N/A 418 121 391 N/A N/A N/A N/A

Port level

summary

analysis

N/A Terminal operating at design

and installed capacity

Terminal

operating

close to

installed

capacity

but below

design

capacity

Terminal

operating

close to

installed

capacity but

significantly

below

design

capacity

N/A N/A N/A N/A

Throughput per terminal area compared against average

Containers (Ave: 11 222)

N/A Above ave ( 14 379)

N/A Below ave (8 090)

Below ave (9 264)

N/A Above ave (13 156)

N/A

Ro-Ro (Ave: 8 481)

N/A Above ave (12 858)

Below ave (6 244)

Below ave ( 6 343)

N/A N/A N/A N/A

Dry Bulk (Ave:

284 790)

Above ave (311 130)

Below ave (177 017)

Below ave (35 212)

Above ave (338 867)

N/A N/A Below Ave (92 380)

Above Ave (754 136)

Break Bulk ( Ave: 22 067)

Above ave (41 776)

Above Ave

(42 727)

Below ave (9 375)

Above ave (39 589)

Below ave (16 006)

Below ave

(16 018)

Below ave (20 420)

Above ave (43 690)

Liquid Bulk (Ave:

84 509)

Below ave (24 351

Above Ave*

(170 643)

Below ave (44 044)

Above ave (55 467)

N/A

N/A** Above ave (236 900)

Above ave (8 521

522)

Port level summary

analysis

Mainly Above

Average

Mainly Above

average

Below average

Mainly Above

Average

Below average

Below average

Average Above average

* Some of the Liquid Bulk is handled at the off-shore mooring at Isipingo and is thus not included in the throughput per berth or per

hectare.

**Liquid bulk at the Port of Mossel Bay is handled at the Single Buoy Mooring (SBM) off shore thus no figures are given for berth and

hectare.

*** this is against installed capacity of two berths out of four.

Page 48: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

45

139. This is only a snap shot and as previously indicated; the next iteration will look at trends

based on historical throughput and demand projections to enable some conclusions to be

drawn on the need for expansion capacity, both in terms of infrastructure and installed

capacity. The snap shot is only indicative based on information assessed.

140. The Port of Richards Bay is operating below installed capacity in general, and its operations

are close to and above capacity with regards installed capacity. This indicates that overall

there is capacity that can be made available in the system by addressing matters relating to

installed capacity. It’s overall performance in terms of throughput per metre of berth and per

hectare for all the cargo types suggests above average performance in the system.

141. The Port of Durban numbers suggests that the port is operating close to and above design

capacity in all its terminals in relation to both design and installed capacity pointing to limited

scope for more capacity to be handled with current capacity. The recorded performance of

the terminals in terms of throughput per metre of berth and terminal area points to terminal

performance above average in the system.

142. The Port of East London figures show that it is operating below capacity in terms of design

capacity. The numbers for installed capacity has the port operating mainly close to and above

capacity highlighting that additional capacity can be accessed by addressing installed

capacity. This is supported by below average performance in the port’s throughput per metre

berth and per terminal area. Besides installed capacity, market factors may also account for

the performance of the Port of East London which services a hinterland with lower economic

performance.

143. In the same region, the Port of Port Elizabeth comes through as operating mainly below

design capacity of its terminals but close to and above installed capacity (dry bulk terminal)

with below average performance in both throughput per metre of berth and terminal area.

Overall, this suggests scope for improvement in installed capacity and operational

performance. The dynamic created by the proximity of the Port of Port Elizabeth to the Port

of Nqgurha must also be taken into account.

144. The Port of Ngqurha itself is shown to be operating significantly below installed capacity

whereas the levels of installed capacity suggests above capacity operations. This point to the

fact that installed capacity is not maximizing design capacity in this port, highlighting that

more can be achieved by addressing installed capacity. The Port of Ngqurha performed on

average in terms of throughput per metre of berth and below average on throughput per

terminal area. The above capacity performance against installed capacity must be seen in the

context of installed capacity of two berths.

Page 49: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

46

145. The Port of Mossel Bay’s terminal operations in relation to design capacity is below capacity

for liquid bulk the main cargo type handled at this port and above capacity for breakbulk. Its

operations are above average in relation to installed capacity again suggesting more

throughput can be handled by increasing installed capacity. On both throughput per metre of

berth and terminal area, the port has performed below the averages.

146. The Port of Cape Town operations are mainly below design capacity and close to capacity for

liquid bulk whilst, in relation to installed capacity the terminals are operating mainly below

capacity. With mainly below average and average performance on throughput per metre of

berth and terminal area respectively, the Port of Cape Town improving operations and

installed capacity can provide more capacity.

147. Lastly, the Port of Saldahna’s terminal operations in relation to design and installed capacity

is mainly below capacity, except for dry bulk terminal where operation are above installed

capacity. The terminals are also performing above the system averages.

6. Way forward

148. In the introduction of the review, it has been established that various approaches can be

followed to determine optimal performance standards against which the terminal

performance can be assessed. This includes the Stochastic Frontier Analysis approach, Data

Envelopment Analysis approach, Benchmarking against international ports etc. This requires

much expertise as well as data and has not been used in this initial study. In addition,

efficiencies and utilisation can also be weighed against investment and availability of capital

in analysis such as financial and economic NPV, internal rates of return, payback analysis,

economic value add and many others. At most, the analysis presented in this document

serves to paint a picture of some of the PRSAs observations within the limitation of the data

and expertise available.

149. Another approach, which is presented below, is to use the UNCTAD berth utilisation factor

to determine whether South African terminals are operating optimally. It is proposed that the

NPA be engaged further on this approach, as outlined below.

150. In determining optimal performance standards; berth and terminal utilisation rates as well

as across the ship rates must be calculated using the UNCTAD international norms. Berths

and terminals are the point of interface amongst various players in the port systems,

primarily exchange between vessels and cargo. Terminal and berth utilisation rates i.e. the

time available to vessels to exchange cargo across the quay wall and the rate at which that

Page 50: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

47

exchange happens are key indicators of how well a port or terminal is doing. The following

are the formulae and input parametres used in calculating optimal berth utilisation and ATS

for South African terminals:

151. Operational hours, number of berths per terminal as well as throughput per terminal are

required to calculate both berth utilisation and across the ship rates.

Operating hours:

Ports: No of. Operating hours As per tariff book

Durban, Richards Bay, Ngqurha, Port Elizabeth, Cape Town, Saldahna

365 days * 24hrs = 8760

East London 16hrs * 5 days a week: 60 * 52 = 4160 plus 6hrs on Saturdays: 8*52 = 416 Total hrs: 4576

Mossel Bay 12hrs * 5days a week: 60*52= 3120 Total hrs: 3120

Usable berths:

152. Usable Berths instead of total berths would be used. The intention is to determine the

utilisation of operational rather than design capacity. However as has been done in the

report, the same calculations can be done to determine productivity level of the full

infrastructure that port users are paying for.

153. The terminal utilisation rate describes the ideal number of hours that all the berths,

collectively; in a terminal should be operating cargo. This can be used as a standard by which

South African terminal’s actual utilisation should be compared to.

154. Berth Utilisation calculates an optimum utilization rate of a terminal (in hours) based on the

number of berths (as per utilisation factor) and number of terminal operational hours i.e. the

number of hours that the terminal should be operational per annum.

Berth/terminal utilisation factor

155. The Berth Utilisation Factor attempts to standardize across various factors that influence

operations in a berth to arrive at a commonly agreed figure that a berth must operate in a

year. The Berth Utilisation factors are based on those set by the United Nations Conference

on Trade and Development (UNCTAD:1986) in the port performance measurement manual.

Although determined in the 1980s, these factors have not required material adjustments

over the years, except for upward revisions on container terminal factors. Berth utilisation

factors used in the calculations are provided in Table 15.

Page 51: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

48

Table 15: Berth Utilisation Factor

Number of berths

Vehicles (%) Liquid Bulk(%)

Containers (%)

Dry Bulk(%) Break Bulk(%)

1 45 45 45 70 45

2 50 50 50 70 50

3 55 55 55 70 55

4 60 60 60 70 60

5 65 65 65 70 65

6 70 70 70 70 70

7 70 70 70 70 70

UNCTAD: where there are more than 7 berths, the factor remains 70%.

156. These represents the percentage of time that a berth or number of berths when available

will allow optimal use thereof without congestion or low service. The highest utilisation

factor is 70%. This is however not the maximum but rather the optimal utilization for a

terminal with x number of berths. Where actual utilisation is above the utilisation factor, the

likelihood of congestion is high, pointing to a need for either operational improvements or

additional capacity.

Formulae for calculations:

a. Terminal Utilisation rate (%) = Operational hrs x no. of berths x utilisation factor

(UNCTAD utilisation factors in table above)

b. Berth Utilisation rate (%) Terminal Utilisation rate Number of berths

c. Across the ship rate (ATS) = Throughput Terminal Utilisation

157. As an example, using the 2013/14 cargo throughputs gives the following indicative utilisation

rates:

Page 52: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

49

Table 16: Example of possible optimal berth utilisation and ATS for SA terminals

158. According to these calculations for Durban container terminals as an example, the optimal

berth utilisation rate for this 7 berth, 8760 hrs terminal must be 42 924hrs in a year. Across

the ship working rate, is 62 TEU per hr, which can be verified by simply multiplying the

calculated optimal ATS and Berth Utilisation to find the Annual throughput 42 924 x 62 =

2 660 144. However, actual performance must be assessed when actual terminal availability

in hours and actual ship working rates are computed.

159. Table 15 therefore provides an indication of the optimal levels or standard for ATS and Berth

Utilisation rates as per the UNCTAD model which should be compared to the actual ATS and

Berth Utilisation for South African terminals as reported by the NPA.

7. Conclusion

160. This review reports on the infrastructure the NPA provides to service the various cargo types

handled in South African ports. The report provides a birds “eye-view” on the utilisation of

infrastructure in the various terminals, identifies using various capacity measures,

infrastructure that may be close to full capacity, and points towards prioritisation of

infrastructure needs in the NPA CAPEX programme. The study forms a baseline which will lay

a foundation for the next phase of the Regulator’s Review which will gradually improve

CAPEX analysis capability on behalf of port users.

Containers Automotive Dry Bulk Break bulk Liquid Bulk

Ship rate

(ATS)

Berth Utilisation

(hrs)

Ship rate

(ATS)

Berth Utilisation

(hrs)

Ship rate

(ATS)

Berth Utilisation

(hrs)

Ship rate

(ATS)

Berth Utilisation

(hrs)

Ship rate

(ATS)

Berth Utilisation

(hrs)

Richards Bay Coal n/a n/a n/a n/a 2368 36 792 n/a n/a n/a n/a

Richards Bay n/a n/a n/a n/a 0 36 792 92 36 792 203 8 760

Durban 62 42 924 35 14 454 243 42 924 40 85 848 546 49 056

East London 9 4 576 27 2 059 n/a n/a 20 4 576 406 2 059

Port Elizabeth 33 8 760 30 4 380 995 6132 16 19 272 184 4 818

Ngqurha 81 8 760 n/a n/a n/a n/a 20 3 942 n/a n/a

Mossel Bay n/a n/a n/a n/a n/a n/a 41 1 404 679 3 120

Cape Town 37 24 528 n/a n/a 53 12 264 12 36 792 297 8 760

Saldahna n/a n/a n/a n/a 4489 12 264 47 18 396 1081 3 942

Page 53: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

50

8. Bibliography

1. Bichou K & Gray R. 2004. A logistics and supply chain management approach to port performance

measurement. Maritime Policy Management Journal. Vol. 31, No.1. 47-67. Taylor & Francis.

2. Chung , C.K. (1993) Port Performance Indicators, Transportation, water, and urban development

department, The World Bank.

3. Container Ports Fact Book: Antwerp, Zeebruggee, Rotterdam, Bremen and Hamburg. Development

and realisation of growth. Adstrat Consulting, 2012.

4. Kevin Cullinane 2010? Revisiting the productivity and efficiency of ports and terminals:

methods and applications. Transport Research Institute, Edinburgh Napier University.

5. Kevin Cullinane, Rickard Bergqvist and Gordon Wilmsmeier (2012). The dry port concept – theory and

practice. Maritime Economics & Logistics (2012) 14, 1–13 (http://www.palgrave-

journals.com/mel/journal/v14/n1/full/mel201114a.html)

6. Merk, O., Li, J. (2013), “The Competitiveness of Global Port-Cities: the case of Hong Kong – China”,

OECD Regional Development Working Papers, 2013/16, OECD Publishing,

http://dx.doi.org/10.1787/5k3wdkjtzp0w-en

7. Pjevcevic, D; I. Vladisavljevic & K. Vukodinovic (2013) Analysing the efficiency of dry bulk cargo

handling at the inland port terminal using simulation and DEA. A paper presented at the 1st

Logistics

International Conference, Belgrade. November 2013.

8. Port benchmarking for assessing Hong Kong’s Maritime services and associated costs with other

major international ports. Marine Department Planning, Development and Port Security Branch,

December 2006.

9. Salminen, J.B., 2013. Measuring the Capacity of a port system: a case study on a Southeast Asian Port.

Dissertation in partial fulfillment of the requirements for the Degree of Master of Engineering

Logistics, Massechusetts Institute of Technology.

10. Sarriera J.M., T. Serebrisky, G. Araya, C. Briceno- Garmendia and J. Schwartz. Benchmarking container

terminal efficiency in Latin American and the Carribean. Inter-American Development Bank (IDB)

Working Paper Series no. IDB-WP-474.

11. Talley, W.K. (2008) Container Port Efficiency and output measures.

12. The DBSA & DPME, 2012. The State of South Africa’s Economic Infrastructure: Opportunities and

Challenges 2012. A publication of the Department of Performance, Monitoring and Evaluation at the

Presidency and the Development Bank of Southern Africa.

13. The National Ports Act, Act 12 of 2005.

14. The National Ports Authority (NPA), 2013. Long Term Port Development Framework.

15. The Tioga Group (2010). Improving Marine container terminal productivity: development of

productivity measures, proposed sources of data and initial collection of data from proposed sources.

A report prepared for the Cargo Handling Co-operative Program.

Page 54: SA port terminals: capacity and utilisation review 2014/15 MEASURING PORT CAPACITY AND UTILISATION ... Dry bulk, Break Bulk and ... If this transit time is included in the calculation

51

16. UNCTAD 1986 “Manual on a uniform system of port statistics and performance indicators”

www.portsregulator.org