SCHEDULED PATHWAY CLOSURES ATCO is replacing a segment of the natural gas pipeline system that crosses below the Sturgeon River (see map below for exact locations). Our contractor, Arnett & Burgess, will begin construction in early February and will be completing the work by early May (weather permitting). The replacement of the river crossing will be completed by Horizontal Directional Drill (HDD) to minimize disturbance to the river ecosystem. SAFETY: The construction sites will be fenced or flagged off. For your safety and the safety of our construction crews, please do not enter into the work area. We ask that you keep all dogs on leash to avoid our construction site and please keep all children away from the fenced areas. CONTACT: Greg Satre - 780-913-0946 IMPACTS (SEE MAP ABOVE): • Road closures • The BMX Facility can be accessed by pedestrians after April 1. Parking will be available in the south lot of Riel Park during construction. • Path way closures • Multi-use path through Riel Park will be closed intermittenly. Increase in construction traffic • Portion of trail system restricted due to work area

SCHEDULED PATHWAY CLOSURES - stalbert.ca · SCHEDULED PATHWAY CLOSURES ATCO is replacing a segment of the natural gas pipeline system that crosses below the Sturgeon River (see map

Embed Size (px)

Citation preview

Page 1: SCHEDULED PATHWAY CLOSURES - stalbert.ca · SCHEDULED PATHWAY CLOSURES ATCO is replacing a segment of the natural gas pipeline system that crosses below the Sturgeon River (see map

SCHEDULED PATHWAY CLOSURESATCO is replacing a segment of the natural gas pipeline system that crosses below the Sturgeon River (see map below for exact locations). Our contractor, Arnett & Burgess,

will begin construction in early February and will be completing the work by early May (weather permitting). The replacement of the river crossing will be completed by

Horizontal Directional Drill (HDD) to minimize disturbance to the river ecosystem.

SAFETY:The construction sites will be fenced or flagged off. For your safety and the safety of our construction crews, please do not enter into the work area. We ask that you keep all dogs on leash to avoid our construction site and please keep all children away from the fenced areas.

CONTACT:Greg Satre - 780-913-0946

IMPACTS (SEE MAP ABOVE):• Road closures

• The BMX Facility can be accessed by pedestrians after April 1. Parking will be available in the south lot of Riel Park during construction.

• Path way closures• Multi-use path through Riel Park will be

closed intermittenly.• Increase in construction traffic• Portion of trail system restricted due to work area

Page 2: SCHEDULED PATHWAY CLOSURES - stalbert.ca · SCHEDULED PATHWAY CLOSURES ATCO is replacing a segment of the natural gas pipeline system that crosses below the Sturgeon River (see map

SCHEDULED PATHWAY CLOSURESATCO is replacing a segment of the natural gas pipeline system that crosses below the Sturgeon River (see map below for exact locations). Our contractor, Arnett & Burgess,

will begin construction in early February and will be completing the work by early May (weather permitting). The replacement of the river crossing will be completed by

Horizontal Directional Drill (HDD) to minimize disturbance to the river ecosystem.

IMPACTS (SEE MAP ABOVE):• Increase in construction traffic• Portion of trail system restricted due to work area

CONTACT:Greg Satre - 780-913-0946

SAFETY:The construction sites will be fenced or flagged off. For your safety and the safety of our construction crews, please do not enter into the work area. We ask that you keep all dogs on leash to avoid our construction site and please keep all children away from the fenced areas.