12
Title: Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects Unique Identifier: 240-165394120 Alternative Reference Number: N/A Area of Applicability: Kendal PS Documentation Type: Scope of Work Revision: 01 Total Pages: 12 Next Review Date: N/A Disclosure Classification: CONTROLLED DISCLOSURE Compiled by Functional Responsibility Authorised by …………………………… ……………………………… ……………………………….. Mokotedi Mokoena Site Supervisor GCD Phindile Khanyile Contracts Manager GCD Vusi Mlandu Project Manager GCD Date: …………………………… Date: …………………………… Date: …………………………… Scope of Work GCD 30 August 2021 30 August 2021 30 August 2021

Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

  • Upload
    others

  • View
    14

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Title: Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Alternative Reference Number:

N/A

Area of Applicability: Kendal PS

Documentation Type: Scope of Work

Revision: 01

Total Pages: 12

Next Review Date: N/A

Disclosure Classification: CONTROLLED DISCLOSURE

Compiled by Functional Responsibility Authorised by

…………………………… ……………………………… ………………………………..

Mokotedi Mokoena

Site Supervisor

GCD

Phindile Khanyile

Contracts Manager

GCD

Vusi Mlandu

Project Manager

GCD

Date: ……………………………

Date: ……………………………

Date: ……………………………

Scope of Work GCD

30 August 202130 August 2021 30 August 2021

Page 2: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

CONTROLLED DISCLOSURE

When downloaded from the EDMS database, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the database.

Unique Identifier: 240-165394120

Revision: 01

Page: 2 of 12

CONTENTS

PAGE

1. INTRODUCTION .......................................................................................................................................... 3

1.1 BACKGROUND ..................................................................................................................................... 3 1.2 PROJECT OVERVIEW ......................................................................................................................... 4

2. SUPPORTING CLAUSES ............................................................................................................................ 7

2.1 SCOPE .................................................................................................................................................. 7 2.1.1 Purpose ......................................................................................................................................... 7 2.1.2 The purpose of this document it to provide a high-level scope of work outlining the activities which

are required by the Contractor. Applicability ..................................................................................... 7 2.2 NORMATIVE/INFORMATIVE REFERENCES ...................................................................................... 7

2.2.1 Normative References ................................................................................................................... 7 2.2.2 Informative References ................................................................................................................. 8

2.3 DEFINITIONS ........................................................................................................................................ 8 2.3.1 Classification ................................................................................................................................. 8

2.4 ABBREVIATIONS .................................................................................................................................. 9 2.5 RELATED/SUPPORTING DOCUMENTS ............................................................................................. 9

3. SCOPE OF WORK ....................................................................................................................................... 9

4. DELIVERABLES ........................................................................................................................................ 11

5. AUTHORISATION ...................................................................................................................................... 12

6. REVISIONS ................................................................................................................................................ 12

7. DEVELOPMENT TEAM ............................................................................................................................. 12

8. ACKNOWLEDGEMENTS .......................................................................................................................... 12

Page 3: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 3 of 12

1. INTRODUCTION

1.1 BACKGROUND

Kendal Power Station (Kendal) is a 4 116 MW installed capacity base load coal fired power station,

consisting of 6 units. Eskom commenced construction of Kendal in 1982, which was completed in

1993. The ash disposal facility is approximately 2km south-west of the Kendal Power Station terrace,

and to the west of the R686.

Ash is generated as a by-product due to the combustion of coal from the power station. As a result of

this process Kendal produces about 5.5 million tons of ash per annum. The ash is transported from

the boilers to the dry ash dump by means of dual overland conveyors. The ash dump is constructed

by the main stacker and standby spreader in a progressive nature by placing a front stack of ash in

front of the conveyors down to ground level and a 12m backs tack behind. This ash is currently being

disposed of within the premises of the Kendal Power Station, on Eskom owned land in terms of the

current power station Water Use Licence.

The original design of the ash dump was done by Jones & Wagener consulting civil engineers in the

mid 1980’s. The ash dump was designed for a 40 year station life, plus an 8 year contingency area,

by diverting the western clean water stream into the next valley and ashing over the western stream

valley. As only 60% of the land for the ash dump was purchased at the start of the power station,

Kendal did not secure its ashing rights for the total design life and uncontrolled private surface coal

mining took place on the remaining area. This resulted in the original ash dump design no longer being

feasible to construct as the required western clean water stream diversion dam could no longer be

built on the disturbed coal mine area. The remaining properties required for the ash dump construction

were purchased in 2008.

Due to this situation, the footprint of the ash dump was constrained within the original design footprint

on the current dump site, to the area between the northern and western clean water streams, which

resulted in a loss of about 20% of the original design area. This loss of dump capacity, together with

a higher ash volume due to poorer quality coal, higher generating loads and a lower ash dump density

than assumed in the original design, together with the recent increase in the required station life to 60

years, resulted in the current ash dump site not being able to provide ashing capacity for Kendal’s

remaining life.

Page 4: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 4 of 12

1.2 PROJECT OVERVIEW

Due to the need to obtain an Integrated Environmental Authorisation (including Waste) and a Water

Use Licences (WUL) for the ashing operations for the remaining area of the continuous ash dump on

the new properties and the new 30 year ash disposal facility, Zitholele Consulting were appointed to

carry out an EIA study to assess the environmental risks and determine the optimum dump

construction and required mitigation works, in order to provide continuous ashing capability for

Kendal’s 60 year life. The Integrated Environmental Authorization (IEA) was issued on 28 July 2015

for a period of 5 years and WUL was issued on 18 December 2015.

Current environmental legislations require that the construction and operation of an ash disposal

facility, must comply with all relevant environmental legislation such as the National Environmental

Management Act, Act No. 107 of 1998, National Environmental Management Waste Act, Act No. 59

of 2008 and the National Water Act, Act No. 36 of 1998. Therefore the ash disposal facility was

required to obtain the Environmental Authorisation, Waste Management Licence and the Water use

Licence in order to comply with environmental legislation.

The Kendal ADF is currently an unlined dry stack ash dump. The ADF is designed to have one unlined

phase and four lined phases as mentioned in the ADF phasing and development section. Ash

reporting to the Kendal ADF is classified as a Type 3 waste which requires a Class C landfill barrier.

The design, as prescribed by the Norms and Standards, referenced above, takes into account the

specific conditions for the site and waste body and the availability of material. Therefore, stemming

from the foregoing, the following barrier design is proposed (from top to bottom):

As part of the conditions of environmental approval, the detailed design drawings for the Class C liner

were completed with input from the Department of Human Settlements, Water and Sanitation. DWS

have approved the design drawings for the Class C performance liner, with the additional requirement

for a screened 300mm layer of coarse ash to be placed between the geomembrane and the waste

body. Eskom deems the screened material as part of the liner system and construction method

statement of placement of the material is essential for the longevity of the liner.

Page 5: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 5 of 12

Figure 1 Liner Details

Proposed barrier design

Ash waste body;

Drainage layer of coarse ash;

Leachate collection finger drains consisting of the following:

o Graded washed filter sand;

o Graded washed pea gravel;

o Graded washed stone;

o Holed HDPE pipes.

1.5mm HDPE single textured geomembrane; and

300mm thick low permeable subgrade layer with a maximum permeability of 1x10-6 cm/s.

In discussions with Kendal PS operations team and Eskom GTE (Civil), it was concluded that ash can

be sourced from the power station and used as a drainage/protection layer across the footprint of the

ADF, after screening to the below indicated envelope. This should greatly reduce the capital

Page 6: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 6 of 12

expenditure for each phase; alternatively, a washed coarse river sand is required which would have a

substantial cost implication.

Figure 2 Coarse Ash Envelope

The coarse ash layer shall be placed and spread over the liner in a 300mm layer and care should be

taken to avoid damaging the liner during the process. It should be noted that coarse ash can only be

placed on the geomembrane during the coolest parts of the day, when the geomembrane core

temperature is less than 45⁰C. This is done to reduce the entrapment of wrinkles under the layer of

coarse ash and to keep the strain in the geomembrane below 3%.

As stated above, the site works instruction confirms that ash will be a free issue material from the

Kendal Power Plant and will need to be screened to the indicated envelope requirements to remove

particles larger than 3mm and smaller than 0.425 mm as a precaution against any damage to the liner

and to prevent clogging of the leachate drains and transported from the Kendal Emergency Dump (E-

Dump) located inside Kendal Power Station to the Ash disposal facility which is 18km from the E-

dump. The ash will be in a wet state and will be temporarily stockpiled to dry out at the Kendal

Emergency Dump.

Once the ash is suitably dry, it will be screened to meet the requirements of the indicated envelope.

The method statement involves placing the screened course ash on top of the geomembrane in a

300mm layer as prescribed by DWS. The ash particles greater than 3mm and below 0.425mm in size

will be placed on top of the 300mm layer.

The screening and stockpiling of the coarse ash are necessary steps in the process to comply with

the DWS design requirements. A decision was taken during the detailed design phase to truck course

Page 7: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 7 of 12

ash from the E-Dump to the Contractor’s lay-down area. The distance from the E-Dump to the

Contractor’s lay-down area is 18km, one-way trip.

Hence Kendal Power Station should undertake actions that will enable it to comply with the latest

legislations.

2. SUPPORTING CLAUSES

2.1 SCOPE

2.1.1 Purpose

2.1.2 The purpose of this document it to provide a high-level scope of work outlining the activities which are required by the Contractor. Applicability

This document applies to Kendal Power Station.

2.2 NORMATIVE/INFORMATIVE REFERENCES

Parties using this document shall apply the most recent edition of the documents listed in the following

paragraphs:

2.2.1 Normative References

1. Kendal Ash Dump and Dam Operations and Maintenance Manual.

2. Concept Design Report for Kendal’s Continuous and Emergency Ash Disposal Facilities Ref:

12810, 5 May 2014.

3. Kendal Power Station Existing Area Water Use Licence.

4. Water Use Licence for new properties.

5. DWS approval in principal letter.

6. Kendal Extension of Ashing Infrastructure, User Requirement Specification.

7. Kendal Emergency Dump Extension, User Requirement Specification.

8. SANS 10286, Mine Residue.

9. SANS 1200 series, standardized specification for Civil Engineering Construction.

10. The National Water Act & Regulation GN704.

11. Environmental Protection Acts NEMA & NEMWA and regulations.

12. Kusile and Kendal Power Stations Ash Disposal Facilities Waste Classification Report, Ref:

JW030/13/D121 - Rev 3, January 2014.

Page 8: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 8 of 12

13. All work shall be conducted in accordance with the requirements of the Occupational Health

and Safety Act (Act 85 of 1993) as amended.

14. Kendal Continuous Ash Disposal Facility Project – Detailed Design Report

15. 379-KEN-BEEC-D00035-1: Kendal Power Station Emergency Dump Extension Project

Employers Works Information.

16. Kendal Continuous Ash Disposal Facility Project – Works Information Phase 2

17. Kendal Continuous Ash Disposal Facility Project – Works Information Phase 3

2.2.2 Informative References

18. The National Environmental Management Act (No. 107 of 1998) and 2014 Environmental

Impact Assessment Regulations, GN R 982.

19. The National Environmental Management Waste Act (No. 59 of 2008)

20. The National Water Act (Act No. 36 of 1998).

21. Kendal Power Station Ash Disposal Facility Project: Environmental Impact Assessment

Report.

22. ENV13-R019 Water management policy.

23. 240-4332798, Engineering policy.

24. Manage Technical Risk (240-46953787).

25. Hazard and Operability Analysis (HAZOP) Guideline (240-49230111).

26. Kendal Power Station SHE Statement.

27. Kendal Power Station SHEQ Policy.

28. Kendal Power Station’s Integrated Water and Waste Management Plan.

2.3 DEFINITIONS

2.3.1 Classification

Controlled Disclosure: means controlled disclosure to external parties (either enforce by law, or discretionary).

Page 9: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 9 of 12

2.4 ABBREVIATIONS

Abbreviation Description

ADF Ash Disposal Facility

DEFF Department of Environmental, Forestry and Fisheries

DHSWS Department of Human Settlements, Water and Sanitation

EDWL Engineering Design Work Lead

EIA Environmental Impact Assessment

IEA Integrated Environmental Authorisation

HAZOP Hazard and Operability Study

MW Megawatt

N/A Not Applicable

PEM Project Engineering Manager

SME Subject Matter Expert

WUL Water Use Licence

WULA Water Use Licence Application

2.5 RELATED/SUPPORTING DOCUMENTS

Refer to 2.2 Normative/ Informative References.

3. SCOPE OF WORK

This scope of work aims to provide a high level summary of the scope of work outlining the activities

which are required for a Contractor to set-up a screening plant, screen, transport and stockpile coarse

ash at the Contractor’s lay-down area.

The following is a summary of the scope of work:

Setting up a screening plant which will be installed at the Emergency Dump (E-Dump) inside

the Kendal Power Station to screen to the desired particle size to meet the envelope

requirements prior to the coarse ash being trucked to the Contractor’s lay-down area.

The site works instruction confirms that ash will be a free issue material located at the ash

dump and will need to be transported from the Kendal Emergency Dump (E-Dump).

The ash prior to screening will be in a wet state and will be temporarily stockpiled to dry out at

the Kendal Emergency Dump (E-Dump).

Once the ash is suitably dry, it will be screened to remove all ash particles to meet the envelope

requirements.

Page 10: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 10 of 12

Quality control checks will be performed on each 1000m3 processed coarse ash to ensure

compliance to the envelope requirements.

The supplier to use a SANAS ACCREDITED material testing laboratory only to prove

compliance to the specification in line with South African National Standards (SANS)

The supplier will be required to submit laboratory results of the samples taken as prove of

quality checks.

The total quantity of ash to be transported is 90 000m³ for the contract duration.

The coarse ash must then be trucked from the E-Dump to the Contractor’s lay-down area

where it should be stockpiled for placement on the geomembrane in the Ash Disposal Facility

(ADF) Phase 2 and Phase 3. The distance from the E-Dump to the Contractor’s lay-down area

is approximately 36km, return trip.

The supplier will be required to preserve the screened material until is placed on the liner by

the other contractor.

The above activities must be done in an environmentally friendly manner and comply with

Legislative requirements.

The estimated 3 number of 34ton side tippers will be required for the duration of eight months

with a production of 500m³ per day.

The supplier will be required to supply a loader that will load approved material on trucks for

transportation

The transportation of ash will be from 7:00am to 17:00 from Monday to Saturday and ash

screening will be 24 hours a day Monday to Saturday.

Screening Plant requirements is as follows:

Ash with a maximum diameter of 3mm and a minimum diameter of 0.425mm must be transported to

the stock pile.

The ash available from the Kendal Power Station can range up to a diameter of 11mm or

greater.

The screening plant will be installed at the Kendal Emergency Dump to screen the desired

particle size prior to the ash being trucked to the Contractors lay-down area.

It is expected that the screening plant will only be required during the transportation phase,

estimated to be approximately 8 months.

No additional water will be required during the screening of the ash.

The supplier is supposed to provide a screening plant that will meet this specification.

Page 11: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 11 of 12

The requirement for a Screening Plant is considered incidental to the construction activities

associated with the Continuous ADF to ensure that the correct ash particle size is placed in

order to protect the geomembrane being installed.

The Screening Plant will not trigger any Listed Activities in terms of the National Environmental

Management Act (Act 107 of 1998) Environmental Impact Assessment (EIA) Regulations,

2014, as amended (GN R. 324 – 327).

The Screening Plant will be placed on an area that has already been impacted by the current

operations and hence covered by previous impact assessment(s).

Potential dust generated by the Screening Plant will be negligible compared to the dust already

generated during high wind speeds from the existing Ash Dump and during the placement of

the Ash on the Continuous ADF using the conveyor stacker system, all impacts considered in

the EIA and mitigated by the measures included in the EMPr.

The Screening Plant will only be required during the construction phase, approximately 8

months.

The supplier will implement operational dust abatement measures, i.e. the placement of

windscreens, to mitigate any dust from the screening plant.

Based on the above, neither a Part 1 nor Part 2 EA Amendment is required in terms Sections

29 and 31 of the EIA Regulations, 2014, as amended (GN R. 326).

The supplier will be required to supply an excavator that will be used to load material in the

screening plant

4. DELIVERABLES

Attendance of bi-Weekly and/or ad-hoc meetings with the core team.

Weekly and monthly reports.

All work shall be conducted in accordance with the requirements of the Occupational Health

and Safety Act (Act 85 of 1993) as amended.

Supply Eskom with a Schedule and Estimated Screening, Stockpiling and Placement volumes

to support the schedule. Plant should be indicated on the schedule and a letter stating that the

specific plant will be available for the duration of the project life.

Continuously present the findings to Eskom Engineering for review, challenge,

recommendations and approval.

Ensure that the work is to be done with no impact on the station’s performance.

Provide envisaged program/schedules for the above phase of the scope of work.

Page 12: Scope of Work GCD Scope of Work for Ash 240-165394120 N/A

Scope of Work for Ash screening and transportation for Kendal PS Continuous Ash Disposal Facility Projects

Unique Identifier: 240-165394120

Revision: 01

Page: 12 of 12

Screen, Truck and place the coarse ash in the time frame as indicated in this document.

5. AUTHORISATION

This document has been seen and accepted by:

Name Designation

Saihen Govindasami Auxiliary Engineering –Civil Engineer

Klaas Mahlangu Environmental Officer – Kendal PS

Irene Motswenyane Environmental Officer – Kendal PS

Mokotedi Mokoena GCD – Supervisor

Marike Landman GCD – SHE Manager

Delisiwe Nkosi GCD – Environmental Practitioner

Mbekezeli Ndaba GCD – Environmental Practitioner

Vusi Mlandu GCD – Project Manager

6. REVISIONS

N/A

7. DEVELOPMENT TEAM

The following people were involved in the development of this document:

Mokotedi Mokoena

Saihen Govindasami

8. ACKNOWLEDGEMENTS

N/A