7
August 1, 2018 1 Completed and ongoing tasks: Completed steel erection and metal decking for Bar 2. Courtyard foundation walls completed. Bars 3 and 4 steel erection, detailing and metal decking in progress. Perimeter wall waterproofing and backfilling ongoing. Spray fireproofing work ongoing. Ductwork installation at the B2 level is nearly complete. Storm and sanitary piping has begun at G1 level. Plumbing installation at the B2 level is nearly complete. CMU wall installation has begun at B2 level. Stair #1 installation has begun. Metal stud framing has begun at G1 level. Construction activities next month: Façade wall framing will begin. Curtainwall installation will begin. MEP roughin (ductwork, electrical, plumbing) will continue. Process related activities: Washington gas will continue replacement of the gas main along Wilson Blvd. from N. Pierce St. to N. Quinn St. which will allow Gilbane to construct the DVP electrical vault on Wilson Blvd. Secondary School @Wilson Community Newsletter (July 2018)

Secondary School @Wilson

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  August 1, 2018                    1  

 

 

 

 

 

 

 

 

Completed and ongoing tasks: 

Completed steel erection and metal decking for Bar 2. 

Courtyard foundation walls completed. 

Bars 3 and 4 steel erection, detailing and metal decking in progress. 

Perimeter wall waterproofing and backfilling ongoing. 

Spray fireproofing work ongoing. 

Ductwork installation at the B2 level is nearly complete. 

Storm and sanitary piping has begun at G1 level. 

Plumbing installation at the B2 level is nearly complete. 

CMU wall installation has begun at B2 level. 

Stair #1 installation has begun. 

Metal stud framing has begun at G1 level. 

Construction activities next month:  

Façade wall framing will begin. 

Curtainwall installation will begin. 

MEP rough‐in (ductwork, electrical, plumbing) will continue. 

Process related activities:  

Washington gas will continue replacement of the gas main along Wilson Blvd. from N. Pierce St. to N. Quinn St. which will allow Gilbane to construct the DVP electrical vault on Wilson Blvd. 

Secondary School @Wilson 

Community Newsletter (July 2018) 

  August 1, 2018                    2  

 

 

  Roof drains at Terrace 2 

Construction site overview 

  August 1, 2018                    3  

  

 

 

   

Erection of level 3 cantilevered truss  

Erection of level 3 steel 

  August 1, 2018                    4  

  Stair #1 installed next to elevator shaft

  Concrete rebar and window washing davit bases 

  August 1, 2018                    5  

 Preparation before concrete pour on Level 2

  August 1, 2018                    6  

 

Courtyard #1 

 

Steel framing at auditorium balcony 

  August 1, 2018                    7  

 

Plumbing rough‐in at level G1 ceiling