Upload
lydien
View
214
Download
0
Embed Size (px)
Citation preview
PROJECT COMPUTATION BOOK
FINANCIAL PROJECT NO. 408460-1-52-01
HILLSBOROUGH COUNTY
I-75 (SR 93A)/COUNTY ROAD 581 (BRUCE B. DOWNS) FLYOVER FROM THE HILLSBOROUGH RIVER TO
NORTH OF THE I-75/CR 581 INTERCHANGE NOTICE: THE OFFICIAL RECORD OF THIS SHEET IS THE ELECTRONIC FILE SIGNED AND SEALED UNDER RULE 61G15-23.003, F.A.C. PLAN QUANTITY CONCEPT SIGNATURE THE DESIGN ENGINEER RESPONSIBLE FOR CALCULATIONS: ALL SUPPORT MEASUREMENTS AND COMPUTATIONS HAVE BEEN INCLUDED FOR ALL PLAN QUANTITY ITEMS WITHIN THIS COMPUTATION BOOK.
Revision 1: 8/03/06 RH Revised Sheets: 1-4, 11, 16,17,19, 21, 35-37, 76 Revision 2: 2/09/07 RWJ Revised Pay Items: 102-60,102-71-27,102-74-1,102-74-2,102-76,102-99, 425-2-61,425-2-91,430-171-129,430-171-229,575-1-1
PREPARED BY:
URS Corporation Southern 7650 West Courtney Campbell Causeway Tampa, FL 33607-1462 (813) 286-1711
Added Pay Item 730-76-122 Revision 3: 4/27/07 RWJ Revised Pay Items: 102-60,102-71-11,102-74-1,102-79,102-89-7,102-911-1, 102-911-2,339-1,430-171-140,430-171-147 PREPARED BY: Robb Hideck ENGINEER OF RECORD: Robert W. Joel, P.E. CHECKED BY: Robert W. Joel, P.E. DATE: April 27, 2007 P.E. NO.: 52479
1-75 (SR 93A)/COUNTY ROAD NO 581 (BRUCE B DOWNS) FLYOVERBRIDGE NO. 100712
INDEX
DESCRIPTION PAGE NUMBER
COMPUTATION BOOK PAY ITEM SUMMARY SHEET - BRIDGE 100712 (TOTAL) 1 to 2PLAN AND ELEVATION - BRIDGE 100712 3 to 3C400-2-4 CONCRETE CLASS II (SUPERSTRUCTURE) 4 to 4H400-2-10 CONCRETE CLASS II (APPROACH SLABS) 5 to 5B400-4-5 CONCRETE CLASS IV (SUBSTRUCTURE) 6 to 6AB400-4-25 CONCRETE CLASS IV (MASS-SUBSTRUCTURE) 7 to 400-9 BRIDGE DECK GROOVIG AND PLANING (DECK THICKNESS 8.5" OR 8 to 8A415-1-4 REINFORCED STEEL (SUPESTRUCTURE) 4 to 4H415-1-5 REINFORCED STEEL (SUBSTRUCTURE) 6 to 6AB415-1-9 REINFORCE STEEL (APPROACH SLABS) 5 to 5B455-34-5 PRESTESSED CONCRETE PILING (24" SQ.) 9 to 9B455-133-2 STEEL SHEET PILING (TEMPORARY-CRITICAL) 10 to 10A455-137 TEST LOAD (DYNAMIC) 11 to 11455-143-5 TEST PILES (PRESTRESSED CONCRETE) (24" SQ.) 12 to 12459-71 POLYETHYLENE SHEETING ON CONCRETE PILES 13 to 13A460-2-2 STRUCTURAL STEEL (LOW ALLOY) 14 to 14M460-7-5 EXPANSION JOINT SEAL (MODULAR) 15 to 15A461-113-17 MULTIROTATIONAL BEARING ASSEMBLY-FIXED (1501-1750 KIPS) 16 to 16A461-113-19 MULTIROTATIONAL BEARING ASSEMBLY-FIXED (>=2001 KIPS) 17 to 17461-114-14 MULTIROTATIONAL BEARING ASSEMBLY-EXPANSION (751-1000 KIPS) 18 to 18461-114-19 MULTIROTATIONAL BEARING ASSEMBLY-EXPANSION (>=2001 KIPS) 19 to 19506-2 BRIDGE DRAIN PIPING 20 to 20D506-3 BRIDGE DRAINS 21 to 21521-5-1 CONCRETE TRAFFIC RAILING BARRIER (32" F-SHAPE) 22 to 22A521-5-2 CONCRETE TRAFFIC RAILING BARRIER (42" F-SHAPE) 23 to 23A521-8-1 CONCRETE TRAFFIC RAILING BARRIER (RETAINING WALL SYSTEM MOUNTED
WITH SLEEPER SLAB) (32" F-SHAPE) 24 to 24A524-2-2 SLOPE PAVEMENT CONCRETE (4") 25 to 25A548-12 RETAINING WALL SYSTEM (PERMANENT) (EXCLUDINGBARRIER) 26 to 26D548-13 RETAINING WALL SYSTEM (TEMPORARY) (EXCLUDINGBARRIER) 27 to 27C
1
UNIT MEASURE
S.A. No. PAY ITEM DESCRIPTION
Hum. Bird Doc. No. Or
Page No.Item Paid Amount Line Item Adjusted
Amount
2,775.100 CY 400 2 4 CONC CLASS II, (SUPERSTRUCTURE) 4 $ 611.1500 $ 1,696,002.37110.200 CY 400 2 10 CONCRETE CLASS II, (APPROACH SLABS) 5 $ 331.3900 $ 36,519.1876.100 CY 400 4 5 CONCRETE CLASS IV, (SUBSTRUCTURE) 6 $ 1,610.2800 $ 122,542.31
2,438.000 CY 400 4 25 CONCRETE CLASS IV, MASS, SUBSTRUCTURE 7 $ 450.9200 $ 1,099,342.968,906.000 SY 400 9 BRIDGE DECK GROOVING & PLANING, (DECK 8.5"&>) 8 $ 4.1700 $ 37,138.02
868,716.000 LB 415 1 4 REINFORCING STEEL - (SUPERSTRUCTURE) 4 $ 0.8400 $ 729,721.44457,647.000 LB 415 1 5 REINFORCING STEEL- (SUBSTRUCTURE) 6 $ 0.8400 $ 384,423.48
21 498 000 LB 415 1 9 REINFORCING STEEL- (APPROACH SLABS) 5 $ 0 8400 $ 18 058 32
UNIT PRICETotal Item
Paid Amount
Page No.
FORM 700-050-10CONSTRUCTION
05/08
FINAL QUANTITY ITEM CODE
COMPUTATION BOOK PAY ITEM SUMMARY SHEETSTATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
Date:Contract ID:
Fin Proj. Regular Work Paid:
Fin. Proj. ID: Managing District: FAP No.
2/15/20067102 408460-1-52-01 7
$ 21,433,152.93
21,498.000 LB 415 1 9 REINFORCING STEEL- (APPROACH SLABS) 5 $ 0.8400 $ 18,058.3221,712.000 LF 455 34 5 PRESTRESSED CONCRETE PILING, (24" SQ) 9 $ 103.5200 $ 2,247,626.242,079.000 SF 455 133 2 SHEET PILING STEEL, (TEMPORARY-CRITICAL) 10 $ 7.2500 $ 15,072.75
16.000 EA 455 137 TEST LOAD- (DYNAMIC) 11 $ 2,360.1100 $ 37,761.761,865.000 LF 455 143 5 TEST PILES-(PRESTRESSED CONCRETE) (24" SQ) 12 $ 145.5500 $ 271,450.75
850.000 SY 459 71 PILES, POLYETHYLENE SHEETING 13 $ 4.5000 $ 3,825.001.000 LS 460 2 2 STRUCT STEEL, (LOW ALLOY) 14 $ 12,787,000.0000 $ 12,787,000.00
92.000 LF 460 7 5 EXPANSION JOINT SEAL, (MODULAR) 15 $ 541.0000 $ 49,772.002.000 EA 461 113 17 MULTIROTATIONAL BEARING ASSEM-FIXED, (F&I) (1501-1750 KIPS) 16 $ 15,281.8800 $ 30,563.762.000 EA 461 113 19 MULTIROTATIONAL BEARING ASSEM-FIXED, (F&I) (>= 2001KIPS) 17 $ 17,232.4200 $ 34,464.844.000 EA 461 114 14 MULTIROTATIONAL BEARING ASSEM EXP, (F&I) (751- 1000KIPS) 18 $ 14,546.7500 $ 58,187.008.000 EA 461 114 19 MULTIROTATIONAL BEARING ASSEM-EXP,(F&I) (>=2001KIPS) 19 $ 25,007.5400 $ 200,060.32
272.000 LF 506 2 BRIDGE DRAINAGE PIPE 20 $ 71.8400 $ 19,540.484.000 EA 506 3 BRIDGE DRAINS 21 $ 3,923.5100 $ 15,694.04
120.000 LF 521 5 1 CONCRETE TRAFFIC RAILING, BRIDGE (32" F - SHAPE) 22 $ 85.5800 $ 10,269.603,578.000 LF 521 5 2 CONCRETE TRAFFIC RAILING, BRIDGE (42" F - SHAPE) 23 $ 89.3300 $ 319,622.741,364.000 LF 521 8 1 CONCRETE TRAFFIC RAILING BARRIER, (RET WALL SYS) (32" F) 24 $ 284.6800 $ 388,303.52
28.000 SY 524 2 2 CONCRETE SLOPE PAVEMENT,NON REINFORCED, (4") 25 $ 80.9400 $ 2,266.3225,538.000 SF 548 12 RETAINING WALL SYSTEM, (PERMANENT) EXCLUDING BARRIER 26 $ 27.7300 $ 708,168.747,317.000 SF 548 13 RETAINING WALL SYSTEM,(TEMPORARY) EXCLUDING BARRIER 27 $ 15.0000 $ 109,755.00
PAGE TOTAL $ 21,433,152.93
4,762.34$
FORM 700-050-10CONSTRUCTION
05/08
AMOUNTADJUSTMENT DESCRIPTIONADJUSTMENT DESCRIPTION AMOUNTGASOLINE
COMPUTATION BOOK PAY ITEM SUMMARY AND CERTIFICATION SHEETSTATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
COMPUTATION BOOK PAY ITEM SUMMARY AND CERTIFICATION SHEET
CONTRACT ADJUSTMENTS
DIESEL
BITUMINOUS MATERIAL
DIESEL
BITUMINOUS MATERIALSTEEL ADJUSTMENTSLIQUIDATED SAVINGSLIQUIDATED DAMAGES
ADJUSTMENT DESCRIPTION
CONTRACT ID: FIN PROJ ID:
DATE:
Page No. 2
MANAGING DISTRICT: FAP NO.
2/15/2006
7102 408460-1-52-01 7
INCENTIVES/DISINCENTIVES
4,762.34$
21,437,915.27$
I CERTIFY, BASED ON MY PERSONAL KNOWLEDGE AND WELL-FOUNDED BELIEF, THE QUANTITIESARE ACCURATE AND CONFORM TO THE CONTRACT, PLAN DIMENSIONS, SPECIFICATIONTOLERANCES, MANUALS, AND THAT THIS FINAL ESTIMATE, AS SUBMITTED, IS TRUE AND CORRECT.
the Final Estimates Package, as submitted, in accordance with Chapter 4 of the R & AM.DFEO USE ONLY
COURT ORDERS
NO EXCUSE BONUS
DAMAGE RECOVERY
Johnny Vaseline 7/11/2006
PAR REVIEWS
LANE RENTALARBITRATION ORDERS
TOTAL AMOUNT OF CONTRACT ADJUSTMENTS
TOTAL AMOUNT OF CONTRACT (w/Cont. Adj.)
This block shall be signed by an F.E. Qualified Person(s) responsible for the accuracy of CERTIFICATION STATEMENT:
Title: Signature:And/OrTitle: Signature:
Signed Manor MajorsProject Administrator (Print):
Signed
Resident Engineer (Print):
Willie B. Long
Per R & AM, Chapter 4
Reviewer's Signature Date:
Manor Majors
Willie B. Long
Johnny JohnsOffice Engineer
Project Administrator Manor Majors
Page No.
NO.COMPONENT R
NAME E VOLUME VOLUME OVER/UNDER WEIGHT WEIGHT OVER/UNDERQ {CY) {CY) RUN {LB) {LB) RUN
Bridge 100712
Superstructure 2,775.1 See Page 4A - 4H for 2,775.1 868,716 See Designback-up documents Page 4A-4H
DESIGN ORIGINAL
PAY ITEM DESCRIPTION CONC CLASS II(SUPERSTRUCTURE) PAY ITEM DESCRIPTION REINF STEEL (SUPERSTRUCTURE)
REF. REMARKS.REFERENCE/REMARKS REMARKS.
FORM 700-050-07 CONSTRUCTION
06/02
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
CONCRETE AND REINFORCING STEEL COMPUTATIONS
PAY ITEM NO. 400-2-4415-1-4PAY ITEM NO.
REFERENCE/REMARKS
DESIGN ORIGINALCONSTRUCTION FINAL CONSTRUCTION FINAL
REF.
4
back up documents Page 4A 4H
2,775.1 <PAGE TOTAL> 2,775.1 868,716 <PAGE TOTAL> 868,716<PROJECT GRAND> <PROJECT GRAND>
<TOTAL> <TOTAL>868,716 868,7162,775.1 2,775.1
Construction Option:Place Designer quantity or place check mark if final quantity does not change.
Not Showing all back‐up
data
Signature: Thomas S. Peaske Print Name: Thomas S. Peake
CONCRETE: STEEL:
Plan Quantity Item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Design Engineers Responsible for Calculations: All support measurements and computations have been included for thisPlan Quantity Concept Signature Block
Page No. 5
NO.COMPONENT R
NAME E VOLUME VOLUME OVER/UNDER WEIGHT WEIGHT OVER/UNDERQ {CY) {CY) RUN {LB) {LB) RUN
Bridge 100712
Approach Slab 1 55.1 See Page 5A - 5C 10,749 See DesignPage 5A - 5C
DESIGN ORIGINAL
PAY ITEM DESCRIPTION CONC CLASS II (APPROACH SLABS) PAY ITEM DESCRIPTION REINF STEEL (APPROACH SLABS)
REF. REMARKS.REFERENCE/REMARKS REMARKS.
FORM 700-050-07 CONSTRUCTION
06/02
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
CONCRETE AND REINFORCING STEEL COMPUTATIONS
PAY ITEM NO. 400-2-10415-1-9PAY ITEM NO.
REFERENCE/REMARKS
DESIGN ORIGINALCONSTRUCTION FINAL CONSTRUCTION FINAL
REF.
Page 5A 5CApproach Slab 2 55.1 See Page 5A - 5C 10,749
110.2 <PAGE TOTAL> 110.2 21,498 <PAGE TOTAL> 21,498<PROJECT GRAND> <PROJECT GRAND>
<TOTAL> <TOTAL>21,498 21,498110.2 110.2
Construction Option:Place Designer quantity or place check mark if final quantity does not change.
Not showing all back‐up
Signature: Johnson Duvall Print Name: Johnson Duvall
CONCRETE: STEEL:
Plan Quantity Item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Design Engineers Responsible for Calculations: All support measurements and computations have been included for this
Plan Quantity Concept Signature Block
Page No. 6
NO.COMPONENT R
NAME E VOLUME VOLUME OVER/UNDER WEIGHT WEIGHT OVER/UNDERQ {CY) {CY) RUN {LB) {LB) RUN
Bridge 100712 See Design Calc. See Design Calc.Pages 6A - 6AH Pages 6A - 6AH
EB 1 27.1 12,884Pier 2 0 9 102 241
DESIGN ORIGINAL
PAY ITEM DESCRIPTION CONC CLASS IV (SUBSTRUCTURE) PAY ITEM DESCRIPTION REINF STEEL (SUBSTRUCTURE)
REF. REMARKS.REFERENCE/REMARKS REMARKS.
FORM 700-050-07 CONSTRUCTION
06/02
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
CONCRETE AND REINFORCING STEEL COMPUTATIONS
PAY ITEM NO. 400-4-5415-1-5PAY ITEM NO.
REFERENCE/REMARKS
DESIGN ORIGINALCONSTRUCTION FINAL CONSTRUCTION FINAL
REF.
Pier 2 0.9 102,241Pier 3 0.9 70,400Pier 4 0.9 72,290Pier 5 17.6 59,307Pier 6 0.9 67,986Pier 7 0.7 59,689EB 8 27.1 12,850
76.1 <PAGE TOTAL> 76.1 457,647 <PAGE TOTAL> 457,647<PROJECT GRAND> <PROJECT GRAND>
<TOTAL> <TOTAL>457,647 457,64776.1 76.1
Not showing all back‐up
data
Not showing all back‐up
data
Construction Option:Place Designer quantity or place check mark if final quantity does not change.
Signature: Print Name:
CONCRETE: STEEL:
Plan Quantity Item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Design Engineers Responsible for Calculations: All support measurements and computations have been included for thisPlan Quantity Concept Signature Block
Page No. 7
FORM 700-050-07 STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
CONCRETE AND REINFORCING STEEL COMPUTATIONS CONSTRUCTION 06/02
CONCRETE AND REINFORCING STEEL COMPUTATIONS
PAY ITEM NO. 400-4-25PAY ITEM NO.
NO.COMPONENT R
NAME E VOLUME VOLUME OVER/UNDER WEIGHT WEIGHT OVER/UNDER
PAY ITEM DESCRIPTION CONC CLASS IV (MASS)(SUBSTRUCTURE) PAY ITEM DESCRIPTION
DESIGN ORIGINALCONSTRUCTION FINAL CONSTRUCTION FINAL
REF REMARKSREFERENCE/REMARKS REMARKSREFERENCE/REMARKS REF
DESIGN ORIGINAL
Q {CY) {CY) RUN {LB) {LB) RUN
EB 1 64.8Pier 2 590.4Pier 3 377 3
REF. REMARKS.REFERENCE/REMARKS REMARKS.REFERENCE/REMARKS REF.
Pier 3 377.3Pier 4 385.6Pier 5 258.9Pier 6 339.8Pier 7 356.4Pier 7 356.4EB 8 64.8
Construction Option:Place Designer quantity or place check mark if final quantity does not change
2,438.0 <PAGE TOTAL> 2,438.0 <PAGE TOTAL><PROJECT GRAND> <PROJECT GRAND>
<TOTAL> <TOTAL>2 438 0 2,438.0
quantity does not change.
<TOTAL> <TOTAL>
Signature: Robert T. Gaskins Print Name: Robert T. GaskinsPlan Quantity Item
2,438.0
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Design Engineers Responsible for Calculations: All support measurements and computations have been included for this
2,438.0
Plan Quantity Concept Signature Block
STEEL:
Plan Quantity Item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
CONCRETE:
Page No. 8
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION AREA COMPUTATIONS PAY ITEM NO. 400-9
PAY ITEM DESCRIPTION BRIDGE DECK GROOVING AND PLANING (DECK THICKNESS 8.5” OR GREATER)
STATION TO STATION
TRAV.OR
PAGE NO.
S I
D E
DESIGN ORIGINAL CONSTRUCTION FINAL
WIDTH
LENGTH
CURVE CORR.(+/-)
AREA ( S.Y. )
REMARKS
WIDTH
LENGTH
AREA ( S.Y. )
REMARKS
BRIDGE 100712 8,906 See Bridge Plan
8,906
See designer page 8-A
Sheet # B - 6
No changes
Note # 3
8,906 = PAGE TOTAL < 8,906
8,906 = PROJECT GRAND TOTAL <
8,906 If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block Design/Engineers Responsible for Calculations: All support measurements and computations have been included for this Plan Quantity item.
Signature: Print Name:
NOTES FOR EXPLANATION OF OVER/UNDER RUN:
RECYCLED PAPER
FORM 700-050-01 CADD FORM 1
CONSTRUCTION 11/98
UR
S C
orpo
ratio
n
Proj
ect:
BB
D F
lyov
er
Des
igne
d B
y: T
SP
C
heck
ed B
y: M
H
Proj
ect N
umbe
r: 1
2002
951.
0000
5
Dat
e: 0
5- S
ep-0
5
Dat
e: 9
/7/0
5
D
escr
iptio
n: B
ridge
Dec
k G
roov
ing
Le
ngth
A
1742
.4 ft
Wid
th B
49
.500
ft
B
arrie
r 1 W
idth
C
1.75
0 ft
B
arrie
r 2 W
idth
D
1.75
0 ft
A
rea
A*(
B-C
-D)
8015
0 ft^
2
=
8,9
06 y
d2
T
SP
9/1
9/05
Page No._________
FORM 700-050-08STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
PILING TABULATION
9
PAY ITEM NO. 0455 34 5
PAY ITEM DESCRIPTION PRESTRESSED CONCRETE PILING 24" SQ
FORM 700-050-08CONSTRUCTION
11/07
PILING TABULATION
STRUCTURE IDENTIFICATION: Bridge 100712
PAY ITEM DESCRIPTION
NO. LENGTH TOTAL OVER OR UNDER RUNREQ'D EACH LENGTH AUTHORIZED INSTALLED FROM DESIGN ORIGINAL
PRESTRESSED CONCRETE PILING, 24" SQ
DESIGN ORIGINAL QUANTITY CONSTRUCTION FINAL QUANTITY
REFERENCE/REMARKSSTRUCTURE COMPONENT IDENTIFICATION REFERENCE/REMARKS
LINEAR* LINEAR* LINEAR* LINEAR* LINEAR*(LF) (LF) (LF) (LF) (LF)
EB 1 12 138 00 1 656 0 138 00 1 721 00 65 00See Designer Calculations
REFERENCE/REMARKSIDENTIFICATIONEA
REFERENCE/REMARKS
EB 1 12 138.00 1,656.0 138.00 1,721.00 65.00Pier 2 43 93.00 3,999.0 85.00 4,010.00 11.00 See Pile Driving FieldPier 3 26 100.00 2,600.0 100.00 2,656.00 56.00 Book # 20001 Page 78Pier 4 26 100.00 2,600.0 85.00 2,586.00 -14.00 for final tabulationPier 5 30 125.00 3,750.0 125.00 3,775.00 25.00
See Designer CalculationsPage 9-A & 9-B
Pier 5 30 125.00 3,750.0 125.00 3,775.00 25.00Pier 6 26 100.00 2,600.0 85.00 2,597.00 -3.00Pier 7 28 95.00 2,660.0 95.00 2,678.00 18.00EB 8 12 136.00 1,632.0 136.00 1,689.00 57.00
Field Book For Reference Only
21 497 21 712< PAGE TOTAL >*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS SHOWN 21,497 21,71221,497 21,712
< PAGE TOTAL >< PROJECT GRAND TOTAL >
EXPLANATION OF OVER/UNDER RUN (DESIGN ORIGINAL/FINAL PAY LENGTH)
*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS SHOWN
IN CONTRACT (i.e. LF, M1).
PILING AUTHORIZED:Overrun of 215 LF is due to the differnce between estimated lengths versus the required depth piles were driven to obtain specific bearing. This includes Pile
PILING INSTALLED:
Cut-Off's and splices.
Underrun of 38 LF is due to the difference between estimated lengthsversus the actual approved authorized lengths.
EXTRA NOTES / REMARKS:
Page No.________
PAY ITEM NO. 0455133 2
TRAV. SOR I
PAGE D CURVE AREA AREANO. E CORR(+/-) (SF) (SF)
Bridge 100712
TW-1 42.00 55.18 2,318 42.00 49.50 2,079 See F.B. # 3 - Page 20
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
AREA COMPUTATIONS FORM 700-050-01CONSTRUCTION
09/07
DESIGN ORIGINAL
PAY ITEM DESCRIPTION
WIDTHWIDTH LENGTH LENGTH
CONSTRUCTION FINAL
SHEET PILING STEEL, TEMPORARY-CRITICAL
REMARKS REMARKSSTATION TO STATION
10
For Reference Only
Final quantity change due
to utility conflict
See Page - 10A
2,318 2,079
2 318 < PROJECT GRAND TOTAL >< PAGE TOTAL >
2,318 2,079
Signature: Print Name:
EXTRA NOTES / REMARKS:
< PROJECT GRAND TOTAL >If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
NOTES FOR EXPLANATION OF OVER/UNDER RUN: This quantity underran 239 SF due to a utility conflict which required a field change.
Design Engineers Responsible for Calculations: All support measurements and computations have been included for this Plan Quantity item.
Plan Quantity Concept Signature Block
This quantity changed due toconflict with utility.Length = 49' 5"
Page 10 A
Page No._________
OVER/UNDERRUN
Bridge 100712
End Bent 1 1 EA 2 EA 1.0 See Pile Driving Book Pier 2 2 EA 2 EA # 2001, Page No. 27Pi 3 2 EA A f fi l
PAY ITEM DESCRIPTION
SIDELOCATION LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL CONSTRUCTION FINAL
REMARKS
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 455-137
FORM 700-050-03 CONSTRUCTION
06/02
TEST LOAD(DYNAMIC)
REFERENCES/REMARKS
11
Pier 3 2 EA 2 EA for final.Pier 4 2 EA 2 EAPier 5 2 EA 2 EAPier 6 2 EA 3 EA 1.0 See Pile Driving Book Pier 7 2 EA 2 EA # 2001, Page No. 27End Bent 8 1 EA 1 EA for final.
14 EA 16 EA14 EA 16 EASHOWN IN CONTRACT (I e LF M1 LB KG )
*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS
< PROJECT GRAND TOTAL >< PAGE TOTAL >
Field BookFor Reference only
14 EA 16 EA
Signature: Print Name:
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Design Engineers Responsible for Calculations: All support measurements and computations have been
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN Overrun due to requiring additional data for dynamic testing.
< PROJECT GRAND TOTAL >
Page No._________
FORM 700-050-08STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
PILING TABULATION
12
PAY ITEM NO. 0455143 5
PAY ITEM DESCRIPTION
FORM 700-050-08CONSTRUCTION
11/07
PILING TABULATION
STRUCTURE IDENTIFICATION: Bridge 100712
TEST PILES PRESTRESSED CONCRETE 24" SQPAY ITEM DESCRIPTION
NO. LENGTH TOTAL OVER OR UNDER RUNREQ'D EACH LENGTH AUTHORIZED INSTALLED FROM DESIGN ORIGINAL
REFERENCE/REMARKS REFERENCE/REMARKS
TEST PILES-PRESTRESSED CONCRETE,24" SQ
DESIGN ORIGINAL QUANTITY CONSTRUCTION FINAL QUANTITY
STRUCTURE COMPONENT LINEAR* LINEAR* LINEAR* LINEAR* LINEAR*
(LF) (LF) (LF) (LF) (LF)
EB 1 1 153 153 160.0 171.00Pier 2 2 108 216 110 0 219 00 See Pile Driving Field
REFERENCE/REMARKS
See Designer Calculations
REFERENCE/REMARKSIDENTIFICATIONEA
Pages 9 A & 9 BPier 2 2 108 216 110.0 219.00 See Pile Driving FieldPier 3 2 115 230 115.0 258.00 Book # 20001 Page 78Pier 4 2 115 230 115.0 262.00 for final tabulationPier 5 2 140 280 140.0 270.00Pier 6 2 115 230 115 0 268 00
Pages 9-A & 9-B
Pier 6 2 115 230 115.0 268.00Pier 7 2 110 220 110.0 242.00EB 8 1 151 151 160.0 175.00
Field Book For Reference Only
1 710 1 865< PAGE TOTAL >*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS SHOWN 1,710 1,8651,710 1,865
< PAGE TOTAL >< PROJECT GRAND TOTAL >
*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS SHOWN
IN CONTRACT (i.e. LF, M1).
EXPLANATION OF OVER/UNDER RUN (DESIGN ORIGINAL/FINAL PAY LENGTH)
PILING AUTHORIZED:to minimum tip elevation and proper bearing was achieved.
PILING INSTALLED: The Overrun of 155 LF is due to test piling driven
EXTRA NOTES / REMARKS:
Page No.__________
PAY ITEM NO. 0459 71
TRAV. SOR I
PAGE D CURVE AREA AREANO. E CORR(+/-) (SY) (SY)
EB 1 9-A 569 See Designer Calculations 569 See Field Book # 20002EB 2 9-A 281 Page 13-A 281 for final measured qty.
FORM 700-050-01CONSTRUCTION
09/07
DESIGN ORIGINAL CONSTRUCTION FINAL
PILES, POLYETHYLENE SHEETING
WIDTHWIDTH LENGTH LENGTH
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
AREA COMPUTATIONS
STATION TO STATION
PAY ITEM DESCRIPTION
REMARKS REMARKS
13
850 850850 850< PROJECT GRAND TOTAL >
< PAGE TOTAL >
Field BookFor Reference Only
850 850
Signature: Print Name:
EXTRA NOTES / REMARKS:
< PROJECT GRAND TOTAL >
Design Engineers Responsible for Calculations: All support measurements and computations have been included for this Plan Quantity item.
Plan Quantity Concept Signature Block
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
NOTES FOR EXPLANATION OF OVER/UNDER RUN:
Page No._________
PAY ITEM NO.
1 LUMP SUMPAY ITEM DESCRIPTION
VOLUME WEIGHT ITEMS LINEAR ITEMSAREA ITEMS
PAY ITEM DESCRIPTION
SECONDARY UNIT COMPUTATIONS
DESIGNER QUANTITY (WITH SECONDARY UNITS, SEE BELOW)CONSTRUCTION FINAL QUANTITY
CONSTRUCTION FINAL
EA ITEMS
DESIGN ORIGINAL
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LUMP SUM QUANTITIES
DESIGNER QUANTITY (NO SECONDARY UNIT)CONSTRUCTION FINAL QUANTITY 1 Lump Sum
460-2-2
STRUCT STEEL (LOW ALLOY)
FORM 700-050-05 CONSTRUCTION
06/02
14
MISCELLANEOUS INCREASES ORVOLUME WEIGHT ITEMS* DECREASES
MEASURE MEASURE
Bridge 100712 6,426,932 See Designer NO CHANGES
CalculationsPages 14-Athru 14-M
STATION LOCATION
AREA
VOLUME WEIGHT ITEMS LINEAR ITEMSAREA ITEMS
LENGTHREFERENCES
EACHMEASURE
EA. ITEMS
WIDTHREFERENCES
LINEAR
Not showing all back up
data
NOTES FOR EXPLANATION OF OVER/UNDER RUN
Page No.____ ____
OVER/UNDERRUN
Bridge 100712
End Bent 1 46 LF See Designer Calculations No ChangePage 15-A
PAY ITEM DESCRIPTION
SIDELOCATION LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL CONSTRUCTION FINAL
REMARKS
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 460-7-5
FORM 700-050-03 CONSTRUCTION
06/02
EXPANSION JOINT SEAL (MODULAR)
REFERENCES/REMARKS
15
Page 15 AEnd Bent 8 46 LF
92 LF 92 LF*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS < PAGE TOTAL >
Construction Option: Place Designer
quantity or place checkmark if final quantity does not change.
92 LF 92 LF
Signature: Print Name:
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Design Engineers Responsible for Calculations: All support measurements and computations have been
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
< PROJECT GRAND TOTAL >
Page No._______
OVER/UNDERRUN
Bridge 100712
Pier 4 2 EA See Designer Calculations No ChangePage 16-A See page 16A
FORM 700-050-03CONSTRUCTION
09/07
MULTIROTATIONAL BEARING ASSEM-FIXED, F&I, 1501-1750 KIPS
REFERENCES/REMARKS
CONSTRUCTION FINAL
REMARKS
PAY ITEM DESCRIPTION
SIDELOCATION
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 0461113 17
LENGTH*, COMPONENT WEIGHT*, OR
DESIGN ORIGINAL
NUMBER PER HOUR, DAY, EACHLENGTH*, COMPONENT WEIGHT*, OR
NUMBER PER HOUR, DAY, EACH
16
2 EA 2 EA2 EA A
< PAGE TOTAL >*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS
2 EA 2 EA
Signature: Print Name: included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN:
< PROJECT GRAND TOTAL >
Design Engineers Responsible for Calculations: All support measurements and computations have been
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
EXTRA NOTES / REMARKS:
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Page No._________
OVER/UNDERRUN
Bridge 100712No Changes
Pier 5 2 EA See Designer Calculations See Page 16APage 16-A
MULTIROTATIONAL BEARING ASSEM-FIX(F&I)( >=2001 KIPS)
REFERENCES/REMARKS
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 461-113-19
FORM 700-050-03 CONSTRUCTION
06/02
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL CONSTRUCTION FINAL
REMARKS
PAY ITEM DESCRIPTION
SIDELOCATION LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
17
2 EA 2 EA2 EA 2 EA
< PAGE TOTAL >*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS
2 EA 2 EA
Signature: Print Name:
< PROJECT GRAND TOTAL >
included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
Design Engineers Responsible for Calculations: All support measurements and computations have been
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Page No.________
OVER/UNDERRUN
Bridge 100712No Changes
End Bent 1 2 EA See Designer Calculations See Page 16AEnd Bent 8 2 EA Page 16-A
PAY ITEM DESCRIPTION
SIDELOCATION LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL CONSTRUCTION FINAL
REMARKS
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 461-114-14
FORM 700-050-03 CONSTRUCTION
06/02
MULTIROTATIONAL BEARING ASSEM EXP(F&I)( 751-1000 KIPS)
REFERENCES/REMARKS
18
4 EA 4 EA4 EA 4 EASHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS
< PROJECT GRAND TOTAL >< PAGE TOTAL >
4 EA 4 EA
Signature: Print Name:
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Design Engineers Responsible for Calculations: All support measurements and computations have been
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
< PROJECT GRAND TOTAL >
Page No.____________
OVER/UNDERRUN
Bridge 100712No Changes
Pier 2 2 EA See Page 16APier 3 2 EA
FORM 700-050-03 CONSTRUCTION
06/02
MULTIROTATIONAL BEARING ASSEM EXP(F&I)( >=2001 KIPS)
REFERENCES/REMARKS
CONSTRUCTION FINAL
REMARKS
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 461-114-19
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL
PAY ITEM DESCRIPTION
SIDELOCATION
19
Pier 6 2 EAPier 7 2 EA
8 EA 8 EA< PAGE TOTAL >*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS
8 EA 8 EA
Signature: Print Name: included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
< PROJECT GRAND TOTAL >
Design Engineers Responsible for Calculations: All support measurements and computations have been
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Page No.____________
OVER/UNDERRUN
Bridge 100712
EB 1 74 LF See Designer Calculations 74 LF Pier 2,7 AdditionalPier 2 62 LF Pages 20-A & 20-D 70 LF 8.0 pipe added forPier 6 70 LF 70 LF Field Change
BRIDGE DRAINAGE PIPING
REFERENCES/REMARKS
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 506-2
FORM 700-050-03 CONSTRUCTION
06/02
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL CONSTRUCTION FINAL
REMARKS
PAY ITEM DESCRIPTION
SIDELOCATION LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
20
Pier 6 70 LF 70 LF Field ChangePier 7 51 LF 58 LF 7.0
See Field Book # 2001page # 67 formeasured quantities
257 LF 272 LF257 LF 272 LF< PROJECT GRAND TOTAL >
< PAGE TOTAL >*PROVIDE APPROPRIATE UNITS FOR THIS ITEM ASSHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Not showing all back‐up data
Field BookFor Reference Only
257 LF 272 LF
Signature: Gabriel Braesch Print Name: Garbriel Braesch
< PROJECT GRAND TOTAL >
included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
Design Engineers Responsible for Calculations: All support measurements and computations have been
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Page No.____________
OVER/UNDERRUN
Bridge 100712
EB 1 1 EA See Field Book No. 7Pier 2 1 EA Page 77Pier 6 1 EA
BRIDGE DRAINS
REFERENCES/REMARKS
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 506-3
FORM 700-050-03 CONSTRUCTION
06/02
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL CONSTRUCTION FINAL
REMARKS
PAY ITEM DESCRIPTION
SIDELOCATION LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
21
Pier 6 1 EAEB 8 1 EA
4 EA 4 EA4 EA 4 EA< PROJECT GRAND TOTAL >
< PAGE TOTAL >*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Field BookFor Reference Only
4 EA 4 EA
Signature: Gabriel Braesch Print Name: Gabriel Braesch
< PROJECT GRAND TOTAL >
included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
Design Engineers Responsible for Calculations: All support measurements and computations have been
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Page No.____________
OVER/UNDERRUN
Bridge 100712
Approach Slab 1 60 LF See Designer calculations 60 LFon page 22A
Approach Slab 2 60 LF 60 LF See Field Book No 12
CONSTRUCTION FINAL
REMARKS
PAY ITEM DESCRIPTION
SIDELOCATION LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
FORM 700-050-03 CONSTRUCTION
06/02
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL
CONCRETE TRAFFIC RAILING BARRIER BRIDGE (32" F)
REFERENCES/REMARKS
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 521-5-1
22
Field BookFor Reference Only
Approach Slab 2 60 LF 60 LF See Field Book No. 12Page 22
No Changes
120 LF 120 LF120 LF 120 LFSHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS
< PROJECT GRAND TOTAL >< PAGE TOTAL >
120 LF 120 LF
Signature: Thomas S. Peake Print Name: Thomas S. Peake
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN Additional traffic railing barrier overrun of 35 LF due to requiring the match of existing field conditions.
Design Engineers Responsible for Calculations: All support measurements and computations have been
< PROJECT GRAND TOTAL >
Page No.____________
OVER/UNDERRUN
Authorized change3,485 LF See Designer calculations 3,578 LF 93.0 This qty changed
Page 23A due to matchingexisting field c diti s See F B
FORM 700-050-03 CONSTRUCTION
06/02
CONCRETE TRAFFIC RAILING BARRIER BRIDGE (42" F)
REFERENCES/REMARKS
CONSTRUCTION FINAL
REMARKS
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 521-5-2
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL
PAY ITEM DESCRIPTION
SIDELOCATION
Bridge 100712
23
Field Bookconditions. See F.B.# 20003 Page 38
Plan Qty = 3,485Authorized + 93Final Qty = 3,578
3,485 LF 3,578 LF3 485 LF 3 578 LF< PROJECT GRAND TOTAL >
< PAGE TOTAL >*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS
SHOWN IN CONTRACT (I e LF M1 LB KG )
For Reference Only
3,485 LF 3,578 LF
Signature: Thomas S. Peake Print Name: Thomas S. Peake included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN The traffic railing barrier was increased by 93 LF due to matching existing field conditions.
< PROJECT GRAND TOTAL >
Design Engineers Responsible for Calculations: All support measurements and computations have been
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
Plan Quantity Concept Signature Block
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Page No.____________
OVER/UNDERRUN
Bridge 100712
W -1 260 LF See Designer Calculations No ChangesPage 24A
W - 2 1 104 LF
PAY ITEM DESCRIPTION
SIDELOCATIONCONSTRUCTION FINAL
REMARKSLENGTH*, COMPONENT WEIGHT*, OR
NUMBER PER HOUR, DAY, EACH
DESIGN ORIGINAL
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
LINEAR MEASUREMENT, COMPONENT WEIGHT, PER HOUR, PER DAY OR PER EACH COMPUTATIONS
REFERENCE
PAY ITEM NO. 0521 8 1
LENGTH*, COMPONENT WEIGHT*, ORNUMBER PER HOUR, DAY, EACH
FORM 700-050-03CONSTRUCTION
09/07
CONCRETE TRAFFIC RAILING BARRIER, RETAINING WALL SYSTEM
REFERENCES/REMARKS
24
W - 2 1,104 LF
1,364 LF 1,364 LF1,364 LF 1,364 LF< PROJECT GRAND TOTAL >
< PAGE TOTAL >*PROVIDE APPROPRIATE UNITS FOR THIS ITEM AS
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,) 1,364 LF 1,364 LF
Signature: Murray McDonough Print Name: Murray McDonough
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
EXTRA NOTES / REMARKS:
included for this Plan Quantity item.
NOTES FOR EXPLANATION OF OVER/UNDER RUN:
< PROJECT GRAND TOTAL >
Design Engineers Responsible for Calculations: All support measurements and computations have been
Plan Quantity Concept Signature Block
SHOWN IN CONTRACT (I.e. LF, M1, LB, KG,)
Page No.____________
PAY ITEM NO. 0524 2 2
TRAV. SOR I
PAGE D CURVE AREA AREANO. E CORR(+/-) (SY) (SY)
End Bent 1 14.0 See Designer Calculations No ChangesEnd Bent 2 14.0 Page 25A
FORM 700-050-01CONSTRUCTION
09/07
DESIGN ORIGINAL CONSTRUCTION FINAL
CONCRETE SLOPE PAVEMENT,NON REINFORCED, 4"
WIDTHWIDTH LENGTH LENGTH
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
AREA COMPUTATIONS
STATION TO STATION
PAY ITEM DESCRIPTION
REMARKS REMARKS
25
28 2828 28< PROJECT GRAND TOTAL >
< PAGE TOTAL >28 28
Signature: Gabriel Braesch Print Name: Gabriel Braesch
EXTRA NOTES / REMARKS:
< PROJECT GRAND TOTAL >
Design Engineers Responsible for Calculations: All support measurements and computations have been included for this Plan Quantity item.
Plan Quantity Concept Signature Block
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
NOTES FOR EXPLANATION OF OVER/UNDER RUN:
Page No.____________
PAY ITEM NO. 548-12
TRAV. SOR I
PAGE D CURVE AREA AREANO. E CORR(+/-) (SF) (SF)
Bridge 100712
W-1 9,494 See Designer Calculations No ChangesPages 26-A thru 26-D Pay Plan Quantity
W 2 16 044
FORM 700-050-01 CONSTRUCTION
06/02
DESIGN ORIGINAL CONSTRUCTION FINAL
RETAINING WALL SYSTEM(PERMANENT)(EXCLUDING BARRIER)
WIDTHWIDTH LENGTH LENGTH
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
AREA COMPUTATIONS
STATION TO STATION
PAY ITEM DESCRIPTION
REMARKS REMARKS
26
W-2 16,044
25,538 25,53825,538 25,538< PROJECT GRAND TOTAL >
< PAGE TOTAL >25,538 25,538
Signature: Murray McDonough Print Name: Murray McDonough
< PROJECT GRAND TOTAL >
Design Engineers Responsible for Calculations: All support measurements and computations have been included for this Plan Quantity item.
Plan Quantity Concept Signature Block
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
NOTES FOR EXPLANATION OF OVER/UNDER RUN
Page No.____________
PAY ITEM NO. 0548 13
TRAV. SOR I
PAGE D CURVE AREA AREANO. E CORR(+/-) (SF) (SF)
TW - 1 7,317 See Designer Calculations No ChangePages 27-A thru 27-C
FORM 700-050-01CONSTRUCTION
09/07
DESIGN ORIGINAL CONSTRUCTION FINAL
RETAINING WALL SYSTEM,TEMPORARY, EXCLUDING BARRIER
WIDTHWIDTH LENGTH LENGTH
STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
AREA COMPUTATIONS
STATION TO STATION
PAY ITEM DESCRIPTION
REMARKS REMARKS
27
7,317 7,3177 317 7 317< PROJECT GRAND TOTAL >
< PAGE TOTAL >7,317 7,317
Signature: Thomas S. Peake Print Name: Thomas S. Peake
7317
EXTRA NOTES / REMARKS:
< PROJECT GRAND TOTAL >
Design Engineers Responsible for Calculations: All support measurements and computations have been
included for this Plan Quantity item.
Plan Quantity Concept Signature Block
If the above item is under the Plan Quantity Concept, then the block below must be appropriately filled out.
NOTES FOR EXPLANATION OF OVER/UNDER RUN: