Upload
harold-taylor
View
220
Download
0
Embed Size (px)
Citation preview
7/30/2019 Senior Coop Training
1/57
Academic Advisor of Training
Ass.Prof.Dr.Yousef Kebbieh
ENGINEERING COLLAGE
CIVIL DEPARTMENT
Harbi-Fawaz Ali AL
Senior Coop Training
By
7/30/2019 Senior Coop Training
2/57
1 - INTRODUCTION.
3 - SURVEYING. 4LABORATORY.
5BRIDGES. 6 - FIELD PROBLEMS.
7 - Subject Use in Training.
9Conclusions
2-TRAINING SCEHDULE
8 - Gained Experience.
CONTENTS
7/30/2019 Senior Coop Training
3/57
BACK
in applying the idea ofEngineering CollegeThe vision of thecooperative training is to train students and achieve the goals of training
outcomes.
The interest of the college is to meet the needs of the job market for
engineers preparing for college students the opportunity to train in the
best engineering sectors in the Kingdom.
disciplinary-, one of Saudi oldest and largest multiSAUDCONSULT
engineering, founded in 1965(1384H) by Chairman of the board,
Dr.Tarek M.A. Shawaf . It is 100% Saudi privately owned byEngineering Consultancy firm . SAUDCONSULT now comprises a
work force of more than(2000)Engineers ,Architects ,Consultants
,Designers (CADD), Technicians , and Support Staff .
1 - INTRODUCTION.
7/30/2019 Senior Coop Training
4/57
Training Schedule-2
7/30/2019 Senior Coop Training
5/57
Back
7/30/2019 Senior Coop Training
6/57
SURVEYING-3
7/30/2019 Senior Coop Training
7/57
SURVEYING-3
Fieldworks :
3.1 - ESTABLISH CONTROL POINTS / BENCHMARKS:
2.1.1) Reference points (B.M.) for elevation should be at most 200
meters apart to have a good precision.
2.1.2) References points (C.P.) for coordinates should be at 1000
meters(1km) for good precision.
7/30/2019 Senior Coop Training
8/57
3.2 - Establish CENTERLINES / OFFSETS / LEVELS :
3.2.1 ROAD ALIGNMENT:
-This is normally staked at (25m) intervals.
-This alignment becomes the reference for the offsets for
natural ground level (NGL).
7/30/2019 Senior Coop Training
9/57
3.3- CENTERLINE /CORNERS FOR STRUCTURES:
3.3.1 Electrical Poles:
-Centerline (x) levels for foundation is established.
-Depth of excavation.
-Alignment & levels of anchor bolts.
7/30/2019 Senior Coop Training
10/57
7/30/2019 Senior Coop Training
11/57
2.3.2 Crosshead / bearings : (Check Centerlines (x) Levels)
7/30/2019 Senior Coop Training
12/57
3.3.3 Girders:
-check intervals (x) positioning of duct pipes for prestressed reinforcements.
7/30/2019 Senior Coop Training
13/57
3.3.4 Deck slab:
-check levels & slopes.
7/30/2019 Senior Coop Training
14/57
3.3.5 Curb Stones:
-check foundation excavation.
-alignment & levels. ( 25 cm high from the surface of road ) .
7/30/2019 Senior Coop Training
15/57
3.4 - CONTROL THE LAYERS FOR ROAD WORKS (LEVELS):
3.4.1 Embankment .
-50 cm ( max.) for sand per layer .
-30 cm (max.) for earth embankment per layer.
-60 cm for rock embankment per layer.
7/30/2019 Senior Coop Training
16/57
3.4.2 Subgrade :
- 2 layers @ 15 cm (for 30 cm SG).
- 1 layers @ 20 cm (for 20 cm SG).
3.4.3 Aggregate Base Course (ABC): 20 cm layer.
3.4.4 Bituminous Base Course (BBC): 10 cm layer (by string line).
3.4.5 Bituminous Wearing Course (BWC): 5 cm layer (by string line).
BACK
7/30/2019 Senior Coop Training
17/57
LABORATORY-4
7/30/2019 Senior Coop Training
18/57
4.1 - Density of Soil InPlace by the Sand Cone Method :
of soils .place densityThis method of test is intended for determining the in
7/30/2019 Senior Coop Training
19/57
7/30/2019 Senior Coop Training
20/57
The liquid limit of the soil is the water content ,expressed as a
percentage, at which a soilwater mixture passes from plastic to aliquid state .these test are used in classifying soils.
4.2 - Determining liquid limit of soils :
7/30/2019 Senior Coop Training
21/57
E
7/30/2019 Senior Coop Training
22/57
4.3 - Making and Curing Concrete Compressive Test Specimen in the Field :
This method covers procedure for making and curing compressive test specimens
of concrete .
7/30/2019 Senior Coop Training
23/57
7/30/2019 Senior Coop Training
24/57
4.4 - Plastic Fines in Graded Aggregate and Soils by Use of the Sand
Equivalent Test :
This test is a rapid field test to indicate the presence or absence of detrimental
fine dust or clay-like materials in soils or aggregates.
7/30/2019 Senior Coop Training
25/57
7/30/2019 Senior Coop Training
26/57
4.5 - Slump of Portland Cement Concrete :
This method of test includes the procedure to be used for determining
slump of concrete , both in the laboratory and in the field .
BACK
7/30/2019 Senior Coop Training
27/57
BRIDGES-5
7/30/2019 Senior Coop Training
28/57
The girder bridge consist of tow parts:
substructure:-1
Is begin from footing to the crosshead (withconcrete strength 280 kg/cm square).
super structure:-2
Is begin from the crosshead to the top slab
(with concrete strength 360 kg/cm square)..
3.1 Girder Bridge:
7/30/2019 Senior Coop Training
29/57
5.1.1Columns :
3.1.1.1 There are many section of columns famous of them circular and
rectangular.
3.1.1.2 If columns are intermediate called "bearing" and if are ends called
"apputment".
7/30/2019 Senior Coop Training
30/57
5.1.2 Cross head / bleanth:
3.1.2.1 called the cap of the column and it use to carried the girders.
3.1.2.2 check the reinforcement, level and slope(1.5%)and center line of crossheadand blenth.
7/30/2019 Senior Coop Training
31/57
5.1.2.3 Placement of concrete for crosshead and mortar of blenth.
5.1.2.4 Check the concrete and mortar according to the specification
of ministry .
7/30/2019 Senior Coop Training
32/57
5.1.2.5 Check the level and area of bearing.
7/30/2019 Senior Coop Training
33/57
5.1.3 Girders :
5.1.3.1 There are tow types of girder normal stress and pre-stressed (post-tension ,
pre-tension) that we used in our project .the benefit of pre-stressed girder
.reduce the depth and reinforcement of beam and economicare
5.1.3.2 post-tension: is used in our project and it is the commonly used were the
tensioncable put in metal ducts. After hardened of concrete tension the
cable to the required strength by using special equipment and then injection
the grout into the pipes to fill the voided in the ducts.
5.1.3.3 check the reinforcement of girder and put in the ducts.
7/30/2019 Senior Coop Training
34/57
5.1.3.4 After hardened concrete put the cable in the metal ducts.
7/30/2019 Senior Coop Training
35/57
5.1.3.5 Installation of girder on the crosshead.
7/30/2019 Senior Coop Training
36/57
5.1.4.1 Diphram are construct in different way of girder to joint
between girder and prevent sliding of girder when exposure to
external load .
5.1.4.2 The upper slab is a concrete reinforcement slab put up the
girder and it is thickness about 20 cm .
5.1.4Diphram /deck slab :
7/30/2019 Senior Coop Training
37/57
5.1.4.3 Check the reinforcement of diphram , deck slab and overlap between them.
7/30/2019 Senior Coop Training
38/57
5.1.4.5 Check the concrete.
7/30/2019 Senior Coop Training
39/57
5.1.4.4 Placement concrete.
7/30/2019 Senior Coop Training
40/57
5.1.4.6 Isolate the concrete slab.
7/30/2019 Senior Coop Training
41/57
5.1.5Parapets :
5.1.5.1 Check the reinforcement parapets and placement.
7/30/2019 Senior Coop Training
42/57
5.1.5.2 Installation the parapets.
5 1 6 J i
7/30/2019 Senior Coop Training
43/57
5.1.6Joints :
5.1.6.1 joint use in bridge to prevent broken of a approach slab from Thermal
expansion and Contraction .
5.1.6.2 Cutting a layer of asphalt, a distance of 25 cm from the left and right.
7/30/2019 Senior Coop Training
44/57
5.1.6.3 Mixing special mix of industrial materials and called wabo to a height of 5
cm ,and placement the mix and test.
5 1 6 4 Install nails :
7/30/2019 Senior Coop Training
45/57
5.1.6.4 Install nails :
7/30/2019 Senior Coop Training
46/57
5.1.6.5 JDC installation of bridges:
BACK
7/30/2019 Senior Coop Training
47/57
FIELD PROBLEMS-6
7/30/2019 Senior Coop Training
48/57
SAND CONE TEST:1
Has been tested a sample of sub aggregate at the site using the sand cone method to
make sure you moisture density of soil verify ministry's standards, or not? And
the problem by refusing toresolvefound it does not meet the specifications was to
receive sub aggregate layer and re-processed.
PARRAPETS REINFORCEMENT:2
When matching schemes for reinforcing parapets We found that there is a
the problem byresolvedifference between reality and reinforcing scheme was to
refusing to receive the reinforcing parapets and make sure reinforcing some
parapets already installed.
CROSSHEAD CONCRETE:3
After casting 40 cubic meters of concrete for the crosshead and taking samples
from the site to test compressive strength of concrete show that the concrete did not
achieve the force required in the design and then used a Schmidt hammer also did
the problem byresolvenot achieve the force required in the design and was to
refused to receive the crosshead concrete and then broken crosshead.
STREET:-KING FAHAD ROAD INTERSECTION WITH EIGHTY4
7/30/2019 Senior Coop Training
49/57
STREET:-KING FAHAD ROAD INTERSECTION WITH EIGHTY4
After delivery to bridge the intersection of King Fahad Street, with eighty-street
there was a lot of traffic problems and complaints from citizens because of
the problem by modifying some of thesolvedcongestion and designs, then
designs.RAINFALL WHEN PLACING CONCRETE:5
The occurrence of rainfall after casting concrete directly and did not reach the stage of
the problem by putting a plastic insulator during thesolvedhardened concrete, and
rains.
MORTAR OF BLENTH:6
During the beginning of mixing materials and cast of blentgh found that there is
toresolvedan increase in workability due to increased water and the problem was
refuse the receipt of materials.
KING FAHAD ROAD ITERSECTION WITH KING ABDUL AZIZ :7
During the implementation of a bridge and tunnel at the intersection of King Abdul Aziz
Street and King Fahd Street, found that isolated footing of the bridge, prevent the
by replacing the isolated footingresolvedestablishment of tunnel and the problem was
by piles footing.
BACK
7/30/2019 Senior Coop Training
50/57
Subject Use in Training-7
CE 341 -
7/30/2019 Senior Coop Training
51/57
CE 112 -
SurveyingCE 354 -
Geotechnical
Engineering
LaboratoryCE 304 -
Propertiesand testing of
concrete
CE 305 -
Structural
AnalysisCE 353 -
Geotechnical
EngineeringCE 203
Construc.
Materials
GE 211 -
Introduction to
Engineering
Design -1
CE 363 -
Foundation
Engineering
CE 315 -
Reinforced
Concrete
CE 370 -Engineering
drinking
water and
sanitation
CE 320 -
Construction
Management
Engineering
Traffic
Engineering
and Transport
Subject Usein Training
BACK
7/30/2019 Senior Coop Training
52/57
8 - Gained Experience.
G i d E i
7/30/2019 Senior Coop Training
53/57
Gained Experience
Professional field work experience with multidisciplinary professionals on all levels(engineers, technicians, administrative,.etc).
Professional meetings with consultants to resolve whatever field problems appear.
Conducting preliminary and execution construction surveying works.
Conducting quality control/assurance lab/field tests and data reporting.
Experience with bridge engineering works such as girders installation, joints
executions,...etc.
Project management activities and preparing progressive reports.
BACK
7/30/2019 Senior Coop Training
54/57
9
Conclusions
7/30/2019 Senior Coop Training
55/57
Conclusions
Coop training is very useful in providing students with valuable onsite
professional experience.
Lab and field experiments are considered essential tools for engineers in order to
assure the quality of different field engineering activities.
Engineers have to consider the site conditions carefully, among other factors,when planning and managing engineering projects.
Engineers need to learn how to be successfully in dealing with multidisciplinary
professionals at all levels.
Communication and effective team work are essential for onsite work to assure
success.
7/30/2019 Senior Coop Training
56/57
Acknowledgement
I would like to seize this opportunity to thank the Engineering College at
Qassim University and, Professor Ibraheem AL- Salamh , for giving us
the chance to gain necessary on site professional experience.
7/30/2019 Senior Coop Training
57/57
Thank You for Listening