10
25 th Avenue Grade Separation Project Open House April 17, 2018

Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

25th Avenue Grade

Separation Project

Open House

April 17, 2018

Page 2: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

Project Overview

2

• 92 Caltrain trains each weekday use the 25th Avenue

crossing, in addition to freight

• Lack of grade separation increases delays along

corridor

Page 3: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

Project Benefits

• Safe rail operations

• Fewer system-wide delays

• Improved traffic flow

• Improved pedestrian and motorist safety

• Facilitate Caltrain electrification which will

reduce noise and vibration

3

Page 4: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

Grade Separations

4

28th Avenue

31st Avenue

25th Avenue

Relocated Hillsdale

Station

Page 5: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

Station Improvements

5

Page 6: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

Schedule: Overview

6

Activity Date

Construction Begins October 2017

Bridges and MSE Walls Current – Sept. 2018

E. 25th Ave. (intermittent lane closures) Current – Jun. 2018

PG&E Pipeline Work May 2018 – Sept. 2018

Station Closed Early 2019 (5 months)

28th Ave. Complete

31st Ave. Complete

Mar. 2019

Oct. 2019

E. 25th Ave. Closure (full)

E. 25th Ave. Complete

Oct 2019 (60 Days)

Dec 2019

Project Complete Early 2020

Page 7: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

Construction

7

31st Avenue

31st Ave CIDH

Pedestrian Underpass

Borel Creek

Page 8: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

Contact Information

25th Avenue Grade Separation Project

• www.Caltrain.com/25thGS

• Construction Outreach Hotline: 650.508.7726

• Email: [email protected]

PG&E Pipeline Work

• www.PGE.com/Gas

• Project Questions: 650.598.7416

Page 9: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

PG&E Pipeline Work

Page 10: Separation Project - CaltrainAffairs/Capital...Apr 17, 2018  · 25th Avenue Grade Separation Project Open House April 17, 2018 . Project Overview 2 • 92 Caltrain trains each weekday

Open House