Session 1. Disaster Planning and Emergency Preparedness Cathy Simoneaux, Loyola University New Orleans Bob Quinn, The Pennsylvania State University Mary Haldane, Department of Education. Disaster Planning & Emergency Preparedness Cathy Simoneaux. When We Left Work on Friday. - PowerPoint PPT Presentation
Citation preview
Session 1
Disaster Planning and Emergency
PreparednessCathy Simoneaux, Loyola University New Orleans
Bob Quinn, The Pennsylvania State University
Mary Haldane, Department of Education
2
Disaster Planning & Emergency
Preparedness
Cathy Simoneaux
3
When We Left Work on Friday
Katrina Was Forecast to Hit Florida
4
Late Friday, the storm changed course
• “Emergency Plans” began to be implemented
Saturday morning
– We came in and secured our basement office
– Students urged to leave campus
– Mandatory evacuation implemented by Sunday
morning
5
The Levees Failed Late Monday
6
7
Lakeview-Where My Parents Lived
8
St. Dominic –My Elementary School
9
Mt. Carmel –My High School
10
My Neighborhood –1 mile from Loyola
11
Katrina’s Impact
• Personal Impact
(as of 8/14/06)
• 80% of New Orleans flooded, an area equal in size to
seven Manhattan Islands
• 1,464 people died; 134 remain missing
• 204,000-plus homes severely damaged
12
Katrina’s Impact
• 800,000-plus citizens forced to live outside of
their homes - the greatest diaspora since the Dust
Bowl of the 30's
• 81,688 FEMA trailers occupied
• 1.2 million families received Red Cross assistance
• 33,544 persons rescued by Coast Guard
13
Katrina’s Impact
• 34 years’ worth of trash and debris in New
Orleans alone
• 900,000 insureance claims at a cost of $22.6
billion
• (Reference:Women of the Storm
• http://www.womenofthestorm.net/index.php )
14
Hurricane Katrina:Our Story
• Our Emergency Plans Assumed One of the
“Normal” Means of Communication Would
Always Be Available
– How will you “reconnect” when nothing
works?
– Revised basic plan now posted at
http://www.loyno.edu/emergency/
15
The Road to Recovery
• Loyola’s IT Department had a comprehensive
disaster recovery plan in place
– Data routinely sent to Chicago
– Mainframe operations restored within two
weeks of the storm
– Operations transferred to Houston then back to
New Orleans
16
Resuming Operations
• Minimal staff pulled to the University of Houston
(Academic Affairs) and Alexandria LA (Business
Office, Student Affairs, Advancement)
– Shortage of office space “post Katrina”
• NEW PLAN: if this happens again, we are all off
to Houston
17
The Internet Let Us Function
• Web-based Policy and Procedures Manual gave
everyone access to operational info needed
– Need to add technical processes
• Do Need to Be Sure to Have Some Security
Measures to Protect Sensitive Info in the Manual
18
Critical Issue
How Do We Get Students to
Return to New Orleans?
19
Communication With Others Key
• Identify major contact at each major host school
• Over 3,000 students enrolled at over 400 schools
during the semester
• President, Provost, Deans, Academic Advisors
visited many campuses to answer questions and
address concerns
20
• Emergency Web Sites for Students /Parents
– http://loyno.edu/emersite/students
– http://www.loyno.edu/neworleans/
21
“Be A Part of History”
• Opportunities for Community Service
– The “Loyola Corps”
http://cba.loyno.edu/loyolacorps/
– The “NOAH Project”
http://noah.loyno.edu/
Loyola University Community Action Program
http://www.loyno.edu/lucap/
22
Enrollment Comparison
FALL 05 SPR 06 FALL 05 SPR 06 FALL 05 SPR 06 FALL 05 SPR 06COLLEGE FRESH FRESH SOPHS SOPHS JUNIOR JUNIOR SENIOR SENIOR "Day" Divisions 1041 809 810 702 742 662 698 701 City College 44 22 52 40 118 84 170 138 Law 280 201 44 33 268 235 222 208 TOTAL 1365 1032 906 775 1128 981 1090 1047
2/9/2006
23
Facing the Future
• Projected Drop in Enrollment in the Freshmen
Class at all metro New Orleans Schools
– Impacts Revenue for Next Four Years
– Safety of the City is the Major Concern
• Restructuring Plan Being Implemented at Loyola
–”Pathways to Our Future”
• http://www.loyno.edu/strategicplan/
Katrina: One Year Later-What Should We Do?
http://
www.loyno.edu/
universityministry
/katrina.html
25
President’s August 2006 Letter to the Community
• http://www.loyno.edu/financialaid/University%20Update%20%5Bloyolaparents%5D.pdf
26
• We are thankful for all the support that we
received in our “hour of need”
– The Department of Education
– The University of Houston
– The Financial Aid Community
27
Contact InformationI appreciate your feedback and comments.
I can be reached at:
Cathy Simoneaux
Phone: 504-865-3369
E-mail: [email protected]
28
Disaster Planning & Emergency
Preparedness
Bob Quinn
29
Penn State at a Glance
• 24 campus structure
• 80,124 total enrollment during Fall 2005
– 41,289 at Main Campus (University Park)
– 39,415 at all others
• $650 million in aid disbursed 2005-06
– Most administrative functions performed at UP
30
Penn State Campus Structure
31
A Brief History of DR at Penn State
• The 1980s – computing isolation
• The 1990s – distributed computing
• Post 2000 – DR Initiatives
– Change in leadership (admin computing)
– September 14, 2001 meeting
– 2003 audit cited building proximity
– DR Planning Committee
32
Some Definitions
• Disaster Recovery (DR) – Recovery from
unplanned interruptions of normal business
processes beyond the immediate ability of the
organization’s staff and normal management
structure to control. Strongly related to the
recovery of the IT infrastructure
33
Some Definitions
• Business Continuity Planning (BCP) – The
proactive processes and procedures an
organization puts into place to ensure that
essential functions can continue during and after a
disaster
• DR enables BCP
34
Some Definitions
• Incident – An event that leads to a short term business interruption or loss of data on a small scale i.e.. Water damage to an IT area
• Disaster – Loss of the primary IT area or the loss of the secondary mirrored IT computing facility, but not both facilities
• Catastrophe – Loss of the primary and secondary computing facilities
35
DR Committee Recommendation #1
• Establish a Disaster Recovery Position
• This was probably the single most important
strategy
• Currently have multiple positions with
responsibility for DR
• Many other participating in DR activities
37
DR Committee Recommendation #2
• Establish a Catastrophe Contingency Site
• For-Hire sites are expensive
• We chose Altoona Campus
– Somewhat remote
– 40 miles away
– Proximity to high-speed data lines
38
Recommendation #2 (continued)
• Establish a Catastrophe Contingency Site
• Problem: No facilities available
• Immediate/Short-term strategy:
– Mobile Recovery Units
• http://www.rentsys.com/
– Rental Equipment
• http://mainline.com/
39
Mobile Recovery Unit
40
Mobile Recovery Unit
41
Penn State Campus Structure
42
DR Committee Recommendation #3
• Establish a Local Recovery Site
• Decided to retain local computing facility
• Intended for localized incidents & disasters (more
likely than a large event)
• May run some production applications
• http://www.vmware.com/
43
DR Committee Recommendation #4
• Procure Software for Disaster Planning
• Facilitates the development of a DR plan
• Does not build the plan for you
• http://www.strohlsystems.com/
• LDRPS – Living Disaster Recovery Planning
System
44
DR Committee Recommendation #5
• Promote DR Awareness
• General staff awareness
• Brochures, web site, DR Day
• http://ais.its.psu.edu/disaster_recovery/index.html
45
DR Committee Recommendation #6
• Establish Emergency Information Repository
• Designed to track students, faculty & staff
• Consolidate general emergency & local
information
• Web-based interface
46
Contact Information
I appreciate your feedback and comments.
I can be reached at:
Bob Quinn
Phone: 814-863-3580
Fax: 814-863-0322
Email: [email protected]
Disaster Planning &
Emergency Preparedness
Mary Haldane
48
Department of Education Continuity of Operations Plan (COOP)
• COOP is the Department’s “Umbrella plan”
covering ED’s management of “essential
functions.”
• Assures public that Federal Government is
operating
• Every Federal Department /Agency has a COOP
• Required by law
49
Department of Education COOP Priorities
• In the event of a crisis, the Department’s priorities are:
– The safety and welfare of employees and contractors in, and visitors to, Department facilities
– Ensuring continuation of Leadership and communication within the Department to include IT resumption of normal business function in all Department offices
– Continuation of the essential business functions of the Department of Education
50
Department of Education Priorities Actions
• Personnel Safety
– Evacuation
– Shelter in Place (SIP)
– Communication• Call trees
• Accounting of staff
• Toll free line
• Website (Department & Office of Personnel & Management)
• Local Media
51
Department of Education Priorities Actions
• Continuity of Leadership
– Alternate Sites
• Secretary of Education
• Department senior leadership
• Essential staff work at home or alternate location
• Continuity of Business Functions
– Department
• Hot Site
• Federal Student Aid
• Business Continuity Plan (BCP) governs the operations during a crisis and during the restorations of operations
52
Federal Student Aid EnvironmentFederal Student Aid Regional Map
Seattle, WA (13)
San Francisco, CA (61)
Boston, MA (13)
Washington, DC (675)
Atlanta, GA (79)
Denver, CO (17)
Kansas City, MO (24)
Chicago, IL (78)
Philadelphia, PA (21)
New York, NY (28)Seattle, WA (13)
San Francisco, CA (61)
Boston, MA (13)
Washington, DC (675)
Dallas, TX (28)
53
Federal Student Aid EnvironmentFederal Student Aid Major Systems Locations
Meriden, CT
Columbus, GA
Utica, NY
Iowa City, IA
Rockville, MD
Niagara Fall, NY
Bakersfield, CA Atlanta, GA
Louisville, KY
Montgomery, AL
Plano, TX
Greenville, TX
San Antonio, TX
Lawrence, KS
54
Federal Student Aid Business Continuity Plan (BCP)
• Background
– Business Impact Analysis
• Priority of business functions
• Essential staff to support priorities
• Essential systems to support priorities
• Records/Files to support priorities
• Alternate site(s)
55
Federal Student Aid Business Continuity Plan (BCP)
• Priorities and recovery times
– Capability to process student aid applications and determine eligibility – three days
– Capability to deliver funds to schools to support Title IV aid to eligible students and parents – three days
– Delivering student aid only to fully eligible and participating schools – three days
– Capability to make payments to lenders and Gas in support of FFELP lender and GA functions – three days
– Ensuring that DL, DLC, & DCS (FFELP, FPL, grant overpayments) loans enter into repayment on time and interest benefits are calculated – four days
56
Federal Student Aid Business Continuity Plan (BCP)
BCP Team Organization and Roles
• Senior Management Team – activates and direct plan in a crisis
• Business Impact Assessment Team – assesses damage and recovery efforts and time frames for recovery
• Business Function Recovery Team – vital system staff lead continuity of operations during crisis and recovery of operations after crisis ends
• BCP Coordinator - Develops and maintains BCP
57
Federal Student Aid Business Continuity Plan (BCP)
Succession Staff and Vital Systems Staff• Chief Operating Officer – five deep• Vital Systems Staff – four deep• Alternate site is home
– Access to Department network– Vital records access
• Shared drive capacity– Communications
• Alternate media: landline, cell, BlackBerry, fax, personal computer
58
Federal Student Aid Business Continuity Plan (BCP)
Awareness and TrainingAll staff
– New staff orientation– All staff - yearly required training – All staff call tree test four times a year
Federal Student Aid BCP Teams and vital systems staff– Tests two times a year– Tabletop exercises two times a year– All staff call tree test four times a year
59
Contact Information
I appreciate your feedback and comments.
I can be reached at:
Mary Haldane
Phone: 202-377-4324
Fax: 202-275-0907
Email: [email protected]