Session 1. Disaster Planning and Emergency Preparedness Cathy Simoneaux, Loyola University New Orleans Bob Quinn, The Pennsylvania State University Mary Haldane, Department of Education. Disaster Planning & Emergency Preparedness Cathy Simoneaux. When We Left Work on Friday. - PowerPoint PPT Presentation

Citation preview

Page 1: Session  1

Session 1

Disaster Planning and Emergency

PreparednessCathy Simoneaux, Loyola University New Orleans

Bob Quinn, The Pennsylvania State University

Mary Haldane, Department of Education

Page 2: Session  1

2

Disaster Planning & Emergency

Preparedness

Cathy Simoneaux

Page 3: Session  1

3

When We Left Work on Friday

Katrina Was Forecast to Hit Florida

Page 4: Session  1

4

Late Friday, the storm changed course

• “Emergency Plans” began to be implemented

Saturday morning

– We came in and secured our basement office

– Students urged to leave campus

– Mandatory evacuation implemented by Sunday

morning

Page 5: Session  1

5

The Levees Failed Late Monday

Page 6: Session  1

6

Page 7: Session  1

7

Lakeview-Where My Parents Lived

Page 8: Session  1

8

St. Dominic –My Elementary School

Page 9: Session  1

9

Mt. Carmel –My High School

Page 10: Session  1

10

My Neighborhood –1 mile from Loyola

Page 11: Session  1

11

Katrina’s Impact

• Personal Impact

(as of 8/14/06)

• 80% of New Orleans flooded, an area equal in size to

seven Manhattan Islands

• 1,464 people died; 134 remain missing

• 204,000-plus homes severely damaged 

Page 12: Session  1

12

Katrina’s Impact

• 800,000-plus citizens forced to live outside of

their homes - the greatest diaspora since the Dust

Bowl of the 30's

• 81,688 FEMA trailers occupied

• 1.2 million families received Red Cross assistance

• 33,544 persons rescued by Coast Guard

Page 13: Session  1

13

Katrina’s Impact

• 34 years’ worth of trash and debris in New

Orleans alone

• 900,000 insureance claims at a cost of $22.6

billion

• (Reference:Women of the Storm

• http://www.womenofthestorm.net/index.php )

Page 14: Session  1

14

Hurricane Katrina:Our Story

• Our Emergency Plans Assumed One of the

“Normal” Means of Communication Would

Always Be Available

– How will you “reconnect” when nothing

works?

– Revised basic plan now posted at

http://www.loyno.edu/emergency/

Page 15: Session  1

15

The Road to Recovery

• Loyola’s IT Department had a comprehensive

disaster recovery plan in place

– Data routinely sent to Chicago

– Mainframe operations restored within two

weeks of the storm

– Operations transferred to Houston then back to

New Orleans

Page 16: Session  1

16

Resuming Operations

• Minimal staff pulled to the University of Houston

(Academic Affairs) and Alexandria LA (Business

Office, Student Affairs, Advancement)

– Shortage of office space “post Katrina”

• NEW PLAN: if this happens again, we are all off

to Houston

Page 17: Session  1

17

The Internet Let Us Function

• Web-based Policy and Procedures Manual gave

everyone access to operational info needed

– Need to add technical processes

• Do Need to Be Sure to Have Some Security

Measures to Protect Sensitive Info in the Manual

Page 18: Session  1

18

Critical Issue

How Do We Get Students to

Return to New Orleans?

Page 19: Session  1

19

Communication With Others Key

• Identify major contact at each major host school

• Over 3,000 students enrolled at over 400 schools

during the semester

• President, Provost, Deans, Academic Advisors

visited many campuses to answer questions and

address concerns

Page 20: Session  1

20

• Emergency Web Sites for Students /Parents

– http://loyno.edu/emersite/students

– http://www.loyno.edu/neworleans/

Page 21: Session  1

21

“Be A Part of History”

• Opportunities for Community Service

– The “Loyola Corps”

http://cba.loyno.edu/loyolacorps/

– The “NOAH Project”

http://noah.loyno.edu/

Loyola University Community Action Program

http://www.loyno.edu/lucap/

Page 22: Session  1

22

Enrollment Comparison

FALL 05 SPR 06 FALL 05 SPR 06 FALL 05 SPR 06 FALL 05 SPR 06COLLEGE FRESH FRESH SOPHS SOPHS JUNIOR JUNIOR SENIOR SENIOR "Day" Divisions 1041 809 810 702 742 662 698 701 City College 44 22 52 40 118 84 170 138 Law 280 201 44 33 268 235 222 208 TOTAL 1365 1032 906 775 1128 981 1090 1047

2/9/2006

Page 23: Session  1

23

Facing the Future

• Projected Drop in Enrollment in the Freshmen

Class at all metro New Orleans Schools

– Impacts Revenue for Next Four Years

– Safety of the City is the Major Concern

• Restructuring Plan Being Implemented at Loyola

–”Pathways to Our Future”

• http://www.loyno.edu/strategicplan/

Page 24: Session  1

Katrina: One Year Later-What Should We Do?

http://

www.loyno.edu/

universityministry

/katrina.html

Page 25: Session  1

25

President’s August 2006 Letter to the Community

• http://www.loyno.edu/financialaid/University%20Update%20%5Bloyolaparents%5D.pdf

Page 26: Session  1

26

• We are thankful for all the support that we

received in our “hour of need”

– The Department of Education

– The University of Houston

– The Financial Aid Community

Page 27: Session  1

27

Contact InformationI appreciate your feedback and comments.

I can be reached at:

Cathy Simoneaux

Phone: 504-865-3369

E-mail: [email protected]

Page 28: Session  1

28

Disaster Planning & Emergency

Preparedness

Bob Quinn

Page 29: Session  1

29

Penn State at a Glance

• 24 campus structure

• 80,124 total enrollment during Fall 2005

– 41,289 at Main Campus (University Park)

– 39,415 at all others

• $650 million in aid disbursed 2005-06

– Most administrative functions performed at UP

Page 30: Session  1

30

Penn State Campus Structure

Page 31: Session  1

31

A Brief History of DR at Penn State

• The 1980s – computing isolation

• The 1990s – distributed computing

• Post 2000 – DR Initiatives

– Change in leadership (admin computing)

– September 14, 2001 meeting

– 2003 audit cited building proximity

– DR Planning Committee

Page 32: Session  1

32

Some Definitions

• Disaster Recovery (DR) – Recovery from

unplanned interruptions of normal business

processes beyond the immediate ability of the

organization’s staff and normal management

structure to control. Strongly related to the

recovery of the IT infrastructure

Page 33: Session  1

33

Some Definitions

• Business Continuity Planning (BCP) – The

proactive processes and procedures an

organization puts into place to ensure that

essential functions can continue during and after a

disaster

• DR enables BCP

Page 34: Session  1

34

Some Definitions

• Incident – An event that leads to a short term business interruption or loss of data on a small scale i.e.. Water damage to an IT area

• Disaster – Loss of the primary IT area or the loss of the secondary mirrored IT computing facility, but not both facilities

• Catastrophe – Loss of the primary and secondary computing facilities

Page 35: Session  1

35

DR Committee Recommendation #1

• Establish a Disaster Recovery Position

• This was probably the single most important

strategy

• Currently have multiple positions with

responsibility for DR

• Many other participating in DR activities

Page 36: Session  1

36

PSU DR Manager

Ken Schroyer

[email protected]

814.863.8888

Page 37: Session  1

37

DR Committee Recommendation #2

• Establish a Catastrophe Contingency Site

• For-Hire sites are expensive

• We chose Altoona Campus

– Somewhat remote

– 40 miles away

– Proximity to high-speed data lines

Page 38: Session  1

38

Recommendation #2 (continued)

• Establish a Catastrophe Contingency Site

• Problem: No facilities available

• Immediate/Short-term strategy:

– Mobile Recovery Units

• http://www.rentsys.com/

– Rental Equipment

• http://mainline.com/

Page 39: Session  1

39

Mobile Recovery Unit

Page 40: Session  1

40

Mobile Recovery Unit

Page 41: Session  1

41

Penn State Campus Structure

Page 42: Session  1

42

DR Committee Recommendation #3

• Establish a Local Recovery Site

• Decided to retain local computing facility

• Intended for localized incidents & disasters (more

likely than a large event)

• May run some production applications

• http://www.vmware.com/

Page 43: Session  1

43

DR Committee Recommendation #4

• Procure Software for Disaster Planning

• Facilitates the development of a DR plan

• Does not build the plan for you

• http://www.strohlsystems.com/

• LDRPS – Living Disaster Recovery Planning

System

Page 44: Session  1

44

DR Committee Recommendation #5

• Promote DR Awareness

• General staff awareness

• Brochures, web site, DR Day

• http://ais.its.psu.edu/disaster_recovery/index.html

Page 45: Session  1

45

DR Committee Recommendation #6

• Establish Emergency Information Repository

• Designed to track students, faculty & staff

• Consolidate general emergency & local

information

• Web-based interface

Page 46: Session  1

46

Contact Information

I appreciate your feedback and comments.

I can be reached at:

Bob Quinn

Phone: 814-863-3580

Fax: 814-863-0322

Email: [email protected]

Page 47: Session  1

Disaster Planning &

Emergency Preparedness

Mary Haldane

Page 48: Session  1

48

Department of Education Continuity of Operations Plan (COOP)

• COOP is the Department’s “Umbrella plan”

covering ED’s management of “essential

functions.”

• Assures public that Federal Government is

operating

• Every Federal Department /Agency has a COOP

• Required by law

Page 49: Session  1

49

Department of Education COOP Priorities

• In the event of a crisis, the Department’s priorities are:

– The safety and welfare of employees and contractors in, and visitors to, Department facilities

– Ensuring continuation of Leadership and communication within the Department to include IT resumption of normal business function in all Department offices

– Continuation of the essential business functions of the Department of Education

Page 50: Session  1

50

Department of Education Priorities Actions

• Personnel Safety

– Evacuation

– Shelter in Place (SIP)

– Communication• Call trees

• Accounting of staff

• Toll free line

• Website (Department & Office of Personnel & Management)

• Local Media

Page 51: Session  1

51

Department of Education Priorities Actions

• Continuity of Leadership

– Alternate Sites

• Secretary of Education

• Department senior leadership

• Essential staff work at home or alternate location

• Continuity of Business Functions

– Department

• Hot Site

• Federal Student Aid

• Business Continuity Plan (BCP) governs the operations during a crisis and during the restorations of operations

Page 52: Session  1

52

Federal Student Aid EnvironmentFederal Student Aid Regional Map

Seattle, WA (13)

San Francisco, CA (61)

Boston, MA (13)

Washington, DC (675)

Atlanta, GA (79)

Denver, CO (17)

Kansas City, MO (24)

Chicago, IL (78)

Philadelphia, PA (21)

New York, NY (28)Seattle, WA (13)

San Francisco, CA (61)

Boston, MA (13)

Washington, DC (675)

Dallas, TX (28)

Page 53: Session  1

53

Federal Student Aid EnvironmentFederal Student Aid Major Systems Locations

Meriden, CT

Columbus, GA

Utica, NY

Iowa City, IA

Rockville, MD

Niagara Fall, NY

Bakersfield, CA Atlanta, GA

Louisville, KY

Montgomery, AL

Plano, TX

Greenville, TX

San Antonio, TX

Lawrence, KS

Page 54: Session  1

54

Federal Student Aid Business Continuity Plan (BCP)

• Background

– Business Impact Analysis

• Priority of business functions

• Essential staff to support priorities

• Essential systems to support priorities

• Records/Files to support priorities

• Alternate site(s)

Page 55: Session  1

55

Federal Student Aid Business Continuity Plan (BCP)

• Priorities and recovery times

– Capability to process student aid applications and determine eligibility – three days

– Capability to deliver funds to schools to support Title IV aid to eligible students and parents – three days

– Delivering student aid only to fully eligible and participating schools – three days

– Capability to make payments to lenders and Gas in support of FFELP lender and GA functions – three days

– Ensuring that DL, DLC, & DCS (FFELP, FPL, grant overpayments) loans enter into repayment on time and interest benefits are calculated – four days

Page 56: Session  1

56

Federal Student Aid Business Continuity Plan (BCP)

BCP Team Organization and Roles

• Senior Management Team – activates and direct plan in a crisis

• Business Impact Assessment Team – assesses damage and recovery efforts and time frames for recovery

• Business Function Recovery Team – vital system staff lead continuity of operations during crisis and recovery of operations after crisis ends

• BCP Coordinator - Develops and maintains BCP

Page 57: Session  1

57

Federal Student Aid Business Continuity Plan (BCP)

Succession Staff and Vital Systems Staff• Chief Operating Officer – five deep• Vital Systems Staff – four deep• Alternate site is home

– Access to Department network– Vital records access

• Shared drive capacity– Communications

• Alternate media: landline, cell, BlackBerry, fax, personal computer

Page 58: Session  1

58

Federal Student Aid Business Continuity Plan (BCP)

Awareness and TrainingAll staff

– New staff orientation– All staff - yearly required training – All staff call tree test four times a year

Federal Student Aid BCP Teams and vital systems staff– Tests two times a year– Tabletop exercises two times a year– All staff call tree test four times a year

Page 59: Session  1

59

Contact Information

I appreciate your feedback and comments.

I can be reached at:

Mary Haldane

Phone: 202-377-4324

Fax: 202-275-0907

Email: [email protected]