Upload
2003vinay
View
219
Download
0
Embed Size (px)
Citation preview
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
1/85
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
2/85
Forward
I have the pleasure in releasing the 2011 Seven Year Electricity Planning Statement (7YPS) fortransmission within the Emirate of Abu Dhabi and, where appropriate, our network outside of theauthorized area covering the period 2012-2018. In producing this document, we have endeavoredto ensure that our customers, both existing and future, are presented with an opportunity tounderstand the scale and type of transmission network operated by us. We have sought to ensurethat customers are able to identify areas of the network where additional investment is proposed inorder to increase available capacity or otherwise ensure that network performance continues toattain the targets expected from such a critical infrastructure provider.
This is the second 7YPS released in response to Condition 15 of the Transmission and DespatchLicence that provides detailed short to medium-term plans for the transmission network. The plans
included in the 7YPS are linked to the needs and investment requirements and are based on thenetwork development strategy covering the period 2010-2030 that places much greater emphasison the trends and drivers which provides a long-term vision for taking the transmission systemforward consistent with Governments 2030 vision.
Feedback on this 7YPS is most welcome in order that TRANSCO is able to continue to adjust its
planning and development strategies to meet the regulatory, customer and stakeholderrequirements and expectations.
Copies of approved 7YPS could be downloaded from our website www.transco.ae .
Dr. Najib H DandachiAsset Management DirectorTRANSCO
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
3/85
Table of Contents Main Report
Forward......2
Table of Contents.......3
Acronyms and Definitions.........5
Executive Summary.......8
1 Introduction.........21
2 Network Development Strategy......24
3 Planning Principles......39
4 Demand-Generation Background........44
5 Planned Transfers....52
6 Evolution and Performance of Transmission Network...55
7 Asset Management...64
8 Transmission System Capabilities and Opportunities.........65
9 Capital Delivery..........76
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
4/85
Table of Contents (continued)
Attachments
Attachment-A
Electricity generation capacity expansion plan and electricity demand forecast schedules.
Attachment-B
Electricity transmission network topology (400kV, 220kV, 132kV system).Geo-map of transmission network topology (400kV and 220kV system) for Year 2011 & 2018.
Attachment-C
Forecast power flows and loading on the transmission system for Year 2011-2018.
Attachment-D
Fault levels at the transmission nodes for Year 2011-2018.
Attachment-E
Transmission system dataset.
Attachment-F
Brief description on major existing generation plants and planned committed generation projects.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
5/85
Acronyms and Definitions
7YPS: Seven Year Planning Statement
AC: Alternating Current
AED: UAE Dhirams
AAPS: Al-Ain Power Station
AADC: Al-Ain Distribution Company
ADDC: Abu Dhabi Distribution Company
ADNOC: Abu Dhabi National Oil Company
ADWEA: Abu Dhabi Water and Electricity Authority
ADWEC: Abu Dhabi Water and Electricity Company
ACCC: Aluminum Conductor Composite Core
ACSR: Aluminum Conductor Steel Reinforced
CSP: Concentrated Solar Power
CAPEX: Capital expenditure
DEWA: Dubai Electricity and Water Authority
DISCOs: Distribution Companies
DSM: Demand Side Management
EMAL: Emirates Aluminum Smelter Plant
ENG: Emirates National Grid
FEWA: Federal Electricity and Water Authority
GCC: Gulf Cooperation Council
GDP: Gross Domestic Product
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
6/85
HVDC LCC: High Voltage Direct Current Line Commuted Converter
ICAD: Industrial City of Abu Dhabi
kV: Kilovolt
KPIZ: Khalifa Port and Industrial Zone
KSA: Kingdom of Saudi Arabia
MEAV: Modern Equivalent Asset Value
MW: Megawatt
MVA: Megavoltampere
NPV: Net Present Value
OPEX: Operational expenditure
PAS55: 55 th Publicly Available Specification
PV: Photovoltaic
RSB: Regulation and Supervision Bureau
SASN/UAN: Sas Al Nakheel/Umn Al Nar
STATCOM: Static Synchronous Compensator
SVC: Static VAr Compensator
TRANSCO: Abu Dhabi Transmission and Despatch Company
UPC: Abu Dhabi Urban Planning Council
USERs: DISCOs, GENCOs, ADNOC, Non-embedded customers, interconnected utilities
UAE: United Arab Emirates
VAr: Volt Ampere
VSC: Voltage Sourced Converters
WLCC: Whole Life Cycle Cost
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
7/85
Planned transfer is the planned power flows across the identified boundary/lines.
Transfer capability is the maximum power flow across the identified transmission boundarywithout causing any unacceptable conditions as a result of secured events.
Secured event is the event that relates to a fault outage of a single transmission circuit under IntactSystem; or outage of a single transmission circuit with planned outage of another transmission
circuit, a generating unit or reactive element.
Identified generation capacity is the total gross electricity generation capacity available from allexisting power plants, power plants which are under construction and committed power plants lessthe off-set capacity available due to life-time capacity retirements.
Required generation capacity is the total gross electricity generation capacity required to satisfythe generation security of supply standard that takes into account the generation planning criteriaand other factors such as forced outage rate, demand forecast error, spinning reserve.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
8/85
Executive Summary
E1 Introduction
Condition 15 of the Transmission Licence requires the Abu Dhabi Transmission and Despatch
Company (TRANSCO) to prepare a seven year planning statement (7YPS) annually in a form
approved by the Regulation and Supervision Bureau (RSB or Bureau). In relation to the electricity
transmission system, the requirement is to contain the following information in each of the seven
succeeding financial years:
a) Capacity, forecast power flows and loading on each part of the transmission system, and faultlevels for each electricity transmission node.
b) Plans for capital expenditure necessary to ensure the relevant transmission system meets thesecurity and performance standards and future demands.
The 7YPS has been developed in the context of the TRANSCOs network development strategy
for the period to 2030 that sets a long-term vision for taking the transmission system forward. The
network development strategy places much greater emphasis on the trends and drivers which
provides a long-term vision for taking the transmission system forward consistent withGovernments 2030 vision. The 7YPS describes more detailed short to medium-term plans for the
transmission system and is linked to the needs and investment requirements for the period 2012-
2018.
The main purpose of the 7YPS is to enable the Users seeking the use of the transmission system, to
identify and evaluate the opportunities available when connecting to and making use of suchsystem. Such opportunities shall be guided by the Statement of Connection Charging
Methodology to make a reasonable estimate of the charges to which they would be liable for the
provision of such services. It also gives a forward view on the proposed transmission infrastructure
expansion plans to meet the forecast demand growth and planned new generation
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
9/85
and status. The cutoff date for input data is 30 April 2011. All information received after this date
will be updated in TRANSCO 2012 7YPS (2013-2019). The 7YPS presents a wide range of
information relating to the planning and development of 400kV, 220kV and 132kV transmission
system within the Emirate of Abu Dhabi and, where appropriate, TRANSCOs network outside of
the authorized area.
E2 Network Development Strategy
TRANSCOs network development strategy is to continue to develop a flexible, reliable, secure,
accessible, robust, economical, efficient, environmentally friendly and safe transmission system
that meets the needs of its customers in a manner consistent with its License obligations.
This is achieved through:
Implementing a structured asset management process that takes cognizance of best practiceasset management principles for the development and stewardship of the transmission network
and requirements for capital assurance governance.
Continuing with the development of 400kV main bulk transmission system. Given the
uncertainty in the demand and generation background, the possible need to migrate to 765kVor HVDC as the main overlay transmission system option across the West-East corridor is to
be kept under review, particularly if significant level of additional generation capacity beyond
Shuweihat S3 and Braka nuclear plant are contracted in the Western region, and that there is
increased requirement to provide power to Northern Emirates.
Incremental deployment and integration of new technologies and best available practice.
It is intended that the development of the transmission network will be done in such a manner to:
Have minimum negative side-effects on the environment and society.
Accommodate large central and decentralized generation and storage.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
10/85
Optimize asset utilization and operate efficiently through integrated outage management, riskassessment, improved process, resource management and use of technology and decision
support tools.
Anticipate and respond to system disturbances.
Operate resiliently under unforeseen events.
Figure E-1 shows the expected 400kV transmission system configuration by 2030.
2025 Best View (30GW)
Al-AinSouth West
Dahma
Sweihan
Mussafah
Shahama
Warsan
Dhaid
Ras AlKhaimah
To Salwa 400kVGrid Station
(KSA)
Sharjah
SASN
Taweelah
Qidfa
Sila
ICAD
MahawiBahia
Al Wasit Area(Sultanate of Oman)Shamkha
Hameem
Al-Ain Airport
Ajman
New FujairahCity
Mirfa
Wathba
SAS Al NakheelBeach
Al Qurm
ADST
ReemSadiyat
Bahia
ZayedSports City
Braka
400kV grid station
400kV Tower (double circuit)
400kV CableSingle Circuit
Single 400kVOverhead Line Circuit
400kV grid station associated with Power Plant
Madinat Zayed
Bab
ChemaWEyaat
Shuweihat
Ruwais
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
11/85
E3 Demand-Generation Background
Global peak electricity demand (include supplies to Abu Dhabi Emirate and Northern Emirates) is
forecast to increase to between 16GW-24GW by 2018 according to ADWECs 2011 forecast
update. This represents an average growth rate of about 9% and 16% per annum for the period
2010-2018 related to the two demand forecasts. For the purposes of preparing this 7YPS an
intermediate demand level of about 20GW by 2018 is also considered. This together with the
generation background described below is consistent with the best-view long-term transfersestablished in the network development strategy. The demand scenarios are used to indicate
uncertainty and market volatility in the forecast. The principle demand drivers are industrial,
residential and commercial development expansions; and export supplies to Northern Emirates.
The proportion of industrial demand relative to peak demand is forecast to increase as the UAE
diversifies its economy and there is the potential for variations of the locational development of
demand within the outlier demand scenario.
To meet these demands, the existing power generation plants contribute about 12GW (as on 2010)
of capacity. New committed generation projects identified to date which are expected to be
integrated into the main bulk transmission grid during the period 2011-2020 are:
Shuweihat S2 (~1.62GW) and Shuweihat S3 (~1.65GW) combined cycle fossil fuel plantslocated adjacent to the existing Shuweihat S1 site in the Al Gharbia region.
Shuweihat S2 is integrated to transmission network and operational in 2011.
The Braka site in the Gharbia region has been identified to promote nuclear generation of totalcapacity 5.6GW by 2020. Generator units of 1400MWe are expected to be integrated to the
transmission system.
Shams-1 concentrated solar power (CSP) plant with a maximum installed capacity of 110MWat a facility located south of Madinat Zayed in the Gharbia region.
Nour-1 photovoltaic solar power (PV) plant with a maximum installed capacity of 100MW at apotential facility in Al-Ain region.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
12/85
Some of the existing generation plants are expected to retire during the period 2017-2020. These
are located at Mirfa (186MW), Umn Al Nar (778MW), Al-Ain Power Station (256MW) and
Madinat Zayed Power Station (109MW). The available capacity off-set due to the closure of above
existing generation will be about 1.3GW by 2020. To compensate for the expected generation
retirements, there could be a possibility to locate some new generation capacity (of the order of
1GW) either by re-developing the existing Umn Al Nar (UAN) plant site (in Eastern region close
to Abu Dhabi Island) or locate some new generation capacity close to Sweihan (in Al-Ain region).
In either case, no major 400kV transmission reinforcement works are required as theexisting/planned main bulk transmission infrastructure by 2020 in UAN and Sweihan has
sufficient transmission capability to evacuate the above generation.
To meet the TRANSCOs best view planned transfers after Shuweihat S3 generation; there is a
need to integrate an additional major new generation into the transmission system from 2015.In addition to Taweela-C option (in Eastern region), there are two other potential generation sites
options available. These are Al Mirfa (in Gharbia region) and Hamria/Ras Al Khaimah
(in Northern Emirates). While the need to utilize all of the above three generation sites could be
possible in the long-term, nevertheless one of the above-mentioned generation sites is considered
to be the most likely next generation site to satisfy the demand-supply gap and the emerging gap
between the identified generation capacity and the required generation capacity upto 2020. 400kV transmission reinforcement is required across Shamkha-Sweihan corridor common for all
the three potential generation site options in addition to the generation integration works required
at their respective generation sites. For the potential generation site option at Mirfa (in Gharbia
region) only, major 400kV transmission reinforcement is required within the Gharbia region and
across the West-East corridor to evacuate power generation from the Gharbia region.
Figure E-2 shows the demand-generation background for the period 2010-2018.
Figure E-3 shows the region-wise demand forecast for the 20GW intermediate scenario.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
13/85
Figure E-2 Demand-generation background upto 2018 .
0
5
10
15
20
25
30
2010 2011 2012 2013 2014 2015 2016 2017 2018
Year
G W
Installed Gen Capacity (Existing) Committed Gen Capacity 22.5GW Scenario (16GW by 2018)
32.5GW Sce nario (18. 5GW by 2018) 20GW Intermediate Scena rio (20GW by 2018) 38.5GW Scenario (24GW by 2018)
Global demand growth rate (2010-2018)
ADWEC's 22.5GW scenario = 9.2%
ADWEC's 32.5GW scenario = 11.9%
20GW Intermediate scenario = 13.1%
ADWEC's 38.5GW scenario = 16.1%
8,485
9,845
11,167
13,436
14,730
16,85117,582
18,783
20,046
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000
22,000
24,000
P e a k
D e m a n
d ( M W )
Abu Dhabi Islands' Eastern RegionGharbia (Western) Region Al-Ain RegionNorthern Emirates Incl. Water Pump & Aux. Loads Auxiliary & Desalination Process Loads i n AD EmirateTransmission Losses Coincident Total System Peak
Growth Rate (2010-2018)
System (AD+NE) = 13.1%; Abu Dhabi Emirate = 11.9%
Abu Dhabi Islands' = 7.8%; Eastern Region = 15.7%
Gharbia Region = 24.4%; Al-Ain Region = 6.3%
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
14/85
E4 Regional and International Grid Interconnections
To support the Government of Abu Dhabi initiative to bolster the domestic energy security,
TRANSCOs transmission system will increasingly integrate with Emirates National Grid (ENG)
and Gulf Cooperation Council (GCC). Figure E-4 shows the simplified high-level grid
interconnection arrangement (existing and current plans) with ENG/GCC grids.
Figure E-4 Simplified high-level grid interconnection arrangement with ENG/GCC grids.
Existing 400kV GridsCommitted 400kV Grids
Sweihan
Warsan
Dhaid
Ras Al Khaimah
Shuweihat
To Salwa 400kV Grid Station
(KSA)
Sharjah
Qidfa
Sila
Al Wasit Area(Sultanate of Oman)
Ajman
New FujairahCity
Taweela
New 400kV Tower (double circuit)
T R A N
S C O T
r a n s m i s s i o
n N e t w
o r k
i n
A b u D
h a b i E m
i r a t e
Foah
Existing 220kV Grids
Existing 220kV Tower (double circuit)
400kV OHL Tower (double circuit)
Generation Site
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
15/85
Potential maximum transfers between TRANSCO and regional/international grids under Secured
Event conditions could include:
1GW through the current existing Northern GCC 400kV interconnector between UAE-KSA.
170MW through the current existing Southern GCC 220kV interconnector between UAE-Oman. Maximum transfers are planned to be increased to about 1GW through the future
400kV interconnector between UAE-Oman.
2GW through the current existing ENG interconnections to Northern Emirates (i.e. through400kV interconnector between Taweela-Warsan, and 400kV interconnector between Fujairah
Qidfa-Sweihan) with possible range of exports.
These interconnections will not only enhance the security of supply but also reduce the spinning
reserve requirements and facilitate power exchange among member utilities and states, while
providing a mechanism to mitigate against gas supply shortages and uncertainty in the levels of
demand growth. It will also reduce plant procurement cost through achieving higher efficiency and
plant load factors apart from reducing the global operating costs of the integrated electricity
market.
E5 Planned Transfers
The requirements for the transmission system development and its associated investments are
primarily driven by the demand and generation backgrounds identified above and the resulting
power transfers on the transmission system. There are uncertainties associated with the demand
and generation backgrounds as with any forecasts and plans. These uncertainties will affect futureplanned power transfers on the transmission system and hence the way the transmission system
develops. Using scenarios analysis, the planned power transfers on the transmission system are
established for the most probable demand-generation scenarios envisaged during the period 2010-
2018 and ensure consistency with the long-term approach Envelopes of possible transfers are
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
16/85
Different demand forecast scenarios namely 22.5GW scenario (i.e. 16GW by 2018),Intermediate scenario (i.e. 20GW by 2018) and 38.5GW scenario (i.e. 24GW by 2018).
Different locational development of next possible generation (Mirfa, Taweela-C, Hamria) tomeet the above demands from 2014/2015 through to 2018 after Shuweihat S3 generation.
Figure E-5 shows the envelope of possible transfers and the best-view planned transfers across the
five identified boundary corridors for the peak demand-generation background during the period
2010-2018. It also shows the transfer capability (represented in blue text) across the identified
boundary corridors for the peak demand-generation background in 2010.
-2,000
-1,000
0
1,000
2,000
3,000
4,000
5,000
6,000
2010 2015 2020 2025 2030
B o u n d a r y
T r a n s
f e r s
( M W )
-2 ,000
-1 ,000
0
1 ,000
2 ,000
3 ,000
4 ,000
5 ,000
6 ,000
2010 2012 2014 2 016 201 8
A l - A i n
r e g i o
n
N o r t h
e r n E
m i r a
t e s-2,000
-1,000
0
1,000
2,000
2010 2012 2014 2016 2018
B o u n d a r y T r a n s f e r s ( M W )
-1,000
0
1,000
2,000
3,000
4,000
5,000
2010 2012 2014 2016 2018
B o u n d a r y T r a n s f e r s ( M W )
6,000
8,000
r s ( M W )
1,000
2,000
3,000
4,000
B o u n d a r y T r a n s f e r s ( M W )
0
1,000
2,000
3,000
4,000
5,000
2010 2012 2014 2016 2018
B o u n d a r y
T r a n s
f e r s ( M W )
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
17/85
E6 Evolution of Transmission Network
Using the best view planned transfers as the basis a network development plan has been produced.
The evolution of the transmission network based on the best-view planned transfers is detailed
below. This is consistent with the network development strategy.
Major committed 400kV transmission system expansion projects are expected to be completed
during the period 2011-2015 to meet the system needs and to accommodate committed newgeneration projects.
The 400kV transmission facilities from the existing Shuweihat Power Station is capable of
evacuating power from both Shuweihat S1 & S2 generation (total about 3.2GW) to meet the
demand requirements in the Western (Gharbia) region and exports to the Abu Dhabi Region. To
evacuate power generation from the committed Shuweihat S3 generation (about 1.65GW), a new400kV grid station is planned within the Shuweihat S3 plant site. A new 400kV grid station is also
planned at Braka in 2015 to facilitate the integration of the nuclear power plant in 2017/2018. The
400kV West-East corridor reinforcements ensure an integrated approach to evacuating power from
S3 and Braka while meeting the demands in the Western region.
New 400kV grid stations and related 400kV overhead line works are expected to be integrated tothe transmission network to meet the respective regions demand requirements. These are
400/220kV grid stations in Ruwais and Bab (in Gharbia region); 400/220kV grid station in ICAD
and 400/132kV grid stations in Bahia, Mahawi and Shamkha regions (in Eastern region); and
400/132kV grid stations in Ajman, Sharjah and New Fujairah City (in Northern Emirates).
A new 400kV grid station and related 400kV overhead line works at Sila have been completed in2011 as part of the UAE plan to integrate with the GCC grid. A new 400kV grid station and related
400kV overhead line works are planned to facilitate increased interconnection with Oman grid.
400kV XLPE underground cables projects along the Abu Dhabi Island-Sadiyat-Bahia corridor
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
18/85
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
19/85
E7 Asset Management
The transmission network is comparatively young. However, there will be requirements for assets
approaching the end of their useful lives to be managed and replaced at an appropriate time. Asset
management process improvements are required to capture the knowledge to build only what
needed. Integrated outage management and risk assessment needs to be considered for improved
operational efficiency. Maintenance practices and resource management processes shall be
programmed and managed innovatively to better position the transmission network for next20 years of operation and maintenance.
It should be noted that TRANSCO recent management practice is to move towards achieving
PAS55 requirements. This is to be achieved through a structured asset management process that
takes cognizance of best practice asset management principles for the development and
stewardship of the transmission network and requirements for capital assurance governance. The
PASS55 framework includes policies, procedures and processes for managing the asset base and
also embraces continuous improvement - an aspect important to TRANSCO as it seeks to better
understand its assets to identify the short- and long-term replacement requirements. As part of the
PASS55 process and the associated need of a long term network development strategy,
consideration has not only been given to the requirements of the transmission system to
accommodate load growth but also to the requirements to replace assets as they come to the end oftheir useful life or where their performance or technologies employed result in inefficiency.
In the short to medium term, the average total forecast replacement expenditure is expected to be
less than 1% of the total load-related expenditure for the next five years. The asset class that
contributes to the replacement expenditure is transformers, switchgear, protection and auxiliary
systems. This is due to their age reaching the end of useful life and technology being obsolete.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
20/85
E8 Capital Delivery
The transmission system development requirements and associated investments are largely driven
by the demand and generation background and the resulting power transfers on the transmission
system. As there will continue to be a degree of uncertainty in the realization of the volume,
location and timing of demand and generation backgrounds in any given area, the potential
transmission reinforcement plans shall be established in a phased manner and that the options are
maintained at minimum cost to provide a least regret solution.
In view of the economic downturn and greater uncertainty in the development requirements; some
project proposals and schemes are evaluated with intent of optimizing the assets utilization taking
into account the potential risks. The risks could be if the demand does not materialize as expected
or if the demand comes early, project delays and its impact on network performance and security
of supply could result. Risk mitigation measures through various scenario/optioneering approachesare built into the planning proposals by engaging relevant Stakeholders and Users in order to
achieve a consensus on the optimum balance of overall benefits/savings and risk trade-off.
Considering the current economic scenario, TRANSCO has already taken action in delaying some
planned assets or relocating elsewhere if the contracts already awarded. Hence, there is a
likelihood of potential deviations of some project proposals and schemes included in this 7YPS.
Chapter-9 provides a brief high-level summary of capital and replacement projects. These include
only the major on-going, currently under tendering process and new planned power projects to
meet the future demands and performance standards for the period 2012-2018. These projects have
been categorized according to their needs and drivers. Whilst some of these identified seven year
capital projects shall be initiated depending on their priority level and subject to the receipt of
approvals from relevant authorities, for others it is proposed to continue monitor the developmentsof the market and update the plans accordingly.
The detailed capital delivery and capital forecast for the on-going and planned power projects to
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
21/85
1.0 Introduction
Condition 15 of the Transmission Licence requires Abu Dhabi Transmission and Despatch
Company (TRANSCO) to prepare seven year planning statement (7YPS) annually in a form
approved by the Regulation and Supervision Bureau (RSB or Bureau). In relation to the electricity
transmission system, the requirement is to contain the following information in each of the seven
succeeding financial years:
a) Capacity, forecast power flows and loading on each part of the transmission system, and faultlevels for each electricity transmission node.
b) Plans for capital expenditure necessary to ensure the relevant transmission system meets thesecurity and performance standards and future demands.
The Sector Law requires the Abu Dhabi Water and Electricity Company (ADWEC) to prepare a
demand forecast and accordingly secure the future generation capacity to meet the short and long-
term requirements of the Sector.
The 7YPS has been developed in the context of the TRANSCOs network development strategy
for the period to 2030 that sets a long-term vision for taking the transmission system forward. Thenetwork development strategy places much greater emphasis on the trends and drivers which
provides a long-term vision for taking the transmission system forward consistent with
Governments 2030 vision. The 7YPS describes more detailed short to medium-term plans for the
transmission system and is linked to the needs and investment requirements for the period 2012-
2018.
The main purpose of the 7YPS is to enable the Users seeking the use of the transmission system, to
identify and evaluate the opportunities available when connecting to and making use of such
system. Such opportunities shall be guided by the Statement of Connection Charging
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
22/85
This is the second 7YPS which contains the latest updated information and replaces all Statements
released earlier. The 7YPS covers the planning horizon 2012-2018. 2011 7YPS (2012-2018) isbased on the best available updated information from ADWEC and Users; updated project scope
and status. The cutoff date for input data is 30 April 2011. All information received after this date
will be updated in TRANSCO 2012 7YPS (2013-2019). The 7YPS presents a wide range of
information relating to the planning and development of 400kV, 220kV and 132kV transmission
system within the Emirate of Abu Dhabi and, where appropriate, TRANSCO network outside of
the authorized area.
The 7YPS update contains the following chapters:
a) Network development strategy
This chapter summarizes the network development strategy for the period to 2030 that sets a long-
term vision for taking the transmission system forward. It places much greater emphasis on thetrends and drivers which provides a long-term vision for taking the transmission system forward
consistent with Governments 2030 vision.
b) Planning principles
The principles used for the planning and development of the electricity transmission system arebriefly described. For ease of understanding, these principles are summarized under five categories
namely the general criteria, connections conditions, generation connection criteria, main
interconnected transmission system criteria and demand connection criteria. These principles are
fully described in the latest versions of the Electricity Transmission Code and Electricity
Transmission System Security Standard.
c) Demand-generation background
The requirement for the transmission system development and its associated investments is
primarily driven by the demand and generation backgrounds. In this chapter, the demand-
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
23/85
d) Planned transfers
This chapter summarizes the possible transfers and best-view planned transfers based on thedemand-generation backgrounds that determine the requirements for the transmission system
developments and its associated investment plans.
e) Evolution and performance of transmission network
The evolution of 400kV, 220kV and 132kV transmission system within the Emirate of Abu Dhabiand, where appropriate, the TRANSCO network outside of the authorized area up to 2018 are
presented. The evolution of the transmission network is based on the best-view planned transfers.
A brief description of its impact on the system performance is described. The forecast power flows
on the transmission system in PSS/E format; fault levels for each electricity transmission node for
valid load conditions for the best-view scenario are included.
f) Asset management
The requirements for assets approaching the end of their useful lives to be managed and replaced
at an appropriate time are briefly summarized in this chapter.
g) Transmission system capabilities and opportunities
This chapter describes bulk transmission system capabilities which give an indication of the extent
to which the system can accommodate the circumstances outside the chosen likely best view
planned transfers. It also provides an appreciation of opportunities available in the transmission
system to accommodate new generation and demand in across the system.
h) Capital delivery
The chapter summarizes the on-going and planned power projects to meet the future demands and
performance standards. These projects have been categorized and explicitly identify the needs and
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
24/85
2.0 Network Development Strategy
TRANSCO has over the years developed a modern and reliable transmission system making use of
best available technology to provide a high degree of energy security. TRANSCO aims to continue
to develop, operate and maintain a safe, flexible, accessible, robust, reliable, and efficient
transmission system that meets the needs of its customers in a manner consistent with its License
obligations. This is to be achieved through a structured asset management process that takes
cognizance of best practice asset management principles for the development and stewardship ofthe transmission network and requirements for capital assurance governance.
TRANSCOs power network development strategy for the period to 2030 provides a long-term
vision for taking the transmission system forward and provides direction to the 7YPS and its
associated investment plans. The strategy places much greater emphasis on the trends and drivers
which provides a long-term vision for taking the transmission system forward consistent with
Governments 2030 vision. The 7YPS describes more detailed short to medium-term plans for the
transmission system and is linked to the needs and investment requirements for the period 2012-
2018.
2.1 Challenges
Over the period to 2030 the development of the transmission system will face many challenges.
High levels of projected future demand growth along with changing customer and social needs that
influence the location and timing of demand development will require greater participation and
active engagement with customers. Meanwhile, there are uncertainties in the future primary
generation energy mix and associated demand-generation backgrounds. There is a need to manage
these uncertainties and reduce the risk in making investment decisions, while limiting if not
avoiding congestion on the transmission system. Efforts to mitigate the effects of global climate
change combined with a shortage of domestic gas will encourage promoting low-carbon and
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
25/85
operation and maintenance. All these require greater understanding and managing the technical
challenges, and thereby create opportunities for integrating new technologies, operation and
maintenance practices that are now available particularly in primary transmission equipment, and
information and communication technology.
2.2 Objectives
TRANSCO has two options to meet these challenges and fulfill the expectations of stakeholders. It
could either continue the development of the transmission network as is or adopt fresh thinking
and innovation. This requires a shared vision and strategic implementation plan to ensure the
aspirations of all stakeholders in the transmission system are met. The strategic plan presented in
this report adopts a holistic approach to the development and stewardship of the transmission
system with the aim of building sufficient flexibility and robustness into its future system
architecture to accommodate uncertainties.
The long-term network development strategy for the period to 2030 (20 years) aims to provide an
optimized vision for taking the transmission system forward that takes into account the
government objectives and policies, particularly those associated with the United Arab Emirates
(UAE) future social, environmental and economic requirements. The Abu Dhabi Economic Vision
2030 envisaged a real Gross Domestic Product (GDP) average target growth rate of about 6.4%
per annum for the period 2010-2030. The Abu Dhabi Urban Planning Council (UPC) developed
the Plan Abu Dhabi 2030-Urban Structure Framework Plan calibrated to achieve the target
population growth rate at about 4.8% for the period 2010-2030. The electricity transmission
infrastructure continues to be developed consistent with the above set policy targets among others
to support the future economic development of the Abu Dhabi Emirate.
The adopted transmission network development strategy along with the application of relevant
novel technologies will ensure achieving the following objectives:
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
26/85
Secure the domestic energy supplies to minimize vulnerabilities associated with unplanneddomestic system disruptions, import disruptions, and other crises.
Provide accessibility in granting connection access to all network users and benefits tocustomers at the earliest opportunity, particularly for renewable power sources and high
efficiency local generation with zero or low carbon emissions.
Reliable in assuring and improving the security of supply standards, transmission code andquality of supply to accommodate the customer requirements having different technical
characteristics.
Economical by providing the best value through innovation and efficient energy managementwhile supporting economic competitiveness and diversification by facilitating supply of
reasonably priced energy and tariff regulations.
Facilitate implementation of Abu Dhabi Water and Electricity Authority (ADWEA) DemandSide Management (DSM) program. This program presents policies, means and techniques to
achieve a scale of possible reduction of electricity demand keeping high standards of living and
customer satisfaction.
Flexible in fulfilling the customers needs and broader spectrum of stakeholders whilstresponding to the changes and challenges ahead.
Environmentally friendly and safe. Protect the environment by facilitating renewable andalternative energy technologies, mitigating the negative effects of traditional energy
production, and achieving increased energy efficiency among consumers within the Emirate.
The target renewable energy share is set at 7% by 2020.
Reduce uncertainty and risk to investment decisions.
Ensure end of life renewal of assets for sustainable operation of the grid.
2 3 Principle Long-Term Drivers and Trends
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
27/85
a) Electricity demand
Electricity is the critical enabler for the economic and social development of the UAE.Peak electricity demand (including supplies to Abu Dhabi Emirate and Northern Emirates) is
forecast to increase from 8.5GW (in 2010) to between 22.5GW-40.5GW by 2030 according to
ADWECs 2011 forecast update. Figure 2-1 shows the historical and future electricity demand
forecast up to 2030.
Figure 2-1 Historical and future electricity demand forecast
Source GDP data from Ministry of Economy Website (from 2001-2006) & Abu Dhabi EconomicVision 2030 (from 2006-2030). Demand data from ADWEC received in March 2011.
Th i i l d d d i i d t i l i g id ti l d i l
0
50
100
150
200
250
300
350
400
450
500
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030
Year
G D P - U
S $ b i l l i o n
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
P e a k
D e m a n
d ( G W )
Real GDP 38.5GW Scenario 22.5GW Scenario40.5GW Scenario 32.5GW Scenario
Real GDP Growth Rate
2000-2010: 11.4% (Actual)
2010-2030: 6.4%
ADWEC Demand Growth Rate
2000-2010: 9.8% (Actual)
2010-2030: 5% (for 22.5GW Scenario) 6.9% (for 32.5GW Scenario) 7.8% (for 38.5GW Scenario) 8.1% (for 40.5GW Scenario)
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
28/85
b) Regional and international grid interconnections
To support the Government of Abu Dhabi initiative to bolster the domestic energy security,TRANSCOs transmission system will increasingly integrate with Emirates National Grid (ENG)
and Gulf Cooperation Council (GCC) transmission system. Figure 2-2 shows the simplified high-
level grid interconnection arrangement (existing and current plans) with ENG/GCC grids.
Figure 2-2 Simplified high-level grid interconnection arrangement with ENG/GCC grids.
Potential maximum transfers between TRANSCO and regional/international grids under Secured
Existing 400kV GridsCommitted 400kV Grids
Sweihan
Warsan
Dhaid
Ras Al Khaimah
Shuweihat
To Salwa 400kV Grid Station
(KSA)
Sharjah
Qidfa
Sila
Al Wasit Area(Sultanate of Oman)
Ajman
New FujairahCity
Taweela
New 400kV Tower (double circuit)
T R A N S C O
T r a n s
m i s s i o n
N e t w o
r k
i n
A b u D
h a b i E m i r
a t e
Foah
Existing 220kV Grids
Existing 220kV Tower (double circuit)
400kV OHL Tower (double circuit)
Generation Site
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
29/85
170MW through the current existing Southern GCC 220kV interconnector between UAE-Oman. Maximum transfers are planned to be increased to about 1GW through the future
400kV interconnector between UAE-Oman.
2GW through the current existing ENG interconnections to Northern Emirates (i.e. through400kV interconnector between Taweela-Warsan, and 400kV interconnector between Fujairah
Qidfa-Sweihan) with possible range of exports.
These interconnections will not only enhance the security of supply but also reduce the spinning
reserve requirements and facilitate power exchange among member utilities and states, while
providing a mechanism to mitigate against gas supply shortages and uncertainty in the levels of
demand growth. It will also reduce plant procurement cost through achieving higher efficiency and
plant load factors apart from reducing the global operating costs of the integrated electricity
market.
c) Generation trends and energy storage
The production of electricity and the desalinated of water are dominated by large-scale operators
using conventional technologies such as gas turbines and thermal desalination. Figure 2-3 shows
the historical and future demand-generation trend upto 2030.
To support the Government objectives of achieving energy sufficiency, energy security, economic
diversification, and reduce the negative environmental impact of fossil fuel generation within the
Emirate, connection of essential new generation such as nuclear and renewable are planned which
have different technical characteristics to the current generation portfolio. Figure 2-4 shows the
existing and future potential generation site candidates and range of generation capacity assumed
at each of those sites.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
30/85
Figure 2-3 Demand-generation trends for the period 2000-2030
The target of the Governments objective is not to displace the existing or future fossil fuel plants,
but to supplement them with a diverse mix of technologies and fuel sources that make theelectricity sector less vulnerable to supply interruptions, market swings, and other crises while
creating the commercial impetus for the emergence of new technology-based clusters within the
local economy. This has required consideration of:
Committed new generation expansion projects.
ADWECs view on the future potential capacity and their potential site locations as outlined intheir 2011 Statement of Future Capacity Requirements.
Closures of some existing generating plants due to various legislation and age profile.
Policy drivers on renewable energy targets (objective is to drive towards establishing a 7%share of renewable energy by 2020) and demand side management initiatives
-5.0
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030
Year
G W
Installed Gen Capacity (Existing) Committed Gen Capacity Proposed Gen Retirement 22.5GW Scenario
32.5GW Scenario 38.5GW Scenario 40.5GW Scenario
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
31/85
Figure 2-4 Existing and future potential generation site candidates
d) Technological developments
Technologies such as higher rating overhead line conductors for increased power transfers,increased use of XLPE cables in areas of high amenity value at voltages up to 400kV, adoption of765kV or HVDC transmission voltage levels and the application of static and dynamic reactivepower compensators, while not necessarily all these new technologies require considerations in thetransmission system development.
Shuweihat
Umn Al Nar/SAS Al Nakheel
Masdar
Existing Fossil Fuel Power Plants
Future Potential Sites
Existing/Future Potential Renewables
Expected Retire
Gharbia (Western Region)1) Shuweihat (S1, S2) existing2) Shuweihat S3 - open cycle
3) Braka (NPP-1)4) North Braka (cogen/NPP)5) Mirfa (Combined/cogen)6) Madinat Zayed (Renewable)7) Sir Baniyas Island (Renewable)8) Sila (Renewable)
Eastern Region1) Taweela/TANE (Existing)2) Taweela-C (combined/cogen)3) SASN/UAN (Existing)4) UAN Re-development (open cycle)5) Masdar City (Renewable)
Northern Emirates1) Fujairah Qidfa (F1, F2) - Existing2) Fujairah F3 (cogen/open cycle)3) Ras Al Khaimah/Umn Al Quwain Border (cogen/NPP)4) Hamria (cogen/open cycle)
BrakaMirfa
Sir Baniyas Island
Madinat Zayed
North Braka
Fujairah Qidfa
Ras Al Khaimah
Taweela
SASN/UAN
Al-Ain Power Station
Sweihan
Sanaiya/Maziyad
Al-Ain Region1) Al-Ain P.S (Renewable)2) Sanaiya/Maziyad (Renewable)
3) Sweihan (Fossil fuel/Renewable)
Combination of generationsite candidates provides
~ 42.5GW capacity
Sila
40-100MW 50-200MW
100-700MW
0-500MW
0-700MW
100-350MW
0-350MW
4.65-6.75GW
1.65-2.43GW
4.89GW
0-5.6GW
5.6-11.2GW
2.97-4.27G
0-5.6GW
0-3.6GW
Hamria
0-3.3GW
0-1GW
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
32/85
of smart meters in the selective areas of the distribution network within the Abu Dhabi Emirate
have been considered.
From a transmission perspective, the smart grid components could essentially include and integrate
synchrophasor measurement, intelligent protection schemes, power flow control, static var
compensation, real time monitoring, energy storage management and solar/wind forecasting tools,
advanced metering (AMR), demand response, energy storage devices, condition monitoring,
control and decision support systems. These requires massive changes in the electrical system and
the way it should be structured and operated, which has the potential to create a new system
architecture.
e) System operation and despatch
The generation mix and demand side technologies along with the changes expected in the loadduration curve due to high industrial demand growth and export requirements will required to be
considered. These are likely to alter the summer-winter peak demand ratio to about 40% and
system load factor to about 70% by 2020. The impact of these changes, particularly the need to
take into account the inter-relationship between power and water production, could lead to the
need to introduce other methods of water production such as reverse osmosis (RO) and
opportunities for energy storage. As a result the intermittency and non-despatchable plant
characteristics of wind and solar generation, and plans to despatch nuclear plant as base load
and/or introduce degree of flexibility in their operation needs to be considered.
f) Asset management
While the transmission network is comparatively young, there will be requirements for assets
approaching the end of their useful lives to be managed and replaced at an appropriate time. AssetManagement process improvements will be required to capture the knowledge to build only what
is needed. Integrated outage management and risk assessment need to be considered for improved
operational efficiency. Maintenance practices and resource management processes shall be
d d d i i l b i i h i i k f 20
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
33/85
g) Standards and procedures
The evolution of bulk transmission network over the period to 2030 requires review of standardsand procedures related to the network operation and despatch that needs to address:
System complexity as the network develops to meet the demand requirements of 2030.
Operational connection topology to manage fault levels within acceptable limits.
Levels of security (infeed risk), power factor, reactive power management, stability including
fault ride through and frequency response, and spinning reserve issues. Power quality requirements of customers and sensitive loads.
2.4 Approach to Developing the Main Bulk Transmission System
The requirements for the transmission system development and its associated investments areprimarily driven by the demand and generation backgrounds and the resulting power transfers onthe transmission system. There are uncertainties associated with the demand and generationbackgrounds as with any forecasts and plans. These uncertainties will affect future planned powertransfers on the transmission system and hence the way the transmission system develops.
To manage the uncertainties, the approach adopted in this strategy is based on the scenario
analysis taking into account the sensitivities, constraints and risks through considering:
Different demand forecast scenarios in the range 22.5GW-40.5GW by 2030.
Considering different locational development of demand including different levels of transfersto the Northern Emirates.
Different locational development of generation to meet the above demands.
Using the scenarios developed, the planned power transfers on the transmission system are
established for various demand generation scenarios Given the differences in scenarios envelopes
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
34/85
Figure 2-5 Representative example of most likely boundary transfers across West-East corridor
Figure 2-6 shows the envelope of possible transfers and the best-view planned transfers across the
five identified boundary corridors for the peak demand-generation background during the period
2010-2030. It also shows the transfer capability (represented in blue text) across the identifiedboundary corridors for the peak demand-generation background in 2010.
Gharbia-Eastern Region boundary
0
2000
4000
6000
8000
10000
12000
14000
16000
2010 2015 2020 2025 2030
Year
M W
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
35/85
Figure 2-6 Envelope of possible transfers and best-view planned transfers by 2030
Bulk transmission system options centred on 400kV, 765kV and HVDC technologies have been
explored to meet the system needs for the range of planned transfer requirements. Figure 2-7
-2,000
-1,000
0
1,000
2,000
3,000
4,000
5,000
6,000
2010 2015 2020 2025 2030
B o u n d a r y
T r a n s
f e r s
( M W )
~8GW(~1.8GW)
~5GW(~2.2GW)
~3.5GW(~2GW)
~1.5GW(~3.2GW)
~2GW(~0.3GW)
Best-view planned transfers in 2030
Gharbia region
N o r t h e r
n E m i
r a t e s
Abu DhabiIslands
Eastern region
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
2010 2015 2020 2025 2030
B o u n d a r y
T r a n s f e r s
( M W )
0
1,000
2,000
3,000
4,000
5,000
2010 2015 2020 2025 2030
B o u n d a r y T r a n s f e r s ( M W )
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
2010 2015 2020 2025 2030
B o u n d a r y T r a n s f e r s ( M W )
-4,000
-3,000
-2,000
-1,000
0
1,000
2,000
3,000
4,000
5,000
2010 2015 2020 2025 2030
B o u n d a r y
T r a n s
f e r s
( M W )
-2,000
-1,000
0
1,000
2,000
3,000
4,000
5,000
6,000
2010 2015 2020 2025 2030
B o u n d a r y
T r a n s
f e r s
( M W )
Transfer capability in 2010
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
36/85
Figure 2-7 Main options for bulk transmission system development.
400kV is chosen as the most likely transmission system option to ensure that the investments are
economical and efficient and that those Users connecting to the system can reasonably identify and
evaluate opportunities. As there will continue to be a degree of uncertainty in the realization of the
volume, location and timing of demand and generation backgrounds in any given area, it is
proposed to continue monitor the developments of the market and update the scenarios
accordingly. Hence, the potential transmission reinforcement plans shall be established in a phased
manner and that the options are maintained at minimum cost to provide a least regret solution.
It should be noted that the 400kV transmission reinforcements associated with the 1 st and 2 nd Braka
nuclear units are able to exploit the synergies with the committed transmission network associated
with Shuweihat S3 generation integration. Migration to 765kVAC or HVDC as the main overlay
i i i h i i 400kV k h W E id i
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
37/85
In developing the transmission system, considerations have also been given to the increasing
requirements for renewal of existing assets in the period to 2030.
2.5 Network Development Strategy
TRANSCOs network development strategy is to continue to develop a flexible, reliable, secure,
accessible, robust, economical, efficient, environmentally friendly and safe transmission system
that meets the needs of its customers in a manner consistent with its Licence obligations.
This is achieved through:
Implementing a structured asset management process that takes cognizance of best practiceasset management principles for the development and stewardship of the transmission network
and requirements for capital assurance governance.
Continuing with the development of 400kV main bulk transmission system. Given theuncertainty in the demand and generation background, the possible need to migrate to 765kV
or HVDC as the main overlay transmission system option across the West-East corridor is to
be kept under review, particularly if significant level of additional generation capacity beyond
Shuweihat S3 and Braka nuclear plant are contracted in the Western region, and that there is
increased requirement to provide power to Northern Emirates.
Incremental deployment and integration of new technologies and best available practice.
It is intended that the development of the transmission network will be done in such a manner to:
Have minimum negative side-effects on the environment and society.
Accommodate large central and decentralized generation and storage.
Enable active participation of consumers including demand response.
Provide high quality of supply and reliable power that satisfy the expectation and needs of thecustomer and comply with international best practice and standards.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
38/85
Figure 2-8 shows the expected 400kV transmission system configuration by 2030.
Figure 2-8 Expected 400kV transmission system configuration by 2030.
2025 Best View (30GW)
Al-AinSouth West
Dahma
Sweihan
Mussafah
Shahama
Warsan
Dhaid
Ras AlKhaimah
To Salwa 400kVGrid Station
(KSA)
Sharjah
SASN
Taweelah
Qidfa
Sila
ICAD
MahawiBahia
Al Wasit Area(Sultanate of Oman)Shamkha
Hameem
Al-Ain Airport
Ajman
New FujairahCity
MirfaWathba
SAS Al NakheelBeach
Al Qurm
ADST
ReemSadiyat
Bahia
ZayedSports City
Braka
400kV grid station
400kV Tower (double circuit)
400kV CableSingle Circuit
Single 400kVOverhead Line Circuit
400kV grid station associated with Power Plant
Madinat Zayed
Bab
ChemaWEyaat
Shuweihat
Ruwais
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
39/85
3.0 Planning Principles
The Electricity Transmission System Security Standard, Issue 1, Rev (0) dated March 2005 sets
out the criteria and methodology, which TRANSCO shall use in the planning, development,
operation and maintenance of the electricity transmission system. The Electricity Transmission
Code (Ver.1, Rev.3, issued in September 2006) contains additional criteria and other aspects of
quality of supply standards that shall be considered for planning the transmission network. A
summary of the planning principles are discussed below;
3.1 General Criteria
The following general criteria are adopted for network planning and development;
Electricity transmission system shall be planned to comply with N-1 criteria.
400kV overhead line system feeding Abu Dhabi Island shall comply with N-2. Electrical and thermal ratings of the equipment shall NOT be exceeded.
Power system shall remain stable with respect to voltage and frequency control undernormal and secured outage conditions.
Power system shall be developed in an efficient and economical manner.
Acceptable safety standards shall be maintained.
Both the Electricity Transmission System Security of Supply Standard and the Electricity
Transmission Code are under review. However, for the purposes of this Seven Year Electricity
Planning Statement, 400kV overhead line circuits planned to be connected to Nuclear Power
Station shall meet N-Tower criteria (i.e. for tower failure).
3.2 Connection Conditions
TRANSCO and Users connected to the Transmission System (Gencos, Discos and Non-Embedded
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
40/85
connections, main interconnected transmission topology and demand connections shall satisfy the
deterministic criteria specified in the Security Standards.
Frequency Deviation
The System Frequency of the Transmission System shall be nominal 50Hz with System Frequency
set points between 49.95Hz 50.05Hz and shall be controlled within the limits of 49.9Hz
50.1Hz unless exceptional circumstances prevail.
Under transient disturbed conditions, System Frequency could rise to 53Hz or fall to 47Hz.
However, under disturbed steady-state conditions, System Frequency will NOT exceed 51.5Hz or
fall below 48.5Hz.
Voltage Variation
The voltage on the 400kV, 220kV and 132kV parts of the Transmission System at each
Connection Site with the User will normally remain within 5% of the nominal value. The
minimum voltage is -10% and the maximum voltage are +10%; but voltages between +5% and
+10% will not last longer than 15 minutes unless abnormal conditions prevail.
The voltage on the 33kV and 11kV parts of the Distribution System will normally remain within
6% of the nominal value unless abnormal conditions prevail.
Harmonic Distortion
The Compatibility/Planning Levels for harmonic distortion on the Transmission System from all
sources under both Planned Outage and fault outage conditions (unless abnormal conditions
prevail) shall comply with the levels shown in Appendix-F of the Electricity Transmission Code.
TRANSCO apply the Planning Levels to the connection of non-linear loads to the Transmission
System, which may result in harmonic emission limits being specified in the relevant ConnectionAgreement. The Total Harmonic Distortion (THD) for Planning and Compatibility Levels shall not
exceed the limits shown in the Table 3-1 below;
Table 3-1 Planning Levels for Total Harmonic Distortion
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
41/85
Phase Unbalance
Under Planned Outage conditions, the maximum negative phase sequence component of the phase
voltage on the Transmission System should remain below 1% unless abnormal conditions prevail.
Voltage Fluctuations
Voltage fluctuations at a Point of Common Coupling (PCC) with a fluctuating Load directly
connected to the Transmission System shall NOT exceed;
1% of voltage level for step changes which may occur repetitively. Any large voltageexcursions other than step changes may be allowed up to 3% provided this does not
constitute a risk to the Transmission System or in TRANSCOs view to the System of any
User.
Flicker Severity (Short Term) of 0.8 Unit and a Flicker Severity (Long Term) of 0.6 Unit,as set out in IEC 61000-3-7 Standard.
Demand Power Factor
Demand power factor shall NOT be less than 0.91 lag at 33kV and 11kV connection points
between TRANSCO and Distribution Companies.
3.3 Generation Connection Criteria
The generation connections shall satisfy deterministic criteria comprising of the following;
a) Criteria which determine the maximum Normal and Infrequent Infeed Loss Risk for a set of
Secured Events .
For network design and planning purposes the level of these limits are 400MW and 800MW
respectively. These limits are currently under review and expected to be increased to take into
account the changes in the power network e.g. interconnection with ENG/GCC and Nuclear Plants.
The review will be undertaken after validating and updating the plants dynamic models (governor,
exciter, PSS models). The Normal Infeed Loss Risk limit aims to ensure that the system frequency
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
42/85
b) Criteria which determine Transmission Capacity require avoiding un-acceptable network
conditions for a set of Secured Events .
In either case, prior to any fault or Secured Events , the Transmission Capacity for the
connection to the Power Station should be planned such that the following conditions shall NOT
prevail;
Loss of Supply Capacity (valid only for the Secured Event of fault outage except aspermitted by the Demand Connection Criteria).
Primary equipment loading exceeding normal rating.
Voltage outside the pre-fault planning voltage limits or insufficient voltage performancemargins; or
System instability.
Secured Events could be a fault outage of a single transmission circuit or reactive element, outageof busbar section or outage of a single transmission circuit with planned outage of another
transmission circuit, a Generating Unit or reactive element.
3.4 Main Interconnected Transmission System (MITS) criteria
The Minimum Transmission Capacity requirements for the Main Interconnected Transmission
System (MITS) shall satisfy deterministic criteria and shall be planned such that prior to any fault
or Secured Events , the following conditions shall NOT prevail;
Loss of Supply Capacity (valid only for Secured Event of fault outage except as permitted bythe Demand Connection Criteria).
Primary equipment loading exceeding normal rating. Voltage outside the pre-fault planning voltage limits or insufficient voltage performance
margins; or
System instability.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
43/85
3.5 Demand Connection Criteria
The planning of demand connections (132/11kV substations or 220/33kV substations) to thetransmission system shall satisfy deterministic criteria and there should be NO loss of supply
capacity for the Group Demand following Secured Events as illustrated in Table 3-2.
Table 3-2 Planning supply capacity following Secured Events
Initial System ConditionsGroup Demand
(MW) Intact System With Single Arranged Outage
Over 150MWImmediately [1]
Group Demand
Immediately [1]
Maintenance Period Demand
27MW-150MWImmediately [1]
Group Demand
5 minutes [2]
Maintenance Period Demand
Up to 27MW Subject to Discos system security criteriaSubject to Discos system securitycriteria
Notes:
[1] Loss of supply not exceeding 5 minutes may be acceptable if leads to significant economies.
[2] For sites where economies prohibit the provision of a third Transmission Circuit, the
Maintenance Group Demand may be lost for the necessary time to restore outage.
Secured Events could be a fault outage of a single transmission circuit under Intact System; or
outage of a single transmission circuit with planned outage of another transmission circuit, a
Generating Unit or reactive element.
Maintenance Period is the period of the Year (November to April) during which maintenance oftransmission equipment is normally undertaken. Maintenance Period Demand is the demand level
experienced at a Demand Supply Point and is the maximum demand level expected during the
normal maintenance period. Unless better data is available, this should be 50% of the Group
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
44/85
4.0 Demand-Generation Background
The Sector Law requires ADWEC to prepare a demand forecast and accordingly secure the future
generation capacity to meet the short and long-term requirements of the Sector. The requirement
for the transmission system development and its associated investments is primarily driven by the
demand and generation backgrounds. In this chapter, the demand-generation trends and the choice
of the key assumptions are summarized. Based on the electrical connectivity and geographical
dispersion, the capacity and demand forecast at each part of the transmission network are
highlighted.
4.1 Demand Background
In 2010 the total system peak demand recorded was about 8.5GW, which included supplies to theAbu Dhabi Emirate and the Northern Emirates. Historically, the electricity peak demand sustained
an average growth of 9.8% for the period 2000-2010. The average peak demand growth for the
Abu Dhabi Emirate was 7.8% for the same period. In 2006 TRANSCO established interconnection
with Emirates National Grid (ENG) with the intention of supporting the member utilities of the
UAE.
Global peak electricity demand (include supplies to Abu Dhabi Emirate and Northern Emirates) is
forecast to increase to between 16GW and 24GW by 2018 according to ADWECs 2011 forecast
update. This represents an average growth rate of about 9% and 16% per annum for the period
2010-2018 related to the two demand forecasts. For the purpose of preparing this 7YPS an
intermediate demand level of about 20GW by 2018 is also considered. This together with the
generation background described in the next Section is consistent with the best-view long-termtransfers established in the network development strategy.
In developing the demand forecast the updated Users demand forecast data demand notifications
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
45/85
The principle demand drivers are industrial, residential and commercial development expansions;
and export supplies to Northern Emirates. The proportion of industrial demand relative to peak
demand is forecast to increase as the UAE diversifies its economy and there is the potential for
variations of the locational development of demand within the outlier demand scenario.
The 7YPS looks at 16GW, 20GW intermediate and 24GW demand scenarios. Attachment-A
include detailed summary and area-wise/zone-wise demand forecast for the 16GW, 20GW
intermediate and 24GW demand scenarios; expected capacity and peak demand forecast at the exitdemand supply points for the period 2010-2018.
Attachment-A includes summary of region-wise peak demand forecast for 16GW, 20GW
intermediate and 24GW demand scenario (Table-A1). Area-wise/zone-wise detailed demand
forecast for the three demand scenarios is included in Table A2. The expected capacity and peak
demand forecast at the exit demand supply points in Abu Dhabi Emirate for the period 2010-2018
for 16GW and 24GW demand scenario is included in Table-A3 and Table-A4 respectively.
For the 20GW intermediate scenario, the global peak electricity demand (Abu Dhabi Emirate and
Northern Emirates) is expected to reach about 20GW in 2018 representing an average growth rate
of about 13% for the period 2010-2018. Figure 4-1 shows the region-wise demand forecast for the
20GW intermediate scenario. Table 4-1 shows the detailed break-up of region-wise demand
forecast for the 20GW intermediate scenario.
The expected capacity and peak demand forecast at the exit demand supply points in Abu Dhabi
Emirate for the period 2010-2018 for 20GW demand scenario is included in the Attachment (refer
Table-A6).
The expected capacity and peak demand forecast at the 400kV grid supply points in Northern
Emirates for the period 2010-2018 for 20GW demand scenario is included in the Attachment (refer
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
46/85
Figure 4-1 Region-wise demand forecast for 20GW intermediate scenario.
8,485
9,845
11,167
13,436
14,730
16,85117,582
18,783
20,046
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000
22,000
24,000
2010 2011 2012 2013 2014 2015 2016 2017 2018
Year
P e a k
D e m a n
d ( M W )
Abu Dhabi Islands' Eastern Region
Gharbia (Western) Region Al-Ain RegionNorthern Emirates Incl. Water Pump & Aux. Loads Auxiliary & Desalination Process Loads in AD EmirateTransmission Losses Coincident Total System Peak
Growth Rate (2010-2018)
System (AD+NE) = 13.1%; Abu Dhabi Emirate = 11.9%
Abu Dhabi Islands' = 7.8%; Eastern Region = 15.7%
Gharbia Region = 24.4%; Al-Ain Region = 6.3%
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
47/85
Table 4-1 Region-wise demand forecast for the 20GW intermediate scenario.
a) Demand developments in Northern Emirates
The supply requirements of the Northern Emirate are expected to exceed 2.5GW in the short-term
and could possibly reach about 5GW by 2018. Existing and on-going main bulk 400kV
transmission development works in Northern Emirates (in Fujairah, Ajman, Sharjah) will enablesecuring the above supplies and meet the rise in electricity demand in the regions. These
development works will not only contribute to the Abu Dhabis continued support to the energy
requirements of the Northern Emirates but also will improve the overall security of the ENG grid
d d th i k t th TRANSCO f h t d/ t k it i i th N th
1, 1, 1 2,0 2,23 2,3 2,4 2 2, 2, 3 3,031
1, 14 2,12 2, 4 2, 11 3,13 3, 4,1 4, 30 ,02
1,031 1,24 1, 10 2,2 2, 2, 40 2, 0 3,030
1, 4 1, 3 2,000 2,0 4 2,1 2 2,24 2,3 0 2,421 2, 22
, 0 , , , 4 , 11,4 4 12,041 12, 13, 11
0 0 0 1 40 40 0 1,0
, , , , 34 10, 1 12,3 4 12, 1 13, 14,
1,44 1, 00 2,100 3,324 3,420 3, 0 3, 4,23 4,4 0
2 0 2 2 323 33 4 0 4 0 4 0 4 0
1, 1 1, 2,3 3, 4 3, 4,240 4,34 4, 4, 30
104 104 123 1 1 4 21 2 2 342 430
, , , , , , , , ,
( )
( )
)
& ( )
2) & . ( )
)
1)
( )
) ( )
1) ( )
1 ( )
2)
3) ( )
4)
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
48/85
b) Demand developments in Industrial Zones
Expansion of the oil and gas sector and their increasing reliance upon the utility grid for its
electricity requirements has directly attributed to the significant demand growth in the Gharbia
(Western) region. The growth of oil and gas sector has significant long-term macro-economic
impact on the economy of Abu Dhabi Emirate. The supply requirements of all Abu Dhabi National
Oil Company (ADNOC) group projects located in the Gharbia region is expected to exceed
2GW by 2018.
Development of heavy industrial zones is another important driver contributing to the significant
demand growth. These include developments of the Mussafah Steel Plant in Mussafah/ICAD-1
area, Industrial City of Abu Dhabi (ICAD) in ICAD area, Khalifa Port and Industrial Zone (KPIZ)
in the Taweela area, and ChemaWEyaats Chemical Industrial City in the RUWAIS area. The
supply requirements of these industrial zones and other light industries in Abu Dhabi Emirate are
expected to exceed 1.5GW by 2018.
For the TRANSCOs best-view planned transfers, the cumulative demand requirements of
ADNOC group projects, heavy and light industrial demand categories is expected to reach about
4.4GW which represents about 22% of the total electricity demand by 2018. The existing and on-
going transmission development works in RUWAIS, BAB, SHAH/ASAB, and ICAD among othersites is expected to secure the above supplies to meet the short and long-term requirements in the
respective regions.
c) Demand developments in Abu Dhabi Islands, Eastern and Al-Ain regions
New residential and commercial developments in Abu Dhabi islands and Eastern region; and
developments in Al-Ain region are expected to contribute to the cumulative electricity demand
growth of Abu Dhabi Emirate within next few years. The existing and planned transmission
development works are expected to secure the supplies in the above regions.
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
49/85
The residential and commercial developments in Eastern region are concentrated in Yas island,
Raha Beach, Bahia, Mahawi, and Shamkha regions. For the TRANSCOs best-view planned
transfers, the cumulative demand requirement of Eastern region (excluding industrial demandcategory) is expected to reach about 2.8GW which represents about 14% of the total electricity
demand by 2018.
The developments in Al-Ain region are concentrated in Sweihan, Dahma, and Al-Ain South West
zones. For the TRANSCOs best-view planned transfers, the cumulative demand requirement of
Al-Ain region is expected to reach about 2.5GW which represents about 12.5% of the total
electricity demand by 2018.
4.2 Generation Background
The production of electricity and the desalinated water are dominated by the large-scale operators
using conventional technologies such as gas turbines and thermal desalination. To meet the above-
mentioned demand background, the existing power generation plants contribute about 12GW (as
on 2010) of capacity. The following are the major new committed generation projects identified to
date which are expected to be integrated into the main bulk transmission grid during the period
2011-2020:
Shuweihat S2 (~1.62GW) and Shuweihat S3 (~1.65GW) combined cycle fossil fuel plantslocated adjacent to the existing Shuweihat S1 site in the Al Gharbia region.
Shuweihat S2 is integrated to transmission network and operational in 2011.
The Braka site in the Gharbia region has been identified to promote nuclear generation of totalcapacity 5.6GW by 2020. Generator units of 1400MWe are expected to be integrated to the
transmission system.
A number of committed renewable generation projects have also been identified to date and these
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
50/85
The above generation projects contribute an additional capacity of about 9.5GW by 2020, among
other potential new generation additions (e.g. relocation of Al Zawra gas turbines to Mirfa site,
Masdar hydrogen plant at Shuweihat).
To satisfy the emerging gap between the demand and generation outlook, and ensure sufficient
generation margin is available from 2013, following assumptions have been considered in line
with the 2011 ADWEC Statement of Future Capacity Requirements:
Procuring IWPP peak capacity in excess of PWPA contracted capacity to the extent of about200MW for the period 2013-2016.
Availability of FEWA reserve stand-by capacity to the extent of about 700MW for the period2013-2016.
It should be recognized that the actual commitment to the new conventional generation capacity
takes place on a shorter time scale (about 4 years) to close the emerging gap. Figure 4-2 shows the
demand-generation background for the period 2010-2018. Attachment-A (Table-A8) includes the
detailed summary of generation capacity expansion plan assumed for the TRANSCOs best-view
planned transfers for the period 2010-2018.
10
15
20
25
30
G W
Installed Gen Capacity (Existing) Committed Gen Capacity 22.5GW Scenario (16GW by 2018)
32.5GW Sce nario (18. 5GW by 2018) 20GW Intermediate Scena rio (20GW by 2018) 38.5GW Scenario (24GW by 2018)
Global demand growth rate (2010-2018)
ADWEC's 22.5GW scenario = 9.2%
ADWEC's 32.5GW scenario = 11.9%
20GW Intermediate scenario = 13.1%
ADWEC's 38.5GW scenario = 16.1%
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
51/85
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
52/85
5.0 Planned Transfers
The requirements for the transmission system development and its associated investments are
primarily driven by the demand and generation backgrounds and the resulting power transfers on
the transmission system. There are uncertainties associated with the demand and generation
backgrounds as with any forecasts and plans. These uncertainties will affect future planned power
transfers on the transmission system and hence the way the transmission system develops. Using
the scenarios developed, the planned power transfers on the transmission system are established
for the most probable demand-generation scenarios envisaged during the period 2010-2018 and
ensure consistency with the long-term approach. Envelopes of possible transfers are established
and the most likely (best-view) planned power transfers are identified across each of the
transmission corridors that is used as a basis to inform how best to develop the transmission
system. The approach adopted in the 7YPS in establishing the envelope of possible transfers and
planned transfers taking into account the following considerations:
Different demand forecast scenarios namely 22.5GW scenario (i.e. 16GW by 2018),intermediate scenario (i.e. 20GW by 2018) and 38.5GW scenario (i.e. 24GW by 2018).
Different locational development of next possible generation (Mirfa, Taweela-C, Hamria) tomeet the above demands from 2014/2015 through to 2018 after Shuweihat S3 generation.
Figure 5-1 shows the envelope of possible transfers and the best-view planned transfers across the
five identified boundary corridors for the peak demand-generation background during the period
2010-2018. It also shows the transfer capability (represented in blue text) across the identified
boundary corridors for the peak demand-generation background in 2010.
The main features of the fan diagrams across the five identified boundary corridors are:
a) The transfers across the Gharbia-Eastern region corridor are the sum of the transfers from theGharbia region to the Eastern region and from the Gharbia region to Al-Ain region. During the
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
53/85
Figure 5-1 Envelope of possible transfers and best-view planned transfers for period 2010-2018
b) The transfers across the Northern Emirates-other regions corridor are the sum of the transfers
-2,000
-1,000
0
1,000
2,000
3,000
4,000
5,000
6,000
2010 2015 2020 2025 2030
B o u n d a r y
T r a n s
f e r s
( M W )
-2,000
-1,000
0
1,000
2,000
3,000
4,000
5,000
6,000
2010 2012 2014 2016 2018
A l - A i n
r e g i o
n
N o r t h
e r n E m
i r a t e s
-2,000
-1,000
0
1,000
2,000
2010 2012 2014 2016 2018
B o u n d a r y
T r a n s
f e r s
( M W )
-1,000
0
1,000
2,000
3,000
4,000
5,000
2010 2012 2014 2016 2018
B o u n d a r y T r a n s f e r s ( M W )
0
2,000
4,000
6,000
8,000
2010 2012 2014 2016 2018
B o u n d a r y
T r a n s
f e r s
( M W )
0
1,000
2,000
3,000
4,000
2010 2012 2014 2016 2018
B o u n d a r y T r a n s f e r s ( M W )
0
1,000
2,000
3,000
4,000
5,000
2010 2012 2014 2016 2018
B o u n d a r y
T r a n s
f e r s
( M W )
8/11/2019 Seven Year Electricity Planning Statement-Main-report (1)
54/85
c) The transfers across the Eastern region-other regions include transfers from the Eastern regionto Abu Dhabi Islands, plus Eastern region to Al-Ain region, minus Gharbia region to Eastern
region, minus Northern Emirates to Eastern region. During the period 2010-2018, the most
likely demand in the Eastern region is expected to increase from 2.5GW to about 6GW. The
scheduled generation in the region is assumed to rise significantly from 5GW to about 8GW.
Consequently, the best-view planned transfer across this boundary is expected to increase to
2GW in 2018.
d) The transfers