25
Sharing The Big Risk: An Assessment Framework for Revenue Risk 1 Sharing Mechanisms in Transportation Public-Private Partnerships 2 Ting Liu 1,2 , Michael Bennon 3 , Michael Garvin 4 , Shouqing Wang 5 3 1. Ph.D. Candidate, Department of Construction ManagementHang Lung Center for Real EstateTsinghua 4 UniversityBeijing 100084China 5 2. Joint-supervised Ph.D. Candidate, Stanford Global Project Center, Stanford University, CA94306, United 6 States 7 3. MBA/MSc, Stanford Global Project Center, Stanford University, CA94306, United States 8 4. Ph.D., Department of Civil and Environmental Engineering, Virginia Tech, VA24061, United States 9 5. Ph.D., Department of Construction ManagementHang Lung Center for Real EstateTsinghua University10 Beijing 100084China 11 Abstract: A number of toll roads delivered via PPPs have encountered financial distress due to 12 revenue risk with traffic levels significantly lower than those forecasts in recent years. As a result, 13 there has been a shift in PPP road procurements to models in which the government retains some or 14 all of the demand risk for the project, instead of the concessionaire. A tangible framework to guide 15 governments’ decisions in choosing among financial support mechanisms in allocating revenue 16 risks is thus a relevant development for policymakers. This paper proposes a framework to 17 evaluate fiscal support alternatives by comparing the marginal leverage they enable a project to 18 take and the level of financial exposure they allocate to the procuring government. A quantitative 19 methodology is developed that defines inputs and measurable indicators, and also incorporates 20 stochastic modeling and simulation techniques designed for use at an early stage of project 21 planning. The results of a numerical case study demonstrate that flexible term procurement does 22 little to increase project leverage, minimum revenue guarantee is most applicable to projects with 23 significant revenue volatility, while availability payment procurement is more applicable to 24 projects that are projected to have a lower volatility and lower mean revenue relative to their 25 capital investment. 26 Key words: Public-Private Partnerships (PPPs); toll road; revenue risk; government financial 27 support; borrowing capacity; value at risk 28 1. Introduction 29 As an alternative approach to traditional public procurement, Public-Private Partnerships (PPPs) 30 have been increasingly adopted by governments globally to procure infrastructure based on the 31 complete life-cycle costs of developing and maintaining the asset, and to transfer the risks 32 associated with complex infrastructure project development and operation to the private sector. 33 In the US, highways have been, to date, the predominant sector in which PPPs have been used to 34 develop new infrastructure, and prevailing PPP model used is the toll/revenue risk concession. 35 This is in part due to the fact that they are often large, complex projects but also because they are 36 funded through user-fees and entail significant risk in assessing the future demand and toll revenue 37

Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

Sharing The Big Risk: An Assessment Framework for Revenue Risk 1

Sharing Mechanisms in Transportation Public-Private Partnerships 2

Ting Liu1,2, Michael Bennon3, Michael Garvin4, Shouqing Wang5 3

1. Ph.D. Candidate, Department of Construction Management,Hang Lung Center for Real Estate,Tsinghua 4

University,Beijing 100084,China 5

2. Joint-supervised Ph.D. Candidate, Stanford Global Project Center, Stanford University, CA94306, United 6

States 7

3. MBA/MSc, Stanford Global Project Center, Stanford University, CA94306, United States 8

4. Ph.D., Department of Civil and Environmental Engineering, Virginia Tech, VA24061, United States 9

5. Ph.D., Department of Construction Management,Hang Lung Center for Real Estate,Tsinghua University,10

Beijing 100084,China 11

Abstract: A number of toll roads delivered via PPPs have encountered financial distress due to 12

revenue risk with traffic levels significantly lower than those forecasts in recent years. As a result, 13

there has been a shift in PPP road procurements to models in which the government retains some or 14

all of the demand risk for the project, instead of the concessionaire. A tangible framework to guide 15

governments’ decisions in choosing among financial support mechanisms in allocating revenue 16

risks is thus a relevant development for policymakers. This paper proposes a framework to 17

evaluate fiscal support alternatives by comparing the marginal leverage they enable a project to 18

take and the level of financial exposure they allocate to the procuring government. A quantitative 19

methodology is developed that defines inputs and measurable indicators, and also incorporates 20

stochastic modeling and simulation techniques designed for use at an early stage of project 21

planning. The results of a numerical case study demonstrate that flexible term procurement does 22

little to increase project leverage, minimum revenue guarantee is most applicable to projects with 23

significant revenue volatility, while availability payment procurement is more applicable to 24

projects that are projected to have a lower volatility and lower mean revenue relative to their 25

capital investment. 26

Key words: Public-Private Partnerships (PPPs); toll road; revenue risk; government financial 27

support; borrowing capacity; value at risk 28

1. Introduction 29

As an alternative approach to traditional public procurement, Public-Private Partnerships (PPPs) 30

have been increasingly adopted by governments globally to procure infrastructure based on the 31

complete life-cycle costs of developing and maintaining the asset, and to transfer the risks 32

associated with complex infrastructure project development and operation to the private sector. 33

In the US, highways have been, to date, the predominant sector in which PPPs have been used to 34

develop new infrastructure, and prevailing PPP model used is the toll/revenue risk concession. 35

This is in part due to the fact that they are often large, complex projects but also because they are 36

funded through user-fees and entail significant risk in assessing the future demand and toll revenue 37

Page 2: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

to support the project. These factors, and federal support programs for the PPP model, have made 38

toll roads an ideal sector for P3s in the US. However, in recent years, predominantly in the wake of 39

the global financial crisis, many toll roads delivered via PPPs have encountered financial distress. 40

Notable recent PPP bankruptcies include I-185 in South Carolina, SR125 in California, and SH130 41

in Texas, among several others. In these and other recent toll road bankruptcies one factor has 42

been cited as a predominant cause: traffic levels significantly lower than that forecast for the 43

project (See “First Amended Disclosure Statement to First Amended Plan for Adjustment of Debt 44

of I-185”, “Drop in Traffic Takes Toll on Investors in Private Roads” on the Wall Street Journal, 45

etc.). 46

Revenue risk for a toll road is the risk that low traffic levels will cause project revenue to be 47

insufficient to service the operation and maintenance costs, the debt, and the adequate rate of 48

investor return (Chiara, Garvin et al. 2007). Since the majority of toll revenue will be used in debt 49

and equity service, concession contracts with private financing are naturally very sensitive to 50

fluctuations in demand (Charoenpornpattana, Minato et al. 2002). Retrospective studies illustrate 51

that many renegotiations and cancellations of transportation projects with private participation like 52

trains and toll roads take place due to revenue risks (Guasch 2000, Charoenpornpattana, Minato et 53

al. 2002, Guasch, Laffont et al. 2003, Harris, Hodges et al. 2003). 54

Intuitively, demand for a toll road, like other critical infrastructure services, can be expected to be 55

relatively inelastic. However, this varies significantly based on the asset itself and nearby free 56

alternatives. In addition, the vast majority of toll road concessions in the US naturally include a set 57

or maximum toll schedule, so concessionaires are unable to simply adjust tolls as they see fit. In 58

addition, traffic demand in the years following the global financial crisis demonstrated that toll 59

road demand is more closely correlated to broader economic conditions than expected by many 60

investors before the recession (Bain 2009). Therefore, revenue risk is beyond concessionaires’ 61

control and thus it should not be fully allocated to concessionaires. 62

Revenue Risk for toll roads and other transportation infrastructure has also been shown to not 63

necessarily be normally distributed. A sample of 210 transportation projects in 14 nations shows 64

that traffic forecasts are so inaccurate that 90% of rail projects are overestimated by 106% on 65

average, 50% of road projects have forecast errors larger than ±20%, and forecasts have not become 66

more accurate over time (Flyvbjerg, Skamris Holm et al. 2005). Those studies show that the 67

majority of demand forecasts are not just wrong – they are more often than not too high. There are 68

several potential causes of this trend, perhaps most notably the general if not explicit pressure in 69

early stage project planning to make favorable assumptions for a new project (Bain 2009). 70

For an individual project and from the perspective of the procuring government agency, most PPP 71

bankruptcies due to revenue risk are actually an indication that revenue risk was successfully 72

transferred to the private sector – risk that otherwise would have been borne by taxpayers. Trends 73

like those in the US, however, can have regional impacts on the market and future procurements. As 74

a resul, there has been a shift in PPP road procurements to models in which the government retains 75

all or part of the revenue risk for the project, instead of the concessionaire (Parker 2011) (Cruz and 76

Marques 2012). Governments can provide financial support to mitigate the revenue risk undertaken 77

by the private sector, and increase the attractiveness of PPP contracts. Commonly adopted financial 78

supports provided by governments include Availability Payment (AP) concessions, minimum 79

Page 3: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

revenue guarantees (MRG) and, to a lesser extent, flexible-term concessions. Each is described in 80

detail in Section 2. 81

Government financial support mitigates revenue risk transferred to the project company, but also 82

exposes the government to contingent liabilities. The guarantees offered by the Mexican 83

government in its toll road program from 1989 to 1994 resulted in an unanticipated cost of $8.9 84

billion to the government after the 1994 Mexican economic crises, when the actual project revenues 85

fell 30% below the original projections on average (Brandao and Saraiva 2008) (Ruster 1997). Also, 86

in Columbia, the adverse fiscal impact of MRGs have been very significant, where the total amount 87

of guarantees paid by government during 1995 to 2004 amounted to 70% of the investments of the 88

11 guaranteed concessions (Carpintero, Vassallo et al. 2013). In practice, some international 89

studies have identified governments’ inability to design guarantees or support mechanisms using a 90

well-founded quantitative and transparent process, which often lead to unreasonably generous 91

guarantees and ex post renegotiations (Cruz and Marques 2012) and (Xu, Yeung et al. 2014). 92

The purpose of this article is to propose a methodology through which government sponsors can 93

evaluate and compare various mechanisms for transferring or sharing revenue risk for a toll-funded 94

highway PPP. Specifically, the objectives are to (1) identify critical indicators of marginal benefit 95

and government financial exposure to establish a measurable and comparable basis for comparing 96

various government financial support alternatives, (2) outline a rationale to choose among the 97

fiscal support alternatives based on the indicators, (3) propose a stochastic model to calculate the 98

identified indicators of these fiscal supports quantitatively with Monte Carlo simulation and (4) 99

adopt a numerical case study to demonstrate the application of the proposed methodology and to 100

explore under what circumstance which fiscal support mechanism may be most applicable. The 101

following section introduces common mechanisms to allocate revenue risk. Section 3 includes a 102

literature review of approaches to evaluate revenue risk sharing mechanisms. Section 4 introduces 103

the framework. Section 5 proposes stochastic models for the mechanisms reviewed and Section 6 104

introduces a hypothetical numerical case study. The final section displays conclusions, discusses 105

the limitations of the proposed model, and identifies areas for future research. 106

2. Fiscal Support Mechanisms to Transfer or Share Revenue Risk 107

For a toll-funded road project, a “base case” toll concession would transfer revenue risk to the 108

private concessionaire. In most cases, though not always, tolling is capped at designated levels to 109

avoid excessive pricing, so total project revenue is largely driven by traffic volume. Three 110

commonly used forms of revenue risk-sharing via payments by governments to concessionaires are 111

listed below: 112

An availability payment (AP) is a public procurement mechanism in which the 113

government makes periodic performance-based and inflation-linked payments to the 114

concessionaire with monitoring of actual asset performance against predefined 115

performance specifications and quality standards (Sharma and Cui 2012). Under AP 116

procurements, the government retains all revenue risk, as well as the authority to manage 117

toll rates dynamically. It is a mechanism that generally increases competition for a 118

procurement, in that bidders are not required to take on revenue risk for the project. Under 119

AP procurements, however, concessionaires have no incentive to increase traffic for the 120

Page 4: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

project through their design, operations, and maintenance practices. Shadow toll is 121

another mechanism that the government makes payments to the concessionaire. This 122

mechanism may not use government funds efficiently to protect investors from revenue 123

risk as payments are generally higher when traffic is high and vise versa (Fisher and 124

Babbar 1996). Therefore this paper does not dive further into shadow toll mechanism in 125

this paper. 126

Flexible-term contract is a procurement mechanism in which the duration of the 127

concession is not fixed. Instead it ends once the concessionaire achieves a target 128

cumulative revenue, “Least Present Value of Revenue (LPVR)”, as proposed by Engel, 129

Fischer et al. (1998). This approach was first introduced in the concession of the Second 130

Severn Crossing in the United Kingdom in 1990, and has since mostly been implemented 131

in Chile (Vassallo 2006). However, relatively few concessions have been awarded with 132

flexible-term contracts (Cruz and Marques 2012). The mechanism is generally more 133

complex to incorporate into a procurement than other support mechanisms, and it may 134

conflict with the maximum duration of concessions defined by local legislation. It also 135

injects uncertainty into the financing of a project when the concession duration is 136

indeterminate (Nombela and De Rus 2004) (Cruz and Marques 2012). To mitigate these 137

constraints, an adjusted version of the flexible-term concession has been proposed which 138

requires the government to pay the remaining LPVR at the end of the maximum 139

concession term (Vassallo 2004). 140

Minimum revenue guarantee (MRG) has been implemented in Chilean concessions, in 141

the early Colombian concessions (1994–1997) and in some Peruvian, South Korean 142

concessions, etc. (Vassallo 2006, Carpintero, Vassallo et al. 2013). By offering an MRG, 143

the government will make a compensation payment to the concessionaire in the case that, 144

in any one year, the actual revenue falls below the specified minimum annual revenue. 145

MRGs are sometimes implemented together with an Excess Revenue Sharing (ERS) 146

mechanism to achieve a symmetrical risk profile. Unlike payment obligations under AP 147

procurements, which are explicitly prescribed in agreements, MRGs expose governments 148

to some contingent liabilities—payments that are uncertain and driven by demand relative 149

to projections (Cebotari 2008). 150

3. Approaches to Evaluate Revenue Risk Sharing Mechanisms 151

In order to evaluate the various alternative revenue risk sharing mechanisms and support 152

government decision making, a number of researchers have made efforts to construct quantitative 153

models and instruments to value the benefits and contingent liabilities incurred by such support. 154

3.1. Incentive theory based evaluation 155

Some measure the impacts of government guarantees on projects theoretically by modeling 156

objectives, incentives and decision-making processes of the involved parties. Engel, Fischer et al. 157

(1997) Nombela and De Rus (2001) and Nombela and De Rus (2004) build up mathematical 158

bidding programming models with an asymmetric information assumption, seeking minimum life 159

cycle cost and concessionaire’s financial equilibrium objectives of both the public and private 160

Page 5: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

sectors. The models demonstrate that auctions based on bids for the least present value of 161

revenue/net revenue with a flexible-term contract, rather than on bids for minimum price or 162

maximum payment to government, help to eliminate bias towards selecting firms with optimistic 163

demand forecasts, and help to select the most cost-efficient firm. They claim that contingent 164

concession length is a critical factor of an optimal demand risk-sharing contract. Feng, Zhang et al. 165

(2015) build a bidding model with stochastic traffic demand, assuming that private investors 166

determine toll charges, road quality, and road capacity to maximize profit. By comparing the 167

outcomes between contracts with and without government guarantees, they demonstrate that high 168

MRGs increase toll charges while decreasing road quality and road capacity. 169

3.2. Real option based evaluation 170

Other researchers have made efforts to develop quantitative evaluation methods from a financial 171

perspective. The widely used traditional Discounted Cash Flow (DCF) method to evaluate 172

engineering projects works well for short-term projects in stable markets. However, for long-term 173

and uncertain projects, the expected cash flow cannot adequately reflect market fluctuations and 174

managerial flexibility, and thus may lead to poor investment decisions (Martins, Marques et al. 175

2015). In order to remedy this defect and take flexibility into consideration, Myers (1977) derives 176

a Real Options valuation approach from the concept of options in corporate finance. 177

Other studies have proposed tools to evaluate government supports as a bundle of real options 178

(Charoenpornpattana, Minato et al. 2002), in PPPs for infrastructure investments (Garvin and 179

Cheah 2004) (Martins, Marques et al. 2015). Ho and Liu (2002) present an option-pricing based 180

model to evaluate the impacts of government loan guarantees on the financial viability of a BOT 181

(build-operate-transfer) project with project value and construction cost as two at-risk variables, 182

and argue that government guarantees will increase investment value, though this is not accounted 183

for in a DCF model. Huang and Chou (2006) demonstrate that an MRG can create substantial 184

value when modeled using real options, assuming operating revenue is a stochastic variable 185

following a generalized Wiener process. Cheah and Liu (2006) adopt a risk-neutral pricing method 186

to value governmental supports as real options, and propose to incorporate the value of such 187

supports into negotiation frameworks. Instead of structuring MRG as a series of European put 188

options (that can only be exercised at the end of its life), Chiara, Garvin et al. (2007) propose a 189

Bermudan or a simple multiple-exercise real option model, which can be exercised on 190

predetermined dates between the purchase date and the expiration date. They also employ a 191

multiple-least squares Monte Carlo technique to value the more flexible MRG. Brandao and 192

Saraiva (2008) extend the standard option pricing model to value minimum traffic guarantees by 193

using market data of project returns to estimate stochastic project parameters, and propose to put a 194

cap on total government outlays of guarantees to limit budgetary impacts of contingent liability. 195

Jun (2010) Ashuri, Kashani et al. (2011) and Iyer and Sagheer (2011) also apply real option 196

models to value MRG together with a traffic revenue cap. All of these studies conclude that MRGs 197

and other support mechanisms can create value. 198

Scholars have also applied the real option based models to measure the fiscal burden incurred by 199

taxpayers from government guarantees. Indicators frequently used include 1) the expected present 200

value of all guarantee payments, or the expected amount to be paid each year; 2) the probability 201

distributions of the amount of MRG to be paid, the excess payment with a certain confidence 202

Page 6: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

interval, the exceedance probability, or the probability of a budget shortfall under a certain budget; 203

and 3) the probability distributions of the timing and number of times when the MRG may be 204

exercised (Ashuri, Kashani et al. 2011, Almassi, McCabe et al. 2012, Wibowo, Permana et al. 2012). 205

Wibowo and Kochendoerfer (2010) also develop a framework to quantify the contingent liability 206

of government guarantees, which allows the government to examine relationships among the 207

expected total payment, budget-at-risk allocated, and a desired confidence interval of actual 208

payment not exceeding the budget-at-risk. 209

3.3. Empirical studies 210

Despite the common conclusion drawn from theoretical studies that government financial support 211

creates value, some empirical studies show that these revenue risk sharing mechanisms are not as 212

effective as expected. Vassallo (2006) conducted interviews with government agencies, 213

concessionaires and university professors to find that the flexible-term with LPVR mechanism 214

applied in Chile initially met strong opposition from concessionaires for a variety of reasons: (1) 215

the mechanism does not improve the project’s ability to fulfill its commitments to lenders; (2) the 216

variable length of the contract makes the concession operation (resource planning) difficult to 217

organize in advance; and (3) the flexible-term procurement limits upside opportunity while not 218

always limiting downside risk. That study did, however, conclude that the LPVR procurement 219

mechanism was effective in reducing renegotiation expectations in Chile. Carpintero, Vassallo et 220

al. (2013) adopt a cross-country analysis based on project data from 1990 to 2010 in Chile, 221

Colombia, Peru, Mexico and Brazil, and find that traffic risk mitigation mechanisms, including 222

flexible-term procurements, MRGs, and APs in Latin American toll roads have not been very 223

successful in reducing renegotiation rates or in increasing the number of bidders in the tenders. 224

3.4. Optimization of individual revenue sharing mechanisms 225

Based on the evaluation researches and empirical evidences cited above, other researchers have 226

proposed models to optimize support mechanisms. Nombela and De Rus (2004) propose a way to 227

improve flexible term contracts by introducing bi-dimensional bids on LPVR, together with 228

maintenance costs, which turn into bidding on LPVNR (least present value of net revenue). 229

Vassallo (2006) suggests flexible term concessions implemented with a limit on the downside risk 230

by forcing the government to pay the LPVR left at the end, as well as a minimum concession 231

duration to make this mechanism more attractive to private bidders. Shan, Garvin et al. (2010) 232

propose a “collar option” which combines a put (MRG) and a call (ERS) option to be properly 233

matched. Ashuri, Kashani et al. (2010) Rocha Armada, Pereira et al. (2012) Sun and Zhang (2014) 234

Carbonara, Costantino et al. (2014) Wang and Liu (2015) all try to optimize the thresholds of MRG 235

and ERS by balancing the rate of investment return for the private sector and the government’s 236

cost to offer such a support. Engel, Fischer et al. (2013) propose a flexible term concession 237

mechanism with a revenue cap to be combined with a minimum income guarantee for 238

intermediate-demand projects. Sharma and Cui (2012) seek to optimize the design of concession 239

and annual payment for AP PPP projects. 240

3.5. Comparison among various revenue risk sharing mechanisms 241

Despite a number of existing studies on evaluation and optimization of individual fiscal support 242

alternatives, there are few studies that compare alternative revenue risk-sharing mechanisms 243

Page 7: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

quantitatively or that propose a systematic rationale to choose among fiscal support alternatives. 244

Irwin (2003) suggests that choosing among different fiscal support instruments should be based on 245

comparisons of their accuracy—“accuracy” here assesses their effectiveness in internalizing 246

externalities, overcoming market failures, mitigating political and regulatory risks, circumventing 247

political constraints on prices or profits, redistributing resources to the poor, etc.—transparency, as 248

well as cost. Wibowo (2004) adopts a real option pricing model to evaluate and compare fiscal 249

supports with two dimensions of expected payoff: (1) governments’ contingent liabilities; and (2) 250

the concessionaire’s risk of having negative NPVs. The results of that study demonstrate that 251

minimum revenue/traffic guarantees can be more effective than equivalent direct subsidies; and 252

Brandão, Bastian-Pinto et al. (2012) reaches a similar conclusion. 253

Considering the circumstances under which a given financial support mechanism is most 254

appropriate should be an important issue for policymakers: Yet there remains a research gap in 255

laying out an integral and consistent framework to guide decisions on choosing among 256

government financial support mechanisms. Also, none of the above research has taken lenders’ 257

(who are critical stakeholders in project finance) perspective into consideration. This paper seeks 258

to propose such a framework based on the instruments identified and developed in the research 259

above, and critical factors reflecting governments’, concessionaires’ as well as lenders’ 260

perspectives. 261

4. A framework to evaluate and compare support mechanisms 262

Fisher and Babbar (1996) claim that the type and level of government financial support embedded 263

into PPP projects should be limited to the extent needed to attract financing and promote a 264

successful procurement. They establish a conceptual two-dimensional framework to locate the 265

spectrum of possibilities for government financial support, as illustrated in Figure 1. In this 266

framework, the higher the impact on ability to raise financing and the lower the government’s 267

financial exposure the better. The framework is cited and recommended by several subsequent 268

studies (Charoenpornpattana, Minato et al. 2002) and public reports (World Bank Group 2016) . 269

However, a model to incorporate measurable variables to plot mechanisms along those two 270

abstract dimensions is beyond the scope of these existing studies. There is a research gap to go a 271

step further to elaborate the framework into a tangible and measurable model. 272

Page 8: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

Impact on

Ability to

Raise

Financing

High

LowGovernment Financial Exposure High

Concession Extension

Revenue Enhancement

Shadow Toll

Minimum Traffic/Revenue Guarantee

Subordinated Loan

Grant

Exchange Rate Guarantee

Debt Guarantee

Equity Guarantee

273

Figure 1. Range of Options for Government Support (reprinted from Fisher and Babbar 1996) 274

4.1. Definition of measurable indicators 275

The proposed model quantifies the implications of various options for revenue risk sharing 276

mechanisms along two dimensions: The impact of the support mechanism on the cost of capital 277

for the project, and risk exposure of the government. 278

4.1.1. Impact on cost of capital 279

Governments offer financial support to projects with revenue risk to make projects bankable and 280

reduce the weighted average cost of capital (WACC) for the project. Project WACC is determined 281

by the costs and weights of both equity and debt: WACC = w𝑒 ∗ 𝐶𝑒 +𝑤𝑑 ∗ 𝐶𝑑 . All of the 282

variables in this fomula will vary based on the project risks, and it is difficult to calculate total 283

costs of financing for a project early in the planning process. However, the revenue risk support 284

mechanisms described above can be used to decrease the cost of financing a project primarily by 285

increasing the leverage a project can take. This is a key assumption of the proposed model, in 286

using increased borrowing capacity as a proxy for reducing the financing costs of a project. 287

In practice, lenders calculate a project’s borrowing capacity based on annual cash flows available 288

for debt service (CFADS) over the loan life, and required coverage ratios such as DSCR (debt 289

service coverage ratio), and LLCR (loan life coverage ratio). CFADS is the amount of cash 290

available to service debt after all essential operating expenses have been met (see Equation 1). 291

DSCR is defined as annual CFADS divided by the annual debt service. LLCR is equal to the 292

present value of CFADS 𝑃𝑉(𝐶𝐹𝐴𝐷𝑆) over the loan life to the outstanding debt. Since annual 293

debt service and DSCR can be adjusted through structuring debt repayment schedules, the model 294

uses LLCR to determine the project’s borrowing capacity at financial close (see Equation 2). 295

CFADS and LLCR will vary with project economics, credit enhancement mechanisms (including 296

fiscal support), and the seniority of the lien. A key driver for projects with revenue risks, of course, 297

is the lenders’ evaluation of the traffic demand study for the project. Lenders and underwriters 298

generally use a very conservative probability of demand to determine CFADS, say 10% or even 5% 299

of the probability distribution. LLCRs also vary widely based on whether the project is exposed to 300

revenue risk. The required LLCR for CFADS with guaranteed revenue is generally between 301

1.2-1.3; while the market LLCR for CFADS with demand risk is generally between 1.5-1.9 (Khan 302

Page 9: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

and Parra 2003). 303

𝐶𝐹𝐴𝐷𝑆 = 𝑅𝑜𝑏𝑢𝑠𝑡 𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡 𝑜𝑓 𝑅𝑒𝑣𝑒𝑛𝑢𝑒 − 𝑂&𝑀 𝐶𝑜𝑠𝑡 (1) 304

𝐵𝑜𝑟𝑟𝑜𝑤𝑖𝑛𝑔 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 = 𝐵𝐶 =𝑃𝑉(𝐶𝐹𝐴𝐷𝑆)

𝐿𝐿𝐶𝑅 (2) 305

4.1.2. Government risk exposure 306

Fiscal supports dealing with project revenue risk may create contingent liabilities and claims for 307

the government, which increases the challenge of public budgeting. In order to better meet overall 308

fiscal constraints, a stochastic analysis is needed not only of the expected value, but also of the 309

volatility of the government’s financial exposure (Kim and Ryan 2015). A fiscal support with 310

lower expected value of government expenditure doesn’t necessarily dominate one with a higher 311

expected value, if the volatility of the former is larger than the volatility of the latter. The concept 312

of value at risk (VaR) was first introduced to improve risk management in finance and insurance 313

(Embrechts, Klüppelberg et al. 2013). VaR takes volatility into account and stands for a threshold 314

loss value given a probability level (say P5, P10). VaR offers a better understanding of 315

government liabilities in extreme cases and a more informed decision can be achieved, especially 316

when a project’s traffic forecast has an optimistic bias. Therefore, VaR is adopted as the dominant 317

indicator for government financial exposure, while expected value is used as a secondary indicator. 318

The VaR and expected value of the present value of government cash flow (CFg) can be calculated 319

through stochastic modeling and Monte Carlo simulation (see the next section “stochastic 320

modeling” for more details). 321

𝐺𝑜𝑣𝑒𝑟𝑛𝑚𝑒𝑛𝑡 𝑓𝑖𝑛𝑎𝑛𝑐𝑖𝑎𝑙 𝑒𝑥𝑝𝑜𝑠𝑢𝑟𝑒 = {𝑉𝑎𝑅[𝑃𝑉(𝐶𝐹𝑔)], 𝜇[𝑃𝑉(𝐶𝐹𝑔)]} (3) 322

These two variables can not only be used to measure government financial exposure from an 323

individual project, but could also be combined with those variables from other projects to generate 324

portfolio level measures of risk, thus improving overall, long term budgeting and deficit control. 325

4.2. Value at Risk - Borrowing Capacity comparison framework 326

To facilitate comparison, here the indicators are integrated into a two-dimensional coordinate (see 327

Figure 2). The borrowing capacity is on the Y-axis, illustrating the leverage or marginal benefit of 328

government fiscal support. Value at risk (VaR) of government expenditure is on the X-axis, 329

illustrating the maximum potential cost of fiscal support given a certain probability level, e.g.: 5%. 330

Page 10: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

Borrowing

Capacity

Government Financial Exposure at Risk (5%)

Arrangement 1

Arrangement 2

Expenditure Income

Arrangement 3

Dominate

331

Figure 2. Value at Risk - Borrowing Capacity comparison coordinate 332

In this coordinate, a point on the top right dominates a point on the bottom left, therefore the fiscal 333

support mechanism for Arrangement 1 in Figure 2 dominates the one for Arrangement 2. However, 334

a point on the top left and a point on the bottom right cannot be directly compared via this 335

coordinate system. For example, fiscal support with Arrangement 3 has a lower cost of financing 336

than Arrangement 1, but public VaR to revenue risk is higher. In this case, external constraints 337

such as government budget for this project, maximum debt to equity ratio required by relevant 338

regulations or lenders’ policies are needed to narrow down the range of feasible options. If the 339

possible borrowing capacity with Arrangement 3 exceeds the maximum debt ratio desired by the 340

procuring agency, or the government expenditure at risk is higher than desired, then Arrangement 341

3 should be rejected because it offers more fiscal support than what is necessary or affordable. 342

However, if Arrangement 3 meets the external limits, then further analysis of the comparison 343

between Arrangement 1 and 3 in more detail is needed. Non-financial issues such as transparency, 344

accuracy of incentive mechanisms, regulatory difficulties, government’s preferences, etc. should 345

be taken into consideration. 346

In practice, each fiscal support mechanism can be arranged in various structures. For example, 347

MRG can be structured with annual minimum revenue thresholds as 70%,80%, etc. of forecasted 348

revenue. The borrowing capacity and indicators of government financial exposures with each 349

support structure can be calculated, and plotted in this coordinate system. A rough outline of the 350

results of potential structures for a certain fiscal support mechanism is shown in Figure 3. The 351

arrangements that increase borrowing capacity are compared with a “base case,” of complete 352

transfer of revenue risk to the concessionaire. This is constrained by the maximum acceptable 353

leverage ratio, and the public budget resilience within a given confidence interval (public VaR) as 354

additional feasible option frontiers for each fiscal support mechanism. The fiscal support 355

mechanism with a feasible option frontier on the top right dominates one with a feasible frontier 356

on the bottom left. As illustrated in Figure 3, fiscal support Mechanism 2 is a better choice than 357

Mechanism 1, given the constraints. 358

Page 11: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

Borrowing

Capacity

Government Exposure

at Risk (5%)

Base Case Borrowing Capacity

Government Budget

Feasible

Options

Mechanism 1

Mechanism 2Maximum Debt Amount Allowed

IncomeExpenditure

359

Figure 3. A rough outline of the rationale for choosing among potential options 360

5. Stochastic Modeling 361

In this section, a stochastic model is built for revenue risk, and calculate borrowing capacities and 362

government financial exposures at risk with various fiscal support alternatives based on the 363

stochastic model. 364

5.1. Stochastic projection model of revenue 365

For a typical toll road concession, toll rates are adjusted annually according to a fixed schedule, 366

except for High Occupancy Toll (HOT) lanes or roads with dynamically priced tolls. A simplified 367

model is introduced for a toll road, by assuming project revenue equals to traffic multiplied by unit 368

price: 369

𝑅𝑡 = 𝑃𝑡 ∗ 𝐴𝐴𝐷𝑇𝑡 ∗ 365 (4) 370

𝑅𝑡 is the project revenue of Year t (the count starts from the beginning of the operation period); 371

𝑃𝑡 stands for the unit price predetermined in the concession agreement, and 𝐴𝐴𝐷𝑇𝑡 represents 372

the annual average daily traffic. 373

A traffic forecast for a project is developed through a Project Feasibility Study or Traffic and 374

Revenue Study. Generally, concessionaires develop their own, internal studies of potential traffic, 375

but at financial close a final traffic study is developed and often publically released by the 376

procuring agency, with lenders or bond underwriters using a conservative probable outcome from 377

that study (or their own study) to size project debt if the concession is taking some revenue risk. 378

Sponsor’s Traffic Forecast: 379

𝐴𝐴𝐷𝑇(𝑡+1)_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡 = 𝐴𝐴𝐷𝑇𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡 ∗ 𝑒𝛼𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡 (5) 380

Pessimistic Traffic Forecast: 381

𝐴𝐴𝐷𝑇(𝑡+1)_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡_𝑝𝑒𝑠 = 𝐴𝐴𝐷𝑇𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡_𝑝𝑒𝑠 ∗ 𝑒𝛼𝑡_𝑝𝑒𝑠 (6) 382

𝐴𝐴𝐷𝑇𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡_𝑝𝑒𝑠 ≤ 𝐴𝐴𝐷𝑇𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡 (7) 383

α𝑡- Annual traffic growth rate for Year t (in operation period). 384

Page 12: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

A stochastic projection model is used to reflect the unknowns by adding a random time series to 385

the traditional forecast. A common assumption adopted in relevant research is that traffic follows a 386

GBM (Geometric Brownian Motion), which is a stochastic process following a Brownian Motion 387

(think about the physical phenomenon of random motion of particles suspended in a fluid) with 388

drift. It is widely used to model stock prices, and recently has been introduced to model toll road 389

traffic volumes and revenues. The drift term in GBM model could represent the traditional traffic 390

forecast based on available information, while the Brownian Motion term represents the influence 391

of unknown factors. Galera and Soliño (2010) adopt a Dickey-Fuller approach to test the GBM 392

hypothesis for highway traffic with historical traffic data of 11 highway projects and the results of 393

that study affirm their GBM hypothesis. Therefore, the model utilizes the assumption that traffic 394

follows GBM. 395

𝐴𝐴𝐷𝑇𝑡+1 = 𝐴𝐴𝐷𝑇𝑡 ∗ 𝑒(𝛼𝑡−

𝜎2

2)𝛥𝑡+𝜎ɛ√𝛥𝑡

, 𝑡 ≥ 1 (8) 396

σ stands for traffic volatility, and ε~N(0,1) is a standard Wiener process which is a 397

mathematical model commonly used to describe a Brownian Motion. 398

Also, the actual initial traffic in the first year is assumed to follow a triangular probability 399

distribution defined by the forecast of lowest, most-likely, and highest traffic for the first year (see 400

Equation 9), following Brandao and Saraiva (2008), Ashuri, Kashani et al. (2011). 401

𝑓(𝐴𝐴𝐷𝑇1|(𝐴𝐴𝐷𝑇1_𝑙𝑜𝑤𝑒𝑠𝑡 , 𝐴𝐴𝐷𝑇1_𝑚𝑜𝑠𝑡 𝑙𝑖𝑘𝑒𝑙𝑦 , 𝐴𝐴𝐷𝑇1_ℎ𝑖𝑔ℎ𝑒𝑠𝑡)

=

{

2(𝐴𝐴𝐷𝑇1 − 𝐴𝐴𝐷𝑇1_𝑙𝑜𝑤𝑒𝑠𝑡)

(𝐴𝐴𝐷𝑇1_𝑚𝑜𝑠𝑡 𝑙𝑖𝑘𝑒𝑙𝑦 − 𝐴𝐴𝐷𝑇1_𝑙𝑜𝑤𝑒𝑠𝑡)(𝐴𝐴𝐷𝑇1_ℎ𝑖𝑔ℎ𝑒𝑠𝑡 − 𝐴𝐴𝐷𝑇1_𝑙𝑜𝑤𝑒𝑠𝑡)

𝑓𝑜𝑟 𝐴𝐴𝐷𝑇1_𝑙𝑜𝑤𝑒𝑠𝑡 ≤ 𝐴𝐴𝐷𝑇1 ≤ 𝐴𝐴𝐷𝑇1_𝑚𝑜𝑠𝑡 𝑙𝑖𝑘𝑒𝑙𝑦

2(𝐴𝐴𝐷𝑇1_ℎ𝑖𝑔ℎ𝑒𝑠𝑡 − 𝐴𝐴𝐷𝑇1)

(𝐴𝐴𝐷𝑇1_ℎ𝑖𝑔ℎ𝑒𝑠𝑡 − 𝐴𝐴𝐷𝑇1_𝑙𝑜𝑤𝑒𝑠𝑡)(𝐴𝐴𝐷𝑇1_ℎ𝑖𝑔ℎ𝑒𝑠𝑡 − 𝐴𝐴𝐷𝑇1_𝑚𝑜𝑠𝑡 𝑙𝑖𝑘𝑒𝑙𝑦)

𝑓𝑜𝑟 𝐴𝐴𝐷𝑇1_𝑚𝑜𝑠𝑡 𝑙𝑖𝑘𝑒𝑙𝑦 ≤ 𝐴𝐴𝐷𝑇1 < 𝐴𝐴𝐷𝑇1_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡_𝑜𝑝𝑡

(9)

5.2. Modeling borrowing capacity and public VaR under various supports 402

Three revenue risk sharing mechanisms are looked in this paper:(1) availability payment with 403

equal annual payment, (2) flexible term concession with LPVNR and maximum term limitation, 404

and (3) minimum revenue guarantee with excess revenue sharing. A base case is adopted as a 405

baseline for comparison. 406

5.2.1. Base case toll road without any credit enhancement 407

A base case without any credit enhancement is established in order to clarify the relative change 408

brought by government financial support. Generally, lenders will adopt both a conservative 409

probability for the forecast and a high debt coverage ratio to calculate a project’s borrowing 410

capacity if there is no credit enhancement. 411

𝐶𝐹𝐴𝐷𝑆𝑡 = 𝑅𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑒𝑡_𝑝𝑒𝑠 − 𝑂&𝑀𝑡 = 𝑃𝑡 ∗ 𝐴𝐴𝐷𝑇𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑒𝑡_𝑝𝑒𝑠 ∗ 365 − 𝑂&𝑀𝑡 (10) 412

𝑃𝑉(𝐶𝐹𝐴𝐷𝑆𝑡) = ∑𝐶𝐹𝐴𝐷𝑆𝑡

(1+𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1 (11) 413

Page 13: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

𝐵𝐶𝑏𝑎𝑠𝑒 𝑐𝑎𝑠𝑒 =𝑃𝑉(𝐶𝐹𝐴𝐷𝑆𝑡)

𝐿𝐿𝐶𝑅𝑟𝑖𝑠𝑘=

∑𝑃𝑡∗𝐴𝐴𝐷𝑇𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑒𝑡_𝑝𝑒𝑠∗365−𝑂&𝑀𝑡

(1+𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1

𝐿𝐿𝐶𝑅𝑟𝑖𝑠𝑘 (12) 414

𝑇𝐶 is the construction period, and 𝑇𝑑 is the average loan life. 𝐿𝐿𝐶𝑅𝑟𝑖𝑠𝑘 is the market loan life 415

coverage ratio that lenders set for a project taking revenue risk. 416

In this case, the government has no financial exposure: 417

𝑃𝑉(𝐶𝐹𝑔)𝑏𝑎𝑠𝑒 𝑐𝑎𝑠𝑒= 0 (13) 418

𝑃𝑉(𝐶𝐹𝑔) is the present value of government cash inflow; a negative value denotes cash outflow. 419

5.2.2. Availability payment 420

Under an AP structure, the government retains all the revenue risk, and lenders will use the 421

amount of annual payment 𝐴𝑃(𝑡)1 and the relatively low coverage ratio 𝐿𝐿𝐶𝑅𝑔𝑢𝑎𝑟𝑎𝑛𝑡𝑒𝑒𝑑 to 422

calculate borrowing capacity. 423

𝐶𝐹𝐴𝐷𝑆𝑡 = 𝐴𝑃(𝑡) − 𝑂&𝑀𝑡 (14) 424

𝐵𝐶𝐴𝑃 =𝑃𝑉(𝐶𝐹𝐴𝐷𝑆𝑡)

𝐿𝐿𝐶𝑅𝑔𝑢𝑎𝑟𝑎𝑛𝑡𝑒𝑒𝑑=

∑𝐴𝑃(𝑡)−𝑂&𝑀𝑡

(1+𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1

𝐿𝐿𝐶𝑅𝑔𝑢𝑎𝑟𝑎𝑛𝑡𝑒𝑒𝑑 (15) 425

For the proposed model, it is assumed that the project is still toll funded but that those toll 426

revenues are collected by the government. Government cash flows consist of availability payment 427

cash outflows and toll revenue inflows. The model accounts for the fact that project toll revenue is 428

often not a completely independent variable, and is impacted by the owner of project revenue risk. 429

When all revenue risk is allocated to the government, toll revenue collected may be less than the 430

amount collected by a private concessionaire, due to incentive issues and varying public sector 431

objectives (e.g. affordability). Also, some toll revenue may be diverted to general funds rather than 432

the project itself. To account for this, a coefficient parameter 𝛽 (0 ≤ 𝛽 ≤ 1) is introduced to 433

represent these factors. Equation 16 presents the present value of government cash flows with AP 434

procurement, where 𝑟𝐺 is the capital cost of government and 𝑇𝑂 is the operation period. 435

𝑃𝑉(𝐶𝐹𝑔) = ∑𝐶𝐹𝑔(𝑡)+𝛽∗𝑅𝑡

(1+𝑟𝐺)𝑡+𝑇𝐶

𝑇𝑂𝑡=1 = ∑

−𝐴𝑃(𝑡)+𝛽∗𝑅𝑡

(1+𝑟𝐺)𝑡+𝑇𝐶

𝑇𝑂𝑡=1 (16) 436

5.2.3. Flexible term concession with LPVNR and maximum term limitation 437

Flexible term procurements introduce an additional uncertainty from the perspective of project 438

lenders, in that when revenues are much higher than expected, the concession duration actually 439

shortens, thus exposing lenders to prepayment risk. This can be mitigated for projects with bank 440

loan financing in the terms of the loan, but nevertheless a flexible term procurement should not 441

reduce default risk for project lenders in a downside scenario. This mechanism usually does not 442

change the cash flow over the loan life, therefore it should not have significant influence on 443

borrowing capacity. 444

1 We don’t consider performance deduction here for simplification. A reason behind this is the fact that the income

received by the concessionaire is expected to decrease with poor performance, no matter which procurement

mechanism is adopted.

Page 14: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

𝐵𝐶𝑓𝑙𝑒𝑥𝑖𝑏𝑙𝑒 𝑡𝑒𝑟𝑚 = 𝐵𝐶𝑏𝑎𝑠𝑒 𝑐𝑎𝑠𝑒 =∑

𝑃𝑡∗𝐴𝐴𝐷𝑇𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑒𝑡_𝑝𝑒𝑠∗365−𝑂&𝑀𝑡

(1+𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1

𝐿𝐿𝐶𝑅𝑟𝑖𝑠𝑘 (17) 445

This mechanism helps to reduce the uncertainty of the equity holder’s rate of return and 446

potentially to increase competition, but at the same time creates public VaR primarily via 447

termination compensation or lost revenue at the tail end of a concession, when the asset would 448

otherwise transfer to public ownership. Government contingent liabilities under this mechanism 449

occur at the end of the maximum concession term (Tmax, excluding construction period) with the 450

amount of the shortfall of the actual PVNR (present value of net revenue) compared with the 451

target LPVNR (see Equation 18, where WACC is the weighted average cost of capital for the 452

project special purpose vehicle). 453

𝑃𝑉(𝐶𝐹𝑔)𝑓𝑙𝑒𝑥𝑖𝑏𝑙𝑒 𝑡𝑒𝑟𝑚= 𝑚𝑖𝑛 {0, [PVNR(𝑇𝑚𝑎𝑥) − 𝐿𝑃𝑉𝑁𝑅] ∗(

1+𝑊𝐴𝐶𝐶

1+𝑟𝐺)𝑇𝑚𝑎𝑥+𝑇𝐶} (18) 454

PVNR(𝑇𝑚𝑎𝑥) = ∑𝑃𝑡∗𝐴𝐴𝐷𝑇𝑡∗365−𝑂&𝑀𝑡

(1+𝑊𝐴𝐶𝐶)𝑡+𝑇𝐶

𝑇𝑚𝑎𝑥𝑡=1 (19) 455

5.2.4. Minimum revenue guarantee together with excess revenue sharing 456

The relationship between the effective revenue received by the concessionaire 𝑅(𝑡) , the 457

government’s cash flow 𝐶𝐹𝑔(𝑡), and the actual project revenue 𝑅𝑡 under an MRG and ERS 458

procurement is illustrated in Equation 20 and 21, as well as Figure 4 and Figure 52. 𝑅𝑚𝑖𝑛_𝑡 and 459

𝑅𝑚𝑎𝑥_𝑡 are minimum and maximum revenue thresholds for each year as negotiated between the 460

public and private parties. 461

𝑅(𝑡) = 𝑚𝑖𝑛[𝑚𝑎𝑥 (𝑅𝑡, 𝑅𝑚𝑖𝑛_𝑡), 𝑅𝑚𝑎𝑥_𝑡] (20) 462

𝐶𝐹𝑔(𝑡) = 𝑅𝑡 − 𝑅(𝑡) = 𝑅𝑡 − 𝑚𝑖𝑛[𝑚𝑎𝑥 (𝑅𝑡, 𝑅𝑚𝑖𝑛_𝑡), 𝑅𝑚𝑎𝑥_𝑡] (21) 463

2 A full compensation MRG is more effective than partial compensation in attracting debt financing, because

robust cash flows are lenders’ major concern. However, partial revenue sharing is more efficient than a revenue cap

because the former is better in maintaining the incentive of the concessionaire to make efforts aimed at improving

service. Since debt sizing and government financial at risk are determined by downside cases, the structure of

revenue sharing won’t significantly change the result. Therefore, here we assume a full-compensation MRG and a

revenue cap for simplicity.

Page 15: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

Rt

Project’s actual revenue

R(t)

Concessionaire's

effective revenue

Rmin_t

O

Rmin_t

Rmax_t

Rmax_t

464 Figure 4. Concessionaire’s effective revenue with MRG and excess revenue sharing 465

Rt Project’s actual revenue

CFg(t) Government’s

Cash Flow

ORmin_t

-Rmin_t

Rmax_t

466

Figure 5. Government’s cash flow with MRG and excess revenue sharing 467

Generally, lenders will use the guaranteed level of revenue and a relatively low coverage ratio 468

(𝐿𝐿𝐶𝑅𝑔𝑢𝑎𝑟𝑎𝑛𝑡𝑒𝑒𝑑) to calculate the borrowing capacity of a project with MRG (Equation 22 and 23). 469

Equation 24 presents the present value of government contingent expenditures. 470

𝐶𝐹𝐴𝐷𝑆𝑡 = 𝑅𝑚𝑖𝑛 _𝑡 − 𝑂&𝑀𝑡 (22) 471

𝐵𝐶𝑀𝑅𝐺 =𝑃𝑉(𝐶𝐹𝐴𝐷𝑆𝑡)

𝐿𝐿𝐶𝑅𝑔𝑢𝑎𝑟𝑎𝑛𝑡𝑒𝑒𝑑=

∑𝑅𝑚𝑖𝑛 _𝑡−𝑂&𝑀𝑡

(1+𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1

𝐿𝐿𝐶𝑅𝑔𝑢𝑎𝑟𝑎𝑛𝑡𝑒𝑒𝑑 (23) 472

𝑃𝑉(𝐶𝐹𝑔)𝑀𝑅𝐺= ∑

𝑅𝑡− 𝑚𝑖𝑛[𝑚𝑎𝑥 (𝑅𝑡,𝑅𝑚𝑖𝑛_𝑡),𝑅𝑚𝑎𝑥_𝑡]

(1+𝑟𝐺)𝑡+𝑇𝐶

𝑇𝑂𝑡=1 (24) 473

5.3. Summary 474

The project borrowing capacity and present value of government cash flows incurred by each 475

fiscal support mechanisms are summarized in Table 1. 476

Table 1. Borrowing capacity and government financial exposure of various fiscal supports 477

Fiscal Support Borrowing Capacity Government Financial Exposure

Base case

no credit

enhancement

∑𝑅𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑒𝑡_𝑝𝑒𝑠 −𝑂&𝑀𝑡

(1 + 𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1

𝐿𝐿𝐶𝑅𝑟𝑖𝑠𝑘

0

Availability

Payment

∑𝐴𝑃(𝑡) − 𝑂&𝑀𝑡

(1 + 𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1

𝐿𝐿𝐶𝑅𝑔𝑢𝑎𝑟𝑎𝑛𝑡𝑒𝑒𝑑 ∑

−𝐴𝑃(𝑡) + 𝛽 ∗ 𝑅𝑡(1 + 𝑟𝐺)

𝑡+𝑇𝐶

𝑇𝑂

𝑡=1

Page 16: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

Flexible term with

LPVNR and

maximum term

∑𝑅𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑒𝑡_𝑝𝑒𝑠 −𝑂&𝑀𝑡

(1 + 𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1

𝐿𝐿𝐶𝑅𝑟𝑖𝑠𝑘

𝑚𝑖𝑛 {0, [PVNR(𝑇𝑚𝑎𝑥) − 𝐿𝑃𝑉𝑁𝑅] ∗(1 +𝑊𝐴𝐶𝐶

1 + 𝑟𝐺)𝑇𝑚𝑎𝑥+𝑇𝐶}

MRG with ERS ∑

𝑅𝑚𝑖𝑛 _𝑡 − 𝑂&𝑀𝑡

(1 + 𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1

𝐿𝐿𝐶𝑅𝑔𝑢𝑎𝑟𝑎𝑛𝑡𝑒𝑒𝑑 ∑

𝑅𝑡 − 𝑚𝑖𝑛[𝑚𝑎𝑥 (𝑅𝑡, 𝑅𝑚𝑖𝑛_𝑡), 𝑅𝑚𝑎𝑥_𝑡]

(1 + 𝑟𝐺)𝑡+𝑇𝐶

𝑇𝑂

𝑡=1

It should be noted that all of the inputs for this framework are based on information available to 478

the government, and are naturally uncertain due to the nature of early stage project planning, as 479

well as the information asymmetry among the involved parties. However, the comparison is still 480

helpful during early stage project planning in enabling the government to evaluate various support 481

mechanisms for sharing in revenue risk and for creating a procurement structure designed around 482

public priorities at the outset. 483

6. Numerical Case Study 484

A case study of a hypothetical toll funded highway concession is adopted to illustrate the 485

application of the proposed framework. The concession includes a two-year construction phase and 486

a 35-year operation phase. The basic project information is described in Table 2. The interest rate 487

and growth rates of toll price and O&M cost are presented in nominal values. 488

Table 2. Project Information 489

Capital Variables

Capital Investment $110,000,000

Government’s Capital Cost rG 3%

Average Interest Rate rd 5%

Average Loan Life 25 years

LLCRguaranteed 1.2

LLCRrisk 1.5

Operating Variables

Initial Traffic Volume AADT1 (most likely) 25,000

Downside and Upside Range of AADT1 ±30% of 25,000

Continuous Annual Traffic Growth Rate αt (year 1-10) 6%

Continuous Annual Traffic Growth Rate αt (year 11-20) 3.5%

Continuous Annual Traffic Growth Rate αt (year 21-35) 2%

Initial Toll Rate $1.3

Annual Toll Growth Rate (year 1-5) 5%

Annual Toll Growth Rate (year 6-10) 3%

Annual Toll Growth Rate (year 11-35) 2%

Initial O&M Cost $6,500,000

Annual O&M Cost Growth Rate 3%

6.1. Structuring of fiscal support mechanisms 490

According to the formulas in Table 1, the borrowing capacity for base case without any credit 491

Page 17: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

enhancement is equal to ∑

𝑅𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑒𝑡_𝑝𝑒𝑠−𝑂&𝑀𝑡

(1+𝑟𝑑)𝑡+𝑇𝐶

𝑇𝑑𝑡=1

𝐿𝐿𝐶𝑅𝑟𝑖𝑠𝑘, where 𝑅𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑒𝑡_𝑝𝑒𝑠 = 𝑃𝑡 ∗ 𝐴𝐴𝐷𝑇𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡_𝑝𝑒𝑠 ∗ 365 , 492

𝐴𝐴𝐷𝑇𝑡_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡_𝑝𝑒𝑠 = 𝐴𝐴𝐷𝑇𝑡−1_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡_𝑝𝑒𝑠 ∗ 𝑒𝛼𝑡 , 𝐴𝐴𝐷𝑇1_𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡_𝑝𝑒𝑠 = 25,000 ∗ 0.7 = 17,500 , 𝑇𝑑 = 25 , 493

𝑇𝐶=2, therefore the borrowing capacity is around $50.3 million. The expected NPV for this project 494

is $8.5 million if the required return on equity (ROE) is 12%. Government has zero expenditure in 495

this case. 496

For each fiscal support mechanism, governments may, for various reasons, need to first identify 497

appropriate structures that are able to increase the project’s borrowing capacity and at the same time, 498

keep the project attractive to equity investors. For example, annual availability payments must 499

meet market requirements for ROEs. A trial-and-error method is taken to calculate the project’s 500

borrowing capacities and the ROEs with varying levels of annual payment and find that the ROE 501

equals to 6.4%, 12.0%, 18.3%, 41.4% when the annual payment is 16.5 million, 16.75 million, 502

17.0 million and 17.5 million. Similarly, LPVNRs for flexible term contracts should be larger than 503

zero, and the expected project PVNR without any credit enhancement is taken as the value of 504

LPVNR in the analysis to facilitate comparison. Under MRG, it is assumed that the revenue 505

support and excess revenue sharing thresholds “mirror” the expected revenue projected, as is 506

common in MRG procurements (Vassallo and Soliño 2006). In other words, if the lower threshold 507

is θ% of the forecasted revenue, then the upper threshold is (2-θ%) of the forecasted revenue. It is 508

assumed that the MRG only covers the loan life, while the ERS covers the whole operation phase. 509

In order to increase the project borrowing capacity compared to the base case but not to exceed the 510

capital cost, θ% should lie in the range of 65%-88%. When θ% equals 65%, the ROE has an 511

expected value larger than 12%, but it has a probability of 19% to be lower than 5%, which is the 512

interest rate for debt financing. As θ% increases, the concessionaire is able to achieve a higher 513

return on investment. 514

6.2. Simulation results 515

As toll price limitations are set by the prevailing contract, the principal source of revenue 516

uncertainty is the traffic volume in the first and subsequent years, which can be simulated, based on 517

downside and upside ranges of initial traffic volume and traffic volatility σ.3 Initial traffic range 518

AADT1_lowest and AADT1_highest are assumed to be ±30% of 25,000. Traffic volatility σ can be (1) 519

observed from historical traffic series (for existing roads), (2) estimated and computed from a 520

Monte Carlo simulation based on historical GDP data under the standard assumption that traffic 521

levels are positively correlated with GDP (Banister 2005) (Brandão, Dyer et al. 2005). For the 522

purpose of focusing on the application of the whole comparison framework, here σ is assumed to be 523

10%, following Almassi, McCabe et al. (2012) and Carbonara, Costantino et al. (2014). It is also 524

assumed that the revenue coefficient β is 1; in other words, the actual toll revenue collected is 525

independent of the owner of project revenue risk. Sensitivity analyses are also conducted on these 526

parameters to explore under what circumstances, which fiscal support mechanism would be the 527

most advantageous choice. 528

10,000 revenue streams are randomly generated that follow GBM, and the probability 529

3 This is a simplification assumed in the proposed planning model. In practice concessionaires may choose to lower

toll prices below the limits included in the concession agreement if they determine that a lower toll will maximize

revenue. The model assumes that tolls are set at the limits in the concession.

Page 18: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

distributions of the present value of government cash flows under different fiscal support 530

mechanisms are calculated. The figures of expected value, 5% quantile of government 531

expenditures are listed in Table 3, where negative values stand for expenditures while positive 532

value stands for incomes. 533

Table 3. Borrowing Capacities and Government Financial Exposures with Fiscal Support Alternatives 534

Fiscal Support Borrowing

Capacity (million $)

Debt to Capital

Ratio

E(GE)

(million $)

P5(GE)

(million $)

Base Case 50.325 45.75% 0 0

Flexible term

LPVNR=8.5 million

50.325

45.75%

-7.577

-25.900

MRG with ERS

65%MRG+135%ERS 51.029 46.39% 31.269 -43.827

70%MRG+130%ERS 62.907 57.19% 32.766 -57.257

75%MRG+125%ERS 74.784 67.99% 34.026 -71.210

80%MRG+120%ERS 86.662 78.78% 35.046 -86.101

85%MRG+115%ERS 98.539 89.58% 35.864 -101.620

88%MRG+112%ERS 105.670 96.06% 36.302 -111.540

Availability Payment

AP=16.50 million 90.410 82.19% 200.420 -68.105

AP=16.75 million 93.350 84.86% 190.290 -73.168

AP=17.00 million 96.290 87.53% 180.160 -78.232

AP=17.50 million 102.160 92.87% 170.040 -88.358

The simulation results are put into the “Borrowing Capacity- VaR” comparison coordinate space 535

(See Figure 6), and some potential acceptable levels of risk for a procuring agency are added for 536

illustrative purposes. This demonstrates that the acceptable risk level for the procuring agency may 537

guide them in determining which fiscal support is best for a given project. The results illustrate 538

that (1) the flexible term contract is unable to increase project’s borrowing capacity; (2) AP can 539

raise more debt financing than MRG with the same VaR of government expenditure; (3) however, 540

if the government has a tight budget constraint, AP may turn out to be unaffordable; and (4) MRG 541

is the better choice if flexibility in revenue risk allocation is preferred – MRG can be structured 542

with a low guaranteed level of revenue and a high upside threshold that gives the concessionaire a 543

chance to capture a large part of the excess revenue opportunity. 544

545 Figure 6. Borrowing Capacity- 5% VaR Comparison Framework 546

Page 19: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

6.3. Sensitivity analysis and discussions 547

Sensitivity analysis on traffic volatility σ illustrates that, AP procurement tends to be a more 548

advantageous choice than MRG for government when the volatility σ reduces, for example, 549

σ=0.05 (see Figure 7); vice versa, for example, when σ=0.15, MRG dominates AP (see Figure 8). 550

The same results are generated when the possible range of AADT1 changes. However, when the 551

revenue uncertainty is very small, i.e. an extreme case where there is effectively no revenue 552

uncertainty, government supports in either the form of MRG or AP may be unnecessary since a 553

concession without any credit enhancement is attractive enough to lenders and equity investors. 554

555 Figure 7. Sensitivity Analysis: σ=0.05 556

557 Figure 8. Sensitivity Analysis: σ=0.15 558

As the expected return on investment for a project decreases, the feasible choices of MRG 559

structures decrease and the added flexibility of MRG is less advantageous. For example, when the 560

capital investment of this project increases to 140 million while project revenues are unchanged, 561

an MRG with a downside threshold equals 65% of the forecasted revenue will offer equity 562

investors an ROE that has an expected value of 8.5%, with a probability of 28% to be lower than 563

5%, and a probability of 41% to be lower than 7%, which is very likely not attractive to equity 564

investors. When θ% increases to 85%, the expected value of ROE increases to 12% and the 565

probability that ROE falls below 5% decreases to 15%, which is similar to the ROE distribution 566

with a 65% MRG under the original project conditions. MRGs with thresholds higher than 85% 567

are dominated by feasible AP arrangements, see Figure 9. 568

Page 20: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

569 Figure 9. Sensitivity Analysis: I=140 million 570

Based on the sensitivity analysis and discussions, it is observed that the mean value of return on 571

investment, and the extent of revenue uncertainty may influence the optimal choice among the 572

alternative revenue risk sharing mechanisms. More specifically, if a project has an attractive return 573

on investment (a high mean revenue projection relative to its capital costs) and the revenue 574

uncertainty is very small, then a concession without any fiscal support is the best choice. If a 575

project has a high level of projected revenue volatility, MRG is more applicable. Finally, if a 576

project has a low expected return on investment (or has no viable toll revenue sources), AP is the 577

best choice if the revenue uncertainty is not very large. Figure 10 presents the fiscal support 578

mechanisms within a decision support matrix. 579

Return on Investment/ Revenue Projection Relative to Capital Cost

Revenue

Volatility

Low High

High

Low

MRG

AP Base Case

580 Figure 10. Decision Matrix 581

Our model can also account for varying toll collection incentives created by these fiscal support 582

mechanisms. This accounts for the assumption that toll revenues collected may be lower under an 583

AP procurement, in which revenue risk is held by the government, than MRG or another structure 584

in which some or all of it is allocated to the concessionaire. These are accounted for by using a β 585

coefficient less than 1 in calculating the retained risk under an AP structure. For example, if β 586

equals to 0.8, AP will be dominated by MRG, see Figure 11. 587

Page 21: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

588 Figure 11. Sensitivity Analysis: β=0.8 million 589

7. Conclusions, Limitations and Future Research 590

This research identifies the borrowing capacity of a project as a measurable indicator of the 591

marginal benefit provided by each government fiscal support mechanism to mitigate revenue risk, 592

and the “value at risk” retained by the government sponsor as an indicator of the cost of such a 593

fiscal support. These two indicators constitute a two dimensional framework to support 594

government sponsors in evaluating and selecting fiscal support alternatives at an early stage of 595

project planning. 596

The proposed model as designed does shed light on the applicability of one support mechanism in 597

particular – the flexible term concession. As described above, under the model the flexible term 598

procurement does little to increase project leverage, and hence reduce the cost of financing. While 599

the mechanism may reduce financing costs by increasing competition under particular global 600

infrastructure market conditions, it is unlikely that this particular support mechanism will be 601

effective in a developed, federal procurement market like the United States. 602

From the numerical case study, conclusions can be drawn regarding the applicability of two 603

additional support mechanisms (MRG/ERS and AP) based on project circumstances. Specifically, 604

it is found that MRG/ERS support mechanisms to be more flexible in sharing revenue risk 605

between a public sponsor and the private concessionaire for projects with a higher expected return 606

but significant volatility. AP is more applicable to projects that are projected to have a lower mean 607

revenue relative to their capital investment and lower volatility (or, of course, that will have no toll 608

revenue sources). 609

While this model is designed for an individual project, the outcomes (regarding the expected value 610

and volatility of government expenditure) from this framework can contribute to a more 611

comprehensive approach to fiscal portfolio management, and can thus improve fiscal deficit risk 612

management. The framework is also useful as a way to clarify and organize concepts qualitatively 613

in order to consider the value and cost of alternative fiscal supports for governments to share 614

revenue risk with PPP concessionaires. Future publications planned under this research initiative 615

include applying the proposed model to other revenue risk sharing mechanisms in practice, such as 616

limited credit enhancement supports. 617

It should be noted that, for federal procurement markets like the United States, this model does not 618

address federal support mechanisms to mitigate revenue risk, such as the Transportation 619

Page 22: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

Infrastructure Finance and Innovation Act (TIFIA) federal loan program. Federal loan and grant 620

programs that assume revenue risk can assist local procuring governments in mitigating that risk. 621

However, this model is specifically focused on the risk assumed by either the local government 622

agency procuring the asset or the concessionaire, and how those procuring governments evaluate 623

mechanisms for sharing that risk with concessionaires. It goes without saying that project sponsors 624

should pursue federal or other support programs to mitigate revenue risk for a given project 625

whenever these are available. 626

Structuring and optimizing each form of fiscal support, as well as improving the accuracy of the 627

inputs, are beyond the scope of this research. Although some relevant literature exists, these topics 628

remain a promising research opportunity. Also the framework suggested in this paper only 629

accounts for the cost of financing and public VaR in evaluating support mechanisms. There are 630

many other factors that can and should influence the allocation of revenue risk for a project. These 631

include market conditions that require one mechanism or another to generate enhanced levels of 632

competition for a procurement, which is less easily measurable. Social welfare priorities may also 633

be a relevant factor. Finally, and perhaps most importantly, the allocation of revenue risk also 634

drives incentives for bidding concessionaires to design, build, and operate a project to maximize 635

traffic demand to mitigate that risk. This is a critical factor that cannot be accounted for in the 636

quantitative evaluation framework. Deep-dive, empirical research on a set of operating toll road 637

concessions with different revenue risk sharing mechanisms is needed to assess the strength of this 638

effect. 639

Finally, as Kim and Ryan (2015) asserted, it is important to stress the importance of developing 640

precise analytical tools for evaluating fiscal supports to PPPs. Fiscal supports are a good way to 641

leverage private investment, but using them requires a clear understanding of the problems and 642

risks retained by the public. As is often the case, the devil is in the details. Adding an explicit 643

marginal benefit/risk analysis of alternative mechanisms to allocate or share revenue risk is a step 644

in the right direction in developing a project portfolio that includes both PPPs and traditionally 645

procured assets. 646

Acknowledgements 647

The author/s gratefully acknowledge the support for this research provided by the National 648

Science Foundation Grant # 1334292, the Stanford Global Projects Center, and the National 649

Natural Science Foundation of China # 71572089. All conclusions and opinions expressed in this 650

paper are those of the author/s and not of the National Science Foundation or the Global Projects 651

Center. 652

Reference 653

Almassi, A., et al. (2012). "Real Options–Based Approach for Valuation of Government Guarantees in 654

Public–Private Partnerships." Journal of infrastructure systems 19(2): 196-204. 655

Ashuri, B., et al. (2011). "Risk-neutral pricing approach for evaluating BOT highway projects with 656

government minimum revenue guarantee options." Journal of Construction Engineering and 657

Page 23: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

Management. 658

Ashuri, B., et al. (2010). A valuation model for choosing the optimal Minimum Revenue Guarantee 659

(MRG) in a Highway project: A Real-Option approach. Construction Research Congress 2010: 660

Innovation for Reshaping Construction Practice - Proceedings of the 2010 Construction Research 661

Congress. 662

Bain, R. (2009). "Error and optimism bias in toll road traffic forecasts." Transportation 36(5): 469-482. 663

Banister, D. (2005). Unsustainable transport: city transport in the new century, Taylor & Francis. 664

Brandão, L. E., et al. (2012). "Government Supports in Public–Private Partnership Contracts: Metro 665

Line 4 of the São Paulo Subway System." Journal of infrastructure systems 18(3): 218-225. 666

Brandão, L. E., et al. (2005). "Response to Comments on Brandão et al.(2005)." Decision Analysis 2(2): 667

103-109. 668

Brandao, L. E. T. and E. Saraiva (2008). "The option value of government guarantees in infrastructure 669

projects." Construction Management and Economics 26(11): 1171-1180. 670

Carbonara, N., et al. (2014). "Revenue guarantee in public-private partnerships: a fair risk allocation 671

model." Construction Management and Economics 32(4): 403-415. 672

Carpintero, S., et al. (2013). "Dealing with traffic risk in Latin American toll roads." Journal of 673

Management in Engineering 31(2): 05014016. 674

Cebotari, A. (2008). Contingent liabilities: issues and practice, International Monetary Fund. 675

Charoenpornpattana, S., et al. (2002). Government supports as bundle of real options in 676

built-operate-transfer highways projects. 7th Annual International Conference on Real Options. 677

Cheah, C. Y. and J. Liu (2006). "Valuing governmental support in infrastructure projects as real options 678

using Monte Carlo simulation." Construction Management and Economics 24(5): 545-554. 679

Chiara, N., et al. (2007). "Valuing simple multiple-exercise real options in infrastructure projects." 680

Journal of infrastructure systems 13(2): 97-104. 681

Cruz, C. O. and R. C. Marques (2012). "Risk-sharing in highway concessions: contractual diversity in 682

Portugal." Journal of Professional Issues in Engineering Education and Practice 139(2): 99-108. 683

Embrechts, P., et al. (2013). Modelling extremal events: for insurance and finance, Springer Science & 684

Business Media. 685

Engel, E., et al. (1997). "Highway franchising: pitfalls and opportunities." The American economic 686

review 87(2): 68-72. 687

Engel, E., et al. (2013). "The basic public finance of public–private partnerships." Journal of the 688

European Economic Association 11(1): 83-111. 689

Engel, E. M., et al. (1998). Least-present-value-of-revenue auctions and highway franchising, National 690

Bureau of Economic Research. 691

Feng, Z., et al. (2015). "Modeling the impact of government guarantees on toll charge, road quality and 692

Page 24: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

capacity for Build-Operate-Transfer (BOT) road projects." Transportation Research Part A: Policy and 693

Practice 78: 54-67. 694

Fisher, G. and S. Babbar (1996). Private financing of toll roads, World Bank Washington, DC. 695

Flyvbjerg, B., et al. (2005). "How (in) accurate are demand forecasts in public works projects?: The 696

case of transportation." Journal of the American Planning Association 71(2): 131-146. 697

Galera, A. L. L. and A. S. Soliño (2010). "A real options approach for the valuation of highway 698

concessions." Transportation Science 44(3): 416-427. 699

Garvin, M. J. and C. Y. Cheah (2004). "Valuation techniques for infrastructure investment decisions." 700

Construction Management and Economics 22(4): 373-383. 701

Group, W. B. (2016). "Debunking traffic and revenue risk in highway PPP projects- different 702

perspectives. World Bank Group." 703

Guasch, J. L. (2000). "Impact of Concessions' Design in Sector Performance: An Empirical Analysis of 704

Ten Years of Performance." 705

Guasch, J. L., et al. (2003). Renegotiation of concession contracts in Latin America, World Bank 706

Publications. 707

Harris, C., et al. (2003). "Infrastructure Projects: A Review of Canceled Private Projects." 708

Ho, S. P. and L. Y. Liu (2002). "An option pricing-based model for evaluating the financial viability of 709

privatized infrastructure projects." Construction Management & Economics 20(2): 143-156. 710

Huang, Y. L. and S. P. Chou (2006). "Valuation of the minimum revenue guarantee and the option to 711

abandon in BOT infrastructure projects." Construction Management and Economics 24(4): 379-389. 712

Irwin, T. (2003). Public money for private infrastructure: deciding when to offer guarantees, 713

output-based subsidies, and other fiscal support, World Bank Publications. 714

Iyer, K. and M. Sagheer (2011). "A real options based traffic risk mitigation model for 715

build-operate-transfer highway projects in India." Construction Management and Economics 29(8): 716

771-779. 717

Jun, J. (2010). "Appraisal of combined agreements in bot project finance: Focused on minimum 718

revenue guarantee and revenue cap agreements." International Journal of Strategic Property 719

Management 14(2): 139-155. 720

Khan, M. F. K. and R. J. Parra (2003). Financing large projects: Using project finance techniques and 721

practices, Pearson Prentice Hall. 722

Kim, J. and J. Ryan (2015). "Public-Sector Deficit Risk and Infrastructure P3s: A Value for Funding 723

Analytical Approach to Evaluation." The Journal of Structured Finance 21(2): 63-73. 724

Martins, J., et al. (2015). "Real options in infrastructure: revisiting the literature." Journal of 725

infrastructure systems 21(1). 726

Myers, S. C. (1977). "Determinants of corporate borrowing." Journal of financial economics 5(2): 727

147-175. 728

Page 25: Sharing The Big Risk: An Assessment Framework …...1 Sharing The Big Risk: An Assessment Framework for Revenue Risk 2 Sharing Mechanisms in Transportation Public-Private Partnerships

Nombela, G. and G. De Rus (2001). "Auctions for infrastructure concessions with demand uncertainty 729

and unknown costs." 730

Nombela, G. and G. De Rus (2004). "Flexible-term contracts for road franchising." Transportation 731

Research Part A: Policy and Practice 38(3): 163-179. 732

Parker, M. (2011). Availability Payments and Other Forms of P3s For Surface Transportation. The 733

Forum on Funding and Financing Solutions for Surface Transportation in the Coming Decade–734

Conference Report, AASHTO Centre for Excellence in Project Finance. 735

Rocha Armada, M. J., et al. (2012). "Optimal subsidies and guarantees in public-private partnerships." 736

European Journal of Finance 18(5): 469-495. 737

Ruster, J. (1997). "A retrospective on the Mexican toll road program (1989–94)." The Private Sector in 738

Infrastructure: Strategy Regulcztion and Risk. 739

Shan, L., et al. (2010). "Collar options to manage revenue risks in real toll public‐private partnership 740

transportation projects." Construction Management and Economics 28(10): 1057-1069. 741

Sharma, D. and Q. Cui (2012). Design of Concession and Annual Payments for Availability Payment 742

Public Private Partnership (PPP) Projects. Proceedings of the Construction Research Congress, West 743

Lafayette, IN. 744

Sun, Y. and L. Zhang (2014). "Balancing Public and Private Stakeholder Interests in BOT Concessions: 745

Minimum Revenue Guarantee and Royalty Scheme Applied to a Water Treatment Project in China." 746

Journal of Construction Engineering and Management. 747

Vassallo, J. M. (2004). "Short-Term Infrastructure Concessions Conceptual Approach and Recent 748

Applications in Spain." Public Works Management & Policy 8(4): 261-270. 749

Vassallo, J. M. (2006). "Traffic risk mitigation in highway concession projects: the experience of 750

Chile." Journal of Transport Economics and Policy: 359-381. 751

Vassallo, J. M. and A. S. Soliño (2006). Minimum income guarantee in transportation infrastructure 752

concessions in Chile. Transportation Research Record: 15-22. 753

Wang, Y. and J. Liu (2015). "Evaluation of the excess revenue sharing ratio in PPP projects using 754

principal–agent models." International Journal of Project Management. 755

Wibowo, A. (2004). "Valuing guarantees in a BOT infrastructure project." Engineering, Construction 756

and Architectural Management 11(6): 395-403. 757

Wibowo, A. and B. Kochendoerfer (2010). "Selecting BOT/PPP infrastructure projects for government 758

guarantee portfolio under conditions of budget and risk in the Indonesian context." Journal of 759

Construction Engineering and Management 137(7): 512-522. 760

Wibowo, A., et al. (2012). "Modeling contingent liabilities arising from government guarantees in 761

Indonesian BOT/PPP toll roads." Journal of Construction Engineering and Management. 762

Xu, Y., et al. (2014). "Determining appropriate government guarantees for concession contract: lessons 763

learned from 10 PPP projects in China." International Journal of Strategic Property Management 18(4): 764

356-367. 765