Upload
m-waqas-pk
View
226
Download
0
Embed Size (px)
Citation preview
8/13/2019 sld10
1/77
Standard Costs and The Balanced Scorecard
Chapter
10
8/13/2019 sld10
2/77
McGraw-Hill Ryerson Limited., 2001
10-2
LEARNING OBJECTIVES
1. Explain how direct materials standards anddirect labour standards are set.
2. Compute the direct materials price and quantityvariances and explain their significance.
3. Compute mix and yield variances for materialsand explain their significance.
4. Compute the direct labour rate and efficiencyvariances and explain their significance.
5. Compute the variable manufacturing overheadspending and efficiency variances.
After studying this chapter, you should be able to:
8/13/2019 sld10
3/77
McGraw-Hill Ryerson Limited., 2001
10-3
LEARNING OBJECTIVES
6. Understand the advantages of and the potentialproblems with using standard costs.
7. Understand how a balanced scorecard fitstogether and how it supports a companysstrategy.
8. Compute the delivery cycle time, the throughputtime and the manufacturing cycle efficiency(MCE).
9. (Appendix 10A) Prepare journal entries to recordstandard costs and variances.
10. (Appendix 10B) Explain the value of learning
curves.
After studying this chapter, you should be able to:
8/13/2019 sld10
4/77
McGraw-Hill Ryerson Limited., 2001
10-4
Standard Costs
benchmarks for measuring performance.
the expected levelof performance.
based on carefullypredetermined amounts.
used for planning labour, material
and overhead requirements.Standard Costs are:
8/13/2019 sld10
5/77
McGraw-Hill Ryerson Limited., 2001
10-5
Standard Costs
DirectMaterial
Managers focus on quantities and coststhat exceed standards, a practice known as
management by exception .
Type of Product Cost
A m o u n
t
DirectLabour
ManufacturingOverhead
Standard
8/13/2019 sld10
6/77
McGraw-Hill Ryerson Limited., 2001
10-6
Accountants, engineers, personneladministrators, and production managerscombine efforts to set standards based on
experience and expectations.
Setting Standard Costs
8/13/2019 sld10
7/77
McGraw-Hill Ryerson Limited., 2001
10-7
Setting Standard Costs
Should we usepractical standardsor ideal standards?
Engineer ManagerialAccountant
8/13/2019 sld10
8/77
McGraw-Hill Ryerson Limited., 2001
10-8
Setting Standard CostsPractical standardsshould be set at levels
that are currentlyattainable withreasonable andefficient effort.
Productionmanager Managerial
Accountant
8/13/2019 sld10
9/77
McGraw-Hill Ryerson Limited., 2001
10-9
Setting Standard Costs I agree. Ideal standards,that are based on
perfection, areunattainable anddiscourage most
employees.
HumanResources
Manager ManagerialAccountant
8/13/2019 sld10
10/77
McGraw-Hill Ryerson Limited., 2001
10-10
Setting Direct Material StandardsQuantity
Standards
Use productdesign specifications.
PriceStandards
Final, deliveredcost of materials,net of discounts.
8/13/2019 sld10
11/77
McGraw-Hill Ryerson Limited., 2001
10-11
Setting Direct Labour StandardsRate
Standards
Use wagesurveys and
labour contracts.
TimeStandards
Use time andmotion studies for
each labour operation.
8/13/2019 sld10
12/77
McGraw-Hill Ryerson Limited., 2001
10-12
Setting Variable OverheadStandards
RateStandards
The rate is thevariable portion of the
predetermined overhead rate.
ActivityStandards
The activity is the base used to calculate
the predeterminedoverhead.
8/13/2019 sld10
13/77
McGraw-Hill Ryerson Limited., 2001
10-13
Standard Cost Card VariableProduction Cost A standard cost card for one unit of
product might look like this:
A A x BStandard Standard StandardQuantity Price Cost
Inputs or Hours or Rate per Unit
Direct materials 3.0 kg. 4.00$ per kg. 12.00$Direct labour 2.5 hours 14.00 per hour 35.00 Varia ble mfg. overhead 2.5 hours 3.00 per hour 7.50
Total standard unit cost 54.50$
B
8/13/2019 sld10
14/77
McGraw-Hill Ryerson Limited., 2001
10-14
Are standards thesame as budgets?
A standard is theexpected cost for one
unit.
A budget is theexpected cost for allunits.
Standards vs. Budgets
8/13/2019 sld10
15/77
McGraw-Hill Ryerson Limited., 2001
10-15
Standard Cost Variances
P r o d u c
t C o s t
Standard
This variance is unfavourablebecause the actual cost
exceeds the standard cost.
A standard cost variance is the amount by whichan actual cost differs from the standard cost.
8/13/2019 sld10
16/77
McGraw-Hill Ryerson Limited., 2001
10-16
Standard Cost Variances
I see that there
is anunfavourablevariance.
But why arevariances
important to me?
First, they point to causes of problems and directions
for improvement.Second, they trigger
investigations in departments having responsibility
for incurring the costs.
8/13/2019 sld10
17/77
McGraw-Hill Ryerson Limited., 2001
10-17
Variance Analysis Cycle
Prepare standardcost performance
report
Conduct nextperiods
operations
Analyzevariances
Identifyquestions
Receiveexplanations
Take
correctiveactions
Begin
8/13/2019 sld10
18/77
McGraw-Hill Ryerson Limited., 2001
10-18
Standard Cost Variances
Price Variance
The difference betweenthe actual price and the
standard price
Standard Cost Variances
Quantity Variance
The difference betweenthe actual quantity andthe standard quantity
8/13/2019 sld10
19/77
McGraw-Hill Ryerson Limited., 2001
10-19
A General Model for VarianceAnalysis
Actual Quantity Actual Quantity Standard Quantity Actual Price Standard Price Standard Price
Price Variance Quantity Variance
Standard price is the amount that shouldhave been paid for the resources acquired.
8/13/2019 sld10
20/77
McGraw-Hill Ryerson Limited., 2001
10-20
Price Variance Quantity Variance
Actual Quantity Actual Quantity Standard Quantity Actual Price Standard Price Standard Price
A General Model for VarianceAnalysis
Standard quantity is the quantity allowed for the actual good output.
8/13/2019 sld10
21/77
McGraw-Hill Ryerson Limited., 2001
10-21
A General Model for VarianceAnalysis
AQ(AP - SP) SP(AQ - SQ) AQ = Actual Quantity SP = Standard Price AP = Actual Price SQ = Standard Quantity
Price Variance Quantity Variance
Actual Quantity Actual Quantity S tandard Quantity Actual Price S tandard Price S tandard Price
8/13/2019 sld10
22/77
McGraw-Hill Ryerson Limited., 2001
10-22
Standard Costs
Lets use thegeneral model to
calculate standardcost variances,
starting withdirect material .
8/13/2019 sld10
23/77
McGraw-Hill Ryerson Limited., 2001
10-23
Hanson Inc. has the following direct materialstandard to manufacture one Zippy:
1.5 kilograms per Zippy at $4.00 per kilogram
Last week 1,700 kilograms of material werepurchased and used to make 1,000 Zippies.
The material cost a total of $6,630.
Material Variances Example Zippy
8/13/2019 sld10
24/77
McGraw-Hill Ryerson Limited., 2001
10-24
What is the actual price per kilogrampaid for the material?a. $4.00 per kilogram.b. $4.10 per kilogram.c. $3.90 per kilogram.
d. $6.63 per kilogram.
What is the actual price per kilogrampaid for the material?a. $4.00 per kilogram.b. $4.10 per kilogram.c. $3.90 per kilogram.
d. $6.63 per kilogram.
Material Variances Zippy
8/13/2019 sld10
25/77
McGraw-Hill Ryerson Limited., 2001
10-25
What is the actual price per kilogrampaid for the material?a. $4.00 per kilogram.b. $4.10 per kilogram.c. $3.90 per kilogram.
d. $6.63 per kilogram.
What is the actual price per kilogrampaid for the material?a. $4.00 per kilogram.b. $4.10 per kilogram.c. $3.90 per kilogram.
d. $6.63 per kilogram. AP = $6,630 1,700 kg.AP = $3.90 per kg.
Material Variances Zippy
8/13/2019 sld10
26/77
McGraw-Hill Ryerson Limited., 2001
10-26
Hansons material price variance (MPV)for the week was:a. $170 unfavourable.b. $170 favourable.c. $800 unfavourable.
d. $800 favourable.
Hansons material price variance (MPV)for the week was:a. $170 unfavourable.b. $170 favourable.c. $800 unfavourable.
d. $800 favourable.
Material Variances Zippy
8/13/2019 sld10
27/77
McGraw-Hill Ryerson Limited., 2001
10-27
Hansons material price variance (MPV)for the week was:a. $170 unfavourable.b. $170 favourable.c. $800 unfavourable.
d. $800 favourable.
Hansons material price variance (MPV)for the week was:a. $170 unfavourable .b. $170 favourable.c. $800 unfavourable.
d. $800 favourable. MPV = AQ(AP - SP) MPV = 1,700 kg. ($3.90 - 4.00) MPV = $170 Favourable
Material Variances Zippy
8/13/2019 sld10
28/77
McGraw-Hill Ryerson Limited., 2001
10-28
The standard quantity of material thatshould have been used to produce1,000 Zippies is:
a. 1,700 kilograms.b. 1,500 kilograms.
c. 2,550 kilograms.d. 2,000 kilograms.
The standard quantity of material thatshould have been used to produce1,000 Zippies is:
a. 1,700 kilograms.b. 1,500 kilograms.c. 2,550 kilograms.d. 2,000 kilograms.
Material Variances Zippy
8/13/2019 sld10
29/77
McGraw-Hill Ryerson Limited., 2001
10-29
The standard quantity of material thatshould have been used to produce1,000 Zippies is:
a. 1,700 kilograms.b. 1,500 kilograms.
c. 2,550 kilograms.d. 2,000 kilograms.
The standard quantity of material thatshould have been used to produce1,000 Zippies is:
a. 1,700 kilograms.b. 1,500 kilograms.c. 2,550 kilograms.d. 2,000 kilograms.SQ = 1,000 units 1.5 kg per unit
SQ = 1,500 kg
Material Variances Zippy
10 30
8/13/2019 sld10
30/77
McGraw-Hill Ryerson Limited., 2001
10-30
Hansons material quantity variance (MQV)for the week was:a. $170 unfavourable.
b. $170 favourable.c. $800 unfavourable.
d. $800 favourable.
Hansons material quantity variance (MQV)for the week was:a. $170 unfavourable.
b. $170 favourable.c. $800 unfavourable.d. $800 favourable.
Material Variances Zippy
10 31
8/13/2019 sld10
31/77
McGraw-Hill Ryerson Limited., 2001
10-31
Hansons material quantity variance (MQV)for the week was:a. $170 unfavourable.
b. $170 favourable.c. $800 unfavourable.
d. $800 favourable.
Hansons material quantity variance (MQV)for the week was:a. $170 unfavourable.
b. $170 favourable.c. $800 unfavourable.d. $800 favourable.
MQV = SP(AQ - SQ) MQV = $4.00(1,700 kg - 1,500 kg) MQV = $800 unfavourable
Material Variances Zippy
10 32
8/13/2019 sld10
32/77
McGraw-Hill Ryerson Limited., 2001
10-32
1,700 kg. 1,700 kg. 1,500 kg.
$3.90 per kg. $4.00 per kg. $4.00 per kg.
= $6,630 = $ 6,800 = $6,000
Price variance$170 favourable
Quantity variance$800 unfavourable
Actual Quantity Actual Quantity Standard Quantity Actual Price Standard Price Standard Price
Material Variances Summary Zippy
10-33
8/13/2019 sld10
33/77
McGraw-Hill Ryerson Limited., 2001
10 33
Material Variances
Hanson purchased andused 1,700 kilograms.
How are the variancescomputed if the amountpurchased differs from
the amount used?
The price variance iscomputed on the entire
quantity purchased .
The quantity variance iscomputed only on the
quantity used .
10-34
8/13/2019 sld10
34/77
McGraw-Hill Ryerson Limited., 2001
0 3
Hanson Inc. has the following materialstandard to manufacture one Zippy:
1.5 kilograms per Zippy at $4.00 per kilogram
Last week 2,800 kilograms of material werepurchased at a total cost of $10,920, and
1,700 kilograms were used to make 1,000Zippies.
Material Variances ContinuedZippy
10-35
8/13/2019 sld10
35/77
McGraw-Hill Ryerson Limited., 2001
Actual Quantity Actual Quantity Purchased Purchased Actual Price Standard Price
2,800 kg. 2,800 kg.
$3.90 per kg. $4.00 per kg.
= $10,920 = $11,200
Price variance$280 favourable
Price variance increasesbecause quantity
purchased increases.
Material Variances ContinuedZippy
10-36
8/13/2019 sld10
36/77
McGraw-Hill Ryerson Limited., 2001
Actual Quantity Used Standard Quantity Standard Price Standard Price
1,700 kg. 1,500 kg.
$4.00 per kg. $4.00 per kg.
= $6,800 = $6,000
Quantity variance$800 unfavourable
Quantity variance isunchanged becauseactual and standard
quantities are unchanged.
Material Variances ContinuedZippy
10-37
8/13/2019 sld10
37/77
McGraw-Hill Ryerson Limited., 2001
Isolation of Material Variances
I need the price variancesooner so that I can better
identify purchasing problems.You accountants just dont
understand the problems thatpurchasing managers have.
Ill start computingthe price variance
when material ispurchased rather thanwhen its used.
10-38
8/13/2019 sld10
38/77
McGraw-Hill Ryerson Limited., 2001
Responsibility for Material
Variances
I am not responsible for this unfavourable materialquantity variance.
You purchased cheapmaterial, so my peoplehad to use more of it.
You used too much materialbecause of poorly trained
workers and poorlymaintained equipment.
Also, your poor schedulingsometimes requires me to
rush order material at ahigher price, causing
unfavourable price variances.
10-39
8/13/2019 sld10
39/77
McGraw-Hill Ryerson Limited., 2001
Standard Costs
Now lets calculatestandard costvariances for direct labour .
10-40
8/13/2019 sld10
40/77
McGraw-Hill Ryerson Limited., 2001
Hanson Inc. has the following direct labour standard to manufacture one Zippy:
1.5 standard hours per Zippy at $6.00 per direct labour hour
Last week 1,550 direct labour hours wereworked at a total labour cost of $9,610 to
make 1,000 Zippies.
Labour Variances ExampleZippy
10-41
8/13/2019 sld10
41/77
McGraw-Hill Ryerson Limited., 2001
What was Hansons actual rate (AR)for labour for the week?
a. $6.20 per hour.b. $6.00 per hour.c. $5.80 per hour.
d. $5.60 per hour.
What was Hansons actual rate (AR)for labour for the week?a. $6.20 per hour.b. $6.00 per hour.c. $5.80 per hour.
d. $5.60 per hour.
Labour VariancesZippy
8/13/2019 sld10
42/77
10-43
8/13/2019 sld10
43/77
McGraw-Hill Ryerson Limited., 2001
Hansons labour rate variance (LRV) for the week was:
a. $310 unfavourable.b. $310 favourable.c. $300 unfavourable.
d. $300 favourable.
Hansons labour rate variance (LRV) for the week was:a. $310 unfavourable.b. $310 favourable.c. $300 unfavourable.
d. $300 favourable.
Labour VariancesZippy
10-44
8/13/2019 sld10
44/77
McGraw-Hill Ryerson Limited., 2001
Hansons labour rate variance (LRV) for the week was:
a. $310 unfavourable.b. $310 favourable.c. $300 unfavourable.
d. $300 favourable.
Hansons labour rate variance (LRV) for the week was:a. $310 unfavourable.b. $310 favourable.c. $300 unfavourable.
d. $300 favourable.
Labour Variances
LRV = AH(AR - SR) LRV = 1,550 hrs($6.20 - $6.00) LRV = $310 unfavourable
Zippy
10-45
8/13/2019 sld10
45/77
McGraw-Hill Ryerson Limited., 2001
The standard hours (SH) of labour thatshould have been worked to produce1,000 Zippies is:a. 1,550 hours.b. 1,500 hours.
c. 1,700 hours.d. 1,800 hours.
The standard hours (SH) of labour thatshould have been worked to produce1,000 Zippies is:
a. 1,550 hours.b. 1,500 hours.c. 1,700 hours.d. 1,800 hours.
Labour VariancesZippy
10-46
8/13/2019 sld10
46/77
McGraw-Hill Ryerson Limited., 2001
The standard hours (SH) of labour thatshould have been worked to produce1,000 Zippies is:a. 1,550 hours.b. 1,500 hours.
c. 1,700 hours.d. 1,800 hours.
The standard hours (SH) of labour thatshould have been worked to produce1,000 Zippies is:
a. 1,550 hours.b. 1,500 hours.c. 1,700 hours.d. 1,800 hours.
Labour Variances
SH = 1,000 units 1.5 hours per unit SH = 1,500 hours
Zippy
10-47
8/13/2019 sld10
47/77
McGraw-Hill Ryerson Limited., 2001
Hansons labour efficiency variance (LEV)for the week was:a. $290 unfavourable.b. $290 favourable.c. $300 unfavourable.
d. $300 favourable.
Hansons labour efficiency variance (LEV)for the week was:a. $290 unfavourable.b. $290 favourable.c. $300 unfavourable.
d. $300 favourable.
Labour VariancesZippy
10-48
8/13/2019 sld10
48/77
McGraw-Hill Ryerson Limited., 2001
Hansons labour efficiency variance (LEV)for the week was:a. $290 unfavourable.b. $290 favourable.c. $300 unfavourable.
d. $300 favourable.
Hansons labour efficiency variance (LEV)for the week was:a. $290 unfavourable.b. $290 favourable.c. $300 unfavourable.
d. $300 favourable.
Labour Variances
LEV = SR(AH - SH) LEV = $6.00(1,550 hrs - 1,500 hrs) LEV = $300 unfavourable
Zippy
10-49
8/13/2019 sld10
49/77
McGraw-Hill Ryerson Limited., 2001
Actual Hours Actual Hours Standard Hours Actual Rate Standard Rate Standard Rate
Labour Variances Summary
Rate variance$310 unfavourable
Efficiency variance$300 unfavourable
1,550 hours 1,550 hours 1,500 hours
$6.20 per hour $6.00 per hour $6.00 per hour
= $9,610 = $9,300 = $9,000
Zippy
10-50
Labour Rate Variance
8/13/2019 sld10
50/77
McGraw-Hill Ryerson Limited., 2001
Labour Rate Variance
A Closer Look
High skill,high rate
Low skill,low rate
Using highly paid skilled workers to
perform unskilled tasks results in anunfavourable rate variance.
Production managers who make work assignmentsare generally responsible for rate variances.
Production managers who make work assignmentsare generally responsible for rate variances.
10-51
Labour Efficiency Variance
8/13/2019 sld10
51/77
McGraw-Hill Ryerson Limited., 2001
Labour Efficiency Variance
A Closer Look
UnfavourableEfficiencyVariance
Poorly
trainedworkers
Poor
qualitymaterials
Poorlymaintainedequipment
Poor supervisionof workers
10-52
Responsibility for Labour
8/13/2019 sld10
52/77
McGraw-Hill Ryerson Limited., 2001
Responsibility for Labour
Variances
I am not responsible for the unfavourable labour efficiency variance!
You purchased cheapmaterial, so it took moretime to process it.
You used too muchtime because of poorly
trained workers andpoor supervision.
10-53
Responsibility for Labour
8/13/2019 sld10
53/77
McGraw-Hill Ryerson Limited., 2001
Responsibility for Labour
Variances
Maybe I can attribute the labour and material variances to personnel
for hiring the wrong peopleand training them poorly.
10-54
8/13/2019 sld10
54/77
McGraw-Hill Ryerson Limited., 2001
Standard Costs
Now lets calculate
standard costvariances for thelast of the variableproduction costs
variablemanufacturing
overhead .
10-55
Variable Manufacturing
8/13/2019 sld10
55/77
McGraw-Hill Ryerson Limited., 2001
Hanson Inc. has the following variablemanufacturing overhead standard to
manufacture one Zippy:
1.5 standard hours per Zippy at $3.00 per direct labour hour
Last week 1,550 hours were worked to make1,000 Zippies, and $5,115 was spent for
variable manufacturing overhead.
Variable Manufacturing
Overhead Variances ExampleZippy
10-56
Variable Manufacturing
8/13/2019 sld10
56/77
McGraw-Hill Ryerson Limited., 2001
What was Hansons actual rate (AR) for variable manufacturing overhead ratefor the week?
a. $3.00 per hour.b. $3.19 per hour.c. $3.30 per hour.d. $4.50 per hour.
What was Hansons actual rate (AR) for variable manufacturing overhead ratefor the week?
a. $3.00 per hour.b. $3.19 per hour.c. $3.30 per hour.d. $4.50 per hour.
Variable Manufacturing
Overhead VariancesZippy
10-57
Variable Manufacturing
8/13/2019 sld10
57/77
McGraw-Hill Ryerson Limited., 2001
What was Hansons actual rate (AR) for variable manufacturing overhead ratefor the week?
a. $3.00 per hour.b. $3.19 per hour.c. $3.30 per hour.d. $4.50 per hour.
What was Hansons actual rate (AR) for variable manufacturing overhead ratefor the week?
a. $3.00 per hour.b. $3.19 per hour.c. $3.30 per hour.d. $4.50 per hour.
Variable Manufacturing
Overhead Variances
AR = $5,115 1,550 hours
AR = $3.30 per hour
Zippy
10-58
Variable Manufacturing
8/13/2019 sld10
58/77
McGraw-Hill Ryerson Limited., 2001
Hansons spending variance (SV) for variable manufacturing overhead for the week was:
a. $465 unfavourable.b. $400 favourable.c. $335 unfavourable.d. $300 favourable.
Hansons spending variance (SV) for variable manufacturing overhead for the week was:
a. $465 unfavourable.b. $400 favourable.c. $335 unfavourable.d. $300 favourable.
Variable Manufacturing
Overhead VariancesZippy
10-59
Variable Manufacturing
8/13/2019 sld10
59/77
McGraw-Hill Ryerson Limited., 2001
Hansons spending variance (SV) for variable manufacturing overhead for the week was:
a. $465 unfavourable.b. $400 favourable.c. $335 unfavourable.d. $300 favourable.
Hansons spending variance (SV) for variable manufacturing overhead for the week was:
a. $465 unfavourable.b. $400 favourable.c. $335 unfavourable.d. $300 favourable.
V g
Overhead Variances
SV = AH(AR - SR) SV = 1,550 hrs($3.30 - $3.00) SV = $465 unfavourable
Zippy
10-60
Variable Manufacturing
8/13/2019 sld10
60/77
McGraw-Hill Ryerson Limited., 2001
Hansons efficiency variance (EV) for variable manufacturing overhead for theweek was:
a. $435 unfavourable.b. $435 favourable.c. $150 unfavourable.d. $150 favourable.
Hansons efficiency variance (EV) for variable manufacturing overhead for theweek was:
a. $435 unfavourable.b. $435 favourable.c. $150 unfavourable.d. $150 favourable.
g
Overhead VariancesZippy
10-61
Variable Manufacturing
8/13/2019 sld10
61/77
McGraw-Hill Ryerson Limited., 2001
Hansons efficiency variance (EV) for variable manufacturing overhead for theweek was:
a. $435 unfavourable.b. $435 favourable.c. $150 unfavourable.d. $150 favourable.
Hansons efficiency variance (EV) for variable manufacturing overhead for theweek was:
a. $435 unfavourable.b. $435 favourable.c. $150 unfavourable.d. $150 favourable.
g
Overhead Variances
EV = SR(AH - SH) EV = $3.00(1,550 hrs - 1,500 hrs) EV = $150 unfavourable
1,000 units 1.5 hrs per unit
Zippy
8/13/2019 sld10
62/77
10-63
Variable Manufacturing Overhead
8/13/2019 sld10
63/77
McGraw-Hill Ryerson Limited., 2001
g
Variances A Closer Look
If variable overhead is applied on the basisof direct labour hours, the labour efficiencyand variable overhead efficiency variances
will move in tandem.
If variable overhead is applied on the basisof direct labour hours, the labour efficiencyand variable overhead efficiency variances
will move in tandem.
10-64
Variance Analysis and
8/13/2019 sld10
64/77
McGraw-Hill Ryerson Limited., 2001
Larger variances, indollar amount or asa percentage of the
standard, areinvestigated first.
Management by Exception
How do I know whichvariances toinvestigate?
10-65
Advantages of Standard Costs
8/13/2019 sld10
65/77
McGraw-Hill Ryerson Limited., 2001
Advantages of Standard Costs
Management by
exception
Improved cost control and performance
evaluation
Better Informationfor planning anddecision making
Possible reductions
in production costs
Advantages
10-66
Emphasis on negative Favourable variances
8/13/2019 sld10
66/77
McGraw-Hill Ryerson Limited., 2001
PotentialProblems
Emphasis on negativemay impact morale.
Emphasizing standardsmay exclude other
important objectives.
Favourable variancesmay be misinterpreted.
Continuous improvementmay be more
important thanmeeting standards.
Standard costreports may
not be timely.
Labour quantity standardsand efficiency variancesmay not be appropriate.
10-67
The Balanced Scorecard
8/13/2019 sld10
67/77
McGraw-Hill Ryerson Limited., 2001
The Balanced Scorecard
Management translates its strategy intoperformance measures that employees
understand and accept.
Management translates its strategy intoperformance measures that employees
understand and accept.
Performancemeasures
Financial Customers
Learningand growth
Internalbusiness
processes
10-68
The Balanced Scorecard
8/13/2019 sld10
68/77
McGraw-Hill Ryerson Limited., 2001
The Balanced Scorecard
How do we lookto the owners?
How can we
continually learn,grow, and improve?
In which internal
business processes must we excel?
How do we lookto customers?
10-69
The Balanced Scorecard
8/13/2019 sld10
69/77
McGraw-Hill Ryerson Limited., 2001
The Balanced Scorecard
Learning improvesbusiness processes.
Improved business
processes improvecustomer satisfaction.
Improving customer satisfaction improves
financial results.
10-70
Delivery Performance Measures
8/13/2019 sld10
70/77
McGraw-Hill Ryerson Limited., 2001
Process time is the only value-added time.
Delivery Performance Measures
Wait TimeProcess Time + Inspection Time
+ Move Time + Queue Time
Order Received
ProductionStarted
GoodsShipped
Delivery Cycle Time
Throughput Time
10-71
Delivery Performance Measures
8/13/2019 sld10
71/77
McGraw-Hill Ryerson Limited., 2001
Delivery Performance Measures
ManufacturingCycle
Efficiency
Value-added timeThroughput time
=
Wait Time
Throughput Time
Process Time + Inspection Time+ Move Time + Queue Time
Order Received
ProductionStarted
GoodsShipped
Delivery Cycle Time
Appendix
8/13/2019 sld10
72/77
General Ledger Entries toRecord Variances
10A
10-73
Journal Entries - Material Variances
8/13/2019 sld10
73/77
McGraw-Hill Ryerson Limited., 2001
Price varianceDr Raw Materials
Dr Materials Price Variance (U)Cr Materials Price Variance (F)Cr Accounts Payable
Quantity varianceDr Work in ProcessDr Materials Quantity Variance (U)
Cr Materials Quantity Variance (F)Cr Raw Materials
10-74
Journal Entries - Labour Variances
8/13/2019 sld10
74/77
McGraw-Hill Ryerson Limited., 2001
Rate varianceDr Work in Process
Dr Labour Rate Variance (U)Cr Labour Rate Variance (F)Cr Wages Payable
Efficiency varianceDr Work in Process
Dr Labour Efficiency Variance (U)Cr Labour Efficiency Variance (F)Cr Wages Payable
Appendix
8/13/2019 sld10
75/77
The Learning Curve
10B
10-76
The Learning Curve
8/13/2019 sld10
76/77
McGraw-Hill Ryerson Limited., 2001
g
! Productivity in hours per unit will
decrease as an employee produces moreunits.! Used to set and revise standard labour
hours in a repetitive task environment.! Used for labour intensive manufacturing.
10-77
End of Chapter 10
8/13/2019 sld10
77/77
McGraw-Hill Ryerson Limited., 2001
p