Upload
sempatik721
View
26
Download
1
Tags:
Embed Size (px)
DESCRIPTION
rf
Citation preview
Cement Clinker Grinding Practice and Technology
Hakan Benzer*, Alex Jankovic†, Levent Ergun*
* Hacettepe University, Ankara, Turkey† Metso Minerals Process Technology Asia Pacific, Brisbane, Australia
ABSTRACT
The current world consumption of cement is close to 2 billion tonnes per annum and it is
increasing at about 1% per annum. Conventional cement grinding circuits consist of two-
compartment tube mills and the air separators. Alternative mills such as High Pressure Grinding
Rolls, Vertical Roller Mill and Horomill has been applied in recent times in order to improve the
grinding efficiency. Air separators play crucial role in improving overall energy efficiency of the
cement grinding circuits and has been improved continuously over the decades.
Introduction of clinker pre-crushing stage can significantly improve the cement grinding energy
efficiency. Due to relatively low capital cost the Barmac crusher is an attractive upgrade option.
Hybrid grinding circuits with HPGR are being widely used primarily due to higher energy
efficiency, with specific energy consumption reduced to almost 50% compared to some
conventional circuits.
INTRODUCTION
The current world consumption of cement is close to 2 billion tones per annum. During the last
10 years the cement production has increased 38 %. Different types of Portland cement are
manufactured to meet different physical and chemical requirements for specific purposes. The
American Society for Testing and Manufacturing (ASTM) has designated five types of Portland
cement as given in Table 1.
Table 1. Portland cement classification with its constituents and fineness
Types Clinker%
Admixture %
Minor component%
Fineness +45µm %
CEM I 95-100 - 0-5 11.4CEM II 80-94 6-20 0-5 14.2CEM III 35-64 36-65 0-5 5.9CEM IV 65-89 11-35 0-5 11.6CEM V 40-64 18-30 0-5 17.0
Grinding Portland cement is made from exact proportions of materials containing calcium, silica,
alumina and iron. Approximately 1.5 tonnes of raw materials are required to produce 1 tonne of
finished cement. Grinding operation is the major operation and occurs at the beginning and the
end of the cement making process. The last step in the process of manufacturing portland cement
is the finish grinding of clinker together with small amount of gypsum and some admixtures. The
principal objectives of clinker grinding are to promote the hydration of cement and to ensure
complete coating of inert aggregates. The fineness of the cement effects on the concrete
properties in terms of the placeability, strength and permeability. The finer the grind the more
reactive is the finished cement. Therefore, every type of cement has got its own fineness to meet
the required quality. In Figure 1 the particle size distribution of the different cement types are
presented.
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1
Particle Size (mm)
Cum
. % p
assi
ng
CEM I
CEM II
CEM III
CEM IV
CEM V
Figure 1 Size distribution variation among the different cement types
The electrical energy consumed in the conventional cement making process is in order of 110
kWh/tonne and about 30% of which is used for the raw materials preparation and about 40% for
the final cement production by cement clinker grinding. Figure 2 shows the electrical energy
consumption split in a typical plant (Fujimoto, 1993). Production costs and environmental
concerns are emphasizing the need to use less energy and therefore the development of more
energy efficient machines for grinding and classification.
Figure 2 Energy consumption for different stages of cement production
EQUIPMENT USED FOR CLINKER GRINDING
Tube Ball Mills
The continuous ball mill has been used for just over one hundred years and it still the most widely
installed grinding equipment in cement manufacturing. Cement is ground in tube ball mills
operating either in open or closed circuit. The tube mills are characterized by the length/diameter
(L/D) ratio and it is found that the best alternative for the ratio is 3 in terms of energy expenditure
(Schnatz and Knobloch, 2000). The tube ball mills can be operated as one, two or three
compartment and the length of the each compartment should be evaluated based on the size
distribution variation from feed end to the discharge end.
Special diaphragms divide the cylinders of multi compartment mills. The diaphragms are
primarily designed to prevent passing of the balls to the next compartment and to allow the flow
Quarry crushing and prehomo
5%Raw material
grinding24%
Feed homogenization
6%Burning and
cooling22%
Conveying, packing and
loading5%
Finish cement grinding
38%
and pre-homogenization
of ground material through the mill. The design of the diaphragms influence the fineness of the
ground material (Duda, 1985).
Figure 3 Example of mill liners in the first and second compartment of a cement ball mill
Various shapes of mill liners have been developed for the cement mills (see Figure 3). The
classifying liners are special application in clinker grinding. This lining causes a classification of
the grinding ball sizes resulting in a decrease in size along the grinding path. The grooved liner
application also favours the slipping motion in the second compartment of the mills where
abrasion breakage is dominant.
Operation of the tube ball mills is relatively well understood and there are several design and
operating parameters of the ball milling operations, which affect the mill efficiency and the
quality of the cement produced (Gouda, 1981).
Vertical Roller Mill (VRM)
Vertical roller mills have been in use for limestone and coal grinding in cement industry for many
years thanks to high drying capacity, low energy consumption, compactness and reliability in
operation. The largest mill in operation has an installed power of 6 MW grinding 840 t/h from the
lump feed size down to 85 % 90µm. Cement grinding by a vertical roller mill is applied in
pregrinding systems, advanced pregrinding systems and finish grinding systems (Schimoide,
1996).
In a VRM the interparticle comminution takes place in a material filled gap between the rotating
table and the grinding rollers. The mill feed is charged to the center of the table and moves
affected by centrifugal forces and friction towards the table’s edge. On it is way it is nipped by 2,
3, 4 or 6 conical rollers installed at the outside rim of the table. The rollers are attached to
hydraulic cylinders which provide grinding forces for comminution of the material. The ground
particles leave the table by an air stream and taken up to the separator incorporated in the casing
of the mill. The fine product is taken as the mill discharge and the coarse reject of the separator
falls back on to the table as the circulating load.
Finish grinding of cement by means of a VRM was first put into commercial operation in 1984
(Shimoide, 1996). Since then, however, further applications were relatively limited. One reason is
that a portion of the power savings achieved in the VRM (attributed to higher grinding efficiency)
is lost due to a higher power consumption from the fan (FLS, 1998). The second one is the wear
problem, however in the recent years plant trials indicated that the problems can be reduced with
new roller design. The wear rate and the throughput of the system depends very heavily on the
consistency of the materials being ground (Nobis, 2001). Effective comminution largely depends
on the formation of a stable grinding bed between the rollers and the grinding table.
The main operational bottle neck’s of the VRM is the high circulating loads from separator
rejects. These cause an inefficient grinding operation because of the high load accumulation
inside the mill. In order to overcome this problem the roller mills are operated with external
material circulation. It was reported that the specific power consumption for producing portland
cement with external material circulation was 30 % less than for producing these cements in tube
mills (Feige, 1983). CKP mill is an example for this type machine and CKP mills were developed
on the basis of the proven technology of vertical roller mills (Suton et al., 1992). In CKP system,
materials are fed through a central chute. Centrifugal force, combined with rotation of the table,
distributes the product over the table surface. After grinding, which is carried out between the
table and rollers, the material is extracted from the CKP by gravity with the assistance of the
scrapers (Miranda et.al, 1998). CKP mills are generally used as pregrinders and the grinding
energy efficiency of using CKP mill as a pregrinder resulted with grinding energy saving of 17
% (Dupuis and, Rhin, 2003).
Horizantal Roller Mills (HOROMILL)
The HOROMILL consists of a horizontal cylinder supported onslide-shoe bearings and driven
through an open gear train. The principles of HOROMILL are briefly summarized as a bed
material compression mill, a multi-compression mill and as high capacity mills (Cornille, 1999).
The simplified diagram is given in Figure 3.
Figure 3 Comminution principle in Horomill
The material passes into the mill at one end of the cylinder and, because of the centrifugal effect
caused by operating the cylinder above the critical speed, is carried as a uniformly distributed
layer of material on its inner surface. The finished product is collected in a dust filter, while the
coarse particles are recycled to the mill. The grinding force is transmitted to the roller by
hydraulic cylinders. Internal fittings are provided to control the material recirculation. It’s been
reported that the grinding process based on multiple compressions give the machine a high
stability and also the recirculating load can be adjusted to suit the quality target (Cordonnier,
1994).
The comparison with a ball mill indicate that HOROMILL operates with a large grinding bed
thickness and moderate pressures which leads to energy savings of 35 to 40 % for cement
grinding. The operational experience indicates that the specific cost concerning the liners and
wear parts are higher than an equivalent ball mill (Brunelli, 2001). Mechanical problems with a
Horomill are reported in Konya cement plant in Turkey (Fochardiere, 1999).
High Pressure Grinding Rolls (HPGR)
The High Pressure Grinding Rolls (HPGR) developed by Professor Schoenert has been offered as
a comminution technology with claims of improved performance relative to conventional
grinding technology. In particular, it has been claimed that the advantage of the high pressure
grinding roll is its lower specific energy consumption (Schoenert, 1979).
The material to be ground is compressed in a gap between two counter rotating grinding rolls (see
Figure 5) with circumferential speed of 1 to 1.8 m/s to form a compacted cake. The compacted
cake contains fine particles, coarser particles with larger numbers of incipient cracks and weak
points, which greatly reduce the energy expenditure during further comminution (Ellerbrock,
1994).
Fixed roll
Feed
Moveable rollOil cylinders
Product
Nitrogen cylinder
Figure 5 The principle of operation of high pressure grinding rolls
HPGR can be used at several stages in cement grinding. These configurations are named as pre-
grinding, finish grinding, hybrid grinding and semi finish grinding. In pregrinding configuration,
reductions of overall energy consumption in the range of 20 % have been achieved (Kellerwessel,
1986). The hybrid grinding configuration is achieved by splitting the coarse fraction from the air
classifier to the high pressure grinding rolls and ball mill respectively. In the semi-finish grinding
configuration the high pressure grinding roll is operated in closed circuit with the air classifier
and the fines from the separator are finally ground in a tube mill circuit. In the finish grinding
configuration the high pressure grinding rolls operate with an air classifier in closed circuit. In
this alternative the energy saving potential is up to 50 % (Kellerwessel 1996). Hovewer, in finish
grinding application the water requirement to make mortar increases significantly as result of the
narrow size distribution (Roseman, 1989 ; Odler and Chen, 1995).
Air Classifiers
Classification in the clinker grinding circuits is achieved using the air separators. Development of
air classifiers was based on the principles of two devices, the simple expansion chamber and
Mumford and Mood separator, patented in 1885 (Klumpar et al., 1986).
There are two types of air classifiers, dynamic and static. Dynamic classifiers have moving and
fixed internal parts respectively. Dynamic classifiers have evolved through three generations,
each being significantly better than its predecessor.
Static air classifiers does not have moving parts and classification achieved is by changes in air
velocity and direction were an early invention. The principle of operation is shown in Figure 5a.
The air stream carrying the particles is converted from a directional flow through the outer cone
into a rotating flow by guide vanes. The particles are subject to centrifugal force, the coarse
particles move to the outer wall of the inner cone and are collected in a bin, and the fine particles
leave with the air and are sent to a dust collector. The product size can be altered to some extent
by changing the angle of the vanes but the efficiency is low and static classifiers can be regarded
more as grit separators than efficient classifiers.
a. b.
Figure 6 a - schematic view of the static air classifier, b - separation mechanism in a
dynamic air classifier
The dynamic air classifiers utilize a distribution plate to disperse the feed material into the
separation zone. Thus a particle of material is subjected to three forces: centrifugal force from the
distribution plate, uplift from the air current and gravity. Figure 5b indicates the forces acting on
a particle in a dynamic air classifier.
The first generation classifier had a distributor plate and the air circulation in the classifier was
provided by a vertically supported rotor. The main problems with the first generation classifiers
were the circulating air becomes very hot, fine particles were not removed from the recycling air
and the control of the product is very difficult. Figure 7a shows a simplified sketch of a first
generation air separator.
a. b.
Figure 7 First (a) and second (b) generation dynamic air separator
In the second generation type (see Figure 7b), the main difference from the first generation was
the external fan replaced to circulate the air and these are equipped with a cyclone for the fines.
The product control can be achieved individually by adjusting the rotor speed and air velocity
separately.
The third generation separators are known as high efficiency separators (see Figure 8). The
feeding of the material to the separator is achieved as dispersed curtain of particles and the
horizontal air flow to the separator gives a uniform separation performance. The fine particles
passes through a rotating cage before goes to the fine product. The bars of the cage assists in the
performance of the separator.
Figure 8 Schematic of a third generation dynamic air separator
CIRCUIT CONFIGURATION FOR IMPROVED ENERGY EFFICIENCY
For most of the twentieth century, the common dry grinding circuits for the production of
finished cement from cement clinker, consist of two-compartment tube mills with or without the
air separators. The advantage of this circuit is its simplicity and easy operation; however, the
energy consumption is high especially for the open circuit operation.
The circuit with two-compartment tube mills has limited energy efficiency partly due to high
reduction ratio required in a single comminution/classification step. Clinker feed size can vary
from F80=10–40 mm and the final product size is P80=35-40 microns and the size reduction ratio
could be in order of 250-1000. Large balls (up to 100mm) are used in the first compartment of the
tube mill to crush the coarse clinker, however the ball mill energy efficiency reduces for feed
sizes larger than F80=2-3 mm. It should be therefore more energy effective to pre-crush the
clinker. Recent work indicates that introduction of the Barmac crusher for clinker pre-crushing
can increase the cement circuit throughput in order of 10-20%. Alternatively, the total energy
consumption of the circuit can be reduced in order of 5-10% (Jankovic et al, 2004). This is an
attractive upgrade option due to relatively low capital investment for the Barmac crusher.
Clinker pre-crushing can be carried out with different crushers. Figure 9 shows the product size
distribution of the closed Barmac and HP cone crusher circuits with 4.75 mm screen at 2.3 kWh/t
specific energy input. Although the 80% passing size for the HP cone crusher is finer, the Barmac
product is potentially more favorable due to higher content of fines. This advantage however is
not crucial for the selection as the clinker feed size, hardness and abrasivity, as well as the
required capacity, may favor the selection of the particular crusher.
0
10
20
30
40
50
60
70
80
90
100
0.01 0.1 1 10 100
size (mm)
cum
ula
tive
% p
assi
ng
HP cone, 2.3 kWh/t, productBarmac, 2.3 kWh/t, product
HP cone feedBarmac feed
Figure 9 Product size distribution from the closed Barmac and HP cone crusher circuit
In order to obtain the most efficient breakage in the first compartment of the ball mill after
introduction of the pre-crushing stage, the ball size distribution should be selected according to
the particle size distribution of the material fed to the mill. The particle size distribution of the
combined ball mill feed (new feed + 150% recycle) with raw and pre-crushed clinker is shown in
Figure 10. It can be observed that there is a significant fraction of the material coarser than 5 mm
in the feed containing the raw clinker. For such feed, top size ball required would be 90-100 mm
according to Bond formula. For pre-crushed feed the top ball size would be 35-40 mm due to
absence of coarse particles. Therefore, if the feed to the ball mill is pre-crushed, ball charge in the
first compartment has to be optimized to maximize grinding efficiency.
In addition to ball size optimization, the optimum length ratio between the first and second
compartment would be affected. Design of the transfer grate, mill liners and sweep air velocity
should be also reviewed for reduced ball size in order to provide efficient removal of fine
particles.
0
2
4
6
8
10
12
14
16
18
0.01 0.1 1 10 100size (mm)
% r
etai
ned
raw clinkerpre-crushed clinker
Particle size (mm)
Optimum ball size
(mm) Raw clinker
(% ret)
Pre-crushed clinker (% ret)
37.5 142 0.20 0 25 116 0.53 0 19 101 3.71 0
13.7 90 6.30 0 9.5 71 4.15 0
4.75 50 10.28 0.40 2.36 36 7.50 9.65 1.18 25 2.86 11.26 0.6 18 0.94 4.74 0.3 13 4.63 4.40
0.15 9 3.821 6.83 0.075 6 13.92 16.12 0.053 / 9.82 9.89 0.038 / 8.17 8.63 0.032 / 3.41 3.84 0.025 / 3.97 4.60 0.01 / 8.27 9.53
0 / 7.49 10.10
0
2
4
6
8
10
12
14
16
18
0.01 0.1 1 10 100size (mm)
% r
etai
ned
raw clinkerpre-crushed clinker
Particle size (mm)
Optimum ball size
(mm) Raw clinker
(% ret)
Pre-crushed clinker (% ret)
37.5 142 0.20 0 25 116 0.53 0 19 101 3.71 0
13.7 90 6.30 0 9.5 71 4.15 0
4.75 50 10.28 0.40 2.36 36 7.50 9.65 1.18 25 2.86 11.26 0.6 18 0.94 4.74 0.3 13 4.63 4.40
0.15 9 3.821 6.83 0.075 6 13.92 16.12 0.053 / 9.82 9.89 0.038 / 8.17 8.63 0.032 / 3.41 3.84 0.025 / 3.97 4.60 0.01 / 8.27 9.53
0 / 7.49 10.10
Figure 10 Combined ball mill feed size distribution with raw and pre-crushed clinker
In last 20 years High Pressure Grinding Rolls (HPGR) are being extensively used in cement
grinding circuit mainly due to higher grinding efficiency compared to conventional two
compartment tube mills. HPGR can be used for pre-crushing, finish grinding, hybrid grinding and
semi finish grinding. Table 2 shows the energy consumption of five cement grinding circuit with
different HPGR application (Aydogan et al, 2003). It can be observed that the overall circuit
specific energy consumption decreases when larger portion of size reduction (higher HPGR
kWh/t) is done by HPGR. Compared to circuit utilizing the ball mill only for grinding, energy
savings in excess of 40% are achievable providing that circuit is optimized and automated
process control is applied.
Table 2 Specific energy consumption in different cement grinding circuit utilising HPGR
Cement Grinding Circuit DescriptionHPGR
specific energy consumption
(kWh/t)
Circuit overall specific energy consumption
(kWh/t)Open circuit HPGR, closed circuit ball mill 4.05 34.2Open circuit HPGR with partial recycling, closed circuit ball mill
8.9 29.6
Hybrid grinding / 29.9Closed circuit HPGR, closed circuit ball mill 8.0 21.7Semi-Finish grinding 9.8 23.0
In order to assess the performance of a particular cement grinding circuit and to compare
efficiency of different circuit configurations, complete audits are required. The audit includes
monitoring and sampling different circuit streams during the steady state operation, as well as
mill inspection and sampling after the crush-stop. Based on information obtained from the audit
circuit mass balance can be carried out to determine material flows (solids and air) around the
circuit. Only after this the detailed performance of the circuit as well as individual equipment can
be assessed and potential bottlenecks identified. To assist with circuit optimization, site and
equipment specific models are calibrated based on the results from the audit. Models can be then
used to simulate different operating conditions and circuit scenarios (Benzer et al, 2001, 2003).
CONCLUSION
The current world consumption of cement is close to 2 billion tonnes per annum and it is
increasing at about 1% per annum. The electrical energy consumed in the conventional cement
making process is approximately 110 kWh/tonne, and around 40% of this energy is consumed for
clinker grinding.
For most of the twentieth century, the dry grinding circuits for the production of finished cement
from cement clinker consist of two-compartment tube mills and the air separators. Alternative
mills such as High Pressure Grinding Rolls (HPGR), Vertical Roller Mill and HOROMILL has
been applied in recent times in order to improve the grinding efficiency. Significant energy
savings are reported in applications of these mills, HPGR being the most widely used.
Air separators were improved over the time from very inefficient static separators to high
efficiency dynamic separators. They play crucial role in improving overall energy efficiency of
the cement grinding circuits.
The increasing demand for “finer cement” products, and the need for reduction in energy
consumption and green house gas emissions, reinforces the need for grinding optimisation. In the
last two decade significant progress has been achieved by new equipment design and new circuit
configuration. Introduction of clinker pre-crushing stage can significantly improve the energy
efficiency. Due to relatively low capital cost Barmac crusher is an attractive upgrade option.
Hybrid grinding circuits with HPGR are being widely used primarily due to higher energy
efficiency, with specific energy consumption reduced to almost 50% compared to some
conventional circuits.
In order to optimize grinding circuit, detailed knowledge of circuit operation is required.
Modelling and simulation techniques can be effectively utilized to assist in process optimization.
REFERENCE AND BIBLIOGRAPHY
Benzer H., Ergun L., Oner M. and Lynch A.J. 2001. Simulation of Open Circuit Clinker Grinding. Minerals Engineering, vol 14. No 7, pp 701-710.
Benzer H., Ergun L., Oner M. and Lynch A.J. 2003.Case Studies of Models of Tube Mill and Air Separator Grinding Circuits, Proceedings: XXII International Mineral Processing Congress, Chief Editors: L. Lorenzen and D.J. Bradshaw, pp 1524-1533.
Brunelli G., 2001, A proven partnership, Int. Cement Review, February,37-40.
Buzzi S., 1997, The Horomill, ZKG International, Nr 3, 127-138.
Duda W. H., 1985, Cement Data Book-International Process Engineering in the Cement Industry, 3rd Ed., Bauwerlag GMBH, 302 pages.
Dupuis J. and Rhin C., 2003, Increased grinding capacity at R.A.K., World Cement, February, 79-83.
Feige et al; 1983 Energy-saving manufacture of standard cements in roller mills with external material circuation, ZKG, 11/83, 628-632.
Fochardiere R., 1999, Horomill: One year’s operating experience , World Cement, September, 98-104.
Fujimoto S., 1993, Reducing Specific power Usage in Cement Plants, World Cement, No. 7, 25-35
Gouda G.R., 1981, Technical Aspects of Comminution in the Cement Industry-Part 1, World Cement Technology, April, 112-122
Cordonnier A., 1994, The Horomill-A New Finish Grinding Mill, ZKG, No. 11, 643-647
Cornille J.P., 1999, Horomill: Latest Developments and Results, European Cement Conference 1999, 21.1-21.2
Ellerbrock H.G., 1994, High Pressure Grinding Rolls, ZKG, No.4, 1047-1101998 FLS Comminution Manual
Jankovic, A., Valery Jnr., W. and Davis, E. (2004) Cement Grinding Optimisation, Minerals Engineering Journal, Vol.17 No.11-12, 2004
Kellerwessel H. A. M., 1996, High pressure particle bed comminution. State of the art, application, recent developments, Engineering and Mining Journal, Feb., p45-52.
Klumpar et al; 1986, Air Classifiers, Chemical Engineering, March, 77-92.
Marchal G., 1995, FCB breaks into Asian market with Horomill, World Cement, September, 23-25.
Miranda R.F. et al., 1998, Brazilian progress in grinding, World cement, May,40-42.
Namik A.A, Levent E., Benzer H., 2004. High Pressure Grinding Rolls (HPGR) Application in the Cement Industry. Presented at JKMRC International Conference, Brisbane, Australia
Nobis E.; 2001, Experience with grinding slag and clinker in a Loesche mill, ZKG, Vol. 54, No 4,196-204.
Odler I,; Chen Y., 1995, Influence of the method of comminution on the properties of the cement, ZKG, vol 48, No 9, 496-500.
Roseman H., 1989, Investigations on a high pressure grinding roll mill used for cement grinding, ZKG, Vol. 42, No 6, 142-144.
Schimoide K, 1996, Cement grinding by vertical roller mill, World cement, September, 68-74.
Schnatz R.and Knobloch O.; 2000, Influence of the ball filling factor on the power consumption and throughput of ball mills in combined grinding plants
Schoenert K., 1979, Verfahren zur Fein- und Feinstzerkleinerung von Materialien sproden Stoffverhaltens, German Patent DP 2708053.
Sutoh K. et al., 1992, Current report on preliminary grinding of clinker and raw material using the CKP system, Zement Kalk Gibs, No. 3, p. 94-96.