Upload
vodat
View
214
Download
0
Embed Size (px)
Citation preview
17304 PRESTON ROAD, SUITE 800 DALLAS TEXAS 75252PHONE: 214-438-3662 FAX: 214-438-3663
Southern California Consolidation Project
Riverside, California
Master Plan Preliminary Construction Cost Estimate - 6th RevisionNovember 4, 2016
Clarke Project No. 16-1016
California Air Resources Board
Prepared by Clarke Sheet 2 of 74
Southern California Consolidation ProjectCalifornia Air Resources BoardMaster Plan Preliminary Construction Cost Estimate - 6th Revision November 4, 2016
Conceptual Site Plan, 1 page, not datedReview Comments, 2 documents, not datedAdditional Review Comments (via e-mails)
Performance Criteria Report, 477 pages, dated August 19, 2016Narratives, all disciplines, various dates and page counts
Basis for QuantitiesWherever possible, this estimate has been based upon the actual measurement of different items of work. For the remaining items, parametric measurements were used in conjunction with references from other projects of a similar nature.
In general, this estimate has been prepared from documents provided by HED and received by Clarke Project Solutions through October 6, 2016. These documents include:
Further information was obtained through discussions with the design team Architects, Engineers, and Consultants.
Method of ProcurementIt is our understanding that the cost of design and construction will be bid by three to four qualified local design-builders.
Bid ConditionsThis estimate has been based upon competitive bid situations (minimum of 3 bidders) for all items of subcontracted work.
Estimate FormatA component cost classification format (UNIFORMAT) has been used for the preparation of this estimate. It classifies costs by building system, or element, rather than trade. Because building systems remain relatively consistent from building to building, regardless of functional use or type of construction, this component format provides the necessary means for cost planning. Efforts have been made to keep our format similar to that used by the general contractor, so that reconciliations can easily be done.
Construction ScheduleCosts as included herein have been based upon a reasonable construction period. Any costs for excessive overtime to meet stringent milestone dates are not included in this estimate.
INTRODUCTION
Purpose of EstimateThis preliminary estimate has been prepared, pursuant to an agreement between HED and Clarke Project Solutions, for the purpose of establishing a probable cost of construction prior to Conceptual Design.
Project DescriptionThis estimate encompasses those costs related to the construction of a new emissions testing facility for the California Air Resources Board in Southern California. The project includes five buildings of approximately 349,030 square feet and related adjacent site development work (on 18.8 acres).
Basis of Estimate
Prepared by Clarke Sheet 3 of 74
Southern California Consolidation ProjectCalifornia Air Resources BoardMaster Plan Preliminary Construction Cost Estimate - 6th Revision November 4, 2016
INTRODUCTION
A Professional fees as stated herein.
Items Included in the Estimate
Estimate ContingencyAn allowance of 9% for undeveloped design details has been included in the summary of this document. As the design of each system is further developed, details which historically increase cost became apparent and must be incorporated into the estimate. This allowance is intended to cover the cost of such details.
General Contractor's Overhead and ProfitJobsite general conditions, home office overhead, profit, and bond are shown on the summaries for each building of this estimate. It is our opinion that for this project, a cunulative rate of 17% is appropriate to cover these mark-ups.
Sources for PricingThis estimate was prepared by a team of qualified cost consultants experienced in estimating construction costs at all stages of design. These consultants have used pricing data from Clarke Project Solutions' database for research facility construction, updated to reflect current conditions in the Southern California area. In some cases, quotes may have been solicited from outside sources to substantiate in-house pricing data.
Escalation Allowance
Items which are detailed in the backup to this estimate include the following:
Prices included herein are reflective of current prices. They do not have escalation included to the midpoint of construction if the project were to be bid today.
Construction ContingencyIt is prudent for all program budgets to include an allowance for change orders which occur during construction. These change orders normally increase the cost of the project. It is recommended that the Owner, in their program budget, carry a percentage of anywhere from 2% to 5% of the construction cost for this construction contingency.
Subcontractor's Mark-upsAs stated earlier, subcontractor’s mark-ups have been included in each line item unit cost. Depending on the trade, these mark-ups can range from 25% to 35% of the raw cost for that particular item of work.
Basis for Unit CostsUnit costs as contained herein are based on current bid prices in the Southern California area. Subcontractor’s overhead and profit is included in each line item unit cost. This overhead and profit covers each subcontractor’s cost for labor burden, field overhead, home office overhead, and profit. The general contractor’s overhead and profit is shown separately on the Summary.
Design-Builder's ContingencyAn allowance of 3% for undeveloped design details has been included in the Buildings and Site Summary of this document. As the design of each system is further developed, details which historically increase cost became apparent and must be incorporated into the estimate. This allowance is intended to cover the cost of such details.
Design-Builder's Design FeeThere is a fee allowance of 4.25% for design services provided by the design-builder. This, too, is found in the Buildings and Site Summary of this document.
Prepared by Clarke Sheet 4 of 74
Southern California Consolidation ProjectCalifornia Air Resources BoardMaster Plan Preliminary Construction Cost Estimate - 6th Revision November 4, 2016
INTRODUCTION
B
CD
A Land acquisition and real estate fees.B Owner’s field inspection costs.C Program or project manager’s fees.D Costs of hazardous material surveys, abatements, and disposals unless noted in estimate.E Major site and building structures demolition unless noted in body of estimate.F Blasting or excavation of rock.G Buried utility relocation.H Below grade utility tunnels.I Costs of offsite construction unless noted in estimate (i.e. central plant upgrades, road improvements, etc.).
JK Phone system.L Low voltage systems equipment (cable installation is included).M Artwork or public art.N Escalation beyond today's date.O Move-in costs or maintenance costs after move-in.
ABCD
EF
Design and estimating contingency allowances.
Items which are not included in this estimate are:
Foundations, superstructure, exterior closure, roofing, interior construction, stairs, interior finishes, conveying, plumbing, HVAC, fire protection, electrical, equipment, site preparation, site improvements, and site utilities as detailed on plans and outline specifications referred to herein.Subcontractor’s and general contractor’s mark-ups.
Furnishings, fixtures, and equipment (FF&E) except built-in cabinets, counters, and other casework normally provided by a General Contractor.
Unforeseen sub-surface conditions.Restrictive technical specifications or excessive contract conditions.
Any other non-competitive bid situations.Bids delayed beyond the projected schedule.
Any specified item of equipment, material, or product that cannot be obtained from at least three different sources.
Clarke Project Solutions has no control over the cost of labor and materials, the general contractor’s or any subcontractor’s method of determining prices, or competitive bidding and market conditions. This opinion of the probable cost of construction is made on the basis of the experience, qualifications, and best judgment of a professional consultant familiar with the construction industry. Clarke Project Solutions, however, cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from this or subsequent cost estimates.
Clarke Project Solutions has no control over the quality, completeness, intricacy, constructability, or coordination of design documents. Clarke Project Solutions also has no control over the amount of funds available for the project. We, therefore, cannot be responsible for any design revision costs incurred in the event that this estimate is in excess of the budget.
Statement of Probable Cost
Items which may change the estimated construction cost include, but are not limited to:
Items Excluded from the Estimate
Items Affecting the Cost Estimate
Modifications to the scope of work included in this estimate.
Prepared by Clarke Sheet 5 of 74
Southern California Consolidation ProjectCalifornia Air Resources BoardMaster Plan Preliminary Construction Cost Estimate - 6th Revision November 4, 2016
INTRODUCTION
Our opinion of the total cost of the project prior to design, based on all information stated herein, is:
$240,716,420
Clarke Project Solutions recommends that the Owner and the Architect carefully review this entire document to insure that it reflects their design intent. Requests for modifications of any apparent errors or omissions to this document must be made to Clarke Project Solutions within ten days of receipt of this estimate. Otherwise, it will be understood that the contents have been concurred with and accepted. If the project is over budget, or there are unresolved budgeting issues, alternate systems/schemes should be evaluated before proceeding into further design phases.
It is recommended that there are preparations of further cost estimates throughout design by Clarke Project Solutions to determine overall cost changes since the preparation of this rough order of magnitude estimate. These future estimates will have detailed breakdowns indicating materials by type, kind, and size, priced by their respective units of measure.
It is also recommended that a detailed construction schedule be developed to confirm that fact that the current schedule is a reasonable allowance for construction activities.
Total Project Cost
Clarke Project Solutions' staff of professional cost consultants has prepared this estimate in accordance with generally accepted principles and practices. This staff is available to discuss its contents with any interested party.
Recommendations for Cost Control
Prepared by Clarke Sheet 6 of 74
Southern California Consolidation ProjectCalifornia Air Resources BoardMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Buildings TotalSchedule of Areas GSF SF
Enclosed Areas Building Basement MezzanineOffice 63,824 0 0 63,824 sfChemistry 41,631 0 0 41,631 sfLight Duty Testing 64,500 17,159 35,490 117,149 sfHeavy Duty and OBD Testing / PEMS / Penthouse 44,400 12,240 27,179 83,819 sfCentral Plant 5,850 0 0 5,850 sfASD Building Support 22,243 0 0 22,243 sfShared Facilities and Visitor Center 36,392 0 0 36,392 sfShared Testing 12,152 0 0 12,152 sf
Subtotal, Enclosed Areas 290,992 29,399 62,669 383,060 sf 383,060
Total Gross Floor Area 383,060
Schedule of Areas & Control Quantities
Prepared by Clarke Sheet 7 of 74
Southern California Consolidation ProjectCalifornia Air Resources BoardMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
BUILDINGS & SITE SUMMARY
Element Area Cost/SF Total
Office 63,824 SF $422.43 $26,960,954
Chemistry 41,631 SF $561.75 $23,386,393
Light Duty Testing 117,149 SF $337.17 $39,499,620
Heavy Duty and OBD Testing / PEMS / Penthouse 83,819 SF $349.02 $29,254,209
Central Plant 5,850 SF $2,682.12 $15,690,418
ASD Building Support 22,243 SF $271.99 $6,049,822
Shared Facilities and Visitor Center 36,392 SF $483.26 $17,586,867
Shared Testing 12,152 SF $514.26 $6,249,293
SUBTOTAL - BUILDINGS 383,060 SF $429.90 $164,677,574
Site Work 818,928 SF $72.66 $59,500,135
TOTAL ESTIMATED CONSTRUCTION COST $224,177,710
OTHER COSTSDesign-Builder's Contingency (Allow 3.00%) $6,725,331Design-Builder's Design Fee (Allow 4.25%) $9,813,379
SUBTOTAL OTHER COSTS $16,538,711
TOTAL PROJECT COST $240,716,420
Prepared by Clarke Sheet 8 of 74
Southern California Consolidation ProjectOfficeMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Office Construction Cost Summary
Element Total Cost / SF
1 Foundations $790,354 $12.38
2 Substructure $430,812 $6.75
3 Superstructure $1,791,332 $28.07
4 Exterior Closure $4,899,366 $76.76
5 Roofing $586,117 $9.18
6 Interior Construction $4,978,272 $78.00
7 Conveying $103,009 $1.61
8 Mechanical $3,615,630 $56.65
9 Electrical $3,743,278 $58.65
10 General Conditions & Profit
11 Equipment $146,795 $2.30
12 Sitework $50,271 $0.79
Subtotal $21,135,236 $331.15
General Conditions 10.0% $2,113,524 $33.11
Subtotal $23,248,759 $364.26
General Contractor OH & P 4.0% $929,950 $14.57
Subtotal $24,178,709 $378.83
Bonds & Insurance 2.3% $556,110 $8.71
Subtotal $24,734,820 $387.55
Estimate Contingency 9.0% $2,226,134 $34.88
SUBTOTAL - ESTIMATED CONSTRUCTION COST $26,960,954 $422.43
Total Area: 63,824 SF
Prepared by Clarke Sheet 9 of 74
Southern California Consolidation ProjectOfficeMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Office Component Summary
Element Subtotal Total Cost / SF Cost / SF
1 Foundations $790,354 $12.38011 Standard Foundations $481,871 $7.55012 Special Foundations $308,483 $4.83
2 Substructure $430,812 $6.75021 Slab on Grade $430,812 $6.75022 Basement Excavation023 Basement Walls
3 Superstructure $1,791,332 $28.07031 Floor Construction $997,787 $15.63032 Roof Construction $477,616 $7.48033 Stair Construction $315,929 $4.95
4 Exterior Closure $4,899,366 $76.76041 Exterior Walls $3,606,930 $56.51042 Exterior Doors / Windows $1,292,436 $20.25
5 Roofing $586,117 $9.18050 Roofing $586,117 $9.18
6 Interior Construction $4,978,272 $78.00061 Partitions $1,901,955 $29.80062 Interior Finishes $2,023,221 $31.70063 Specialties $516,974 $8.10064 Interior Doors & Windows $536,122 $8.40
7 Conveying $103,009 $1.61070 Conveying $103,009 $1.61
8 Mechanical $3,615,630 $56.65081 Plumbing $976,507 $15.30082 HVAC $2,288,090 $35.85083 Fire Protection $351,032 $5.50084 Special Mechanical
9 Electrical $3,743,278 $58.65091 Standard Electrical $3,743,278 $58.65092 Special Electrical
10 General Conditions and Overhead & Profit N/A100 General Conditions and Overhead & Profit (Included at Summary Level) N/A
11 Equipment $146,795 $2.30111 Fixed / Movable Equipment $76,589 $1.20112 Furnishings $70,206 $1.10113 Special Construction
12 Sitework $50,271 $0.79 121 Site Preparation $50,271 $0.79 122 Site Improvements
123 Site Utilities124 Off-Site Work
Total Net Cost $21,135,236 $331.15
Prepared by Clarke Sheet 10 of 74
Southern California Consolidation ProjectOfficeMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Office Detail Elements
Element Quantity Unit Unit Cost Total
011 Standard Foundations
Standard FoundationsFootings, foundations , thickened slabs, etc. 21,275 sf $22.65 $481,871
Total - 011 Standard Foundations $481,871
012 Special Foundations
Special FoundationsElevator pits, sump pits, drilled piers, etc. 21,275 sf $14.50 $308,483
Total - 012 Special Foundations $308,483
021 Slab on Grade
Slab on GradeLowest floor construction 21,275 sf $20.25 $430,812
Total - 021 Slab on Grade $430,812
023 Basement Walls
Basement WallsWalls, framing, etc. N/A
Total - 023 Basement Walls
031 Floor Construction
Elevated Floors and FramingFloor construction 42,550 sf $23.45 $997,787
Total - 031 Floor Construction $997,787
032 Roof Construction
Roof ConstructionRoof framing, deck 21,275 sf $22.45 $477,616Structure for PV panels, with Site Work sf $30.00
Total - 032 Roof Construction $477,616
Prepared by Clarke Sheet 11 of 74
Southern California Consolidation ProjectOfficeMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Office Detail Elements
Element Quantity Unit Unit Cost Total
033 Stair Construction
Stair ConstructionStairs, handrails, etc. 63,824 sf $4.95 $315,929
Total - 033 Stair Construction $315,929
041 Exterior Walls
Exterior Wall System Framing and walls 43,800 sf $82.35 $3,606,930
Total - 041 Exterior Walls $3,606,930
042 Exterior Doors / Windows
Exterior Doors Exterior doors and windows 63,824 sf $20.25 $1,292,436
Total - 042 Exterior Doors / Windows $1,292,436
050 Roofing
Roofing, Including InsulationRoofing, insulation, sheet metal, etc. 21,275 sf $27.55 $586,117
Total - 050 Roofing $586,117
061 Partitions
Interior PartitionsCMU, drywall partitions, etc. 63,824 sf $29.80 $1,901,955
Total - 061 Partitions $1,901,955
062 Interior Finishes
Floor FinishesSealed concrete, resilient, carpet, ceramic, etc. 63,824 sf $10.20 $651,005
BaseResilient base, wood, ceramic, etc. 63,824 sf $0.70 $44,677
Prepared by Clarke Sheet 12 of 74
Southern California Consolidation ProjectOfficeMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Office Detail Elements
Element Quantity Unit Unit Cost Total
Wall FinishesPaint walls, ceramic tile, acoustical panels, etc. 63,824 sf $6.55 $418,047
Ceiling FinishesPaint structure above, drywall, acoustical tile, etc. 63,824 sf $14.15 $903,110
MiscellaneousUnistrut, access panels, etc. 63,824 sf $0.10 $6,382
Total - 062 Interior Finishes $2,023,221
063 Specialties
SpecialtiesMillwork, bath accessories, lockers, etc. 63,824 sf $8.10 $516,974
Total - 063 Specialties $516,974
064 Interior Doors & Windows
Interior Doors and WindowsDoors, frames, and hardware 63,824 sf $8.40 $536,122
Total - 064 Interior Doors & Windows $536,122
070 Conveying
ElevatorsPassenger elevator, 3 stops, including finishes 1 ea $103,009.00 $103,009
Total - 070 Conveying $103,009
081 Plumbing
PlumbingRough in, fixtures, water, drainage, etc. 63,824 sf $15.30 $976,507
Total - 081 Plumbing $976,507
082 HVAC
HVAC
Prepared by Clarke Sheet 13 of 74
Southern California Consolidation ProjectOfficeMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Office Detail Elements
Element Quantity Unit Unit Cost Total
Equipment, ductwork, controls, etc. 63,824 sf $35.85 $2,288,090
Total - 082 HVAC $2,288,090
083 Fire Protection
Fire ProtectionAutomatic sprinkler system (no fire pumps) 63,824 sf $5.50 $351,032
Total - 083 Fire Protection $351,032
091 Standard Electrical
Service and DistributionService and distribution 63,824 sf $19.80 $1,263,715
Lighting and PowerFixtures and fittings 63,824 sf $14.85 $947,786
Special Systems PA/VE 63,824 sf $24.00 $1,531,776PV panel system, with Site Work sf $20.20
Total - 091 Standard Electrical $3,743,278
111 Fixed / Movable Equipment
EquipmentFixed and movable equipment 63,824 sf $1.20 $76,589
Total - 111 Fixed / Movable Equipment $76,589
112 Furnishings
FurnishingsFurniture and furnishings, window blinds, etc. 63,824 sf $1.10 $70,206
Total - 112 Furnishings $70,206
121 Site Preparation
DemolitionRemove pavings, utilities, fixtures, etc. N/A
Prepared by Clarke Sheet 14 of 74
Southern California Consolidation ProjectOfficeMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Office Detail Elements
Element Quantity Unit Unit Cost Total
ExcavationOverexcavate and recompact 8,667 cy $5.80 $50,271
Total - 121 Site Preparation $50,271
122 Site Improvements
Site ImprovementsPavings, landscaping, etc. N/A
Total - 122 Site Improvements
123 Site Utilities
Site UtilitiesUnderground utilities, electrical, etc. N/A
Total - 123 Site Utilities
123 Offsite
Offsite WorkOffsite improvements and utilities N/A
Total - 123 Offsite
Prepared by Clarke Sheet 15 of 74
Southern California Consolidation ProjectChemistryMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Chemistry Construction Cost Summary
Element Total Cost / SF
1 Foundations $730,624 $17.55
2 Substructure $421,514 $10.13
3 Superstructure $1,161,505 $27.90
4 Exterior Closure $3,231,178 $77.61
5 Roofing $573,467 $13.78
6 Interior Construction $5,690,958 $136.70
7 Conveying $103,009 $2.47
8 Mechanical $3,282,604 $78.85
9 Electrical $2,368,804 $56.90
10 General Conditions & Profit
11 Equipment $720,216 $17.30
12 Sitework $49,186 $1.18
Subtotal $18,333,065 $440.37
General Conditions 10.0% $1,833,307 $44.04
Subtotal $20,166,372 $484.41
General Contractor OH & P 4.0% $806,655 $19.38
Subtotal $20,973,026 $503.78
Bonds & Insurance 2.3% $482,380 $11.59
Subtotal $21,455,406 $515.37
Estimate Contingency 9.0% $1,930,987 $46.38
SUBTOTAL - ESTIMATED CONSTRUCTION COST $23,386,393 $561.75
Total Area: 41,631 SF
Prepared by Clarke Sheet 16 of 74
Southern California Consolidation ProjectChemistryMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Chemistry Component Summary
Element Subtotal Total Cost / SF Cost / SF
1 Foundations $730,624 $17.55011 Standard Foundations $471,471 $11.33012 Special Foundations $259,153 $6.23
2 Substructure $421,514 $10.13021 Slab on Grade $421,514 $10.13022 Basement Excavation023 Basement Walls
3 Superstructure $1,161,505 $27.90031 Floor Construction $488,123 $11.73032 Roof Construction $467,308 $11.23033 Stair Construction $206,073 $4.95
4 Exterior Closure $3,231,178 $77.61041 Exterior Walls $2,388,150 $57.36042 Exterior Doors / Windows $843,028 $20.25
5 Roofing $573,467 $13.78050 Roofing $573,467 $13.78
6 Interior Construction $5,690,958 $136.70061 Partitions $1,665,240 $40.00062 Interior Finishes $1,452,922 $34.90063 Specialties $2,289,705 $55.00064 Interior Doors & Windows $283,091 $6.80
7 Conveying $103,009 $2.47070 Conveying $103,009 $2.47
8 Mechanical $3,282,604 $78.85081 Plumbing $1,273,909 $30.60082 HVAC $1,711,034 $41.10083 Fire Protection $297,662 $7.15084 Special Mechanical
9 Electrical $2,368,804 $56.90091 Standard Electrical $2,368,804 $56.90092 Special Electrical
10 General Conditions and Overhead & Profit N/A100 General Conditions and Overhead & Profit (Included at Summary Level) N/A
11 Equipment $720,216 $17.30111 Fixed / Movable Equipment $661,933 $15.90112 Furnishings $58,283 $1.40113 Special Construction
12 Sitework $49,186 $1.18 121 Site Preparation $49,186 $1.18 122 Site Improvements
123 Site Utilities124 Off-Site Work
Total Net Cost $18,333,065 $440.37
Prepared by Clarke Sheet 17 of 74
Southern California Consolidation ProjectChemistryMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Chemistry Detail Elements
Element Quantity Unit Unit Cost Total
011 Standard Foundations
Standard FoundationsFootings, foundations , thickened slabs, etc. 20,816 sf $22.65 $471,471
Total - 011 Standard Foundations $471,471
012 Special Foundations
Special FoundationsElevator pits, sump pits, drilled piers, etc. 20,816 sf $12.45 $259,153
Total - 012 Special Foundations $259,153
021 Slab on Grade
Slab on GradeLowest floor construction 20,816 sf $20.25 $421,514
Total - 021 Slab on Grade $421,514
023 Basement Walls
Basement WallsWalls, framing, etc. N/A
Total - 023 Basement Walls
031 Floor Construction
Elevated Floors and FramingFloor construction 20,816 sf $23.45 $488,123
Total - 031 Floor Construction $488,123
032 Roof Construction
Roof ConstructionRoof framing, deck 20,816 sf $22.45 $467,308Structure for PV panels, with Site Work sf $30.00
Total - 032 Roof Construction $467,308
Prepared by Clarke Sheet 18 of 74
Southern California Consolidation ProjectChemistryMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Chemistry Detail Elements
Element Quantity Unit Unit Cost Total
033 Stair Construction
Stair ConstructionStairs, handrails, etc. 41,631 sf $4.95 $206,073
Total - 033 Stair Construction $206,073
041 Exterior Walls
Exterior Wall System Framing and walls 29,000 sf $82.35 $2,388,150
Total - 041 Exterior Walls $2,388,150
042 Exterior Doors / Windows
Exterior Doors Exterior doors and windows 41,631 sf $20.25 $843,028
Total - 042 Exterior Doors / Windows $843,028
050 Roofing
Roofing, Including InsulationRoofing, insulation, sheet metal, etc. 20,816 sf $27.55 $573,467
Total - 050 Roofing $573,467
061 Partitions
Interior PartitionsCMU, drywall partitions, etc. 41,631 sf $40.00 $1,665,240
Total - 061 Partitions $1,665,240
062 Interior Finishes
Floor FinishesSealed concrete, resilient, carpet, ceramic, etc. 41,631 sf $12.25 $509,980
BaseResilient base, wood, ceramic, etc. 41,631 sf $0.80 $33,305
Prepared by Clarke Sheet 19 of 74
Southern California Consolidation ProjectChemistryMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Chemistry Detail Elements
Element Quantity Unit Unit Cost Total
Wall FinishesPaint walls, ceramic tile, acoustical panels, etc. 41,631 sf $7.60 $316,396
Ceiling FinishesPaint structure above, drywall, acoustical tile, etc. 41,631 sf $14.15 $589,079
MiscellaneousUnistrut, access panels, etc. 41,631 sf $0.10 $4,163
Total - 062 Interior Finishes $1,452,922
063 Specialties
SpecialtiesMillwork, bath accessories, lockers, etc. 41,631 sf $55.00 $2,289,705
Total - 063 Specialties $2,289,705
064 Interior Doors & Windows
Interior Doors and WindowsDoors, frames, and hardware 41,631 sf $6.80 $283,091
Total - 064 Interior Doors & Windows $283,091
070 Conveying
ElevatorsPassenger elevator, 3 stops, including finishes 1 ea $103,009.00 $103,009
Total - 070 Conveying $103,009
081 Plumbing
PlumbingRough in, fixtures, water, drainage, etc. 41,631 sf $30.60 $1,273,909
Total - 081 Plumbing $1,273,909
082 HVAC
HVAC
Prepared by Clarke Sheet 20 of 74
Southern California Consolidation ProjectChemistryMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Chemistry Detail Elements
Element Quantity Unit Unit Cost Total
Equipment, ductwork, controls, etc. 41,631 sf $41.10 $1,711,034
Total - 082 HVAC $1,711,034
083 Fire Protection
Fire ProtectionAutomatic sprinkler system 41,631 sf $7.15 $297,662
Total - 083 Fire Protection $297,662
091 Standard Electrical
Service and DistributionService and distribution 41,631 sf $19.80 $824,294
Lighting and PowerFixtures and fittings 41,631 sf $14.85 $618,220
Special Systems Fire alarm, telephone/data, security, grounding, and PA/VE 41,631 sf $22.25 $926,290PV panel system, with Site Work sf $20.20
Total - 091 Standard Electrical $2,368,804
111 Fixed / Movable Equipment
EquipmentFixed and movable equipment 41,631 sf $15.90 $661,933
Total - 111 Fixed / Movable Equipment $661,933
112 Furnishings
FurnishingsFurniture and furnishings, window blinds, etc. 41,631 sf $1.40 $58,283
Total - 112 Furnishings $58,283
121 Site Preparation
DemolitionRemove pavings, utilities, fixtures, etc. N/A
Prepared by Clarke Sheet 21 of 74
Southern California Consolidation ProjectChemistryMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Chemistry Detail Elements
Element Quantity Unit Unit Cost Total
ExcavationOverexcavate and recompact 8,480 cy $5.80 $49,186
Total - 121 Site Preparation $49,186
122 Site Improvements
Site ImprovementsPavings, landscaping, etc. N/A
Total - 122 Site Improvements
123 Site Utilities
Site UtilitiesUnderground utilities, electrical, etc. N/A
Total - 123 Site Utilities
123 Offsite
Offsite WorkOffsite improvements and utilities N/A
Total - 123 Offsite
Prepared by Clarke Sheet 22 of 74
Southern California Consolidation ProjectLight Duty TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Light Duty Testing Construction Cost Summary
Element Total Cost / SF
1 Foundations $2,263,950 $19.33
2 Substructure $1,721,526 $14.70
3 Superstructure $3,963,502 $33.83
4 Exterior Closure $3,257,550 $27.81
5 Roofing $1,776,975 $15.17
6 Interior Construction $5,392,927 $46.03
7 Conveying $94,200 $0.80
8 Mechanical $5,590,311 $47.72
9 Electrical $5,165,282 $44.09
10 General Conditions & Profit
11 Equipment $1,461,508 $12.48
12 Sitework $276,819 $2.36
Subtotal $30,964,549 $264.32
General Conditions 10.0% $3,096,455 $26.43
Subtotal $34,061,004 $290.75
General Contractor OH & P 4.0% $1,362,440 $11.63
Subtotal $35,423,444 $302.38
Bonds & Insurance 2.3% $814,739 $6.95
Subtotal $36,238,183 $309.33
Estimate Contingency 9.0% $3,261,436 $27.84
SUBTOTAL - ESTIMATED CONSTRUCTION COST $39,499,620 $337.17
Total Area: 117,149 SF
Prepared by Clarke Sheet 23 of 74
Southern California Consolidation ProjectLight Duty TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Light Duty Testing Component Summary
Element Subtotal Total Cost / SF Cost / SF
1 Foundations $2,263,950 $19.33011 Standard Foundations $1,460,925 $12.47012 Special Foundations $803,025 $6.85
2 Substructure $1,721,526 $14.70021 Slab on Grade $1,306,125 $11.15022 Basement Excavation023 Basement Walls $415,401 $3.55
3 Superstructure $3,963,502 $33.83031 Floor Construction $1,853,245 $15.82032 Roof Construction $1,770,525 $15.11033 Stair Construction $339,732 $2.90
4 Exterior Closure $3,257,550 $27.81041 Exterior Walls $2,614,613 $22.32042 Exterior Doors / Windows $642,938 $5.49
5 Roofing $1,776,975 $15.17050 Roofing $1,776,975 $15.17
6 Interior Construction $5,392,927 $46.03061 Partitions $2,580,000 $22.02062 Interior Finishes $869,613 $7.42063 Specialties $654,675 $5.59064 Interior Doors & Windows $1,288,639 $11.00
7 Conveying $94,200 $0.80070 Conveying $94,200 $0.80
8 Mechanical $5,590,311 $47.72081 Plumbing $1,883,040 $16.07082 HVAC $2,869,656 $24.50083 Fire Protection $837,615 $7.15084 Special Mechanical
9 Electrical $5,165,282 $44.09091 Standard Electrical $5,165,282 $44.09092 Special Electrical
10 General Conditions and Overhead & Profit N/A100 General Conditions and Overhead & Profit (Included at Summary Level) N/A
11 Equipment $1,461,508 $12.48111 Fixed / Movable Equipment $1,368,313 $11.68112 Furnishings $93,195 $0.80113 Special Construction
12 Sitework $276,819 $2.36 121 Site Preparation $276,819 $2.36 122 Site Improvements
123 Site Utilities124 Off-Site Work
Total Net Cost $30,964,549 $264.32
Prepared by Clarke Sheet 24 of 74
Southern California Consolidation ProjectLight Duty TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Light Duty Testing Detail Elements
Element Quantity Unit Unit Cost Total
011 Standard Foundations
Standard FoundationsFootings, foundations , thickened slabs, etc., per footprint 64,500 sf $22.65 $1,460,925
Total - 011 Standard Foundations $1,460,925
012 Special Foundations
Special FoundationsElevator pits, sump pits, drilled piers, etc. 64,500 sf $12.45 $803,025
Total - 012 Special Foundations $803,025
021 Slab on Grade
Slab on GradeLowest floor construction 64,500 sf $20.25 $1,306,125
Total - 021 Slab on Grade $1,306,125
023 Basement Walls
Basement WallsWalls, framing, etc. 7,860 sf $52.85 $415,401
Total - 023 Basement Walls $415,401
031 Floor Construction
Elevated Floors and FramingRaised floor construction 52,649 sf $35.20 $1,853,245
Total - 031 Floor Construction $1,853,245
032 Roof Construction
Roof ConstructionRoof framing, deck, including long spans 64,500 sf $27.45 $1,770,525Structure for PV panels, with Site Work sf $30.00
Total - 032 Roof Construction $1,770,525
Prepared by Clarke Sheet 25 of 74
Southern California Consolidation ProjectLight Duty TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Light Duty Testing Detail Elements
Element Quantity Unit Unit Cost Total
033 Stair Construction
Stair ConstructionStairs, handrails, etc. 117,149 sf $2.90 $339,732
Total - 033 Stair Construction $339,732
041 Exterior Walls
Exterior Wall System Framing and walls 31,750 sf $82.35 $2,614,613
Total - 041 Exterior Walls $2,614,613
042 Exterior Doors / Windows
Exterior Doors Exterior doors and windows 31,750 sf $20.25 $642,938
Total - 042 Exterior Doors / Windows $642,938
050 Roofing
Roofing, Including InsulationRoofing, insulation, sheet metal, etc. 64,500 sf $27.55 $1,776,975
Total - 050 Roofing $1,776,975
061 Partitions
Interior PartitionsCMU, drywall partitions, etc. 64,500 sf $40.00 $2,580,000
Total - 061 Partitions $2,580,000
062 Interior Finishes
Floor FinishesSealed concrete, etc. at testing areas 64,500 sf $1.55 $99,975Sealed concrete at basement areas 17,159 sf $1.55 $26,596Sealed concrete at mezzanine areas 35,490 sf $1.55 $55,010
Prepared by Clarke Sheet 26 of 74
Southern California Consolidation ProjectLight Duty TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Light Duty Testing Detail Elements
Element Quantity Unit Unit Cost Total
BaseResilient base, etc. 64,500 sf $0.20 $12,900Rubber base at basement areas 17,159 sf $0.20 $3,432Rubber base at mezzanine areas 35,490 sf $0.20 $7,098
Wall FinishesPaint walls, ceramic tile, acoustical panels, etc. 64,500 sf $6.55 $422,475Paint walls in basement 17,159 sf $1.30 $22,307Paint walls at mezzanine 35,490 sf $1.30 $46,137
Ceiling FinishesPaint structure above 64,500 sf $1.35 $87,075Paint structure above in basement 17,159 sf $1.35 $23,165Paint structure above at mezzanine 35,490 sf $1.35 $47,912
MiscellaneousUnistrut, access panels, etc. 64,500 sf $0.20 $12,900Miscellaneous finishes in basement 17,159 sf $0.05 $858Miscellaneous finishes at mezzanine 35,490 sf $0.05 $1,775
Total - 062 Interior Finishes $869,613
063 Specialties
SpecialtiesMillwork, bath accessories, lockers, etc. 64,500 sf $10.15 $654,675
Total - 063 Specialties $654,675
064 Interior Doors & Windows
Interior Doors and WindowsDoors (including overhead doors), frames, and hardware 117,149 sf $11.00 $1,288,639
Total - 064 Interior Doors & Windows $1,288,639
070 Conveying
ElevatorsLULA elevator, 3 stops 1 ea $94,200.00 $94,200
Total - 070 Conveying $94,200
081 Plumbing
Prepared by Clarke Sheet 27 of 74
Southern California Consolidation ProjectLight Duty TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Light Duty Testing Detail Elements
Element Quantity Unit Unit Cost Total
PlumbingRough in, fixtures, water, drainage, etc. 64,500 sf $22.95 $1,480,275Plumbing systems in basement 17,159 sf $7.65 $131,266Plumbing systems at mezzanine 35,490 sf $7.65 $271,499
Total - 081 Plumbing $1,883,040
082 HVAC
HVACEquipment, ductwork, controls, etc. 64,500 sf $30.90 $1,993,050HVAC systems in basement 17,159 sf $16.65 $285,697HVAC systems at mezzanine 35,490 sf $16.65 $590,909
Total - 082 HVAC $2,869,656
083 Fire Protection
Fire ProtectionAutomatic sprinkler system 64,500 sf $7.15 $461,175Fire protection systems in basement 17,159 sf $7.15 $122,687Fire protection systems at mezzanine 35,490 sf $7.15 $253,754
Total - 083 Fire Protection $837,615
091 Standard Electrical
Service and DistributionService and distribution 64,500 sf $19.80 $1,277,100Service and distribution systems in basement 17,159 sf $9.90 $169,874Service and distribution systems at mezzanine 35,490 sf $9.90 $351,351
Lighting and PowerFixtures and fittings 64,500 sf $14.85 $957,825Lighting and power systems in basement 17,159 sf $7.40 $126,977Lighting and power systems at mezzanine 35,490 sf $7.40 $262,626
Special Systems Fire alarm, telephone/data, security, grounding, and PA/VE 64,500 sf $22.25 $1,435,125PV panel system, with Site Work sf $20.20Special systems in basement 17,159 sf $11.10 $190,465Special systems at mezzanine 35,490 sf $11.10 $393,939
Prepared by Clarke Sheet 28 of 74
Southern California Consolidation ProjectLight Duty TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Light Duty Testing Detail Elements
Element Quantity Unit Unit Cost Total
Total - 091 Standard Electrical $5,165,282
111 Fixed / Movable Equipment
EquipmentFixed and movable equipment, including overhead cranes 64,500 sf $19.50 $1,257,750Equipment in basement 17,159 sf $2.10 $36,034Equipment at mezzanine 35,490 sf $2.10 $74,529
Total - 111 Fixed / Movable Equipment $1,368,313
112 Furnishings
FurnishingsFurniture and furnishings, window blinds, etc. 64,500 sf $1.20 $77,400Furnishings in basement 17,159 sf $0.30 $5,148Furnishings at mezzanine 35,490 sf $0.30 $10,647
Total - 112 Furnishings $93,195
121 Site Preparation
DemolitionRemove pavings, utilities, fixtures, etc. N/A
ExcavationOverexcavate and recompact 47,727 cy $5.80 $276,819
Total - 121 Site Preparation $276,819
122 Site Improvements
Site ImprovementsPavings, landscaping, etc. N/A
Total - 122 Site Improvements
123 Site Utilities
Site UtilitiesUnderground utilities, electrical, etc. N/A
Total - 123 Site Utilities
Prepared by Clarke Sheet 29 of 74
Southern California Consolidation ProjectLight Duty TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Light Duty Testing Detail Elements
Element Quantity Unit Unit Cost Total
123 Offsite
Offsite WorkOffsite improvements and utilities N/A
Total - 123 Offsite
Prepared by Clarke Sheet 30 of 74
Southern California Consolidation ProjectHeavy Duty and OBD Testing / PEMS / PenthouseMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Heavy Duty and OBD Testing / PEMS / Penthouse Construction Cost Summary
Element Total Cost / SF
1 Foundations $1,558,440 $18.59
2 Substructure $1,279,620 $15.27
3 Superstructure $2,849,404 $33.99
4 Exterior Closure $3,215,194 $38.36
5 Roofing $1,223,220 $14.59
6 Interior Construction $3,578,538 $42.69
7 Conveying $94,200 $1.12
8 Mechanical $4,156,138 $49.58
9 Electrical $3,645,860 $43.50
10 General Conditions & Profit
11 Equipment $1,134,291 $13.53
12 Sitework $198,061 $2.36
Subtotal $22,932,965 $273.60
General Conditions 10.0% $2,293,297 $27.36
Subtotal $25,226,262 $300.96
General Contractor OH & P 4.0% $1,009,050 $12.04
Subtotal $26,235,312 $313.00
Bonds & Insurance 2.3% $603,412 $7.20
Subtotal $26,838,724 $320.20
Estimate Contingency 9.0% $2,415,485 $28.82
SUBTOTAL - ESTIMATED CONSTRUCTION COST $29,254,209 $349.02
Total Area: 83,819 SF
Prepared by Clarke Sheet 31 of 74
Southern California Consolidation ProjectHeavy Duty and OBD Testing / PEMS / PenthouseMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Heavy Duty and OBD Testing / PEMS / Penthouse Component Summary
Element Subtotal Total Cost / SF Cost / SF
1 Foundations $1,558,440 $18.59011 Standard Foundations $1,005,660 $12.00012 Special Foundations $552,780 $6.59
2 Substructure $1,279,620 $15.27021 Slab on Grade $899,100 $10.73022 Basement Excavation023 Basement Walls $380,520 $4.54
3 Superstructure $2,849,404 $33.99031 Floor Construction $1,387,549 $16.55032 Roof Construction $1,218,780 $14.54033 Stair Construction $243,075 $2.90
4 Exterior Closure $3,215,194 $38.36041 Exterior Walls $2,316,094 $27.63042 Exterior Doors / Windows $899,100 $10.73
5 Roofing $1,223,220 $14.59050 Roofing $1,223,220 $14.59
6 Interior Construction $3,578,538 $42.69061 Partitions $1,776,000 $21.19062 Interior Finishes $677,135 $8.08063 Specialties $450,660 $5.38064 Interior Doors & Windows $674,743 $8.05
7 Conveying $94,200 $1.12070 Conveying $94,200 $1.12
8 Mechanical $4,156,138 $49.58081 Plumbing $1,590,542 $18.98082 HVAC $1,966,290 $23.46083 Fire Protection $599,306 $7.15084 Special Mechanical
9 Electrical $3,645,860 $43.50091 Standard Electrical $3,645,860 $43.50092 Special Electrical
10 General Conditions and Overhead & Profit N/A100 General Conditions and Overhead & Profit (Included at Summary Level) N/A
11 Equipment $1,134,291 $13.53111 Fixed / Movable Equipment $948,580 $11.32112 Furnishings $185,711 $2.22113 Special Construction
12 Sitework $198,061 $2.36 121 Site Preparation $198,061 $2.36 122 Site Improvements
123 Site Utilities124 Off-Site Work
Total Net Cost $22,932,965 $273.60
Prepared by Clarke Sheet 32 of 74
Southern California Consolidation ProjectHeavy Duty and OBD Testing / PEMS / PenthouseMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Heavy Duty and OBD Testing / PEMS / Penthouse Detail Elements
Element Quantity Unit Unit Cost Total
011 Standard Foundations
Standard FoundationsFootings, foundations , thickened slabs, etc. 44,400 sf $22.65 $1,005,660
Total - 011 Standard Foundations $1,005,660
012 Special Foundations
Special FoundationsElevator pits, sump pits, drilled piers, etc. 44,400 sf $12.45 $552,780
Total - 012 Special Foundations $552,780
021 Slab on Grade
Slab on GradeLowest floor construction 44,400 sf $20.25 $899,100
Total - 021 Slab on Grade $899,100
023 Basement Walls
Basement WallsWalls, framing, etc. 7,200 sf $52.85 $380,520
Total - 023 Basement Walls $380,520
031 Floor Construction
Elevated Floors and FramingRaised floor construction 39,419 sf $35.20 $1,387,549
Total - 031 Floor Construction $1,387,549
032 Roof Construction
Roof ConstructionRoof framing, deck, including long spans 44,400 sf $27.45 $1,218,780Structure for PV panels, with Site Work sf $30.00
Total - 032 Roof Construction $1,218,780
Prepared by Clarke Sheet 33 of 74
Southern California Consolidation ProjectHeavy Duty and OBD Testing / PEMS / PenthouseMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Heavy Duty and OBD Testing / PEMS / Penthouse Detail Elements
Element Quantity Unit Unit Cost Total
033 Stair Construction
Stair ConstructionStairs, handrails, etc. 83,819 sf $2.90 $243,075
Total - 033 Stair Construction $243,075
041 Exterior Walls
Exterior Wall System Framing and walls 28,125 sf $82.35 $2,316,094
Total - 041 Exterior Walls $2,316,094
042 Exterior Doors / Windows
Exterior Doors Exterior doors and windows 44,400 sf $20.25 $899,100
Total - 042 Exterior Doors / Windows $899,100
050 Roofing
Roofing, Including InsulationRoofing, insulation, sheet metal, etc. 44,400 sf $27.55 $1,223,220
Total - 050 Roofing $1,223,220
061 Partitions
Interior PartitionsCMU, drywall partitions, etc. 44,400 sf $40.00 $1,776,000
Total - 061 Partitions $1,776,000
062 Interior Finishes
Floor FinishesSealed concrete, etc. 44,400 sf $1.55 $68,820Floor finishes at basement 12,240 sf $1.55 $18,972Floor finishes at mezzanine 27,179 sf $1.55 $42,127
Prepared by Clarke Sheet 34 of 74
Southern California Consolidation ProjectHeavy Duty and OBD Testing / PEMS / PenthouseMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Heavy Duty and OBD Testing / PEMS / Penthouse Detail Elements
Element Quantity Unit Unit Cost Total
BaseResilient base, etc. 44,400 sf $0.20 $8,880Rubber base at basement areas 12,240 sf $0.20 $2,448Rubber base at mezzanine areas 27,179 sf $0.20 $5,436
Wall FinishesPaint walls, ceramic tile, acoustical panels, etc. 44,400 sf $7.95 $352,980Paint walls in basement 12,240 sf $1.30 $15,912Paint walls at mezzanine 27,179 sf $1.30 $35,333
Ceiling FinishesPaint structure above 44,400 sf $1.35 $59,940Paint structure above in basement 12,240 sf $1.35 $16,524Paint structure above at mezzanine 27,179 sf $1.35 $36,692
MiscellaneousUnistrut, access panels, etc. 44,400 sf $0.25 $11,100Miscellaneous finishes in basement 12,240 sf $0.05 $612Miscellaneous finishes at mezzanine 27,179 sf $0.05 $1,359
Total - 062 Interior Finishes $677,135
063 Specialties
SpecialtiesMillwork, bath accessories, lockers, etc. 44,400 sf $10.15 $450,660
Total - 063 Specialties $450,660
064 Interior Doors & Windows
Interior Doors and WindowsDoors, frames, and hardware 83,819 sf $8.05 $674,743
Total - 064 Interior Doors & Windows $674,743
070 Conveying
ElevatorsLULA elevator, 3 stops 1 ea $94,200.00 $94,200
Total - 070 Conveying $94,200
081 Plumbing
Prepared by Clarke Sheet 35 of 74
Southern California Consolidation ProjectHeavy Duty and OBD Testing / PEMS / PenthouseMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Heavy Duty and OBD Testing / PEMS / Penthouse Detail Elements
Element Quantity Unit Unit Cost Total
PlumbingRough in, fixtures, water, drainage, etc. 44,400 sf $27.30 $1,212,120Plumbing systems in basement 12,240 sf $9.60 $117,504Plumbing systems at mezzanine 27,179 sf $9.60 $260,918
Total - 081 Plumbing $1,590,542
082 HVAC
HVACEquipment, ductwork, controls, etc. 44,400 sf $27.95 $1,240,980HVAC systems in basement 12,240 sf $18.40 $225,216HVAC systems at mezzanine 27,179 sf $18.40 $500,094
Total - 082 HVAC $1,966,290
083 Fire Protection
Fire ProtectionAutomatic sprinkler system 44,400 sf $7.15 $317,460Fire protection systems in basement 12,240 sf $7.15 $87,516Fire protection systems at mezzanine 27,179 sf $7.15 $194,330
Total - 083 Fire Protection $599,306
091 Standard Electrical
Service and DistributionService and distribution 44,400 sf $19.80 $879,120Service and distribution systems in basement 12,240 sf $9.90 $121,176Service and distribution systems at mezzanine 27,179 sf $9.90 $269,072
Lighting and PowerFixtures and fittings 44,400 sf $14.85 $659,340Lighting and power systems in basement 12,240 sf $7.40 $90,576Lighting and power systems at mezzanine 27,179 sf $7.40 $201,125
Special Systems Fire alarm, telephone/data, security, grounding, and PA/VE 44,400 sf $22.25 $987,900PV panel system, with Site Work sf $37.50Special systems in basement 12,240 sf $11.10 $135,864Special systems at mezzanine 27,179 sf $11.10 $301,687
Prepared by Clarke Sheet 36 of 74
Southern California Consolidation ProjectHeavy Duty and OBD Testing / PEMS / PenthouseMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Heavy Duty and OBD Testing / PEMS / Penthouse Detail Elements
Element Quantity Unit Unit Cost Total
Total - 091 Standard Electrical $3,645,860
111 Fixed / Movable Equipment
EquipmentFixed and movable equipment, including overhead cranes 44,400 sf $19.50 $865,800Equipment in basement 12,240 sf $2.10 $25,704Equipment at mezzanine 27,179 sf $2.10 $57,076
Total - 111 Fixed / Movable Equipment $948,580
112 Furnishings
FurnishingsFurniture and furnishings, window blinds, etc. 44,400 sf $3.65 $162,060Furnishings in basement 12,240 sf $0.60 $7,344Furnishings at mezzanine 27,179 sf $0.60 $16,307
Total - 112 Furnishings $185,711
121 Site Preparation
DemolitionRemove pavings, utilities, fixtures, etc. N/A
ExcavationOverexcavate and recompact 34,148 cy $5.80 $198,061
Total - 121 Site Preparation $198,061
122 Site Improvements
Site ImprovementsPavings, landscaping, etc. N/A
Total - 122 Site Improvements
123 Site Utilities
Site UtilitiesUnderground utilities, electrical, etc. N/A
Total - 123 Site Utilities
Prepared by Clarke Sheet 37 of 74
Southern California Consolidation ProjectHeavy Duty and OBD Testing / PEMS / PenthouseMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Heavy Duty and OBD Testing / PEMS / Penthouse Detail Elements
Element Quantity Unit Unit Cost Total
123 Offsite
Offsite WorkOffsite improvements and utilities N/A
Total - 123 Offsite
Prepared by Clarke Sheet 38 of 74
Southern California Consolidation ProjectCentral PlantMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Central Plant Construction Cost Summary
Element Total Cost / SF
1 Foundations $205,335 $35.10
2 Substructure $613,931 $104.95
3 Superstructure $136,598 $23.35
4 Exterior Closure5 Roofing $161,168 $27.55
6 Interior Construction $78,098 $13.35
7 Conveying8 Mechanical $10,748,858 $1,837.41
9 Electrical $332,865 $56.90
10 General Conditions & Profit
11 Equipment $9,360 $1.60
12 Sitework $13,823 $2.36
Subtotal $12,300,035 $2,102.57
General Conditions 10.0% $1,230,003 $210.26
Subtotal $13,530,038 $2,312.83
General Contractor OH & P 4.0% $541,202 $92.51
Subtotal $14,071,240 $2,405.34
Bonds & Insurance 2.3% $323,639 $55.32
Subtotal $14,394,878 $2,460.66
Estimate Contingency 9.0% $1,295,539 $221.46
SUBTOTAL - ESTIMATED CONSTRUCTION COST $15,690,418 $2,682.12
Total Area: 5,850 SF
Prepared by Clarke Sheet 39 of 74
Southern California Consolidation ProjectCentral PlantMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Central Plant Component Summary
Element Subtotal Total Cost / SF Cost / SF
1 Foundations $205,335 $35.10011 Standard Foundations $132,503 $22.65012 Special Foundations $72,833 $12.45
2 Substructure $613,931 $104.95021 Slab on Grade $118,463 $20.25022 Basement Excavation023 Basement Walls $495,469 $84.70
3 Superstructure $136,598 $23.35031 Floor Construction032 Roof Construction $131,333 $22.45033 Stair Construction $5,265 $0.90
4 Exterior Closure 041 Exterior Walls042 Exterior Doors / Windows
5 Roofing $161,168 $27.55050 Roofing $161,168 $27.55
6 Interior Construction $78,098 $13.35061 Partitions $14,625 $2.50062 Interior Finishes $25,448 $4.35063 Specialties $12,285 $2.10064 Interior Doors & Windows $25,740 $4.40
7 Conveying 070 Conveying
8 Mechanical $10,748,858 $1,837.41081 Plumbing $89,505 $15.30082 HVAC $10,617,525 $1,814.96083 Fire Protection $41,828 $7.15084 Special Mechanical
9 Electrical $332,865 $56.90091 Standard Electrical $332,865 $56.90092 Special Electrical
10 General Conditions and Overhead & Profit N/A100 General Conditions and Overhead & Profit (Included at Summary Level) N/A
11 Equipment $9,360 $1.60111 Fixed / Movable Equipment $8,483 $1.45112 Furnishings $878 $0.15113 Special Construction
12 Sitework $13,823 $2.36 121 Site Preparation $13,823 $2.36 122 Site Improvements
123 Site Utilities124 Off-Site Work
Total Net Cost $12,300,035 $2,102.57
Prepared by Clarke Sheet 40 of 74
Southern California Consolidation ProjectCentral PlantMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Central Plant Detail Elements
Element Quantity Unit Unit Cost Total
011 Standard Foundations
Standard FoundationsFootings, foundations , thickened slabs, etc. 5,850 sf $22.65 $132,503
Total - 011 Standard Foundations $132,503
012 Special Foundations
Special FoundationsElevator pits, sump pits, drilled piers, etc. 5,850 sf $12.45 $72,833
Total - 012 Special Foundations $72,833
021 Slab on Grade
Slab on GradeLowest floor construction 5,850 sf $20.25 $118,463
Total - 021 Slab on Grade $118,463
023 Basement Walls
Basement WallsFraming and walls 9,375 sf $52.85 $495,469
Total - 023 Basement Walls $495,469
031 Floor Construction
Elevated Floors and FramingFloor construction N/A
Total - 031 Floor Construction
032 Roof Construction
Roof ConstructionRoof framing, deck 5,850 sf $22.45 $131,333Structure for PV panels, with Site Work sf $30.00
Total - 032 Roof Construction $131,333
Prepared by Clarke Sheet 41 of 74
Southern California Consolidation ProjectCentral PlantMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Central Plant Detail Elements
Element Quantity Unit Unit Cost Total
033 Stair Construction
Stair ConstructionStairs, handrails, etc. 5,850 sf $0.90 $5,265
Total - 033 Stair Construction $5,265
041 Exterior Walls
Exterior Wall System Framing and walls N/A
Total - 041 Exterior Walls
042 Exterior Doors / Windows
Exterior Doors Exterior doors and windows N/A
Total - 042 Exterior Doors / Windows
050 Roofing
Roofing, Including InsulationRoof deck (concrete lid) 5,850 sf $27.55 $161,168
Total - 050 Roofing $161,168
061 Partitions
Interior PartitionsCMU, drywall partitions, etc. 5,850 sf $2.50 $14,625
Total - 061 Partitions $14,625
062 Interior Finishes
Floor FinishesSealed concrete, etc. 5,850 sf $1.50 $8,775
BaseResilient base, etc. 5,850 sf $0.20 $1,170
Prepared by Clarke Sheet 42 of 74
Southern California Consolidation ProjectCentral PlantMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Central Plant Detail Elements
Element Quantity Unit Unit Cost Total
Wall FinishesPaint walls, etc. 5,850 sf $1.25 $7,313
Ceiling FinishesPaint structure above, etc. 5,850 sf $1.30 $7,605
MiscellaneousUnistrut, access panels, etc. 5,850 sf $0.10 $585
Total - 062 Interior Finishes $25,448
063 Specialties
SpecialtiesSpecialties 5,850 sf $2.10 $12,285
Total - 063 Specialties $12,285
064 Interior Doors & Windows
Interior Doors and WindowsDoors, frames, and hardware 5,850 sf $4.40 $25,740
Total - 064 Interior Doors & Windows $25,740
070 Conveying
ElevatorsPassenger, service elevators N/A
Total - 070 Conveying
081 Plumbing
PlumbingRough in, fixtures, water, drainage, etc. 5,850 sf $15.30 $89,505
Total - 081 Plumbing $89,505
082 HVAC
HVAC (Central Plant Equipment)
Prepared by Clarke Sheet 43 of 74
Southern California Consolidation ProjectCentral PlantMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Central Plant Detail Elements
Element Quantity Unit Unit Cost Total
Chiller, 800 ton, centrifugal 2 ea $463,408.25 $926,817Valves and fittings 2 ea $92,681.65 $185,363Chiller, 275 ton, absorption 1 ea $368,803.00 $368,803Valves and fittings 1 ea $73,754.20 $73,754Chiller, 275 ton, screw 1 ea $213,666.20 $213,666Valves and fittings 1 ea $92,681.65 $92,682Thermal energy storage tank, 905,142 gal. 1 ea ########### $1,217,376Boiler, 440 KW, electric 2 ea $28,650.55 $57,301Valves and fittings 2 ea $6,043.95 $12,088Heat exchanger, plate type, 400 gpm 2 ea $45,976.40 $91,953Piping for heat exchanger 160 lf $80.80 $12,928Valves and fittings 2 ea $9,195.25 $18,391Air system, oil-less compressed air, allowance 1 ea $50,000.00 $50,000Air system, Zero-Air, allowance 1 ea $50,000.00 $50,000Purified water generator, allowance 1 ea $200,000.00 $200,000Air dryer, allowance 1 ea $50,000.00 $50,000Air receiver, allowance 1 ea $25,000.00 $25,000Hot water pumps, solar, 200 gpm 2 ea $5,358.75 $10,718Valves and fittings 2 ea $1,071.75 $2,144Hot water pumps, 2 primary, 4 secondary 6 ea $5,358.75 $32,153Valves and fittings 6 ea $1,071.75 $6,431Chilled water pumps, 4 primary, 4 secondary 8 ea $5,358.75 $42,870Valves and fittings 8 ea $1,071.75 $8,574Hydronic piping 3,000 lf $370.05 $1,110,150Fuel cells, natural gas, 400 kw, complete system 2 ls $2,627,096 $5,254,191Gas meter 1 ea $245.85 $246Gas piping, above ground 1 ls $28,087.10 $28,087Cooling tower, 800 ton 2 ea $126,952.95 $253,906Cooling tower, 300 ton 1 ea $49,218.55 $49,219Waterside economizer heat exchanger 2 ea $79,338.70 $158,677Miscellaneous equipment, ductwork, controls, etc. 5,850 sf $2.40 $14,040
Total - 082 HVAC $10,617,525
083 Fire Protection
Fire ProtectionAutomatic sprinkler system 5,850 sf $7.15 $41,828
Total - 083 Fire Protection $41,828
091 Standard Electrical
Service and DistributionService and distribution 5,850 sf $19.80 $115,830
Prepared by Clarke Sheet 44 of 74
Southern California Consolidation ProjectCentral PlantMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Central Plant Detail Elements
Element Quantity Unit Unit Cost Total
Lighting and PowerFixtures and fittings 5,850 sf $14.85 $86,873
Special Systems Fire alarm, telephone/data, etc. 5,850 sf $22.25 $130,163PV panel system, with Site Work sf $20.20
Total - 091 Standard Electrical $332,865
111 Fixed / Movable Equipment
EquipmentFixed and movable equipment, loading dock equipment 5,850 sf $1.45 $8,483
Total - 111 Fixed / Movable Equipment $8,483
112 Furnishings
FurnishingsFurniture and furnishings, window blinds, etc. 5,850 sf $0.15 $878
Total - 112 Furnishings $878
121 Site Preparation
DemolitionRemove pavings, utilities, fixtures, etc. N/A
ExcavationOverexcavate and recompact 2,383 cy $5.80 $13,823
Total - 121 Site Preparation $13,823
122 Site Improvements
Site ImprovementsPavings, landscaping, etc. N/A
Total - 122 Site Improvements
123 Site Utilities
Site Utilities
Prepared by Clarke Sheet 45 of 74
Southern California Consolidation ProjectCentral PlantMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Central Plant Detail Elements
Element Quantity Unit Unit Cost Total
Underground utilities, electrical, etc. N/A
Total - 123 Site Utilities
123 Offsite
Offsite WorkOffsite improvements and utilities N/A
Total - 123 Offsite
Prepared by Clarke Sheet 46 of 74
Southern California Consolidation ProjectASD Building SupportMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
ASD Building Support Construction Cost Summary
Element Total Cost / SF
1 Foundations $598,337 $26.90
2 Substructure $280,262 $12.60
3 Superstructure $333,645 $15.00
4 Exterior Closure $880,904 $39.60
5 Roofing $322,524 $14.50
6 Interior Construction $448,196 $20.15
7 Conveying8 Mechanical $715,112 $32.15
9 Electrical $1,043,197 $46.90
10 General Conditions & Profit
11 Equipment $67,841 $3.05
12 Sitework $52,559 $2.36
Subtotal $4,742,577 $213.22
General Conditions 10.0% $474,258 $21.32
Subtotal $5,216,835 $234.54
General Contractor OH & P 4.0% $208,673 $9.38
Subtotal $5,425,509 $243.92
Bonds & Insurance 2.3% $124,787 $5.61
Subtotal $5,550,295 $249.53
Estimate Contingency 9.0% $499,527 $22.46
SUBTOTAL - ESTIMATED CONSTRUCTION COST $6,049,822 $271.99
Total Area: 22,243 SF
Prepared by Clarke Sheet 47 of 74
Southern California Consolidation ProjectASD Building SupportMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
ASD Building Support Component Summary
Element Subtotal Total Cost / SF Cost / SF
1 Foundations $598,337 $26.90011 Standard Foundations $389,253 $17.50012 Special Foundations $209,084 $9.40
2 Substructure $280,262 $12.60021 Slab on Grade $280,262 $12.60022 Basement Excavation023 Basement Walls
3 Superstructure $333,645 $15.00031 Floor Construction032 Roof Construction $311,402 $14.00033 Stair Construction $22,243 $1.00
4 Exterior Closure $880,904 $39.60041 Exterior Walls $656,250 $29.50042 Exterior Doors / Windows $224,654 $10.10
5 Roofing $322,524 $14.50050 Roofing $322,524 $14.50
6 Interior Construction $448,196 $20.15061 Partitions $278,038 $12.50062 Interior Finishes $83,411 $3.75063 Specialties $23,355 $1.05064 Interior Doors & Windows $63,393 $2.85
7 Conveying 070 Conveying
8 Mechanical $715,112 $32.15081 Plumbing $340,318 $15.30082 HVAC $274,701 $12.35083 Fire Protection $100,094 $4.50084 Special Mechanical
9 Electrical $1,043,197 $46.90091 Standard Electrical $1,043,197 $46.90092 Special Electrical
10 General Conditions and Overhead & Profit N/A100 General Conditions and Overhead & Profit (Included at Summary Level) N/A
11 Equipment $67,841 $3.05111 Fixed / Movable Equipment $54,495 $2.45112 Furnishings $13,346 $0.60113 Special Construction
12 Sitework $52,559 $2.36 121 Site Preparation $52,559 $2.36 122 Site Improvements
123 Site Utilities124 Off-Site Work
Total Net Cost $4,742,577 $213.22
Prepared by Clarke Sheet 48 of 74
Southern California Consolidation ProjectASD Building SupportMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
ASD Building Support Detail Elements
Element Quantity Unit Unit Cost Total
011 Standard Foundations
Standard FoundationsFootings, foundations , thickened slabs, etc. 22,243 sf $17.50 $389,253
Total - 011 Standard Foundations $389,253
012 Special Foundations
Special FoundationsElevator pits, sump pits, drilled piers, etc. 22,243 sf $9.40 $209,084
Total - 012 Special Foundations $209,084
021 Slab on Grade
Slab on GradeLowest floor construction 22,243 sf $12.60 $280,262
Total - 021 Slab on Grade $280,262
023 Basement Walls
Basement WallsWalls, framing, etc. N/A
Total - 023 Basement Walls
031 Floor Construction
Elevated Floors and FramingFloor construction N/A
Total - 031 Floor Construction
032 Roof Construction
Roof ConstructionRoof framing, deck 22,243 sf $14.00 $311,402Structure for PV panels, with Site Work sf $30.00
Total - 032 Roof Construction $311,402
Prepared by Clarke Sheet 49 of 74
Southern California Consolidation ProjectASD Building SupportMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
ASD Building Support Detail Elements
Element Quantity Unit Unit Cost Total
033 Stair Construction
Stair ConstructionStairs, handrails, etc. 22,243 sf $1.00 $22,243
Total - 033 Stair Construction $22,243
041 Exterior Walls
Exterior Wall System Framing and walls 21,000 sf $31.25 $656,250
Total - 041 Exterior Walls $656,250
042 Exterior Doors / Windows
Exterior Doors Exterior doors and windows 22,243 sf $10.10 $224,654
Total - 042 Exterior Doors / Windows $224,654
050 Roofing
Roofing, Including InsulationRoofing, insulation, sheet metal, etc. 22,243 sf $14.50 $322,524
Total - 050 Roofing $322,524
061 Partitions
Interior PartitionsCMU, drywall partitions, etc. 22,243 sf $12.50 $278,038
Total - 061 Partitions $278,038
062 Interior Finishes
Floor FinishesSealed concrete, etc. 22,243 sf $1.50 $33,365
BaseResilient base, etc. 22,243 sf $0.10 $2,224
Prepared by Clarke Sheet 50 of 74
Southern California Consolidation ProjectASD Building SupportMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
ASD Building Support Detail Elements
Element Quantity Unit Unit Cost Total
Wall FinishesPaint walls, etc. 22,243 sf $0.75 $16,682
Ceiling FinishesPaint structure above, etc. 22,243 sf $1.30 $28,916
MiscellaneousUnistrut, access panels, etc. 22,243 sf $0.10 $2,224
Total - 062 Interior Finishes $83,411
063 Specialties
SpecialtiesSpecialties 22,243 sf $1.05 $23,355
Total - 063 Specialties $23,355
064 Interior Doors & Windows
Interior Doors and WindowsDoors, frames, and hardware 22,243 sf $2.85 $63,393
Total - 064 Interior Doors & Windows $63,393
070 Conveying
ElevatorsPassenger, service elevators N/A
Total - 070 Conveying
081 Plumbing
PlumbingRough in, fixtures, water, drainage, etc. 22,243 sf $15.30 $340,318
Total - 081 Plumbing $340,318
082 HVAC
HVAC
Prepared by Clarke Sheet 51 of 74
Southern California Consolidation ProjectASD Building SupportMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
ASD Building Support Detail Elements
Element Quantity Unit Unit Cost Total
Equipment, ductwork, controls, etc. 22,243 sf $12.35 $274,701
Total - 082 HVAC $274,701
083 Fire Protection
Fire ProtectionAutomatic sprinkler system 22,243 sf $4.50 $100,094
Total - 083 Fire Protection $100,094
091 Standard Electrical
Service and DistributionService and distribution 22,243 sf $19.80 $440,411
Lighting and PowerFixtures and fittings 22,243 sf $14.85 $330,309
Special Systems Fire alarm, telephone/data, etc. 22,243 sf $12.25 $272,477PV panel system, with Site Work sf $20.20
Total - 091 Standard Electrical $1,043,197
111 Fixed / Movable Equipment
EquipmentFixed and movable equipment, loading dock equipment 22,243 sf $2.45 $54,495
Total - 111 Fixed / Movable Equipment $54,495
112 Furnishings
FurnishingsFurniture and furnishings, window blinds, etc. 22,243 sf $0.60 $13,346
Total - 112 Furnishings $13,346
121 Site Preparation
DemolitionRemove pavings, utilities, fixtures, etc. N/A
Prepared by Clarke Sheet 52 of 74
Southern California Consolidation ProjectASD Building SupportMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
ASD Building Support Detail Elements
Element Quantity Unit Unit Cost Total
ExcavationOverexcavate and recompact 9,062 cy $5.80 $52,559
Total - 121 Site Preparation $52,559
122 Site Improvements
Site ImprovementsPavings, landscaping, etc. N/A
Total - 122 Site Improvements
123 Site Utilities
Site UtilitiesUnderground utilities, electrical, etc. N/A
Total - 123 Site Utilities
123 Offsite
Offsite WorkOffsite improvements and utilities N/A
Total - 123 Offsite
Prepared by Clarke Sheet 53 of 74
Southern California Consolidation ProjectShared Facilities and Visitor CenterMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Facilities and Visitor Center Construction Cost Summary
Element Total Cost / SF
1 Foundations $1,277,359 $35.10
2 Substructure $736,938 $20.25
3 Superstructure $860,671 $23.65
4 Exterior Closure $2,703,044 $74.28
5 Roofing $1,002,600 $27.55
6 Interior Construction $2,838,576 $78.00
7 Conveying8 Mechanical $1,994,282 $54.80
9 Electrical $2,070,705 $56.90
10 General Conditions & Profit
11 Equipment $216,532 $5.95
12 Sitework $85,993 $2.36
Subtotal $13,786,700 $378.84
General Conditions 10.0% $1,378,670 $37.88
Subtotal $15,165,370 $416.72
General Contractor OH & P 4.0% $606,615 $16.67
Subtotal $15,771,984 $433.39
Bonds & Insurance 2.3% $362,756 $9.97
Subtotal $16,134,740 $443.36
Estimate Contingency 9.0% $1,452,127 $39.90
SUBTOTAL - ESTIMATED CONSTRUCTION COST $17,586,867 $483.26
Total Area: 36,392 SF
Prepared by Clarke Sheet 54 of 74
Southern California Consolidation ProjectShared Facilities and Visitor CenterMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Facilities and Visitor Center Component Summary
Element Subtotal Total Cost / SF Cost / SF
1 Foundations $1,277,359 $35.10011 Standard Foundations $824,279 $22.65012 Special Foundations $453,080 $12.45
2 Substructure $736,938 $20.25021 Slab on Grade $736,938 $20.25022 Basement Excavation023 Basement Walls
3 Superstructure $860,671 $23.65031 Floor Construction032 Roof Construction $817,000 $22.45033 Stair Construction $43,670 $1.20
4 Exterior Closure $2,703,044 $74.28041 Exterior Walls $1,966,106 $54.03042 Exterior Doors / Windows $736,938 $20.25
5 Roofing $1,002,600 $27.55050 Roofing $1,002,600 $27.55
6 Interior Construction $2,838,576 $78.00061 Partitions $1,084,482 $29.80062 Interior Finishes $1,153,626 $31.70063 Specialties $294,775 $8.10064 Interior Doors & Windows $305,693 $8.40
7 Conveying 070 Conveying
8 Mechanical $1,994,282 $54.80081 Plumbing $556,798 $15.30082 HVAC $1,177,281 $32.35083 Fire Protection $260,203 $7.15084 Special Mechanical
9 Electrical $2,070,705 $56.90091 Standard Electrical $2,070,705 $56.90092 Special Electrical
10 General Conditions and Overhead & Profit N/A100 General Conditions and Overhead & Profit (Included at Summary Level) N/A
11 Equipment $216,532 $5.95111 Fixed / Movable Equipment $89,160 $2.45112 Furnishings $127,372 $3.50113 Special Construction
12 Sitework $85,993 $2.36 121 Site Preparation $85,993 $2.36 122 Site Improvements
123 Site Utilities124 Off-Site Work
Total Net Cost $13,786,700 $378.84
Prepared by Clarke Sheet 55 of 74
Southern California Consolidation ProjectShared Facilities and Visitor CenterMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Facilities and Visitor Center Detail Elements
Element Quantity Unit Unit Cost Total
011 Standard Foundations
Standard FoundationsFootings, foundations , thickened slabs, etc. 36,392 sf $22.65 $824,279
Total - 011 Standard Foundations $824,279
012 Special Foundations
Special FoundationsElevator pits, sump pits, drilled piers, etc. 36,392 sf $12.45 $453,080
Total - 012 Special Foundations $453,080
021 Slab on Grade
Slab on GradeLowest floor construction 36,392 sf $20.25 $736,938
Total - 021 Slab on Grade $736,938
023 Basement Walls
Basement WallsWalls, framing, etc. N/A
Total - 023 Basement Walls
031 Floor Construction
Elevated Floors and FramingFloor construction N/A
Total - 031 Floor Construction
032 Roof Construction
Roof ConstructionRoof framing, deck 36,392 sf $22.45 $817,000Structure for PV panels, with Site Work sf $30.00
Total - 032 Roof Construction $817,000
Prepared by Clarke Sheet 56 of 74
Southern California Consolidation ProjectShared Facilities and Visitor CenterMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Facilities and Visitor Center Detail Elements
Element Quantity Unit Unit Cost Total
033 Stair Construction
Stair ConstructionStairs, handrails, etc. 36,392 sf $1.20 $43,670
Total - 033 Stair Construction $43,670
041 Exterior Walls
Exterior Wall System Framing and walls 23,875 sf $82.35 $1,966,106
Total - 041 Exterior Walls $1,966,106
042 Exterior Doors / Windows
Exterior Doors Exterior doors and windows 36,392 sf $20.25 $736,938
Total - 042 Exterior Doors / Windows $736,938
050 Roofing
Roofing, Including InsulationRoofing, insulation, sheet metal, etc. 36,392 sf $27.55 $1,002,600
Total - 050 Roofing $1,002,600
061 Partitions
Interior PartitionsCMU, drywall partitions, etc. 36,392 sf $29.80 $1,084,482
Total - 061 Partitions $1,084,482
062 Interior Finishes
Floor FinishesSealed concrete, resilient, carpet, ceramic, etc. 36,392 sf $10.20 $371,198
BaseResilient base, wood, ceramic, etc. 36,392 sf $0.70 $25,474
Prepared by Clarke Sheet 57 of 74
Southern California Consolidation ProjectShared Facilities and Visitor CenterMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Facilities and Visitor Center Detail Elements
Element Quantity Unit Unit Cost Total
Wall FinishesPaint walls, ceramic tile, acoustical panels, etc. 36,392 sf $6.55 $238,368
Ceiling FinishesPaint structure above, drywall, acoustical tile, etc. 36,392 sf $14.15 $514,947
MiscellaneousUnistrut, access panels, etc. 36,392 sf $0.10 $3,639
Total - 062 Interior Finishes $1,153,626
063 Specialties
SpecialtiesMillwork, bath accessories, lockers, etc. 36,392 sf $8.10 $294,775
Total - 063 Specialties $294,775
064 Interior Doors & Windows
Interior Doors and WindowsDoors, frames, and hardware 36,392 sf $8.40 $305,693
Total - 064 Interior Doors & Windows $305,693
070 Conveying
ElevatorsPassenger, service elevators N/A
Total - 070 Conveying
081 Plumbing
PlumbingRough in, fixtures, water, drainage, etc. 36,392 sf $15.30 $556,798
Total - 081 Plumbing $556,798
082 HVAC
HVAC
Prepared by Clarke Sheet 58 of 74
Southern California Consolidation ProjectShared Facilities and Visitor CenterMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Facilities and Visitor Center Detail Elements
Element Quantity Unit Unit Cost Total
Equipment, ductwork, controls, etc. 36,392 sf $32.35 $1,177,281
Total - 082 HVAC $1,177,281
083 Fire Protection
Fire ProtectionAutomatic sprinkler system 36,392 sf $7.15 $260,203
Total - 083 Fire Protection $260,203
091 Standard Electrical
Service and DistributionService and distribution 36,392 sf $19.80 $720,562
Lighting and PowerFixtures and fittings 36,392 sf $14.85 $540,421
Special Systems Fire alarm, telephone/data, etc. 36,392 sf $22.25 $809,722PV panel system, with Site Work sf $20.20
Total - 091 Standard Electrical $2,070,705
111 Fixed / Movable Equipment
EquipmentFixed and movable equipment, loading dock equipment 36,392 sf $2.45 $89,160
Total - 111 Fixed / Movable Equipment $89,160
112 Furnishings
FurnishingsFurniture and furnishings, fixed seating, window blinds, etc. 36,392 sf $3.50 $127,372
Total - 112 Furnishings $127,372
121 Site Preparation
DemolitionRemove pavings, utilities, fixtures, etc. N/A
Prepared by Clarke Sheet 59 of 74
Southern California Consolidation ProjectShared Facilities and Visitor CenterMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Facilities and Visitor Center Detail Elements
Element Quantity Unit Unit Cost Total
ExcavationOverexcavate and recompact 14,826 cy $5.80 $85,993
Total - 121 Site Preparation $85,993
122 Site Improvements
Site ImprovementsPavings, landscaping, etc. N/A
Total - 122 Site Improvements
123 Site Utilities
Site UtilitiesUnderground utilities, electrical, etc. N/A
Total - 123 Site Utilities
123 Offsite
Offsite WorkOffsite improvements and utilities N/A
Total - 123 Offsite
Prepared by Clarke Sheet 60 of 74
Southern California Consolidation ProjectShared TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Testing Construction Cost Summary
Element Total Cost / SF
1 Foundations $426,535 $35.10
2 Substructure $246,078 $20.25
3 Superstructure $287,395 $23.65
4 Exterior Closure $1,388,684 $114.28
5 Roofing $334,788 $27.55
6 Interior Construction $786,234 $64.70
7 Conveying8 Mechanical $665,930 $54.80
9 Electrical $691,449 $56.90
10 General Conditions & Profit
11 Equipment $43,140 $3.55
12 Sitework $28,715 $2.36
Subtotal $4,898,947 $403.14
General Conditions 10.0% $489,895 $40.31
Subtotal $5,388,842 $443.45
General Contractor OH & P 4.0% $215,554 $17.74
Subtotal $5,604,395 $461.19
Bonds & Insurance 2.3% $128,901 $10.61
Subtotal $5,733,296 $471.80
Estimate Contingency 9.0% $515,997 $42.46
SUBTOTAL - ESTIMATED CONSTRUCTION COST $6,249,293 $514.26
Total Area: 12,152 SF
Prepared by Clarke Sheet 61 of 74
Southern California Consolidation ProjectShared TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Testing Component Summary
Element Subtotal Total Cost / SF Cost / SF
1 Foundations $426,535 $35.10011 Standard Foundations $275,243 $22.65012 Special Foundations $151,292 $12.45
2 Substructure $246,078 $20.25021 Slab on Grade $246,078 $20.25022 Basement Excavation023 Basement Walls
3 Superstructure $287,395 $23.65031 Floor Construction032 Roof Construction $272,812 $22.45033 Stair Construction $14,582 $1.20
4 Exterior Closure $1,388,684 $114.28041 Exterior Walls $1,142,606 $94.03042 Exterior Doors / Windows $246,078 $20.25
5 Roofing $334,788 $27.55050 Roofing $334,788 $27.55
6 Interior Construction $786,234 $64.70061 Partitions $362,130 $29.80062 Interior Finishes $272,812 $22.45063 Specialties $49,216 $4.05064 Interior Doors & Windows $102,077 $8.40
7 Conveying 070 Conveying
8 Mechanical $665,930 $54.80081 Plumbing $185,926 $15.30082 HVAC $393,117 $32.35083 Fire Protection $86,887 $7.15084 Special Mechanical
9 Electrical $691,449 $56.90091 Standard Electrical $691,449 $56.90092 Special Electrical
10 General Conditions and Overhead & Profit N/A100 General Conditions and Overhead & Profit (Included at Summary Level) N/A
11 Equipment $43,140 $3.55111 Fixed / Movable Equipment $29,772 $2.45112 Furnishings $13,367 $1.10113 Special Construction
12 Sitework $28,715 $2.36 121 Site Preparation $28,715 $2.36 122 Site Improvements
123 Site Utilities124 Off-Site Work
Total Net Cost $4,898,947 $403.14
Prepared by Clarke Sheet 62 of 74
Southern California Consolidation ProjectShared TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Testing Detail Elements
Element Quantity Unit Unit Cost Total
011 Standard Foundations
Standard FoundationsFootings, foundations , thickened slabs, etc. 12,152 sf $22.65 $275,243
Total - 011 Standard Foundations $275,243
012 Special Foundations
Special FoundationsElevator pits, sump pits, drilled piers, etc. 12,152 sf $12.45 $151,292
Total - 012 Special Foundations $151,292
021 Slab on Grade
Slab on GradeLowest floor construction 12,152 sf $20.25 $246,078
Total - 021 Slab on Grade $246,078
023 Basement Walls
Basement WallsWalls, framing, etc. N/A
Total - 023 Basement Walls
031 Floor Construction
Elevated Floors and FramingFloor construction N/A
Total - 031 Floor Construction
032 Roof Construction
Roof ConstructionRoof framing, deck 12,152 sf $22.45 $272,812Structure for PV panels, with Site Work sf $30.00
Total - 032 Roof Construction $272,812
Prepared by Clarke Sheet 63 of 74
Southern California Consolidation ProjectShared TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Testing Detail Elements
Element Quantity Unit Unit Cost Total
033 Stair Construction
Stair ConstructionStairs, handrails, etc. 12,152 sf $1.20 $14,582
Total - 033 Stair Construction $14,582
041 Exterior Walls
Exterior Wall System Framing and walls 13,875 sf $82.35 $1,142,606
Total - 041 Exterior Walls $1,142,606
042 Exterior Doors / Windows
Exterior Doors Exterior doors and windows 12,152 sf $20.25 $246,078
Total - 042 Exterior Doors / Windows $246,078
050 Roofing
Roofing, Including InsulationRoofing, insulation, sheet metal, etc. 12,152 sf $27.55 $334,788
Total - 050 Roofing $334,788
061 Partitions
Interior PartitionsCMU, drywall partitions, etc. 12,152 sf $29.80 $362,130
Total - 061 Partitions $362,130
062 Interior Finishes
Floor FinishesSealed concrete, resilient, carpet, ceramic, etc. 12,152 sf $1.45 $17,620
BaseResilient base, etc. 12,152 sf $0.20 $2,430
Prepared by Clarke Sheet 64 of 74
Southern California Consolidation ProjectShared TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Testing Detail Elements
Element Quantity Unit Unit Cost Total
Wall FinishesPaint walls, ceramic tile, acoustical panels, etc. 12,152 sf $6.55 $79,596
Ceiling FinishesPaint structure above, drywall, acoustical tile, etc. 12,152 sf $14.15 $171,951
MiscellaneousUnistrut, access panels, etc. 12,152 sf $0.10 $1,215
Total - 062 Interior Finishes $272,812
063 Specialties
SpecialtiesMillwork, bath accessories, lockers, etc. 12,152 sf $4.05 $49,216
Total - 063 Specialties $49,216
064 Interior Doors & Windows
Interior Doors and WindowsDoors, frames, and hardware 12,152 sf $8.40 $102,077
Total - 064 Interior Doors & Windows $102,077
070 Conveying
ElevatorsPassenger, service elevators N/A
Total - 070 Conveying
081 Plumbing
PlumbingRough in, fixtures, water, drainage, etc. 12,152 sf $15.30 $185,926
Total - 081 Plumbing $185,926
082 HVAC
HVAC
Prepared by Clarke Sheet 65 of 74
Southern California Consolidation ProjectShared TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Testing Detail Elements
Element Quantity Unit Unit Cost Total
Equipment, ductwork, controls, etc. 12,152 sf $32.35 $393,117
Total - 082 HVAC $393,117
083 Fire Protection
Fire ProtectionAutomatic sprinkler system 12,152 sf $7.15 $86,887
Total - 083 Fire Protection $86,887
091 Standard Electrical
Service and DistributionService and distribution 12,152 sf $19.80 $240,610
Lighting and PowerFixtures and fittings 12,152 sf $14.85 $180,457
Special Systems Fire alarm, telephone/data, etc. 12,152 sf $22.25 $270,382PV panel system, with Site Work sf $20.20
Total - 091 Standard Electrical $691,449
111 Fixed / Movable Equipment
EquipmentFixed and movable equipment, loading dock equipment 12,152 sf $2.45 $29,772
Total - 111 Fixed / Movable Equipment $29,772
112 Furnishings
FurnishingsFurniture and furnishings, window blinds, etc. 12,152 sf $1.10 $13,367
Total - 112 Furnishings $13,367
121 Site Preparation
DemolitionRemove pavings, utilities, fixtures, etc. N/A
Prepared by Clarke Sheet 66 of 74
Southern California Consolidation ProjectShared TestingMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Shared Testing Detail Elements
Element Quantity Unit Unit Cost Total
ExcavationOverexcavate and recompact 4,951 cy $5.80 $28,715
Total - 121 Site Preparation $28,715
122 Site Improvements
Site ImprovementsPavings, landscaping, etc. N/A
Total - 122 Site Improvements
123 Site Utilities
Site UtilitiesUnderground utilities, electrical, etc. N/A
Total - 123 Site Utilities
123 Offsite
Offsite WorkOffsite improvements and utilities N/A
Total - 123 Offsite
Prepared by Clarke Sheet 67 of 74
Southern California Consolidation ProjectSite WorkMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Site Work Construction Cost Summary
Element Total Cost / SF
1 Foundations2 Substructure3 Superstructure4 Exterior Closure5 Roofing6 Interior Construction7 Conveying8 Mechanical9 Electrical $6,282,705 $7.67
10 General Conditions & Profit
11 Equipment12 Sitework $40,360,652 $49.28
Subtotal $46,643,357 $56.96
General Conditions 10.0% $4,664,336 $5.70
Subtotal $51,307,693 $62.65
General Contractor OH & P 4.0% $2,052,308 $2.51
Subtotal $53,360,000 $65.16
Bonds & Insurance 2.3% $1,227,280 $1.50
Subtotal $54,587,280 $66.66
Estimate Contingency 9.0% $4,912,855 $6.00
SUBTOTAL - ESTIMATED CONSTRUCTION COST $59,500,135 $72.66
Total Area: 818,928 SF
Prepared by Clarke Sheet 68 of 74
Southern California Consolidation ProjectSite WorkMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Site Work Component Summary
Element Subtotal Total Cost / SF Cost / SF
1 Foundations011 Standard Foundations012 Special Foundations
2 Substructure 021 Slab on Grade022 Basement Excavation023 Basement Walls
3 Superstructure 031 Floor Construction032 Roof Construction033 Stair Construction
4 Exterior Closure 041 Exterior Walls042 Exterior Doors / Windows
5 Roofing 050 Roofing
6 Interior Construction 061 Partitions062 Interior Finishes063 Specialties064 Interior Doors & Windows
7 Conveying 070 Conveying
8 Mechanical 081 Plumbing082 HVAC083 Fire Protection084 Special Mechanical
9 Electrical $6,282,705 $7.67091 Standard Electrical $6,282,705 $7.67092 Special Electrical
10 General Conditions and Overhead & Profit100 General Conditions and Overhead & Profit (Included at Summary Level)
11 Equipment 111 Fixed / Movable Equipment112 Furnishings113 Special Construction
12 Sitework $40,360,652 $49.28 121 Site Preparation $5,363,978 $6.55 122 Site Improvements $27,395,078 $33.45
123 Site Utilities $6,592,370 $8.05124 Off-Site Work $1,009,225 $1.23
Total Net Cost $46,643,357 $56.96
Prepared by Clarke Sheet 69 of 74
Southern California Consolidation ProjectSite WorkMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Site Work Detail Elements
Element Quantity Unit Unit Cost Total
011 Standard Foundations
Standard FoundationsFootings, foundations , thickened slabs, etc. N/A
Total - 011 Standard Foundations
012 Special Foundations
Special FoundationsElevator pits, sump pits, etc. N/A
Total - 012 Special Foundations
021 Slab on Grade
Slab on GradeLowest floor construction N/A
Total - 021 Slab on Grade
023 Basement Walls
Basement WallsWalls, framing, etc. N/A
Total - 023 Basement Walls
031 Floor Construction
Elevated Floors and FramingFloor construction N/A
Total - 031 Floor Construction
032 Roof Construction
Roof ConstructionRoof framing N/A
Total - 032 Roof Construction
Prepared by Clarke Sheet 70 of 74
Southern California Consolidation ProjectSite WorkMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Site Work Detail Elements
Element Quantity Unit Unit Cost Total
033 Stair Construction
Stair ConstructionStairs, handrails, etc. N/A
Total - 033 Stair Construction
041 Exterior Walls
Exterior Wall System Framing and walls N/A
Total - 041 Exterior Walls
042 Exterior Doors / Windows
Exterior Doors Exterior doors and windows N/A
Total - 042 Exterior Doors / Windows
050 Roofing
Roofing, Including InsulationRoofing, insulation, sheet metal, etc. N/A
Total - 050 Roofing
061 Partitions
Interior PartitionsCMU, drywall partitions, etc. N/A
Total - 061 Partitions
062 Interior Finishes
Floor FinishesSealed concrete, resilient, carpet, ceramic, etc. N/A
BaseResilient base, wood, ceramic, etc. N/A
Prepared by Clarke Sheet 71 of 74
Southern California Consolidation ProjectSite WorkMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Site Work Detail Elements
Element Quantity Unit Unit Cost Total
Wall FinishesPaint walls, ceramic tile, acoustical panels, etc. N/A
Ceiling FinishesPaint structure above, drywall, acoustical tile, etc. N/A
MiscellaneousUnistrut, access panels, etc. N/A
Total - 062 Interior Finishes
063 Specialties
SpecialtiesMillwork, bath accessories, lockers, etc. N/A
Total - 063 Specialties
064 Interior Doors & Windows
Interior DoorsDoors, frames, and hardware N/A
Total - 064 Interior Doors & Windows
070 Conveying
ElevatorsPassenger, service elevators N/A
Total - 070 Conveying
081 Plumbing
PlumbingRough in, fixtures, water, drainage, etc. N/A
Total - 081 Plumbing
082 HVAC
HVACEquipment, ductwork, controls, etc. N/A
Prepared by Clarke Sheet 72 of 74
Southern California Consolidation ProjectSite WorkMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Site Work Detail Elements
Element Quantity Unit Unit Cost Total
Total - 082 HVAC
083 Fire Protection
Fire ProtectionAutomatic sprinkler system N/A
Total - 083 Fire Protection
091 Standard Electrical
Service and DistributionService and distribution N/A
Lighting and PowerFixtures and fittings N/A
Special Systems PV panel system at 16' structure 19,275 sf $20.20 $389,355PV panel system at 14' structure 65,550 sf $20.20 $1,324,110PV panel system at 10' structure 4,500 sf $20.20 $90,900PV panel system at 8' structure 213,450 sf $20.20 $4,311,690PV panel system at 4' structure 8,250 sf $20.20 $166,650PV panel system at undefined structure
Total - 091 Standard Electrical $6,282,705
111 Fixed / Movable Equipment
EquipmentFixed and movable equipment N/A
Total - 111 Fixed / Movable Equipment
112 Furnishings
FurnishingsFurniture and furnishings, window blinds, etc. N/A
Total - 112 Furnishings
121 Site Preparation
Prepared by Clarke Sheet 73 of 74
Southern California Consolidation ProjectSite WorkMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Site Work Detail Elements
Element Quantity Unit Unit Cost Total
DemolitionRemove pavings, utilities, fixtures, etc. (minimal amount) 818,928 sf $1.05 $859,874
Site PreparationClear and grub site 818,928 sf $0.15 $122,839Rough grading 818,928 sf $5.35 $4,381,265
Total - 121 Site Preparation $5,363,978
122 Site Improvements
Site Improvements (Including Landscaping, Fencing, etc.)Entry plaza 14,400 sf $63.25 $910,800Landscape plaza 13,200 sf $35.70 $471,240Visitor/staff parking 108,000 sf $15.85 $1,711,800Service yards 103,200 sf $16.70 $1,723,440Fleet parking 40,000 sf $15.85 $634,000Main roadways 74,000 sf $19.20 $1,420,800Decomposed granite 69,200 sf $11.40 $788,880Secondary roadways, landscaped areas, circulation, etc. 217,685 sf $18.85 $4,103,362Canopies over service yards 10,320 sf $118.30 $1,220,856Hazardous waste storage building 1 ls $105,000.00 $105,000Structure for PV panels, 16', including piers 25,700 sf $50.80 $1,305,560Structure for PV panels, 14', including piers 87,400 sf $47.85 $4,182,090Structure for PV panels, 10', including piers 6,000 sf $42.40 $254,400Structure for PV panels, 8' 284,600 sf $28.50 $8,111,100Structure for PV panels, 4' 11,000 sf $19.25 $211,750Structure for PV panels 8,000 sf $30.00 $240,000
Total - 122 Site Improvements $27,395,078
123 Site Utilities
Site UtilitiesFuel island, tank storage, liquid nitrogen tank, field drum storage 1 ls $941,767.00 $941,767Charging stations, 480 V (with Equipment budget) N/AUnderground utilities, site electrical, etc. 818,928 sf $6.90 $5,650,603
Total - 123 Site Utilities $6,592,370
123 Offsite
Offsite WorkIowa Avenue widening for CARB site 1 ls $1,009,225 $1,009,225
Prepared by Clarke Sheet 74 of 74
Southern California Consolidation ProjectSite WorkMaster Plan Preliminary Construction Cost Estimate - 6th Revision 11/04/16
Site Work Detail Elements
Element Quantity Unit Unit Cost Total
Total - 123 Offsite $1,009,225