15
SPP 2012 Probabilistic Assessment Analysis July 27, 2012 Michael Odom, SPP [email protected] · 501.688.8205 Jinxiang Zhu, ABB Inc. [email protected] 919.807.8246

SPP 2012 Probabilistic Assessment Analysis - IEEEewh.ieee.org/cmte/pes/rrpa/RRPA_files/LBP20120726/Item 7 - LOLEWG - SPP 2012... · SPP 2012 Probabilistic Assessment Analysis July

Embed Size (px)

Citation preview

SPP 2012 Probabilistic Assessment Analysis

July 27, 2012

Michael Odom, SPP [email protected] · 501.688.8205

Jinxiang Zhu, ABB Inc. [email protected] 919.807.8246

• Gather input data

• Model data in GridView

• Run simulation

• Sensitivities

• Compile results into report

• Submit report to NERC

Process Overview

2

• Area Load shapes

• Demand Response

• Thermal / Renewable Generation data

• Wind Generation shapes

• Interface, Contingency, Nomogram data

• Purchases and Sales

• Uncertainty data

• Transmission topology

Data Inputs

3

• The summer period is defined as June 1st – September 1st

• Load shed penalty < Branch overload penalty

• (Generally) 2400 trials per simulation will be ran to get a proper convergence

• Only Existing, Certain and Future, Planned reported generation are used as inputs from the LTRA

• Future, Planned generation as stated in the LTRA is “firm and deliverable”

• Uncertainty based generation outages are randomly selected

• Spinning reserve is 50% of the Operating reserve

Assumptions

4

• Import Load, Wind shapes from .csv

• 25 zones within SPP region for 2012

• Import Bus, Load, Branch data from PSSE

• Update Interface monitoring, Line monitoring, Contingency monitoring, Operating guides, and Regional configuration

• Update Generation in .csv using LTRA and GADS data then import

• Schedule Thermal Generation maintenance

• Model Demand Response & Imports/Exports as flat hourly resources

• Model DC ties as variable hourly resources

• Model probability pattern and 7 value probability distribution

Modeling

5

• Probability distribution is comprised of historical actual load and temperature values

• Temperature values are regressed against load

• User defined load patterns are used to apply a monthly multiplier

• Each modeled area (zone) will have 7 patterns available

Data Uncertainty

6

0.0062

0.0606

0.2417

0.383

0.2417

0.0606

0.0062

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.4

0.45

0.922 0.928 0.951 1.000 1.032 1.053 1.057

Pro

bab

ilit

y

Peak Load Multiplier

• Monte Carlo simulation

– Uncertainty in generator outages, transmission outages, and load modifiers

– Each hour (8760 typical): SCUC, SCED, Indices calculation

– Each hour update Generator/Interface/Load status

– Will commit all units (minus scheduled and random outages)

– Rate C will be used for constraint limits for all branches

– Congestion values per branch calculated

– Hourly Load, Capacity, Congestion values

– LOLE, LOLH, EUE indices calculated

– 2400 trials per simulation

Simulation

7

• Capacity Margin analysis

– SPP Criteria requires each control area to maintain a minimum of 12% capacity margin.

– Study year capacity margin is calculated and peak load is increased proportionally in each control area to match the 12% capacity margin criteria.

Sensitivity

8

• Severe event simulation

• Random or scheduled transmission and generation outages

• Can be specific by unit, bus, branch

• Can be clustered and outaged in groups

Sensitivity

9

• Finalized metric results (LOLH, LOLE, EUE, Normalized EUE)

• Adjusted 12% Capacity Margin results for SPP Criteria

• Severe event scenario results (if requested by stakeholders)

• SPP 2011 Probabilistic Assessment Report

Reporting

10

Transportation Model vs. Transmission Model

11

Transfer capability from A to C? - Supply Curve Model - Transportation Model - LMP Model

75

0 75

[100, 0.1]

[10

0, 0

.1]

A

B

C

Low Cost

High Cost

150

40 190

50 MW

A

B

C

Low Cost

High Cost

Limiting line

Unconstrained Constrained

25 MW 1

2 2

1

• Multi-State Transition Rate Model

– Generators

– Interface limits

• Transmission Forced and Schedule Outages

– N-x transmission forced outages

• Unit Deration due to Temperature

• Wind Generation Uncertainty

• Load Uncertainty and Correlation

• Fuel Price Uncertainty and Correlation

Uncertainties in GridView Model

12

GridView Outputs

13

• Benchmark with IEEE RTS systems and commercial software

• Model normal and emergency limits

• Interface limits dependent on some unit status and load

– Central East (Oswego units)

• Reliability Study and Economic Study

– Consistency on the transmission model

– Enforcing intra-zonal and inter-zonal constraints

– Enforcing transmission ratings under normal and contingency conditions

• NY STARS Project Phase II Final Report

http://www.nyiso.com/public/webdocs/services/planning/stars/Phase_2_Final_Report_4_30_2012.pdf

GridView Applications

14

Questions

15

Are there any questions?