125
STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 Table of Contents TOC-1 TABLE OF CONTENTS DIVISION 1 – GENERAL REQUIREMENTS 01010 SUMMARY OF WORK 01010-1 to 01010-4 01025 MEASUREMENT AND PAYMENT 01025-1 to 01025-3 01050 FIELD ENGINEERING 01050-1 to 01050-2 01060 REGULATORY REQUIREMENTS AND SAFETY 01060-1 to 01060-21 01570 MAINTENANCE AND PROTECTION OF 01570-1 to 01570-4 VEHICULAR AND PEDESTRIAN TRAFFIC 01700 CONTRACT CLOSEOUT 01700-1 to 01700-3 01710 FINAL CLEANING 01710-1 to 01710-3 DIVISION 2 – SITE CONSTRUCTION 02230 SITE PREPARATION 02230-1 to 02230-1 02300 EXCAVATION, BACKFILL AND COMPACTION 02300-1 to 02300-16 02322 EXCAVATION, BACKFILL AND COMPACTION FOR UTILITIES 02322-1 to 02322-6 02360 EXCAVATION SUPPORT SYSTEMS 02360-1 to 02360-5 02370 EROSION AND SEDIMENTATION CONTROL 02370-1 to 02370-6 02400 SOILS MANAGEMENT 02400-1 to 02400-4 02440 SITE IMPROVEMENTS 02440-1 to 02440-3 02520 BITUMINOUS CONCRETE PAVING 02520-1 to 02520-5 02533 CONCRETE SIDEWALKS 02533-1 to 02533-5 02534 POURED IN PLACE CONCRETE CURB 02534-1 to 02534-4 02605 UTILITY STRUCTURES 02605-1 to 02605-7 02721 STORM DRAINAGE SYSTEMS 02721-1 to 02721-9 02941 LANDSCAPING 02941-1 to 02941-3 DIVISION 3 – CONCRETE 03100 CONCRETE FORMWORK 03100-1 to 03100-3 03300 CAST-IN-PLACE CONCRETE 03300-1 to 03300-8 APPENDIX A1 SIDEWALK DETAIL

STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

Table of Contents TOC-1

TABLE OF CONTENTS

DIVISION 1 – GENERAL REQUIREMENTS

01010 SUMMARY OF WORK 01010-1 to 01010-4 01025 MEASUREMENT AND PAYMENT 01025-1 to 01025-3 01050 FIELD ENGINEERING 01050-1 to 01050-2 01060 REGULATORY REQUIREMENTS AND SAFETY 01060-1 to 01060-21 01570 MAINTENANCE AND PROTECTION OF 01570-1 to 01570-4 VEHICULAR AND PEDESTRIAN TRAFFIC 01700 CONTRACT CLOSEOUT 01700-1 to 01700-3 01710 FINAL CLEANING 01710-1 to 01710-3

DIVISION 2 – SITE CONSTRUCTION

02230 SITE PREPARATION 02230-1 to 02230-1 02300 EXCAVATION, BACKFILL AND COMPACTION 02300-1 to 02300-16 02322 EXCAVATION, BACKFILL AND COMPACTION FOR UTILITIES 02322-1 to 02322-6 02360 EXCAVATION SUPPORT SYSTEMS 02360-1 to 02360-5 02370 EROSION AND SEDIMENTATION CONTROL 02370-1 to 02370-6 02400 SOILS MANAGEMENT 02400-1 to 02400-4 02440 SITE IMPROVEMENTS 02440-1 to 02440-3 02520 BITUMINOUS CONCRETE PAVING 02520-1 to 02520-5 02533 CONCRETE SIDEWALKS 02533-1 to 02533-5 02534 POURED IN PLACE CONCRETE CURB 02534-1 to 02534-4 02605 UTILITY STRUCTURES 02605-1 to 02605-7 02721 STORM DRAINAGE SYSTEMS 02721-1 to 02721-9 02941 LANDSCAPING 02941-1 to 02941-3

DIVISION 3 – CONCRETE

03100 CONCRETE FORMWORK 03100-1 to 03100-3 03300 CAST-IN-PLACE CONCRETE 03300-1 to 03300-8

APPENDIX

A1 SIDEWALK DETAIL

Page 2: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

Table of Contents TOC-2

A2 PLAIN CEMENT CONCRETE CURB DETAIL

A3 TYPICAL PARKING SPACE WITH BUMPER

A4 STALL SIGN DETAIL

A5 TYPICAL STALL POST AND SIGN

Page 3: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SUMMARY OF WORK 01010-1

SECTION 01010

SUMMARY OF WORK

PART 1 – GENERAL 1.1 PROCEDURES FOR PERFORMING WORK

A. Perform all Work under this Contract in accordance with the Contract Documents.

1.2 DESCRIPTION OF WORK

A. The work of this contract is to provide paving and site work construction for SEPTA under a “blanket” contract described in these Specifications, Division 1 through 3. As such, specific assignments will be made on a case-by-case, as needed basis. This contract covers the following items:

1. Providing pavement maintenance, such at pothole repair and pavement overlay. 2. Maintenance and protection of vehicular and pedestrian traffic. 3. Site clearing. 4. Excavation and grading. 5. Erosion and sediment control. 6. Furnishing and installing drainage pipes and structures. 7. Placing both cement and bituminous pavement 8. Constructing curb and sidewalk. 9. Providing painted pavement marking 10. Site signing 11. Site work

B. Furnish all materials, tools, equipment, supervision, and transportation, and perform all labor and services necessary to complete all work described in these specifications and indicated on the Contract Drawings.

C. No Contract Drawings accompany this specification, other than the details attached. Contract Drawings will be provided on a case-by-case basis for specific projects as they are needed.

D. The Projects will be executed under one contract by and under the direction of the Contractor.

1.3 DEFINITIONS

A. These definitions are supplementary to those contained in the Contract. B. Whenever within the Contract Documents the following terms are used, or pronouns in their

place, they shall have the meaning here given:

1. Contractor - Where the term "Contractor" or "Contractors" is used in the Contract Documents, it shall mean the General Contractor, including its subcontractors, having responsibility for the particular item of work being addressed by the document.

Page 4: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SUMMARY OF WORK 01010-2

2. The Owner - Where the term "Owner" is used in the Contract Documents, it shall be considered synonymous with the Southeastern Pennsylvania Transportation Authority (SEPTA).

3. Authority - There the term "Authority" is used in the Contract Documents, it shall be

considered synonymous with the Southeastern Pennsylvania Transportation Authority (SEPTA).

4. Engineer - Wherever the term "Engineer" is used in the Contract Documents, it shall

mean SEPTA, Rail Facilities Department or representatives as may be designated for the work.

5. Project Manager Wherever the term “Project Manager” is used in this document, it shall

mean the representative from SEPTA’s Construction Support group, Operations Support Division.

6. Agent - Wherever the term "Agent" is used in the Contract and these Specifications when

referring to an agent of SEPTA, it shall include the Engineer and its representatives. 7. Written Notice - Written notice shall be considered to have been duly served if delivered

in person to the individual, to a member of the firm or to an Officer to the Corporation for whom it is intended, or if delivered at, or sent by registered mail to, the last business address known to him who gives the notice.

1. 4 CONTRACTOR USE OF WORKSITE

A. In addition to requirements specified in the Agreement, perform the following:

1. Safety First. In all operations, the safety of SEPTA’s patrons, SEPTA and Contractor personnel, and the general public shall be of paramount consideration. Protect the general public from construction-related activities; do not unduly inconvenience those persons by construction activities. Conduct work in and on streets in a manner which will ensure that pedestrian and vehicular traffic will either not be obstructed or obstructed to the least possible degree.

2. In general, the work assigned will be expected be performed UNDER SERVICE. SEPTA cannot consider interrupting service for the convenience of the Contractor. If necessary, the desired staging will have been worked out before hand, and indicated in the Contract Drawings. The contractor, therefore, will be expected to perform the work with a minimum disruption to SEPTA’s service or its patrons. Should there arise a situation in which service must be interrupted, promptly notify the Project Manager for a resolution. The Contractor has no authority to interfere with SEPTA’s operations on his own.

3. The security of stored materials will be the Contractor's responsibility. It shall be the Contractor's sole responsibility to secure additional storage and work areas outside SEPTA's Right-of-Way, if required, for construction operations and absolve the Authority from any and all responsibility in connection with the use of such property.

4. Promptly vacate the worksite upon completion of the work by the Contractor and acceptance of the work by SEPTA.

Page 5: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SUMMARY OF WORK 01010-3

1.5 RESPONSIBILITY OF CONTRACTOR

A. The Contractor shall be held responsible for a finished product, fit for its intended purpose, and in accordance with the drawings and specifications. He shall provide, items and perform all work required as part of his work even though not particularly specified or indicated. Minor, incidental items, not specifically provided for in the Contract Documents will be understood to be part of the intent of the documents and will be provided for without additional charge.

B. In order to complete the various items of the Scope of Work, as defined by the Drawings and

Specifications or reasonably implied therein, the Contractor may require the service of other crafts. The Contractor is responsible for assigning the work of the various crafts in accordance with national and/or local jurisdiction agreements.

C. The Contractor, prior to start of any Work, shall contact the Pennsylvania-One-Call System (POCS) at 1-800-242-1776 in order to locate and mark all underground facilities. The serial number (s) shall be noted in the final report and/or drawings.

1.6 COORDINATION

A. All communications shall be handled through SEPTA's Project Manager. Do not deal with any other parties within SEPTA unless specifically authorized by the Project Manager. All responses from within SEPTA shall be made through SEPTA's Project Manager.

B. Thoroughly check all details of work and working conditions. Verify all dimensions and interfaces

in the field. Accurately check fit and dimensions required for adjoining the related work that is to connect in-place. Take actual field measurements of existing work, clearances, limitations, and other conditions along the lines of the work which affect accuracy of construction operations before laying out, furnishing or installing any work. Notify the Project Manager of any discrepancy before ordering material or performing work.

1. The Contractor is responsible for all coordination on site with the subcontractors.

1.7 SCHEDULE OF OPERATIONS

A. Submit a schedule of operations at the pre-construction meeting. This schedule shall be complete with regard to construction sequences and dates.

B. Maintenance of Traffic: Where required, show how he intends to maintain and enforce traffic flow.

1.8 REFERENCED STANDARDS

A. Provide materials, equipment, workmanship and design work conforming to the latest edition, revision, supplement and amendment thereto in effect on the effective date of Bid Opening.

1. Any reference within PA. DOT Specifications, Publication 408, to: a) "Department" shall be interpreted to mean the Authority.

Page 6: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SUMMARY OF WORK 01010-4

b) "Engineer" shall be interpreted to mean the Project Manager. 1.9 AVAILABLE INFORMATION

A. SEPTA will furnish the Contractor two complete sets of the Contract Drawings including full size Contract Drawings, Specifications, and Addenda. Additional copies will be available through the Project Manager for the cost of reproduction.

END OF SECTION

Page 7: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

MEASUREMENTS AND PAYMENTS 01025-1

SECTION 01025

MEASUREMENT AND PAYMENT 1.1 DESCRIPTION

A. This Section specifies the general requirements for measurement of quantities and the provisions for payment of the Contract in addition to the requirements and provisions set forth in the Agreement.

1.2 CONTRACT PRICES

A. Deviation in the actual quantities either above or below the estimated quantities shown on the Contract Drawings shall not be made a basis for a claim or adjustment in any of the contract prices.

1.3 PAYMENT

A. Payment will be made at the contract lump sum price in accordance with the provisions of the Agreement and will constitute full compensation for providing complete usable items. Payment will not be made until the Project Manager has inspected and accepted the work. All cost for work to be performed shall be covered by the lump sum price stated in the Schedule of Bid Items. Where work shown on the Contract Drawings or described in the Specifications is not directly indicated to be covered by a specific price item, the costs in connection with such work shall be included in the prices bid for the appropriate items in the Schedule of Bid Items.

B. The price of asphalt cement is indexed in accordance with the Commonwealth of Pennsylvania,

Department of Transportation Specifications, Publication No. 408/2011, Section 110.4 PRICE ADJUSTMENT OF BITUMINOUS MATERIALS.

1. The Price Index (IB) of Asphalt Cement Per Ton for this proposal shall be the May 2015

pricing shown on the Pennsylvania Department of Transportation Asphalt Cement/Diesel Fuel Price Index website. The frequency of adjustments to the Contract value for escalation/de-escalation shall be performed on a semi-annual basis

1.4 SCHEDULE OF BID ITEMS

A. In addition to the requirements of this Agreement, the payment items in the Schedule of Bid Items shall be governed by the provisions hereunder.

1. Mobilization: a) Work under this Item shall consist of initiation and demobilization for each project

under this Contract: setting up the Contractor's general plant, offices, shops, storage areas, sanitary and other facilities as required; providing access to the Project site; obtaining necessary permits, grants and licenses, and payment of fees.

b) Mobilization will be incorporated into the contractor’s bid items. No separate itemization of Mobilization will appear in the bid documents.

Page 8: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

MEASUREMENTS AND PAYMENTS 01025-2

2. Field Engineering:

a) Work under this item shall consist of setting survey controls, lines and grades in accordance with Section 01050, “Field Engineering”.

b) Field Engineering will be incorporated into the contractor’s bid items. No separate itemization of Field Engineering will appear in the bid documents will not be measured for payment.

3. Site Preparation: a) Work under this item shall consist of the clearing and grubbing the sites, and

the removal and disposal of objectionable materials and obstructions interfering with the proposed work in accordance with Section 02230, "Site Preparation".

b) Site Preparation will be measured for payment c) Site Preparation will be paid for at the Contract Unit Bid Price for SITE

PREPARATION as indicated on the schedule of Bid Items. 4. Excavation and Grading:

a) Work under this item shall consist of excavation, grading, and backfilling required for the work of this contract in accordance with Section 02300, "Excavation and Grading". Excavation will be unclassified.

b) Excavation and grading will be measured for payment c) Excavation and grading will be paid for at the Contract Unit Bid Price for for

EXCAVATION AND GRADING as indicated on the schedule of Bid Items 5. Erosion and Sediment Control:

a) Work under this item shall consist of providing Silt Fence, Drainage Inlet Protection, Sediment Filter Bag, and Straw Hay Bales to control erosion during construction per Section 02370.

b) Erosion and Sediment Control will be measured for payment c) Erosion and Sediment Control will be paid for at the Contract Unit Bid Price for

EXCAVATION AND GRADING as indicated on the schedule of Bid Items. 6. Site Improvements:

a) Work under this item shall consist of providing parking bumpers, pavement markings, site signing, concrete filled bollards, and highway guiderail per Section 02440.

b) Site Improvements Concrete will be measured for payment c) Site Improvements will be paid for at the Contract Unit Bid Price for SITE

IMPROVEMENTS as indicated on the schedule of Bid Items. 7. Bituminous Concrete Pavement:

a) Work under this item shall consist of providing all labor, tools, materials, supervision and transportation as required for constructing asphalt concrete pavement in accordance with Section 02520 " Bituminous Concrete Pavement".

b) Bituminous Concrete Pavement will be measured for payment c) Bituminous Concrete Pavement will be paid for at the Contract Unit Bid Price for

BITUMINOUS CONCRETE PAVING as indicated on the schedule of Bid Items. 8. Concrete Sidewalk:

a) Work under this item shall consist of providing all labor, tools, materials, supervision and transportation as required to construct concrete sidewalks in accordance with Section 02533 "Concrete Sidewalk".

b) Concrete Sidewalks will be measured for payment

Page 9: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

MEASUREMENTS AND PAYMENTS 01025-3

c) Concrete Sidewalks will be paid for at the Contract Unit Bid Price for CONCRETE SIDEWALKS as indicated on the schedule of Bid Items.

9. Concrete Curb: a) Work under this item shall consist of providing all labor, tools, materials,

supervision and transportation as required to construct concrete sidewalks in accordance with Section 02534 "Concrete Curbs".

b) Concrete Curbs will be measured for payment c) Concrete Curbs will be paid for at the Contract Unit Bid Price for CONCRETE

CURBS as indicated on the schedule of Bid Items. 10. Storm Sewerage Systems:

a) Work under this item shall consist of providing all labor, tools, materials, supervision and transportation as required for installation of the storm systems including stake out, excavation, de-watering, pipe, inlets, manholes, endwalls, frames, grates, lids, connections, and backfill in accordance with Section 02721 "Storm Sewerage System".

b) Storm Sewerage Systems will be measured for payment c) Storm Sewerage Systems will be paid for at the Contract Unit Bid Price for

STORM SEWERAGE SYSTEMS as indicated on the schedule of Bid Items. 11. Landscaping:

a) Work under this item shall consist of providing all labor, tools, materials, supervision and transportation as required for installation of the topsoil and hydro-seeding in accordance with Section 02941 "Landscaping".

b) Landscaping will be measured for payment c) Landscaping will be paid for at the Contract Unit Bid Price for LANDSCAPING

as indicated on the schedule of Bid Items. 12. Formwork:

a) Work under this item shall consist of providing all labor, equipment, material, and insurance to provide formwork for all cast in place concrete items, including curbs, sidewalks, and concrete track paving. Formwork will be incorporated into the contractor’s bid items for Cast-In-Place Concrete, Concrete Curbs, and Concrete Sidewalks. No separate itemization or Formwork will appear in the bid documents.

13. Cast-In-Place Concrete: a) Work under this item shall consist of providing all labor, tools, materials,

supervision and transportation as required to install curbing, islands, and steps in accordance with Section 3300 “Cast-In-Place Concrete”

b) Cast in Place Concrete will be measured for payment c) Cast-In-Place Concrete will be paid for at the Contract Unit Bid Price for CAST-

IN-PLACE CONCRETE as indicated on the schedule of Bid Items.

END OF SECTION

Page 10: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

FIELD ENGINEERING 01050-1

SECTION 01050

FIELD ENGINEERING PART 1 GENERAL

1.01 DESCRIPTION

A. Work included: This Section of the Specifications covers field engineering services as necessary to correctly complete the Work including, but not limited to:

1. Establishing and maintaining lines, levels and other survey controls as dictated by the specific project parameters.

2. Responsibilities: Each Separate Contractor is responsible to perform its own field engineering/surveying work.

1.02 QUALITY ASSURANCE

A. Use adequate numbers of skilled professionals and technicians who are thoroughly trained and experienced in the necessary areas and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this section.

B. A Professional Land Surveyor (PLS) Licensed to Practice in the Commonwealth of Pennsylvania shall perform the survey work for the Contractor. The PLS shall be on the Work site whenever survey activities are taking place.

C. Temporary support/excavation support shop drawings shall be prepared, signed and sealed by a Professional Engineer licensed in the Commonwealth of Pennsylvania.

1.03 PROCEDURES

A. In addition to procedures directed by the Contractor for proper performance of the Work, the Contractor shall:

1. Locate and protect control points before starting work on the site.

2. Preserve permanent reference points during progress of the Work.

3. Not change or relocate reference points or items of the Work without specific approval from SEPTA.

4. Promptly advise SEPTA when a reference point is lost or destroyed, or requires relocation because of other changes in the Work.

a. Upon direction of SEPTA, require the Contractor's surveyor to replace reference stakes or markers.

Page 11: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

FIELD ENGINEERING 01050-2

b. Locate such replacements according to the original survey control.

B. Before proceeding with the layout of actual work, the (insert each Prime for Multi-Prime contracts) Contractor shall verify the layout information shown on the drawings, in relation to the property survey and existing benchmarks. As the work proceeds, the surveyor shall check every major element for line, level and plumb. A surveyor's log or record book of such checks shall be maintained current at all times. Make this log or record book available for SEPTA or SEPTA's Architect and/or Engineer's reference. The surveyor shall record deviations from the required lines and levels, and shall, upon detection, promptly advise SEPTA of deviations exceeding indicated or recognized tolerances. The Contractor shall update final survey information on as-built drawings.

C. The Contractor shall be responsible for the stakeout of all property lines and corners

required to establish the location of fences and other items of work, of which location is referenced thereto.

D. The Contractor shall assume full responsibility for dimensions and elevations taken from benchmarks and baselines and for the setting of lines and grades.

F. The Contractor shall provide SEPTA with any assistance required for checking lines, grades, and measurements as may be requested by SEPTA.

1.04 PROJECT SURVEY RECORDS

A. On completion of any major structural element of the Work such as foundations, abutments, piers or other significant site improvement, the Contractor shall prepare and submit a certified survey illustrating dimensions, locations, angles, and elevations of the final construction and site work.

B. The Contractor shall preserve all field books and stakeout data until Final Acceptance of the Work at which time they will be signed and sealed by the licensed Surveyor (PLS) and turned over to SEPTA. The Contractor shall comply with any requests by SEPTA to review field books and stakeout data at any time during the course of Work. Submit field books and stakeout data to SEPTA as part of Project Closeout. The field books and stakeout data will become the property of SEPTA.

1.05 SURVEY CREWS

A. The Contractor shall employ a survey crew. The minimum required crew shall be onsite at all times to perform all survey related tasks as necessary to properly execute the Work in accordance with these specifications and the Contract Drawings. The members of the survey crew must be located in such proximity to the Work site that mobilization is possible within four hours of notification by SEPTA.

END OF SECTION

Page 12: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-1

SECTION 01060

REGULATORY REQUIREMENTS AND SAFETY

PART 1 - SAFETY 1.01 DESCRIPTION A. This Section specifies the safety & environmental requirements for contractor personnel

involved in construction, maintenance, and rehabilitation projects on SEPTA property. The Contractor is required to assure that all employees, subcontractors, and suppliers/vendors, while on the Work site comply with the provisions of this Section.

B. At those facilities to remain in operation during construction, or are adjacent to SEPTA right or

way, the Contractor shall take every precaution necessary to assure the safe access and egress of all SEPTA customers and employees, the safe and continuous operation of all SEPTA vehicles, ensure the appropriate protection of the environment as well as the safety and general welfare of the public at large. Depending on the configuration of the project, the contractor may be responsible for providing temporary pedestrian access including access which is accessible to those with disabilities. Under no circumstances is the contractor to block or restrict public or SEPTA entrances or the SEPTA vehicle right of way without prior written approval of the SEPTA Project Manager.

1.02 SUBMITTALS

The Contractor shall furnish a copy of the Contractor’s project/site specific safety plan (and corporate program if referenced) and protocols to the Project Manager within 30 days from receipt of the Notice to Proceed. The SEPTA Project Manager may prohibit and/or restrict any work on site until this plan has been received and approved. If these specifications call for certification or licenses from the Commonwealth of Pennsylvania, it is understood that certification or licensure shall be from the state where the work is occurring and in the case of work in multiple states, then licensure from multiple states may be required.

1.03 QUALITY ASSURANCE

A. The Contractor shall be responsible for ensuring compliance with the regulations of all applicable occupational safety and health statutes and regulations of all of the applicable political jurisdictions where the work is being performed including those relating to the U.S. Department of Labor, FRA, FTA, and Occupational Safety and Health Administration (OSHA) standards. The Contractor shall conduct daily monitoring and document the compliance and performance of the requirements set forth in this document and those required by applicable governmental agencies. This documentation will be based on the applicable code requirements and shall be made available upon request of the SEPTA PM.

Page 13: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-2

B. SEPTA Project Managers (SEPTA PM), Authority employees, and SEPTA’s third party

consultant staff will monitor compliance with all applicable internal safety and environmental regulations and environmental contract specifications.

C. The Contractor’s employee safety program, which must be site specific, shall include but not be limited to the following (as applicable):

1) Work Site Orientation

a. Safety and health hazards present in the work assignment and the general work area.

2) OSHA - written programs applicable to scope of work.

3) Required training, licensing or certification, and documentation of same

4) Workers’ Compensation Reporting

5) Fall Protection equipment and requirements

6) Personal Protective Equipment

7) Confined Space Procedures

8) Hazardous Materials Handling and Disposal

9) Trenching and Excavation including shoring and sheeting

10) Cranes

11) Electrical Protection

12) Drug and Alcohol prohibitions and testing

13) Public, SEPTA Employee, and Passenger Protection

14) Site Emergency Procedures and Contact Information

a. Emergency contact numbers

b. Emergency escape routes and evacuation meeting place.

15) Nearest hospital including directions from the site with route maps

D. The Contractor shall provide a designated qualified safety officer who shall be responsible for all safety-related activities until the completion of the Work. The Contractor is also responsible for all safety related activities for all their subcontractors and suppliers working at the work site.

E. The safety officer shall report all on-the-job injuries at once to the SEPTA Project Manager and submit all paperwork pertaining to such injuries, within 24 hours or as required by the SEPTA PM.

F. The Contractor's safety officer shall, as a minimum hold weekly (tool box) safety meetings

Page 14: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-3

with all of the Contractor’s personnel. Subjects, time, and location may be set at the Contractor's convenience. At least three (3) days prior to each meeting, SEPTA requires an agenda be submitted to the SEPTA Project Manager, including the time and location of each meeting. Copies of signed attendance sheets and the meeting minutes shall be submitted to the Project Manager at each regularly-scheduled project coordination meeting.

G. The Contractor is required, by Agreement, to maintain an alcohol and drug free environment.

The Contractor shall describe in their employee safety program on how this contract stipulation is to be accomplished and maintained. Please note that SEPTA reserves the right to restrict access to its property, because of the inherent safety hazard to its employees and general public. Any person shall be immediately removed and barred from SEPTA property if in the opinion of SEPTA’s Project Manager, and/or other appropriate SEPTA representative, that person constitutes a safety risk.

1.05 GENERAL SAFETY REQUIREMENTS

A. The Contractor shall supply and furnish all required personal protective equipment (PPE) for their employees. The Contractor is also responsible for ensuring that PPE is worn correctly by all employees while on the work site. The Contractor’s employees shall wear compliant safety equipment including, but not limited to, hard hats, work shoes/boots, safety vests, safety glasses, and fully body cover clothing, including flame retardant (FR) clothing where and when it is required.

1. The minimum PPE standards must be met as outlined below:

a. Hard hats shall be ANSI-Z89.1 2003, Class E. Hard hats shall be worn at all times while on the work site.

b. Work shoes (ASTM 2413-11 C75 / I75) shall have non-slip soles. Permanent

metal plates or cleats on the sole or heel of shoes are prohibited. Shoelaces are to be kept short so they do not pose a tripping hazard. Athletic shoes, sandals, open-toed shoes, moccasins and/or shoes with heels higher than 1” are not permitted.

c. Contractor personnel shall wear eye protection at all times on the work site. Eye

protection shall be safety glasses with rigid side shields that comply with ANSI Z-87.1. Prescription eyewear shall also meet the same requirements as described above, or the individual shall wear equivalent eye protection over their prescription glasses or contact lenses.

d. The safety vest shall be ANSI 107, Class 2 high-visibility with a yellow-green

background and 2-inch retro-reflective striping for work on SEPTA owned property within any public right-of-way, where exposed to vehicular traffic, or otherwise required by rules or regulations. Work in Amtrak territory requires the use of an orange vest subject to approval by Amtrak.

e. The Contractor’s personnel shall wear long pants (without cuffs) and, at a

minimum, short sleeve shirts. Sleeveless shirts are prohibited.

Page 15: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-4

f. Approved hearing protection shall be worn in all designated areas identified by

signs or when operating high noise level equipment. The contractor is responsible for providing acceptable hearing protection for their employees as outlined in OSHA 29 CFR 1910.95.

g. The Contractor is responsible for providing acceptable respiratory protection for their employees as outlined in OSHA 29 CFR 1926.103.

h. Gloves shall be worn where hand injuries are likely to occur based on the hazard present.

B. The Contractor shall take all necessary precautions and provide protective measures to

prevent injury to the public and damage to property of others. To prevent unauthorized access to the work zone and storage areas, the Contractor shall furnish and erect construction fencing or barricades and signage, as specified in the contract documents or as directed by the SEPTA PM, for the safeguarding of the public against accident or damage before commencing operations. The Contractor shall maintain the protective measures and/or construction fencing in good condition as evaluated by the SEPTA PM, until removal.

C. The Contractor shall dismantle, remove and/or relocate construction fencing and barricades

when directed by the SEPTA Project Manager.

D. The Contractor must ensure personnel, including subcontractors and vendors, receive the required SEPTA (and Amtrak or other railroad if applicable) Safety Training for the affected mode(s) before starting work. This covers the rules and procedures for personnel and equipment including but not limited to, working in or about stations, yards, tunnels, or adjacent to the track right-of-way. All personnel who are present at the job site at any time must have this training. All personnel are required to wear / display their safety training card.

E. The Contractor is required to comply with OSHA’s Noise Standard 29 CFR 1910.95 and any local noise ordinances.

F. Where it is permitted to store materials on streets, the Contractor shall place such materials in a secured place in accordance with local jurisdictions so as to cause minimum obstruction to traffic and public safety. The Contractor shall not place materials within 15 feet of fire hydrants nor obstruct drainage gutters and inlets. The Contractor shall obtain and pay for all required permits relative to materials storage.

G. Material stored on site must be secured to prevent vandals from placing debris or material on

the right-of-way. Material placed on the right of way must be removed by the contractor immediately upon notification, at any time, at no cost to SEPTA. At no time shall any merchandise, material, or other articles be permitted to remain piled or assembled on the ground or on platforms adjacent to any track at a distance of less than ten feet, (10'-0") from the center line of such track.

Page 16: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-5

H. Copies of Safety Data Sheets (SDS) and the quantity of each chemical must be provided to the

SEPTA Project Manager for review and approval before chemicals can be brought to any SEPTA property. The SDS will be reviewed by SEPTA’s System Safety and Risk Management Department for approval.

I. All SDS must comply with OSHA’s Hazard Communication Standard 29 CFR 1910.1200. In addition, all Contractors must be trained per the Hazard Communication Standard. The Contractor is responsible for maintaining all SDS used at the work site.

J. The storage of hazardous and flammable materials on SEPTA property is restricted and permission for each material must be granted by the SEPTA Project Manager. When storing flammable and hazardous materials and hazardous waste, they must be stored in compliance with all applicable regulations. Flammable materials shall not be stored in confined spaces or other similar areas such as tunnels, underground rooms and building basements.

K. If hazardous substances are present, such as wastes, or if the potential for a hazardous release exists, the Contractor is responsible for following their Site Safety Plan covering policies and procedures to protect workers and the public from the potential hazards.

L. Firearms or any items classified as concealed weapons will not be brought onto SEPTA’s property.

M. All tobacco use is prohibited within the construction project and all areas subject to restrictions by SEPTA or by local, state and federal law. Smoking within SEPTA indoor facilities is prohibited.

N. The Contractor may not block or obstruct access to emergency equipment such as first aid kits, AED units, eyewash stations, fire extinguishing equipment, fire hydrants, transformers, or emergency generators. Emergency equipment must not be disconnected or relocated by the Contractor without permission from SEPTA’s Project Manager.

O. All electronic devices must be turned OFF or placed in airplane mode when working within the

fouling envelope of the right of way. If an individual must make a phone call, they must first step outside the fouling envelope of the right of way to make or receive the call or otherwise use an electronic device. The contractor and his personnel are libel for all fines assessed by the Federal and/or state regulators for a violation of this regulation. Violation of this regulation can result in the individual being prohibited from working on the project.

P. The use of head phones, ear buds, etc. are prohibited while in a construction area.

1.06 ACCIDENT AND INJURY REPORTING

A. The Contractor is responsible for reporting and investigating all work related accidents and

Page 17: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-6

incidents. This shall be completed in a timely manner with recommendations for corrective actions to prevent similar accidents or incidents. Accidents and incidents include:

a. Personal Injury b. Property Damage c. Near Misses d. Actual or potential exposure to toxic substances e. Hazardous material spills and releases f. Fires

B. The Contractor must notify the SEPTA Project Manager for all accidents and incidents that occur on SEPTA property immediately.

C. SEPTA reserves the right to conduct an independent investigation of all accidents and

incidents that occur on the work site with the full cooperation of the contractor, subcontractor and employees.

D. At accident locations where conditions are immediately dangerous to life and health, work shall be suspended until corrective actions are taken to the satisfaction of the appropriate SEPTA representative.

1.07 EMERGENCY PROCEDURES A. The Contractor shall set up emergency procedures and prepare written guidelines discussing

such procedures for the following categories: 1. Fire 2. Injury to contractor’s and/or SEPTA employees 3. Injury to general public 4. Property damage, including property of utilities, i.e., gas, water, sewage, electrical,

telephone or pedestrian and vehicle routes.

5. Hazardous/toxic material spill, discharges and/or exposure.

6. Site evacuation.

B. Copies of all guidelines for emergency procedures shall be written and posted prior to the initiation of actual construction. Posting shall include emergency telephone numbers and directions to and from the nearest hospital. The Contractor shall have standing arrangements for the transportation and hospital treatment of any employees who may be injured, are exposed to hazardous material, or who may become ill. These guidelines shall be included in

Page 18: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-7

the Contractor's written safety program and shall be submitted to SEPTA. C. The Contractor shall provide a fully equipped first aid kit at the site. This kit will be made

available to the SEPTA PM for their inspection and approval at any time. D. The Contractor must discuss site emergency procedures at the beginning of the project, with

the addition of a new worker to the site, and at least monthly with all personnel at tool box safety meetings. Any changes to the work site emergency procedures must be documented and employees, vendors and the SEPTA Project Manager notified.

E. SEPTA operational emergencies will be handled by the senior SEPTA Operations personnel present. This individual, designated “The Incident Commander” is responsible for summoning the number of persons required by the situation and assignment of all recommended procedures.

1.08 PROTECTION OF SEPTA FACILITIES

A. The Contractor shall be cognizant of and bound by SEPTA's safety rules and regulations specified herein and conduct operations in strict accordance with same.

B. SEPTA shall be the sole judge of protection necessary for the safe operation of its facilities.

SEPTA reserves the right to alter this protection at any time. C. SEPTA’s Facilities and/or Structures shall not be utilized by the Contractor for temporary

scaffolding and/or support for the construction effort without permission. A Contractor may request SEPTA’s consideration for such action. The Contractor shall provide a detailed plan to utilize SEPTA’s Facilities and/or Structures. The plans will be submitted for SEPTA’s review and approval prior to the initiation of any work. SEPTA also reserves the right to have the drawings and supporting calculations sealed by a Professional Engineer registered in the Commonwealth of Pennsylvania, or appropriate jurisdiction, at no cost to SEPTA.

D. Before any work is done in the vicinity of an existing structure, SEPTA must be notified and

may require a plan for stabilizing and underpinning the structure prepared and sealed by a Professional Engineer licensed in Pennsylvania, or appropriate jurisdiction, at no expense to SEPTA.

1.09 CRANE, MATERIAL HANDLING, AND ERECTION SAFETY

A. The Contractor shall take care to prevent any structure from being loaded with a weight, for any duration, which will endanger its stability, or the safety of persons.

B. The contractor shall adhere to all Local, State, and Federal laws pertaining to crane operations.

Page 19: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-8

C. All cranes must be inspected annually as well as monthly. The most recent reports shall be submitted to SEPTA prior to the use of the cranes on any work site. SEPTA’s Project Manager must ensure that daily safety inspections are completed. The monthly reports for the crane must be submitted to the SEPTA Project Manager on a pre-determined schedule as long as the crane is operating on the project.

D. The Contractor shall ensure all crane operators and riggers are trained and competent in the

use of such equipment. The Contractor shall provide a competent person to oversee and/or perform lifting operations as required by OSHA. Personnel qualifications will be made available to SEPTA upon request.

E. The Contractor shall submit for review to the Project Manager, sketches defining the

operations of all cranes, material handling equipment, and erection activities used in support of construction during periods of train operations. The Contractor shall submit, at the Project Manager's request, similar information for cranes or other equipment in use and capable of encroachment.

1. These sketches shall include planned locations and movements of the equipment,

calculations demonstrating the adequacy of the capacity of the crane for the loads, the interface between the footprint of the equipment the movement of the boom and loads relative to the existing structure and surrounding buildings, the support grillages and the protection of existing utilities and facilities, and any other pertinent details required by the Project Manager.

2. The following data shall be required for all hoisting operations adjacent to active SEPTA

operations and facilities and shall be prepared by and sealed by a Professional Engineer licensed in Pennsylvania.

a Plans and sections showing locations of cranes, horizontally and vertically,

operating radii, with delivery of disposal locations shown. The location of the SEPTA Right of Way and all active facilities shall also be shown.

b Crane rating sheets showing cranes to be adequate for 150% of the actual weight

being lifted. A complete set of crane charts, including crane, counterweight, and boom nomenclature is to be submitted.

c A location plan showing all obstructions such as wires, poles, adjacent structures,

etc., and that the proposed lifts are clear of these obstructions.

d A data sheet shall be prepared listing the type, size, and arrangements of slings, shackles, or other connecting equipment, all to be designed for 150% of the actual weight being lifted. Copies of a catalog or information sheets for specialized equipment shall be included.

e A complete procedure is to be included, indicating the location and order of lifts

and any repositioning or re-hitching of the crane or cranes.

Page 20: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-9

f Temporary support of any components or intermediate stages is to be shown and

detailed.

g A time schedule of the various stages must be shown as well as a schedule for the entire lifting procedure.

F. Specialty slings and hooks shall not be used to set steel or move materials over workers. All

sling and crane load line hooks shall have safety latches installed or shall be moused, except for specialty slings and hooks such as sorting or shake out slings or self-adjusting pipe slings.

G. The Contractor shall not leave suspended loads unattended. When moving loads, the

operator shall ensure a clear path free of personnel or other barriers.

H. The Contractor shall establish a restricted work area using barricades and other appropriate controls to minimize the hazards to personnel, customers, and equipment from swinging or falling objects.

1.10 SNOW REMOVAL

A. The Contractor shall remove all snow and ice within the project site as required for the proper protection and prosecution of the Work, and to protect SEPTA employees and the public. The Contractor shall at all times provide and maintain adequate protection against weather so as to preserve all Work, materials, equipment, apparatus, and fixtures free from damage.

B. The Contractor shall not use sodium chloride (or any chloride) on any facilities adjacent to

SEPTA electric rail lines where the possibility exists that melting mixture may leach onto the contact rail within the Right of Way.

1.11 WELDING, CUTTING AND OTHER HOT WORK

Gas or electric cutting, burning, or welding shall be done in accordance with the guidelines of NFPA 51 B, the International Fire Code, federal, state, and local rules and regulations, or the provisions below, whichever is more restrictive.

A. If hot work is to be executed at a job site, the prime contractor’s safety officer must have a copy of the current version of NFPA 51B at the job site.

B. The prime contractor’s safety officer shall act as a Permit Authorizing Individual (PAI) and complete the checklist to fulfill the requirements of by 51 B for all torch work. The contractor shall obtain the current copy of SEPTA’s “Hot Work Checklist” for this purpose.

C. The SEPTA PM shall be notified at least 48 hours in advance of any hot work on site. A copy of each checklist completed for that period shall be delivered to the SEPTA PM at the next job progress meeting.

Page 21: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-10

D. Spark shields and a fire watch must be posted when executing hot work and for a period of at least four hours after all activity has been completed. The SEPTA PM reserves the right to extend the duration of the fire watch in special circumstances. A supply of water and an approved fire extinguisher shall be readily available to the location where the work was done.

E. All oxygen/acetylene bottles must be removed and stored outside of all tunnels, underground stations and other confined spaces at the end of the workday. While in use in a tunnel, underground station or other confined space, they shall be attended at all times. At no times when not in use shall oxygen and acetylene bottles be stored together.

E. Anti-flashback devices must be installed on the fuel side of all gas and oxygen cutting torches

1.12 GAS CYLINDERS

A. Compressed gas cylinders shall be handled and properly supported and secured in an upright position away from heat or flame sources. Cylinders that are not being transported must have their caps in place.

B. Regulators, hoses, and torch assemblies must be in working order and checked for leaks prior

to initial use or installation. If a leak is discovered, the cylinder must be removed to a safe location.

C. Cylinders must be labeled and stored according to compatibility with signs posted. D. Oxygen and acetylene cylinders, empty or full, shall not be stored together. Full oxygen

cylinders must be separated from acetylene cylinders or other fuel-gas cylinders or combustible materials a minimum distance of 20 feet or by a noncombustible barrier at least 5 feet high having a fire-resistance rating of at least one-half hour.

E. All cylinder valves must be closed when cylinders are not in use and the hose pressure bled

down. F. All cylinders must be removed from confined spaces at the end of each work day.

1.13 UTILITIES

A. Before any excavation begins, the Contractor must determine the location of all utility installations such as but not limited to sewer lines, telephone lines, fuel lines, underground electric lines, water lines, or any other underground installations that may be present during excavations.

B. As per 73 P.S., § 176, et seq., the Contractor is required to notify utilities prior to all

excavations. The Contractor shall be held responsible for any damage done to any utility in the prosecution of the Work. The Contractor shall exercise any precautions necessary to prevent damage in working underneath or adjacent to any underground structure. If it becomes necessary for a utility company, through emergency procedures or because of unforeseen conditions, to repair, reconstruct, relay or relocate utilities within the contract area,

Page 22: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-11

after work has commenced by the Contractor, then the said utility company and the Contractor shall make suitable arrangements to overcome such interference. All work shall be accomplished at no extra cost or charge to SEPTA. No compensation shall be allowed the Contractor for the disruption to his work. A no-cost time extension may be granted in accordance with the Contract to the Contractor by SEPTA for the delay that has occurred.

1.14 HOUSEKEEPING

A. The Contractor shall maintain their work area in an orderly manner. B. The Contractor shall provide containers for trash and scrap metal unless prearranged with the

SEPTA Project Manager before the start of the project. C. The Contractor is responsible for the proper disposal of hazardous, flammable, trash, and/or

excess waste material. All waste must be removed or secured on site daily. See SEPTA’s Contractor Environmental Safety Requirements for more information on hazardous waste.

D. The Contractor is responsible for maintaining all disposal records, including chain of custody

records for hazardous or untested material, and providing copies to the SEPTA Project Manager where applicable.

E. No on site burning or burying of waste or material is permitted.

1.15 ELECTRICAL

A. The Contractor directly involved with electrical work, or work adjacent to electrical hazards shall do so only after details of the work has been planned and approved by SEPTA.

B. All electrical work shall comply with OSHA 29 CFR 1926.400 (Electrical Standard), OSHA 29

CFR 1910.147 (Lockout/Tagout), The National Electric Code (NEC), NFPA 70E (latest editions), and any SEPTA standards.

C. All equipment and cords must be free from damage. Frayed or cut electrical cords, or cords

with damaged plugs or missing ground plugs shall immediately be removed from service, rendered unusable, and removed from the work site.

D. All electrical tools and equipment must be grounded. E. Before working on a de-energized circuit, it must be electrically tested to ensure it is de-

energized. F. The Contractor must complete lockout/tagout procedures for all machines, equipment, and

systems that require service or maintenance as required by 29 CFR 1910.147.

Page 23: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-12

1. A lock or tag can only be removed by the individual or their designee. G. After the Contractor performs repairs, maintenance or installations, and before SEPTA

employees attempt to re-energize the electrical equipment, verification shall be performed in the presence of the SEPTA PM to ensure that the electrical equipment components are operationally intact and that no electrical hazard is present up on re-energizing.

1.16 CONFINED SPACE

A. The Contractor shall be required to have competent and trained personnel for restricted or confined space entry work.

B. All confined spaces at SEPTA are permit required spaces and the Contractor is required to

utilize SEPTA’s confined space permit. C. Confined spaces refer to a space which by design has limited openings for entry and exit but

large enough to enter to perform work, the potential for toxic atmosphere or one that can produce a toxic atmosphere, and is not designed for continuous occupancy. Confined spaces at SEPTA can include, but not limited to, storage tanks, boilers, trenches, manholes, lift stations, and valve pits.

D. The Contractor shall coordinate and obtain approval from the SEPTA Project Manager for all

confined and restricted space activities. E. The Contractor must provide emergency rescue based on the work being conducted.

Documentation on the rescue procedures, authorized rescuers, training and equipment must approved by SEPTA and be available on site prior to conducting confined space entries.

1.17 EXCAVATION AND TRENCHES

A. The Contractor shall provide training to all personnel required for safe trenching and excavation projects on SEPTA property and comply with OSHA Excavation Standard 29 CFR 1926 Subpart P.

B. Prior to any excavations or trenching, the Contractor shall be responsible for utility marking to

ensure the area impacted is free from underground hazards. C. Excavations and trenches over 4-feet must have appropriate protective systems such as but

not limited to sloping, trench shields, and shoring, if soil conditions are unstable excavations less than 4 feet must have protection. This requirement is in addition to any other regulatory requirements including OSHA requirements.

D. Daily inspections of excavations, adjacent areas, and protective systems must be made by

the Contractor to ensure safety systems are functional and effective.

Page 24: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-13

E. The Contractor shall place warning signage and barricades or fencing to prevent unauthorized or accidental access to the site.

F. The Contractor shall cease work immediately and contact the SEPTA Project Manager if

suspect material such as strong odors, discolored soils, pipes, pipe covering or other material indicating the potential presence of asbestos, or other hazardous materials is encountered.

1.18 LADDER SAFETY

A. All ladders and their use must comply with OSHA 29 CFR 1926.1053 and ANSI specifications.

B. Metal or other conductive ladders are prohibited. C. Ladders must be inspected before use and must be in good condition and free of any broken

or defective parts. Defective ladders must be removed from service. D. The Contractor must provide training to all employees using ladders in their proper use, how

to recognize ladder hazards and how to correct identified safety hazards.

E. Job fabricated ladders are prohibited.

1.19 FALL PROTECTION

A. The Contractor shall provide fall protection and proper training for its employees, as required by 29 CFR 1926.500. Fall protection is required in areas where the fall hazard is 6 feet or greater from the worker’s foot level.

B. The Contractor shall isolate work areas to protect persons from falling objects and to prevent

unauthorized access to the work site. C. The Contractor shall perform documented inspections of their fall protection equipment before

each use. D. Work being conducted within six feet of a floor opening (skylight, hole, open hatch, etc.)

requires the appropriate fall protection. E. Work being conducted on a roof within six feet of the edge requires the appropriate fall

protection. The Contractor shall not work on or access roofs without prior approval from SEPTA Project Manager.

1.20 SCAFFOLDS

Page 25: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-14

A. All scaffolding, staging, and work platforms must satisfy OSHA 29 CFR 1926.450 and the manufacturer’s requirements.

B. The Contractor shall ensure that scaffolding be erected and inspected by trained personnel. C. The Contractor shall perform documented pre-use inspections for erected scaffolding.

1.21 POWERED EQUIPMENT/WORK PLATFORMS

A. The Contractor shall not use SEPTA owned or leased powered equipment or aerial work platforms unless approved by the SEPTA Project Manager.

B. The Contractor shall ensure only trained an authorized personnel operate any powered

equipment such as but not limited to forklifts, extendable boom lift, scissor lifts, and cranes. C. The Contractor shall perform documented inspections of equipment prior to each day’s use to

ensure safe operating condition. Defective equipment must be segregated and not be used on the work site.

D. The Contractor must ensure all its employees and subcontractors have had appropriate and

effective training in compliance with OSHA 29 CFR 1910.178 (Powered Industrial Vehicles) and 29 CFR 1926.453 (Aerial Lifts) and the manufacturer’s recommendations.

1.22 FIRE SAFETY

A. The Contractor’s personnel should be familiar with the location of fire alarm pull stations, portable fire extinguishers and exit routes from the work area. The Contractor shall not obstruct access to exits, exit routes, or fire equipment or prop-open stair well doors.

B. Fires shall be reported by activating the nearest fire alarm station and calling 911. C. The Contractor’s personnel shall be trained in the proper use of a portable fire extinguisher in

the event fire watch duties are required. D. Flammable and combustible materials at a minimum must be labeled, properly stored, and

disposed of. Please see the Contractor Environmental Requirements. E. The Contractor must follow requirements listed in the “Welding, Cutting and Other Hot Work”

section of this document, if welding, torch cutting, soldering or other forms of “hot work” will be performed.

F. The Contractor must take precautions to prevent damage to fire protection systems. All

damage must be reported immediately to the SEPTA Project Manager.

Page 26: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-15

G. The Contractor must not disable a fire protection system (sprinklers, fire alarm system components, etc.) unless prior approval has been provided by the SEPTA Project Manager and local fire department. If a system is disabled, fire watch personnel must be present until that system is reconnected or other arrangements have been made and approved by the SEPTA PM.

H. Materials or equipment must not be temporarily or permanently suspended on sprinkler pipes,

valves, or supports. 1.23 PROTECTION OF EXISTING WATER AND SEWER LINES

A. When the equipment axle load exceeds 15 tons, the Contractor shall provide and work from timber mats placed over existing underground water lines and sewer lines.

B. SEPTA reserves the right to require additional protection and/or protection plans sealed by a professional engineer.

PART 2 - ENVIRONMENTAL 2.01 SUBMITTALS

A. The Contractor shall furnish for review by SEPTA the Contractor’s Environmental and/or Waste Management Program within thirty (30) days from receipt of the Notice to Proceed (see Section 2.04.B).

B. Prior to the start of work, Contractor shall furnish for review by SEPTA a Means and Methods Plan describing the day-to-day activities the contractor will employ to complete construction in accordance with the specification requirements. The Means and Methods Plan shall include the following:

1. A detailed, stepwise description of the construction process organized sequentially; 2. A description of any specialized equipment to be utilized to complete the work; 3. Identification of potential hazards in the construction process; and 4. A description of the construction mitigation measures that the contractor will implement to

mitigate identified hazards. C. Prior to the start of work, Contractor shall furnish for review by SEPTA a copy of asbestos and

lead survey findings/reports. If asbestos abatement or lead removal is conducted, Contractor shall further furnish to SEPTA prior to the start of those activities, all relevant submittals including but not limited to notifications, work plans, and health and safety plans. Within thirty

Page 27: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-16

[30] days of completion of work, waste disposal records documenting disposal at a SEPTA-approved facility shall also be submitted to SEPTA (see Section 2.07.H).

2.02 QUALITY ASSURANCE

A. The Contractor shall daily monitor and document the compliance and performance of the requirements set forth in this Section consistent with appropriate SEPTA Work rules and Federal, Commonwealth of Pennsylvania, and Local rules and regulations. The Contractor shall document the Contractor's compliance with applicable codes and regulations.

B. The Contractor’s Environmental and/or Waste Management Program, as a minimum, shall

include but not be limited to the following as applicable to the Work:

1. Sustainability and Recycling

2. Waste Management and Disposal

3. Hazardous Materials

4. Soils Management

5. Erosion and Sedimentation Control

6. Noise Control (if applicable)

C. The Contractor shall provide a qualified environmental safety officer who shall be responsible for all environmental safety-related activities until the completion of the Work. The environmental safety officer shall report all on-the-job environmental incidents at once to the Project Manager and submit all paperwork pertaining to such incidents as required.

2.03 EMERGENCY PROCEDURES

A. The Contractor shall set up emergency procedures and prepare written guidelines discussing

response and notification actions related to hazardous/toxic material spills, discharges, or releases. Such guidelines shall be incorporated into one or more Contractor’s required site-specific plan submittals, such as the Health and Safety Plan, Work Plan, Contingency Plan, or Environmental/Waste Management Program.

2.04 STORAGE AND HANDLING OF MATERIALS

A. Materials Handling:

1. All scrap material of any kind, type, or nature shall be placed into designated confined areas or containers specifically supplied for this purpose. Containers shall be removed

Page 28: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-17

from the job site when full. 2. The Contractor shall assure that all chemicals, paints, solvents, and cleaners are

maintained per OSHA's hazard standards. Discarded chemicals shall be disposed of in accordance with applicable Commonwealth of Pennsylvania Department of Environmental Protection (PaDEP) and/or Environmental Protection Agency (EPA) requirements. Copies of all Material Safety Data Sheets (MSDS), OSHA Form 20, and the Product Use sheets shall be given to SEPTA's Project Manager before or at the time of material delivery. All training shall be done in accordance with OSHA's Hazard Communication Standard.

3. Materials handling shall be conducted in accordance with the Contractor’s Environmental

/ Waste Management Program (see Section 2.04).

2.05 ENVIRONMENTAL PROTECTION

A. Environmental protection considerations consist of, but are not limited to, the following factors:

1. Natural resources, including air, water, and land. 2. Solid Waste disposal. 3. Noise. 4. Control of toxic substances, hazardous materials, and radiation. 5. The presence of chemical, physical, and biological elements and agents that adversely

affect and alter ecological balances. 6. Degradation of the aesthetic use of the environment. 7. Historical, archaeological, and cultural resources.

B. General Requirements:

1. The Contractor shall provide and maintain environmental protection as defined herein or

as required by regulation, whichever is more restrictive. 2. The Contractor's operation shall comply with all applicable Federal, Commonwealth and

Local laws, ordinances, and regulations pertaining to environmental protection.

3. Compliance of subcontractors and suppliers with the provisions of this and all other sections of these Specifications shall be the responsibility of the Contractor.

4. The Contractor shall not use equipment from which factory-installed antipollution and

Page 29: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-18

noise control devices have been removed, altered or rendered ineffective intentionally or through lack of proper maintenance.

5. Unless the Contractor has tested and established the safety of existing paints and

coverings, he shall provide adequate pollution controls for painting and surface preparation in compliance with the PaDEP Regulations.

C. Protection of Natural Resources: 1. General

a. It is intended that the natural resources within the project boundaries and outside the limits of permanent Work performed shall be preserved in their existing condition or be restored to an equivalent of the existing condition, as approved by the Project Manager upon completion of the Work. The Contractor shall confine its on-site construction activities to areas defined by the Contract Drawings and Specifications or as directed by the Project Manager.

2. Protection of Project Site and Existing Roadways:

a. Debris or rubbish of any kind shall not be dumped onto the site or roadways. This shall include paint splatters, cleaning, stripping and surface preparation chemicals and spillage during painting operations. Care shall be taken to prevent damage and injury to personnel, vessels, and vehicles using roadways, or areas accessible to pedestrians. Devices shall be provided and maintained by the Contractor as required to prevent such occurrences. Material or items falling onto roadways shall be promptly removed at the Contractor's expense. All damage to third party property shall be restored by the contractor to the owner’s satisfaction at no cost to SEPTA.

b. The operator shall remove from the site, recycle, or dispose of all building materials and wastes in accordance with the PaDEP solid waste management regulations at 25 pa code 260.1 et seq., 271.1 et seq. The contractor shall not illegally bury, dump, or discharge any building material or wastes at this site.

3. Land Resources:

a. Except in areas indicated to be cleared or excavated, the Contractor shall not remove, cut, deface, injure, or destroy trees, shrubs, or vegetation. No ropes, cables, or guys shall be fastened or attached to any existing nearby trees for anchorage unless specifically permitted by the Project Manager. Where such use is permitted, the Contractor shall be responsible for any resulting damage.

b. The use of pesticides or herbicides is not permitted unless approved in writing by

the SEPTA PM. c. The Contractor shall submit a plan for protecting existing trees and vegetation

that are to remain and that may be injured, bruised, defaced, or otherwise

Page 30: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-19

damaged by construction operations. Rocks that are displaced into uncleared areas shall be removed. Monuments, markers, and works of art shall be protected prior to the start of the operations. A preconstruction survey, including photographs, shall be performed by the Contractor in the presence of the SEPTA PM, and a written report of the survey shall be furnished to SEPTA within five (5) days of its request by the Project Manager.

d. Repair and Restoration: All trees, vegetation and other man made or natural

landscape features that are to remain and become scarred or damaged by the Contractor's equipment or operations shall be repaired and restored to their original condition at the Contractor's expense. The Project Manager shall approve the repair and restoration program prior to its initiation and after completion.

4. Water Resources: At all times, measures shall be taken to prevent oil, gasoline and other

hazardous substances and pollutants from entering the ground, drainage areas, sewers, streams, and other local bodies of water.

5. Wildlife Resources: The Contractor shall not disturb native habitat adjacent to the project

construction area. D. Erosion and Sediment Controls: 1. Site burning of any kind, including ground vegetation, is not permitted. 2. The Contractor shall conform to all applicable requirements of the PaDEP and the County

with respect to erosion and sediment control measures to prevent discharge into storm water discharge systems and active waterways.

E. Toxic Substances: 1. The Contractor shall comply with the Toxic Substance Control Act, P.L. 94-469 (TSCA). a. No toxic chemical substance, mixture, equipment, container, sealant, coating, or

dust-control agent shall be used except in accordance with all provisions of the TSCA as interpreted by the rules and regulations of 40 CFR 761.

b. Any toxic chemical substance, mixture, equipment, container, sealant, coating, or

dust-control agent found stored within the project area shall be immediately reported to the Project Manager in writing and work shall be stopped in the area. The Project Manager shall make arrangements for the removal of the toxic materials, will ensure that the area is safe for the Contractor to continue work in the area.

F. Control and Disposal of Chemical and Sanitary Wastes:

Page 31: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-20

1. Trash shall be picked up and placed in containers that shall be emptied on a regular schedule. Handling and disposal shall be so conducted as to prevent contamination of the site and other areas, and shall not be disposed of in wetlands or burned on the right-of-way. On completion, the area shall be left clean and in natural condition.

2. Disposal of rubbish and debris shall be as follows: The Contractor shall transport

all waste, including excess excavated material, off the site and dispose of it in a manner that complies with the Federal, Commonwealth of Pennsylvania, and Local requirements. The Contractor shall secure a permit or license prior to transporting any material off the site. Waste materials shall not be burned on the site. The Contractor shall be responsible for the disposal of waste material to a pickup point or disposal area.

4. Chemical waste shall be stored in corrosion-resistant containers, removed from the

project site, and disposed of as necessary, as but not less frequently as monthly. Disposal of chemical waste shall be in accordance with standard established practices as approved by the Project Manager. Fueling and lubricating of equipment and motor vehicles on the site shall be conducted in a manner that affords the maximum protection against spills and evaporation. Lubricants to be discarded, including burned oil, shall be disposed of in accordance with approved procedures meeting Federal, Commonwealth of Pennsylvania, and Local regulations. For oil and hazardous material spills that may violate Federal, Commonwealth of Pennsylvania, or Local regulations, the Project Manager shall be notified immediately.

G. Dust Control:

1. Airborne dust shall be minimized at all times, including non-Working hours, weekends, and holidays. Soil at the site, station platforms, haul roads, and other areas disturbed by the Contractor's operations and materials stockpiled for the project shall be treated with dust suppressors or covered to control dust. Dry power brooming shall not be permitted. Vacuuming, wet mopping, wet sweeping, or wet power brooming shall be used instead. Air blowing shall be permitted only for cleaning off non-particle debris, such as that from reinforcing bars. Sandblasting shall not be permitted except as otherwise specified elsewhere. Only wet cutting of concrete block, concrete, and asphalt shall be permitted.

2. The Contractor shall comply with all applicable provisions of the National Emission

Standards (40 CFR 61).

3. The Contractor shall inspect all vehicles for dirt prior to their leaving the construction site. Dirt, soil, and rubble likely to be dislodged during transit shall be removed from the trucks and other vehicles prior to leaving the site.

4. The Contractor shall ensure that equipment transporting material to and from the site that

may become airborne is covered. 5. The Contractor shall not cause or permit fugitive particulate matter to be emitted into the

outdoor atmosphere from any source such that emissions are visible beyond the project

Page 32: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

REGULATORY REQUIREMENTS AND SAFETY 01060-21

property line. G. Noise Control:

1. The Contractor shall research and determine the applicable jurisdiction requirements for noise control in the project area. In the event a project site lies in two or more jurisdictional areas and the requirements conflict, the strictest will govern. City of Philadelphia Air Management regulations govern for any work within Philadelphia. In absence of specific jurisdictional instructions regarding noise control, OSHA 29 CFR §1910 will apply.

H. Asbestos and Lead Containing Materials

1. Prior to the commencement to work, Contractor shall coordinate performance of a survey of the project area for asbestos containing materials and lead-based paint by asbestos and lead inspectors/investigators properly licensed and certified to perform such work in Pennsylvania (and the City of Philadelphia where applicable). Contractor shall submit to the SEPTA Project Manager with a copy of the findings/report (see Section 2.03.C). Given the age of many SEPTA properties it is always possible to encounter suspicious material.

2. The Contractor shall comply with all applicable Federal, Commonwealth, and Local laws including but not limited to the City of Philadelphia Asbestos Control Regulations, 29 CFR 1926.1101, 40 CFR 763 Subpart E, 29 CFR 1910.120, 29 CFR 1910.134 and 29 CFR 1910.1200, 29 CFR 1926.62, 29 CFR 1910.1025, 40 CFR 745, 40 CFR 262.11 and 25 Pa Code 261.

3. All asbestos abatements shall be conducted by licensed abatement Workers and

Supervisors and air monitoring shall be conducted by third party licensed Building Inspector and/or Asbestos Project Inspector (depending on location as determined by System Safety) and the specification shall be written by a licensed Asbestos Project Designer.

4. All submittals including but not limited to notifications, work plans, and health and safety

plans shall be submitted to SEPTA for review prior to the commencement of work. Within thirty [30] days of completion of work, waste disposal records documenting disposal at a SEPTA-approved facility shall also be submitted to SEPTA (see Section 2.03.C).

5. All newly installed materials shall be asbestos and lead free.

END OF SECTION

Page 33: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

MAINTENANCE AND PROTECTION OF 01570-1 VEHICULAR AND PEDESTRIAN TRAFFIC

SECTION 01570

MAINTENANCE AND PROTECTION OF VEHICULAR AND PEDESTRIAN TRAFFIC PART 1 - GENERAL 1.1 DESCRIPTION

A. Full pedestrian access must be maintained in the project area at all times. If this is not possible through the established paths, then alternate routes must be created using appropriate barricades and signs. The alternate route must be conspicuous and easy to follow for pedestrian traffic, while being safely barricaded from the construction activities. Similarly, vehicular traffic must also have either free access in the vicinity of the work site. Access to local residences and business must be maintained.

B. The work specified in this Section consists of furnishing, installing, maintaining, and subsequently

removing signs cones, fences and barricades used for controlling, warning, guiding, and protecting vehicular and pedestrian traffic in the project area.

1.2 QUALITY ASSURANCE

A. Referenced Standards: 1. Commonwealth of Pennsylvania Department of Transportation Standard Specifications

Publication 408 PADOT. 2. Commonwealth of Pennsylvania Department of Transportation, Publication No. 203, Work

Zone Traffic Control. 3. Maintenance and Protection of Traffic Plan Submitted by SEPTA for each project.

B. Be alert for conditions which may call for closings of pathways or sidewalks not anticipated in the

specific site plans. Alert the Project Manager to these conditions at once.

C. Notices: 1. Notify Project Manager, in writing, not less than 5 work days before closing each street,

lane or sidewalk. 2. Notify PADOT when operating on state roads, and otherwise notify the municipality, in

writing, not less than 5 days before prohibiting stopping and parking of vehicles; submit copy of each notice to Project Manager.

1.3 JOB CONDITIONS

A. Maintain pedestrian access at all times for the duration of the Project.

B. To the greatest extent possible, the work is to be carried out with a minimum disruption to SEPTA’s operations. Should it be necessary, however, to stop SEPTA operations, notify the Project

Page 34: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

MAINTENANCE AND PROTECTION OF 01570-2 VEHICULAR AND PEDESTRIAN TRAFFIC

Manager first. Under no circumstances is the contractor to undertake a service interruption on his own.

1. Overhead wires, where applicable, will remain energized.

PART 2 - PRODUCTS 2.1 TEMPORARY TRAFFIC CONTROL DEVICES

A. Orange, plastic traffic cones.

B. Orange, plastic construction fence and fence posts.

C. Wooden horses with amber flashers mounted.

D. “Jersey Barriers”.

E. Fifty-five gallon drums, equipped with amber flasher lights.

F. Flagmen will be equipped with: 1. Flagman sign, 24 inches, octagonal, and attached to five-foot handle. One side of sign

shall be a stop sign, and other side shall be a slow sign. 2. Stop Sign: Have white reflectorized letters, not shorter than eight inches, spelling STOP

on a reflectorized, red, octagonal background. 3. Slow Sign: Have black letters, not shorter than eight inches, spelling “SLOW” on a

reflectorized, orange, diamond background. Area between diamond and edge of flagmen sign shall be black.

PART 3 - EXECUTION 3.1 TEMPORARY TRAFFIC CONTROL DEVICES

A. Post devices before diverting traffic, and where indicated on plans. Place drums as indicated. Operate warning lights between sunset and sunrise. Place barricades, cones, and similar protective devices if personnel and equipment will be working within five feet of edge of traffic lane which will be bearing traffic. Either repair or clean devices damaged, defaced, and otherwise rendered unfit or replace those devices with new devices within 24 hours after such damage, defacement or unfitness.

B. Remove traffic control devices as soon as construction activities have been completed.

3.2 FLAGMEN

A. Furnish flagmen, with signs as specified in Article 2.1 herein, where opposing vehicular traffic must be diverted onto single traffic lanes, where traffic must change lanes abruptly, where construction equipment either enters or crosses traffic lanes and sidewalks, where construction equipment may intermittently encroach on traffic lanes and unprotected sidewalks and crosswalks, where

Page 35: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

MAINTENANCE AND PROTECTION OF 01570-3 VEHICULAR AND PEDESTRIAN TRAFFIC

construction operations would affect public safety and convenience, and where traffic regulation is needed because of the rerouting of vehicles around the worksite.

3.3 CONTROLLING PEDESTRIAN FLOW ADJACENT TO WORKSITE

A. Ensure that construction operations will not impede pedestrian traffic to the extent that public safety will be threatened and passage of emergency vehicles will be restricted. Do not obstruct platforms or public ways, including sidewalks, and accesses to platforms and public and private properties. Do not reduce carrying capacity. Maintain pavement surfaces in a smooth plane where pedestrian traffic is routed. Restore obstructed public ways, including sidewalks, and accesses to public and private properties, to public and private uses when obstruction thereto is no longer necessary for execution of the Project.

B. Provide such precautions as required to prevent unauthorized pedestrian access to the work site.

These precautions may include but are not necessarily limited to, construction of fences and barricades and the use of flagging and security personnel.

3.4 VEHICULAR AND PEDESTRIAN ACCESS TO BUILDINGS

A. Pedestrian Access to buildings adjacent to worksite shall be unimpeded by construction operations to the extent that public safety will not be threatened and that public convenience will not be unduly impaired, in opinion of Project Manager.

3.5 TRAFFIC CONTROL DEVICES

A. Place devices along traveled ways where construction activities occur as indicated on TCP, maintain as required throughout construction period, modify as shown on updated plans, and remove as soon as construction activities have been completed.

B. Construction Signs:

1. Furnish and erect, move and remove, as required and as directed by the Project Manager, signs to adequately and safely inform and direct the motorist and to satisfy legal requirements.

2. All signs shall be kept clean, mounted at the required height on adequate supports and placed in proper position and alignment so as to give maximum visibility both night and day. All wood support and backs of plywood sign panels shall be painted with two coats of white paint. All signs and markers shall indicate actual existing conditions and shall be moved, removed, relocated or changed immediately as directed by the Project Manager.

3. All signs shall be mounted in accordance with the referenced codes. All signs shall be mounted at a height of at least five feet. Under special conditions, signs may be mounted at a greater height, as ordered by the Project Manager to fit the situation.

4. All signs shall be the property of the Contractor and shall be maintained in good condition for the duration of the contract and removed from the work site when the contract is accepted.

5. Place name of contractor someplace on the sign for purpose of owner identification only.

Page 36: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

MAINTENANCE AND PROTECTION OF 01570-4 VEHICULAR AND PEDESTRIAN TRAFFIC

END OF SECTION

Page 37: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

FINAL CLEANING 01710-1

SECTION 01700

CONTRACT CLOSEOUT PART 1 - GENERAL

1.01 DESCRIPTION

A. This Section specifies the requirements for closing out the Contract and supplements requirements specified in Paragraph XII of the Agreement.

B. Contract closeout is the term used to describe the collective Project requirements that are to be fulfilled near the end of the Contract term in preparation for final acceptance and occupancy of the Work by SEPTA, as well as final payment to the Contractor and the completion of the Contract.

C. If in the event that the Work of the Contract is completed in phases and/or portions of the Work is completed to the full satisfaction of SEPTA and SEPTA is to utilize that completed phase and/or portion, SEPTA shall issue a Certificate of Substantial Completion in accordance with 1.03 below.

1.02 RELATED DOCUMENTS

A. Section 01710: Final Cleaning

1.03 PREREQUISITES TO SUBSTANTIAL COMPLETION

A. General: The Contractor shall complete the following before requesting the Project Manager's inspection for certification of substantial completion for the Work of the Contract. The Contractor shall list known exceptions in the request.

1. What constitutes substantial completion will be determined by the Project Manager.

2. In the progress payment request that coincides with, or is the first request following the date substantial completion is claimed, activities should be either 100 percent complete for the portion of the Work claimed as "substantially complete," or provide a list incomplete items, the value of incomplete Work, and reasons for the Work being incomplete. Include supporting documentation for completion as indicated in the Contract Documents.

3. Submit written certification to the Project Manager that the project, or designated portion thereof, is substantially complete.

4. Provide written acknowledgment by the Warranty Holders that their products have been installed to their satisfaction and their full warranty shall be honored.

5. Submit the list of items to be completed or corrected and material delivery dates of major items, as applicable.

Page 38: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

FINAL CLEANING 01710-2

6. Advise SEPTA of pending insurance change-over requirements.

7. All contract record documents, maintenance manuals, warranties, and bonds shall be submitted as defined in the Agreement.

8. Obtain and submit releases enabling SEPTA full, unrestricted use of the Work and access to services and utilities. Where required, include occupancy permits, operating certificates and similar releases.

9. Deliver any access tools and material stock as required and further defined elsewhere n the specifications.

10. Change out locks, transmit keys and transfer security provisions if required by the Specifications.

11. Discontinue or change over and remove temporary facilities and services from the project site as directed by the Project Manager along with construction tools and facilities, mock-ups, and similar elements.

12. Touch up and otherwise repair and restore marred exposed finishes.

13. All maintenance instructions for the SEPTA's personnel shall be completed as defined elsewhere in the specifications.

B. Inspection Procedures: Upon receipt of the Contractor's request and submittal for inspection, the Project Manager will either proceed with inspection or advise the Contractor of unresolved prerequisites.

1. Following the initial inspection, the Project Manager or the Architect/Engineer will either prepare the Certificate of Substantial Completion or advise the Contractor of Work which must be performed before the certificate will be issued. The Project Manager will repeat the inspection when requested and when assured that the Work has been completed.

2. Results of the completed inspection will form the initial "punch list" for final acceptance.

3. The "punch list" shall include a reasonable time period to effectuate the work, which is mutually agreed upon by all parties.

1.03 PREREQUISITES TO FINAL ACCEPTANCE

A. General: The Contractor shall complete the following before requesting the Project Manager's final inspection for certification of final acceptance and final payment as required by the Agreement, specifically Agreement Paragraphs XII: F. and I. and VIII H. The Contractor shall list known exceptions, if any, in the request.

1. Submit the final payment request with final releases and supporting documentation not previously submitted and accepted. Include certificates of insurance for products and completed operations where required.

Page 39: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

FINAL CLEANING 01710-3

2. Submit an updated final statement to account for final additional changes to the Contract sum.

3. Submit a Certified copy of the Project Manager's final "punch list" which documents all work which has been completed.

4. Submit final meter readings for utilities, a measured record of stored fuel and similar data as of the date of Substantial Completion or as of the date SEPTA took possession of and responsibility for corresponding elements of the Work, if required.

5. Submit Consent of Surety. Affidavit of Payments of Debts and Claims, Affidavit of Release of Liens. General Release by Trade Contractor of Owner, Guarantee against Defects, any Warranties and Maintenance Bonds. Any special documentation such as a copy of Engineer or DER Permits or Certification of Occupancy.

6. Submit evidence of final, continuing insurance coverage, which complies with insurance requirements.

7. Submit any remaining record documents and drawings, maintenance manuals, final project photographs, damage or settlement survey, property survey, and similar final record information.

B. Reinspection Procedure: The Project Manager will re-inspect the Work upon receipt of the Contractor’s notice that the Work, including “punch list” items resulting from earlier inspections, has been completed except for those items whose completion has been delayed because of circumstances that are acceptable to the Project Manager.

1. Upon completion of reinspection, the Project Manager will either prepare a Certificate of Final Acceptance or will advise the Contractor of Work that is incomplete or of obligations that have not been fulfilled but which are required for final acceptance.

2. If necessary, the reinspection procedure will be repeated.

END OF SECTION

Page 40: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

FINAL CLEANING 01710-1

SECTION 01710

FINAL CLEANING PART 1 - GENERAL

1.01 DESCRIPTION

A. The section details work for preparing the site and/or facility for substantial completion.

B. The Contractor shall only be responsible for cleaning those portions of the work it has installed.

1.02 QUALITY ASSURANCE

A. In addition to the standards described in this Section the Contractor shall comply with pertinent requirements of governmental agencies having jurisdiction.

B. "Clean," for the purpose of the Article, and except as may be specifically provided otherwise, shall be interpreted as meaning the level of cleanliness generally provided by skilled cleaners using commercial quality building maintenance equipment and materials.

PART 2 - PRODUCTS

2.01 CLEANING MATERIAL AND EQUIPMENT

A. The Contractor shall provide required personnel, equipment, and materials needed to achieve the specified standard of cleanliness.

2.02 COMPATIBILITY

A. The Contractor shall use only the cleaning materials and equipment which are compatible with the surface being cleaned, as recommended by the manufacturer of the material and acceptable to SEPTA.

B. The Contractor shall replace surfaces damaged from improper use of material and/or cleaning methods.

PART 3 - EXECUTION

3.01 FINAL CLEANING

A. The Contractor shall, prior to turning over the substantially completed area to SEPTA maintenance, remove from the area all tools, surplus materials, equipment, scrap, debris, and waste. If any of the Contractor's work continues in the substantially completed area, the Contractor shall continue the cleaning specified in Section 01500. Schedule final

Page 41: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

FINAL CLEANING 01710-2

cleaning date as approved by SEPTA.

B. Site:

1. Unless otherwise specifically directed by SEPTA, the Contractor shall sweep grade areas within the contract limit and paved areas adjacent to the site.

2. The Contractor shall completely remove resultant debris.

3. The Contractor shall remove graffiti from all surfaces and restore surface to original condition.

C. Structures

1. The Contractor shall visually inspect all existing and finished surfaces and remove all traces of soil, waste materials, smudges, graffiti and other foreign matter.

2. The Contractor shall remove all traces of splashed materials from structure within contract limit and from adjacent surfaces.

3. If necessary to achieve a uniform degree of cleanliness, the Contractor shall wash the exterior of the structure with high pressure detergent.

4. In the event of stubborn stains not removable with detergent, the Contractor shall utilize light sandblasting or other cleaning methods at no additional cost to SEPTA.

5. The Contractor shall remove paint droppings, spots, stains and dirt from existing and finished surfaces.

6. The Contractor shall clean existing and new glass surfaces and frames inside and outside.

D. Finished Surface:

1. The Contractor shall remove all labels and tags, which are strictly used for the convenience of manufacturing, assembly, installation and identifications.

2. The Contractor shall clean glass and glazing to a polished condition. Remove substances, which are noticeable on surfaces. Replace any broken glass and damaged transparent materials.

3. The Contractor shall clean stainless steel surfaces (including screens) of all foreign material. Finish surfaces with application of buffed polish material as recommended by the manufacturer.

4. The Contractor shall clean existing and new tile surfaces including the grout joints to a dirt and graffiti free condition.

E. Equipment:

1. The Contractor shall wipe surfaces of all mechanical and electrical equipment

Page 42: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

FINAL CLEANING 01710-3

including system components to a dirt free condition. Touch up the surfaces to match with the overall finish of the equipment/system component.

2. Insure that the equipment and system components are properly identified as required by the Contract Documents.

END OF SECTION

Page 43: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SITE PREPARATION 02230-1

SECTION 02230

SITE PREPARATION PART 1 - GENERAL 1.1 DESCRIPTION

A. The work specified in this Section consists of cutting vegetation, grubbing stumps and roots; clearing refuse, foundations, signs, rubbish, trash, debris, dislodged materials, asphalt pavement, curbing, and cut vegetation, all within the limits of construction as part of this Contract. Haul from site all such matter and debris from the work of this Section.

RELATED WORK

A. Division 1 – General Requirements B. Section 02370 – Erosion and Sedimentation Control

PART 2 - PRODUCTS Not used. PART 3 - EXECUTION 3.1 GENERAL

A. Earthwork operations shall not be started in any area where clearing and grubbing is not complete except that clearing and grubbing of items embedded in the ground such as roots and stumps may be removed concurrent with excavation in accordance with Section 02300.

3.2 GRUBBING

A. Grub in a manner which will result in entire stumps being removed and in roots larger than three inches being removed from within one foot of the indicated subgrade.

3.3 CLEARING

A. Gather, load, and transport from the worksite, foundations, refuse, rubbish, trash, debris, cut vegetation, trimmed roots and tree branches, grubbed stumps and roots, felled trees, and dislodged material.

END OF SECTION

Page 44: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-1

SECTION 02300

EXCAVATION, BACKFILL, AND COMPACTION PART 1 GENERAL 1.01 SUMMARY

A. Section includes: Excavation for pavement; excavation, and placement of compacted fill and backfill for structures; and drainage; construction of embankments; subgrade and foundation preparation; and subsurface extraction of miscellaneous structures and facilities indicated to be removed.

B. Related Sections:

1. Section 02370 – Erosion and Sedimentation Control.

1.02 REFERENCES

A. American Society for Testing and Materials (ASTM):

B. Occupational Safety and Health Administration (OSHA).

C. Management of Clean Fill Policy (PADEP)

D. Management Program for Soils, Construction, and Demolition Debris Generated from SEPTA Property (SEPTA)

1.03 DEFINITIONS

A. Earthwork Terminology: Terms used in this Section and not defined herein shall be interpreted in accordance with the definitions given in ASTM D 653.

B. Approved Material: Material which meets specified requirements for use as embankment, fill, or

backfill.

C. Backfill: Soil or soil-rock material used to backfill excavations and to backfill excavated spaces around foundation walls, building walls, retaining walls, and abutments.

D. Borrow: Soil material used in embankment or other construction which is excavated from any

location other than required onsite excavations.

E. Embankment: Soil or soil-rock material placed to raise the subgrade or natural grade of the site for embankment construction.

F. Excavation is the removing of all materials encountered within the indicated or specified limits, regardless of the nature of the material encountered and the method by which removed, and further defined in Article 1.05 below.

Page 45: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-2

G. Excess Excavation: Material excavated beyond or below cross section shown, as well as unavoidable overbreakage in rock.

H. Imported Material: Soil or granular material which is hauled in from off-site areas.

I. Optimum Moisture Content: The water content at which a soil can be compacted to a maximum dry

unit weight by a given compactive effort.

J. Relative Compaction: The ratio, expressed as a percentage, of the in-place dry density of fill material as compacted in the field to the maximum dry density of the same material as determined by laboratory test ASTM D 1557, Method D.

K. Relative Density: Refer to ASTM D 4253 and ASTM D 4254.

L. Soil Classification: Soil classification is based on the Unified Soil Classification system given in

ASTM D 2487. Group symbols, when used, conform with the symbols of ASTM D 2487.

M. Subgrade: Subgrade is the lowest elevation of excavation and the highest elevation of embankment required to accommodate the indicated construction.

N. Unsuitable Material: Excavated material or material below the natural ground surface in

embankment areas or below subgrade elevation in excavated areas, which is unsuitable for its planned use as determined by the Engineer. Unsuitable material is further defined as material determined to be:

1. Of such unstable nature as to be incapable of being compacted to specified density using

ordinary methods at optimum moisture content; or 2. Too wet to be properly compacted and circumstances prevent suitable in-place drying prior

to incorporation into the work; or 3. Otherwise unsuitable for the planned use.

1.04 QUALITY ASSURANCE

A. Inspections and Tests: The Contractor shall provide quality control inspections and tests as specified under Article 3.15 to assure compliance with specified requirements.

B. Laboratory and Geotechnical Services: Engage the services of an approved independent soils

testing laboratory to perform the above-specified inspections and tests. Foundation and subgrade preparation and the placement and compaction of fills shall be performed under the surveillance of a (state) registered geotechnical engineer employed by the Contractor.

C. Tolerances:

1. Construct finished sub-grades to plus 0 or minus 1/2 inch of the elevations indicated. 2. Construct finished grade of slopes not steeper than 3:1 plus or minus 1/2 inch and on

slopes steeper than 3:1 plus or minus 2 inches. Do not encroach upon the trackway bed or roadbed.

Page 46: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-3

3. Maintain the moisture content of fill material as it is being placed within plus or minus two percent of the optimum moisture content of the material as determined by the laboratory tests herein specified.

D. Blasting: Not allowed in the performance of the earthwork.

1.05 CLASSIFICATION OF EARTHWORK

A. No consideration will be given to the nature of materials encountered in excavating operations. Therefore, as unclassified excavation no additional payment will be made for difficulties occurring in excavating and handling of materials.

B. Where the required quantity of backfill exceeds the quantity of suitable site material, provide

material at no increase to the Contract Price.

C. No right of property in materials is granted the contractor of excavated materials prior to backfilling.

This provision does not relieve the contractor of his responsibility to remove and dispose of surplus excavated material of excavated material not suitable for backfilling.

1.06 JOB CONDITIONS

A. Unfavorable Weather Conditions:

1. Excavating, filling, backfilling, and grading work shall not be performed during weather conditions which might damage or be detrimental to the condition of existing ground, in-progress work, or completed work. When the work is interrupted by rain, excavating, filling, backfilling, and grading work shall not resume until the site and soil condition (moisture content) are suitable for compaction.

2. Subgrade shall be free from mud, snow, ice, and deleterious material when work is resumed.

3. Soil material which is too wet for compaction shall be left to drain, to be aerated and dried by disking and harrowing or other approved method until the moisture content of the area is uniform and within the specified limits.

B. Erosion Prevention: Protect stockpiles, ditches, embankments, filled, backfilled, and graded areas

to prevent erosion until such time as permanent drainage and erosion control measures have been installed.

C. Barricade open excavations and post with warning lights those excavations occurring on property

adjacent to or within public access. Operate warning lights during hours from dusk to dawn each day and as otherwise required.

D. Do not allow proof-rolling equipment to enter area within seven feet of piers, abutments, and

retaining walls retaining more than ten feet if equipment's gross weight exceeds 35 tons. Do not operate vibratory compactor having a gross weight more than 5,000 pounds closer than five feet to face of retaining wall. Do not operate non-vibrating equipment having an axle load of 21,000 pounds or greater closer than three feet from back of retaining wall. Grade to essentially finish grade on both sides of wall before starting to proof-roll.

Page 47: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-4

E. Do not operate proof-rolling equipment having one axle loading of more than 21,000 pounds within

height-of-fill-being-retained of retaining walls retaining less than ten feet.

F. Before moving equipment, including proof-rolling equipment that exceeds 21,000 pounds for any axle, across underground duct banks having less than four feet of cover, place decking on the path of that equipment. Extend decking outward from each side of the duct bank for a distance equal to the depth of the bottom of the duct bank, but not further than four feet. Decking shall consist of a three inch thick timber platform or one inch thick steel plate. If duct bank is exposed, do not place decking directly on duct bank.

G. Use of Explosives: Is not permitted.

H. Toxic and Combustible Substances:

1. During excavation, provide equipment and carry out such tests as necessary to detect

presence of toxic and combustible substances. 2. If the presence of noxious or explosive gas is indicated, immediately discontinue

excavation operations and notify the Engineer. Do not resume work at this location until the necessary safety measures have been enforced and further tests indicate the absence of noxious and explosive gases.

3. Take action to safeguard persons and property in accordance with rules and regulations of jurisdictional agencies and utility owners.

4. Promptly notify utility owners when problems concerning their facilities become apparent. PART 2 PRODUCTS 2.01 FILL AND BACKFILL MATERIALS

A. General Requirements:

1. Fill, backfill, and embankment material: Inert, non-expansive soil, free from organic matter and other deleterious substances, and of such quality that it will compact thoroughly without the presence of voids when watered and rolled. Excavated on-site material will be considered suitable for fill, backfill, and embankment construction if it is free from organic matter and other deleterious substances and conforms to the requirements specified herein.

2. Excavated material which is suitable for fill, backfill, and embankment construction shall be conditioned for reuse and properly stockpiled for later filling and backfilling operations. Conditioning shall consist of spreading material in layers not to exceed 8 inches and raking free of debris and rubble. Rocks exceeding four inches in largest dimension and deleterious material shall be removed from the site and disposed of as specified herein under Disposal of Surplus Material.

3. Where conditions require the importing of fill or backfill material, the material shall be an inert, non-expansive soil or soil-rock material free of organic matter and meeting or exceeding the minimum requirements specified herein for the location.

4. Fill, backfill, and embankment material shall conform to the following minimum requirements, unless otherwise specified:

Page 48: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-5

a. Liquid Limit (ASTM D 4318): 40 maximum b. Plasticity Limit (ASTM D 4318): 15 maximum

B. Specific Requirements:

1. Common Fill: Well- to moderately well-graded soils consisting of sands, silts, and clays, with or without gravel, as excavated, screened, or blended, having the following physical properties and gradation:

a. Laboratory Dry Density: 95 pcf minimum b. Dry Change (ASTM D 427): 15 percent maximum c. Gradation (ASTM D 422):

Sieve Percent Passing

Opening By Weight

4 inch square 100

3 inch square 85 minimum

U.S. No. 200 50 maximum

2. Common Embankment: Common fill, with the following additional requirements:

a. Laboratory Dry Density: 100 pcf minimum. b. Material Retained on. c. U.S. No. 10 Sieve (ASTM D 422): 50 percent maximum. d. Material Passing U.S. No. 40 Sieve:

1) Liquid Limit (ASTM D 4318): 25 maximum. 2) Plasticity Index (ASTM D 4318): 6 maximum.

3. Select Fill: Well- to moderately well-graded soils consisting of sands, silts, and clays, with or without gravel, as excavated, screened, or blended, having the following physical properties and gradation:

a. Laboratory Dry Density: 100 pcf minimum. b. Dry Change (ASTM D 427): 10 percent maximum. c. Gradation (ASTM D 422):

Sieve Percent Passing

Opening By Weight

1 inch square 100

3/8 inch square 75 minimum

U.S. No. 4 20 minimum

U.S. No. 10 10 minimum

U.S. No. 200 45 maximum

d. Sand Equivalent: 15 minimum. 4. Structural Fill: Well- to moderately well-graded granular soils, as excavated, screened, or

blended, having the following mechanical properties and gradation: a. Laboratory Dry Density: 100 pcf minimum. b. Dry Change (ASTM D 427): 12 percent maximum.

Page 49: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-6

c. Material Retained on U.S. No. 40 Sieve (ASTM D 422): 50 percent maximum. d. Material Passing U.S. No. 40 Sieve:

1) Liquid Limit (ASTM D 4318): 25 maximum. 2) Plasticity Index (ASTM D 4318): 6 maximum.

e. Gradation (ASTM D 422):

f. Sand Equivalent: 15 minimum. 5. Structural Embankment: Structural fill, except 100 percent shall pass a four-inch square

sieve. 6. Rock Fill: Sound, dense rock and boulders to 24-inch maximum size, containing sufficient

gravels, sands, crushed or broken rock, and enough fine material to fill all interstices. Material passing U.S. No. 40 Sieve, liquid limit: 30 percent maximum.

7. Select Rock Fill: As specified for Rock Fill, except that the maximum size of rock fragments and boulders shall be such that the material can be readily placed in layers not over 8 inches thick.

2.02 MATERIALS FOR EARTHWORK

A. Fill and Backfill Materials: Where specific fill, backfill, and embankment materials are not indicated on Contract Drawings, conform to the following requirements:

1. Embankment: Structural Embankment. 2. Rock Fill: Fill or embankment may be Rock Fill at depths greater than 6 feet below finished

subgrade, and Select Rock Fill at depths from one to 6 feet below finished subgrade. 3. Subgrade and Foundation: Structural Fill for a depth of not less than 6 inches. 4. Backfill against Concrete Walls and Waterproofing: Select Fill. 5. Backfill for Wing-walls, Retaining Walls, and Abutments: Structural Fill. 6. Backfill for Abandoned Vaults (including airways, cross adits, and similar voids): Structural

Fill. 7. Backfill under Supporting Walls and Columns and Similar 8. Locations: Class 4000 concrete. 8. Backfill Where Not Otherwise Indicated: Common Fill

or Common Embankment.

2.03 SOURCE QUALITY CONTROL

A. Fill backfill, and embankment materials proposed to be used in the work shall be tested in the laboratory for compliance with specified requirements as follows:,

Sieve Percent Passing

Opening By Weight

2 inch square 100

1 inch square 75 minimum

3/8 inch square 30 minimum

U.S. No. 4 25 minimum

U.S. No. 10 15 minimum

U.S. No. 40 8 minimum

U.S. No. 200 15 maximum but not more than 75 percent

of the fraction passing No. 40 Sieve.

Page 50: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-7

1. Moisture-Density Relationship: ASTM D 1557, Method D. 2. Moisture Content: ASTM D 2216. 3. Relative Density: ASTM D 4253 and ASTM D 4254. 4. Liquid Limit: ASTM D 4318. 5. Plastic Limit and Plasticity Index: ASTM D 4318. 6. Dry Change (percent volumetric change): ASTM D 427. 7. Percentage of Wear: ASTM C 131 or ASTM C 535 as applicable. 8. Sieve Analysis: ASTM D 422, and ASTM C 136, as applicable. 9. Percent Passing No. 200 sieve: ASTM D 1140.

B. Where classification of soils is necessary to meet specified requirements, perform laboratory tests

in accordance with ASTM D 2487. 2.04 SOURCE OF MATERIALS

A. To the extent that it is available, obtain material from excavation operations. If sufficient suitable materials are not available to meet embankment, fill and backfill requirements, obtain material meeting specified requirements from outside sources at no additional cost to SEPTA.

1. Earth excavation may contain excess moisture in its natural state or may take on excess

moisture during handling and stockpiling. Manipulation to dry material to proper moisture content prior to compaction may be necessary. Earth excavation will not be considered as unacceptable backfill material by virtue of its moisture content only.

B. Use only material whose quality, source, and zone of placement in the fill have been approved.

C. If borrow areas are provided by SEPTA, dress and shape such areas to ensure positive drainage

when borrow operations are completed. PART 3 EXECUTION 3.01 STAKING AND GRADES

A. Layout the work, establish all necessary markers, benchmarks, grading stakes, and other stakes as required.

B. Perform surveys in accordance with the requirements of Section 01050. Surveys shall include:

1. Initial survey of original ground. 2. Final surveys when excavations, backfills, and embankments are completed.

3.02 EXISTING UTILITIES

A. Verify on site the location and depth (elevation) of all existing utilities and services before performing any excavation work. Perform excavation within 3 feet of a utility line by hand.

B. Remove abandoned sewers, piping, and other utilities encountered during excavation and plug the

ends.

Page 51: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-8

C. Report immediately to the Engineer any active utility lines encountered, which are not indicated in the Contract Documents, and notify utility owners involved. SEPTA, the Engineer and utility authorities shall be permitted free access to determine the measures deemed necessary to repair, relocate, or remove the utility.

3.03 EARTHWORK GENERAL REQUIREMENTS

A. Erosion Protection: Prevent erosion of the site at all times. Construct temporary berms and dikes and cut temporary swales to promote natural drainage of site.

B. Construction Traffic: Disperse travel paths of traffic and construction equipment over entire width of

compacted surfaces so as to aid in obtaining uniform compaction. Protect exposed soil layers with high moisture content from excessive wheel loads.

C. On-Site Excavation or Borrow Pits: Do not excavate or remove any material from the project site or

right-of-way which is not within the designated excavation, as indicated by the slope and grade lines.

D. Disposal of Excavated Material:

1. The contractor must properly dispose of any excavated material per PADEP Management of Fill Policy, SEPTA Soils Management Program, and Section 02400 – Soils Management.

2. During the bidding process the Contractor shall submit, for SEPTA’s review and approval, the anticipated name and location where the contractor plans to dispose of the excavated soil.

3. The Contractor will be responsible to properly transport and dispose of the excavated material in accordance with all Local, State, Federal laws and contract documents.

4. The contractor must submit copies of all manifests and/ or bills of laden to the project manager for SEPTA records.

E. Maintenance of Excavations, Slopes, and Embankments:

1. Excavate and remove material outside the limits of excavation which is unstable and

constitutes potential slides, and material which comes into excavations for any reason including from the driving of piles.

2. Maintain slopes and embankments until final completion and acceptance of the work. Promptly repair slides, slipouts, washouts, settlements, and subsidences which occur for any reason, and refinish the slope or embankment to the indicated lines and grades.

3.04 SUBSURFACE EXTRACTION

A. Remove subsurface facilities and obstructions to the extent indicated. B. When subsurface facilities are encountered during excavation which interferes with new

construction, and such facilities are not indicated, notify the Engineer promptly for corrective determination.

3.05 ROUGH GRADING AND FILLING

Page 52: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-9

A. Prior to commencement of structural earthwork, perform such soil and rock removal and filling as may be required to facilitate the progress of the work and bring all elevations to the rough grading lines indicated on Contract Drawings. Grading shall be by blading or as herein specified under Article 3.06.

B. Fill or backfill wells, test pits, or holes which will not be completely removed by excavation, with

Class 4000 concrete, crushed stone, or clean select fill, and compact as herein specified in layers not exceeding 6 inches after compaction.

C. Fill or backfill holes, swales, and low points which will not otherwise be removed in the course of

the work, to the indicated grades

3.06 DEWATER

A. Keep excavations free from water during the performance of the work. Provide and operate dewatering equipment of sufficient capacity for dewatering the excavations.

1. Provide for the disposal for the water removed from excavations in such manner as not to

cause injury to the public health, to public or private property, to the work of others, to the portion of the work completed or in progress, nor to cause an impediment to the use of streets, roads, and highways.

2. Control groundwater and surface water during construction in order to maintain soil stability.

3. Maintain the water table elevation sufficiently below the levels of excavation so that slops will remain stable and bottoms of excavations will not become loosened by flow of water.

4. If the foundations material looses its strength due to improper dewatering techniques, over-excavate the material and replace it with Structural Fill at no increase in Contract Price.

5. Dewatering efforts are to be maintained until excavations are closed or when determined by SEPTA or the Engineer as no longer necessary.

3.07 EXCAVATION

A. General Excavation Requirements:

1. Perform excavating as indicated and required for concrete footings, foundations, exterior paving, floor slabs, concrete walks, and for site levels and grading, and provide shoring, bracing, underpinning, cribbing, pumping, and planking as required.

2. The bottoms of excavations shall be level, firm, undisturbed earth, clean and free from loose material, debris, and foreign matter.

3. Excavate to the lines and grades indicated on the Contract Drawings. 4. Support and maintain excavations so that sides are stable and will not move. Excavations

may be maintained by sloping cut faces where space permits, or by providing structural support of earth walls.

5. Where the sides of excavations are sloped, angle of slopes shall be as approved by the Engineer but shall not be steeper than allowed by the Title 29 Code of Federal Regulations, Part 1926, Safety and Health Regulations for Construction (OSHA).

6. Maintain sides and slopes of excavations in safe condition until backfilling is completed.

Page 53: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-10

7. Where the Contractor elects to slope the sides of excavations, backfill of the over-excavated areas shall be made in the same manner specified for the adjacent excavated area. All additional backfill required shall be at no additional cost to SEPTA.

8. Limits of excavations shall allow for adequate working space for installing forms, wall waterproofing, and as required for safety of personnel. Cut excavations in solid rock accurately to the neat lines indicated on Contract Drawings, or to the width of the duct bank or concrete encasement.

9. Remove unstable bottom material. Remove large stones, debris, and incompressible soils from common excavation bottoms to a minimum depth of 12 inches. Where required to excavate to rock, it shall be understood to mean sound bedrock. Remove friable and unsound material.

10. Except as otherwise indicated, preserve the material below and beyond the lines of excavations. Where excavation is carried below the indicated grade, backfill to the indicated grade as herein specified.

11. Excavation and its restoration, for convenience of the Contractor, shall be at no additional expense to SEPTA.

12. Place excavated material at sufficient distance from edge of excavation so as not to cause cave-ins or bank slides, but in no case closer than 3 feet from the edge of excavations.

13. Unauthorized over excavations for footings and foundations shall be filled with approved materials to indicated elevations.

14. Condition excavated earth material which is suitable for fill, backfill, or embankment for re-use and properly stockpile for later filling and backfilling operations as herein specified. Test, screen, and mix as necessary to meet specified requirements.

15. Proceed with caution in areas of utility facilities; expose them by hand excavation or other methods acceptable to the facility owner.

16. If unsuitable materials are encountered at the required subgrades, the Engineer may authorize the removal of such unsuitable materials and replacement with suitable compacted fill or with concrete.

B. Rock Excavation:

1. Rock which cannot be broken up and removed by ripper equipment shall be excavated and removed by drilling.

2. If the depth of the cut is more than can be drilled from the top, an 18 inch offset will be allowed in the slope to begin succeeding drilling operations. The end result shall be a relatively smooth shear plane with localized irregularities which do not exceed 2 feet behind or 1 foot in front of the shear plane surface and which do not extend within the neat lines of the excavation.

3. Where footings or foundations are to be placed on rock which is not horizontal, key the center of the foundation approximately 12 inches in depth throughout an area approximately equal to the dimensions of the column or footing to be placed on the rock, or the entire width of the slab, at not more than 10-foot intervals. Remove loose fragments, and clean and fill all seams with lean concrete.

4. Material excavated beyond or below the indicated cross section shall be at the Contractor's expense. Fill overbreakage to required invert with Class 4000 concrete or crushed stone as approved, at no additional expense to SEPTA.

5. Leave the side slopes of rock cuts with reasonably uniform faces whether the excavation is carried beyond the specified side slopes or not. Conform sloped surfaces to the typical

Page 54: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-11

section indicated or to natural cleavage planes, where these are compatible with the typical section.

6. Solid rock boulders 24 inches in greatest dimension and boulders of lesser dimension, broken rock, and all stones occurring within the construction limits and not required for other construction, may be used for rock fill if suitable.

3.08 EMBANKMENT CONSTRUCTION

A. Place initial layer of embankment, fill, and backfill only on subgrade which has been inspected and accepted by the Engineer.

B. Construct embankments to lines, grades, and contours indicated, in layers as nearly uniform and

horizontal as is consistent with the indicated finished contour and profile. Maximum thickness of the layers shall conform to the following requirements:

1. Common Embankment and Structural Embankment: 8 inches before compaction and 6

inches after specified compaction. 2. Rock Fill: At more than 6 feet below the finished surface indicated on Contract Drawings,

limit thickness of rock layers to maximum diameter of rocks placed therein, but in no case more than 24 inches. At 6 feet or less below the finished surface, limit thickness of rock layers to 8 inches. C. Compact each layer to specified density for entire width of the fill or embankment. Achieve required compaction by rolling with compaction equipment suitable for type and condition of the particular material. Roll in a longitudinal direction parallel to longest dimension, starting at outer edges and progressing toward the center. Fill voids in rock fill with suitable embankment fill material.

C. Moisture-condition embankment fill material as required to achieve its compaction to the specified

density, within the tolerances specified herein. D. Do not compact material which contains excessive moisture. In such cases, scarify to the full depth

of the layer having excessive moisture content and dry by reworking, mixing with dry materials, or other approved methods.

E. Remove material which cannot be compacted to required density within specified tolerances, and

replace with suitable material at no additional expense to SEPTA.

F. Where pipes, culverts, or structures extend into embankments, construct embankment to at least 2 feet over and 10 feet on either side of the pipe, culvert, or structure location prior to excavation.

G. Do not commence final shaping until above specified requirements have been completed. Shape

entire surface and the slopes of cuts and embankments to true grade, alignment, and cross section indicated. Leave cut slopes in rock with uniform surface, and remove all loose overhanging rock. Open ditches, drains, and culverts resulting from construction operations to drain effectively.

H. Where utility facilities and structures are supported in place, use special equipment and techniques

as required to achieve specified compaction under and around them. I. When backfilling against structures, place material approximately simultaneously on both sides of

structures to equalize opposing horizontal pressures.

Page 55: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-12

1. Compact embankment, fill or backfill materials within five feet of retaining walls, abutments

or other structures using lightweight compactors. 2. Backfilling against new structures without approval is prohibited.

J. When backfilling on tops of structures, place material in six inch lifts over full area. K. Prior to placing embankment against slopes greater than one vertical to four horizontal cut benches

into existing slopes. Height of bench not to exceed two feet unless otherwise approved.

3.09 SUBGRADE PREPARATION

A. Perform all cutting, blading, and shaping as required to cut and shape the subgrade to the grades and elevations indicated.

B. Subgrade preparation includes fine grading, reworking as necessary, and preparation of cut, fill, or

embankment upon which structure and equipment foundations, pipe, subballast, subbase, base, and pavement will be placed.

C. Remove rigid pavements, slabs, and foundations which would be within five feet of finished grade

and subgrade. Rigid pavements and slabs which will be five feet and more below finished grade and subgrade may be left in-place only if broken into pieces not larger than three feet in greatest dimension.

D. Scarify and mix entire surface of subgrade to a depth of at least 6 inches. Moisture-condition

scarified subgrade to 3 percent above optimum moisture content. If subgrade stabilization material is required, incorporate it into subgrade at this time.

E. After the material has been thoroughly mixed and moisture conditioned, accurately construct and

fine grade the subgrade to indicated line, grade, and contour with high and low spots eliminated. Compact for full width to the specified density. Remove soft spots developed during working, fill with approved material, and re-compact.

F. Where feasible, use pneumatic-tired roller for compaction, suitable to produce the specified

density. Where compaction by roller is not feasible, use mechanical tampers or vibratory compactors.

G. Finish subgrade to straightedge or template within specified tolerances with the finished surface

bladed to a uniform, dense, smooth texture. 3.10 FOUNDATION PREPARATION

A. Complete construction of the excavation support and dewatering systems prior to placement of

structure and equipment foundations. B. Avoid disturbing bottom of excavation. If bottom is disturbed, restore and stabilize the bearing

foundation at no additional expense to SEPTA.

Page 56: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-13

C. If material at bottom of the excavation is rock, remove loose material and roughly level the bearing foundation to indicated elevation. If the bottom contains occasional rock outcroppings or rock in only a portion of the area, remove such rock to a depth of 6 inches below indicated subgrade and backfill with approved material.

3.11 SUBGRADE FILLING/RAISING GRADE

A. Construct compacted fill for raising of subgrade to indicated elevation by approved and accepted

methods. Spread fill material in uniform lifts not exceeding 8 inches in uncompacted thickness. Fill material which does not contain sufficient moisture to compact properly shall be sprinkled with water; if it contains excess moisture it shall be aerated or permitted to dry to the proper water content. Fill material and water shall then be thoroughly mixed before being compacted. Compact each layer of spread fill material to the specified density.

B. Control of fill shall consist of field inspection and testing to determine that each layer has been

compacted to the required density and to ensure that optimum moisture is being obtained. Any layer or portion of a layer that does not attain the compaction required shall be scarified and recompacted until the required compaction is obtained.

C. Perform spreading and compacting as required to produce the required density and a uniform

surface smooth and true to grade. 3.12 COMPACTION

A. Compaction Density: Compact each layer of embankment, fill, and backfill material to not less

than the indicated or specified compaction. Required compactions are defined as Class I or Class II, as follows:

1. Class I Compaction: 95 percent relative compaction as determined by ASTM D 698,

Method D, if the material is cohesive; or 70 percent relative density as determined by ASTM D 4253, Dry Method, and ASTM D 4254, Method A, if the material is granular.

2. Class II Compaction: 100 percent relative compaction as determined by ASTM D 698, Method D, if the material is cohesive; or 75 percent relative density as determined by ASTM D 4253, Dry Method, and ASTM D 4254, Method A, if the material is granular.

B. Required Compactions:

1. Embankment or fill where the surface will be subgrade or bearing foundation: Class II for

full depth. 2. Backfill around Structures: Class I under top 12 inches; Class II for top 12 inches. 3. Cut and Cover Backfill: Class I to 36 inches above structure or utility; Class II for balance. 4. Original Ground or Cut Subgrade: Except as specified in Articles 3.09 and 3.10 where

original ground or cut subgrade, or fill less than 1 foot thick, will be subgrade or bearing foundation, scarify the surfaces and provide Class II compaction for at least 12 inches in depth. Include the following additional requirements:

a. Provide Class II compaction for original ground within 3-1/2 feet of top of rail profile and 2-1/2 feet of finished pavement grade, for full width of trackway and pavement plus three feet on each side thereof.

Page 57: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-14

b. Provide Class II compaction for top 6 inches of undisturbed original ground upon which embankments are to be constructed.

3.13 BACKFILLING

A. Backfilling is required around all substructures. Fill all abandoned vaults, shafts, airways, holes,

pits, and other voids. B. Place backfill in layers not to exceed 8 inches of loose material, and compact each layer to

specified density before the next layer is placed. C. Place backfill material in such manner that unbalanced horizontal loads will not be applied to a

newly-placed structure or portion of structure, utilities, or pipelines. Do not backfill around portions of structures requiring backfill on only one side or on less than all sides, until the concrete has reached the specified strength to withstand the earth pressures.

D. When placing material for backfill around waterproofed structures, protect such structures and the

waterproofing thereof with a shield when necessary to prevent displacement or injury by stones or other hard substances in the backfill.

E. Do not backfill on or against structural concrete until the specified 28-day concrete strength has

been attained. F. Do not use compaction equipment and methods that produce excessive horizontal or vertical

earth pressures. 3.14 FINISH GRADING

A. Finish grade all areas to elevations and grades indicated. In areas to receive topsoil and landscape planting, finish grading shall be performed to a uniform 6 inches below the grades and elevations indicated.

B. Place and spread stockpiled topsoil to a uniform thickness of 4 to 5 inches (approximately) in

areas to receive topsoil and landscape planting. Place and spread to a uniform thickness approximately 1 to 2 inches below finish grades indicated.

3.15 FIELD QUALITY CONTROL

A. Inspections and Tests by the Contractor:

1. Density Tests: Compacted fill, backfill, and embankment shall be tested to verify

compliance with specified requirements in accordance with ASTM D 2922. Minimum frequency of tests shall conform to the following requirements:

a. Expansive Horizontal Areas: One test per 100 cubic yards, or fraction thereof, of fill or backfill placed.

b. Confined Areas, Trenches, and Embankments: One test per lift of fill, backfill, or embankment placed.

Page 58: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION 02300-15

2. Tests for compaction shall be made in accordance with test procedures outlined in ASTM D 698, Method D, as applicable. Field testing of soils or compacted fill in place shall be performed in accordance with applicable requirements of ASTM D 2922.

3. Moisture Content Tests: Compacted fill, backfill, and embankment shall be tested to verify compliance with specified requirements in accordance with ASTM D 3017. Minimum frequency of tests shall be as specified above for density tests.

B. Inspections by the Engineer:

1. Site preparation, cutting and shaping, excavating, filling, backfilling, and embankment

construction shall be carried out under the inspection of the Engineer, who will have the Contractor perform appropriate field and laboratory tests, as necessary, to evaluate the suitability of fill and backfill material, the proper moisture content for compaction, and the degree of compaction achieved. Fill or backfill that does not meet the specified requirements shall be removed or recompacted until the requirements are satisfied.

2. Cutting and shaping, excavating, conditioning, filling, backfilling, and compacting procedures require approval of the Engineer as they are successively performed. Work found to be unsatisfactory or work disturbed by subsequent operations before approval is granted shall be corrected in an approved manner as directed by the Engineer.

END OF SECTION

Page 59: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES 02322-1

SECTION 02322

EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes: Excavating, placing bedding, backfilling, and compacting trenches for pipelines and utility structures specified or indicated on Drawings.

B. Related Sections:

1. Section 02300: Excavation, Backfill, and Compaction. 2. Section 02370: Erosion and Sediment Control. 3. Section 02605: Utility Structures. 4. Section 03300: Cast-In-Place Concrete.

1.02 REFERENCES

A. American Society for Testing and Materials (ASTM):

B. Commonwealth of Pennsylvania Department of Transportation (PENNDOT), Specifications Publication 408, as supplemented.

1. PENNDOT Section 703.1, Fine Aggregate 2. PENNDOT Section 703.2, Coarse Aggregates. 3. PENNDOT Section 703.3, Select Granular Material (2RC).

C. Management of Clean Fill Policy (PADEP)

D. Management Program for Soils, Construction, and Demolition Debris Generated from SEPTA

Property (SEPTA) 1.03 DEFINITIONS

A. Earth Excavation: Removal down to subgrade elevation of clay, silt, loam, sand, gravel, slate, hard pan, pavements, soft sandstone, loose stone in masses, and boulders measuring less than 1/2 cubic yard.

1. Earth Excavation is Unclassified.

B. Rock Excavation: Removal down to subgrade elevation of large rock and boulders measuring more than 1/2 cubic yard or drilling and wedging in opinion of Engineer.

1. Rock excavation is unclassified.

Page 60: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES 02322-2

C. Unclassified Excavation: Material removal of any kind in excavation, including Rock Excavation and Unsuitable Material.

D. Subgrade: Trench bottom prepared as specified to receive Bedding, Concrete Cradle or Concrete Encasement, or excavation bottom prepared to receive pipeline structures.

1.04 QUALITY ASSURANCE

A. Quality Control:

1. Laboratory Tests: Aggregate materials under Part 2 - Products require advance examination or testing according to methods referenced, or as required by Engineer.

a. Arrange for testing laboratory to furnish Engineer test result reports in triplicate.

Test reports are considered sufficient evidence of acceptance or rejection of materials represented.

b. Conduct aggregate quality tests in accordance with requirements of appropriate Referenced Standard.

c. Engineer reserves right to accept aggregate materials based on certification from supplier that aggregate originates from a source approved by PENNDOT and that aggregate complies with specified PENNDOT requirements.

1.05 PROJECT CONDITIONS AND EXECUTION

A. General Requirements: Excavate and backfill trenches necessary for completing work of this Contract. Excavate and backfill trenches by machinery or by hand; The Engineer is empowered, if necessary in his opinion, to direct that hand excavation and backfilling be employed. Excavate whatever substances encountered, to grades and depths indicated on Drawings, as specified, or as directed by Engineer. Remove and waste excavated material not required for backfill.

B. Environmental Requirements:

1. Do not perform trenching, backfilling, or compacting when weather conditions or condition

of materials will prevent satisfactory work, in opinion of Engineer. 2. Do not use frozen materials as backfill or wet materials containing moisture in excess of

quantity necessary for satisfactory compaction. 3. Prior to use, moisten dry backfill material not having sufficient moisture to obtain

satisfactory placement or compaction. 4. Plan work to provide adequate protection during storms with provisions available

constantly for preventing flood damage. Protect installed piping and other work against damage from uplift due to high ground water levels.

5. Accommodation of Drainage: Keep gutters, sewers, drains, and ditches open constantly for surface drainage. No damming, ponding, water in gutters, or other waterways permitted, except where stream crossings are necessary and then only to extent Engineer considers necessary. Do not direct water flows across or over pavements except through approved pipes or properly constructed troughs.

Page 61: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES 02322-3

6. When required, provide pipes or troughs of sizes and lengths required at no expense to SEPTA. Perform grading in vicinity of trenches so that ground surface is properly pitched to prevent water running into trenches.

7. Pumping: Keep excavations free from water during performance of work at no expense to SEPTA. Build dams and other devices necessary for this purpose, and provide and operate pumps of sufficient capacity for dewatering excavations. Provide for disposal of water removed from excavations in a manner not to cause injury to public health, public or private property, work of others, portions of work completed or in progress, or produce an impediment to street, road and highway usage.

8. When necessary to haul soft or wet soil material over roadways, use suitably tight vehicles to prevent spillage. Clear away spillage of materials on roadways caused by hauling.

9. Provide effective dust control by sprinkling water, use of calcium chloride or other method approved by Engineer. Employ dust control when, where and in a manner required by Engineer.

C. Explosives and Blasting: Not permitted in performance of trenching work.

D. Hydraulic hoe-ram equipment may be used with written approval of SEPTA. Hoe-ram use may be

limited as to time of day and size of unit. E. Responsibility for Condition of Excavation: Assume responsibility for condition and results of

excavation. Remove slides and caveins at whatever time and under whatever circumstance they occur.

F. Protection: Assume risks attending presence or proximity of overhead or underground public utility

and private lines, pipes, conduits and support work, existing structures and property of whatever nature. Assume responsibility for damages and expenses for direct or indirect injury to structures or to person or property by reason of them or by reason of injury to them; whether structures are or are not shown on Drawings, by work of this Contract.

1. Outside Project Limits: Take necessary precautions to protect trees, shrubs, lawns and

other landscaping from damage. Restitution work for damages rests solely with Contractor and at no expense to SEPTA.

2. Pipe Supports: Adequately support underground pipes or conduits exposed as a result of excavations. Provide adequate support along entire exposed length by timber or planking. Install supports in a manner that backfilling may be performed without dislodging pipes or conduits. Place and carefully compact Coarse aggregate around supports, and leave supports in place as a guard against breakage due to backfill settlement. No additional payment will be made for support material left in place or for labor of installing and maintaining supports.

G. Structure Supports: Where trenching past buildings or structures that by their construction or

position might exert detrimental pressure upon trench, right is reserved by Engineer to require that buildings or structures, be underpinned or supported and protected, or special sheeting be driven, or that short lengths of trench be opened at one time.

H. Removal of Obstructions:

Page 62: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES 02322-4

1. Remove, realign, or change direction of above or below ground utilities and appurtenant

supports, if required in opinion of Engineer. Perform as extra work unless performed by owner of obstruction without cost to Contractor. However, uncover and sustain obstruction at no additional cost prior to final disposition of obstruction. No claims for damage or extra compensation due to presence of obstructions or delay in removal or rearrangement of obstructions will be made. Additional precautions concerning obstructions as follows:

a. Do not interfere with persons, firms, corporations, or utilities employing protective measures, removing, changing, or replacing their property or structures, but allow taking measures necessary or advisable under circumstances, without relieving responsibilities of Contract.

b. Without extra compensation, break through and reconstruct if necessary, invert or arch of sewers, culverts or conduits encountered if structure is in a position, in judgment of Engineer, as not to require its removal, realignment or complete reconstruction.

I. Advance Trenching: Where existing utilities or other suspected underground obstructions are within

close proximity of proposed pipelines, uncover and verify exact location of obstructions far enough in advance of pipe laying to allow changes in pipe alignment or grade required to bypass obstructions and to avoid removing sections of pipe already installed. If sections of installed pipe require removal and reinstallation as a result of not verifying utilities or other underground obstructions far enough in advance, remove and reinstall pipe at no additional cost.

J. Excavated Materials: No right of property in materials is granted for excavated materials prior to

backfilling. This provision does not relieve responsibility to remove and dispose of excavated materials. Obtain written consent and any necessary permits and approvals before disposing of excavated materials at an off-site location.

K. Borrow Excavation: Where required quantity of backfill exceeds quantity of suitable material

excavated within limits of Project site, obtain sufficient material to complete backfill at no additional cost to SEPTA. If borrow excavation is needed, notify Engineer sufficiently in advance of borrow excavation requirements to permit Engineer to verify need for borrow excavation and to view proposed borrow pit and determine suitability of material to be provided. Borrow excavation from outside sources is subject to approval of Engineer. Obtain written consent and any necessary permits and approvals before use of borrow excavation from outside sources.

L. Change of Trench Location or Depth:

1. Should Engineer require a change in location of a trench from that indicated on Drawings

due to presence of an obstruction, or from other cause, and change in location is made before excavation is begun, no extra compensation or claim for damages will be granted.

2. If a change in trench location made at requirement of 3. Engineer involves abandonment of excavation already made, abandoned excavation,

together with necessary refill is classed as unclassified excavation and backfill as applicable, in case full width of trench has not been abandoned.

4. If a change in trench location made at requirement of Engineer involves abandonment of excavation already made, abandoned excavation, together with necessary refill is classed

Page 63: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES 02322-5

as earth or rock excavation and backfill as applicable, in case full width of trench has not been abandoned.

5. If a changed location of a trench is authorized by Engineer upon Contractor's request, Contractor is not entitled to extra compensation or to a claim for damage. If change of trench location involves abandonment of excavation already made, abandoned excavation and refill is at Contractor's expense.

M. Classification of Excavated Materials: No consideration is given to nature of materials encountered

in trenching operations. Therefore, no additional payment will be made for difficulties encountered in handling, disposal, or replacement of materials removed.

N. Bedding: Excavate trench and construct bedding as shown on the Construction Detail Drawings.

1. Excavate the trench to at least six inches below the required bottom of pipe. Excavate

further if necessary, in the opinion of the engineer, to reach suitable material for support of the utility.

2. Place AASHTO #8 bedding material, compacting in 4” layers to cover the bottom one-quarter of the pipe. Hand shape a cradle conforming to the bottom of the pipe.

3. Fill the spaces beside and over the pipe to a depth of 12” above the top of pipe. Where the pipe is rigid, tamp this material in layers 4” thick. Where the pipe is corrugated metal or plastic storm sewer pipe, avoid tamping directly over the pipe. See the Construction Detail Drawings.

O. Backfill: Install backfill on top of the completed bedding as shown on the Construction Details and

as follows: 1. In areas under lawn or otherwise not paved nor exposed to vehicular traffic, fill the trench

to one foot below finished grade with suitable backfill obtained from site excavation or imported. Backfill must be compacted in layers not to exceed 6”.

2. Complete filling the trench to finish grade with topsoil. 3. In vehicular areas, fill the trench above bedding with AASHTO #57 Coarse Aggregate,

compacted in 6” layers, to subgrade elevation. PART 2 PRODUCTS 2.01 MATERIAL

A. General: Reuse only materials free of topsoil, plant life, lumber, metal, refuse, coal waste, slag, and cinders. Remove all other material from the site.

B. Approved Backfill: On-site excavated soil or soil-rock mixed materials free of rocks or similar hard

objects larger than six inches in any dimension. Rocks or similar hard objects may not represent more than 20 percent of backfill by volume.

C. Select Backfill: On site excavated material free of rocks or similar hard objects larger than one inch

in any dimension.

Page 64: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES 02322-6

D. Aggregate Backfill: AASHTO No. 57 Stone. E. Pipe Bedding: AASHTO No. 8 Stone F. Concrete Cradle and Encasement: Per requirements of Cast-In-Place Concrete - Section 03300

and of Class B: 3000 psi. G. Underground Warning Tapes: Printed polyethylene metallic detection tape, six inches minimum

width, color coded, one inch minimum lettering, printed with name of utility buried below, and suitable for installation in all soil types.

1. Provide detection tape for the following pipe lines and utilities as installed or encountered:

a. Sanitary Sewers – Green b. Storm Sewers – Green c. Sewage Force Main – Green d. Water Line- Blue e. Gas Line – Yellow tape plus a tracer wire where indicated by the Utility. f. Electric – Red g. Telephone – Orange h. CATV Conduit – Orange i. Petroleum Line - Yellow

H. Flowable Backfill:

1. Cement: Type I or II conforming to PENNDOT Section 701. 2. Fine Aggregate: Type A, B, or C conforming to PENNDOT Section 703.1, except having a

maximum loss of 20 percent in the Soundness Test. 3. Coarse Aggregate: Type C or better, AASHTO No. 10, conforming to PENNDOT Section

703.2. 4. Water: Conforming to PENNDOT Section 720.1. 5. Admixtures: Conforming to PENNDOT Section 711.3. Can be used when specifically

approved. 6. Mix Design (Per Cubic Yard):

a. Provide design mix in accordance with PENNDOT 704.1 (c). 7. Density (PTM No. 613): 125 pcf minimum. 8. Compressive Strength (PTM No. 604):

a. 3 days: 500 minimum. b. 28 days: 900.

END OF SECTION

Page 65: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION SUPPORT SYSTEMS 02360-1

SECTION 02360

EXCAVATION SUPPORT SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION

A. The work specified in this Section consists of designing, furnishing, installing, and removing temporary supports for excavations; all to the extent that construction will cause neither harm to personnel nor damage to existing structures and utilities; and as required by OSHA or applicable codes, rules, or regulations.

1.02 QUALITY ASSURANCE

A. The Contractor shall have either in his employ or on a consulting basis a civil engineer who is registered as a Professional Engineer in the Commonwealth of Pennsylvania, and who is qualified to determine extent of work necessary to satisfy requirements of this Section.

B. Provide for the protection of the public, employees and property, in accordance with applicable

requirements of Part 1926, Subpart P, "Excavation, Trenching and Shoring", CONSTRUCTION SAFETY AND HEALTH REGULATIONS (OSHA), which, by reference, is made a part of this specification, including sections relative to protection of the public; shoring and bracing; trenches and excavating equipment.

C. Design Criteria:

1. Design component members of system to support earth pressures, unrelieved hydrostatic

pressures, utility loads, existing structures, stored material, and moving of stationary vehicles and equipment.

2. Design support system in a manner permitting safe and expeditious construction of permanent structures, minimizing movement or settlement of the ground and preventing damage to adjacent buildings, structures and utility facilities.

3. For support systems in which struts are installed between opposite sides of the excavation, design and construct support of both sides to obtain comparable rigidity.

4. Choose location of soldier piles to allow for expected deviations from true line during driving procedure without encroaching on future permanent structures.

D. Working drawings and design calculations shall be stamped and under-signed by either a civil or

structural engineer registered as a Professional Engineer in the Commonwealth of Pennsylvania.

E. The use of pre-engineered trench support systems is acceptable. 1.03 JOB CONDITIONS

Page 66: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION SUPPORT SYSTEMS 02360-2

A. The Contractor shall be solely responsible for properly and adequately protecting the excavation from caving or slipping and shall not impose any liability on the Authority related to injury to persons or property with respect to such duties. Nor shall any delay howsoever caused resulting in keeping the excavation open for a longer period of time relieve the Contractor of such obligation or entitle him to any claims for extra compensation.

B. Protect trench excavations deeper than five feet with tight sheeting from the top at the original

ground line to below the trench bottom.

C. Review and acceptance of working drawings and designs required for excavation supports shall not impose liability on the Authority.

D. Monitor performance of components of support system, both vertical and horizontal movements, at

regular intervals not to exceed 3 days. PART 2 - PRODUCTS 2.01 MATERIALS

A. Timber Lagging: Structural grade, minimum allowable flexural stress of 1,100 psi.

B. Structural Steel: ASTM A36.

C. Wood Sheeting: Sound, with no strength-impairing defects.

D. Cast-in-Place Concrete: 3500 psi conforming to PennDOT Class AA.

E. Other Materials: Those best suited for use intended and indicated on accepted working drawings. PART 3 - EXECUTION 3.01 SHEETING, SHORING AND PILING

A. Install soldier piles by driving, preboring or other pre-excavation methods. Prebore piles that are within 10 feet of underground lines. Drive soldier pile only in those areas where shown or approved. Install piles vertical within tolerance of one foot per each 100 feet for full depth of each pile.

B. Where piles are installed by preboring or other pre-excavation methods, take appropriate

measures to stabilize excavation to preclude loss of ground.

C. Provide prebored holes for soldier piles adequate to accommodate pile section shown on approved working drawings. Extend hole to necessary depth below top of subgrade.

D. Carry bottom of support system to depth below main excavation, adequate to prevent lateral

movement. In areas where additional excavation is required below main excavation subgrade, make provisions to prevent movement of main excavation supports.

Page 67: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION SUPPORT SYSTEMS 02360-3

E. Multiple-layered Horizontal Bracing:

1. At locations where top of weathered bedrock is above the subgrade of main excavation,

install soldier piles so that tips are at least two feet below top of subgrade. 2. At locations where top of weathered bedrock is five feet or more below subgrade of main

excavation, install soldier pile so that lower tip is at least five feet below bottom of excavation.

3. If weathered bedrock is encountered at elevation between subgrade elevation and five feet below subgrade, install soldier piles so that lower tip is five feet below subgrade or two feet into rock, whichever is higher.

F. After seating soldier piles in pre-excavated holes, encase piles with 3,500 psi concrete up to lowest

point of excavation.

G. Use timber lagging secured in place for sheeting of excavations.

H. Follow excavation closely with placement of lagging. Do not allow maximum height of unlagged face of excavation to exceed five feet in rock or predominantly clayey soils and three feet in sandy soils.

I. Do not permit height of unlagged face to exceed 15 inches if water flows from face of excavation or

if soil in face moves toward excavation area.

J. If unstable material is encountered during excavation, take suitable measures to contain it in place and prevent ground displacement which may cause damage.

K. Maintain sufficient quantity of material on hand for shoring, bracing and other operations for

protection of work and for use in case of accident or emergency. 3.02 PRIMARY SUPPORT

A. Use wales, struts and tieback anchors as necessary to provide primary support of excavation faces retained by soldier piles.

B. Provide struts with intermediate bracing as needed to enable them to carry maximum design load

without distortion or buckling.

C. Provide diagonal bracing as needed to maintain stability of system.

D. Include web stiffeners, plates or angles as needed to prevent rotation, crippling or buckling of connections and points of bearing between structural steel members.

E. Install and maintain primary support members in tight contact with each other and with surface

being supported.

F. Design primary support members to support maximum loads occurring during excavation.

Page 68: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION SUPPORT SYSTEMS 02360-4

3.03 SUPPORT SYSTEM WITH TIEBACKS

A. Install tieback system in accordance with approved working drawings.

B. Stress tiebacks to proof loads equal to 140 percent of maximum design load and maintain proof load for 30 minutes prior to reducing to design load. Reject tiebacks which lose more than five percent of proof load during 30-minutes period.

C. Apply proof loads in increments of five tons at one minute intervals and provide means to measure

load application within accuracy of plus or minus five percent.

D. After reducing tieback load to design load, encase anchors in grout maintaining design load until anchors are fixed in place.

E. In transfer of loads from jacks to support system, use fixation method which will limit load loss to no

more than five percent of design load.

F. Provide and maintain convenient access and appropriate means to accomplish these observations. G. Preliminary and Creep Tests on Tiebacks:

1. Reapply proof loads equal to 140 percent of design load at each level of support in

excavation on first installation on each side of excavation at horizontal intervals not exceeding 500 feet and wherever there is significant difference in soil in which tiebacks are installed.

2. As specified for proof loading, apply proof loads in increments of five tons at one minute intervals. Provide means of measuring load applications with an accuracy of plus or minus five percent of design load. Maintain proof load for 24 hours prior to reducing it to design load.

3. Make records of axial movement with incremental applications of load as well as amount and time of load fall-off with no pumping of jack or axial movement during 24-hour period that proof load on tieback is maintained. If during 24-hour period axial deformation of tieback system exceeds 0.02 inch or decrease in jack pressure without pumping is more than five percent after correcting for temperature changes during the test period, redesign tieback system to satisfy requirements.

H. Vertical Support System with Tiebacks:

1. Install piles or other vertical support system members incorporated in a system utilizing

tiebacks so that they are capable of resisting vertical components of tieback loads without significant settlement during excavation and construction.

2. Install vertical support members so that settlements will not be caused by construction. In general, install members to be end-bearing in stratum below maximum depth of excavation and capable of carrying total vertical loads without assistance of skin friction at depth of excavation.

Page 69: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EXCAVATION SUPPORT SYSTEMS 02360-5

3.04 LAGGING

A. Unless otherwise shown or specified, provide timber lagging of three inches minimum thickness where it spans soldier piles placed at distances five to seven feet on centers and for excavation depths up to 25 feet. Increase minimum lagging thickness to four inches for excavation blow 25 feet in depth.

B. Install lagging members in a manner which will prevent loss of soil. Wedge lagging members

against either undisturbed earth or compacted fill. 3.05 TRENCH EXCAVATION

A. Perform sheeting, shoring and bracing for trench excavation for utility facilities and other purposes in accordance with specified safety requirements.

3.06 FIELD QUALITY CONTROL

A. Tests: 1. Where system of tiebacks is proposed in conjunction with or in lieu of struts, bracing and

shores, undertake approved number of on-site tests to demonstrate adequacy of tiebacks for typical subsurface conditions.

2. Conduct tests and obtain approval prior to use of tieback system for excavation support.

B. Remove components of support system which inadvertently penetrate or encroach on permanent structure without endangering stability of support.

3.07 REMOVAL OF SUPPORTING SYSTEM

A. Remove sheeting, bracing and shores as trenches and other excavations are being backfilled, except where and to such an extent as the Project Manager shall require, in writing, that the same be left in place or where he shall permit the Contractor to leave the same in place at the Contractor's request and cost.

B. Cut off sheeting left in place whenever and at such points as the Project Manager shall require and

remove from the site the portion cut off. No additional compensation will be allowed for such cutting, removal and disposal.

C. When removing support of excavation system, wholly or in part, do not disturb or damage adjacent

buildings, structures, construction or utility facilities. Fill voids immediately with lean concrete or with approved backfill compacted to density specified in Section 02300.

END OF SECTION

Page 70: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EROSION AND SEDIMENTATION CONTROL 02370-1

SECTION 02370

EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.01 SUMMARY

A. Section Includes: Provision for soil erosion and sedimentation control work.

B. Related Sections:

1. Section 02300 – Excavation, Backfill, and Compaction. 2. Section 02322 – Excavation, Backfill, and Compaction for Utilities.

1.02 REFERENCES

A. American Society for Testing and Materials (ASTM): B. Commonwealth of Pennsylvania Department of Transportation (PENNDOT) Specifications,

Publication 408.

1. PENNDOT Section 703, Aggregates. 2. PENNDOT Section 735, Geotextiles. 3. PENNDOT Section 805, Mulching. 4. PENNDOT Section 806, Water Course and Slope Erosion Protection. 5. PENNDOT Section 865, Silt Barrier Fence.

C. Commonwealth of Pennsylvania, Department of Environmental Protection, Bureau of Soil and

Water Conservation. 1. Erosion and Sediment Pollution Control Program Manual.

a. Chapter 5, Standards and Specifications. PART 2 - PRODUCTS 2.01 MATTING FOR EROSION CONTROL

A. Jute Matting: PENNDOT Section 806.2(a)1. B. Wood Excelsior Blanket: PENNDOT Section 806.2(a)2. C. Mulch Control Netting: PENNDOT Section 806.2(d). D. Nylon Erosion Control Mat: PENNDOT Section 806.2(b)2. E. Staples: PENNDOT Section 806.2(e).

Page 71: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EROSION AND SEDIMENTATION CONTROL 02370-2

2.02 EROSION CONTROL DEVICES

A. Straw Bale Barriers: 1. Bales: Straw stalks of threshed grain or tall hay grass stalks commercially available locally. 2. Stakes: Wood Stakes. Sound, rough sawn, red, or white cedar or hardwood measuring two

inches by two inches; of required length, with tapered point. 3. Reinforcement Bars: ASTM A 615 (S1), Grade 60, Deformed.

B. Wire: ASTM A 82. C. Filter Fabric Fence: PENNDOT Section 865.2. D. Rock Construction Entrance:

1. Crushed Stone - PENNDOT Section 703.2, AASHTO No. 1. 2. Filter Cloth - PENNDOT Section 735, Class 4.

E. Pumped Water Sediment Control Device (PWSCD):

1. Nonwoven geotextile fabric sewn with double needle machine using high strength thread. 2. Provide PWSCD with opening large enough to accommodate a 4 inch discharge hose with

attached strap to tie off the hose preventing pumped water from escaping from PWSCD without being filtered.

3. Properties:

PROPERTY TEST METHOD TEST RESULT

Weight ASTM D 3776 10 oz./yd.

Grab Tensile ASTM D 4632 270 lbs.

Puncture Puncture ASTM D 4833 150 lbs.

Flow Rate ASTM D 4491 70 gal./min./ft.²

Permittivity ASTM D 4491 1.3 sec-1

UV Resistance ASTM D 4355 70%

AOS % Retained ASTM D 4751 100 100

Seam Strength ASTM D 4884 100 lbs./in.

All properties are minimum average roll value except the weight of

the fabric which is given for information only.

4. Manufacturer:

a. ACF Environmental, Dirtbag. b. Or approved equal.

F. Inlet Sediment Control Device (ISCD):

Page 72: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EROSION AND SEDIMENTATION CONTROL 02370-3

1. Woven geotextile fabric sack sewn with double needle machine using high strength thread. Geotextile fabric sack to have an average wide width strength of 100 lb/in per ASTM D 4884.

2. Provide ISCD manufactured to fit openings of the inlets. 3. Provide ISCD with integral dump straps, lifting loops and restraining strap. 4. Properties:

PROPERTY TEST METHOD TEST RESULT

Grab Tensile ASTM D 4632 300 lbs.

Grab Elongation ASTM D 4632 20%

Puncture Puncture ASTM D

4833 120 lbs.

Mullen Burst ASTM D 3786 80 psi

Trapezoid Tear ASTM D 4533 120 lbs

UV Resistance ASTM D 4355 80%

Apparent Opening Size ASTM D 4751 40 US Sieve

Flow Rate ASTM D 4491 40 Gal/Min/Sq.

Ft.

Permittivity ASTM D 4491 0.55 sec-1

All properties are minimum average roll values.

5. Manufacturer:

a. ACF Environmental, Siltsack. b. Or approved equal.

G. Channel Inlet Protection: DEP Erosion and Sediment Pollution Control Program Manual Details and Notes and Detail Drawings.

H. Curbed Roadway Inlet Protection: DEP Erosion and Sediment Pollution Control Program Manual

Details and Notes and Detail Drawings. I. Rock Filters: DEP Erosion and Sediment Pollution Control Program Manual, Chapter 5, Section 11.

2.03 TEMPORARY SEEDING MIXTURES

A. As follows:

Variety of Seed Spring Summer Fall & Winter

Mar. 1-May 15

May 15-Aug. 15

Aug. 15-Mar. 1

lb. per acre lb. per acre lb. per acre

Annual rye grass 20 40

Barley or Oats (local seed) 96

Page 73: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EROSION AND SEDIMENTATION CONTROL 02370-4

Millet (Japanese) 35

Annual rye grass 40

Winter rye or 168

Winter wheat 180

2.04 MULCHING MATERIALS

A. Mulches: As specified in PENNDOT Section 805.2(a)1. B. Mulch Binding: As specified in PENNDOT Section 805.2(b). C. Wood Chips: Wood chips, recovered from clearing and grubbing operations is acceptable as mulch

for seeding and used at a rate of 35 cubic yard per acre. PART 3 - EXECUTION 3.01 INSTALLATION

A. Silt Barrier Fence: Install fence near limits of excavation or fills where indicated on Drawings or as directed by Engineer to control erosion until disturbed areas are permanently stabilized.

1. Construct silt barrier fencing with Class 3 geotextile material with wire or plastic mesh support fencing fastened to support posts. Overall height of fabric above ground to be nominally 18 inches. Provide geotextile material of width required including an 8-inch to 12-inch section for embedment.

2. Excavate a trench 6 inches wide by 6 inches deep on fabric side of barrier and along inside of post line.

3. Install posts a minimum of 18 inches deep, by an approved method, on downstream edge of trench at a maximum spacing of 10 feet.

4. Provide wire or plastic mesh support fence when used, of sufficient height to extend from top of fabric to ground or into excavated trench and be securely fastened to posts. Provide staples for wood posts and tie wires for steel and plastic posts, with a minimum of three fasteners per post.

5. Secure geotextile fabric material by fasteners to top of wire mesh and posts, keeping sag to a minimum, and at a maximum spacing of 30 inches. Extend fabric 8 to 12 inches into excavated trench for embedment. Backfill and compact over geotextile material to prevent water from flowing under fabric. Overlap fabric roll ends a minimum of 6 inches at post locations.

6. Preassembled silt barrier fence systems to be approved by Engineer. Install preassembled fence systems in accordance with manufacturer's recommendations.

7. Construct silt barrier fence across a ditch or swale area of sufficient length to eliminate end flow, with ends pointing upstream and upslope.

8. Maintain silt barrier fence satisfactorily to keep functional. This includes removal of trapped sediment and cleaning fabric of trapped sediment by tapping fabric material when dry. Replace fabric not functioning due to clogging, damage, or deterioration as directed by Engineer.

Page 74: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EROSION AND SEDIMENTATION CONTROL 02370-5

9. Remove fencing when no longer required, as determined by Engineer. Dispose of fencing materials in a suitable manner and restore area where fence had been erected at no additional cost to SEPTA.

B. Pumped Water Sediment Control Device (PWSCD):

1. Install the PWSCD on a slope. It should be placed so the incoming water flows into the bag

and will flow through the PWSCD and then flow off the site without creating more erosion. The neck of the PWSCD should be tied off tightly to stop the water from flowing out of the PWSCD without going through the walls of the bag. To increase the surface area being used, the PWSCD may be placed on a gravel bed to allow water to flow in all directions.

2. The PWSCD is considered full and should be disposed when it is impractical for the bag to filter the sediment out at a reasonable flow rate and should be replaced with a new PWSCD.

3. Disposal may be accomplished as directed by the Engineer. If the site allows, the PWSCD may be buried on site and seeded, visible fabric removed and seeded or removed from site to a proper disposal area.

C. Inlet Sediment Control Device (ISCD):

1. Installation and emptying instructions in accordance with manufacturers printed

instructions.

D. Temporary Seeding and/or Mulching:

1. General: Engineer reserves right to direct temporary seeding and/or mulching of disturbed areas in event permanent grading and seeding cannot be immediately performed. Include cost of temporary erosion control measures in appropriate pay item.

2. Liming: Lime application rates will be determined on basis of tests performed by Contractor or apply a minimum of 800 pounds of agricultural lime stone per 1000 square yards.

3. Fertilizer: Apply fertilizer at a rate of 140 pounds per 1000 square yards of 10-20-20 fertilizer or in conformance with results of soil tests performed.

4. Tilling: Till seedbed to a depth of 3 inches prior to seeding. Lime (if required) and fertilizer may be applied during tilling operation.

5. Seeding: Type of temporary seed mixture to be used is determined by Engineer. Sow seed at rate indicated in Temporary Seeding Mixtures Article. Cover seed with ½ inch of topsoil and lightly roll seeded area.

6. Mulching: Apply hay or straw mulch at rate of three tons per acre on slopes of 1.5 to 1 or flatter. Apply asphalt material to anchor mulch at rate of 50 gallons per ton on straw or hay mulch. Apply wood cellulose fiber mulch on slopes steeper than 1.5 to 1 at a rate of 1500 pounds per acre. Wood chips, recovered from clearing and grubbing operations, is acceptable as mulch for temporary seeding. Use at a rate of 35 cubic feet per acre in lieu of straw or hay.

E. Mulching Alone: For embankments or cuts 1.5 to 1 or flatter, susceptible to critical erosion during

periods of cold weather or other site conditions, Engineer may require a three ton per acre application of straw or hay mulch for temporary erosion control and later seeding. Apply asphalt for anchoring mulch at a rate of 50 gallons per ton. Straw or hay may be rolled immediately with a

Page 75: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

EROSION AND SEDIMENTATION CONTROL 02370-6

sheepsfoot roller to anchor mulch in lieu of using asphalt. When weather becomes favorable, seed areas provided with a mulch cover alone using normal application rates of seed, fertilizer, and lime. If additional mulch is needed, rate of application and area to be mulched will be as determined by Engineer.

F. Matting for Erosion Control: Provide matting in lieu of mulch on slopes 3:1 and steeper or when directed by Engineer.

1. Prepare area to be covered as a fine seedbed, fertilized, and seeded. Place matting

immediately and water to give a firm bond to soil and start germination of seed. Either jute or excelsior matting may be used.

2. Jute Matting: Lay jute matting snugly to ground with a 4-inch overlap on edges and a 12-inch overlap on ends. Make check slots from a 2-foot-wide strip of jute matting folded and buried in a 6-inch-deep trench with a 6-inch flap extending on each side of trench. Place check slots perpendicular to water flow, tamped and stapled in place before jute matting is laid. Use check slots for jute matting when slope exceeds a 5 percent grade. On grades or slopes steeper than 5 percent, Engineer will determine spacing of check slots.

3. Excelsior Matting: Lay excelsior matting with netting on top and fibers in contact with soil over entire area. Butt ends and sides of excelsior blanket snugly and staple. It is not necessary to dig check slots, anchor ditches, or bury ends of excelsior matting.

4. Staples: Hold matting in place by means of wire staples driven at a 90-degree angle to soil surface. Space staples not more than 3 feet apart in three rows for each strip, with one row along each edge and one row alternately spaced in middle. Space staples 6 inches apart across matting ends and check slots width.

3.02 MAINTENANCE

A. Begin maintenance operations immediately and continue throughout construction period until

Contract is completed. Inspect sediment control structures and repair after each storm. 3.03 SOIL EROSION AND SEDIMENTATION PLAN

A. Should modification to the Erosion and Sedimentation Control Plan be desired during construction,

obtain necessary approvals prior to implementing any provisions at no additional cost to SEPTA.

END OF SECTION

Page 76: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SOILS MANAGEMENT 02400-1

SECTION 02400

SOILS MANAGEMENT PART 1 - GENERAL 1.01 DESCRIPTION

A. The Work of this Section includes, but is not limited to the handling, storage, transportation, and disposal of excavated soils associated with Specification Section 02300, Excavation and Grading.

1.02 RELATED WORK

A. All appropriate Sections of Division 1, Division 2, and Division 3 of these Specifications. 1.03 JOB CONDITIONS

A. SEPTA conducted soil borings within the proposed excavation areas at the 33rd and Dauphin Bus Loop and collected soil samples for chemical analysis. The objective was to determine if the excavated soils to be generated from the project could be classified as Pennsylvania Clean Fill and if not, adequately characterize these soils to determine acceptance at Clean Earth Inc. and/or Waste Management facilities. A copy of the project report presenting sampling locations, field sampling and analytical methods and the disposal documentation submitted to Bellmawr Waterfront development project and approvals is presented in “Attachment I – Soils Management”.

B. Soil sampling results indicate that the soils to be excavated on the project will not meet

Pennsylvania Clean Fill criteria; however, the soils can be disposed of at Bellmawr Waterfront development project or any other facilities approved by System Safety as regulated fill.

C. The Contractor’s off-site soil disposal facility(ies) need to be pre-approved during the bidding

process.

1.04 SUBMITTALS A. The Contractor shall submit proof of qualifications for its proposed transportation contractor(s)

for excavated soils and liquids in accordance with all Local, Federal Laws, and contract documents.

B. During the bidding process the Contractor shall submit proof of qualifications for its proposed

disposal facility(ies) for soils and liquids to be removed from the site in accordance with all Local, Federal Laws, and contract documents.

C. The Contractor shall provide SEPTA with all records including manifests and certificates of

disposal for all excavated soils and liquids to be removed from the site.

Page 77: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SOILS MANAGEMENT 02400-2

PART 2 - PRODUCTS Not Used PART 3 - EXECUTION 3.01 GENERAL A. The Contractor shall comply with the requirements of the Specifications. Should conditions

arise that are not covered by these documents, the Contractor shall immediately notify SEPTA.

B. Limits of excavation shall be as directed by the contract documents and SEPTA.

3.02 EXCAVATED SOILS

A. The Contractor shall perform excavation of soils in accordance with Specification Section

02300. B. On-Site Storage

1. SEPTA will not allow temporary staging of soils generated as part of Specification

Section 02300. The Contractor shall direct load all excavated soils resulting from excavation activities that cannot be reused onsite for offsite transportation and disposal.

C. Loading

1. The Contractor shall furnish all equipment necessary for loading of excavated soils in an effective and safe manner. Loading areas shall be designed to contain any spillage. The Contractor is responsible for removing any spillage or leakage outside of areas of excavation at no additional cost to SEPTA.

2. All vehicles used to haul excavated soils shall be delivered to the Site in a completely clean manner, and shall be cleaned prior to first use. Records and documentation of cleaning/decontamination for each vehicle shall be kept on file by the Contractor for the duration of the project.

3. The Contractor shall implement measures to strictly control dust, odors, and spills during the transport of excavated materials. The Contractor shall use covers/tarps to prevent the release of dusts and odors from trucks or other equipment, as necessary.

4. All vehicles hauling excavated soils shall be inspected by the Contractor following loading. No dripping or leaking of any quantity of material is allowed. Soils that contain excess moisture may be blended with drier materials to reduce their water content. Blending shall occur as part of loading activities at no additional cost to SEPTA. The hauling vehicles shall be sealed tightly in accordance with Federal, State, and local codes to prevent the release of materials during transport. Vehicles shall not be overloaded.

Page 78: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SOILS MANAGEMENT 02400-3

5. All vehicles shall be inspected by the Contractor to assure no excavated soil adheres to its wheels or undercarriage to avoid tracking of soils. Exteriors of all vehicles must be cleaned prior to leaving the site.

D. Transportation

1. All excavated soils must be transported off-site only to the facility(ies) pre-approved by SEPTA during the bidding process.

2. Transportation shall be provided in accordance with Department of Transportation (DOT) Hazardous Materials Regulations and State and local requirements.

3. The Contractor shall submit proof of qualifications that its proposed waste transportation contractor is licensed and permitted in all states and Canadian provinces through which they will travel with decals/placards appropriate for the excavated soils and liquids removed from the Project. This includes having a PADEP Waste Transporter Authorization issued under Act 90. The Contractor shall also submit documentation of Department of Transportation (DOT) training requirements, a list of vehicles and DOT approved containers which will be available for use on the project, DOT violation history and a list of other projects similar in magnitude to this project with contact names and telephone numbers.

4. The Contractor is responsible for obtaining fully executed manifests and certificates of disposal from the facility(ies) approved by SEPTA. This documentation must be maintained by the Contractor for the duration of the project, with copies supplied to SEPTA. The Contractor shall maintain the log of all manifests with corresponding truck numbers and waste weights onsite at all times for SEPTA inspection.

5. The Contractor is responsible for controlling any possible tracking or spilling of materials on public roadways and shall perform all cleanup if such occurs at no additional cost to SEPTA.

E. Disposal

1. Excavated soils disposal will be at a facility(ies) pre-approved by SETPTA during the

bidding process. 2. Disposal of excavated soils shall occur in accordance with the contract documents and

with all local, State, and Federal laws and regulations. 3. The Contractor shall submit proof of qualifications that the Bidder’s proposed disposal

facility(ies) is permitted for the soils to be removed from the project for off-site disposal. It is recommended that the Contractor use Clean Earth, Inc. (soils classified as regulated fill) or Waste Management, Inc.’s GROWS facility (soils classified as residual waste) as the proposed disposal facility for soils removed from the project and requiring off-site disposal. The Contractor shall submit copies of the current permits for the facility. The Contractor shall also submit the name and telephone number of the primary contact at the state regulatory agency that issued the permit, a copy of the most recent inspection report from the disposer state, a history of any violations/orders/deficiencies and their resolution, financial assurance documents and a list of major customers with contact names and phone numbers. In addition, the Contractor may submit an alternative proposed waste disposal facility subject to the

Page 79: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SOILS MANAGEMENT 02400-4

requirements of these specifications. Disposal shall not occur until written approval is provided by SEPTA.

4. The Contractor shall maintain and provide SEPTA with all records (fully executed manifests and certificates of disposal) for all soils and liquids taken off-site.

F. Water/Liquids Management

1. The Contractor shall minimize the amount of water in the area of excavation by

employing diversion berms or other approved applicable techniques. The excavation area should be limited to the boundaries shown in the Specifications or as directed by SEPTA. The Contractor must ensure that minimal disturbance is caused by diversions and proper controls are employed to minimize erosion and sediment transport. Surface runoff, seepage, or groundwater shall be managed according to the reviewed and approved Contract Drawings.

2. If any water appears at the bottom of the excavation, it may not be discharged into the storm sewer. When possible, all water should be left in place. If necessary, water may be removed along with the soil and placed into containers for future disposal.

3. If water in the excavation can no longer be managed by excavation equipment, the Contractor shall pump and collect it in 55-gallon drums or other suitable watertight containers for further testing and disposal by the Contractor at a SEPTA-approved facility, at no additional cost to SEPTA.

4. All water used for cleaning of the Contractor’s equipment shall be collected into 55-gallon drums or other suitable watertight containers for further testing and disposal by the Contractor at a SEPTA-approved facility, and at no additional cost to SEPTA.

5. The Contractor shall submit proof of qualifications that its proposed facility(ies) is/are permitted for the treatment/disposal of water and liquids generated from the work activities. The Contractor shall submit copies of the current permits for the facility(ies). The Contractor shall submit the name and telephone number of the primary contact at the state regulatory agency that issued the permit, a copy of the most recent inspection report from the disposer state, a history of any violations/orders/deficiencies and their resolution, financial assurance documents and a list of major customers with contact names and phone numbers. Disposal shall not occur until written approval is provided by SEPTA.

END OF SECTION 02400

Page 80: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SITE IMPROVEMENTS 02440-1

SECTION 02440

SITE IMPROVEMENTS

PART 1 GENERAL 1.1 DESCRIPTION

A. The work specified in this Section consists of furnishing and installing:

1. Parking bumpers 2. Pavement Markings

a. Stall Markings b. Directional Arrows c. Legends d. Painted Islands e. Line Hatching f. Cross walks g. Stop bars h. Lettering

3. Site Signage 4. Concrete Filled Bollards 5. Highway Guiderail

1.2 REFERENCES

A. Commonwealth of Pennsylvania Department of Transportation (PADOT) Specification, Publication 408, and its supplements.

1.3 JOB CONDITIONS

A. Environment Requirements: 1. Apply only when ambient air temperature is above 40 F.

PART 2 PRODUCTS 2.1 PARKING BUMPERS

A. Fabrication

1. Pre-cast concrete blocks in accordance with dimensions shown on the Contract Drawings. 2. #5 rebar dowels, 18” long.

2.2 PAVEMENT MARKING A. Water Based Paint

Page 81: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SITE IMPROVEMENTS 02440-2

1. White and yellow pavement marking paint equal to that specified in PADOT Pub 408, Section 962, expect that glass beads shall not be required.

B. Thermoplastic 1. White and yellow pavement marking paint equal to that specified in PADOT Pub 408,

Section 960. C. Blue paint for handicapped parking legend as approved by the Project Manager.

2.3 PARKING STALL BOLLARD

A. Parking stall bollard in accordance with dimensions shown on the Contract Drawings.

1. 6” diameter steel schedule 40 pipe. 2.4 SITE SIGNING

A. Traffic Signing shall conform to that specified in PADOT Pub 408, Section 1103.

2.5 HIGHWAY GUIDERAIL

A. Highway guiderail shall conform to that specified in PADOT Pub 408, Section 620.

PART 3 EXECUTION 3.1 FIELD QUALITY CONTROL

A. Layout of Work:

1. Layout lane widths, parking spaces, lettering, stop bars, and crosswalks in accordance with regulations of jurisdictional authorities and as shown.

B. Width and color of Lines for Pavement Striping:

1. Apply lines for pavement stripping as follows: a. Width:

i. Parking space markings: 4” ii. Lane striping: 4” iii. Solid crosswalk lines: 6” iv. Solid stop bar line: 12”

b. Lines: i. Dashed lane lines: 10’ in length separated by 20’ of unmarked surface. ii. Line hatching shall be used to denote no parking areas. Line hatching consists

of diagonal lines spaced 2’-0” on center. c. Color

i. White, except handicap parking and loading areas. ii. Blue for the handicap parking and loading areas

C. All pavement marking lettering shall be as followings:

a. Height: 12”

Page 82: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

SITE IMPROVEMENTS 02440-3

b. Thickness: 2”

D. Allowable Tolerances: 1. Width of lines not to vary from specified width by more than ½” in each 12”.

3.2 INSTALLING PARKING BUMPERS

A. Align 2’-6” from head end of parking space. Center in stall width and secure with two dowels.

3.3 INSTALLING PAVEMENT MARKINGS

A. Satisfactorily clean and dry the pavement surface. Blow or sweep free loose dirt and other debris.

B. Follow striping plan, as directed by SEPTA’s Project Manager.

C. Layout stalls according to plan. Immediately notify SEPTA’s Project Manager of any discrepancy.

D. Paint the stalls using an approved pavement marking paint.

E. Apply to a uniform wet film thickness of 15 mils. Provide test panel for SEPTA’s Project Manager

to inspect.

F. Provide satisfactory protection for lines and legends for at least 30 minutes or until paint is dry and track free from traffic. Barrier cones are satisfactory protection. Repaint marked or damaged area, as directed.

G. All damages to automobiles, pedestrians, etc. caused by painting operations shall be corrected by

the Contractor at no expense to SEPTA.

3.4 PARKING STALLS A. Stalls shall be 9’0” by 18’0”, or as directed by the Contract Drawings. B. Concrete filled steel bollard shall be installed at the centerline of set of handicap parking stalled

3.5 INSTALLING TRAFFIC SIGNING

A. Installation of traffic singing shall conform to that specified in PADOT Pub 408, Section 1103.

3.6 INSTALLING HIGHWAY GUIDERAIL

A. Installation of highway guiderail shall conform to that specified in PADOT Pub 408, Section 620.

END OF SECTION

Page 83: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

BITUMINOUS CONCRETE PAVING 02520-1

SECTION 02520

BITUMINOUS CONCRETE PAVING

PART 1 GENERAL 1.01 SUMMARY

D. Section Includes: The work specified in this Section consists of the bituminous concrete paving and

repaving operations for the areas indicated for new paving; and pavement marking. E. Related Sections:

1. Section 02300: Excavation, Backfill, and Compaction. 2. Section 02533: Plain Cement Concrete Pavement. 3. Section 02534: Poured in Place Concrete Curb. 4. Section 03300: Cast-In-Place Concrete.

1.02 REFERENCES

A. Pennsylvania Department of Transportation (PENN DOT) References: The PENNDOT Sections noted herein refer to sections contained in the Commonwealth of Pennsylvania Department of Transportation Specifications Publication 408, as supplemented. The payment provisions do not apply to work to be performed under this Specifications Section.

B. Commonwealth of Pennsylvania Department of Transportation Bulletin 25 and Bulletin 27. C. American Society for Testing and Materials (ASTM):

1. ASTM D 1557, Test Method for Moisture-Density Relations of Soils and Soil-Aggregate

Mixtures, Using ten pound (4.5- kg) Rammer and 18-inch (457-mm) Drop. 2. ASTM D 2167, Test Method for Density of Soil in Place by the Rubber-Balloon Method.

D. American Association of State Highway and Transportation Officials: AASHTO T 180, Moisture-

Density Relations of Soils using a ten pound Rammer and an 18-inch Drop.

1.03 DEFINITIONS A. Street: Unless otherwise specifically qualified herein, the term Street as used in this Section is

understood to mean a street, highway, avenue, boulevard, road, alley, lane, driveway, parking lot, or any other area used as a way for vehicles.

1.04 QUALITY ASSURANCE

A. Source Quality Control: Maintain the quality of work by using the products of a qualified bituminous concrete producer and qualified plant operating workmen.

Page 84: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

BITUMINOUS CONCRETE PAVING 02520-2

1. Use products of a bituminous concrete bulk producer regularly engaged in production of

hot-mix, hot-laid bituminous concrete conforming to the standards referenced herein. 2. Use materials conforming to the requirements of the Commonwealth of Pennsylvania

Department of Transportation Specifications Publication 408, as supplemented.

B. Workmen Qualifications: Provide at least one person thoroughly trained and experienced in the skills required and who readily understands the design and is completely familiar with the application of bituminous concrete paving work. During progress of bituminous concrete paving work the trained person shall be present to direct the performance of work.

1. For actual finishing of bituminous concrete surfaces and operation of the equipment, use

only personnel thoroughly trained and experienced in the skills required. 1.05 PROJECT CONDITIONS

A. Environmental Requirements: 1. Dust Control: Provide effective dust control by sprinkling water, by the use of calcium

chloride, or by other methods as approved by the Engineer. Use dust control measures where and when, and in a manner as required by the Engineer.

2. Temperature Limitations: Terminate placement of bituminous concrete surface courses of permanent pavement after October thirty-first, and do not resume placement prior to April first; interim days between date limits may be used for placement as determined by the Engineer depending upon weather temperature conditions.

a) Do not install aggregate courses when ambient temperature is below or is expected to fall below freezing.

b) Do not use aggregate containing frost nor place aggregate courses on frozen subgrade.

c) Do not place bituminous concrete surface courses of permanent pavement when the ambient temperature is 40 degrees F. or lower; nor when the temperature of the pavement, base or binder on which it is to be placed is 40 degrees F. or lower.

3. Paint Application Limitations: Adhere to manufacturer's data on air and surface temperature limits and relative humidity during application and curing of coatings.

a) Do not spray apply paint when wind velocity is above 15 mph. b) Schedule painting work to avoid dust and airborne contaminants. c) Apply paint during daylight hours only.

PART 2 PRODUCTS 2.01 BASE COURSE MATERIALS

A. Subbase: Composed of Coarse Aggregate Type C (or better) stone conforming to PENNDOT Section 703.2, No. 2A aggregate.

B. Bituminous Concrete Base Course: Conforming to PENNDOT Section 305 and Section 403 for

RAP requirements.

Page 85: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

BITUMINOUS CONCRETE PAVING 02520-3

C. Bituminous Material: Use one of the following conforming to PENNDOT Section 702 and Bulletin

25.

1. Asphalt Cement: Class AC-20. 2.02 SURFACE COURSE MATERIALS

A. Bituminous Materials:

1. Asphalt Cement: AC-20 conforming to PENNDOT Bulletin 25. 2. Bituminous Tack Coat: Class E-1, E-6, or E-8 emulsified asphalt conforming to PENNDOT

Bulletin 25.

B. Bituminous Pavement Materials: 1. Superpave Wearing Course: Hot mixed, hot laid, Bituminous Superpave Wearing Course:

Conforming to PENNDOT Section 409 of Pennsylvania Department of Transportation Publication 408, as amended.

a. 9.5 mm Graded Aggregate b. PG 64-22 Asphalt Cement c. 3 to 30 Million ESALs d. Skid Resistance Level H (SRL H)

2. Superpave Base Course: Hot mixed, hot laid, Bituminous Superpave Base Course: Conforming to PENNDOT Section 409 of Pennsylvania Department of Transportation Publication 408, as amended.

a. 25 mm Graded Aggregate b. PG 64-22 Asphalt Cement c. 3 to 30 Million ESALs

2.03 MISCELLANEOUS MATERIALS

A. Traffic Zone Paint: PENNDOT Section 704 1. Yellow Traffic Zone Paint: Low-heat, rapid-dry formulation for center lines; reflective. 2. White Traffic Zone Paint: Low-heat, rapid-dry formulation for edge lines and stop bars;

reflective. 3. Paint Quality: Paint material composition shall conform to AASHTO Type F paint

formulation and AASHTO M-247, Type (standard gradation) for reflective media (glass beads).

2.04 PAVEMENT MIXES

A. Composition of Mixtures: Binder and wearing course mixture composition shall conform to the

requirements of PENNDOT Section 401. 1. Establish a job-mix formula prior to beginning work which shall not be changed during the

progress of work without the Engineer's approval. Job-mixing tolerances shall not be

Page 86: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

BITUMINOUS CONCRETE PAVING 02520-4

presumed to permit acceptance of materials whose gradations fall outside the master ranges set in the specified PENNDOT Sections.

2. The approved job-mix formula shall lie within the specification limits and be suitable for the

layer thickness and other conditions prevailing. It shall not be changed after work has started without the approval of the Engineer.

PART 3 - EXECUTION 3.01 PREPARATION

A. Subgrade Preparation: Just prior to subbase installation, as specified in Section 02300, perform

grading and finish rolling.

1. Perform subgrade preparation only after site grading, trenching, etc., have been completed and accepted by the Engineer.

2. The moisture content of the subgrade material at the time of compaction shall not exceed two percentage points above the optimum moisture content.

B. General Requirements for Pavement Removal: Cut existing pavement to neat lines with a

mechanical saw.

1. At joints between existing pavements and new paving work, cut and neatly trim the edges of existing pavements in a manner subject to the Engineer's approval. Provide an application of Class AC-20 petroleum asphalt at the locations where new bituminous paving joins existing bituminous paving.

3.02 PERMANENT PAVING INSTALLATION

A. General Requirements: Methods of preparing paving mixture, placing paving mixture, compaction, and protection of in-place bituminous concrete pavement shall comply with PENNDOT Sections 305.3 and 401.3. The specified thicknesses are the compacted thicknesses.

1. Location of types and thicknesses of pavements are delineated on Drawings. 2. Install surface course of replacement pavement with top surface flush with surface of

adjacent pavement.

B. Base Course Installation:

1. Superpave Bituminous Concrete Base Course: Construct in accordance with the requirements of PENNDOT Section 409 of Pennsylvania Department of Transportation Publication 408, as ammended.

C. Wearing Course Installation:

Page 87: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

BITUMINOUS CONCRETE PAVING 02520-5

1. Superpave Bituminous Concrete Wearing Course: Construct in accordance with the requirements of PENNDOT Section 409 of Pennsylvania Department of Transportation Publication 408, as ammended.

a. Use Bituminous Tack Coat material to seal joints in wearing courses as specified

in PENNDOT Section 401.3 Q) 3. 3.03 MAINTENANCE

A. Continuously maintain temporary pavement without additional compensation until it is replaced with permanent pavement.

B. Without an increase in Contract Price, maintain the work done under this Section for a period as

stated in the Agreement after the date of SEPTA's approval of the Substantial Completion Certificate issued by the Engineer. Maintenance shall include the repair or removal and replacement of such work which has failed, or wherever surface depressions have developed. Materials and methods used to repair or replace such work shall conform to the applicable requirements of this Section.

C. Should the Contractor fail to perform required maintenance or repairs within three days after

receiving written notice from SEPTA or the Engineer, SEPTA may perform such maintenance or repairs and deduct the cost thereof from monies due or to become due the Contractor.

END OF SECTION

Page 88: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CONCRETE SIDEWALK 02533-1

SECTION 02533

CONCRETE SIDEWALK

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Requirements for furnishing and installing plain cement concrete sidewalks.

B. Related Sections:

1. Section 02300 - Excavation, Backfill, and Compaction. 2. Section 03300 - Cast-in-Place Concrete.

1.02 REFERENCES

A. American Association of State Highway and Transportation Officials (AASHTO):

B. American Society for Testing and Materials (ASTM): 1.03 QUALITY ASSURANCE

A. Qualifications: 1. Quality Assurance Testing and Inspection Agency Qualifications:

a. Employ an independent quality assurance testing and inspection agency qualified to perform the inspections and testing required by this Section. 1) Materials and fabrication procedures are subject to inspection and testing at

the source and the field by the independent quality assurance testing and inspection agency.

2) Inspections and tests performed by the quality assurance testing and inspection agency do not relieve the Contractor of responsibility for providing materials and fabrication procedures in compliance with specified requirements.

b. The independent quality assurance testing and inspection agency must conform to the quality standards of the nationally recognized associations and agencies that promulgate the test standards, particularly ASTM E 329.

B. Certifications:

1. Submit certified copies of test reports from the independent quality assurance testing and

inspection agency for all analyses and tests required by the referenced AASHTO and ASTM Standards.

Page 89: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CONCRETE SIDEWALK 02533-2

a. Direct the independent quality assurance testing and inspection agency to submit certified written reports that document the results of all tests and inspections performed directly to the Engineer immediately after the work is performed. 1) In the reports, state whether the tested and inspected items comply with

specified requirements or deviate from them. PART 2 - PRODUCTS 2.01 MATERIALS

A. Concrete:

1. Portland Cement: Normal strength, Type 1A air entrained, conforming to ASTM C 150. a. Cement concrete shall be a minimum of six and maximum of eight 96-pound

bags per cubic yard. b. Fine aggregate shall be Type A. Do not use fine aggregate produced from

limestone in concrete wearing surfaces. c. Coarse aggregate shall be Type A, No. 57 as specified in PENNDOT 408,

Section 703.2 Tables B, C, and D.

B. Normal weight aggregates: ASTM C 33-92a.

C. Potable water.

D. Concrete shall have an entrained air content of 6% in the plastic state with a tolerance of +1- 1.5% during the work. Entrained air in the hardened concrete shall not be less than 3.5% or greater than 7.5%. Testing for air entrainment shall be in accordance with PENNDOT 408.

E. Concrete Forms:

1. Furnish acceptable wood or metal forms that meet the requirements and that extend the

full depth of the concrete. 2. Erect forms true to line and grade. Maintain alignment using steel stakes at intervals not

greater than 4 feet.

F. Expansion Joint Fillers:

1. Joint Filler: Non-extruding and resilient bituminous type complying with ASTM D 1751.

G. Stone Aggregate:

1. Crushed Stone: PENNDOT No. 2A coarse aggregate; natural stone, free of shale, clay, friable material, sand, and debris; graded in accordance with ASTM C 136.

2.02 MIXES

A. Provide Class A Concrete to the following criteria and in accordance with Section 03300.

Page 90: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CONCRETE SIDEWALK 02533-3

1. Compressive strength at 28 days: 3300 psi. 2. Slump: 3 inches. 3. Aggregate size: 1 inch.

2.03 SOURCE QUALITY CONTROL

A. Submit Certificates of Compliance from the quality assurance testing and inspection agency certifying that the materials provided comply with the specified requirements.

B. Have the quality assurance testing and inspection agency perform acceptance testing of the stone

aggregate at the source. PART 3 – EXECUTION 3.01 EXAMINATION

A. Verify that previously installed protection measures are in place. B. Verify that all surfaces abutting new concrete pavement are clean, true, and free from chips, etc. C. Beginning installation means acceptance of existing conditions.

3.02 PREPARATION

A. Do not place crushed stone on soft, muddy, or frozen areas. Correct irregularities or soft areas before placing crushed stone.

B. Place and secure forms to correct location, dimension, and profile. C. Assemble formwork to permit easy stripping and dismantling without damaging concrete. D. Proof roll prepared subbase to check for unstable areas and need for additional compaction. E. Moisten base to minimize absorption of water from fresh concrete.

3.03 INSTALLATION OF AGGREGATE BASE

A. Maintain optimum moisture content of materials in order to attain required compaction density. B. Spread crushed stone on prepared subgrade, in a manner not causing segregation, in locations

and to attain depth shown on Drawings, after final compaction. Use acceptable equipment and methods per PENNDOT Publication 408.

1. Compact uniformly spread crushed stone to not less than 100% of the maximum dry-

weight density, which will be determined in accordance with PTM No.1 06, Method B.

Page 91: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CONCRETE SIDEWALK 02533-4

2. Proceed with compaction gradually from sides to center, with each succeeding pass uniformly overlapping the previous pass. Continue until the entire area is shaped and compacted.

3. If crushed stone does not contain sufficient moisture after placement, add water to obtain proper compaction.

C. Top surface of compacted crushed stone shall be plus or minus Y. inch from required depth.

3.04 INSTALLATION OF CONCRETE

A. Comply with ACI recommendations when placing concrete. B. Mix and deliver concrete in accordance with ASTM C 94-92A.

1. Use accelerating admixtures in cold weather only when approved by SEPTA. Use of

admixtures will not relax cold weather placement requirements. 2. Use set-retarding admixtures during hot weather only when approved by SEPTA.

C. Place expansion joint filler between new and existing work and as shown on drawings and secure

to formwork during concrete placement.

1. Provide joint filler abutting existing concrete, concrete curbs, catch basins, inlets, manholes, and any other fixed objects.

2. Recess joint filler 1/2 inch from top of slab.

D. Construct control and construction joints in locations indicated on the Drawings.

1. Form control joints in fresh concrete by grooving top portion with cutting tool and finishing edges with a metal edger having a 3/8-inch radius.

a. Control joints shall have a depth of at least 25% of the concrete thickness. b. Space control joints at the width of the sidewalk, 6' maximum.

2. Place construction joints at the end of placements and at locations where placement

operations are stopped for more than 1/2 hour except where placements stop at expansion joints.

a. Place expansion joints at 30' maximum spacing. b. Construct joints using standard metal keyway section forms.

3. The concrete around light standards, poles, fire hydrants, access frames, and covers to underground utilities, manhole frames and covers, and similar structures shall be scored, by edging or grooving, in a block 8 inches wider than the maximum dimensions of the structure.

E. Maintain records of concrete placement. Record date, location of pour, quantity, air temperature,

and test samples taken. F. Provide concrete pavement with a light broom finish.

Page 92: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CONCRETE SIDEWALK 02533-5

G. The edges and perimeter and expansion and control joint scoring of all slabs shall be edged with a

metal edger having a 1/4-inch radius to produce a dense compact border outlining each slab.

3.05 CONCRETE CURING

A. Immediately after placement, protect concrete from premature drying, excessive hot or cold temperatures, and mechanical injury.

1. Maintain concrete with minimal moisture loss at a relatively constant temperature for the

period necessary for hydration of cement and hardening of concrete. 2. When the average daily temperature is less than 40 degrees F, maintain temperature of

newly placed concrete between 50 to 70 degrees F during the required curing period. 3. When the average daily temperature is above 70 degrees F, protect the newly placed

concrete from high temperatures and drying winds by keeping the concrete surface continually wet and by providing wind breaks during the required curing period.

4. Provide 30 days curing period before applying Special Coating. 3.07 PROTECTION

A. Protect the walks from damage until acceptance of the work.

1. Exclude pedestrians from walks for at least 3 days after placement. 2. Provide necessary watchmen to prevent vandalism to freshly poured concrete walks.

3.08 REMEDIAL WORK

A. Repair or replace deficient work as directed by SEPTA's Project Manager and at no additional cost to SEPTA.

B. Patch defective concrete surfaces with a suitable, approved patching material, mix or product as

directed by SEPTA's Project Manager. 3.09 CLEANING

A. Sweep the concrete walks. B. Wash the concrete walks so they are free of stains, graffiti, discoloration, dirt, and other foreign

materials. 1. Completely remove graffiti from graffiti-marked sidewalks.

C. Satisfactorily dispose of unsuitable and surplus materials provided under this Contract.

END OF SECTION

Page 93: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

POURED IN PLACE CONCRETE CURB 02534-1

SECTION 02534

POURED IN PLACE CONCRETE CURB

PART 1 - GENERAL 1.01 SUMMARY

A. The work specified in this Section consists of furnishing and installing concrete curbs and combination curb and gutter.

B. Related Sections:

1. Section 02300 - Excavation, Backfill, and Compaction. 2. Section 03300 - Cast-In-Place Concrete.

1.02 REFERENCES

A. American Society for Testing and Materials (ASTM):

B. American Association of State Highway and Transportation Officials (AASHTO): PART 2 - PRODUCTS 2.01 FORMS

A. Steel forms:

1. Approved flexible forms of steel or wood may be used for construction of circular curb where radius is 200 feet or less.

B. Forming:

1. Use acceptable metal forms, except on sharp curves, and short tangent sections, where

wood forms may be used if acceptable to the Contracting Officer. 2. Forms shall extend full depth of the concrete.

2.02 MATERIALS

A. Concrete: Concrete conforming to requirements of Section 03300 except use NO.8 coarse aggregate, conforming to AASHTO M43, for concrete placed by extrusion method.

1. Maximum Slump: 3 inches. For curbs placed by extrusion, maximum slump: 1 1/2 inches. 2. Class A, Compressive strength 3300 psi at 28 days minimum.

B. Preformed Expansion Joint Filler:

Page 94: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

POURED IN PLACE CONCRETE CURB 02534-2

1. Fiber Type, ASTM D 1751. 2. Cork or Sponge Rubber: ASTM D 1752.

C. Joint Sealer:

1. Hot-applied: Rubberized joint sealing material, ASTM D 1190 or ASTM D 3405. 2. Cold-applied: Elastorneric type, ASTM C 920.

PART 3 – EXECUTION 3.01 PREPARATORY WORK

A. Excavation: Excavate to the required depth, then compact the material upon which the curb is to be constructed to a firm, even surface.

B. Forms

1. Erect forms true to line and grade. 2. Secure forms in-place with iron stakes spaced on not more than four-foot centers. 3. Indicate line and grade of curb tops by an offset guideline for extrusion placement.

3.02 CONSTRUCTION

A. Placing Concrete:

1. Cast-In-Place: Conform to requirements of Section 03300 except place the concrete in the forms in layers not exceeding 5 inches in depth when spading, or layers not exceeding 15 inches in depth when using a vibrator to eliminate voids.

2. By extruding machine (Where approved by the Contracting Officer): a. Uniformly feed the concrete to the machine so that concrete maintains the

shape of the section without slumping after extrusion. b. Voids or honeycombs on the surface of the finished curb will not be allowed.

Apply any additional surface finishing required immediately after extrusion.

B. Joints: Construct joints as follows:

1. Expansion Joints: a. Space expansion joints at 30' maximum or to match the adjoining sidewalk. b. Place 1/2 inch preformed expansion joint filler at expansion joints at ends of

curb returns, and at junctures with structures. Place filler in single piece conforming to curb cross-section and depressed ½ inch below finished surface.

c. Where curb is constructed in conjunction with adjacent sidewalk, the expansion joint in the curb and sidewalk shall coincide.

2. Contraction Joints: a. For curb not constructed integrally with new base or pavement, form or saw

contraction joint 3/16 inch wide, to a depth of 1/5 of the curb height at 10 foot intervals.

Page 95: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

POURED IN PLACE CONCRETE CURB 02534-3

b. Saw as soon as possible after the concrete has set sufficiently to preclude raveling during the sawing.

c. Fill joint with hot-applied joint sealer. 3. Tool the edges of all joints adjacent to expansion filler to a 1/4 inch radius, leaving all joints

free of mortar and concrete. Leave the joint filler exposed for the full length of the joint with clean and true edges.

C. Removal of Forms: Do not remove forms until such time that it will not be detrimental to the

concrete. Correct irregular faces by rubbing with a carborundum stone. D. Finishing:

1. Finish top edge of face to a one inch radius. 2. Trowel curb faces smooth either to a depth of not less than two inches below top of

pavement or to the flow line of integral curb and gutter. Hand finish the face of curb with a steel trowel.

3. Provide a final fine brush finish to the top and face of curb with brush strokes parallel to the line of the curb.

4. Allow no coarse aggregate to show on the finished curb surface.

E. Curing: Conform to requirement of Section 03300, except that liquid membrane curing compound shall not be used on curb when temperature tends to go lower than 40 degrees F within 24 hours after application.

F. Sealing Joints:

1. Seal all expansion joints, all joints between curb and vehicular pavements and all joints between gutters and vehicular pavements to within 1/8 inch of the surface. (Do not seal other joints unless otherwise indicated or directed by the Contracting Officer.

2. Seal joints with (poured) joint sealer in conformance with the manufacturer's recommendations.

G. Backfilling:

1. As soon as possible after the removal of forms, and finishing as specified herein, backfill the voids in front and back of the curb using acceptable embankment material as specified in Section 02300.

2. Complete embankments in back of raised curb, as indicated, and as specified in Section 02300, except carefully compact the embankment by means of mechanical tampers, or rollers, if permitted, not exceeding 8 tons.

3.03 REMEDIAL WORK

A. Repair or replace deficient work as directed by SEPTA's Project Manager and at no additional cost to SEPTA.

B. Patch defective concrete surfaces with a suitable, approved patching material, mix or product as

directed by SEPTA's Project Manager.

Page 96: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

POURED IN PLACE CONCRETE CURB 02534-4

END OF SECTION

Page 97: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

UTILITY STRUCTURES 02605-1

SECTION 02605

UTILITY STRUCTURES

PART1 - GENERAL 1.01 SUMMARY

A. Section Includes: 1. Storm sewer inlets, spacers, and tops. 2. Storm and sanitary sewer manhole bases, risers, and top units. 3. Inlet and manhole frames, grates, and covers.

B. Related Sections:

1. Section 02300 - Excavation, Backfill, and Compaction for Utilities. 2. Section 03300 - Cast-In-Place Concrete.

1.02 REFERENCES

A. American Society for Testing and Materials (ASTM):

1. ASTM A 48, Specification for Gray Iron Castings. 2. ASTM A 185, Specification for Welded Steel Wire Fabric for Concrete Reinforcement. 3. ASTM A 307, Specification for Carbon Steel Externally Threaded Standard Fasteners. 4. ASTM A 615, Specification for Deformed and Plain Billet-Steel Bars for Concrete

Reinforcement. 5. ASTM C 31, Methods of Making and Curing Concrete Test Specimens in the Field. 6. ASTM C 33, Specification for Concrete Aggregates. 7. ASTM C 39, Test Method for Compressive Strength of Cylindrical Concrete Specimens. 8. ASTM C 150, Specification for Portland Cement. 9. ASTM C 270, Specification for Mortar for Unit Masonry. 10. ASTM C 309, Specification for Liquid Membrane-Forming Compounds for Curing concrete. 11. ASTM C 923, Specification for Resilient Connectors Between Reinforced Concrete Manhole

Structures, Pipes and Laterals. 12. ASTM D 2000, Classification System for Rubber Products in Automotive Applications (SAE

Recommended Practice J200).

B. American Association of State Highway and Transportation Officials (AASHTO) Standards as referenced throughout these Specifications.

C. American Concrete Institute (ACI).

1. ACI 304, Recommended Practice for Measuring, Mixing, Transporting and Placing Concrete. 2. ACI 308, Standard Practice for Curing Concrete. 3. ACI 309, Guide for Consolidation of Concrete.

Page 98: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

UTILITY STRUCTURES 02605-2

4. AC1318, Building Code Requirements for Reinforced Concrete.

D. Federal Specifications:

1. Fed. Spec. SS-S-210A, Sealing Compound, Preformed Plastic, for Expansion Joints and Pipe Joints (Type 1 Rope Form).

1.03 QUALITY ASSURANCE

A. Precast Concrete Producer Qualifications: Provide documentation from the precast concrete unit producer that their products have been in continuous service for a minimum of five years.

B. Design Criteria: Provide documentation that the precast concrete utility structures are designed to meet

the minimum structural loading requirements of AASHTO HS20-44, ACI 318, and the loads exceeding AASHTO and ACI requirements as may be indicated on the Drawings.

C. Certifications:

1. Obtain certificate of construction compliance with ASTM C 478 from the precast reinforced concrete manhole manufacturer. Submit same certificate as part of required submittals.

2. Obtain certificate of material compliance with ASTM A 48, Class 30 tensile strength from the manhole frame and cover manufacturer. Furnish certification that tensile test bars were from same pour as castings. Submit the certificates as part of required submittals.

1.04 DELIVERY, STORAGE, AND HANDLING

A. Delivery and Handling: Transport and handle precast concrete units and their associated components, and other products specified herein, in a manner recommended by their respective manufacturers to prevent damage and defects of whatever nature.

B. Through-wall lifting holes are not permitted in structure component construction.

C. Storage: Store precast concrete structure components in accordance with their manufacturer's

recommendations to prevent joint damage and joint contamination. Exercise such care in storage of other specified products as recommended by their respective manufacturers.

PART 2 - PRODUCTS 2.01 BASIC MATERIALS

A. Acceptable Manufacturers: 1. PENNDOT Bulletin 15. 2. Or equal.

B. Aggregate Materials: Conforming to ASTM C 33. Both fine and coarse aggregates shall be free of

deleterious substances which cause reactivity with oxidized hydrogen sulfide.

Page 99: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

UTILITY STRUCTURES 02605-3

C. Reinforcing: Bars conforming to ASTM A 615 Grade 60, and wire fabric conforming to ASTM A 185. D. Cast-In-Place Concrete Products: As specified in Section 03300. E. Non-Shrink Non-Metallic Grout: As specified in Section 05120 - Structural Steel. F. Masonry Products: Provide the following products to field form the required adjustment to grade of

frames, grates and covers: G. Portland Cement: Conforming to ASTM C 150, Type I. H. Sand: Conforming to ASTM C 144. I. Water: Clean and free from deleterious amounts of acids, alkalis, and organic materials.

2.02 MANUFACTURED UNITS

A. Manhole Covers and Frames:

1. Grey iron castings conforming to ASTM A 48, Class 35B. Provide castings of uniform quality, free from blowholes, porosity, hard spots, shrinkage distortion, and other defects. Frame and cover design and dimensions as indicated on Drawings.

2. Provide casting designed for AASHTO H-20 loading. a. Finish: Bearing surfaces machined to prevent rocking and rattling. b. Identification: Cast the applicable word integrally on cover in 2 inch size raised letters. c. Frame Hold-down Bolts: ASTM A 307. d. Tensile Test Bar: Size B, cast separately, but poured from same iron as castings they

represent. e. Aluminum Inner Cover: Fabricate from aluminum alloy 6061-T6 sheet or plate to

dimensions indicated on Drawings. Provide cover with vents and lift handle. f. Cover Gasket: One piece O-ring gasket factory installed in a machined rectangular or

dovetail groove in the cover bearing surface. g. Gasket material of neoprene composition having good abrasion resistance, low

compression set, 40 durometer hardness and suited for use in sanitary sewer manholes. 3. Acceptable Manufacturer:

a. PENNDOT Bulletin 15. b. Or approved equal.

B. Inlet Frames and Grates:

1. Provide inlet grates and frames as shown on the PENNDOT Standard Drawings RC-34 and as

shown on the Drawings. Grates and frames may be either fabricated structural steel or cast gray, malleable, or ductile iron.

2. Fabricated: a. Coat structural steel grates with bituminous paint in the shop or in the field, prior to

placement.

Page 100: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

UTILITY STRUCTURES 02605-4

b. Coat structural steel frames with bituminous paint at the time of casting the concrete inlet top unit.

c. As an alternative to bituminous paint, hot dip galvanized structural steel grates and frames. 3. Castings:

a. Gray iron castings conforming to AASHTO M 105(ASTM A 48), Class No. 207. b. Malleable iron castings conforming to ASTM A 47/A 47M, Grade 24018. c. Ductile iron castings conforming to ASTM A 536, Grade 60-40-18 unless otherwise

specified. d. Sandblast all castings or otherwise effectively clean scale and sand so as to present a

smooth, clean, and uniform surface. 4. Acceptable Manufacturer:

a. PENNDOT Bulletin 15. b. Or approved equal.

C. Manhole Steps: Provide steps with minimum width of 10 inches, minimum projection from wall of 5-3/8

inches, unless indicated otherwise on Drawings.

1. Aluminum Step: Aluminum Alloy AA Designation 6061-T6. Coat the portion of aluminum step being embedded in concrete with heavy bodied bituminous paint.

2. Reinforced Plastic Step: Composed of a 1/2 inch Grade 60, ASTM A 615 deformed steel reinforcing bar completely encapsulated in polypropylene copolymer compound conforming to ASTM D 4101; MA Industries, Inc., Type PS4, or equal.

2.03 PRECAST CONCRETE COMPONENTS

A. Manufacturers:

1. PENNDOT Bulletin 15.

B. Materials and Fabrication: Provide steel reinforced precast concrete structure of either one piece construction, or component construction, conforming to the following:

1. Forming: Use form of sufficient design and bracing to maintain alignment and prevent

deforming under pressure during pouring and vibrating of concrete. 2. Reinforcing: Bars conforming to ASTM A 615 Grade 60, and wire fabric conforming to ASTM A

185. 3. Concrete: Composed of Portland cement conforming to ASTM C 150, Type 1 and aggregate

conforming to ASTM C 33. Both fine and coarse aggregates shall be free of deleterious substances which cause reactivity with oxidized hydrogen sulfide. Materials shall be accurately weighed at a certified central batching facility prior to mixing. Concrete mixture shall contain cement content in amounts adequate to produce a minimum strength of 5,000 psi concrete at 28 days.

a. The concrete strengths shall be as confirmed by cylinder strength tests in accordance with ASTM C 31 and C 39.

4. Placing: Pour concrete in a continuous operation, without segregation or loss in ingredients, until completion of unit; all in accordance with ACI 304. Consolidate concrete by mechanical internal vibrating equipment.

Page 101: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

UTILITY STRUCTURES 02605-5

5. Curing: In general, perform concrete curing by water curing, sheet form curing, or sealing methods; all in accordance with AC1308.

a. If steam curing is used, cure units in forms after initial set at temperatures not to exceed 160 degrees F with temperature rise above ambient not to exceed 40 degrees F per hour.

b. After steam curing and form stripping continue curing by water spray or liquid membrane curing using compounds conforming to ASTM C 309.

6. Dimensions: a. Side Walls: Unit dimensions as indicated on Drawings and formed with pipe opening

provisions. b. Removable Top: Top dimensions as indicated on Drawings with openings sized to

accommodate manhole frame and cover. C. Precast Base, Wall, and Top Sections: Designs as indicated on the Drawings, materials, and

construction as specified previously under Materials and Fabrication.

1. Removable Top Section: Top section of flat slab design, dimensions as indicated on Drawings. The access hatch shall be either field installed or factory installed integral with the top section during the casting process.

2. Base and Wall Sections: The base and wall sections shall be cast as a single unit except where the base section is required to be separate for installation purposes. Where the depth of the structure exceeds the limitation of single unit construction, provide the appropriately sized riser sections to meet proposed grade.

D. Precast Concrete Leveling/Adjusting Units: Provide units of not less than two inches thickness and of

materials and construction as specified for Precast Base, Wall, and Top Sections.

E. Waterproof Coating: Of materials as specified previously, and either shop or field applied to the precast concrete components.

1. Apply coating in two coats at the rate of 75 to 100 square feet per gallon per coat. Allow 24

hours drying time between coats. PART 3 – EXECUTION 3.01 PREPARATION

A. Earthwork: Perform earthwork for precast concrete utility structures installation as previously specified in Section 02300 and according to the following:

1. Protection: During earthwork operations, keep pipe or conduit and structure interiors cleared of

debris as construction progresses. 2. Excavation Limits: Make excavations for the structures to a nearly vertical plane beginning at

bottom of excavation one-foot beyond structure footer to two-feet beyond top of the structure. a. The excavation limits specified herein are based on allowable payment quantities

in the Project.

Page 102: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

UTILITY STRUCTURES 02605-6

b. Backfill spaces outside structures using material as specified in Section 02300 and Section 2322.

c. If surface pavement of any type is encountered (vehicle or pedestrian ways), cut such pavement to a rectangular shape. Make limits of cut not to exceed one-foot beyond top-of-excavation limit as specified previously.

d. No additional compensation allowed should excavation limits or surface pavement cut limit be exceeded. Additionally, should bottom-of-excavation limit be exceeded, provide at no increase in Contract Price, concrete cradle or encasement for pipes or conduits entering or leaving the structure.

3.02 CONSTRUCTION METHODS

A. Cast-In-Place Concrete Construction: Construct in accordance with design and dimensions indicated on Drawings.

1. Concrete Work: Form, reinforce and pour concrete in accordance with requirements of Division

3 - Concrete. a. Use Class A (4000 psi) concrete as specified in Section 03300, unless indicated

otherwise on Drawings.

B. Precast Concrete Utility Structures Installation: Unless indicated otherwise, install structures on a six inch deep compacted layer of Aggregate Backfill or Foundation Backfill as selected by the Construction Manager in the field.

C. Frame and Cover Installation: Where required, make final adjustment of frame to elevation using

materials specified in Part 2 Products.

1. Set precast grade rings in Water-proof Mortar, of thickness not to exceed 3/4 inch maximum and 3/8 inch minimum. Wet, but do not saturate precast grade rings immediately before laying.

2. Precast grade ring: Pre-set to proper plane and elevation using wedges or blocks of cementitious material not exceeding one square inch wide on all sides. No more than four wedges or blocks per grade ring permitted. Incorporate wedges or blocks in fresh mortar in a manner to completely encase each. Crown fresh mortar to produce squeeze-out between grade rings. Tool exposed joints with appropriately shaped tool and compact mortar edge into joints. Clean off excess mortar prior to initial mortar set.

3. Bolt manhole frames in place on manhole top section, or on leveling units if required, after installing 1/2 inch thick preformed plastic sealing compound on bearing surface of manhole frame. Remove excess sealing compound squeeze-out after manhole frame is bolted in place.

4. Use bolts of sufficient length to properly pass through leveling units, if any, engage full depth of manhole top section inserts and allowing enough threaded end to pass through manhole frame to properly tighten nut and washer. Tighter manhole frame bolts after mortar has cured.

D. Frame and Grate Installation: Where required, make final adjustment of top section and frame to

elevation using materials specified in Part 2 Products. If grade sections are used, they must encompass all four sides of the box.

Page 103: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

UTILITY STRUCTURES 02605-7

1. Set loose frames in cast-in-place inlet tops only where they are securely held in position by sturdy stringers spanning the entire width of the excavation and confirmed to be to final pavement grade prior to placement of concrete.

3.03 FIELD QUALITY CONTROL

A. General: Make a visual inspection of each unit constructed to ensure compliance with installation requirements.

1. Repair or replace defective materials and workmanship, as is the case, and conduct such

additional inspection and such subsequent repairs as required until manholes and inlets meet requirements.

2. Materials and methods used to make manhole repairs must meet with Engineer's approval prior to use.

3. Make repairs and replacements at no additional expense to SEPTA.

END OF SECTION

Page 104: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

STORM DRAINAGE SYSTEMS 02721-1

SECTION 02721

STORM DRAINAGE SYSTEMS

PART 1 - GENERAL 1.1 DESCRIPTION

A. The work specified in this Section consists of furnishing and installing pipe, inlets, grates, castings, and manholes.

1.2 RELATED WORK

A. Section 02322 - Excavation, Backfill, and Compaction for Utilities B. Section 03300 - Cast-In-Place Concrete C. Section 02370 - Erosion and Sediment Control

D. Section 02605 - Utility Structures

1.3 DELIVERY, STORAGE, AND HANDLING

A. Delivery and Storage

1. Materials delivered to site shall be inspected for damage, unloaded, and stored with a minimum of handling. Materials shall not be stored directly on the ground. The inside of pipes and fittings shall be kept free of dirt and debris. Before, during, and after installation, plastic pipe and fittings shall be protected from any environment that would result in damage or deterioration to the material. The Contractor shall have a copy of the manufacturer's instructions available at the construction site at all times and shall follow these instructions unless directed otherwise by the Contracting Officer. Solvents, solvent compounds, lubricants, elastomeric gaskets, and any similar materials required to install plastic pipe shall be stored in accordance with the manufacturer's recommendations and shall be discarded if the storage period exceeds the recommended shelf life. Solvents in use shall be discarded when the recommended pot life is exceeded.

B. Handling

1. Materials shall be handled in a manner that ensures delivery to the trench in sound,

undamaged condition. Pipe shall be carried to the trench, not dragged.

PART 2 - PRODUCTS 2.1 PIPE CULVERTS

Page 105: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

STORM DRAINAGE SYSTEMS 02721-2

A. Reinforced Concrete Cement Pipe, Class II, in accordance with PADOT Publication 408, Section

601, "Pipe Culverts". 2.2 PRECAST INLETS

A. In accordance with PADOT Type "C" and "M" per PADOT Standard Drawings and PADOT Publication 408, Section 605, "Endwalls, Inlets, Manholes and Spring Boxes" and Section 713 "Masonry Units".

B. Precast Inlets shall be designed for AASHTO HS-20 wheel load and applicable impact.

2.3 FRAMES, GRATES, MANHOLE COVERS

A. Neenah or approved equal, in accordance with PADOT Publication 408, Section 605, "Endwalls, Inlets, Manholes and Spring Boxes".

B. Frames, Grates, and Manhole Covers shall be designed for AASHTO HS-20 wheel load and

applicable impact.

C. Manhole covers shall contain the words “STORM”, in accordance with PADOT Publication 408, Section 605, "Endwalls, Inlets, Manholes and Spring Boxes".

2.4 PRECAST MANHOLES

A. In accordance with PADOT Publication 408, Section 605 "Endwalls, Inlets, Manholes and Spring Boxes" and Section 713 "Masonry Units".

B. Precast Manholes shall be designed for AASHTO HS-20 wheel load and applicable impact.

2.5 DRAINAGE AGGREGATE

A. Either No. 8 natural sand or No. 8 manufactured sand per PADOT Publication 408, Section 703.1, "Fine Aggregate".

B. Select Granular Material (2RA): PADOT Publication 408, Section 703.3.

2.5 MISCELLANEOUS MATERIALS

A. Concrete

1. Unless otherwise specified, concrete and reinforced concrete shall conform to the requirements for 4000 psi concrete under Section 03300 CAST-IN-PLACE STRUCTURAL CONCRETE. The concrete mixture shall have air content by volume of concrete, based on measurements made immediately after discharge from the mixer, of 5 to 7 percent when maximum size of coarse aggregate exceeds 1-1/2 inches. Air content shall be determined in accordance with ASTM C 231. The concrete covering over steel reinforcing

Page 106: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

STORM DRAINAGE SYSTEMS 02721-3

shall not be less than 1 inch thick for covers and not less than 1-1/2 inches thick for walls and flooring. Concrete covering deposited directly against the ground shall have a thickness of at least 3 inches between steel and ground. Expansion-joint filler material shall conform to ASTM D 1751, or ASTM D 1752, or shall be resin-impregnated fiberboard conforming to the physical requirements of ASTM D 1752.

B. Mortar

1. Mortar for pipe joints, connections to other drainage structures, and brick or block

construction shall conform to ASTM C 270, Type M, except that the maximum placement time shall be 1 hour. The quantity of water in the mixture shall be sufficient to produce a stiff workable mortar. Water shall be clean and free of harmful acids, alkalies, and organic impurities. The mortar shall be used within 30 minutes after the ingredients are mixed with water. The inside of the joint shall be wiped clean and finished smooth. The mortar head on the outside shall be protected from air and sun with a proper covering until satisfactorily cured.

C. Brick

1. Brick shall conform to ASTM C 62, Grade SW; ASTM C 55, Grade S-I or S-II; or ASTM C

32, Grade MS. Mortar for jointing and plastering shall consist of one part portland cement and two parts fine sand. Lime may be added to the mortar in a quantity not more than 25 percent of the volume of cement. The joints shall be filled completely and shall be smooth and free from surplus mortar on the inside of the structure. Brick structures shall be plastered with 1/2 inch of mortar over the entire outside surface of the walls. For square or rectangular structures, brick shall be laid in stretcher courses with a header course every sixth course. For round structures, brick shall be laid radially with every sixth course a stretcher course.

D. Precast Reinforced Concrete Manholes

1. Precast reinforced concrete manholes shall conform to ASTM C 478. Joints between

precast concrete risers and tops shall be [full-bedded in cement mortar and shall be smoothed to a uniform surface on both interior and exterior of the structure] [made with flexible watertight, rubber-type gaskets meeting the requirements of paragraph JOINTS].

E. Prefabricated Corrugated Metal Manholes

1. Manholes shall be of the type and design recommended by the manufacturer. Manholes

shall be complete with frames and cover, or frames and gratings.

F. Frame and Cover for Gratings

1. Frame and cover for gratings shall be cast gray iron, ASTM A 48, Class 35B; cast ductile iron, ASTM A 536, Grade 65-45-12; or cast aluminum, ASTM B 26/B 26M, Alloy 356.OT6. Weight, shape, size, and waterway openings for grates and curb inlets shall be as indicated on the plans.

Page 107: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

STORM DRAINAGE SYSTEMS 02721-4

G. Joints

1. Flexible Watertight Joints

a. Materials: Flexible watertight joints shall be made with plastic or rubber-type

gaskets for concrete pipe and with factory-fabricated resilient materials for clay pipe. The design of joints and the physical requirements for plastic gaskets shall conform to AASHTO M 198, and rubber-type gaskets shall conform to ASTM C 443. Factory-fabricated resilient joint materials shall conform to ASTM C 425. Gaskets shall have not more than one factory-fabricated splice, except that two factory-fabricated splices of the rubber-type gasket are permitted if the nominal diameter of the pipe being gasketed exceeds 54 inches.

b. Test Requirements: Watertight joints shall be tested and shall meet test requirements of paragraph HYDROSTATIC TEST ON WATERTIGHT JOINTS. Rubber gaskets shall comply with the oil resistant gasket requirements of ASTM C 443. Certified copies of test results shall be delivered to the Contracting Officer before gaskets or jointing materials are installed. Alternate types of watertight joint may be furnished, if specifically approved.

2. External Sealing Bands a. Requirements for external sealing bands shall conform to ASTM C 877.

3. Flexible Watertight, Gasketed Joints a. Gaskets: When infiltration or exfiltration is a concern for pipe lines, the couplings

may be required to have gaskets. The closed-cell expanded rubber gaskets shall be a continuous band approximately 7 inches wide and approximately 3/8 inch thick, meeting the requirements of ASTM D 1056, Type 2, and shall have a quality retention rating of not less than 70 percent when tested for weather resistance by ozone chamber exposure, Method B of ASTM D 1171. Rubber O-ring gaskets shall be 13/16 inch in diameter for pipe diameters of 36 inches or smaller and 7/8 inch in diameter for larger pipe having 1/2 inch deep end corrugation. Rubber O-ring gaskets shall be 1-3/8 inches in diameter for pipe having 1 inch deep end corrugations. O-rings shall meet the requirements of AASHTO M 198 or ASTM C 443. Flexible plastic gaskets shall conform to requirements of AASHTO M 198, Type B.

b. Connecting Bands: Connecting bands shall be of the type, size and sheet thickness of band, and the size of angles, bolts, rods and lugs as indicated or where not indicated as specified in the applicable standards or specifications for the pipe. Exterior rivet heads in the longitudinal seam under the connecting band shall be countersunk or the rivets shall be omitted and the seam welded. Watertight joints shall be tested and shall meet the test requirements.

PART 3 - EXECUTION 3.1 EXCAVATION FOR PIPE CULVERTS, STORM DRAINS, AND DRAINAGE STRUCTURES

A. Excavation of trenches, and for appurtenances and backfilling for culverts and storm drains, shall be in accordance with the applicable portions of [Section 02300; Excavation and Backfill]

Page 108: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

STORM DRAINAGE SYSTEMS 02721-5

B. Trenching

1. The width of trenches at any point below the top of the pipe shall be not greater than the

outside diameter of the pipe plus 24 inches to permit satisfactory jointing and thorough tamping of the bedding material under and around the pipe. Sheeting and bracing, where required, shall be placed within the trench width as specified. Contractor shall not over excavate. Where trench widths are exceeded, redesign with a resultant increase in cost of stronger pipe or special installation procedures will be necessary. Cost of this redesign and increased cost of pipe or installation shall be borne by the Contractor without additional cost to the Government.

C. Removal of Rock

1. Rock in either ledge or boulder formation shall be replaced with suitable materials to

provide a compacted earth cushion having a thickness between unremoved rock and the pipe of at least 8 inches or 1/2 inch for each foot of fill over the top of the pipe, whichever is greater, but not more than three-fourths the nominal diameter of the pipe. Where bell-and-spigot pipe is used, the cushion shall be maintained under the bell as well as under the straight portion of the pipe.

D. Removal of Unstable Material

1. Where wet or otherwise unstable soil incapable of properly supporting the pipe, as

determined by the Contracting Officer, is unexpectedly encountered in the bottom of a trench, such material shall be removed to the depth required and replaced to the proper grade with select granular material, compacted as provided in paragraph BACKFILLING. When removal of unstable material is due to the fault or neglect of the Contractor in his performance of shoring and sheeting, water removal, or other specified requirements, such removal and replacement shall be performed at no additional cost to the government.

3.2 BEDDING

A. The bedding surface for the pipe shall provide a firm foundation of uniform density throughout the entire length of the pipe.

B. Concrete Pipe Requirements

1. When no bedding class is specified or detailed on the drawings, concrete pipe shall be bedded in a soil foundation accurately shaped and rounded to conform to the lowest one-fourth of the outside portion of circular pipe or to the lower curved portion of pipe arch for the entire length of the pipe or pipe arch. When necessary, the bedding shall be tamped. Bell holes and depressions for joints shall be not more than the length, depth, and width required for properly making the particular type of joint.

C. Plastic Pipe

Page 109: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

STORM DRAINAGE SYSTEMS 02721-6

1. Bedding for PVC and PE pipe shall meet the requirements of ASTM D 2321. Bedding,

haunching, and initial backfill shall be either Class IB or II material. 3.3 PLACING PIPE

1. Each pipe shall be thoroughly examined before being laid; defective or damaged pipe shall not be used. Plastic pipe shall be protected from exposure to direct sunlight prior to lying, if necessary to maintain adequate pipe stiffness and meet installation deflection requirements. Pipelines shall be laid to the grades and alignment indicated. Proper facilities shall be provided for lowering sections of pipe into trenches. Lifting lugs in vertically elongated metal pipe shall be placed in the same vertical plane as the major axis of the pipe. Pipe shall not be laid in water, and pipe shall not be laid when trench conditions or weather are unsuitable for such work. Diversion of drainage or dewatering of trenches during construction shall be provided as necessary. Begin laying pipe at the down stream end, with the socket end upgrade.

2. Concrete, Clay, PVC, Ribbed PVC and Ductile Iron Pipe

3. Laying shall proceed upgrade with spigot ends of bell-and-spigot pipe and tongue ends of

tongue-and-groove pipe pointing in the direction of the flow.

3.4 JOINTING

A. Cement-Mortar Bell-and-Spigot Joint

1. The first pipe shall be bedded to the established gradeline, with the bell end placed upstream. The interior surface of the bell shall be thoroughly cleaned with a wet brush and the lower portion of the bell filled with mortar as required to bring inner surfaces of abutting pipes flush and even. The spigot end of each subsequent pipe shall be cleaned with a wet brush and uniformly matched into a bell so that sections are closely fitted. After each section is laid, the remainder of the joint shall be filled with mortar, and a bead shall be formed around the outside of the joint with sufficient additional mortar. If mortar is not sufficiently stiff to prevent appreciable slump before setting, the outside of the joint shall be wrapped or bandaged with cheesecloth to hold mortar in place.

B. Cement-Mortar Oakum Joint for Bell-and-Spigot Pipe

1. A closely twisted gasket shall be made of jute or oakum of the diameter required to support

the spigot end of the pipe at the proper grade and to make the joint concentric. Joint packing shall be in one piece of sufficient length to pass around the pipe and lap at top. This gasket shall be thoroughly saturated with neat cement grout. The bell of the pipe shall be thoroughly cleaned with a wet brush, and the gasket shall be laid in the bell for the lower third of the circumference and covered with mortar. The spigot of the pipe shall be thoroughly cleaned with a wet brush, inserted in the bell, and carefully driven home. A small amount of mortar shall be inserted in the annular space for the upper two-thirds of the circumference. The gasket shall be lapped at the top of the pipe and driven home in

Page 110: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

STORM DRAINAGE SYSTEMS 02721-7

the annular space with a caulking tool. The remainder of the annular space shall be filled completely with mortar and beveled at an angle of approximately 45 degrees with the outside of the bell. If mortar is not sufficiently stiff to prevent appreciable slump before setting, the outside of the joint thus made shall be wrapped with cheesecloth. Placing of this type of joint shall be kept at least five joints behind laying operations.

C. Cement-Mortar Diaper Joint for Bell-and-Spigot Pipe

1. The pipe shall be centered so that the annular space is uniform. The annular space shall

be caulked with jute or oakum. Before caulking, the inside of the bell and the outside of the spigot shall be cleaned.

a. Diaper Bands: Diaper bands shall consist of heavy cloth fabric to hold grout in

place at joints and shall be cut in lengths that extend one-eighth of the circumference of pipe above the spring line on one side of the pipe and up to the spring line on the other side of the pipe. Longitudinal edges of fabric bands shall be rolled and stitched around two pieces of wire. Width of fabric bands shall be such that after fabric has been securely stitched around both edges on wires, the wires will be uniformly spaced not less than 8 inches apart. Wires shall be cut into lengths to pass around pipe with sufficient extra length for the ends to be twisted at top of pipe to hold the band securely in place; bands shall be accurately centered around lower portion of joint.

b. Grout: Grout shall be poured between band and pipe from the high side of band

only, until grout rises to the top of band at the spring line of pipe, or as nearly so as possible, on the opposite side of pipe, to ensure a thorough sealing of joint around the portion of pipe covered by the band. Silt, slush, water, or polluted mortar grout forced up on the lower side shall be forced out by pouring, and removed.

c. Remainder of Joint: The remaining unfilled upper portion of the joint shall be

filled with mortar and a bead formed around the outside of this upper portion of the joint with a sufficient amount of additional mortar. The diaper shall be left in place. Placing of this type of joint shall be kept at least five joints behind actual laying of pipe. No backfilling around joints shall be done until joints have been fully inspected and approved.

D. Cement-Mortar Tongue-and-Groove Joint

1. Bedded carefully to the established gradeline with the groove upstream. A shallow excavation shall be made underneath the pipe at the joint and filled with mortar to provide a bed for the pipe. The grooved end of the first pipe shall be thoroughly cleaned with a wet brush, and a layer of soft mortar applied to the lower half of the groove. The tongue of the second pipe shall be cleaned with a wet brush; while in horizontal position, a layer of soft mortar shall be applied to the upper half of the tongue. The tongue end of the second pipe shall be inserted in the grooved end of the first pipe until mortar is squeezed out on interior

Page 111: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

STORM DRAINAGE SYSTEMS 02721-8

and exterior surfaces. Sufficient mortar shall be used to fill the joint completely and to form a bead on the outside.

E. Cement-Mortar Diaper Joint for Tongue-and-Groove Pipe

1. The joint shall be of the type described for cement-mortar tongue-and-groove joint in this

paragraph, except that the shallow excavation directly beneath the joint shall not be filled with mortar until after a gauze or cheesecloth band dipped in cement mortar has been wrapped around the outside of the joint. The cement-mortar bead at the joint shall be at least 1/2 inch, thick and the width of the diaper band shall be at least 8 inches. The diaper shall be left in place. Placing of this type of joint shall be kept at least five joints behind the actual laying of the pipe. Backfilling around the joints shall not be done until the joints have been fully inspected and approved.

F. Plastic Sealing Compound Joints for Tongue-and-Grooved Pipe

1. Sealing compounds shall follow the recommendation of the particular manufacturer in

regard to special installation requirements. Surfaces to receive lubricants, primers, or adhesives shall be dry and clean. Sealing compounds shall be affixed to the pipe not more than 3 hours prior to installation of the pipe, and shall be protected from the sun, blowing dust, and other deleterious agents at all times. Sealing compounds shall be inspected before installation of the pipe, and any loose or improperly affixed sealing compound shall be removed and replaced. The pipe shall be aligned with the previously installed pipe, and the joint pulled together. If, while making the joint with mastic-type sealant, a slight protrusion of the material is not visible along the entire inner and outer circumference of the joint when the joint is pulled up, the pipe shall be removed and the joint remade. After the joint is made, all inner protrusions shall be cut off flush with the inner surface of the pipe. If nonmastic-type sealant material is used, the "Squeeze-Out" requirement above will be waived.

G. Flexible Watertight Joints

1. Gaskets and jointing materials shall be as recommended by the particular manufacturer in

regard to use of lubricants, cements, adhesives, and other special installation requirements. Surfaces to receive lubricants, cements, or adhesives shall be clean and dry. Gaskets and jointing materials shall be affixed to the pipe not more than 24 hours prior to the installation of the pipe, and shall be protected from the sun, blowing dust, and other deleterious agents at all times. Gaskets and jointing materials shall be inspected before installing the pipe; any loose or improperly affixed gaskets and jointing materials shall be removed and replaced. The pipe shall be aligned with the previously installed pipe, and the joint pushed home. If, while the joint is being made the gasket becomes visibly dislocated the pipe shall be removed and the joint remade.

H. External Sealing Band Joint for Noncircular Pipe

1. Surfaces to receive sealing bands shall be dry and clean. Bands shall be installed in

accordance with manufacturer's recommendations.

Page 112: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

STORM DRAINAGE SYSTEMS 02721-9

3.5 DRAINAGE STRUCTURES

A. Manholes and Inlets

1. Construction shall be of reinforced concrete, plain concrete, brick, precast reinforced concrete, precast concrete segmental blocks, prefabricated corrugated metal, or bituminous coated corrugated metal; complete with frames and covers or gratings; and with fixed galvanized steel ladders where indicated. Pipe studs and junction chambers of prefabricated corrugated metal manholes shall be fully bituminous-coated and paved when the connecting branch lines are so treated. Pipe connections to concrete manholes and inlets shall be made with flexible, watertight connectors.

3.6 STEEL LADDER INSTALLATION

A. Ladder shall be adequately anchored to the wall by means of steel inserts spaced not more than 6 feet vertically, and shall be installed to provide at least 6 inches of space between the wall and the rungs. The wall along the line of the ladder shall be vertical for its entire length.

1. Ladder shall be in compliance with OSHA Standards.

END OF SECTION

Page 113: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

LANDSCAPING 02941-1

SECTION 02941

LANDSCAPING PART 1 - GENERAL 1.1 DESCRIPTION

A. The work specified in this section consists of furnishing and placing topsoil and hydro-seeding. 1.2 RELATED WORK

A. Section 02300 - Excavation, Backfill, and Compaction. 1.3 REFERENCE STANDARDS

A. Commonwealth of Pennsylvania, Department of Transportation (PADOT) Specifications, Publication 408, and it Supplements.

PART 2 - PRODUCTS 2.1 TOPSOIL

A. In accordance with PaDOT Specifications, Publication 408, Subsection 801.2. 2.2 SEEDING

A. In accordance with PaDOT Specifications, Publication 408, Subsection 804.2(b) Formula B

seedings (see Table A).

2.3 MULCHING

A. In accordance with PaDOT Specifications, Publication 408, Subsection 805.2 "Material". 2.4 SUPPLEMENTS

A. In accordance with PaDOT Specifications, Publication 408, Subsection 804.2(a) “Soil Supplements".

2.5 ORGANIC TACKIFIER

A. Tackifier shall be organic and consist of one of the following:

1. Guar a. A guar gum based product derived from the ground endosperm of the guar plant,

cyanmopsis tetragonolobus b. Treated with dispersant agents for easy mixing c. Able to be diluted at the rate of 1 to 5 pounds per 100 gallons of water.

Page 114: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

LANDSCAPING 02941-2

2. Psyllium a. Made of the finely ground muciloid coating of plantago ovata or

plantago ispaghula seeds b. Able to dry and form a firm but rewettable membrane

3. Startch a. A non-ionic, water-soluble granular material derived from corn, potato, or other plant-

based source.

B. Tackifier must comply with the following: 1. Nonflammable 2. Nontoxic to the environment 3. free from growth or germination inhibiting factors 4. A natural high molecular weight polysaccharide 5. A high viscosity hydrocolloid is miscible in water 6. Functional for at least 180 days

2.6 COLORING AGENT

A. Coloring agent shall be bio-degradable, nontoxic, and free from copper, mercury, and arsenic. 1. Color: Green

PART 3 - EXECUTION 3.1 PRELIMINARY WORK

A. Grade the areas to be covered by topsoil, using acceptable methods:

1. Loosen existing soil to a depth of 12 inches before placing the topsoil. 2. Remove stones and other foreign material 2 inches or larger in any dimension. 3. Remove and satisfactorily dispose of unsuitable and surplus material.

3.2 PLACEMENT - TOPSOIL

A. Place topsoil on the prepared areas and spread and compact to a 6-inch uniform depth, unless otherwise indicated. Compact with a roller, one weighing not over 65 pounds per foot width of roller or by other acceptable methods, as directed. Remove over depth topsoil, unless otherwise agreed upon in writing. Do not place topsoil in a wet or frozen condition.

3.3 HYDRO-SEEDING

A. Application Rates:

1. Cellulose Fiber Mulch: Apply at a minimum rate of 1500 lbs./acre

2. Organic tackifier shall be applied at rate of 70 lbs/acre

3. Apply seeded slurry with a hydraulic seeder at a rate of 24 lbs per 1000 sq ft evenly in two intersecting directions.

Page 115: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

LANDSCAPING 02941-3

4. Equipment shall have a built in agitation and operating capacity sufficient to agitate, suspend,

and homogeneously mix slurry containing not less than 44lbs of organic mulching amendments plus fertilizer, chemical additives and solids for each 100 gallons of water.

B. Water all plant areas thoroughly to saturate upper layers of soil prior to the hydro-seeding operation. C. Allow the planting areas soil surface to dry out for one day prior to the hydro-seeding application.

Exercise care not to allow the soil surface to be overly saturated with water prior to hydro-seeding installation. At the same time the soil surface should not become too dry during this period. There should be some residual moisture within the first ¼ inch of the soil surface.

D. Do not hydro-seed area in excess of that which can be mulched on same day.

E. Apply the hydro-seeding in the form of a slurry consisting of organic soil amendments, commercial

fertilizer, coloring agent, and any other chemicals that are specified. When hydraulically sprayed onto the soil, the mulch shall form a blotter-like material. Direct the spray operation so that his procedure will drill and mix the slurry components into the soil, the slurry spray will also penetrate the soil surface, thus ensuring maximum impregnation and coverage. The impregnation and mixing of the components will help in retaining moisture while stabilizing soil surface from superficial erosion.

F. Do not allow the hydro-seeding slurry components in the hydro-seeding machine for more than two (2)

hours because of possible seed destruction. If slurry components are left for more than two hours in the machine, add 50% more of the originally specified seed mix to any slurry mixture which has not been applied within the two hours after mixing. Add 75% more of the original seed mix to any slurry mixture which has not been applied eight (8) hour after mixing. All mixtures more than eight (8) hours old must be disposed, off-site, at the contractor’s expense.

G. Spray the area with a uniform visible coat, using the coloring agent as a visual guide. The slurry shall

be applied in a downward drilling motion via a fan stream nozzle. Insure that all of the slurry components enter and mix with the soil. Insure the uniformity of the hydro-seed application.

H. Exercise special care to prevent any of the slurry from being sprayed onto any hardscape areas

including concrete walks, fences, walls, buildings, etc. Remove all slurry sprayed onto these surfaces at the contractor’s expense.

END OF SECTION

Page 116: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CONCRETE FORMWORK 03100-1

SECTION 03100

CONCRETE FORMWORK PART 1 - GENERAL 1.1 DESCRIPTION

A. The work specified in this Section consists of furnishing materials for erecting and removing formwork and accessories for the construction of curb, sidewalks, islands, and stairs.

1.2 QUALITY ASSURANCE

A. Design Criteria: 1. It is the Contractor's responsibility for design, engineering and construction of formwork. 2. Design formwork in accordance with American Concrete Institute's "Recommended

Practice for Concrete Formwork" ACI 347.

B. Allowable Tolerances: Set and maintain concrete forms within tolerance limits stated in American Concrete Institute's "Recommended Practice for Concrete Formwork" ACI 347.

C. Referenced Standards:

1. American Concrete Institute ACI 347, Recommended Practice for Concrete Formwork. 2. American Plywood Association: APA Grade - Trademarks. 3. U.S. Department of Commerce Product Standards: PS-1-74 for Construction and

Industrial Plywood. 4. Western Wood Products Association: WWPA Catalog "A" Product Use Manual.

1.2 JOB CONDITIONS

A. Protection: 1. Protect formwork materials before, during, and after erection to insure acceptable finished

concrete work. Also protect in-place materials and other operations of work in connection with concrete pours.

2. In the event of damage to erected forms, make necessary repairs or replacements prior to concrete pours at no expense to SEPTA.

PART 2 - PRODUCTS 2.1 MATERIALS

1. Lumber: 1. Use lumber free of material defects that would deform the finished concrete product.

2. Plywood:

1. Form Sheathing and Panels: Not less than 5/8 inch thick Exterior Type B-B Plywood Class I and II EXT-APA conforming to U.S. Product Standard PS-1-74.

2. Use Type II only on surfaces not exposed to view.

Page 117: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CONCRETE FORMWORK 03100-2

3. Steel:

1. Sheet: Commercial Grade, not thiner than 16 gauge. 2. Structural Shapes: ASTM A36

4. Applicable Forms: 1. Forms for curbs shall be acceptable standard metal batter or straight face. Wood forms

may be used on sharp curves and short tangent sections. Use forms which will not discolor the concrete.

2. Forms for sidewalk shall be 2” x 4” wood or metal. 3. Forms for lighting foundsations shall be tubes.

5. Form Coatings: 1. Provide commercial formulation form-coating compounds that will not bond with, stain, nor

affect concrete surfaces, and will not impair subsequent treatment of concrete surfaces requiring bond or adhesion, nor impede the wetting of surfaces to be cured with water or curing compounds.

PART 3 - EXECUTION 3.1 INSPECTION

A. Prior to placement of concrete, inspect forms for cleanliness and accuracy of alignment. Remove all foreign material or debris.

3.2 PREPARATION

A. Apply form coatings in accordance with manufacturer's specifications. B. Do not allow excess form coating material to accumulate in the forms.

C. Do not allow form coatings to come in contact with construction joints or reinforcing steel.

3.3 ERECTION

A. Construct forms in accordance with ACI 347 to required dimensions, plumb, straight and mortar tight, and paste tight where appearance is important. Securely brace and shore forms to prevent displacement and to safely support imposed concrete load. Design bracing and shoring where required and furnish calculations to Project Manager.

B. Set forms for concrete sidewalk to the following grade and alignment tolerances:

1. Grade: Plus or minus 1/8 inch. 2. Alignment: Plus or minus 1/4 inch at any point and no more than 1/8 inch deviation from a

10 foot straight edge.

C. Accurately place and securely support items to be built into forms.

D. Wet forms sufficiently to prevent joints in wood forms from opening prior to concrete pour.

Page 118: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CONCRETE FORMWORK 03100-3

3.4 FORM REMOVAL

A. Remove forms in accordance with ACI 347 without damage to concrete and in a manner to insure complete safety to the structure.

B. Upon removal of forms, notify the Project Manager in order that a review of the newly stripped

surfaces may be made before patching and possible rub-up.

3.5 RE-USE OF FORMS

A. Forms for re-use shall meet new form requirements with respect to affect on poured concrete appearances and structural stability

END OF SECTION

Page 119: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CAST IN PLACE CONCRETE 03300-1

SECTION 03300

CAST-IN-PLACE CONCRETE PART 1 - GENERAL 1.1 DESCRIPTION

A. The work specified in this Section consists of furnishing, detailing, delivery, and erecting all materials for the construction of concrete curbs, stairs, islands, and sidewalks.

B. Related work specified elsewhere:

1. Section 02533 - Plain Cement Concrete Pavement 2. Section 02534 - Poured Concrete Curbs 3. Section 03100 - Concrete Formwork

1.2 QUALITY ASSURANCE

A. Design Criteria: B. It is the Contractor's responsibility for design, engineering and construction of formwork. C. Design formwork in accordance with American Concrete Institute's "Recommended Practice for

Concrete Formwork" ACI 347.

D. Allowable Tolerances: Set and maintain concrete forms within tolerance limits stated in American Concrete Institute's "Recommended Practice for Concrete Formwork" ACI 347.

E. Referenced Standards:

5. American Concrete Institute ACI 347, Recommended Practice for Concrete Formwork. 6. American Plywood Association: APA Grade - Trademarks. 7. U.S. Department of Commerce Product Standards: PS-1-74 for Construction and

Industrial Plywood. 8. Western Wood Products Association: WWPA Catalog "A" Product Use Manual.

F. The Project Manager will have the authority to inspect concrete supplier's plant and will have the authority to inspect delivery trucks to verify that plant conforms to the "Check List of Certification of Ready Mix Concrete Production Facilities” published by the national Ready Mix concrete Association, and delivery trucks conform to requirements specified in ASTM C 94.

G. All concrete mixes will meet the requirements of existing plant standard PADOT mixes and in

accordance with sub-section 704.1(c), PADOT Specifications Pub. 408. 1.3 REFERENCES

A. PADOT Publication 408, Section 704. B. ACI Standards C. American Concrete Institute ACI 347, Recommended Practice for Concrete Formwork. D. American Plywood Association: APA Grade - Trademarks.

Page 120: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CAST IN PLACE CONCRETE 03300-2

E. U.S. Department of Commerce Product Standards: PS-1-74 for Construction and Industrial Plywood.

F. Western Wood Products Association: WWPA Catalog "A" Product Use Manual. G. American Concrete Institute (ACI). H. ACI 315, Manual for Standard Practice for Detailing Reinforced Concrete Structures. I. ACI 318 - Building Code Requirements for Reinforced Concrete. J. ACI 117 – Standard Specifications for Tolerances for Concrete Construction and Materials K. ACI SP-66 – ACI Detailing Manual L. Concrete Reinforcing Steel Institute (CRSI), Manual of Standard Practice.

PART 2 - PRODUCTS 2.1 REINFORCEMENT MATERIALS

A. Reinforcing Steel Bars: ASTM A615-S1, Grade 60, deformed billet steel bars.

1. Galvanized Coating: ASTM A123 and ASTM A767 2. Epoxy Coated: ASTM A775 (where specified)

B. Welded Wire Fabric: ASTM A497.

1. Galvanized Coating: ASTM A123 and ASTM A767.

C. Steel Wire: ASTM A82, epoxy coated or galvanized, cold drawn steel; use for securing reinforcing bars

and embedded items.

D. Supports for Reinforcement: Provide supports for reinforcement including bolsters, chairs, spacers and other devices for spacing, supporting and fastening reinforcing bars and welded wire fabric in place. Use wire bar type supports complying with CRSI recommendations, unless otherwise approved.

1. For slabs-on-grade, use supports with sand plates or horizontal runners where base material

will not support chair legs. 2. Provide support reinforcing bars and welded wire fabric in position by means of accepted

spacers, chairs or hangers. 3. Furnish sufficient number of supports and of strength to withstand deflection of reinforcement

from indicated cross sectional position. Do not place reinforcing bars more than two inches beyond the last leg of any continuous bar support.

2.2 CONCRETE MATERIALS

A. All concrete materials shall conform to PADOT Publication 408, Section 704.

2.3 CURING MATERIALS

A. Use curing materials that will not stain or affect concrete finish or lessen the concrete strength and comply with the following requirements:

1. Burlap: Use materials conforming to AASHTO M182.

Page 121: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CAST IN PLACE CONCRETE 03300-3

2. Sheet Materials: Use materials conforming to ASTM C171. 3. Other materials may be used subject to approval of the Project Manager.

2.4 CONCRETE ADMIXTURES

A. Use concrete admixtures in conformance to sub-section 711.3, PADOT Specifications Pub. 408. 2.5 JOINT SEALER

A. Use joint sealer conforming to sub-section 705.4(b) or (c), PADOT, Specifications Pub. 408. PART 3 - EXECUTION 3.1 CONCRETE REINFORCEMENT

A. INSPECTION 1. The fabricator shall inspect and provide signed inspection checklists for each shipment of

reinforcement verify conformance with the specifications, approved placing drawings, tolerances, and proper labeling.

B. INSTALLATION

1. Arrange and place reinforcement as indicated on the plans.

2. Positively secure reinforcement against displacement during placement of concrete.

3. Wire or clip bars together in accordance with ACI recommendations.

4. Accurately position reinforcement, including stirrups, to a clear coverage for concrete protection, measured from outside of bar to surface of concrete, as indicated on the Drawings.

5. Do not place reinforcement continuous through expansion (isolation) and doweled joints.

Reinforcement shall be continuous through construction joints.

6. Place and secure reinforcement bars and welded wire fabric in position by means of accepted spacers, supports, chairs, runners, standees, bolsters or hangers as required.

7. Repair of Epoxy Coating: Repair damage to epoxy coating either as described in ASTM

D3963, Section 11.1 or by mechanical wire brush cleaning and painting with an approved epoxy paint using the paint manufacturer's approved procedure. Repair any reinforcement with visible signs of rust. Repair of damaged epoxy coating of more than five percent of the total reinforcement surface area will not be allowed.

C. SUPPORTS AND SPACERS FOR REINFORCEMENT

1. Support reinforcing bars in position by means of accepted spacers, chairs or hangers.

Page 122: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CAST IN PLACE CONCRETE 03300-4

2. Install sufficient number of supports and of strength to withstand deflection of reinforcement from indicated cross sectional position. Do not place reinforcing bars more than two inches beyond the last leg of any continuous bar support. Do not use supports as bases for runways for concrete conveying equipment and similar construction loads.

3. Support reinforcing steel located in bottom of slabs resting on earth, on precast concrete

mortar blocks of proper size and dimensions to position and support steel.

4. Do not use stones, brick, wood blocks or pieces of broken concrete to support reinforcing steel.

3.2 MIXING CONCRETE

A. Transit mix the concrete in accordance with provisions of ASTM C94.

B. Do not use concrete that has stood for over 30 minutes after leaving the mixer, or concrete that is not placed within 60 minutes after water is first introduced into the mix.

3.3 PLACING CONCRETE

A. Preparation: 1. Remove foreign matter accumulated in the forms. 2. Rigidly close openings left in the framework. 3. Wet wood forms sufficiently to tighten up cracks. Wet other material sufficiently to

maintain workability of the concrete. 4. Use only clean tools.

B. Conveying:

1. Perform concrete placing at such a rate that concrete which is being integrated with fresh concrete is still plastic.

2. Deposit concrete as nearly as practicable in its final location so as to avoid separation due to re-handling and flowing.

3. Do not use concrete which becomes non-plastic and unworkable, or does not meet required quality control limits, or has been contaminated by foreign materials.

4. Remove rejected concrete from the job site.

C. Placing Concrete in Forms: 1. Deposit concrete in horizontal layers not deeper than 18", and avoid inclined construction

joints. 2. Remove temporary spreaders in forms when concrete has reached the elevation of the

spreaders. 3. Deposit concrete as near as possible to final position. Do not drop concrete more than

three feet.

D. Cold Weather Concreting: 1. Temperature of concrete delivered at the job-site shall conform to the following

temperature limitations:

Page 123: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CAST IN PLACE CONCRETE 03300-5

Minimum Concrete Temperature, (Degrees F.)

Air Temperature Degrees F.

For Sections with Least Dimension <

12 in.

For Sections with Least

Dimension 12 in or Greater

30 to 45 60 50 0 to 30 65 55

2. If water or aggregate is heated above 100 degrees F, combine water with aggregate in the

mixer before cement is added. Do not mix with water or with mixtures of water and aggregate having a temperature greater than 100 degrees F.

3. Provide equipment for heating concrete materials and protecting concrete during freezing or near-freezing weather. Do not use foreign materials or materials containing snow or ice.

4. Surfaces which the concrete is to come in contact with must be free of frost, snow and ice. 5. Concrete placed in forms shall have a temperature of 50 degrees F. or higher after

placement. Maintain this temperature a minimum of 5 days. Provide additional time if necessary for proper curing.

6. Housing, covering or other protection used in curing shall remain intact at least 24 hours after artificial heating is discontinued. Do not place dependence on salt or other chemicals for the prevention of freezing.

7. Perform cold weather concreting work in accordance with ACI 306R.

E. Hot Weather Concreting: 1. Temperature of concrete delivered at the job-site shall not exceed 90 degrees F. 2. Cool ingredients before mixing to prevent temperature in excess of 90 degrees F. 3. Make provisions for windbreaks, shading, fog spraying, sprinkling, or wet cover when

necessary. 4. Perform hot weather concreting work in accordance with ACI 305R.

3.4 CONSOLIDATION

A. General: 1. Consolidate each layer of concrete immediately after placing, by use of internal concrete

vibrators supplemented by hand spading, roofing, or tamping. 2. Do not vibrate forms or reinforcement. 3. Do not use vibrators to transport concrete inside the forms. 4. Use vibration equipment of internal type and not the type attached to forms and

reinforcement. 3.5 DEFECTIVE CONCRETE WORK

A. Porous areas, open or porous construction joints and honeycombed concrete will be considered to indicate that the requirements for mixing, placing and handling have not been complied with and will be sufficient cause for rejection of the Work.

B. Defective work exposed upon removal of forms shall be entirely removed or repaired within forty-

eight hours after forms have been removed.

Page 124: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CAST IN PLACE CONCRETE 03300-6

3.6 REPAIR OF DEFECTIVE CONCRETE

A. General: The Project Manager will determine the extent and manner of action to be taken for the correction of defective concrete as may be revealed by surface defects or otherwise.

3.7 CONCRETE FINISHING

A. Finishes: Finish exposed concrete surfaces true and even, free from open or rough area, depressions or projections. Bring concrete up in vertical pours to the required elevation, strike-off with a straight edge and float-finish.

1. Floated Finish: After concrete has been place, consolidated, struck off and leveled, do not work further until ready for floating. Begin floating when water sheen has disappeared and when the surface has stiffened sufficiently to permit the operation. During or after first floating, check plainness of surface with a 10-ft straightedge applied at not less than two different angles. Cut down high spots and fill low spots during this procedure to produce a surface with true planes within 3/16 inch in 10 ft. as determined by a 10-ft. straightedge placed anywhere on the slab in any direction. Following straightedge checking, re-float slab immediately to uniform sandy texture.

2. Flat Trowel Finish: Obtained by hand or power trowelling a "Floated Finish" with a single trowelling. This trowelling (first after power floating) shall produce a smooth surface which is relatively free of defects but which may still show some trowel marks.

3. Broom or Belt Finish: Immediately after concrete has received a "Floated Finish", give surface a coarse transverse scored texture by drawing a broom or burlap belt across the surface.

B. Application for Finishes:

1. Floated Finish: a) Surfaces to receive "Flat Trowel Finish". b) Surfaces to receive "Broom or Belt Finish".

2. Flat Trowel Finish: Curbs. 3. Broom or Belt Finish: Sidewalks.

3.8 FIELD QUALITY CONTROL

A. Testing Services: 1. During the entire period when concrete is being placed, provide testing services by an

independent testing laboratory as specified in Article 1.04.C. 2. Make tests in accordance with the requirements of the applicable ASTM Specifications.

B. Identification: Identify each test by number, mix, amount of admixture, origin of sample in the

project, the date test specimens was made, the date test specimen was tested, the amount slump determined, and the compressive strength test results.

C. Reports:

1. The Testing Laboratory shall prepare and submit all reports required in the various standards and specification reference herein.

2. Distribution of reports shall be:

Page 125: STANDARD BLANKET PAVING AND SITEWORK …...STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015 SUMMARY OF WORK 01010-3 1.5 RESPONSIBILITY OF CONTRACTOR A. The Contractor shall

STANDARD BLANKET PAVING AND SITEWORK SPECIFICATION May 2015

CAST IN PLACE CONCRETE 03300-7

3. Two copies to the Project Manager. 4. One or more copies, as required, to the Contractor. 5. The distribution of all copies shall be indicated on all copies.

D. The Testing Laboratory shall immediately notify the Contractor and the Project Manager of any test

results which do not conform to Specification requirements.

E. Concrete Sampling and Testing: 1. Furnish molds and concrete required for casting specimens and for the specified sampling

and testing. 2. Prepare one set of molds conforming to ASTM C470, in accordance with ASTM C172 for

each 20 cubic yards, or fraction thereof, or each days placing activity whichever is less for each class of concrete placed.

F. Tests: Sample during the placement of concrete according to ASTM C31, ASTM C42, and ASTM

C172 and test according to the following: 1. Slump: ASTM C143; one test for each concrete load at point of discharge or as required

and one test for each set of compressive strength test specimens. 2. Mixes with Chemical Additives: ASTM C494 and as required by the Project Manager. 3. Uniformity Tests: Perform uniformity tests required by ASTM C94 from time to time, as

required to demonstrate to the Project Manager that mixing and delivery equipment is delivering concrete conforming to Appendix XI of ASTM C94. Uniformity of concrete shall be considered as being attained when not less than 5 of the 6 requirements shown in Table XI of ASTM Appendix XI have been met.

4. Compressive strength tests: Test the specimens in accordance with ASTM C39 for the strength required by ASTM C94, Section 16; one set of 4 cylinders for each 20 cubic yards, or fraction thereof in any one day; one specimen tested at seven days, and three specimens tested in 28 days.

3.09 REMEDIAL WORK

A. Repair or replace deficient work as directed by the Project Manager and at no additional cost to SEPTA.

3.10 BACKFILLING

A. Backfill after concrete has properly cured for seven days and has attained 75 percent of its 28 day compressive strength.

B. Backfill in accordance with PADOT Publication 408, Section 206.3(b).

END OF SECTION