Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

Embed Size (px)

Citation preview

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    1/114

    2 5 E ITION

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    2/114

      ontents

    P GE P GE

    Articles of Agreement 5

    5 5 Nominated Supply Contract

    documents

    Attestation

    8 5 6

    Further drawings, details,

    descriptive schedules and similar

    The

    General

    Conditions

    documents

    5 7

    Documents

    to

    be provided to

    1 Interpretation and definitions 9

    Contractor on time

    5 8

    Electronic copies

    of

    drawings

    1 1

    Governing law·

    5 9 Documents on Site

    1 2

    Singular, plural, masculine and

    5 10

    Return

    of

    drawings

    feminine

    5 11

    Submission

    of

    manuals and

    1 3

    Method of reference to clauses and assignment of warranties

    Articles 5 12 Submission

    of

    as-built drawings

    1 4 Articles of Agreement, Conditions 5 13 Limits to use of documents

    and Appendix to be read as a whole

    5 14 Issue

    of

    Architect s certificates

    1 5

    Clauses divided into sub-clauses to

    5 15 Copy of notice to be given

    be read as a whole

    to Employer

    1 6 Definitions

    1 7 The role of the Engineer

    6

    Statutory obligations

    24

    1 8

    Sectional completion

    of

    the Works

    1 9

    Communications

    6 1 Statutory Requirements

    1 10

    Notices of default or determination

    6 2

    Compliance with the Statutory

    to be sent by special delivery

    Requirements

    1 11 Parties to act reasonably and 6 3 Fees or charges

    expeditiously

    6 4

    Statutory undertakers and utility

    companies

    2

    Contractor s obligations

    16

    7

    Setting

    out the Works

    25

    2 1

    Contractor s obligations

    2 2

    Contractor s responsibility Setting out and levels

    2 3

    Contractor s skill and care

    2 4

    Contractor to inform Architect if

    8

    Materials, goods,

    workmanship

    he finds ambiguities

    n

    documents

    and work

    25

    3

    Master

    programme

    17

    8 1 Types, standards and quality

    8 2

    Inspection and tests

    3 1

    Master programme to be submitted

    8 3

    Materials, goods, workmanship

    3 2

    Programmes to be updated or work not in accordance with

    3 3

    Programme and other documents

    Contract

    not to be documents forming

    8 4

    Rectifying defects

    the Contract

    8 5

    Dismissal from the Works

    4

    Architect s

    instructions

    19

    9

    Intellectual property rights

    27

    4 1

    Architect may issue instructions up to 9 1

    Intellectual property n design

    of

    the

    the issue of the Final Certif icate Works

    4 2

    Architect to issue instructions n writing 9 2

    Intellectual property n materials and

    4 3

    Compliance with Architect s goods

    instructions

    9 3

    Intellectual property in plant and

    4 4

    Contractor to carry out preventative equipment

    work 9 4

    Payment

    of

    royalties included n

    Valuation

    5

    Documents

    forming the Contract

    and other documents

    2

    1

    Contractor s site management team

    27

    5 1

    The documents forming the Contract 10 1 Contractor s site management team

    5 2

    Architect and Quantity Surveyor to 10 2 Construction manager

    keep documents available

    5 3

    Copies of documents for 11

    Access

    for

    the

    Architect

    to the

    Contractor

    Works

    28

    5 4

    Nominated Sub-Contract

    documents

    Contractor to give access

    1

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    3/114

    P GE

    12 Architect s representative

    28

    12 1 Architect s representative

    12.2 Delegation of duties and powers

    12.3

    Instruction to bind parties

    13

    Variations, Provisional Quantities,

    Provisional

    Items and Provisional

    Sums 29

    13 1

    Architect s authority to issue

    instructions requiring a Variation

    13.2

    Instructions for Provisional Quantities,

    Provisional Items and Provisional

    Sums

    13.3 Valuation

    of

    Contractor s work

    13.4 Valuation rules

    13.5 Adjustment of Contract Sum

    13.6 Contractor s right to be present during

    measurement on Site

    13.7 Variation necessitated by fault

    of

    Contractor

    13.8 Valuation of Nominated Sub-

    Contractor s work or Nominated

    Supplier s materials and goods

    14

    Contract

    Bills

    33

    14 1 Quality and quantity of work included

    in Contract Sum

    14.2 Standard Method

    of

    Measurement

    of

    Building Works

    14.3 Errors in Contract Bills

    15

    Contract

    Sum

    34

    Adjustment

    of

    Contract Sum

    16 Materials

    and goods

    on or

    off-site

    34

    Property in materials and goods

    17 Substantial

    Completion and

    defects liability

    34

    17 1

    Substantial Completion Certificate

    for the Works

    17.2

    Separate Defects Liability Period for

    each Section and Relevant Part

    17.3

    Rectifying defects

    17.4

    Defects Rectification Certificate for

    the Works

    17.5

    Separate certificate for each Section

    or Relevant Part

    17.6

    Damage by a Specified Peril

    17.7 Other rights and remedies

    18 Partial possession by Employer 36

    18 1 Part·lal possession

    18.2 Substantial Completion

    18.3 Completion of rectifying defects

    P GE

    18.4

    Liquidated and ascertained damages

    18.5 Damage by a Special Peril

    19

    Assignment and sub-letting

    37

    19 1

    Assignment

    19.2 Sub-letting

    i

    2

    Injury

    to

    persons

    and

    property and

    indemnity

    to

    Employer

    38

    Contractor to indemnify Employer

    21

    Insurance against injury

    to persons

    or

    property 39

    21 1

    Employees Compensation Insurance

    21.2

    Third party liability insurance

    21.3 Insurers and terms to be approved

    21.4

    Policies to be produced

    21.5 Event

    of

    failure

    to

    insure

    21.6

    No prejudice to Contractor s indemnity

    22

    Insurance of the

    Works

    40

    22 1

    Alternative clauses

    for

    Contractors

    All Risks Insurance

    of

    the Works

    22.2

    Basic requirements

    for

    Contractors

    All Risks Insurance of the Works

    22.3

    Specific requirements for Contractors

    All Risks Insurance

    of

    the Works

    22.4

    Insurance

    of

    the Works to be in

    joint

    names and period

    of

    insurances

    22.5

    Parties obligations if loss or

    damage

    o urs

    22.6

    Contractor s payment not more than

    insurance proceeds

    22.7

    Insurance without prejudice to

    Contractor s obligations

    22A

    Insurance of the Works by

    the

    Contractor

    43

    22A 1

    Contractor to effect Contractors All

    Risks Insurance of the Works

    22A.2 Insurer to be approved and remedy

    if Contractor fails to insure

    22A.3 Use

    of

    annual policy maintained by

    Contractor

    228

    Insurance of

    the Works by the

    Employer

    44

    22B 1 Employer to effect Contractors

    All Risks Insurance of the Works

    22B.2 Remedy if Employer fails to insure

    22C

    Insurance of existing building

    and

    insurance

    of

    the

    Works

    by the

    Employer

    44

    22C 1

    Employer to effect insurance against

    Specified Perils to the existing building

    r

    I

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    4/114

    P GE

    P GE

    22C.2 Employer to

    effe t

    Contractors

    29

    Nominated Sub Contractors and

    All Risks Insurance

    of

    the Works Nominated Suppliers

    57

    22C.3 Remedy if Employer fails to insure

    29 1

    Nomination of a sub-contractor or a

    23

    Possession, commencement

    and

    supplier

    completion 45 29.2 Contractor s right of reasonable

    objection

    23 1 Posse:;sion of Site

    29.3 Sub-contractor and supplier

    w2:1Tanty

    23.2 Commencement and completion

    to

    Employer

    23.3

    Postponement

    or

    suspension 29.4 Contractor s tender

    for

    work provided

    for by

    a Prime Cost Sum

    24

    Damages for non completion

    45

    29.5 Nomination using the standard

    conditions

    24 1

    Architect to certify Contractor s failure 29.6 Contractor s responsibility for

    to complete on time Nominated Sub-Contractors and

    24.2 Liquidated and ascertained damages Nominated Suppliers

    24.3

    Refund if Completion Date revised

    29.7

    Quantity Surveyor s notification of

    interim payments

    ? )

    Extension

    of

    time

    46 29.8 Direct payment

    of

    Nominated Sub-

    Contractors and Nominated Suppliers

    25 1 Contractor s first notice of delay 29.9

    Extension of time for completion

    25.2

    Contractor s second notice of Nominated Sub-Contract works or

    25.3 Fixing new Completion Date delivery of Nominated Supply

    25.4

    Contractor s default involved in the

    Contract goods

    delay 29.10 Substantial completion of Nominated

    25.5 Rate of progress Sub-Contract works

    25.6

    Nominated Sub-Contractors and 29.11 Architect to certify Nominated Sub-

    Suppliers to be

    kept informed Contractor s failure

    to

    complete on

    time

    26

    Delay

    recovery measures

    51 29.12 Early final payment to Nominated

    Sub-Contractor or Nominated

    26 1

    Delay recovery measures Supplier

    26.2 Delay recovery proposals

    29.13 Re-nomination

    26.3 Contractor

    to

    carry out delay recovery 29.14 Architect s consent

    me sures

    29.15 Employer not liable to a Nominated

    26.4 Extension

    of

    time to cover shortfall in Sub-Contractor or Nominated

    recovering delay

    Supplier

    26.5 Contractor to be reimbursed for the

    cost of preparing the proposal if delay 3 Persons engaged

    by

    Employer

    63

    recovery not instructed

    30 1 Persons

    for

    whom the Employer

    is

    27 Direct loss and/or expense 53

    responsible

    30.2 Access to Site and permission to

    27 1

    Contractor s not ice of claim for

    carry out work

    additional payment 30.3 Contractor to fulfil his obligations to

    27.2 Quantity Surveyor s ascertainment

    of

    persons engaged by the Employer

    Contractor s claim

    27.3 Contractor s defaul t involved

    in

    the

    31 Facilities

    for

    statutory undertakers

    delay

    or

    disruption

    and

    utility

    companies

    64

    27.4

    Nominated Sub-Contractor s claim

    for additional payment

    Access to Site and facilities to canry

    out work

    28

    Notice

    of claims for

    additional

    payment 55

    32

    Certificates

    and payments

    64

    28 1 Contractor to give notice of claim

    32 1 Interim Certificates and interim

    28.2 Contractor to submit particulars

    valuations

    28.3

    Condition precedent to Contractor s

    32.2 Estimate

    of

    amount due in Interim

    entitlement to additional payment Certificate

    32.3

    Off-site materials or goods

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    5/114

    P GE P GE

    32.4 Calculation

    of

    Retention

    37.4 Quantity Surveyor to prepare final

    32.5 Retention Rules

    account

    32.6 Quant ity Surveyor to prepare final 37.5 The final settlement

    account

    37.6

    Architect to notify sub-contractors

    32.7

    Adjustment

    of

    the Contract Sum and suppliers

    32.8 Issue

    of

    Final Certificate

    32.9 Effect

    of

    Final Certificate

    38

    Fluctuations 84

    32.10 Proceedings commenced before

    Final Certificate 38 1 Fluctuation provisions only applicable

    32 11 Proceedings commenced after Final if expressly stated to be

    Certificate 38.2 Adjustment for fluctuations occurring

    32.12 Effect

    of

    Architect s certificates

    after the Completion Date

    32.13 Late payment

    39

    Notices certificates and other

    Surety Bond 73 communications

    85

    33 1

    Contractor to obtain guarantee from Submission of notices, certificates and

    insurance company or bank other communications

    33.2 Release

    of

    insurance company or

    bank

    4

    Recovery of money due to the

    33.3 Employer s remedy

    if

    Contractor fails

    Employer 85

    to deliver bond

    Employer s power to recover damages

    34

    Antiquities

    73

    . etc.

    34 1 Effect

    of

    finding antiquities

    4 Settlement

    of

    dispu1es 85

    34.2

    Architect s instructions concerning a

    fossil, antiquity or object

    41 1

    Procedures and Designated

    Representatives

    35 Detenmination by Employer 74 41.2 Reference to Designated

    Representatives

    35 1 Default by Contractor

    41.3 Reference to mediation

    35.2 Insolvency

    of

    Contractor 41.4 Reference

    to

    arbitration

    35.3 Employer s rights upon notice

    of

    41.5

    Timing of arbitration

    default or determination

    41.6 Arbitrator s powers

    35.4 Consequences of determination 41.7 The place

    of

    arbitration

    35.5 Quanti ty Surveyor to prepare final

    41.8 Contractor to continue to proceed

    account diligently

    35.6 The final settlement

    35.7 Delayed commencement

    of

    Appendix

    89

    completion works Schedule 1

    90

    35.8 Other rights and remedies

    Form

    of

    Surety Bond

    to

    be given y

    the Contractor to the Employer

    6

    Determination by Contractor

    78

    Schedule

    94

    36 1

    Default by Employer Form

    of

    Warranty to be given by

    the

    36.2 Insolvency of Employer

    Nominated Sub-Contractor to the

    36.3 Consequences

    of determination Employer in consideration of

    36.4 Contractor to submit final account Nomination

    36.5 Quant ity Surveyor to check final

    account

    Schedule 3

    97

    36.6 The final settlement Form

    of

    Warranty to be given y the

    36.7 Architect to notify sub-contractors Nominated Supplier to the Employer

    and suppliers in consideration

    of

    Nomination

    36.8 Other rights and remedies

    Index to The General Conditions

    7

    Detenmination by Employer or

    Contractor

    82

    37 1

    Grounds for determination

    37.2 Site security

    37.3 Consequences of determination

    4

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    6/114

      rticles of greement

    This greement

    is made on the ................................ day of .......................... ...... 20 ..... .

    between

    of

    ......................................................................................................................................................

    ( the Employer ) and

    r

    ····················································································································································

    ( the Contractor )

    Whereas the Employer wishes to have work carried

    out

    comprising:

    ( the Works )

    at

    ......................................................................................................................................................

    and has had Tender Documents comprising:

    a)

    a form

    of

    tender ( The Form of Tender );

    b) drawings ( the Contract Drawings );

    c)

    a specification ( the Specification ); and

    d) bills

    of

    quantities

    showing and describing the work to be carried out prepared by

    or

    under the direction of or at

    the

    request

    of

    the Architect;

    and where s

    the

    Contractor

    has, based on

    the

    Tender

    Documents

    made

    in

    the

    Form

    of

    Tender his calculation

    of

    the sum that he will require

    for

    carrying

    out the

    Works by pricing the

    bills of quantities;

    5

    r

    ~ f u : ~

    > ??

    ;,

    l

    t

    f

    j

    I

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    7/114

    and

    whereas

    the Contractor has given a fully priced copy

    of

    the bills of quantities ('the Contract

    Bills') to

    both

    the Employer and the Architect;

    and whereas the Architect has given each party one

    copy of

    the Articles of Agreement, the

    Appendix

    the

    Conditions, the Contract Drawings, the Specification and the

    Contract

    Bills

    each signed

    by

    or

    on behalf

    of

    the parties.

    Now it is agreed

    as

    follows

    Article

    1

    The

    Contractor

    will carry

    out

    and complete the Works in accordance with and subject to the

    Contract

    for the

    consideration stated

    n

    Article

    2

    Article

    2

    The Employer will pay to the Contractor the sum

    of

    Hong Kong Dollars

    (HK ................................................................................................................................................

    ('the Contract Sum')

    or

    such other sum that becomes payable

    n

    accordance with and subject

    to

    the

    Contract.

    Article

    3

    The Architect will be

    of ................................................................................................................................................

    Article

    4

    The Quantity Surveyor will be

    of

    ................................................................................................................................................

    6

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    8/114

      rticle5

    1) In

    the event of the person appointed to act

    as

    either the Architect or the Quantity Surveyor

    ceasing to act, the Employer shall appoint a replacement as soon as practicable.

    2) If the Contractor objects

    to

    the person appointed to succeed either the Architect or the

    Quantity Surveyor, the Contractor has the right to refer his objection to an arbitrator

    under the Contract provided the reference to arbitration is made within 14 days of the

    appointment.

    3) The person appointed as the replacement to the rchitect or the Quantity Surveyor

    shall continue to act pending the award of the arbitrator appointed under Article 5 2)

    but shall immediately cease to act if so directed by the arbitrator s award. In which

    case the Employer shall appoint a further replacement as soon

    as

    practicable.

    4) The Contractor shall have the right of objection under Article 5 2) to a further appointment

    of either the Architect or the Quantity Surveyor.

    A person appointed as the replacement to the Architect or the Quantity Surveyor shall

    not

    be

    entitled to disregand or overrule any agreement, approval, certificate, confirmation,

    consent, decision, direct ion, dissent, instruction, notice, notification, opinion, request

    or

    requirement given

    or

    made by the person previously appointed save insofar as the

    Contract permits.

    Article

    If a dispute arises under or in connection with the Contract, the parties agree to resolve the

    dispute

    in

    accordance with the dispute settlement procedures

    in

    clause 41.

    I

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    9/114

      ttestation

    * SIGNED AND SEALED as a deed SIGNED by the Employer

    signature of signatory for the Employer) signature of wrtness)

    name and office held by signatory for the Employer) name and occupation of witness)

    company seal to be impressed here

    if

    executed as a

    deed

    by a limited company)

    *SIGNED ND SEALED as a deed SIGNED by the Contractor

    signature of signatory for the Contractor)

    signature of witness)

    name and office held by signatory for the Contractor)

    name and occupation of witness)

    company seal

    to be

    impressed here

    if

    executed as a deed by a limited company)

    *delete s applicable

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    10/114

    The General Conditions

    1

    Interpretation

    and definitions

    Governing law

    1 1

    The Contract shall

    be

    governed by

    and

    construed according

    to

    the laws for the time

    being

    in

    force

    in

    Hong Kong.

    Singular plural masculine and feminine

    1 2

    Words in the singular include the plural and vice versa and words in the masculine

    include the feminine and the neuter.

    Method

    of

    reference to clauses and Articles

    1 3 Unless stated otherwise a reference in the Articles the Conditions or the Appendix to

    any clause means that clause of the Conditions and a reference

    to

    an Article means

    that Article of the Articles of Agreement.

    Articles

    of

    Agreement Conditions and ppendix to

    be

    read

    as

    a whole

    1 4

    The Articles of Agreement the Conditions and the Appendix are to be read as a whole.

    Therefore unless stated otherwise each one must be read subject to any relevant

    qualification or modification in any other one.

    Clauses divided

    into

    sub-clauses to

    be

    read as a whole

    1 5 Where a clause is divided into sub-clauses the clause is to be read as a whole and

    each sub-clause shall relate to the others as if there was no division between them.

    Definitions

    1 6 The following words and phrases

    in

    the Articles of Agreement the Conditions and the

    Appendix shall have the meanings given below unless the context

    in

    which they appear

    requires otherwise or the Articles the Conditions or an item or entry in the Appendix

    provides otherwise:

    Appendix: the ppendix to the Conditions.

    Architect: the person named as the Architect in Article 3 or any successor appointed

    under Article 5.

    Articles

    or

    Articles

    of

    Agreement: the Articles of Agreement

    to

    which the Conditions are

    annexed.

    Commencement Date: the date stated in the Appendix for the commencement of the

    Works.

    communication: the giving submitting or issuing of without limitation any agreement

    approval authorisation certificate confirmation consent decision delegation direction

    dissent determination endorsement instruction notice notiftcation opinion request

    requirement or statement.

    Completion Date: the date stated

    in

    the Appendix by which the Works or a Section are

    to be completed or such later date to

    be

    fixed by the Architect under clause 25.

    9

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    11/114

    Interpretation and definitions (Cont d)

    1

    Conditions the Conditions of Agreement and Schedule of Conditions of Building Contract

    lor use in the Hong Kong Special Administrative Region, Private Edition With Quantities

    and any Special Conditions.

    Contract:

    the Articles of Agreement, the Appendix, the Form of Tender submitted by

    Contractor, the Employer s letter of acceptance of the Contractor s tenoer and any

    correspondence between the parties expressed to form part of the Contract, the Special

    Conditions, if any, the Conditions, the Contract Drawings, the Specification and the

    Contract Bills.

    Contract Bills the priced bills of quantities referred to in the recitals of the Articles and

    submitted

    by

    the Contractor with his tender, or a certified true

    copy

    of those bills of

    quantities.

    Contract Drawings

    the drawings referred to

    in

    the first and fourth recitals

    of

    the Articles

    and enumerated as such

    in

    the Contract Bills or the Specification.

    Contract Sum: the sum stated

    in

    Article 2, or such other sum that becomes payable in

    accordance with the Contract.

    Contractor the person named as the Contractor in the Articles.

    Contractors

    All

    Risks Insurance of the Works insurance which provides cover against

    physical loss of or damage to the Works, temporary works and materials and goods, as

    described in clause 22.

    Date

    for Possession of

    the Site

    the date or dates for the possession of the whole or

    parts

    of

    the Site stated in the Appendix under the reference to clause 23.1.

    Date ofSubstantial Completion the date stated in the Substantial Completion Certificate

    for the Works or a Section, issued by the Architect under clauses 17 1 and 17.2.

    day a calendar day and includes Sundays and other days which are general holidays

    by virtue

    of

    the General Holidays Ordinance (Chapter 149, Laws of Hong Kong).

    Defects Liability Period

    the period stated

    in

    the Appendix under the reference

    to

    clause

    17.3, commencing on the day after the Date of Substantial Completion of the Works or

    a Section or the day after the Relevant Date of Substantial Completion of a Relevant

    Part.

    Defects Rectification Certificate a certificate issued by the Architect to the effect that

    all defects, shrinkages and other faults have been rectified in accordance with the

    Contract, as described

    in

    clauses 17.4 and 17.5.

    direct /ass and/or expense the monetary consequences that flow naturally without

    other intervening cause and independently of special circumstances because of the

    direct consequences of a qualifying event and which are not otherwise reimbursed

    to

    the Contractor.

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    12/114

      Interpretation and definitions (Cont d)

    Domestic Sub Contractor: a person, other than a Nominated Sub-Contractor, to whom

    the Contractor sub-lets any part of the Works and includes a labour only sub-contractor.

    Employer: the person named as the Employer in the Articles.

    Engineer: a person engaged as a member of the Employer s design team for the design

    and supervision of one or more

    of

    the geotechnical, civil, structural or building services

    elements of the Works, as referred

    to

    in clause 1.7.

    Excepted Risks: a) Any consequence of war (whether war be declared or not)

    in

    which

    Hong Kong is actively engaged, the invasion of Hong Kong, acts of terrorists in Hong

    Kong, civil war, rebellion, revolution or military or usurped power in Hong Kong, riot,

    commotion or disorder in Hong Kong other than amongst the employees of the

    Contractor or any person for whom the Contractor is responsible;

    b)

    the

    Architect s design

    of

    the Works insofar as damage, loss

    or

    injury is the direct consequence

    of

    the design;

    c) a cause due to any neglect or default of the Architect, the Employer

    or any person for whom the Architect or the Employer is responsible;

    d) ionizing radiation or contamination by radioactivity from any nuclear

    fuel or from any nuclear waste from the combustion of nuclear fuel, radioactive toxic

    explosive or other hazardous properties of any explosive nuclear assembly or nuclear

    component thereof;

    and e) pressure waves caused by aircraft or other aerial devices travelling

    at sonic or supersonic speeds.

    Final Certificate: the certificate issued by the Architect stating the Final Contract Sum

    and the total of the amounts of Interim Certificates

    to

    be set off against that sum, as

    described in clause 32.8.

    Final ontract Sum: the sum resulting from the adjustment

    of

    the Contract Sum in

    accordance with the Contract.

    Form of Tender: the form of tender referred to in the first recital of the Articles as being

    part of the Tender Documents.

    Hong Kong: the Hong Kong Special Administrative Region.

    Interim Certificate: a certificate issued by the Architect stating the amount of an interim

    payment due

    to

    the Contractor, as described in clause 32.1.

    Limit of

    Retention: the amount stated in the ppendix under the reference to clause

    32.4 as the limit to the amount of Retention to be held by the Employer on the payment

    for the Contractor s work in progress.

    Nominated Sub Contract: the sub-contract between the Contractor and a Nominated

    Sub-Contractor.

    11

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    13/114

    I

    Interpretation nd definitions

    (Cont'd)

    12

    Nominated Sub Contractor: a sub-contractor nominated by the Architect under clause

    29 to carry out work forming part

    of

    the Works.

    Nominated Supplier: a supplier nominated by the Architect under clause 29 to supply

    materials

    or

    goods for incorporation into the Works.

    Nominated Supply Contract the

    supply

    contract between the Contractor and a

    Nominated Supplier.

    parties: the Employer and the Contractor.

    Period of Interim Certificates: the period stated in the Appendix under the reference to

    clause 32.1 as the interval between the issuing of Interim Certificates.

    person: an individual, firm, partnership,

    or

    body

    corporate.

    person

    for

    whom

    the Contractor is responsible: the Contractor's servants or agents,

    sub-contractors, suppliers, persons employed or engaged in connection with the Works

    and persons who may properly be on the Site upon or in connection with the Works

    other than the Employer

    or

    any person for whom the Employer is responsible.

    person

    for

    whom the Employer is responsible: the Employer's servants or agents and

    the persons listed in clause 30.1.

    postpone to defer the commencement

    of

    operations on

    an

    activity.

    Prime

    Cost

    Sum: a sum either provided in the Contract Bills

    or

    arising

    as

    described in

    clause 29.1 for work to

    be

    carried

    out

    by a Nominated Sub-Contractor or for materials

    or goods to

    be

    obtained from a Nominated Supplier.

    Provisional/tern: an item

    of

    work identified as provisional in the Contract Bills to be

    carried out by the Contractor if instructed to

    do

    so by the Architect under clause 13.2.

    Provisional Quantities: an estimated quantity

    of work

    identified as provisional in the

    Contract Bills, where the actual quantity could not be accurately determined when the

    bills of quantities were prepared, to be carried out by the Contractor if instructed to do

    so by the Architect under clause 13.2.

    Provisional Sum: a sum provided

    in

    the Contract Bills for work or for costs, which could

    not

    be

    entirely foreseen, defined or detailed when the bil ls of quantities were prepared,

    to be paid to the Contractor if instructed by the Architect under clause 13.2 to carry out

    such work or incur such costs.

    Quantity Surveyor: the person named as the Quantity Surveyor in Article 4,

    or

    any

    successor appointed under Article 5.

    Relevant Date: the date upon which the Employer took possession

    of

    a Relevant Part

    under clause 18.

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    14/114

      Interpretation and definitions (Cont d)

    Relevant Part: the

    part of the Works

    or

    part of a Section taken possession of

    by

    the

    Employer under clause 18 before Substantial Completion of the Works or that Section.

    Retention: the sum

    calculated

    in

    accordance

    with clause 32.4 and retained by the

    Employer from the gross valuation

    of

    the Contractor s work in progress included in n

    Interim Certificate.

    Retention Percentage: the percentage entered

    in

    the Appendix under the reference to

    clause 32.4, used to calculate the Retention

    in

    accordance with the rules set out in that

    clause.

    Section: a part of the Works for which a separate Completion Date is stated in the

    Appendix where the Contract provides for sectional completion of the Works.

    Site: the land and

    other

    places provided

    by

    the Employer for the purpose

    of

    carrying

    out the Works.

    Special Condition: a condition of contract expressly referred to as a Special Condition

    of Contract, which adds to or amends the Conditions and is annexed to the Conditions.

    special delivery: a communication which is either delivered by courier or sent by registered

    post

    or recorded delivery.

    Specialist Contractor: a person, not being a statutory undertaker

    or

    utility company as

    referred to

    in

    clause 6.4(1), engaged by the Employer to carry out work directly connected

    with or ancillary to but not forming part of the Works, s described in clause 30.

    Specialist Works: work directly connected with or ancillary to but not forming part

    of

    the

    Works, to be carried out by a Specialist Contractor.

    Specification: the specification referred to

    in

    the first and fourth recitals

    of

    the Articles

    which describes, without limitation, the types, standards and quality of the materials

    and goods to

    be

    used, the standard and quality

    of

    workmanship required, the manner

    in which work processes are to be carried out, the performance requirements and other

    matters and things relating to the construction

    of

    the Works.

    Specified Perils: fire, lightning, explosion, storm, tropical cyclone, flood, bursting

    or

    overflowing of water tanks, apparatus or pipes, earthquake, aircraft and other aerial

    devices or articles

    dropped

    from them.

    Standard Conditions

    of

    Nominated Sub Contract: the Standard Form of Sub-Contract

    for use where the sub contractor is nominated under the Standard Form of Building

    Contract.

    Standard Conditions

    of

    ominated

    Supply

    Contract: the Standard Form of Supply

    Contract for use where

    the

    supplier

    is

    nominated under the Standard Form of Building

    Contract.

    13

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    15/114

    '

    1

    Interpretation and definitions (Cont d)

    14

    sub contractor: a person who enters into a sub-contract with the Contractor to carry

    out work forming part

    of

    the Works and includes a Domestic Sub Contractor and a

    Nominated Sub-Contractor.

    Substantial Completion: the state of completion where the Works or a Section have

    been substantially completed to the Architect s satisfaction and have passed the required

    inspections and tests, as referred to in clauses 17.1 ·and 17.2.

    Substantial Completion Certificate: a certificate issued by the Architect stating the date

    when in his opinion the Works or a Section have reached Substantial Completion.

    substantially completed: the state

    of

    completion where the Works or a Section may not

    be absolutely completed or entirely free from defects but have reached the stage where

    they can be taken over and used by the Employer for their intended purpose and where

    the unfinished items

    of

    work and the remaining defects then patent are only

    of

    a minor

    nature and extent and their complet ion or rectification will not unreasonably interfere

    with or interrupt the taking over of the Works or Section.

    supplier: a person who enters into a

    supply

    contract with the

    Contractor

    to

    supply

    materials

    or

    goods and includes a Nominated Supplier.

    suspend: to cease operations for a period of time on an activity in which

    work

    has

    commenced.

    Tender Documents: the documents and drawings referred to

    in

    the first recital

    of

    the

    Articles,

    or

    a certified true copy

    of

    those documents and drawings.

    Valuation: the valuation made by the Quantity Surveyor, in accordance with the valuation

    rules under clause 13.4, of work carried out in response to an Architect s instruction

    requiring a Variation, remeasurement of Provisional Quantities and Provisional Items or

    to expend Provisional Sums.

    Variation: a change instructed by the Architect to the design, quality or quantity of the

    Works including:

    0)

    an alteration

    to

    the type, standard or quality of any

    of

    the materials or goods

    comprising the Works;

    ii) the addition, substitution or omission of work; and

    (iii)

    the removal from the Site

    of

    materials or goods and the demolition and removal

    of work

    except

    where provided for in the Contract or where the materials,

    goods

    or

    work are not in accordance with clause 8.1;

    or the imposi tion of an obligation or restriction instructed by the Architect regarding:

    iv) access to the Site or use

    of

    any parts

    of

    the Site;

    v) limitation of working space;

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    16/114

    1 Interpretation and definitions

    (Cont d)

    vi) limitation of working hours; or

    vii) the sequence of carrying out

    or

    completing work;

    or the addition or alteration to or omission of such obligations or restrictions imposed

    by the Contract .

    Works the

    work

    briefly

    described

    in the Articles

    of Agreement and

    shown upon,

    described by or referred to in the Contract including any change made to the

    work

    in

    accordance with the Contract.

    he role of the Engineer

    1 7 1)

    The Architect may, from time to time, delegate any of his duties and powers under

    the Contract to an Engineer.

    2) The delegation shall be in writing and copied to the Contractor. It shall specify the

    duties and

    powers

    that are

    delegated

    and shall remain in

    force

    until

    changed or

    terminated in writing by the Architect.

    3) Where in the

    context of

    the wording

    of

    a clause in the Conditions or where

    recognition of the Engineer s statutory responsibility requires it, the word Architect in

    the Conditions shall be deemed to be read as Engineer .

    Sectional completion of the Works

    1 8 1)

    Where sectional completion of the Works

    is

    provided for in the Contract, a reference

    to the Works shall be deemed to mean the Works

    or

    a Section.

    2)

    The phrase the whole of the Works means the Works including all Sections.

    Communications

    1 9

    Unless otherwise stated, all notices, certificates and other communications under the

    Contract between the Employer, the Architect, the Quantity Surveyor and the Contractor

    shall be in writing.

    Notices of default or determination to

    be sent

    by special delivery

    1 10

    All notices

    of

    default

    or

    determination under clauses 35, 36 and 37 shall be sent by

    special delivery.

    Parties to

    ct

    reasonably

    nd

    expeditiously

    1 11 1) The parties, the

    Architect

    and the Quantity Surveyor shall act reasonably and

    expeditiously in all matters under the

    Contract

    including, without limitation, giving

    or

    withholding consent, approval or agreement, valuing Variations and certifying.

    2)

    All requirements shall be reasonable requirements and, without limitation, the term

    to

    the

    Architect s satisfaction

    shall be construed as meaning to the Architect s

    reasonable satisfaction

    and

    the term practicable shall mean reasonably practicable.

    15

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    17/114

    '

    i

    I

    2 Contractor s obligations

    Contractor s obligations

    2.1 1) The Contractor shall

    in

    compliance with the Contract:

    a) organize, manage, plan and supervise the carrying out

    of

    the Works;

    b) co-ordinate the carrying out

    of

    the Works including the interface between his own

    work and the work carried out by each Domestic Sub-Contractor, Nominated Sub

    Contractor, Specialist Contractor, statutory undertaker and utility company;

    c) assist in the

    co-ordination

    of their work by each

    Domestic Sub-Contractor,

    Nominated Sub-Contractor, Specialist Contractor, statutory undertaker and utility

    company with the work of each

    of

    the others;

    d) design sufficient, safe and adequate temporary works to enable the Contractor to

    comply with his other obligations under the Contract, except where the design

    of

    any temporary works is a statutory obligation

    of

    any person other than the Contractor

    or

    any person for whom the Contractor is responsible;

    e) carry

    out

    any work involved in the development of the Architect s design that may

    be specified in the Contract;

    f) prepare all shop drawings and co-ordination drawings required by the Contract;

    g)

    carry out the maintenance

    of

    mechanical and electrical equipment where required

    to do so by the Contract for the period

    of

    time so specified;

    h) take responsibility for the care

    of

    the Works, except for loss or damage arising

    from the Excepted Risks, from the Commencement Date until 14 days after

    Substantial Completion

    of

    the Works or 14 days after the determination

    of

    the

    employment of the Contractor, whether valid

    or

    not, whichever is earlier,

    except

    that the Contractor s responsibility for the care

    of

    the Works shall terminate in

    relation to a Section or Relevant Part 14 days after the Employer takes possession

    of that Section or Relevant Part; and

    i) carry

    out

    the construction of and complete the Works using materials, goods and

    workmanship

    of

    the types, standards and quality specified

    in

    the Contract.

    2} Where the Contract requires the Contractor to prepare details, to carry out the

    design or the development

    of

    the Architect s design, unless the requirement

    of

    fitness

    for

    purpose is specifically stated, the design or the development

    of

    the

    Architect s design shall

    be

    carried out with reasonable skill and

    care

    and

    the

    Contractor shall be responsible to the Employer for such work.

    Contractor s responsibility

    2.2 The Contractor shall remain wholly responsible for carrying

    out

    and completing the

    Works in accordance with the Contract whether or not the Architect or the Architect s

    representative, if appointed:

    16

    a) visits the Works or a place where materials or goods are being manufactured or

    stored, work is being prepared, or design is being carried out;

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    18/114

    2

    Contractor s

    obligations (Cont d)

    b) inspects or tests any materials or goods;

    c) exercises his

    powers

    under clause

    8; or

    d)

    includes the value of any materials, goods or work in an Interim Certificate.

    Contractor s skill and care

    2.3

    The Contractor shall exercise

    in

    the performance

    of

    his obligations under the Contract

    all the skill, care and diligence to

    be

    expected of a competent contractor experienced

    in carrying out work of a similar scope, nature and size to the Works.

    Contractor to inform rchitect if he finds ambiguities in documents

    2.4 1) The Contractor shall immediately inform the Architect if the Contractor finds an

    ambiguity

    or

    discrepancy in

    or

    divergence between the following documents:

    a) the Contract Drawings;

    {b) the Specification;

    c) the Contract Bills;

    {d) the descriptive schedules .and other similar documents referred to in clause 5.3(d);

    e) the Nominated

    Sub-Contract

    documents and the Nominated Supply Contract

    documents referred to in clauses 5.4 and 5.5; and

    {f) the further drawings, details, descriptive schedules and similar documents referred

    to in clause 5.6 provided from time to time during the carrying

    out

    of the Works.

    2) If the Architect agrees with the Contractor, he shall issue an instruction to resolve

    the ambiguity,

    discrepancy or

    divergence as soon as practicable after receipt

    of

    the

    notice from the Contractor

    and

    the instruction shall, if considered appropr iate by the

    Architect, require a Variation.

    Master

    progr mme

    Master programme to be

    submitted

    3 1

    1)

    The Contractor shall submit to the Architect within the time stated in the Appendix:

    a) 6 copies

    of

    a master programme prepared for his own purposes for organizing,

    managing, planning, supervising and co-ordinating the carrying

    out

    of the Works

    and completing

    them

    by the Completion Date;

    {b)

    a method statement describing the methods of construction and the resources

    that he intends to use to carry out the Works;

    c) a list

    of the

    names and details

    of

    the site management and supervisory team

    personnel, referred to

    in

    clause

    10,

    with job descriptions and details of their durations

    on the Site; and

    7

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    19/114

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    20/114

    3 Master programme (Cont d)

    Programme

    and other

    documents

    not

    to

    be documents

    forming the ontract

    3.3 Neither the programme, the method statement

    nor

    other

    document

    submitted under

    clause 3 shall be documents forming the Contract and no comment made by the Architect

    on any of these documents shall impose

    an

    obligation on the Employer.

    4 Architect s instructions

    Architect

    may

    issu

    instructions up to the

    issu

    of the Final ertificate

    4 1 The Architect may issue instructions that he is empowered to issue under the Conditions

    at any time up to the issue of the Final Certificate including during the time that the

    Contractor may be

    carrying

    out work

    after the Date

    of

    Substantial Completion of the

    Works, but he shall not instruct a Variation after the issue

    of

    the Defects Rectification

    Certificate for the Works, a Section or a Relevant Part as the case may be.

    Architect

    to issue instructions in writing

    2

    1) The

    rchitect

    must

    issue all

    instructions

    in

    writing

    in

    accordance

    with clause

    1.9. All oral instructions given must be confirmed in writing within 5 days of giving the

    oral instruction. If the Architect gives an oral instruction

    that

    the Contractor believes

    requires a Variation it shall have no immediate effect, the Contractor shall confirm the

    oral instruction requiring a Variation in writing to the Architect within 7 days of it being

    issued and if not dissented to in writing by the Architect within 7 days from his receipt

    of the Contractor s confirmation the Variation shall take effect on the expiry

    of

    the latter

    7 days.

    2)

    Where an Architect s oral instruction requiring a Variation has been confirmed in

    writing by the Contractor under clause 4.2(1) and not dissented to by the Architect, the

    Architect shall issue the written instruction for a Variation for record purposes as soon

    as practicable after the Contractor s confirmation.

    ompliance with

    Architect s

    instructions

    4 3 1)

    Subject to clauses 4.2(1) and 4.3 2), the Contractor shall comply with all instructions

    that the Architect is empowered by the Conditions to issue as soon as practicable. If

    there is a d isagreement between the Architect and the Contractor as to whether an

    instruction involves a Variation, the Contractor shall comply with the instruction and

    may,

    if

    he is not satisfied, require the disagreement to be resolved under clause 41.

    2) If the Contractor disagrees that the Architect is empowered by the Conditions to

    issue an instruction he may within 7 days of receipt

    of

    that instruction require the

    disagreement to

    be

    resolved under clause 41 .

    3) If the Contractor does not begin to comply with an instruction within 7 days after

    receipt of a written notice from the Architect requiring compliance with that instruction

    in accordance with clause 4.3(1) and the Architect issues a certificate to that effect by

    special delivery, the Employer

    may,

    without prejudice to his other rights and remedies,

    engage other persons to carry out that instruction. All additional costs incurred by the

    Employer in

    connection

    with the employment of the

    other

    persons to carry out that

    instruction may be recovered from the Contractor under clause 40 or as a debt.

    19

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    21/114

    I

    I

    4 Architect s instructions (Cont d)

    4)

    The Contractor shall provide reasonable access to the persons engaged by the

    Employer under clause 4.3(3) and shall permit them to carry out their work without

    hindrance.

    ontractor to carry ut preventative work

    4.4

    1)

    In the event of an emergency caused by an event arising out

    of

    or in connection

    with the Works that threatens the safety of the Works or any person or property, the

    Contractor shall immediately:

    5

    5 1

    2

    a) carry out

    all

    necessary preventative work

    without

    waiting for

    an Architect s

    instruction; and

    b) immediately inform the Architect of the emergency and

    of

    the action

    taken

    or

    preventative work being carried out.

    2)

    The Architect shall issue an instruction confirming a Variation for preventative work

    carried out initially without an Architect s instruction, provided that the

    work

    was not

    required to

    be

    carried out in fulfilment of a Contractor s obligation or because of a

    breach of contract or other default by the Contractor or any person for whom the

    Contractor is responsible.

    Documents forming the Contract and other documents

    he

    documents forming the ontract

    1)

    The documents forming the Contract shall be:

    a) the Articles of Agreement and the Appendix;

    b) the Form of Tender submitted by the Contractor together with the Employer s letter

    of acceptance of the Contractor s tender and any correspondence between the

    parties expressed to form part of the Contract;

    c) the Special Conditions if any;

    d) the Conditions; and

    e)

    the Contract Drawings, the Specification and the Contract Bills.

    2) The order

    of

    precedence

    of

    the documents forming the Contract shall be as listed

    in paragraphs

    a)

    to

    e)

    above and:

    a) for the purpose of adjusting the Contract Sum the Contract Bills shall take

    precedence over the Contract Drawings and the Specification; but

    b)

    for all other purposes including carrying out the construction

    of

    and completing

    the Works the Contract Drawings and the Specification shall take precedence over

    the Contract Bills.

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    22/114

    5

    Documents

    forming

    the

    Contract and other documents (Cont d)

    Architect and Quantity Surveyor t keep documents available

    5.2 The Archi tect shall provide two copies, certified on behalf of the Employer as a true

    copy, of each of the documents forming the Contract and two certified true copies of

    each of the documents forming the Nominated Sub-Contracts and the Nominated Supply

    Contracts as referred to in clauses 5.4 and 5.5, and the Architect and the Quantity

    Surveyor shall. both keep one of each

    of

    these copies available at all reasonable. times

    for the purposes

    of

    the Contract.

    Copies

    of

    documents

    for

    Contractor

    5.3 As soon as practicable after the acceptance of the Contractor s tender the Architect

    shall provide the Contractor, without charge, with:

    a) 1 copy, certified on behalf of the Employer as a true copy,

    of

    each of the documents

    forming the Contract;

    b) 3 further copies of the Contract Drawings and the Specification;

    c) 3 copies

    of

    the unpriced bills of quantities; and

    d) 3 copies of any descriptive schedules

    or

    other similar documents prepared by

    or

    under the direction of the Architect before the acceptance of the Contractor s tender

    and necessary for use in carrying

    out

    the Works.

    Nominated Sub Contract documents

    5.4 The Architect shall provide the Contractor, without charge, with 3 further copies

    of

    the

    Nominated Sub-Contract, the sub-contract drawings, the sub-contract specification,

    the sub-contract bills of quantities or schedule of quantities and rates,

    as

    the case may

    be, descriptive schedules and other similar documents as soon as practicable after the

    award of each Nominated Sub-Contract.

    Nominated

    Supply

    Contract documents

    i The Architect shall provide the Contractor, without charge, with 3 further copies

    of

    the

    Nominated Supply Contract, the

    supply contract drawings, the

    supply

    contract

    specification, the supply contract bills of quantities

    or

    schedule of quantities and rates,

    as the case may be, descriptive schedules and other similar documents as soon as

    practicable after the award

    of

    each Nominated Supply Contract.

    Further drawings details descriptive schedules and similar documents

    5.6

    1)

    The Architect shall provide the Contractor, without charge, and from time to time

    during the carrying out

    of

    the Works, with 3 copies

    of

    all further drawings, details,

    descriptive schedules or similar documents (referred to in clause 5 as the supplementary

    documentation ) that, in the Architect s opinion, are reasonably necessary for use

    in

    carrying out the Works

    or

    to explain

    or

    amplify the Contract Drawings, the Nominated

    Sub-Contract drawings and the Nominated Supply Contract drawings.

    2)

    If

    in

    the Contractor s opinion

    he

    requires more supplementary documentation than

    that provided by the Architect under clause 5.6(1) he shall submit a written request to

    the Architect specifying what further supplementary documentation

    he

    requires.

    21

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    23/114

    '

    '

    I

    . :

    .

    :: i

    .

    I '

    i

    ' I

    .

    I

    i .

    I

    ,I

    ·

    .,

    i,

    'I

    i

    5 Documents forming the

    Contract

    and other documents (Cont'd)

    5 7

    (3)

    It shall be

    at the

    sole

    discretion of the

    Architect to decide which, if any,

    of the

    supplementary documentation requested by the Contractor

    the

    Architect will provide.

    ocuments to be

    provided

    to ontractor on time

    (1)

    The supplementary documentation referred to in clause 5.6 shall be provided when,

    having regard to the progress of

    the

    Works and the Contractor's procurement, fabrication

    and other lead in times, it is reasonably necessary for

    the

    Contractor to receive it.

    (2)

    The Contractor shall inform

    the

    Architect sufficiently in advance

    of the

    time that he

    requires the supplementary documentation to enable the Architect to fulfil his obligations

    under clause 5.7(1).

    Electronic copies of drawings

    5 8 If,

    within 14 days after the acceptance

    of

    the Contractor's tender,

    the

    Contractor requests

    the

    Architect

    in

    writing

    to do

    so,

    the Architect

    shall

    provide

    the

    Contractor,

    without

    charge with electronic

    copies of

    all

    of the

    drawings required

    to

    be provided under

    clauses 5.3, 5.4, 5.5 and 5.6

    that

    have been produced electronically

    in

    lieu of

    the

    hard

    copies referred to in

    those

    clauses.

    ocuments on Site

    5 9 The Contractor shall keep

    on the

    Site so as to be available to the Architect and the

    Quantity Surveyor at all reasonable times 1 copy of:

    5 10

    22

    (a)

    the Contract Drawings;

    (b)

    the

    Specification;

    (c)

    the

    unpriced bills

    of

    quantities;

    (d) the programmes and other documents referred to in clause 3;

    (e)

    the descriptive schedules

    or

    other

    similar

    documents referred to in clause 5.3

    prepared by the Architect before

    the

    acceptance

    of the

    Contractor's tender;

    (f) the Nominated Sub-Contract documents and Nominated Supply Contract

    documents referred to in clauses 5.4 and 5.5;

    (g)

    the

    supplementary documentat ion referred to in clause 5.6 provided by the Architect

    from time to time

    during

    the carrying

    out

    of the Works; and

    (h) all

    other documents

    that the Contractor is required

    to

    keep on Site in fulfilment of

    his statu tory obligations.

    Return of drawings

    The Contractor

    shall return

    to

    the

    Architect

    all drawings

    specifications details

    descriptive schedules and

    other

    similar documents provided under clause 5,

    if

    required

    by

    the

    Architect to

    do

    so,

    either upon the

    issue of

    the

    Final

    Certificate

    or

    the

    final

    conclusion of any proceedings

    to

    which

    the

    Contractor is a party, whichever is later

    and the Contractor may take copies for

    his

    own records.

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    24/114

    5

    Documents

    forming the Contract and other documents (Cont d)

    Submission

    of

    manuals and assignment

    of

    warranties

    5.11

    1)

    The

    Contractor

    shall

    submit

    to the Architect all the operation and maintenance

    manuals received by the Contractor.

    2) The Contractor shall assign to the Employer (so far as he is lawfully able to

    do

    so)

    the benefits of all suppliers and sub-contractors warranties, guarantees

    or

    other ancillary

    agreements for materials, goods

    or work

    insofar as they are required by the Contract,

    Nominated Sub-Contracts or Nominated Supply Contracts, other than the

    direct

    warranties to the Employer required under the Nominated Sub-Contracts and Nominated

    Supply Contracts, within 60 days after the issue of the Substantial Completion Certificate

    for the whole of the Works.

    -

     3)

    Where the

    Contractor

    assigns the benefit

    of

    a suppliers or

    sub-contractors

    warranty, guarantee or other ancillary agreement for materials, goods or work to the

    Employer, the Employer shall exhaust all remedies under the warranty, guarantee

    or

    ancillary agreement before enforcing the terms

    of

    the Contract against the Contractor

    in

    respect of any matter for which a cause of action exists against the sub-contractor or

    supplier under the warranty, guarantee

    or

    other ancillary agreement.

    Submission

    of

    as built drawings

    5.12 1) The Contractor shall submit to the Architect 2 copies

    of

    a complete set

    of

    the as

    built drawings that are required by the Contract, Nominated Sub-Contracts or Nominated

    Supply Contracts within 60 days

    of

    the issue

    of

    the Substantial Completion Certificate

    for the whole

    of

    the Works.

    2)

    Where the

    drawings

    referred to under clauses 5.3, 5.4, 5.5 and 5.6 have been

    issued electronically, the Contractor shall, if so required by the Architect, provide the

    as-built drawings electronically.

    Limits to use

    of

    documents

    5.13 1) The Contractor shall not use any

    of

    the documents referred to in clause 5 for any

    purpose other than the Works and any proceedings relating to the Contract.

    2)

    Neither the Employer, the Architect

    nor

    the Quantity Surveyor shall divulge any of

    the rates or prices in the Contract Bills or use them except for the purposes of the

    Contract and any proceedings relating to the Contract.

    Issue

    of

    Architect s certificates

    5.14 The Archi tect shall issue all certificates to the Employer and shall, at the same time,

    issue a copy of each certificate to the Contractor.

    Copy

    of

    notice to be given to Employer

    5.15 Whenever the Architect issues a notice to the Contractor by special delivery, he shall

    issue a copy of the notice to the Employer at the same time.

    3

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    25/114

    6

    Statutory

    obligations

    Statutory Requirements

    6.1 The Contractor shall comply with and give the notices required

    by

    any Ordinance,

    regulation, rule, order

    or

    by-law applicable to the Works ('the Statutory Requirements')

    which are to be complied with by the Contractor.

    ompliance with the Statutory Requirements

    6.2 1) The Contractor shall immediately notify the Architect if the Contractor finds that

    carrying

    out

    the Works in compliance with the Contract or with an Architect's instruction

    requiring a Variation will infringe the Statutory Requirements.

    2) If the Archi tect agrees with the Contractor, he shall issue an instruction to resolve

    1

    the infringement as soon as practicable after receipt

    of

    the notice and the instruction

    shall, if appropriate, require a Variation.

    Fees

    or

    charges

    6.3

    1)

    The Contractor shall pay all fees or charges legally demandable under the Statutory

    Requirements.

    6.4

    4

    2)

    The net amount of those fees or charges paid by the Contractor shall be added to

    the Contract Sum unless they:

    a)

    are

    fees or

    charges

    that the

    Contractor is liable to pay under the

    Statutory

    Requirements, and the liability was known prior to the date for submission of tenders

    and has not been increased;

    b)

    are priced, or are required to be allowed for,

    in

    the Contract Bills;

    c)

    are provided for by a Provisional Sum;

    or

    d) arise out of a default, delay or failure by the Contractor or a sub contractor to

    comply with the Statutory Requirements or the Contract

    Statutory undertakers nd utility companies

    1)

    Statutory undertakers

    or

    utility companies carrying out work in pursuance of their

    statutory obligations and not having a contractual relationship with the Employer, the

    Contractor

    or

    any person

    for

    whom the Contractor is responsible shall be classified as

    statutory undertakers or utility companies and not Nominated Sub Contractors or

    persons engaged

    by

    the Employer under clause 30 and the fees or charges for their

    work shall be regarded as fees and charges legally demandable under the Statutory

    Requirements and processed in accordance with clause 6.3.

    2) The Contractor shall allow those persons reasonable access to the Site, permit

    them to carry out their work and provide them with the facilities referred to in clause 31.

    3)

    Statutory undertakers

    or

    utility companies engaged under contracts with the

    Employer to carry out work directly connected with or ancillary to but not forming part

    of

    the Works shall be classified

    as

    Specialist Contractors

    as

    referred

    to

    in clause 30.1.

    F

    l

    l

    f

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    26/114

    Statutory obligations (Cont d)

    4) tatutory undertakers

    or utility

    companies

    engaged

    under contracts

    with the

    Contractor or a Nominated Sub-Contractor to carry out work forming part of the Works

    shall be classified as sub-contractors or sub-sub-contractors as the case may be.

    Setting out the Works

    etting out nd levels

    1)

    The Architect shall provide the Contractor with accurately dimensioned setting out

    drawings containing the information and levels necessary for him to set out the Works.

    2)

    The Contractor shall be responsible for accurately setting out the Works and shall

    correct any error arising from inaccurate setting out at his own

    cost

    unless the Architect

    accepts the error without correction subject to a reasonable reduction in the Contract

    Sum having regard to the Employer s loss of value of the Works and any expenses that

    he may incur arising from the inaccurate setting out.

    Materials goods workmanship and wor

    Types standards nd quality

    1) The Contractor

    must

    provide all materials and goods

    of

    the types, standards and

    quality described in the Contract to the Architect s satisfaction that the Contractor has

    met these requirements.

    2)

    Where the Contractor is responsible for the selection

    of

    the materials and goods in

    accordance with a performance specification

    or

    otherwise, the materials and goods

    must be fit for the purpose stated in the Contract.

    3) If any of the specified materials or goods are not procurable, then the Contractor

    shall submit alternative proposals for materials or goods

    of

    similar type and standard

    and of comparable quality and price

    to

    the Architect for his approval; and

    a)

    if the proposed alternative materials

    or

    goods are of similar type and standard and

    of comparable quality and price to those specified, and the Architect approves

    them, the

    substitution

    of the alternative materials or goods for

    those

    specified

    shall be made with no adjustment to the Contract Sum; or

    b) if the proposed alternative materials

    or

    goods

    are

    not of similar type and standard

    or comparable quality

    or

    price to those specified, and the Architect approves them,

    he shall instruct a Variation to adjust the type, standard, quality or price.

    4)

    The Contractor shall provide the Architect, upon his request, with vouchers, test

    certificates or other evidence to satisfy the Architect that the materials and goods comply

    with the Contract.

    5) The Contractor s workmanship must be of the standard and quality described in

    the Contract

    to

    the Architect s satisfaction.

    5

    I

    I

    i

    I

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    27/114

    8 Materials

    goods,

    workmanship and work

    (Cont d)

    6) All work must be carried out in a proper and workmanlike manner in accordance

    with the Contract

    or, in

    the absence

    of

    any specific performance requirements, to the

    Architect s satisfaction.

    Inspection

    nd

    tests

    8 2 1)

    The Contractor shalf carry out

    or,

    if

    so required by the Contract, arrange for a third

    party

    to

    carry out, the tests specified in the Contract

    in

    compliance with the specified

    testing procedures.

    2) In addition to

    the

    tests specified in the Contract,

    the

    Architect may

    instruct

    the

    Contractor

    to

    open up for inspection any work

    covered

    up and

    to

    carry out,

    or

    arrange

    for

    a third

    party to carry

    out,

    tests

    of materials

    and goods

    {whether

    or not

    already

    incorporated in the Works) and work which has been carried out.

    3) The cost of the testing, the opening up for inspection and any consequential making

    good shalf

    be

    added to the Contract Sum unless:

    a) the inspection

    or

    test is provided

    for

    in the Contract Bills;

    b) the inspection

    or

    test shows

    that

    the materials, goods, workmanship

    or

    work are

    not in accordance with clause 8;

    c)

    the inspection

    or

    test

    was considered necessary

    by

    the Architect because, as a

    result

    of

    the failure of a previous inspection

    or

    test, further investigation of similar

    materials goods

    or

    work was required

    to

    establish

    to

    his

    satisfaction their

    compliance with clause 8;

    or

    d) the work was carried

    out

    without the inspection notice required by the Contract.

    Materials goods workmanship or work

    not

    in accordance with Contract

    8 3

    The Architect may,

    if

    any materials, goods, workmanship

    or

    work are

    not

    in accordance

    with the Contract, instruct:

    6

    a) the removal from the Site and the replacement

    of

    materials and

    goods

    that are

    not

    in

    accordance with clause

    8;

    b)

    the repair

    or

    demolition, removal and reconstruction of work which,

    in

    respect

    of

    materials, goods

    or

    workmanship, is

    not

    in accordance with clause 8;

    c)

    the acceptance

    without

    replacement

    or

    reconstruction

    of some or

    all

    of

    the

    materials,

    goods

    or work

    that are

    not

    in

    accordance

    with clause

    8,

    subject

    to

    a

    reasonable reduction in the

    Contract

    Sum having regard

    to

    the reduction in the

    value of the materials, goods

    or

    work; and

    d) a Variation

    for

    alternative remedial work to sorne

    or

    all of the materials,

    goods or

    work as is reasonably necessary in consequence

    of

    them

    not

    being

    in

    accordance

    with clause

    8,

    with no extension of time

    or

    addition

    to

    the

    Contract Sum.

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    28/114

    8

    8 4

    8 5

    9

    9.1

    9 2

    9 3

    Materials, goods, workmanship and work (Cont d)

    Rectifying defects

    The Architect may instruct the Contractor to rectify defects which appear before the

    commencement of the Defects Liability Period.

    Dismissal from the Works

    The Architect may instruct the Contractor to dismiss any individual from the Works for

    incompetence, misconduct or other similar reasons.

    Intellectual

    property rights

    Intellectual property in design of the Works

    The Contractor shall pay the cost of any royalty, license fee or other sum legally

    demandable for the use of intellectual property in connection with the design

    of

    the

    permanent Works other than works under a Nominated Sub-Contract or materials and

    goods supplied under a Nominated Supply Contract, and the cost shall

    be

    added

    to

    the Contract Sum.

    Intellectual property in materials

    nd

    goods

    The Contractor shall pay the cost o any royalty, license fee or other sum legally

    demandable for the use of intellectual property

    in

    connection with the incorporation

    of

    materials and goods into the permanent Works other than materials and goods supplied

    under a Nominated Sub-Contract

    or

    a Nominated Supply Contract. The cost shall be

    added to the Contract Sum unless the Contractor was responsible for the selection of

    the materials and goods in accordance with a performance specification or otherwise

    in which case the cost shall be deemed to be included in the Contract Sum.

    Intellectual property in pl nt

    nd

    equipment

    1) The payment

    of

    all royalties, license fees or other sums legally demandable for the

    use of intellectual property in respect

    of

    plant, equipment, machinery,

    methods or

    anything whatsoever used in carrying out the Works shall be deemed to be included in

    the Contract Sum.

    2) The

    Contractor

    shall

    indemnify

    the Employer from and

    against

    all claims,

    proceedings, damages, costs and expense arising from the Contractor

    or

    any

    sub-

    contractor

    or

    supplier infringing

    or

    being held to have infringed any of the intellectual

    property rights referred

    to

    in clause

    9.3 1

    ).

    Payment of royalties included in Valuation

    9.4 If the Contractor uses any intellectual

    property

    in

    compliance

    with an

    Architect s

    instruction requiring a Variation, any royalty, license fee or other sum legally chargeable

    which the Contractor pays in connection with that instruction shall be included in the

    Valuation

    of

    the Variation.

    1 0 Contractor s site management

    team

    Contractor s site management team

    10.1 1) The Contractor shall maintain the site management and supervisory team (referred

    to in clause 10 as the team ) listed in clause 3.1

    1

    )(c) on the Site for as long as is

    necessary for the satisfactory fulfilment of his obligations under the Contract.

    7

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    29/114

    10

    Contractor s site

    management

    team

    (Con 'd)

    2)

    The team shall be of sufficient strength with personnel

    of

    appropriate qualifications,

    seniority and experience, having regard to the size, complexity and nature of the Works,

    to

    properly organise, manage, plan, supervise and co-ordinate

    the

    carrying

    out

    of the

    Works.

    Construction manager

    10.2 1)

    The team shall

    be

    headed by

    an

    experienced and competent construction manager

    approved

    by

    the Architect.

    2) An instruction issued by the Architect to the construction manager shall be deemed

    to have been issued to the Contractor.

    3)

    The Architect

    may

    instruct the Contractor to replace the construction manager

    or

    a member of the team

    for

    incompetence or misconduct.

    4)

    The Contractor shall not remove or replace the construction manager

    or

    any member

    of

    the

    team unless requested by

    or

    agreed to by the Architect.

    11

    Access

    for

    the Architect to

    the

    Works

    ontractor

    to

    give

    access

    The

    Contractor

    shall

    give

    the Architect and

    any

    person authorised

    by the Architect

    access, at all reasonable times,

    to

    the Works

    or

    any place where materials

    or goods

    are

    being manufactured

    or

    stored, work is being prepared

    or

    design is being carried out,

    and shall ensure

    that

    all his sub-contractors and suppliers

    do

    the same.

    12 Architect s representative

    Architect s representative

    12.1 The Architect

    and/or the

    Employer may appoint an architect, engineer, clerk of works

    or

    other

    person as the Architect's representative to be resident on the Site and acting

    under the direction

    of

    the Architect.

    8

    The Architect's representatives' duties shall be to:

    a)

    watch and inspect

    the

    Works;

    b)

    inspect and test materials and goods;

    c)

    check that the types, standards and quality

    of

    the materials and goods, the standard

    and quality

    of

    the Contrac tor s

    workmanship and

    the quality

    of his

    work

    are in

    accordance with the requirements

    of

    the Contract;

    d)

    check, amend as necessary, and where appropriate sign the records submitted to

    him by the Contractor for approval; and

    e)

    carry

    out the

    duties and exercise

    the

    powers delegated to him

    by the Architect

    under clause 12.2,

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    30/114

    12

    Architect s

    representative (Con '

    d)

    and the Contractor shall give the Architect's representative every reasonable facility for

    the performance

    of

    these duties.

    Delegation

    of

    duties

    nd

    powers

    12.2 1) The Architect may, from time

    to

    time, delegate any of his duties and powers under

    the Contract to the Architect's representative as defined under clause 12.1.

    2)

    The delegation shall

    be

    in writing and shall

    be

    copied to the Contractor. It shall

    specify the duties and powers

    that

    are delegated and remain in force until changed

    or

    terminated in writing by the Architect.

    Instruction to bind parties

    12.3 1) The Architect's representative shall issue all instructions

    in

    writing and an instruction

    from the Architect's representative shall bind the parties if:

    a)

    the Architect has the power to give it; and

    b) it is within the terms of the delegation.

    2)

    The Contractor may, within 7 days of receiving an instruction from the Architect's

    representative,

    submit

    an objection to the Architect who shall confirm, reverse or vary

    that instruction within a further 7 days, failing which the instruction shall have no effect.

    3 Variations Provisional Quantities Provisional Items and Provisional

    Sums

    Architect s authority to issue instructions requiring a Variation

    13.1

    1)

    The Architect may issue an instruction requiring a Variation provided that:

    a)

    the Contractor has the right

    of

    reasonable objection to a Variation which imposes

    or changes an obligation or restriction on the Contractor regarding access to the

    Site, use

    of

    any part

    of

    the Site or limitation of working space or working hours and

    the Architect shall, upon receipt

    of

    the Contractor's objection, either confirm or

    withdraw the instruction, and if the instruction is confirmed, the Contractor may

    refer the matter to arbitration under clause 41;

    b)

    the Contractor's written consent is given

    to

    an instruction either nominating a sub-

    contractor to carry

    out

    work included in the Contract Bills which is to be carried

    out

    by the

    Contractor or

    omitting work in order for it to be carried out by others;

    and

    c) the instruction or accumulation

    of

    instructions shall not fundamentally change the

    scope or nature

    of

    the Works.

    2)

    The instruction requiring a Variation shall describe the change required to the design,

    quality or quantity of the Works or the imposition of or change to any obligation or

    restriction on the Contractor and where appropr iate the Architect shall issue revised

    drawings and/or schedules.

    9

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    31/114

    13 Variations, Provisional Quantities, Provisional Items and Provisional Sums (Cont d)

    3)

    The Contractor has

    no

    right to carry out work involving a Variation without a written

    instruction from the Architect or confirmation

    of

    an oral instruction from the Contractor

    except in the event of an emergency as provided for in Clause 4.4.

    Instructions

    for

    Provisional Quantities, Provisional Items nd Provisional Sums

    13 2 The Architect shall issue an instruction for:

    a) the carrying out of work or the provision of goods covered by Provisional Quantities

    or Provisional Items

    in

    the Contract Bills, Nominated Sub-Contracts or Nominated

    Supply Contracts; and

    b) the expenditure of Provisional Sums included in the Contract Bills, Nominated Sub

    Contracts or Nominated Supply Contracts.

    Valuation

    of

    Contractor s work

    13 3 The Quantity Surveyor shall measure and value work carried out by the Contractor in

    response to an Architect s instruction under:

    a) clause 13.1 requiring a Variation;

    b) clause 13.2(a) for the remeasurement of Provisional Quantities and Provisional Items;

    and

    c) clause 13.2(b) to expend a Provisional Sum,

    and the Valuation shall

    be

    made

    in

    accordance with the rules set out

    in

    clause 13.4.

    Valuation rules

    13 4

    1)

    Where the Valuation relates to the carrying

    out

    of:

    3

    a) additional or substituted work which can be properly valued by measurement;

    b)

    work which is the subject of Provisional Quantities or Provisional Items; or

    c) work involved in the expenditure

    of

    Provisional Sums,

    the work shall be measured and shall be valued in accordance with the following rules:

    i) where the work is the same as or similar in character to and is carried out

    under the same

    or

    similar conditions to work priced in the Contract Bills, and

    the Variation does not substantially change the quantity of that work, the rates

    in the Cont ract Bills for that work shall determine the Valuation;

    ii) where the work is the same as or similar in character to work priced in the

    Contract Bills but is not carried out under the same or similar conditions, or

    the Variation substantially changes the quantity

    of

    that work, the rates in the

    ontract Bifls for

    that

    work shall determine the Valuation

    but

    with a fair

    adjustment for the difference in conditions or quantity;

  • 8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)

    32/114

    13 Variations, Provisional Quantities,

    Provisionalltems

    and Provisional Sums (Cont d)

    iii) where the work

    is

    not the same as or similar in character to any work priced in

    the Contract Bills the work shall be valued at fair rates; and

    iv)

    the word conditions in clause 13.4(1) shall mean physical conditions and not

    financial conditions.

    2) Where the Valuation relates

    to

    work which cannot be properly measured and valued

    under

    clause 13.4(1) the work may, with the prior consent of the Architect, be carried

    out as daywork and provided that the Contractor:

    a)

    gives at least 7 days notice to the Architect before carrying out the work,

    or

    where

    the work is required urgently, as much prior notice

    as

    practicable; and

    b) submits vouchers

    spec