Upload
lcreading
View
649
Download
96
Embed Size (px)
Citation preview
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
1/114
2 5 E ITION
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
2/114
ontents
P GE P GE
Articles of Agreement 5
5 5 Nominated Supply Contract
documents
Attestation
8 5 6
Further drawings, details,
descriptive schedules and similar
The
General
Conditions
documents
5 7
Documents
to
be provided to
1 Interpretation and definitions 9
Contractor on time
5 8
Electronic copies
of
drawings
1 1
Governing law·
5 9 Documents on Site
1 2
Singular, plural, masculine and
5 10
Return
of
drawings
feminine
5 11
Submission
of
manuals and
1 3
Method of reference to clauses and assignment of warranties
Articles 5 12 Submission
of
as-built drawings
1 4 Articles of Agreement, Conditions 5 13 Limits to use of documents
and Appendix to be read as a whole
5 14 Issue
of
Architect s certificates
1 5
Clauses divided into sub-clauses to
5 15 Copy of notice to be given
be read as a whole
to Employer
1 6 Definitions
1 7 The role of the Engineer
6
Statutory obligations
24
1 8
Sectional completion
of
the Works
1 9
Communications
6 1 Statutory Requirements
1 10
Notices of default or determination
6 2
Compliance with the Statutory
to be sent by special delivery
Requirements
1 11 Parties to act reasonably and 6 3 Fees or charges
expeditiously
6 4
Statutory undertakers and utility
companies
2
Contractor s obligations
16
7
Setting
out the Works
25
2 1
Contractor s obligations
2 2
Contractor s responsibility Setting out and levels
2 3
Contractor s skill and care
2 4
Contractor to inform Architect if
8
Materials, goods,
workmanship
he finds ambiguities
n
documents
and work
25
3
Master
programme
17
8 1 Types, standards and quality
8 2
Inspection and tests
3 1
Master programme to be submitted
8 3
Materials, goods, workmanship
3 2
Programmes to be updated or work not in accordance with
3 3
Programme and other documents
Contract
not to be documents forming
8 4
Rectifying defects
the Contract
8 5
Dismissal from the Works
4
Architect s
instructions
19
9
Intellectual property rights
27
4 1
Architect may issue instructions up to 9 1
Intellectual property n design
of
the
the issue of the Final Certif icate Works
4 2
Architect to issue instructions n writing 9 2
Intellectual property n materials and
4 3
Compliance with Architect s goods
instructions
9 3
Intellectual property in plant and
4 4
Contractor to carry out preventative equipment
work 9 4
Payment
of
royalties included n
Valuation
5
Documents
forming the Contract
and other documents
2
1
Contractor s site management team
27
5 1
The documents forming the Contract 10 1 Contractor s site management team
5 2
Architect and Quantity Surveyor to 10 2 Construction manager
keep documents available
5 3
Copies of documents for 11
Access
for
the
Architect
to the
Contractor
Works
28
5 4
Nominated Sub-Contract
documents
Contractor to give access
1
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
3/114
P GE
12 Architect s representative
28
12 1 Architect s representative
12.2 Delegation of duties and powers
12.3
Instruction to bind parties
13
Variations, Provisional Quantities,
Provisional
Items and Provisional
Sums 29
13 1
Architect s authority to issue
instructions requiring a Variation
13.2
Instructions for Provisional Quantities,
Provisional Items and Provisional
Sums
13.3 Valuation
of
Contractor s work
13.4 Valuation rules
13.5 Adjustment of Contract Sum
13.6 Contractor s right to be present during
measurement on Site
13.7 Variation necessitated by fault
of
Contractor
13.8 Valuation of Nominated Sub-
Contractor s work or Nominated
Supplier s materials and goods
14
Contract
Bills
33
14 1 Quality and quantity of work included
in Contract Sum
14.2 Standard Method
of
Measurement
of
Building Works
14.3 Errors in Contract Bills
15
Contract
Sum
34
Adjustment
of
Contract Sum
16 Materials
and goods
on or
off-site
34
Property in materials and goods
17 Substantial
Completion and
defects liability
34
17 1
Substantial Completion Certificate
for the Works
17.2
Separate Defects Liability Period for
each Section and Relevant Part
17.3
Rectifying defects
17.4
Defects Rectification Certificate for
the Works
17.5
Separate certificate for each Section
or Relevant Part
17.6
Damage by a Specified Peril
17.7 Other rights and remedies
18 Partial possession by Employer 36
18 1 Part·lal possession
18.2 Substantial Completion
18.3 Completion of rectifying defects
P GE
18.4
Liquidated and ascertained damages
18.5 Damage by a Special Peril
19
Assignment and sub-letting
37
19 1
Assignment
19.2 Sub-letting
i
2
Injury
to
persons
and
property and
indemnity
to
Employer
38
Contractor to indemnify Employer
21
Insurance against injury
to persons
or
property 39
21 1
Employees Compensation Insurance
21.2
Third party liability insurance
21.3 Insurers and terms to be approved
21.4
Policies to be produced
21.5 Event
of
failure
to
insure
21.6
No prejudice to Contractor s indemnity
22
Insurance of the
Works
40
22 1
Alternative clauses
for
Contractors
All Risks Insurance
of
the Works
22.2
Basic requirements
for
Contractors
All Risks Insurance of the Works
22.3
Specific requirements for Contractors
All Risks Insurance
of
the Works
22.4
Insurance
of
the Works to be in
joint
names and period
of
insurances
22.5
Parties obligations if loss or
damage
o urs
22.6
Contractor s payment not more than
insurance proceeds
22.7
Insurance without prejudice to
Contractor s obligations
22A
Insurance of the Works by
the
Contractor
43
22A 1
Contractor to effect Contractors All
Risks Insurance of the Works
22A.2 Insurer to be approved and remedy
if Contractor fails to insure
22A.3 Use
of
annual policy maintained by
Contractor
228
Insurance of
the Works by the
Employer
44
22B 1 Employer to effect Contractors
All Risks Insurance of the Works
22B.2 Remedy if Employer fails to insure
22C
Insurance of existing building
and
insurance
of
the
Works
by the
Employer
44
22C 1
Employer to effect insurance against
Specified Perils to the existing building
r
I
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
4/114
P GE
P GE
22C.2 Employer to
effe t
Contractors
29
Nominated Sub Contractors and
All Risks Insurance
of
the Works Nominated Suppliers
57
22C.3 Remedy if Employer fails to insure
29 1
Nomination of a sub-contractor or a
23
Possession, commencement
and
supplier
completion 45 29.2 Contractor s right of reasonable
objection
23 1 Posse:;sion of Site
29.3 Sub-contractor and supplier
w2:1Tanty
23.2 Commencement and completion
to
Employer
23.3
Postponement
or
suspension 29.4 Contractor s tender
for
work provided
for by
a Prime Cost Sum
24
Damages for non completion
45
29.5 Nomination using the standard
conditions
24 1
Architect to certify Contractor s failure 29.6 Contractor s responsibility for
to complete on time Nominated Sub-Contractors and
24.2 Liquidated and ascertained damages Nominated Suppliers
24.3
Refund if Completion Date revised
29.7
Quantity Surveyor s notification of
interim payments
? )
Extension
of
time
46 29.8 Direct payment
of
Nominated Sub-
Contractors and Nominated Suppliers
25 1 Contractor s first notice of delay 29.9
Extension of time for completion
25.2
Contractor s second notice of Nominated Sub-Contract works or
25.3 Fixing new Completion Date delivery of Nominated Supply
25.4
Contractor s default involved in the
Contract goods
delay 29.10 Substantial completion of Nominated
25.5 Rate of progress Sub-Contract works
25.6
Nominated Sub-Contractors and 29.11 Architect to certify Nominated Sub-
Suppliers to be
kept informed Contractor s failure
to
complete on
time
26
Delay
recovery measures
51 29.12 Early final payment to Nominated
Sub-Contractor or Nominated
26 1
Delay recovery measures Supplier
26.2 Delay recovery proposals
29.13 Re-nomination
26.3 Contractor
to
carry out delay recovery 29.14 Architect s consent
me sures
29.15 Employer not liable to a Nominated
26.4 Extension
of
time to cover shortfall in Sub-Contractor or Nominated
recovering delay
Supplier
26.5 Contractor to be reimbursed for the
cost of preparing the proposal if delay 3 Persons engaged
by
Employer
63
recovery not instructed
30 1 Persons
for
whom the Employer
is
27 Direct loss and/or expense 53
responsible
30.2 Access to Site and permission to
27 1
Contractor s not ice of claim for
carry out work
additional payment 30.3 Contractor to fulfil his obligations to
27.2 Quantity Surveyor s ascertainment
of
persons engaged by the Employer
Contractor s claim
27.3 Contractor s defaul t involved
in
the
31 Facilities
for
statutory undertakers
delay
or
disruption
and
utility
companies
64
27.4
Nominated Sub-Contractor s claim
for additional payment
Access to Site and facilities to canry
out work
28
Notice
of claims for
additional
payment 55
32
Certificates
and payments
64
28 1 Contractor to give notice of claim
32 1 Interim Certificates and interim
28.2 Contractor to submit particulars
valuations
28.3
Condition precedent to Contractor s
32.2 Estimate
of
amount due in Interim
entitlement to additional payment Certificate
32.3
Off-site materials or goods
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
5/114
P GE P GE
32.4 Calculation
of
Retention
37.4 Quantity Surveyor to prepare final
32.5 Retention Rules
account
32.6 Quant ity Surveyor to prepare final 37.5 The final settlement
account
37.6
Architect to notify sub-contractors
32.7
Adjustment
of
the Contract Sum and suppliers
32.8 Issue
of
Final Certificate
32.9 Effect
of
Final Certificate
38
Fluctuations 84
32.10 Proceedings commenced before
Final Certificate 38 1 Fluctuation provisions only applicable
32 11 Proceedings commenced after Final if expressly stated to be
Certificate 38.2 Adjustment for fluctuations occurring
32.12 Effect
of
Architect s certificates
after the Completion Date
32.13 Late payment
39
Notices certificates and other
Surety Bond 73 communications
85
33 1
Contractor to obtain guarantee from Submission of notices, certificates and
insurance company or bank other communications
33.2 Release
of
insurance company or
bank
4
Recovery of money due to the
33.3 Employer s remedy
if
Contractor fails
Employer 85
to deliver bond
Employer s power to recover damages
34
Antiquities
73
. etc.
34 1 Effect
of
finding antiquities
4 Settlement
of
dispu1es 85
34.2
Architect s instructions concerning a
fossil, antiquity or object
41 1
Procedures and Designated
Representatives
35 Detenmination by Employer 74 41.2 Reference to Designated
Representatives
35 1 Default by Contractor
41.3 Reference to mediation
35.2 Insolvency
of
Contractor 41.4 Reference
to
arbitration
35.3 Employer s rights upon notice
of
41.5
Timing of arbitration
default or determination
41.6 Arbitrator s powers
35.4 Consequences of determination 41.7 The place
of
arbitration
35.5 Quanti ty Surveyor to prepare final
41.8 Contractor to continue to proceed
account diligently
35.6 The final settlement
35.7 Delayed commencement
of
Appendix
89
completion works Schedule 1
90
35.8 Other rights and remedies
Form
of
Surety Bond
to
be given y
the Contractor to the Employer
6
Determination by Contractor
78
Schedule
94
36 1
Default by Employer Form
of
Warranty to be given by
the
36.2 Insolvency of Employer
Nominated Sub-Contractor to the
36.3 Consequences
of determination Employer in consideration of
36.4 Contractor to submit final account Nomination
36.5 Quant ity Surveyor to check final
account
Schedule 3
97
36.6 The final settlement Form
of
Warranty to be given y the
36.7 Architect to notify sub-contractors Nominated Supplier to the Employer
and suppliers in consideration
of
Nomination
36.8 Other rights and remedies
Index to The General Conditions
7
Detenmination by Employer or
Contractor
82
37 1
Grounds for determination
37.2 Site security
37.3 Consequences of determination
4
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
6/114
rticles of greement
This greement
is made on the ................................ day of .......................... ...... 20 ..... .
between
of
......................................................................................................................................................
( the Employer ) and
r
····················································································································································
( the Contractor )
Whereas the Employer wishes to have work carried
out
comprising:
( the Works )
at
......................................................................................................................................................
and has had Tender Documents comprising:
a)
a form
of
tender ( The Form of Tender );
b) drawings ( the Contract Drawings );
c)
a specification ( the Specification ); and
d) bills
of
quantities
showing and describing the work to be carried out prepared by
or
under the direction of or at
the
request
of
the Architect;
and where s
the
Contractor
has, based on
the
Tender
Documents
made
in
the
Form
of
Tender his calculation
of
the sum that he will require
for
carrying
out the
Works by pricing the
bills of quantities;
5
r
~ f u : ~
> ??
;,
l
t
f
j
I
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
7/114
and
whereas
the Contractor has given a fully priced copy
of
the bills of quantities ('the Contract
Bills') to
both
the Employer and the Architect;
and whereas the Architect has given each party one
copy of
the Articles of Agreement, the
Appendix
the
Conditions, the Contract Drawings, the Specification and the
Contract
Bills
each signed
by
or
on behalf
of
the parties.
Now it is agreed
as
follows
Article
1
The
Contractor
will carry
out
and complete the Works in accordance with and subject to the
Contract
for the
consideration stated
n
Article
2
Article
2
The Employer will pay to the Contractor the sum
of
Hong Kong Dollars
(HK ................................................................................................................................................
('the Contract Sum')
or
such other sum that becomes payable
n
accordance with and subject
to
the
Contract.
Article
3
The Architect will be
of ................................................................................................................................................
Article
4
The Quantity Surveyor will be
of
................................................................................................................................................
6
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
8/114
rticle5
1) In
the event of the person appointed to act
as
either the Architect or the Quantity Surveyor
ceasing to act, the Employer shall appoint a replacement as soon as practicable.
2) If the Contractor objects
to
the person appointed to succeed either the Architect or the
Quantity Surveyor, the Contractor has the right to refer his objection to an arbitrator
under the Contract provided the reference to arbitration is made within 14 days of the
appointment.
3) The person appointed as the replacement to the rchitect or the Quantity Surveyor
shall continue to act pending the award of the arbitrator appointed under Article 5 2)
but shall immediately cease to act if so directed by the arbitrator s award. In which
case the Employer shall appoint a further replacement as soon
as
practicable.
4) The Contractor shall have the right of objection under Article 5 2) to a further appointment
of either the Architect or the Quantity Surveyor.
A person appointed as the replacement to the Architect or the Quantity Surveyor shall
not
be
entitled to disregand or overrule any agreement, approval, certificate, confirmation,
consent, decision, direct ion, dissent, instruction, notice, notification, opinion, request
or
requirement given
or
made by the person previously appointed save insofar as the
Contract permits.
Article
If a dispute arises under or in connection with the Contract, the parties agree to resolve the
dispute
in
accordance with the dispute settlement procedures
in
clause 41.
I
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
9/114
ttestation
* SIGNED AND SEALED as a deed SIGNED by the Employer
signature of signatory for the Employer) signature of wrtness)
name and office held by signatory for the Employer) name and occupation of witness)
company seal to be impressed here
if
executed as a
deed
by a limited company)
*SIGNED ND SEALED as a deed SIGNED by the Contractor
signature of signatory for the Contractor)
signature of witness)
name and office held by signatory for the Contractor)
name and occupation of witness)
company seal
to be
impressed here
if
executed as a deed by a limited company)
*delete s applicable
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
10/114
The General Conditions
1
Interpretation
and definitions
Governing law
1 1
The Contract shall
be
governed by
and
construed according
to
the laws for the time
being
in
force
in
Hong Kong.
Singular plural masculine and feminine
1 2
Words in the singular include the plural and vice versa and words in the masculine
include the feminine and the neuter.
Method
of
reference to clauses and Articles
1 3 Unless stated otherwise a reference in the Articles the Conditions or the Appendix to
any clause means that clause of the Conditions and a reference
to
an Article means
that Article of the Articles of Agreement.
Articles
of
Agreement Conditions and ppendix to
be
read
as
a whole
1 4
The Articles of Agreement the Conditions and the Appendix are to be read as a whole.
Therefore unless stated otherwise each one must be read subject to any relevant
qualification or modification in any other one.
Clauses divided
into
sub-clauses to
be
read as a whole
1 5 Where a clause is divided into sub-clauses the clause is to be read as a whole and
each sub-clause shall relate to the others as if there was no division between them.
Definitions
1 6 The following words and phrases
in
the Articles of Agreement the Conditions and the
Appendix shall have the meanings given below unless the context
in
which they appear
requires otherwise or the Articles the Conditions or an item or entry in the Appendix
provides otherwise:
Appendix: the ppendix to the Conditions.
Architect: the person named as the Architect in Article 3 or any successor appointed
under Article 5.
Articles
or
Articles
of
Agreement: the Articles of Agreement
to
which the Conditions are
annexed.
Commencement Date: the date stated in the Appendix for the commencement of the
Works.
communication: the giving submitting or issuing of without limitation any agreement
approval authorisation certificate confirmation consent decision delegation direction
dissent determination endorsement instruction notice notiftcation opinion request
requirement or statement.
Completion Date: the date stated
in
the Appendix by which the Works or a Section are
to be completed or such later date to
be
fixed by the Architect under clause 25.
9
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
11/114
Interpretation and definitions (Cont d)
1
Conditions the Conditions of Agreement and Schedule of Conditions of Building Contract
lor use in the Hong Kong Special Administrative Region, Private Edition With Quantities
and any Special Conditions.
Contract:
the Articles of Agreement, the Appendix, the Form of Tender submitted by
Contractor, the Employer s letter of acceptance of the Contractor s tenoer and any
correspondence between the parties expressed to form part of the Contract, the Special
Conditions, if any, the Conditions, the Contract Drawings, the Specification and the
Contract Bills.
Contract Bills the priced bills of quantities referred to in the recitals of the Articles and
submitted
by
the Contractor with his tender, or a certified true
copy
of those bills of
quantities.
Contract Drawings
the drawings referred to
in
the first and fourth recitals
of
the Articles
and enumerated as such
in
the Contract Bills or the Specification.
Contract Sum: the sum stated
in
Article 2, or such other sum that becomes payable in
accordance with the Contract.
Contractor the person named as the Contractor in the Articles.
Contractors
All
Risks Insurance of the Works insurance which provides cover against
physical loss of or damage to the Works, temporary works and materials and goods, as
described in clause 22.
Date
for Possession of
the Site
the date or dates for the possession of the whole or
parts
of
the Site stated in the Appendix under the reference to clause 23.1.
Date ofSubstantial Completion the date stated in the Substantial Completion Certificate
for the Works or a Section, issued by the Architect under clauses 17 1 and 17.2.
day a calendar day and includes Sundays and other days which are general holidays
by virtue
of
the General Holidays Ordinance (Chapter 149, Laws of Hong Kong).
Defects Liability Period
the period stated
in
the Appendix under the reference
to
clause
17.3, commencing on the day after the Date of Substantial Completion of the Works or
a Section or the day after the Relevant Date of Substantial Completion of a Relevant
Part.
Defects Rectification Certificate a certificate issued by the Architect to the effect that
all defects, shrinkages and other faults have been rectified in accordance with the
Contract, as described
in
clauses 17.4 and 17.5.
direct /ass and/or expense the monetary consequences that flow naturally without
other intervening cause and independently of special circumstances because of the
direct consequences of a qualifying event and which are not otherwise reimbursed
to
the Contractor.
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
12/114
Interpretation and definitions (Cont d)
Domestic Sub Contractor: a person, other than a Nominated Sub-Contractor, to whom
the Contractor sub-lets any part of the Works and includes a labour only sub-contractor.
Employer: the person named as the Employer in the Articles.
Engineer: a person engaged as a member of the Employer s design team for the design
and supervision of one or more
of
the geotechnical, civil, structural or building services
elements of the Works, as referred
to
in clause 1.7.
Excepted Risks: a) Any consequence of war (whether war be declared or not)
in
which
Hong Kong is actively engaged, the invasion of Hong Kong, acts of terrorists in Hong
Kong, civil war, rebellion, revolution or military or usurped power in Hong Kong, riot,
commotion or disorder in Hong Kong other than amongst the employees of the
Contractor or any person for whom the Contractor is responsible;
b)
the
Architect s design
of
the Works insofar as damage, loss
or
injury is the direct consequence
of
the design;
c) a cause due to any neglect or default of the Architect, the Employer
or any person for whom the Architect or the Employer is responsible;
d) ionizing radiation or contamination by radioactivity from any nuclear
fuel or from any nuclear waste from the combustion of nuclear fuel, radioactive toxic
explosive or other hazardous properties of any explosive nuclear assembly or nuclear
component thereof;
and e) pressure waves caused by aircraft or other aerial devices travelling
at sonic or supersonic speeds.
Final Certificate: the certificate issued by the Architect stating the Final Contract Sum
and the total of the amounts of Interim Certificates
to
be set off against that sum, as
described in clause 32.8.
Final ontract Sum: the sum resulting from the adjustment
of
the Contract Sum in
accordance with the Contract.
Form of Tender: the form of tender referred to in the first recital of the Articles as being
part of the Tender Documents.
Hong Kong: the Hong Kong Special Administrative Region.
Interim Certificate: a certificate issued by the Architect stating the amount of an interim
payment due
to
the Contractor, as described in clause 32.1.
Limit of
Retention: the amount stated in the ppendix under the reference to clause
32.4 as the limit to the amount of Retention to be held by the Employer on the payment
for the Contractor s work in progress.
Nominated Sub Contract: the sub-contract between the Contractor and a Nominated
Sub-Contractor.
11
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
13/114
I
Interpretation nd definitions
(Cont'd)
12
Nominated Sub Contractor: a sub-contractor nominated by the Architect under clause
29 to carry out work forming part
of
the Works.
Nominated Supplier: a supplier nominated by the Architect under clause 29 to supply
materials
or
goods for incorporation into the Works.
Nominated Supply Contract the
supply
contract between the Contractor and a
Nominated Supplier.
parties: the Employer and the Contractor.
Period of Interim Certificates: the period stated in the Appendix under the reference to
clause 32.1 as the interval between the issuing of Interim Certificates.
person: an individual, firm, partnership,
or
body
corporate.
person
for
whom
the Contractor is responsible: the Contractor's servants or agents,
sub-contractors, suppliers, persons employed or engaged in connection with the Works
and persons who may properly be on the Site upon or in connection with the Works
other than the Employer
or
any person for whom the Employer is responsible.
person
for
whom the Employer is responsible: the Employer's servants or agents and
the persons listed in clause 30.1.
postpone to defer the commencement
of
operations on
an
activity.
Prime
Cost
Sum: a sum either provided in the Contract Bills
or
arising
as
described in
clause 29.1 for work to
be
carried
out
by a Nominated Sub-Contractor or for materials
or goods to
be
obtained from a Nominated Supplier.
Provisional/tern: an item
of
work identified as provisional in the Contract Bills to be
carried out by the Contractor if instructed to
do
so by the Architect under clause 13.2.
Provisional Quantities: an estimated quantity
of work
identified as provisional in the
Contract Bills, where the actual quantity could not be accurately determined when the
bills of quantities were prepared, to be carried out by the Contractor if instructed to do
so by the Architect under clause 13.2.
Provisional Sum: a sum provided
in
the Contract Bills for work or for costs, which could
not
be
entirely foreseen, defined or detailed when the bil ls of quantities were prepared,
to be paid to the Contractor if instructed by the Architect under clause 13.2 to carry out
such work or incur such costs.
Quantity Surveyor: the person named as the Quantity Surveyor in Article 4,
or
any
successor appointed under Article 5.
Relevant Date: the date upon which the Employer took possession
of
a Relevant Part
under clause 18.
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
14/114
Interpretation and definitions (Cont d)
Relevant Part: the
part of the Works
or
part of a Section taken possession of
by
the
Employer under clause 18 before Substantial Completion of the Works or that Section.
Retention: the sum
calculated
in
accordance
with clause 32.4 and retained by the
Employer from the gross valuation
of
the Contractor s work in progress included in n
Interim Certificate.
Retention Percentage: the percentage entered
in
the Appendix under the reference to
clause 32.4, used to calculate the Retention
in
accordance with the rules set out in that
clause.
Section: a part of the Works for which a separate Completion Date is stated in the
Appendix where the Contract provides for sectional completion of the Works.
Site: the land and
other
places provided
by
the Employer for the purpose
of
carrying
out the Works.
Special Condition: a condition of contract expressly referred to as a Special Condition
of Contract, which adds to or amends the Conditions and is annexed to the Conditions.
special delivery: a communication which is either delivered by courier or sent by registered
post
or recorded delivery.
Specialist Contractor: a person, not being a statutory undertaker
or
utility company as
referred to
in
clause 6.4(1), engaged by the Employer to carry out work directly connected
with or ancillary to but not forming part of the Works, s described in clause 30.
Specialist Works: work directly connected with or ancillary to but not forming part
of
the
Works, to be carried out by a Specialist Contractor.
Specification: the specification referred to
in
the first and fourth recitals
of
the Articles
which describes, without limitation, the types, standards and quality of the materials
and goods to
be
used, the standard and quality
of
workmanship required, the manner
in which work processes are to be carried out, the performance requirements and other
matters and things relating to the construction
of
the Works.
Specified Perils: fire, lightning, explosion, storm, tropical cyclone, flood, bursting
or
overflowing of water tanks, apparatus or pipes, earthquake, aircraft and other aerial
devices or articles
dropped
from them.
Standard Conditions
of
Nominated Sub Contract: the Standard Form of Sub-Contract
for use where the sub contractor is nominated under the Standard Form of Building
Contract.
Standard Conditions
of
ominated
Supply
Contract: the Standard Form of Supply
Contract for use where
the
supplier
is
nominated under the Standard Form of Building
Contract.
13
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
15/114
'
1
Interpretation and definitions (Cont d)
14
sub contractor: a person who enters into a sub-contract with the Contractor to carry
out work forming part
of
the Works and includes a Domestic Sub Contractor and a
Nominated Sub-Contractor.
Substantial Completion: the state of completion where the Works or a Section have
been substantially completed to the Architect s satisfaction and have passed the required
inspections and tests, as referred to in clauses 17.1 ·and 17.2.
Substantial Completion Certificate: a certificate issued by the Architect stating the date
when in his opinion the Works or a Section have reached Substantial Completion.
substantially completed: the state
of
completion where the Works or a Section may not
be absolutely completed or entirely free from defects but have reached the stage where
they can be taken over and used by the Employer for their intended purpose and where
the unfinished items
of
work and the remaining defects then patent are only
of
a minor
nature and extent and their complet ion or rectification will not unreasonably interfere
with or interrupt the taking over of the Works or Section.
supplier: a person who enters into a
supply
contract with the
Contractor
to
supply
materials
or
goods and includes a Nominated Supplier.
suspend: to cease operations for a period of time on an activity in which
work
has
commenced.
Tender Documents: the documents and drawings referred to
in
the first recital
of
the
Articles,
or
a certified true copy
of
those documents and drawings.
Valuation: the valuation made by the Quantity Surveyor, in accordance with the valuation
rules under clause 13.4, of work carried out in response to an Architect s instruction
requiring a Variation, remeasurement of Provisional Quantities and Provisional Items or
to expend Provisional Sums.
Variation: a change instructed by the Architect to the design, quality or quantity of the
Works including:
0)
an alteration
to
the type, standard or quality of any
of
the materials or goods
comprising the Works;
ii) the addition, substitution or omission of work; and
(iii)
the removal from the Site
of
materials or goods and the demolition and removal
of work
except
where provided for in the Contract or where the materials,
goods
or
work are not in accordance with clause 8.1;
or the imposi tion of an obligation or restriction instructed by the Architect regarding:
iv) access to the Site or use
of
any parts
of
the Site;
v) limitation of working space;
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
16/114
1 Interpretation and definitions
(Cont d)
vi) limitation of working hours; or
vii) the sequence of carrying out
or
completing work;
or the addition or alteration to or omission of such obligations or restrictions imposed
by the Contract .
Works the
work
briefly
described
in the Articles
of Agreement and
shown upon,
described by or referred to in the Contract including any change made to the
work
in
accordance with the Contract.
he role of the Engineer
1 7 1)
The Architect may, from time to time, delegate any of his duties and powers under
the Contract to an Engineer.
2) The delegation shall be in writing and copied to the Contractor. It shall specify the
duties and
powers
that are
delegated
and shall remain in
force
until
changed or
terminated in writing by the Architect.
3) Where in the
context of
the wording
of
a clause in the Conditions or where
recognition of the Engineer s statutory responsibility requires it, the word Architect in
the Conditions shall be deemed to be read as Engineer .
Sectional completion of the Works
1 8 1)
Where sectional completion of the Works
is
provided for in the Contract, a reference
to the Works shall be deemed to mean the Works
or
a Section.
2)
The phrase the whole of the Works means the Works including all Sections.
Communications
1 9
Unless otherwise stated, all notices, certificates and other communications under the
Contract between the Employer, the Architect, the Quantity Surveyor and the Contractor
shall be in writing.
Notices of default or determination to
be sent
by special delivery
1 10
All notices
of
default
or
determination under clauses 35, 36 and 37 shall be sent by
special delivery.
Parties to
ct
reasonably
nd
expeditiously
1 11 1) The parties, the
Architect
and the Quantity Surveyor shall act reasonably and
expeditiously in all matters under the
Contract
including, without limitation, giving
or
withholding consent, approval or agreement, valuing Variations and certifying.
2)
All requirements shall be reasonable requirements and, without limitation, the term
to
the
Architect s satisfaction
shall be construed as meaning to the Architect s
reasonable satisfaction
and
the term practicable shall mean reasonably practicable.
15
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
17/114
'
i
I
2 Contractor s obligations
Contractor s obligations
2.1 1) The Contractor shall
in
compliance with the Contract:
a) organize, manage, plan and supervise the carrying out
of
the Works;
b) co-ordinate the carrying out
of
the Works including the interface between his own
work and the work carried out by each Domestic Sub-Contractor, Nominated Sub
Contractor, Specialist Contractor, statutory undertaker and utility company;
c) assist in the
co-ordination
of their work by each
Domestic Sub-Contractor,
Nominated Sub-Contractor, Specialist Contractor, statutory undertaker and utility
company with the work of each
of
the others;
d) design sufficient, safe and adequate temporary works to enable the Contractor to
comply with his other obligations under the Contract, except where the design
of
any temporary works is a statutory obligation
of
any person other than the Contractor
or
any person for whom the Contractor is responsible;
e) carry
out
any work involved in the development of the Architect s design that may
be specified in the Contract;
f) prepare all shop drawings and co-ordination drawings required by the Contract;
g)
carry out the maintenance
of
mechanical and electrical equipment where required
to do so by the Contract for the period
of
time so specified;
h) take responsibility for the care
of
the Works, except for loss or damage arising
from the Excepted Risks, from the Commencement Date until 14 days after
Substantial Completion
of
the Works or 14 days after the determination
of
the
employment of the Contractor, whether valid
or
not, whichever is earlier,
except
that the Contractor s responsibility for the care
of
the Works shall terminate in
relation to a Section or Relevant Part 14 days after the Employer takes possession
of that Section or Relevant Part; and
i) carry
out
the construction of and complete the Works using materials, goods and
workmanship
of
the types, standards and quality specified
in
the Contract.
2} Where the Contract requires the Contractor to prepare details, to carry out the
design or the development
of
the Architect s design, unless the requirement
of
fitness
for
purpose is specifically stated, the design or the development
of
the
Architect s design shall
be
carried out with reasonable skill and
care
and
the
Contractor shall be responsible to the Employer for such work.
Contractor s responsibility
2.2 The Contractor shall remain wholly responsible for carrying
out
and completing the
Works in accordance with the Contract whether or not the Architect or the Architect s
representative, if appointed:
16
a) visits the Works or a place where materials or goods are being manufactured or
stored, work is being prepared, or design is being carried out;
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
18/114
2
Contractor s
obligations (Cont d)
b) inspects or tests any materials or goods;
c) exercises his
powers
under clause
8; or
d)
includes the value of any materials, goods or work in an Interim Certificate.
Contractor s skill and care
2.3
The Contractor shall exercise
in
the performance
of
his obligations under the Contract
all the skill, care and diligence to
be
expected of a competent contractor experienced
in carrying out work of a similar scope, nature and size to the Works.
Contractor to inform rchitect if he finds ambiguities in documents
2.4 1) The Contractor shall immediately inform the Architect if the Contractor finds an
ambiguity
or
discrepancy in
or
divergence between the following documents:
a) the Contract Drawings;
{b) the Specification;
c) the Contract Bills;
{d) the descriptive schedules .and other similar documents referred to in clause 5.3(d);
e) the Nominated
Sub-Contract
documents and the Nominated Supply Contract
documents referred to in clauses 5.4 and 5.5; and
{f) the further drawings, details, descriptive schedules and similar documents referred
to in clause 5.6 provided from time to time during the carrying
out
of the Works.
2) If the Architect agrees with the Contractor, he shall issue an instruction to resolve
the ambiguity,
discrepancy or
divergence as soon as practicable after receipt
of
the
notice from the Contractor
and
the instruction shall, if considered appropr iate by the
Architect, require a Variation.
Master
progr mme
Master programme to be
submitted
3 1
1)
The Contractor shall submit to the Architect within the time stated in the Appendix:
a) 6 copies
of
a master programme prepared for his own purposes for organizing,
managing, planning, supervising and co-ordinating the carrying
out
of the Works
and completing
them
by the Completion Date;
{b)
a method statement describing the methods of construction and the resources
that he intends to use to carry out the Works;
c) a list
of the
names and details
of
the site management and supervisory team
personnel, referred to
in
clause
10,
with job descriptions and details of their durations
on the Site; and
7
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
19/114
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
20/114
3 Master programme (Cont d)
Programme
and other
documents
not
to
be documents
forming the ontract
3.3 Neither the programme, the method statement
nor
other
document
submitted under
clause 3 shall be documents forming the Contract and no comment made by the Architect
on any of these documents shall impose
an
obligation on the Employer.
4 Architect s instructions
Architect
may
issu
instructions up to the
issu
of the Final ertificate
4 1 The Architect may issue instructions that he is empowered to issue under the Conditions
at any time up to the issue of the Final Certificate including during the time that the
Contractor may be
carrying
out work
after the Date
of
Substantial Completion of the
Works, but he shall not instruct a Variation after the issue
of
the Defects Rectification
Certificate for the Works, a Section or a Relevant Part as the case may be.
Architect
to issue instructions in writing
•
2
1) The
rchitect
must
issue all
instructions
in
writing
in
accordance
with clause
1.9. All oral instructions given must be confirmed in writing within 5 days of giving the
oral instruction. If the Architect gives an oral instruction
that
the Contractor believes
requires a Variation it shall have no immediate effect, the Contractor shall confirm the
oral instruction requiring a Variation in writing to the Architect within 7 days of it being
issued and if not dissented to in writing by the Architect within 7 days from his receipt
of the Contractor s confirmation the Variation shall take effect on the expiry
of
the latter
7 days.
2)
Where an Architect s oral instruction requiring a Variation has been confirmed in
writing by the Contractor under clause 4.2(1) and not dissented to by the Architect, the
Architect shall issue the written instruction for a Variation for record purposes as soon
as practicable after the Contractor s confirmation.
ompliance with
Architect s
instructions
4 3 1)
Subject to clauses 4.2(1) and 4.3 2), the Contractor shall comply with all instructions
that the Architect is empowered by the Conditions to issue as soon as practicable. If
there is a d isagreement between the Architect and the Contractor as to whether an
instruction involves a Variation, the Contractor shall comply with the instruction and
may,
if
he is not satisfied, require the disagreement to be resolved under clause 41.
2) If the Contractor disagrees that the Architect is empowered by the Conditions to
issue an instruction he may within 7 days of receipt
of
that instruction require the
disagreement to
be
resolved under clause 41 .
3) If the Contractor does not begin to comply with an instruction within 7 days after
receipt of a written notice from the Architect requiring compliance with that instruction
in accordance with clause 4.3(1) and the Architect issues a certificate to that effect by
special delivery, the Employer
may,
without prejudice to his other rights and remedies,
engage other persons to carry out that instruction. All additional costs incurred by the
Employer in
connection
with the employment of the
other
persons to carry out that
instruction may be recovered from the Contractor under clause 40 or as a debt.
19
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
21/114
I
I
4 Architect s instructions (Cont d)
4)
The Contractor shall provide reasonable access to the persons engaged by the
Employer under clause 4.3(3) and shall permit them to carry out their work without
hindrance.
ontractor to carry ut preventative work
4.4
1)
In the event of an emergency caused by an event arising out
of
or in connection
with the Works that threatens the safety of the Works or any person or property, the
Contractor shall immediately:
5
5 1
2
a) carry out
all
necessary preventative work
without
waiting for
an Architect s
instruction; and
b) immediately inform the Architect of the emergency and
of
the action
taken
or
preventative work being carried out.
2)
The Architect shall issue an instruction confirming a Variation for preventative work
carried out initially without an Architect s instruction, provided that the
work
was not
required to
be
carried out in fulfilment of a Contractor s obligation or because of a
breach of contract or other default by the Contractor or any person for whom the
Contractor is responsible.
Documents forming the Contract and other documents
he
documents forming the ontract
1)
The documents forming the Contract shall be:
a) the Articles of Agreement and the Appendix;
b) the Form of Tender submitted by the Contractor together with the Employer s letter
of acceptance of the Contractor s tender and any correspondence between the
parties expressed to form part of the Contract;
c) the Special Conditions if any;
d) the Conditions; and
e)
the Contract Drawings, the Specification and the Contract Bills.
2) The order
of
precedence
of
the documents forming the Contract shall be as listed
in paragraphs
a)
to
e)
above and:
a) for the purpose of adjusting the Contract Sum the Contract Bills shall take
precedence over the Contract Drawings and the Specification; but
b)
for all other purposes including carrying out the construction
of
and completing
the Works the Contract Drawings and the Specification shall take precedence over
the Contract Bills.
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
22/114
5
Documents
forming
the
Contract and other documents (Cont d)
Architect and Quantity Surveyor t keep documents available
5.2 The Archi tect shall provide two copies, certified on behalf of the Employer as a true
copy, of each of the documents forming the Contract and two certified true copies of
each of the documents forming the Nominated Sub-Contracts and the Nominated Supply
Contracts as referred to in clauses 5.4 and 5.5, and the Architect and the Quantity
Surveyor shall. both keep one of each
of
these copies available at all reasonable. times
for the purposes
of
the Contract.
Copies
of
documents
for
Contractor
5.3 As soon as practicable after the acceptance of the Contractor s tender the Architect
shall provide the Contractor, without charge, with:
a) 1 copy, certified on behalf of the Employer as a true copy,
of
each of the documents
forming the Contract;
b) 3 further copies of the Contract Drawings and the Specification;
c) 3 copies
of
the unpriced bills of quantities; and
d) 3 copies of any descriptive schedules
or
other similar documents prepared by
or
under the direction of the Architect before the acceptance of the Contractor s tender
and necessary for use in carrying
out
the Works.
Nominated Sub Contract documents
5.4 The Architect shall provide the Contractor, without charge, with 3 further copies
of
the
Nominated Sub-Contract, the sub-contract drawings, the sub-contract specification,
the sub-contract bills of quantities or schedule of quantities and rates,
as
the case may
be, descriptive schedules and other similar documents as soon as practicable after the
award of each Nominated Sub-Contract.
Nominated
Supply
Contract documents
i The Architect shall provide the Contractor, without charge, with 3 further copies
of
the
Nominated Supply Contract, the
supply contract drawings, the
supply
contract
specification, the supply contract bills of quantities
or
schedule of quantities and rates,
as the case may be, descriptive schedules and other similar documents as soon as
practicable after the award
of
each Nominated Supply Contract.
Further drawings details descriptive schedules and similar documents
5.6
1)
The Architect shall provide the Contractor, without charge, and from time to time
during the carrying out
of
the Works, with 3 copies
of
all further drawings, details,
descriptive schedules or similar documents (referred to in clause 5 as the supplementary
documentation ) that, in the Architect s opinion, are reasonably necessary for use
in
carrying out the Works
or
to explain
or
amplify the Contract Drawings, the Nominated
Sub-Contract drawings and the Nominated Supply Contract drawings.
2)
If
in
the Contractor s opinion
he
requires more supplementary documentation than
that provided by the Architect under clause 5.6(1) he shall submit a written request to
the Architect specifying what further supplementary documentation
he
requires.
21
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
23/114
'
'
I
. :
.
:: i
.
I '
i
' I
.
I
i .
I
,I
·
.,
i,
'I
i
5 Documents forming the
Contract
and other documents (Cont'd)
5 7
(3)
It shall be
at the
sole
discretion of the
Architect to decide which, if any,
of the
supplementary documentation requested by the Contractor
the
Architect will provide.
ocuments to be
provided
to ontractor on time
(1)
The supplementary documentation referred to in clause 5.6 shall be provided when,
having regard to the progress of
the
Works and the Contractor's procurement, fabrication
and other lead in times, it is reasonably necessary for
the
Contractor to receive it.
(2)
The Contractor shall inform
the
Architect sufficiently in advance
of the
time that he
requires the supplementary documentation to enable the Architect to fulfil his obligations
under clause 5.7(1).
Electronic copies of drawings
5 8 If,
within 14 days after the acceptance
of
the Contractor's tender,
the
Contractor requests
the
Architect
in
writing
to do
so,
the Architect
shall
provide
the
Contractor,
without
charge with electronic
copies of
all
of the
drawings required
to
be provided under
clauses 5.3, 5.4, 5.5 and 5.6
that
have been produced electronically
in
lieu of
the
hard
copies referred to in
those
clauses.
ocuments on Site
5 9 The Contractor shall keep
on the
Site so as to be available to the Architect and the
Quantity Surveyor at all reasonable times 1 copy of:
5 10
22
(a)
the Contract Drawings;
(b)
the
Specification;
(c)
the
unpriced bills
of
quantities;
(d) the programmes and other documents referred to in clause 3;
(e)
the descriptive schedules
or
other
similar
documents referred to in clause 5.3
prepared by the Architect before
the
acceptance
of the
Contractor's tender;
(f) the Nominated Sub-Contract documents and Nominated Supply Contract
documents referred to in clauses 5.4 and 5.5;
(g)
the
supplementary documentat ion referred to in clause 5.6 provided by the Architect
from time to time
during
the carrying
out
of the Works; and
(h) all
other documents
that the Contractor is required
to
keep on Site in fulfilment of
his statu tory obligations.
Return of drawings
The Contractor
shall return
to
the
Architect
all drawings
specifications details
descriptive schedules and
other
similar documents provided under clause 5,
if
required
by
the
Architect to
do
so,
either upon the
issue of
the
Final
Certificate
or
the
final
conclusion of any proceedings
to
which
the
Contractor is a party, whichever is later
and the Contractor may take copies for
his
own records.
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
24/114
5
Documents
forming the Contract and other documents (Cont d)
Submission
of
manuals and assignment
of
warranties
5.11
1)
The
Contractor
shall
submit
to the Architect all the operation and maintenance
manuals received by the Contractor.
2) The Contractor shall assign to the Employer (so far as he is lawfully able to
do
so)
the benefits of all suppliers and sub-contractors warranties, guarantees
or
other ancillary
agreements for materials, goods
or work
insofar as they are required by the Contract,
Nominated Sub-Contracts or Nominated Supply Contracts, other than the
direct
warranties to the Employer required under the Nominated Sub-Contracts and Nominated
Supply Contracts, within 60 days after the issue of the Substantial Completion Certificate
for the whole of the Works.
-
3)
Where the
Contractor
assigns the benefit
of
a suppliers or
sub-contractors
warranty, guarantee or other ancillary agreement for materials, goods or work to the
Employer, the Employer shall exhaust all remedies under the warranty, guarantee
or
ancillary agreement before enforcing the terms
of
the Contract against the Contractor
in
respect of any matter for which a cause of action exists against the sub-contractor or
supplier under the warranty, guarantee
or
other ancillary agreement.
Submission
of
as built drawings
5.12 1) The Contractor shall submit to the Architect 2 copies
of
a complete set
of
the as
built drawings that are required by the Contract, Nominated Sub-Contracts or Nominated
Supply Contracts within 60 days
of
the issue
of
the Substantial Completion Certificate
for the whole
of
the Works.
2)
Where the
drawings
referred to under clauses 5.3, 5.4, 5.5 and 5.6 have been
issued electronically, the Contractor shall, if so required by the Architect, provide the
as-built drawings electronically.
Limits to use
of
documents
5.13 1) The Contractor shall not use any
of
the documents referred to in clause 5 for any
purpose other than the Works and any proceedings relating to the Contract.
2)
Neither the Employer, the Architect
nor
the Quantity Surveyor shall divulge any of
the rates or prices in the Contract Bills or use them except for the purposes of the
Contract and any proceedings relating to the Contract.
Issue
of
Architect s certificates
5.14 The Archi tect shall issue all certificates to the Employer and shall, at the same time,
issue a copy of each certificate to the Contractor.
Copy
of
notice to be given to Employer
5.15 Whenever the Architect issues a notice to the Contractor by special delivery, he shall
issue a copy of the notice to the Employer at the same time.
3
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
25/114
6
Statutory
obligations
Statutory Requirements
6.1 The Contractor shall comply with and give the notices required
by
any Ordinance,
regulation, rule, order
or
by-law applicable to the Works ('the Statutory Requirements')
which are to be complied with by the Contractor.
ompliance with the Statutory Requirements
6.2 1) The Contractor shall immediately notify the Architect if the Contractor finds that
carrying
out
the Works in compliance with the Contract or with an Architect's instruction
requiring a Variation will infringe the Statutory Requirements.
2) If the Archi tect agrees with the Contractor, he shall issue an instruction to resolve
1
the infringement as soon as practicable after receipt
of
the notice and the instruction
shall, if appropriate, require a Variation.
Fees
or
charges
6.3
1)
The Contractor shall pay all fees or charges legally demandable under the Statutory
Requirements.
6.4
4
2)
The net amount of those fees or charges paid by the Contractor shall be added to
the Contract Sum unless they:
a)
are
fees or
charges
that the
Contractor is liable to pay under the
Statutory
Requirements, and the liability was known prior to the date for submission of tenders
and has not been increased;
b)
are priced, or are required to be allowed for,
in
the Contract Bills;
c)
are provided for by a Provisional Sum;
or
d) arise out of a default, delay or failure by the Contractor or a sub contractor to
comply with the Statutory Requirements or the Contract
Statutory undertakers nd utility companies
1)
Statutory undertakers
or
utility companies carrying out work in pursuance of their
statutory obligations and not having a contractual relationship with the Employer, the
Contractor
or
any person
for
whom the Contractor is responsible shall be classified as
statutory undertakers or utility companies and not Nominated Sub Contractors or
persons engaged
by
the Employer under clause 30 and the fees or charges for their
work shall be regarded as fees and charges legally demandable under the Statutory
Requirements and processed in accordance with clause 6.3.
2) The Contractor shall allow those persons reasonable access to the Site, permit
them to carry out their work and provide them with the facilities referred to in clause 31.
3)
Statutory undertakers
or
utility companies engaged under contracts with the
Employer to carry out work directly connected with or ancillary to but not forming part
of
the Works shall be classified
as
Specialist Contractors
as
referred
to
in clause 30.1.
F
l
l
f
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
26/114
Statutory obligations (Cont d)
4) tatutory undertakers
or utility
companies
engaged
under contracts
with the
Contractor or a Nominated Sub-Contractor to carry out work forming part of the Works
shall be classified as sub-contractors or sub-sub-contractors as the case may be.
Setting out the Works
etting out nd levels
1)
The Architect shall provide the Contractor with accurately dimensioned setting out
drawings containing the information and levels necessary for him to set out the Works.
2)
The Contractor shall be responsible for accurately setting out the Works and shall
correct any error arising from inaccurate setting out at his own
cost
unless the Architect
accepts the error without correction subject to a reasonable reduction in the Contract
Sum having regard to the Employer s loss of value of the Works and any expenses that
he may incur arising from the inaccurate setting out.
Materials goods workmanship and wor
Types standards nd quality
1) The Contractor
must
provide all materials and goods
of
the types, standards and
quality described in the Contract to the Architect s satisfaction that the Contractor has
met these requirements.
2)
Where the Contractor is responsible for the selection
of
the materials and goods in
accordance with a performance specification
or
otherwise, the materials and goods
must be fit for the purpose stated in the Contract.
3) If any of the specified materials or goods are not procurable, then the Contractor
shall submit alternative proposals for materials or goods
of
similar type and standard
and of comparable quality and price
to
the Architect for his approval; and
a)
if the proposed alternative materials
or
goods are of similar type and standard and
of comparable quality and price to those specified, and the Architect approves
them, the
substitution
of the alternative materials or goods for
those
specified
shall be made with no adjustment to the Contract Sum; or
b) if the proposed alternative materials
or
goods
are
not of similar type and standard
or comparable quality
or
price to those specified, and the Architect approves them,
he shall instruct a Variation to adjust the type, standard, quality or price.
4)
The Contractor shall provide the Architect, upon his request, with vouchers, test
certificates or other evidence to satisfy the Architect that the materials and goods comply
with the Contract.
5) The Contractor s workmanship must be of the standard and quality described in
the Contract
to
the Architect s satisfaction.
5
I
I
i
I
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
27/114
8 Materials
goods,
workmanship and work
(Cont d)
6) All work must be carried out in a proper and workmanlike manner in accordance
with the Contract
or, in
the absence
of
any specific performance requirements, to the
Architect s satisfaction.
Inspection
nd
tests
8 2 1)
The Contractor shalf carry out
or,
if
so required by the Contract, arrange for a third
party
to
carry out, the tests specified in the Contract
in
compliance with the specified
testing procedures.
2) In addition to
the
tests specified in the Contract,
the
Architect may
instruct
the
Contractor
to
open up for inspection any work
covered
up and
to
carry out,
or
arrange
for
a third
party to carry
out,
tests
of materials
and goods
{whether
or not
already
incorporated in the Works) and work which has been carried out.
3) The cost of the testing, the opening up for inspection and any consequential making
good shalf
be
added to the Contract Sum unless:
a) the inspection
or
test is provided
for
in the Contract Bills;
b) the inspection
or
test shows
that
the materials, goods, workmanship
or
work are
not in accordance with clause 8;
c)
the inspection
or
test
was considered necessary
by
the Architect because, as a
result
of
the failure of a previous inspection
or
test, further investigation of similar
materials goods
or
work was required
to
establish
to
his
satisfaction their
compliance with clause 8;
or
d) the work was carried
out
without the inspection notice required by the Contract.
Materials goods workmanship or work
not
in accordance with Contract
8 3
The Architect may,
if
any materials, goods, workmanship
or
work are
not
in accordance
with the Contract, instruct:
6
a) the removal from the Site and the replacement
of
materials and
goods
that are
not
in
accordance with clause
8;
b)
the repair
or
demolition, removal and reconstruction of work which,
in
respect
of
materials, goods
or
workmanship, is
not
in accordance with clause 8;
c)
the acceptance
without
replacement
or
reconstruction
of some or
all
of
the
materials,
goods
or work
that are
not
in
accordance
with clause
8,
subject
to
a
reasonable reduction in the
Contract
Sum having regard
to
the reduction in the
value of the materials, goods
or
work; and
d) a Variation
for
alternative remedial work to sorne
or
all of the materials,
goods or
work as is reasonably necessary in consequence
of
them
not
being
in
accordance
with clause
8,
with no extension of time
or
addition
to
the
Contract Sum.
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
28/114
8
8 4
8 5
9
9.1
9 2
9 3
Materials, goods, workmanship and work (Cont d)
Rectifying defects
The Architect may instruct the Contractor to rectify defects which appear before the
commencement of the Defects Liability Period.
Dismissal from the Works
The Architect may instruct the Contractor to dismiss any individual from the Works for
incompetence, misconduct or other similar reasons.
Intellectual
property rights
Intellectual property in design of the Works
The Contractor shall pay the cost of any royalty, license fee or other sum legally
demandable for the use of intellectual property in connection with the design
of
the
permanent Works other than works under a Nominated Sub-Contract or materials and
goods supplied under a Nominated Supply Contract, and the cost shall
be
added
to
the Contract Sum.
Intellectual property in materials
nd
goods
The Contractor shall pay the cost o any royalty, license fee or other sum legally
demandable for the use of intellectual property
in
connection with the incorporation
of
materials and goods into the permanent Works other than materials and goods supplied
under a Nominated Sub-Contract
or
a Nominated Supply Contract. The cost shall be
added to the Contract Sum unless the Contractor was responsible for the selection of
the materials and goods in accordance with a performance specification or otherwise
in which case the cost shall be deemed to be included in the Contract Sum.
Intellectual property in pl nt
nd
equipment
1) The payment
of
all royalties, license fees or other sums legally demandable for the
use of intellectual property in respect
of
plant, equipment, machinery,
methods or
anything whatsoever used in carrying out the Works shall be deemed to be included in
the Contract Sum.
2) The
Contractor
shall
indemnify
the Employer from and
against
all claims,
proceedings, damages, costs and expense arising from the Contractor
or
any
sub-
contractor
or
supplier infringing
or
being held to have infringed any of the intellectual
property rights referred
to
in clause
9.3 1
).
Payment of royalties included in Valuation
9.4 If the Contractor uses any intellectual
property
in
compliance
with an
Architect s
instruction requiring a Variation, any royalty, license fee or other sum legally chargeable
which the Contractor pays in connection with that instruction shall be included in the
Valuation
of
the Variation.
1 0 Contractor s site management
team
Contractor s site management team
10.1 1) The Contractor shall maintain the site management and supervisory team (referred
to in clause 10 as the team ) listed in clause 3.1
1
)(c) on the Site for as long as is
necessary for the satisfactory fulfilment of his obligations under the Contract.
7
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
29/114
10
Contractor s site
management
team
(Con 'd)
2)
The team shall be of sufficient strength with personnel
of
appropriate qualifications,
seniority and experience, having regard to the size, complexity and nature of the Works,
to
properly organise, manage, plan, supervise and co-ordinate
the
carrying
out
of the
Works.
Construction manager
10.2 1)
The team shall
be
headed by
an
experienced and competent construction manager
approved
by
the Architect.
2) An instruction issued by the Architect to the construction manager shall be deemed
to have been issued to the Contractor.
3)
The Architect
may
instruct the Contractor to replace the construction manager
or
a member of the team
for
incompetence or misconduct.
4)
The Contractor shall not remove or replace the construction manager
or
any member
of
the
team unless requested by
or
agreed to by the Architect.
11
Access
for
the Architect to
the
Works
ontractor
to
give
access
The
Contractor
shall
give
the Architect and
any
person authorised
by the Architect
access, at all reasonable times,
to
the Works
or
any place where materials
or goods
are
being manufactured
or
stored, work is being prepared
or
design is being carried out,
and shall ensure
that
all his sub-contractors and suppliers
do
the same.
12 Architect s representative
Architect s representative
12.1 The Architect
and/or the
Employer may appoint an architect, engineer, clerk of works
or
other
person as the Architect's representative to be resident on the Site and acting
under the direction
of
the Architect.
8
The Architect's representatives' duties shall be to:
a)
watch and inspect
the
Works;
b)
inspect and test materials and goods;
c)
check that the types, standards and quality
of
the materials and goods, the standard
and quality
of
the Contrac tor s
workmanship and
the quality
of his
work
are in
accordance with the requirements
of
the Contract;
d)
check, amend as necessary, and where appropriate sign the records submitted to
him by the Contractor for approval; and
e)
carry
out the
duties and exercise
the
powers delegated to him
by the Architect
under clause 12.2,
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
30/114
12
Architect s
representative (Con '
d)
and the Contractor shall give the Architect's representative every reasonable facility for
the performance
of
these duties.
Delegation
of
duties
nd
powers
12.2 1) The Architect may, from time
to
time, delegate any of his duties and powers under
the Contract to the Architect's representative as defined under clause 12.1.
2)
The delegation shall
be
in writing and shall
be
copied to the Contractor. It shall
specify the duties and powers
that
are delegated and remain in force until changed
or
terminated in writing by the Architect.
Instruction to bind parties
12.3 1) The Architect's representative shall issue all instructions
in
writing and an instruction
from the Architect's representative shall bind the parties if:
a)
the Architect has the power to give it; and
b) it is within the terms of the delegation.
2)
The Contractor may, within 7 days of receiving an instruction from the Architect's
representative,
submit
an objection to the Architect who shall confirm, reverse or vary
that instruction within a further 7 days, failing which the instruction shall have no effect.
3 Variations Provisional Quantities Provisional Items and Provisional
Sums
Architect s authority to issue instructions requiring a Variation
13.1
1)
The Architect may issue an instruction requiring a Variation provided that:
a)
the Contractor has the right
of
reasonable objection to a Variation which imposes
or changes an obligation or restriction on the Contractor regarding access to the
Site, use
of
any part
of
the Site or limitation of working space or working hours and
the Architect shall, upon receipt
of
the Contractor's objection, either confirm or
withdraw the instruction, and if the instruction is confirmed, the Contractor may
refer the matter to arbitration under clause 41;
b)
the Contractor's written consent is given
to
an instruction either nominating a sub-
contractor to carry
out
work included in the Contract Bills which is to be carried
out
by the
Contractor or
omitting work in order for it to be carried out by others;
and
c) the instruction or accumulation
of
instructions shall not fundamentally change the
scope or nature
of
the Works.
2)
The instruction requiring a Variation shall describe the change required to the design,
quality or quantity of the Works or the imposition of or change to any obligation or
restriction on the Contractor and where appropr iate the Architect shall issue revised
drawings and/or schedules.
9
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
31/114
13 Variations, Provisional Quantities, Provisional Items and Provisional Sums (Cont d)
3)
The Contractor has
no
right to carry out work involving a Variation without a written
instruction from the Architect or confirmation
of
an oral instruction from the Contractor
except in the event of an emergency as provided for in Clause 4.4.
Instructions
for
Provisional Quantities, Provisional Items nd Provisional Sums
13 2 The Architect shall issue an instruction for:
a) the carrying out of work or the provision of goods covered by Provisional Quantities
or Provisional Items
in
the Contract Bills, Nominated Sub-Contracts or Nominated
Supply Contracts; and
b) the expenditure of Provisional Sums included in the Contract Bills, Nominated Sub
Contracts or Nominated Supply Contracts.
Valuation
of
Contractor s work
13 3 The Quantity Surveyor shall measure and value work carried out by the Contractor in
response to an Architect s instruction under:
a) clause 13.1 requiring a Variation;
b) clause 13.2(a) for the remeasurement of Provisional Quantities and Provisional Items;
and
c) clause 13.2(b) to expend a Provisional Sum,
and the Valuation shall
be
made
in
accordance with the rules set out
in
clause 13.4.
Valuation rules
13 4
1)
Where the Valuation relates to the carrying
out
of:
3
a) additional or substituted work which can be properly valued by measurement;
b)
work which is the subject of Provisional Quantities or Provisional Items; or
c) work involved in the expenditure
of
Provisional Sums,
the work shall be measured and shall be valued in accordance with the following rules:
i) where the work is the same as or similar in character to and is carried out
under the same
or
similar conditions to work priced in the Contract Bills, and
the Variation does not substantially change the quantity of that work, the rates
in the Cont ract Bills for that work shall determine the Valuation;
ii) where the work is the same as or similar in character to work priced in the
Contract Bills but is not carried out under the same or similar conditions, or
the Variation substantially changes the quantity
of
that work, the rates in the
ontract Bifls for
that
work shall determine the Valuation
but
with a fair
adjustment for the difference in conditions or quantity;
8/20/2019 Standard Form of Building Contract, Private Edition -With Quantities(2005 Edition)
32/114
13 Variations, Provisional Quantities,
Provisionalltems
and Provisional Sums (Cont d)
iii) where the work
is
not the same as or similar in character to any work priced in
the Contract Bills the work shall be valued at fair rates; and
iv)
the word conditions in clause 13.4(1) shall mean physical conditions and not
financial conditions.
2) Where the Valuation relates
to
work which cannot be properly measured and valued
under
clause 13.4(1) the work may, with the prior consent of the Architect, be carried
out as daywork and provided that the Contractor:
a)
gives at least 7 days notice to the Architect before carrying out the work,
or
where
the work is required urgently, as much prior notice
as
practicable; and
b) submits vouchers
spec