Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION
Dakota Access, LLC and Energy Transfer Crude Oil Company, LLC
: : :
Joint Petition for an Order under Section 8-503 of the Public Utilities Act for authority to install additional pumping stations and pumping facilities on existing certificated pipelines in the State of Illinois.
: : : : :
19-0673
INITIAL BRIEF OF
SAVE OUR ILLINOIS LAND, SIERRA CLUB, AND WILLIAM KLINGELE
*** PUBLIC VERSION ***
April 23, 2020
2
Table of Contents I. OVERVIEW ........................................................................................................................... 4
II. JOINT PETITIONERS’ PROPOSAL ................................................................................ 5
III. STATUTORY AND LEGAL STANDARDS .................................................................. 7
A. Section 8-503 of the PUA .......................................................................................... 7
B. Section 15-401 of the PUA ........................................................................................ 8
C. The Joint Petition is Deficient in Not Seeking Section 15-401 Certification 11
D. Burden of Proof ......................................................................................................... 19
E. Section 8-101 of the PUA Does Not Create a Legal Obligation for Joint Petitioners to Meet Shipper Demands for Transportation Services ...................... 20
F. Interstate Commerce Act Does Not Require that Joint Petitioners Expand Capacity to Meet Customer Demand .............................................................................. 22
IV. PUBLIC NEED ................................................................................................................ 24
A. Commission’s Determination of Need in Other Common Carrier by Pipeline Dockets................................................................................................................... 25
1. Lakehead .................................................................................................................. 25
2. Dockets after Lakehead ....................................................................................... 28
B. Joint Petitioners Reliance on Short-Term Production Forecasts Is Not Sufficient to Meet Its Burden of Proof for a Public Need .......................................... 34
C. Joint Petitioners’ Reliance on TSA Contractual Commitments Is Insufficient to Meet Its Burden of Proof ......................................................................... 40
D. Existing Take-Away Capacity from North Dakota Is Sufficient to Transport Forecasted and Contracted Volumes ............................................................................. 44
E. Refineries Are Operating at Capacity And Do Not Need More Crude ......... 47
F. Additional Crude Volumes Appear Destined for Export ................................. 53
G. The Public Burdens Outweigh the Private Benefits ........................................ 59
1. Balancing Costs and Benefits is Appropriate and Necessary .................. 59
2. Purported Benefits .................................................................................................... 63
3. Burdens of Joint Petitioners’ Proposal ............................................................... 69
4. Public versus Private ............................................................................................ 86
5. A Net Burden on the Public ................................................................................ 91
H. Conclusion on Public Need .................................................................................... 92
V. DESIGN, ENGINEERING, AND OPERATIONS........................................................... 92
3
A. Surge Overpressure ................................................................................................. 95
B. Specpoint Break ...................................................................................................... 104
C. The Questionable Record of Joint Petitioners’ Operator ............................. 105
D. Inadequate Leak Detection and Response Time ............................................ 108
VI. OTHER............................................................................................................................ 113
A. Interstate Commerce Act Compliance ........................................................... 113
1. Applicable Statutes and Case Law ................................................................. 113
2. The Record Indicates Likely Violations ......................................................... 124
B. Section 8-101 of the PUA ...................................................................................... 133
C. Conclusion and Consequences .......................................................................... 134
VII. CONCLUSION ............................................................................................................... 135
4
STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION
Dakota Access, LLC and Energy Transfer Crude Oil Company, LLC
: : :
Joint Petition for an Order under Section 8-503 of the Public Utilities Act for authority to install additional pumping stations and pumping facilities on existing certificated pipelines in the State of Illinois.
: : : : :
19-0673
INITIAL BRIEF OF
SAVE OUR ILLINOIS LAND, SIERRA CLUB, AND WILLIAM KLINGELE
*** PUBLIC VERSION ***
Pursuant to Section 200.800 of 83 Illinois Administrative Code 200, “Rules of
Practice,” and the schedule adopted by the Administrative Law Judge (“ALJ”), Save Our
Illinois Land (“SOIL”), Sierra Club (“SC”), and William Klingele (“WK”) (collectively “SOIL-
SC-WK”) respectfully submit their Initial Brief in this matter.
I. OVERVIEW
The Illinois Commerce Commission (“Commission”) has jurisdiction over
improvements and changes to existing common carrier crude oil pipelines pursuant to
Section 8-503 of the Public Utilities Act (“PUA”), 220 ILCS 5/1-101 et seq., which section
also contains the standards applicable to the exercise of such jurisdiction. PUA Section
15-401(a) and (b) require that crude oil pipeline companies apply for a certificate of good
standing (“Certificate”) prior to beginning or continuing construction of a pipeline to the
5
extent that a need for service exists and the public convenience and necessity requires
issuance of such Certificate.
The Joint Petition of Dakota Access, LLC (“DA”) and Energy Transfer Crude Oil
Company, LLC (“ETCO”) (collectively “Joint Petitioners”) seeks authorization to construct
additional pumping stations and related facilities along the existing DA and ETCO
pipelines (“DA Pipeline” and “ETCO Pipeline,” respectively) within the State of Illinois.
The evidence in the record demonstrates that Joint Petitioners have failed to meet the
burden under both Section 8-503 and Section 15-401(b) such that the Commission should
not grant the Joint Petition.
II. JOINT PETITIONERS’ PROPOSAL
Joint Petitioners received authority from the Commission to construct and operate
their respective pipelines and to otherwise operate as common carriers by pipeline in
Docket Nos. 14-0754 (DA) and 14-0755 (ETCO) on December 16, 2015 and December
9, 2015, respectively. In these dockets the Commission entered Orders finding a public
need for a crude oil pipeline transportation service to ship up to 570,000 barrels per day
(“bpd”) of crude oil from North Dakota to Patoka, Illinois, on the DA Pipeline, with
continuing service on the ETCO Pipeline to Nederland, Texas. The Commission also
found that Joint Petitioners were fit, willing, and able to provide this level of service, and
that therefore the public convenience and necessity required issuance of a Certificate. In
describing the authorized service, both Orders described a maximum capacity of 570,000
bpd, and both Orders permitted the construction and operation of the proposed pipelines
“as described in this Order.” (14-0754, Order at 53; 14-0755, Order at 27). To be clear,
Joint Petitioners did not request authorization to provide a crude oil transportation service
6
with a capacity greater than 570,000 bpd; the record in these dockets contains no mention
that the pipelines would be capable of operating at a greater capacity; the Orders
considered a public need for service up to 570,000 bpd and no more; and the Orders
evaluated Joint Applicants’ fitness, willingness, and ability to provide only this level of
service. Therefore, the Certificates issued by the Commission authorized Joint
Petitioners to provide crude oil transportation service of up to 570,000 bpd of light sweet
crude oil from North Dakota to Patoka, Illinois, with continuing service on ETCO’s pipeline
system from Patoka, Illinois to Nederland, Texas. Both pipelines were placed in service
in Illinois in June of 2017, and since then Joint Petitioners have operated the pipelines as
one system.
The pumping facilities Joint Petitioners propose to construct will enable them to
transport up to 1,100,000 bpd from North Dakota to Texas. The proposal includes
construction of a new pump station near Carthage, Illinois in Hancock County along the
DA Pipeline with an aggregate 30,000 horsepower (“HP”). At Patoka, Illinois, the
proposed construction involves adding two 6,000 HP pumps and replacing two pumps at
an existing pump station, bringing total pumping capacity at Patoka to 24,000 HP. Along
the ETCO Pipeline, near Joppa, Illinois in Massac County, Joint Petitioners propose to
construct a new pump station with an aggregate 18,000 HP. Independent from their
request under the Joint Petition, Joint Petitioners also plan to add increased storage
capacity at their facilities in Patoka, Illinois. (Joint Petition, ¶ 2, 3) Joint Petitioners refer
to their proposal as their capacity optimization plan. (Id., ¶ 2)
Joint Petitioners have failed to demonstrate that their proposal is needed or in the
public interest. SOIL-SC-WK come to this conclusion after a long and arduous process
7
during which they experienced a great deal of recalcitrance and obstruction by Joint
Petitioners. As SOIL-SC-WK noted in their earlier filings,1 Joint Petitioners have on
multiple occasions objected to providing and refused to provide relevant information
related to the need for the project, the safety aspects of nearly doubling throughput, and
even basic information such as the age of ETCO’s refurbished natural gas pipeline. Joint
Petitioners’ antagonism in the discovery process, repeated objection to allowing time to
consider information whenever it was eventually provided (at times upon the order of the
ALJ and Commission), and apparent presumption of approval has left the Commission
with an insufficient record upon which to find in Joint Petitioners’ favor.
III. STATUTORY AND LEGAL STANDARDS
A. Section 8-503 of the PUA
The Commission’s authority over facility changes made by common carriers by
pipeline emanates in part from Section 8-503 of the PUA, which is applicable to common
carriers via Section 15-101. Section 15-101 identifies other provisions of the PUA outside
of Article XV that are applicable to common carriers, which include Section 8-503. Section
8-503 provides in relevant part:
Whenever the Commission, after a hearing, shall find that additions, extensions, repairs or improvements to, or changes in, the existing plant, equipment, apparatus, facilities or other physical property of any public utility or of any 2 or more public utilities are necessary and ought reasonably to be made or that a new structure or structures is or are necessary and should be erected, to promote the security or convenience of its employees or the public or promote the development of an effectively competitive electricity market, or in any other way to secure adequate service or facilities, the Commission shall make and serve an order authorizing or directing that such additions, extensions, repairs, improvements or changes be made, or such structure or structures be erected at the location, in the
1 See, for example, SOIL-SC’s December 9, 2019 Petition for Interlocutory Review, paragraphs 28-53.
8
manner and within the time specified in said order;
SOIL-SC-WK concur with Joint Petitioners that Section 8-503 is applicable to their
proposed capacity optimization plan. The plain language of this section makes clear that
it (a) authorizes Commission jurisdiction over “additions, extensions, repairs or
improvements to, or changes in” existing pipelines; and (b) contains the standard under
which the Commission may authorize such “improvements or changes.”
B. Section 15-401 of the PUA As noted above, Section 15-401 requires a common carrier to apply for and
possess a Certificate and provides in relevant part:
(a) No person shall operate as a common carrier by pipeline unless the person possesses a certificate in good standing authorizing it to operate as a common carrier by pipeline. No person shall begin or continue construction of a pipeline or other facility, other than the repair or replacement of an existing pipeline or facility, for use in operations as a common carrier by pipeline unless the person possesses a certificate in good standing. (b) Requirements for issuance. The Commission, after a hearing, shall grant an application for a certificate authorizing operations as a common carrier by pipeline, in whole or in part, to the extent that it finds that the application was properly filed; a public need for the service exists; the applicant is fit, willing, and able to provide the service in compliance with this Act, Commission regulations, and orders; and the public convenience and necessity requires issuance of the certificate. Evidence encompassing any of the factors described in items (1) through (9) of this subsection (b) that is submitted by the applicant, any other party, or the Commission's staff shall also be considered by the Commission in determining whether a public need for the service exists under either current or expected conditions. The changes in this subsection (b) are intended to be confirmatory of existing law.
In its determination of public convenience and necessity for a proposed pipeline or facility designed or intended to transport crude oil and any alternate locations for such proposed pipeline or facility, the Commission shall consider, but not be limited to, the following:
(1) any evidence presented by the Illinois Environmental Protection Agency regarding the environmental impact of the proposed pipeline or other facility; (2) any evidence presented by the Illinois Department of
9
Transportation regarding the impact of the proposed pipeline or facility on traffic safety, road construction, or other transportation issues; (3) any evidence presented by the Department of Natural Resources regarding the impact of the proposed pipeline or facility on any conservation areas, forest preserves, wildlife preserves, wetlands, or any other natural resource; (4) any evidence of the effect of the pipeline upon the economy, infrastructure, and public safety presented by local governmental units that will be affected by the proposed pipeline or facility; (5) any evidence of the effect of the pipeline upon property values presented by property owners who will be affected by the proposed pipeline or facility, provided that the Commission need not hear evidence as to the actual valuation of property such as that as would be presented to and determined by the courts under the Eminent Domain Act; (6) any evidence presented by the Department of Commerce and Economic Opportunity regarding the current and future local, State-wide, or regional economic effect, direct or indirect, of the proposed pipeline or facility including, but not limited to, property values, employment rates, and residential and business development; (7) any evidence addressing the factors described in items (1) through (9) of this subsection (b) or other relevant factors that is presented by any other State agency, the applicant, a party, or other entity that participates in the proceeding, including evidence presented by the Commission's staff; (8) any evidence presented by a State agency or unit of State or local government as to the current and future national, State-wide, or regional economic effects of the proposed pipeline, direct or indirect, as they affect residents or businesses in Illinois, including, but not limited to, such impacts as the ability of manufacturers in Illinois to meet public demand for related services and products and to compete in the national and regional economies, improved access of suppliers to regional and national shipping grids, the ability of the State to access funds made available for energy infrastructure by the federal government, mitigation of foreseeable spikes in price affecting Illinois residents or businesses due to sudden changes in supply or transportation capacity, and the likelihood that the proposed construction will substantially encourage related investment in the State's energy infrastructure and the creation of energy related jobs; and (9) any evidence presented by any State or federal governmental entity as to how the proposed pipeline or facility will affect the security, stability, and reliability of energy in the State or in the region. In its written order, the Commission shall address all of the evidence
presented, and if the order is contrary to any of the evidence, the
10
Commission shall state the reasons for its determination with regard to that evidence.
* * *
(d) A common carrier by pipeline may request any other approvals as may be needed from the Commission for completion of the pipeline under Article VIII or any other Article or Section of this Act at the same time, and as part of the same application, as its request for a certificate of good standing under this Section.
Section 15-401 complements Section 8-503 by:
• prohibiting persons from operating as common carriers by pipeline absent receipt
of a Certificate from the Commission;
• prohibiting the start or continuation of construction of a new pipeline or changes to
an existing pipeline for use in common carrier operations absent a Certificate;
• defining the evidentiary scope of Commission hearings for proposed new pipelines
and improvements or changes to existing pipelines;
• identifying the sources of evidence that the Commission may consider; and
• requiring that Commission orders for proposed new pipelines and improvements
and changes to existing pipelines address all of the evidence presented.
Put another way, Section 15-401 provides the enforcement and procedural requirements
needed to implement the jurisdictional authority and decision standards established by
Section 8-503. Thus, petitions seeking to construct “additions,” “improvements,”
“extensions,” or “changes” to existing pipelines are subject to both Sections 8-503 and
15-401.
The contiguous nature of Sections 8-503 and 15-401 is also demonstrated by the
scope of the single jurisdictional exception to Section 15-401. Specifically, Section 15-
401 states that, “other than the repair or replacement of an existing pipeline or facility,” it
11
is applicable to all common carrier pipeline construction. The fact that this exception
relates to existing pipelines indicates that all other instances of construction related to
existing pipelines are subject to Section 15-401.
The only pipeline construction activities that are subject to Section 8-503 but not
subject to 15-401 are repairs and replacements of existing pipelines. Since repairs and
replacements would not change the transportation service authorized by the Commission
when a pipeline is approved, it makes sense that the Commission actions related to
repairs would not be subject to the full requirements of Section 15-401. It also makes
sense that any subsequent changes to the transportation service approved for a new
pipeline would be subject to the same Section 15-401 procedural requirements.
Nothing in the language of these sections indicates that they are mutually
exclusive, such that the Commission must give each section its full independent force.
Moreover, Section 15-401(d) removes any ambiguity about the complementary roles of
these laws by stating that an existing “common carrier by pipeline may request any other
approvals as may be needed from the Commission for completion of the pipeline under
Article VIII . . . at the same time, and as part of the same application, as its request for a
certificate of good standing under this Section.,” which article includes Section 8-503.
The plain language of the law provides a mechanism by which applicants may comply
with both Sections 8-503 and 15-401 at the same time.
C. The Joint Petition is Deficient in Not Seeking Section 15-401 Certification Contrary to the plain meaning of these laws, the Joint Petition does not seek
authority under Section 15-401, and instead assumes that the only section applicable to
the proposed changes is Section 8-503. The Commission should clarify that both Section
12
8-503 and Section 15-401 apply to Joint Petitioners’ proposed capacity optimization plan.
SOIL-SC raised the applicability of Section 15-401 as a threshold matter through
its August 20, 2019 Motion for Amendment or Dismissal of Joint Petition, for Investigation,
and to Stay Schedule. In his September 12, 2019 ruling on SOIL-SC’s August 20, 2019
motion, the ALJ found that Joint Petitioners have the right to determine what relief to seek
in their Joint Petition, but that SOIL and SC can challenge the sufficiency of the Joint
Petition in their testimony and pleadings, including in briefing. In denying SOIL-SC’s
September 18, 2019 petition for interlocutory review of the ALJ’s ruling, the Commission
affirmed the ALJ with Chair Zalewski specifically stating, “If the parties wish to challenge
the sufficiency of the Petition, they can do so in the testimony and pleadings.” (October
10, 2019 Commission Special Open Meeting Tr. at 4) Chair Zalewski stated further, “I
want to emphasize the importance of developing a full record in this case and encourage
the ALJ and the parties to work to ensure all relevant evidence is reflected in the record.”
(Id.)2 SOIL-SC-WK understand that in affirming the ALJ, the Commission did not rule on
the applicability of Section 15-401 but rather that Joint Petitioners were free to choose
under which sections of the PUA to file the Joint Petition, with the determination of
whether they should have included Section 15-401 to be made at the end of this
proceeding. Accordingly, SOIL-SC-WK hereby reassert that the Joint Petitioners were
required by law to seek approval of the proposed improvements and changes under both
Section 8-503 and Section 15-401.
Throughout this proceeding SOIL-SC-WK have continuously asserted that the
2 SOIL-SC-WK have endeavored to develop a complete record, although due to Joint Petitioners’ recalcitrance, significant relevant information which is discussed elsewhere in this Initial Brief has not been provided.
13
Joint Petition should have been filed pursuant to and is subject to the requirements of
Section 15-401, such that Joint Petitioners erred in not seeking authorization under that
provision. The Commission granted each Joint Petitioner a Certificate in the
aforementioned Docket Nos. 14-0754 and 14-0755. Those Certificates were premised
on the pipelines transporting up to 570,000 bpd and certainly did not contemplate a
massive increase in throughput of 1,100,000 bpd and the pumping stations and facilities
proposed under Joint Petitioners’ capacity optimization plan. Further, the Commission
did not evaluate whether there was a need for pipeline transportation services with a
capacity of 1,100,000 bpd, nor did the Commission evaluate Joint Applicants’ fitness and
ability to transport this much greater daily volume of crude oil. In the present docket, Joint
Petitioners’ proposal to nearly double the crude oil throughput capacity on the existing
pipelines will dramatically change the operating characteristics of the pipelines from what
the Commission previously considered.3
Joint Petitioners’ possession of a Certificate based on the record in Docket Nos.
14-0754 and 14-0755 does not create a license to augment the underlying pipelines in
any way they wish without regard to Section 15-401. The above emphasized language
from subsection (a) of Section 15-401 addresses the very situation at hand. Joint
Petitioners propose to construct new facilities along their previously certificated pipelines
and in no way have suggested that the new facilities merely constitute a “repair or
3 Note that a review of the records in Docket Nos. 14-0754 and 14-0755 indicate that the technical operating characteristics of the pipelines do not appear to have received much, if any, consideration. For example, while the records reflect the technical design and operating characteristics of the new pipe each petitioner proposed to install (see Docket No. 14-0754, Application at 28 and Docket No. 14-0755, Application at 30), the record in Docket No. 14-0755 conspicuously lacked any evidence of the age or condition of the natural gas pipeline ETCO proposed to use to transport crude oil. Not until this docket and after SOIL-SC’s October 24, 2019 Motion to Compel did the Commission learn that the natural gas pipeline ETCO relies upon was constructed in the 1960s. Such lack of consideration of pertinent details in Docket Nos. 14-0754 and 14-0755 makes the need for their consideration in the present docket all the more important.
14
replacement of an existing pipeline or facility.” Under the plain language of subsection
(a), Joint Petitioners must obtain either a new or amended Certificate to construct the
facilities contemplated under their capacity optimization plan because those facilities are
not repairs or replacements of their existing pipelines. To conclude that Joint Petitioners
may rely on their earlier Certificates from Docket Nos. 14-0754 and 14-0755 establishes
a dangerous precedent not only in the context of common carriers, but also in the context
of other utilities that must obtain a certificate of public convenience and necessity for their
facilities. The Commission should not allow common carriers to dramatically expand the
scope of their services absent compliance with Section 15-401.
Joint Petitioners’ disregard for the limiting language in Section 15-401(a) and
interpretation of the statute as giving them as much authority as they desire to operate as
a common carrier is disturbing. In essence, once authority is granted under Section 15-
401, Joint Petitioners seem to believe that there is no need to seek additional authority
under that section. Even though Joint Petitioners told the Commission and public in 2014
that they only plan on transporting up to 570,000 barrels per day, Joint Petitioners would
now have the Commission believe that absolutely nothing prohibits them from doubling,
tripling, or quadrupling that capacity if the Commission did not explicitly limit the
throughput volume. Never mind the fact that the Commission relied upon Joint
Petitioners’ description of their project, describing its understanding of the project, and in
coming to its decision in the Orders entered in Docket Nos. 14-0754 and 14-0755.
According to Joint Petitioners, the Commission and the public were apparently just
supposed to assume and accept that the operating parameters of the pipelines would
change in unknown ways and at unknown points in the future. SOIL-SC witness Richard
15
Stuckey commented on the throughput capacity of the original Certificates being up to
570,000 bpd in his direct testimony (SOIL-SC Ex. 1.0, lines 47-53) and noted in his
rebuttal testimony that none of Joint Petitioners’ nine rebuttal witnesses disagreed with
his observation. (SOIL-SC Ex. 4.0, lines 33-39)
To the extent Joint Petitioners argue that the Commission’s Order in Enbridge
Energy Partners, L.P. and Enbridge Energy, Ltd. P’ship, ICC Docket No. 06-0470 (Order,
April 4, 2007), (Order on Reopening, August 6, 2013), (“Enbridge”) establishes precedent
for a pipeline capacity expansion without regard for Section 15-401, such reliance is
misplaced. SOIL-SC-WK recognize that in 2007 the Commission granted Enbridge
Energy Partners, L.P. and Enbridge Energy, Limited Partnership (collectively “Enbridge”)
authority under Section 15-401 to construct and operate a 400,000 bpd pipeline, and then
under the same docket number Enbridge returned in 2013 under just Section 8-503 and
obtained authority to install additional pumping capacity. The distinction, however, is that
unlike the case at hand, Enbridge raised in its original common carrier filing that it may
later increase the capacity of the subject pipeline with the addition of new pumps. (Docket
No. 06-0470, Application at 13, footnote 8) Therefore, the possibility of such expansion
was within the scope of that docket. Moreover, no party chose to contest whether
Enbridge’s 2013 application was required to comply with Section 15-401, such that the
Commission did not consider the applicability of this section in that particular
circumstance.
Even had Enbridge not foreshadowed its capacity increase, and even if the 2013
order is deemed to be an express ruling that Section 15-401 does not apply to pipeline
additions, improvements, and changes, nothing prevents the Commission from
16
acknowledging that it was error to not consider Section 15-401 in Docket No. 06-0470.
As is well established, the Commission is not limited by res judicata. For example, in
Commonwealth Edison Co. v. Ill. Commerce Comm'n, the Illinois Supreme Court held
that it has long recognized that the Commission "is not a judicial body, and its orders are
not res judicata in later proceedings before it." (2016 IL 118129, ¶ 24, 402 Ill. Dec. 36, 42,
51 N.E.3d 788, 794, citing Mississippi River Fuel Corp. v. Illinois Commerce Comm'n, 1
Ill. 2d 509, 513, 116 N.E.2d 394 (1953)) The Court noted further that as a regulatory
body, the Commission has the "power to deal freely with each situation as it comes before
it, regardless of how it may have dealt with a similar or even the same situation in a
previous proceeding." (Id.) So even if Enbridge had not referenced the possibility of a
capacity increase in its original application in Docket No. 06-0470, such an oversight in
an uncontested docket from six years ago should not be used to justify the misapplication
of the law today. Unlike in Enbridge, where the issue was never raised or mentioned, the
issue of the applicability of Section 15-401 to a significant pipeline alteration is now raised
and is squarely before the Commission for its determination.
Moreover, the Commission has previously held that uncontested cases should not
be relied upon as precedent when presented with conflicting positions in a similar but
contested case. In its Order on the application of Lakehead Pipe Line Company
(“Lakehead”) for a Certificate under Section 15-401, the Commission noted that it had
considered the merits of similar applications based only on the testimony of the applicant
company. (Lakehead Pipe Line Co., L.P., ICC Docket No. 96-0145, 1997 Ill. PUC Lexis
255 (Order, May 7, 1997), aff’d, 296 Ill. App. 3d 942, 696 N.E.2d 345 (3d Dist. 1998))
Based on the testimony of the applicants in prior dockets and in the absence of any
17
alternative testimony provided for the Commission’s consideration in those dockets, the
Commission found in favor of the applicants. In the context of Lakehead’s application,
however, the Commission was presented with testimony conflicting with Lakehead’s
position. The Commission concluded that it was not bound by past uncontested cases
and specifically held that “[a]n uncontested case should not be considered as precedence
to judge the instant proceeding.” (Id., Order at 33) Being a Commission finding, such a
conclusion is not itself precedence, but nevertheless remains a prudent and wise
determination warranting continued adherence. Just as the Commission found with
regard to Lakehead’s application in Docket No. 96-0145, the Commission should not feel
compelled to follow the uncontested Order in Docket No. 06-0470 when deciding whether
Section 15-401 of the PUA should apply to Joint Petitioners’ proposed pipeline capacity
expansion. To be clear, SOIL-SC-WK do not agree that Docket No. 06-0470 is analogous
to the docket at hand because Enbridge indicated that it may plan to expand the capacity
of its pipeline in its original common carrier docket, which is in contrast to Joint Petitioners’
original common carrier dockets, but to the extent that the Commission sees parallels
between Docket No. 06-0470 and the pending docket, the Commission should not
consider the absence of consideration of Section 15-401 in an earlier uncontested docket
persuasive for purposes of this contested docket.
Commission precedent supports SOIL-SC-WK’s interpretation and analysis. In
Docket No. 13-0433, Explorer Pipeline Co. filed an application for approval under PUA
Sections 8-503 and 8-509 for an extension to an existing Illinois pipeline, consisting of 18
miles of new pipeline (the “Manhattan Extension Project”). (Explorer Pipeline Co., ICC
Docket No. 13-0433 (Petition, July 3, 2013)) The previously-certificated pipeline was
18
being used for delivery of diluents, a petroleum product. The ALJ issued a notice asking
applicant and Commission Staff (“Staff”) to address whether a prior certificate is sufficient
for the new project. (Id., (Notice of ALJ’s Ruling, August 21, 2013)) In response, the
applicant filed an amended application adding a request for a certificate under Section
15-401. (Id., (Amended Petition, August 27, 2013))
Noteworthy in the consideration of the applicability of Section 15-401 is Joint
Petitioners’ own acknowledgement that Section 15-401 may apply. Specifically, in
footnote 10 of the Joint Petition, Joint Petitioners state they “would not object were the
Commission to conclude that their [Certificate] should also be amended in this
proceeding, pursuant to Section 15-401….” This concession by Joint Petitioners
contradicts their own vehement insistence that Section 15-401 does not apply. (See Joint
Petitioners’ August 27, 2019 Response to Motion for Amendment or Dismissal of Joint
Petition, for Investigation, and to Stay Schedule, at 2-9.)
Because Section 15-401 is clearly applicable and the Commission may not by
order authorize a violation of the plain language of an applicable statute, it is appropriate
for the Commission to conclude that the Joint Petition is deficient for failing to address the
requirements of Section 15-401. Furthermore, given the applicability of Section 15-401,
it is also appropriate to consider under subsection (b) thereof whether a public need for
the capacity optimization plan exists; whether Joint Petitioners are fit, willing, and able to
nearly double the throughput capacity of their pipelines in a manner consistent with the
PUA, Commission rules, and orders; and whether the public convenience and necessity
require granting the requested relief. As the evidence described below will reflect, there
is no public need for Joint Petitioners’ plan, there is insufficient information to conclude
19
that Joint Petitioners are fit and able to raise the throughput capacity to 1,100,00 bpd in
a safe manner, and the public convenience and necessity do not require facilitation of
more fossil fuel transportation and consumption to the detriment of the public within Illinois
and far beyond.
D. Burden of Proof In addition to considering which statutory provisions apply, it is also important to
consider which party in a proceeding has the burden of demonstrating that the standards
set forth in the statutory provisions are met. To obtain the relief they request under
Section 8-503 of the PUA, Joint Petitioners have the burden of demonstrating that their
capacity optimization plan is “necessary and ought reasonably to be made” or that
capacity optimization facilities are “necessary and should be erected, to promote the
security or convenience of its employees or the public … or in any other way to secure
adequate service or facilities.” (§8-503) Joint Petitioners’ burden under Section 8-503
can be narrowed in light of their acknowledgement that their proposal is not necessary
for the security or convenience of their employees (see SOIL-SC Ex. 1.4), leaving the
security and convenience of the public that which Joint Petitioners must prove before the
expansion is authorized. As explained above, Joint Petitioners also have the burden of
demonstrating under Section 15-401 that their Joint Petition was properly filed, a public
need for the capacity optimization plan exists, that they are both fit, willing, and able to
increase crude oil throughput from 570,000 bpd to 1,100,000 bpd in compliance with the
PUA, Commission regulations, and orders, and that the public convenience and necessity
requires issuance of a new or amended Certificate authorizing implementation of the
capacity optimization plan.
20
The Commission in its Order in Lakehead recognized that the burden of proof was
on the applicant. (Lakehead, supra, (1997 Ill. PUC LEXIS 255, at 37) (“Lakehead has
failed to meet its burden of proof under Article 15 of the Act.”)) Under Section 10-15 of
the Illinois Administrative Procedure Act, 5 ILCS 100/1-1 et seq., Joint Petitioners must
demonstrate by the preponderance of the evidence that they have met their burden.
Caselaw discussed later in this Initial Brief provides guidance on what has been found to
have satisfied the burden of proof in prior Commission dockets. As will be shown, Joint
Petitioners’ have failed to prove that their capacity optimization plan is necessary or
benefits anyone more than themselves and possibly a handful of shippers eyeing the
crude oil export market.
E. Section 8-101 of the PUA Does Not Create a Legal Obligation for Joint Petitioners to Meet Shipper Demands for Transportation Services
Joint Petitioners maintain that Section 8-101 of the PUA “obligates” them as
common carriers to meet shipper demands for transportation services. (Joint Petition, ¶
17) Section 15-101 makes Section 8-101 applicable to common carriers. Section 8-101
states in full:
A public utility shall furnish, provide, and maintain such service instrumentalities, equipment, and facilities as shall promote the safety, health, comfort, and convenience of its patrons, employees, and public and as shall be in all respects adequate, efficient, just, and reasonable.
All rules and regulations made by a public utility affecting or pertaining to its charges or service to the public shall be just and reasonable.
A public utility shall, upon reasonable notice, furnish to all persons who may apply therefor and be reasonably entitled thereto, suitable facilities and service, without discrimination and without delay.
Nothing in this Section shall be construed to prevent a public utility from accepting payment electronically or by the use of a customer-preferred financially accredited credit or debit methodology.
SOIL-SC-WK agree that Section 8-101 is applicable to Joint Petitioners’ request,
21
but not in the manner Joint Petitioners suggest. SOIL-SC-WK are not aware of any
situation in which the Commission has applied Section 8-101 to conclude that a common
carrier must increase capacity to satisfy shipper demand, particularly when determination
of such demand is subject to the Commission’s finding of necessity following an
evidentiary hearing pursuant to Sections 8-503 and 15-401.
Joint Petitioners voluntarily initiated an open season on October 19, 2018 offering
to provide additional capacity on their pipelines. (Confidential SOIL-SC Cross Ex. 8, at
1) Joint Petitioners had no obligation to initiate this or any other open season. Moreover,
the six transportation service agreements (“TSA”) Joint Petitioners entered into at the
conclusion of the 2018 open season recognize that implementation of the capacity
optimization plan is contingent upon receiving regulatory approval. (Id. At 10) The 2004
case of Orland Hills v. Citizens Utils. Co., 347 Ill. App. 3d 504, 524, 282 Ill. Dec. 966, 981,
807 N.E.2d 590, 605, supports the position that there is no absolute obligation to serve
under Section 8-101 of the PUA. Moreover, Joint Petitioners’ claim that they are obligated
by law to serve shippers is belied by the testimony of their witness, Dr. Jeff Makholm, that
“Regulators let the market support those investments [like the capacity optimization plan],
given the fact that the ‘private profitability calculations’ are adequate to judge their
desirability as additions to the transport market.” (Dakota Access-ETCO Ex. 6.2, lines
480-482) In other words, Joint Petitioners wish to expand their transportation capacity
because they believe that there is profit to be gained, not because Section 8-101 obligates
them to do so. In any case, whether or not a need to provide the requested service exists
remains for the Commission to decide under Sections 8-503 and 15-401.
Section 8-101 does not obligate Joint Petitioners to serve any shipper that
22
approaches them. Instead, this section obligates Joint Petitioners to “furnish, provide,
and maintain such service instrumentalities, equipment, and facilities as shall promote
the safety, health, comfort, and convenience of … [the] public and as shall be in all
respects adequate, efficient, just, and reasonable” should the proposed improvements be
approved by the Commission and constructed by Joint Petitioners. As will be explained
further below, there is insufficient evidence in the record to conclude that Joint Petitioners’
capacity optimization plan will promote public safety, health, comfort, or convenience with
regard to meeting public demand for energy or avoiding the risk of catastrophic climate
change.
F. Interstate Commerce Act Does Not Require that Joint Petitioners Expand Capacity to Meet Customer Demand
Without providing a cite, Joint Petitioners assert that federal law obligates them as
common carriers to meet customer demands for transportation services. (Joint Petition,
¶ 17) SOIL-SC-WK presume that Joint Petitioners are relying on the Interstate Commerce
Act (“ICA”) for this proposition. Notably, however, the ICA does not impose an obligation
to serve any and all shipper requests for service, as suggested by Joint Petitioners. Prior
to her appointment to the U.S. Supreme Court, Circuit Judge Ruth Ginsburg addressed
a common carrier’s obligation to serve demands by shippers in B.J. Alan Co. v. ICC, 283
U.S. App. D.C. 107 (1990). In evaluating whether United Parcel Service had an obligation
under the ICA as a common carrier to serve a category of shippers, Judge Ginsburg
wrote:
A common carrier undertakes to provide transportation service "on reasonable request," 49 U.S.C. § 11101(a), and "may not subject a person, place, port, or type of traffic to unreasonable discrimination." 49 U.S.C. § 10741(b). Subject to those strictures, however, "a common carrier is free to carve out as large or as small a [niche] as it feels appropriate." Steere Tank
23
Lines, Inc. v. ICC, 675 F.2d 103, 105 (5th Cir. 1982). An unlimited duty of carriage was never the rule. (B.J. Alan Co. v. ICC, 283 U.S. App. D.C. 107, 897 F.2d 561, 563) (emphasis added)
More recently, the Federal Energy Regulatory Commission (“FERC”) has come to
similar conclusions regarding pipeline companies’ service obligations as common
carriers. In the context of an obligation to interconnect with another pipeline in Plantation
Pipe Line Company v Colonial Pipeline Company, FERC concluded that because it
lacked authority over abandonment of service by oil pipelines, “it would be illogical and
inconsistent for [FERC] to conclude here that it has the power to compel an
interconnection that Colonial does not want and could abandon.” (104 FERC ¶ 61,271,
para 28, (2003))
In a subsequent FERC matter also involving an alleged obligation to interconnect
under the ICA, FERC determined, “Just as a pipeline is not required to provide a particular
service, a pipeline may also discontinue a service it previously provided at any time. (High
Prairie Pipeline LLC v Enbridge Energy, LP, 149 FERC ¶ 61,004, ¶ 14 (2014)) In the
same order, FERC also stated, “Yet the mere fact that a pipeline explores whether it can
come to agreement on offering a service in the future does not actually bind that pipeline
to offering that service.” (Id., ¶ 17)
In addition, Joint Petitioners’ claim that federal law obligates them to serve
shippers seeking transportation service is incompatible with provisions in their own TSAs
resulting from their 2018 open season. As will be discussed further below, Section 7(b)
of the 2018 TSAs provides,
***CONFIDENTIAL XXXXXXXXXXXXXXXXXXXXXXXXXX xxxxxxXXxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx xxxxxxXXxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
24
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx. CONFIDENTIAL*** (Confidential SOIL-SC Cross Ex. 8, at 24)
Notably, this section does not obligate Joint Petitioners to offer service under different
terms. If in fact federal law obligated Joint Petitioners to serve shippers seeking
transportation service, the quoted language from the 2018 TSAs would conflict with such
federal law, as well the previously discussed Section 8-101 of the PUA, since some
shipper(s) could still want to transport up to 39% of the total available capacity.
Accordingly, Joint Petitioners’ claim that federal law, and Illinois law, obligates them to
provide transportation service is not in accordance with the law and should be
disregarded by the Commission.4
IV. PUBLIC NEED Arguably the most important hurdle for Joint Petitioners to overcome in this docket
is demonstrating public need. As this proceeding neared the evidentiary hearing phase,
and as the Commission is well aware, a global pandemic impacted the world economy,
which included the oil industry. Demand for oil around the globe plummeted, benchmark
crude prices dropped to never before seen lows, oil producers across the United States
cut capital expenditures and shut in wells, and experts predict a prolonged downturn in
the U.S. oil industry. Unfortunately, the record in this matter does not reflect this extreme
and unprecedented situation that directly impacts the need for the additional throughput
capacity Joint Petitioners propose to implement. SOIL-SC-WK urge the Commission to
take judicial notice of the pandemic and impact on the oil industry pursuant to Section
200.640 of the Rules of the Practice and Rule 201 of the Illinois Rules of Evidence. As
4 The conflict between Joint Petitioners claim that they have an obligation to serve all shippers and the subsequent revelation of the quoted language from the TSA is one example of many indicative of why SOIL-SC-WK have learned to question many of Joint Petitioners’ self-serving assertions in this docket.
25
stated in People v. Ross, “the court could take cognizance of whatever may be known by
common observation, since the court is presumed to be as well informed as the general
public and can certainly take judicial notice of that which everyone knows to be true.” (82
Ill. App. 3d 158, 160 (1980)) The COVID-19 pandemic and its impact on the global
economy in general and the oil industry in particular are facts which everyone knows to
be true.
A. Commission’s Determination of Need in Other Common Carrier by Pipeline Dockets
1. Lakehead
The Commission’s Order in Lakehead 23 years ago (affirmed by the appellate
court) remains a leading, oft-cited5 decision for several purposes, but most importantly on
the issue of public need. “This [public need] is the most contested issue in this proceeding.
It is of overreaching importance that there be a showing of public need because it forms
a condition precedent for any determination of necessity and, therefore, convenience.”
(Lakehead, supra, (1997 Ill. PUC LEXIS 255, at *11, 12) Lakehead sought Commission
approval to construct and operate a pipeline for the transportation of crude oil and other
liquid hydrocarbons. The pipeline would be an addition to a 3,200 mile long pipeline
system that extends from Western Canada, entering United States in North Dakota, with
pipelines routed through the north central U.S., including Illinois, and re-enters Canada
near Ontario. It extended from Wisconsin to Indiana, extending over 115 miles through
northeastern Illinois. It was placed in service in 1968-1969, and delivered crude to
refineries in Illinois and elsewhere. Lakehead contended it had to apportion capacity due
5 See e.g., Enbridge Pipelines (Illinois) L.L.C., ICC Docket No. 07-0446 (Order, July 8, 2009)
26
to physical limitations on its pipeline system. Lakehead sought a Certificate to construct
a new pipeline from Wisconsin to Illinois and interconnect with an existing line in Illinois.
The Commission stated in its Order that “the public need, like the public convenience and
necessity, ‘required to support an order of the Commission is that of the public and not of
any individual or number of individuals.’“ (Id., at *34, quoting Roy v. Illinois Commerce
Comm’n, 322 Ill. 452, 458 (1926)) Continuing in its distinguishing the public need from a
private need or desire, the Commission stated, “The public, as indicated by the [Roy]
court, is greater than a limited number of market players. While it may be in Lakehead’s
own best interest that the proposed pipeline be built, that does not establish a public
need.” (Lakehead, 1997 Ill. PUC LEXIS, at *34). To emphasize this principle further, the
Commission explained, “Whatever basis a petitioner chooses for demonstrating a public
need, the need must be for the public, not for the few.” (Id., at *35) When the issue is
contested, the Commission stated that all evidence is to be considered. “And the
Commission must weigh the evidence presented by the petitioner, that there exists a
public need against the evidence other parties presented that no such public need exists.”
(Id., at *35, 36)
The Commission in Lakehead considered the possibility that Lakehead may seek
eminent domain authority as making the public need determination even more important.
While an affirmative decision would not grant Lakehead eminent domain, the Commission’s granting of a certificate in good standing does indicate a public need and as such eminent domain may be appropriate to fill that public need. That is why the Commission’s ruling in this proceeding must be based upon a demonstrated public need, rather than private interests. (Id., at *36)
In further analyzing the public need requirement, the Commission stated that it
agreed with Staff that the demand for refined petroleum products, and not only crude oil,
27
provides the basis for public need. (Id., at *37) Staff had criticized the testimony of
Lakehead witnesses who represented oil companies that owned refineries along
Lakehead’s pipeline system. It was Staff’s position that none of the witnesses
demonstrated that their refineries needed to obtain additional Canadian crude oil via
Lakehead’s pipeline system. None of them, according to Staff, provided support needed
to show a public need for the proposed pipeline. (Id., at *24, 25)
The Commission also addressed the public convenience and necessity standard
as it relates to public need in its Lakehead Order. “Public convenience and necessity and
public need are not mutually exclusive. If a showing of public need cannot be made for
a proposed pipeline project such as Lakehead’s, the public convenience and necessity is
not being served.” (Id., at *38) The Commission in effect established a showing of public
need as a prerequisite to or required component of, public convenience and necessity.
As part of additional discussion and support for its conclusions, the Commission
expounded further on the public vs. private need relationship. The Commission found it
difficult to reconcile the need of Lakehead and three of its customers with the public need.
The Commission stated that if it were to accept that the public need can be equated with
the need of a group of individuals like those in Lakehead, “the role of the Commission
under Article 15 would be merely to recognize that a private interest is fit, willing and able
to build a pipeline and its customers want the product of that pipeline.” (Id., at *56) The
Commission added that Lakehead did no analysis, economic or engineering, as to the
relevant supply sources for the market. Lakehead “simply stated that demand is growing
and it wanted to supply that demand.” (Id., at *56, 57) Lakehead offered no evidence,
only speculation, that future demand necessitated a new pipeline. Staff attempted to
28
conduct such an analysis and could not find support that a new pipeline was needed in
the relevant market to meet any alleged shortfalls in pipeline capacity. Further,
Lakehead’s own refinery-representative witnesses could not identify any current or future
capacity constraints other than on Lakehead’s system.
The Commission then addressed why a pipeline company would invest a large
sum of money on a new pipeline where there was no analysis that the pipeline was
needed to meet any alleged future capacity shortfalls. As the Commission posited, “One
possible explanation is the conquest of market share. While obtaining market share may
be beneficial to the Company, it is not a public need, it is a private goal.” (Id., at *57)
2. Dockets after Lakehead
Several common carrier by pipeline certification dockets have been considered by
the Commission since Lakehead. Summaries of those dockets, focusing on the related
issues of public need and public convenience and necessity follow.
In Docket No. 06-0458, a common carrier pipeline sought a Section 15-401
Certificate to construct and operate a pipeline to carry crude oil from western Canada to
refineries in Illinois and the surrounding region. The record showed that pipelines serving
southern Illinois were fully utilized and on apportionment. Western Canadian crude was
cheaper and more secure than crude from other sources, such as imports from the Gulf
and other countries. The Wood River refinery in Illinois, near St. Louis, had committed to
shipments on the proposed pipeline, and commitments totaling 78% of the pipeline’s
capacity had been made. That refinery supplied refined petroleum products to the public
in Illinois, and it planned to expand the refinery capacity. Staff supported the petitioner’s
request and no intervenors contended that the Section 15-401 requirements were not
29
met. The Commission granted a Certificate after finding that a public need existed and
the public convenience and necessity required issuance of a Certificate. TransCanada
Keystone Pipeline, LP, ICC Docket No. 06-0458 (Order, April 4, 2007) (Second
Amendatory Order on Reopening, July 16, 2008).
In Docket No. 05-0343, a pipeline by common carrier of refined petroleum products
applied for a Section 15-401 Certificate for existing pipelines in Illinois that the petitioner
had acquired from another company. The pipelines had three delivery points to
customers located in central Illinois. The Commission found the existence of a public
need, as shippers used the pipeline to ship products to local areas where they are used
by the public, and are the only pipelines to serve certain areas of the State. Norco Pipe
Line Co., LLC, ICC Docket No. 05-0343 (Order, September 14, 2005).
In Docket No. 05-0344, the petitioner sought a Section 15-401 Certificate, as a
successor owner, for a pipeline transporting refined petroleum products. The pipeline had
four major branches, one of which originated at an Illinois refinery, extending to a terminal
in Illinois, and then to another Illinois location. Part of the line went to a northwest Indiana
terminal. Another pipeline section extended to a terminal in Chicago, continuing to a Shell
Oil terminal in the suburbs. From there, it delivered jet fuel to O’Hare Airport. Another
pipeline extended from the Wood River Refinery to another Illinois terminal, continuing on
to Indiana and Ohio. Another pipeline extended from Illinois into an Indiana terminal, and
a section of it extended and interconnected with a refinery at Robinson, Illinois. Another
pipeline delivered products from the Wood River Refinery to St. Louis terminals. Over 34
million barrels of products were shipped in the prior year to Illinois destinations. The
Commission found a continuing public need for the Wood River pipelines, used by
30
different shippers to transport products to local areas where they were used by the public.
The pipeline was a major shipper for products of the ConocoPhillips refinery in Wood
River, Illinois, and a significant supplier of jet fuel to O’Hare Airport. The pipelines also
were found to serve the public convenience and necessity, as the efficient transport of
products by the pipeline was found to be superior to other transport methods. Wood River
Pipe Lines, LLC, ICC Docket No. 05-0344 (Order, September 14, 2005).
In Docket No. 06-0470, Enbridge petitioned for a Section 15-401 Certificate, along
with requests for approvals under Sections 8-503 and 8-509, for its Southern Access
Expansion Program, which included two new liquids pipelines in Illinois. One would
transport crude oil through Wisconsin to a storage facility near Pontiac, Illinois. The
second pipeline, the Southern Lights Project, was to transport liquid hydrocarbons
(“diluents”) from Illinois-area refineries and other sources through other pipelines to
northern Alberta. From Pontiac (Enbridge’s Flanagan Terminal), crude oil would be
transported to Chicago and to Cushing, Oklahoma. The petitioner offered supporting
testimony of three witnesses representing the crude oil and refining market sector. Cross-
examination of all witnesses was waived, and no briefs were filed. The Commission
issued the Certificate and approvals as requested. Enbridge Energy Partners, L.P. and
Enbridge Energy, Ltd. P’ship, ICC Docket No. 06-0470 (Order, April 4, 2007) (Order on
Reopening, August 6, 2013).
In Docket No. 07-0446, Enbridge applied for a Section 15-401 Certificate, and
orders under Sections 8-503 and 8-509, to construct, operate and maintain a 170-mile
long crude oil pipeline in Illinois, from Pontiac to Patoka. Enbridge encountered
opposition from a number of intervenors. In its Order, the Commission noted that several
31
parties discussed the Lakehead Order and the appellate court’s decision affirming the
Commission’s Order. The Commission noted the difficulty in determining whether there
was a public need for the pipeline especially given that the statute does not provide a
definition. (Enbridge Pipelines (Illinois) L.L.C., ICC Docket No. 07-0446 (Order at 46, July
8, 2009), aff’d sub nom., Pliura Intervenors v. Ill. Commerce Comm’n, 405 Ill. App. 3d 199
(2010)). Acknowledging that the two polar positions on the issue both have merit, the
Commission endorsed “the broader approach to the public need determination as
proposed by Staff.” (Id.) The Order cited Staff’s suggestion that bringing Canadian crude
to the Patoka hub would provide Illinois, and the nation, with additional crude oil supplies
from a friendly and reliable country. (Id.) Staff stated that several refinery expansion
projects were underway or being contemplated in the Midwest that would increase the
demand for Canadian crude; those refineries could obtain crude directly from the
proposed pipeline, or via the Patoka hub. Staff believed that not all of the oil needed to
remain in the PADD II region, and that even if some oil was shipped to the Gulf Coast or
other regions, it would benefit the refinery industry and thus the nation. (Order, at 40). Oil
going to Gulf Coast refiners could free up alternative local sources of crude and make
them available to the PADD II region. (Id.) Staff took the view that the Commission should
consider local, regional, and national benefits in determining the impact on the public, and
that in doing so Illinoisans would benefit. (Order, at 41). Staff contended that factors such
as $4 gasoline prices, Gulf Coast hurricanes, the September 11 attacks and resulting
Middle East wars, along with the growing demand for oil by China and other developing
countries, serve to make more reliable crude oil supplies more important. Staff pointed
to economic benefit analyses provided by Enbridge that supported a finding of public
32
need. (Order, at 42). Staff also cited Enbridge testimony that prices for gasoline and other
refined products to Illinois consumers would be lower with the pipeline than they would
be without it.
The Commission’s Order in Docket No. 07-0446 was entered on July 8, 2009, and
was upheld on appeal. In May 2014, Enbridge filed a motion to reopen and amend the
2009 Order to authorize a smaller diameter pipeline (24 inches instead of 36 inches) than
the one referenced in the Certificate the Commission granted in the original proceeding.
Enbridge stated that the change in pipe size was due to a change in economic conditions
causing shippers to desire a different type of crude oil, making a smaller diameter pipe
more appropriate. Multiple landowners intervened in the reopened docket. One of the
arguments in opposition advanced by the landowners was that the pipeline was effectively
a private pipeline as a result of a single shipper (Marathon Petroleum Co.) having
committed to approximately two-thirds of the pipeline’s capacity. The Commission noted
that Enbridge was actively seeking commitments from other shippers, while also
reserving 10% of the capacity for uncommitted volumes. The Commission found that the
pipeline qualifies as common carriage despite Marathon’s large capacity commitment,
and again concluded that a public need existed. (Illinois Extension Pipeline Co., Ill.
Commerce Comm’n, Docket No. 07-0446 (Order on Reopening, December 17, 2014))
In Docket No. 12-0347, Enbridge sought a Section 15-401 Certificate, along with
orders under Sections 8-503 and 8-509, for its Flanagan South Pipeline Project, a new
168-mile long crude oil pipeline that would run from its Flanagan Terminal near Pontiac
to the Illinois/Missouri border near Quincy. The pipeline would be part of a larger pipeline
originating in Illinois and terminating at Cushing, Oklahoma. In granting the Certificate
33
and other requested approvals (Enbridge Pipelines (FSP) L.L.C., ICC Docket No. 12-
0347 (Order, February 14, 2013) (Amendatory Order, June 5, 2013)), the Commission
relied on several factors supporting a finding of public need. Multiple shippers had
contracted for over 500,000 bpd of capacity, the pipeline would help remove the
bottleneck in getting supply to the North American market, and it would help serve the
needs of the general public in Illinois and the country for crude oil products. (Order, at
29). Staff also contended that the pipeline, bringing Canadian crude to the Gulf Coast
refining region, should help lower the country’s dependence, and dependence of Gulf
Coast refineries, on foreign oil. (Order, at 28-29).
In Docket No. 13-0134, Enbridge applied for a Section 15-401 Certificate, and
orders under Sections 8-503 and 8-509, to construct, operate and maintain its Line 78, a
77-mile long crude oil pipeline. The pipeline would run from Enbridge’s Flanagan
Terminal near Pontiac, Illinois to Lake County, Indiana. The application stated that the
initial capacity would average about 570,000 bpd, but would have an ultimate capacity of
800,000 bpd. In granting the requested certification and other approvals (Enbridge
Energy Ltd. P’ship., ICC Docket No. 13-0134 (Order, April 29, 2014)), the Commission
pointed to an agreement between Enbridge and Marathon Petroleum by which Marathon
committed to capacity on the pipeline to help serve Marathon’s Detroit refinery. (Order, at
39) A BP refinery in Whiting, Indiana also was seeking more Canadian crude, which
would be transported by the proposed pipeline, for its increased refining capacity. (Order,
at 40). Demand for transportation by Enbridge’s customers had exceeded the capacity
of another Enbridge line and other pipelines in the Chicago region that deliver crude oil
to Enbridge terminals in Indiana and beyond (Id.) The record showed that the pipeline
34
would help enable more crude to be transported to several additional refineries in Ohio,
Pennsylvania, and Ontario. (Order, at 20)
In all of the dockets discussed above in which the Commission granted the
requested relief, evidence existed that (1) Illinois and area refineries needed and planned
to utilize the crude from the proposed pipeline source either directly or through area
terminals; (2) the crude would be delivered to Illinois storage facilities and petroleum
products would be transported from Illinois refineries to other destinations; (3) the pipeline
would provide crude transportation from an Illinois terminal and relieve an existing
pipeline bottleneck; or (4) other customers in Illinois used or would receive and utilize the
transported products. Additionally, in contrast to the pending docket, Staff took an active
role in evaluating the proposals in the referenced dockets. Recognizable benefits to the
citizenry of Illinois and the nation were also apparent. In none of the dockets did the
Commission find exports to be in the public interest.
B. Joint Petitioners Reliance on Short-Term Production Forecasts Is Not Sufficient to Meet Its Burden of Proof for a Public Need
Like any pipeline of the scope and scale of those at issue in the pending docket,
the anticipated lifespan of Joint Petitioners’ pipelines is several decades into the future,
even the ETCO Pipeline which is already 60 years old. Similarly, the pump station and
other facilities proposed for the capacity optimization plan also have a lifespan of several
decades if constructed. In support of the need for the proposed facilities, Joint Petitioners
repeatedly reference recent increases in crude oil production from the Williston Basin
production area. (see, for example, Dakota Access-ETCO Ex. 1.0, lines 143-158; Dakota
Access-ETCO Ex. 1.2, lines 50-58; and Dakota Access-ETCO Ex. 5.0, lines 121-126) In
light of the anticipated lifespan of the proposed facilities, it is natural and reasonable to
35
consider the long-term production forecast for the Williston Basin production area to
evaluate the long-term public need for the proposed facilities. Oddly, however, Joint
Petitioners have not done so.
Rather than consider Williston Basin production forecasts that match the lifespan
of the proposed new facilities, Joint Petitioners have inexplicably relied on forecasts that
extend only to 2023. Joint Petitioners’ witness Glenn Emery identified four sources of
production forecasts for the Bakken-Williston Basin region relied on by Joint Petitioners:
U.S. Energy Information Administration (“EIA”), North Dakota Industrial Commission
(“NDIC”), Enverus (previously known as Drillinginfo), and Wells Fargo Bank, N.A. (Dakota
Access-ETCO Ex. 1.6, lines 160-166) Confidential SOIL-SC Cross Ex. 5 reflects
production levels and forecasts as of August 2019 by the four sources from the period of
January 2017 through December 2023. Mr. Emery discusses each production projection
as of December 2023 but provides no forecasts beyond that point in time. (Dakota
Access-ETCO 1.6, lines 206-219) Joint Petitioners’ witness Laura Olive offered a fifth
production forecast from the NDIC that extends beyond 2023 (Dakota Access-ETCO Ex.
5.0, line 125-126, footnote 11), but the document that she relies upon clearly states,
“Production forecast is for visual demonstration purpose only and should not be
considered accurate for any near or long term planning.” (SOIL-SC Cross Ex. 14, at 2)
Thus, by its own terms, Dr. Olive’s document cannot be relied upon. Moreover, according
to the Joint Petition, the anticipated in-service date for the Hancock County pump station
is no later than the first quarter of 2021.6 (Joint Petition, ¶ 23) Thus, Joint Petitioners are
asking the Commission to sanction a project that is supposedly needed for decades
6 The Joint Petition does not identify the in-service dates for the proposed facilities at Patoka and Joppa, Illinois.
36
based on two years of third-party data. By any standard, such evidence is insufficient to
meet Joint Petitioners’ burden to prove a public need, and any approval based on this
limited evidence would be arbitrary and capricious.
Independent of the length of the forecasts relied upon by Joint Petitioners is the
question of whether the forecasts warrant reliance. SOIL-SC-WK do not suggest that any
of the four sources of data are intentionally misrepresentative, but rather that additional
information warrants consideration. In particular, the Commission should consider crude
oil demand forecasts, because public need (demand) for petroleum fuels is critical to
determining whether the project serves “the security or convenience of . . . the public,”
Section 8-503, and in determining whether or not “a public need for the service exists.”
Section 15-401 (emphasis added). As can be seen from confidential SOIL-SC Cross Ex.
5, the EIA production forecast is consistently the highest. But as SOIL-SC witness
Richard Stuckey explains, EIA forecasts are based on current regulatory requirements.
As such, any curtailment of crude oil demand due to climate change mitigation efforts and
changes in consumer consumption patterns, such as the trend toward electric vehicles,
are not reflected in the EIA’s crude oil production forecast. (SOIL-SC Ex. 4.0, lines 669-
672) Nor does the record reflect any consideration by Joint Petitioners of declines in
fossil fuel use related to climate change mitigation efforts. Dr. Olive acknowledges that
she did not perform an analysis of how efforts to mitigate climate change may impact
demand for fossil fuels. (SOIL-SC Cross Ex. 14, at 1) So Bakken production may not
reach forecasted production levels, whatever they may be in the long-term, if anticipated
demand fails to develop as reliance on fossil fuels declines.
37
SOIL-SC witness David Hughes offers another reason why the production
forecasts relied on by Joint Petitioners do not meet Joint Petitioners’ burden of proof. He
points out that EIA forecasts, to be accurate, require production of more oil than the
aggregate of EIA estimates of proven reserves plus unproven resources. (SOIL-SC Ex.
8.0, lines 99-101) Because one cannot produce more oil than is technically and
economically recoverable, production is likely to be much lower than the EIA forecast.
(Id., lines 103-105) Mr. Hughes also observed that in 2013, the United States Geological
Survey (“USGS”) estimated undiscovered technically recoverable resources in the
Bakken/Williston Basin at a mean of 7.4 billion barrels, compared to the EIA estimate of
unproven resources of 16 billion barrels. (Id., lines 108-111) As shown in the following
chart from SOIL-SC Ex. 8.5, application of USGS data to the EIA 2019 Annual Energy
Outlook indicates that Bakken production will peak in 2021 and remain on a rough plateau
through 2031, after which it will decline to zero over two decades. (Id., lines 119-121)
38
Mr. Hughes notes as well that neither the EIA estimates of unproven resources in the
Bakken/Williston Basin, nor the USGS estimates of undiscovered resources, considered
economics, meaning neither considered whether sufficient demand for crude oil will exist
to make extraction of the oil financially viable. Therefore, neither the EIA production
forecast nor the USGS estimates provide any assurance that the public will demand more
North Dakota crude oil, even if it is technically possible to extract it from the ground. For
this reason, even the production outlook in SOIL-SC Ex. 8.5 is likely optimistic and does
not imply that there will be a public need for the Project. (Id., lines 134-138)
The importance of considering economics in production and demand forecasts is
all the more important in light of the impact the emergence of COVID-19 has had on global
oil markets. The EIA production forecast relied upon by Joint Petitioners certainly does
39
not reflect COVID-19’s impact on the global oil industry, let alone the Bakken region. (Tr.
at 693) Nor does the above chart provided by Mr. Hughes reflect COVID-19’s impact.
Although Staff cites increased crude oil production in the Williston Basin production
area as one reason why it does not object to Joint Petitioners’ capacity optimization plan
(Staff Ex. 1.0, lines 147-149), SOIL-SC-WK respectfully submit that Staff’s position should
not be given much, if any, weight. The source of Staff witness Brett Seagle’s information
concerning increased production in the Williston Basin is the testimony of Joint
Petitioners’ witness Glenn Emery. Mr. Seagle acknowledged during cross examination
that he relied solely on information provided by Joint Petitioners in coming to his
conclusions. (Tr. at 773-774) As mentioned elsewhere in this Initial Brief, there is no
evidence that Staff did anything more than rely on Joint Petitioners’ assertions. There is
no evidence that Staff questioned any response from Joint Petitioners. There is no
evidence that Staff conducted any independent analysis. There is no evidence that Staff
considered any position other than Joint Petitioners’. With all due respect to Staff, such
a review falls far short of the mission statement reflected on the Commission’s website,
which provides in relevant part: “The ICC's mission is to balance the interests of
consumers and utilities to ensure adequate, efficient, reliable, safe and least-cost public
utility services, while promoting the development of an effectively competitive energy
supplier market.”
For the foregoing reasons, the unreasonably short Bakken region production
forecasts relied on by Joint Petitioners offer insufficient evidence of public need for
additional crude oil pipeline take-away capacity from North Dakota. Notably, no
producers have intervened in this case to support Joint Petitioners’ argument that
40
Williston Basin production warrants additional pipeline capacity. Joint Petitioners’
reliance on only three-year long incomplete, overly optimistic production forecasts that
fail to account for rapidly growing electric vehicle use, fail to consider climate change
mitigation efforts, fail to consider critical USGS data, and completely disregard the
economics underlying extraction does not justify a project with a multi-decade lifespan.7
The shortcomings in Joint Petitioners’ production forecasts fail to move them any closer
to meeting their burden to demonstrate that their project is necessary for the security or
convenience of the public under Section 8-503 or that there is a public need for the plan
or that the public convenience and necessity requires its implementation under Section
15-401.
C. Joint Petitioners’ Reliance on TSA Contractual Commitments Is Insufficient to Meet Its Burden of Proof
Joint Petitioners rely primarily on the TSAs executed in response to their 2018
open season to meet their burden of proof under Sections 8-503 and 15-401. The total
commitment to new pipeline capacity made in these contracts total ***CONFIDENTIAL
SSSSSSSSCONFIDENTIAL*** (DA-ETCO Ex. 1.6, lines 64-66) SOIL-SC-WK assert
that both the amount of this commitment and the terms of the TSAs demonstrate that
Joint Petitioners have not met their burden of proof.
SOIL-SC-WK note that the total commitment made in the TSAs amounts
***CONFIDENTIAL XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXX CONFIDENTIAL *** Joint Petitioners also
rely on the potential for a more recent open season that began in July of 2019 to fill
7 The failure of the record to reflect the impact of COVID-19 on the global oil industry alone renders the production forecasts in the record unreliable.
41
additional capacity. However, nine months have passed since the start of this 2019 open
season and Joint Petitioners still have not announced any successful additional capacity
commitments based on it. Instead, Joint Petitioners claim that this open season has been
extended indefinitely. (Tr. at 392) SOIL-SC-WK assert that the Commission should find
that the 2019 open season has failed to produce any additional capacity commitments,
and given current commercial circumstances, it should also find that the 2019 open
season has failed in its entirety, despite Joint Petitioners’ failure to admit to the obvious.
This contracting failure reflects the degree to which oil markets have changed since 2018.
It also means that, at best, the current and foreseeable contractual commitments
supporting the project ***CONFIDENTIAL XXXXXXXXXXXXXXXXXXXXX
CONFIDENTIAL *** Given current market conditions, it is not reasonable to expect
additional capacity commitments for the foreseeable future. SOIL-SC-WK assert that the
existing contractual commitment is insufficient to meet Joint Petitioners’ burden of proof
to show a public need for the capacity optimization plan.8
The Commission should not give undue weight to commercial judgments made by
shippers nearly two years ago, the apparent failure of Joint Petitioners’ 2019 open
season, and subsequent oil market developments. Given these factors, the Commission
should not treat the existence of TSA’s as prima facie evidence of public need. Joint
Petitioners’ contracted shippers have no powers to see the future and are fully capable
of making mistakes in their contracting decisions. Also, more recent market evidence
proves that the shippers’ commercial judgment was in error. Therefore, the Commission
is not bound by the outdated judgments underlying the 2018 TSAs. Therefore, the
8 The impact of the COVID-19 pandemic on both existing shippers and, to the extent different, expansion shippers is unknown.
42
evidence in the record indicates that the Commission should determine that the 2018
TSAs do not by themselves justify expansion of the pipelines, particularly given the risks
that expansion imposes on Illinois.
The terms in the TSAs themselves demonstrate that Joint Petitioners are aware
that the TSAs are not set in stone, but rather must account for future market changes. In
particular, ***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
43
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
• sssssssssssssssssssssssssssssssssssssssssssssss
• ssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss ssssssssssssssss
• ssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss sssssss
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
44
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
CONFIDENTIAL***
Accordingly, SOIL-SC-WK assert that the Commission should not give undue
weight to the existence of TSAs, because the total amount of the commitment is not
relatively high and for practical purposes they are contingent on future market conditions.
D. Existing Take-Away Capacity from North Dakota Is Sufficient to Transport Forecasted and Contracted Volumes
Joint Petitioners’ inadequate crude oil production forecasts should be considered
in light of existing capacity by other carriers to transport any near-term increase in North
Dakota crude production that might materialize. The Commission previously recognized
the propriety of doing so in its aforementioned Lakehead Order. In that Order, the
Commission criticized Lakehead for failing “to consider the relevance of any crude oil and
45
refined petroleum product pipeline systems other than its own in arriving at its conclusion
that a public need for its proposed pipeline project existed.” (1997 Ill. PUC LEXIS 255,
*37) In the docket at hand, Joint Petitioners offered no analysis or other evidence that
existing take-away capacity from the Bakken region is insufficient. In fact, public
information demonstrates that the opposite is true.
SOIL-SC Exs. 8.2 and 8.3 show that existing pipelines and railroads have more
than enough capacity to transport the modest if optimistic short-term production forecasts
provided by Joint Petitioners. FERC data presented by SOIL-SC witness David Hughes
shows that unused capacity on existing pipelines amounted to 297,935 bpd as of the
second quarter of 2019. (SOIL-SC Ex. 8.2, lines 69-70) He also presented evidence that
unused railroad takeaway capacity totaled 1,042,422 bpd. (SOIL-SC Ex. 8.2, lines 74-75)
In contrast, Joint Petitioners claim that North Dakota production will increase by 350,000
to 450,000 bpd over the next 5 years. (Dakota Access-ETCO Ex. 1.0, lines 145-150;
Dakota Access-ETCO Ex. 1.6, at 7) Together, unused pipeline and railroad capacity is
more than adequate to meet Joint Petitioners’ near-term production forecast, should it
materialize.
***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxCONFIDENTIAL *** (Dakota Access-
ETCO Ex, 1.6 lines 64-66) The evidence shows that existing pipeline and railroad
capacity is more than adequate to meet possible future demand for takeaway capacity
from North Dakota, particularly given the lack of evidence supporting Joint Petitioners
crude oil production forecasts and the results of the 2018 open season.
46
Joint Petitioners’ witness David Harrison even agrees that existing Bakken take-
away capacity is sufficient to handle the forecasted production Joint Petitioners rely on.
He provides a map in his prepared testimony which he testifies “shows that the
Bakken/Three Forks oil basin is well-connected by railroad to major refining centers.”
(Dakota Access-ETCO Ex. 9.0, lines 184-185) When asked if there is enough capacity
in the existing railroad and pipeline systems to allow the additional crude oil to be
transported by rail or other pipelines if the Joint Petition is denied, he clearly states, “yes.”
(Id., lines 194-197) Referencing the higher of two projections in the same longer-term
NDIC production forecast cited by Dr. Olive (which contains an advisory against relying
on it for near or long term planning), he goes on to state, “this figure indicates that there
is sufficient rail capacity to carry the additional 0.5 million barrels/day of crude projected
in the Joint Petition to be carried on the Dakota Access and ETCO pipelines.” (Id., lines
204-206) (See also Dakota Access-ETCO Ex. 5.0, line 125-126, footnote 11 and SOIL-
SC Cross Ex. 14, at 2) SOIL-SC-WK appreciate Dr. Harrison’s candor in acknowledging
the lack of need due to other transportation options being available.
But despite the testimony of their own witness that sufficient transportation
capacity already exists, Joint Petitioners refuse to acknowledge that fact and point to a
handful of TSAs as all the evidence they need. For example, Joint Petitioners’ witness
Glenn Emery asserts that the existence of its TSA contractual commitments is evidence
that “the other pipelines and the rail capacity that Mr. Hughes . . . refer[s] to do not
transport crude oil to destinations where these shippers want it delivered and/or are not
viewed by the market as long-term, competitive transportation service options.” (Dakota
Access-ETCO Ex. 1.6, lines 37-44) Essentially, he argues that the Commission should
47
ignore Lakehead and find that the potential costs of the expansion to Illinois are justified
not by an absolute need to transport crude oil from North Dakota, but by the shippers’
2018 judgments that the DA-ETCO route better serves their commercial needs as these
were understood in 2018.
Even if supply grows for the few years forecast by Joint Petitioners such that
shippers have oil to transport pursuant to their TSAs, denial of the project would not result
in stranded oil in North Dakota, though it is possible that it might result in non-optimal
routing of crude oil to market. But, it might not. The Commission should not burden the
public with Joint Petitioners’ questionable project when the evidence shows that the North
Dakota oil industry can move even the overly optimistic supply increase forecasts
provided by Joint Petitioners as well as the specific amounts contracted through the 2018
TSAs to market using existing infrastructure.
E. Refineries Are Operating at Capacity And Do Not Need More Crude In an effort to justify nearly doubling the throughput of their pipelines, Joint
Petitioners have commented on the additional crude they seek to transport being
available to refineries in Petroleum Administration for Defense District9 (“PADD”) II and
PADD III. (See, for example, Dakota Access-ETCO Ex. 1.2, lines 69-90, 159-162, and
Dakota Access-ETCO Ex. 5.0, lines 196-210) At the same time, however, in both their
testimony and in response to discovery, Joint Petitioners have insisted that they do not
9 The Petroleum Administration for Defense Districts are geographic aggregations of the 50 States and the District of Columbia into five districts: PADD 1 is the East Coast, PADD 2 the Midwest, PADD 3 the Gulf Coast, PADD 4 the Rocky Mountain Region, and PADD 5 the West Coast. During World War II the Petroleum Administration for War used these five districts to ration gasoline. Although the Administration was abolished after the war in 1946, Congress passed the Defense Production Act of 1950, which created the Petroleum Administration for Defense and used the same five districts, only now called the Petroleum Administration for Defense Districts.
48
know where the oil they transport will end up. (See, for example, Dakota Access-ETCO
Ex. 1.2, line 119-121; Dakota Access-ETCO Ex. 1.2, lines 242-245; SOIL-SC Ex. 1.5 at
1 and 2; SOIL-SC Ex. 1.6; and SOIL-SC Ex. 4.16) Moreover, in response to DRs SOIL
1.016 and 1.017 (SOIL-SC Ex. 1.5), Joint Petitioners asserted that the destination of the
additional volumes of crude oil they seek to transport is irrelevant. To be clear, SOIL-SC-
WK believe that the destination of the crude oil is relevant in determining whether there
is a public need for the capacity optimization plan under Illinois law – a view the
Commission has shared in common carrier pipeline dockets since Lakehead. What is not
clear is how Joint Petitioners can argue that the destination is not relevant but at the same
time suggest, to support a finding of public need, that domestic refineries will make use
of the additional crude oil Joint Petitioners propose to transport. Such statements are
another example of Joint Petitioners offering inconsistent statements that have led SOIL-
SC-WK to question much of what Joint Petitioners have offered in this docket.
But setting aside the inconsistency of Joint Petitioners’ public need argument, it is
important to consider the ability of PADD II and PADD III refineries to accommodate the
additional crude oil Joint Petitioners propose to transport. As an initial matter, there is no
dispute that the vast majority of the crude oil transported by Joint Petitioners is destined
for the Gulf Coast. SOIL-SC witness Richard Stuckey reports that ***CONFIDENTIAL
xxxx CONFIDENTIAL*** of the current capacity (excluding 10% reserved for walk-up
shippers) is diverted at Patoka, Illinois and the remaining current contracted throughput
continues to Nederland, Texas. (SOIL-SC Ex. 4.0, lines 167-171) Of the shipper
commitments made during Joint Petitioners’ 2018 open season for the capacity
expansion, 97.5% of the additional crude oil is to be shipped to Nederland, Texas in PADD
49
III. The remaining 2.5% would apparently leave Joint Petitioners’ pipelines at Patoka,
Illinois in PADD II (SOIL-SC Ex. 1.0, lines 230-233), although it is possible that some of
the crude oil could still find its way to Nederland. Very little of the additional throughput
would even remain in PADD II to be processed by refineries in that district. This means,
assuming the crude oil even remains in the United States, that refineries in PADD III,
particularly in the Gulf Coast region, would be the ones to most likely process the
additional crude oil Joint Petitioners propose to transport.
The likelihood that PADD III refineries, let alone PADD II refineries, can accept the
additional crude is highly questionable. SOIL-SC-WK concur with Joint Petitioners’
witness Laura Olive that refinery utilization rates in PADDs II and III have been
consistently high over the last 30 years. (Dakota Access-ETCO Ex. 5.0, Table 3) High
utilization rates are indicative of refineries having sufficient supplies of crude oil for
processing. While Joint Petitioners argue that high utilization rates suggest that Midwest
and Gulf Coast refiners may be thinking of expanding operations (Dakota Access-ETCO
Ex. 1.6, lines 361-363), they offer limited evidence of that being anything more than
speculation. At best, Dr. Olive provides a press release from ExxonMobil announcing
plans to expand its existing refinery in Beaumont, Texas. (Dakota Access-ETCO Ex. 5.3)
The January 29, 2019 press release, however, clearly indicates that the capacity
expansion will be “supported by the increased crude oil production in the Permian Basin.”
(Id., at 2) The Permian Basin is in west Texas, not North Dakota, so Dr. Olive’s reliance
on the ExxonMobil press release does nothing to support Joint Petitioners’ underlying
contention that refinery expansion will facilitate the processing of the additional North
Dakota Bakken crude they seek to transport. Dr. Olive’s other references to three refinery
50
expansions in 2015 and 2016 offer similarly weak evidence that refineries will expand
capacity in the future to handle additional Bakken crude. (Dakota Access-ETCO Ex. 5.2,
lines 80-85) SOIL-SC-WK do not question that from time to time refineries may change
their operating capacity, but relying on expansions that occurred several years ago to
support the claim that expansions will occur in the future is simply speculation. Her
reliance on PADD II and III refinery expansion to accommodate additional Bakken crude
is particularly speculative given her admission, as noted previously, that she has not
considered how efforts to mitigate climate change may impact demand for fossil fuels.
(SOIL-SC Cross Ex. 14, at 1) She essentially assumes that the fossil fuel industry will
continue to function as it always has despite the global movement away from fossil fuels.
Even if refineries in PADDs II and III were not operating at near 100% capacity,
there is also the question as to whether the refineries could technically accommodate the
type of crude oil extracted from the Williston Basin. The North Dakota crude shipped by
Joint Petitioners is light, sweet crude. But according to the EIA, Gulf Coast refineries are
configured mostly to process heavy, sour crude oils. (SOIL-SC Ex. 1.14, at 1) SOIL-SC-
WK accept that there could be some refineries in the Gulf Coast region that are configured
to process light, sweet crude oils and even those configured to process heavy, sour crude
oils may be able to blend in some quantity of light, sweet crude oils. But analytical firm
IHS Markit reports that “the light crudes, condensates, and natural gas liquids (NGLs)
produced with unconventional development techniques have saturated US markets, but
they are well-suited for growing markets in Asia and elsewhere.” (SOIL-SC Ex. 4.0, lines
380-383) Similarly, Mr. Stuckey notes that RBN Energy LLC reported as recently as
November 6, 2019 that “U.S. refineries are taking about as much domestic crude as they
51
can and so most incremental barrels of light tight oil ought to be exported. As we track in
our Crude Voyager report, the major regions from which crude is exported are Louisiana,
Beaumont (TX), Houston (TX), and, coming on strong recently, Corpus Christi (TX).”10
(Id., lines 383-388) Generalizations by Joint Petitioners that domestic refineries may or
could process additional light, sweet Bakken crude (Dakota Access-ETCO Ex. 1.2, lines
185-194; Dakota Access-ETCO Ex. 4.0, lines 63-64) in a market awash with light, sweet
crude is hardly persuasive evidence that there is a need for Joint Petitioners to transport
additional light, sweet crude through PADD II and into PADD III. In fact, the EIA document
cited by Dr. Olive indicates that Midwest refineries have actually been processing heavier
grades of crude oil.11 (Dakota Access-ETCO Ex. 5.4, at 1)
Despite Joint Petitioners’ disagreement, the pending reversal of the Capline
Pipeline (“Capline”), the largest northbound crude oil pipeline that historically brought
crude oil from the Gulf Coast to the Midwest, also signals that Midwest refineries are
adequately served. (SOIL-SC Ex. 1.0, lines 217-220) If there was still demand for
additional crude oil in the Midwest, Capline would not be reversed. But as it is, the owners
are Capline are working towards reversing the flow so that additional crude can be
transported from Patoka, Illinois to the Gulf Coast. On cross-examination during the
evidentiary hearing, it was noted that the reversed Capline will carry both light and heavy
crudes south to the Gulf Coast. (Tr. at 428) Regardless of where on Capline light crude
is introduced, the fact remains that additional light and heavy crudes would be transported
10 Although the export of the crude transported by Joint Petitioners will be discussed later, it is worth nothing that in this discussion of domestic refinery capacity that the Beaumont area includes Joint Petitioners’ affiliated Nederland facilities. (SOIL-SC Ex. 4.0, lines 388-389) 11 How the pandemic induced loss of demand for refined petroleum products has impacted refinery operations is not reflected in the record.
52
south, away from the Midwest refineries that Joint Petitioners suggest need more light
crude oil. Again, it is not clear how Joint Petitioners can maintain that refineries need the
additional Bakken crude oil that Joint Petitioners propose to transport.
Dr. Olive’s suggestion that global consumption of refined petroleum products
between 2010 and 2018 justify Joint Petitioners’ proposal also lacks merit. As can be
seen from Table 1 of her surrebuttal testimony (Dakota Access-ETCO Ex. 5.2), while
global consumption has risen since 2010, the annual rate of increase is declining. In
other words, according to Dr. Olive’s Table 1, the global growth rate in the consumption
of refined petroleum products is slowing. This observation supports the SOIL-SC-WK
position that Joint Petitioners’ proposed additional throughput is not needed to address a
shortfall in supply for refiners. Moreover, the record lacks any discussion of the impact
of COVID-19 on global oil demand.
Along those lines, it is worth noting that no refiners have intervened in this
proceeding to support the Joint Petition. Joint Petitioners are alone in speculating that
Midwest and Gulf Coast refineries can currently use or will in the future undertake costly
refittings or expansions in order to process the additional light, sweet crude that Joint
Petitioners contend is needed and in the public interest. Nor is there any evidence that
Staff considered the ability of PADD II or PADD III refineries to process light, sweet crude
or whether they could accommodate any additional crude of any grade. In the absence
of any actual evidence, Joint Petitioners’ claim that refineries may process the additional
Bakken crude fails bring them any closer to meeting their burden.
53
F. Additional Crude Volumes Appear Destined for Export SOIL-SC-WK have found no Commission dockets approving a new common
carrier pipeline where most, or even a substantial portion, of the oil to be transported by
the pipeline would be exported to overseas countries and markets. The subject of
possible exports of oil arose and was discussed briefly in one docket of which SOIL-SC-
WK are aware. In Section IV.A.2. of this Initial Brief, SOIL-SC-WK discuss Docket No. 12-
0347, involving a new Enbridge pipeline project. The Commission cited in its Order the
testimony of a witness for the applicant on the subject of crude oil exports from the U.S.
The witness dismissed suggestions that the crude oil to be carried by the proposed
pipeline was intended for export, as having no basis in fact. (Order, at 26).12 Contrary to
the situation in Docket No. 12-0347, the record in the instant proceeding demonstrates a
strong likelihood that substantial, if not most, incremental volumes of crude oil to be
transported with the increased pipeline capacity will be exported out of the Gulf Coast.
In reviewing the Joint Petition and Joint Petitioners’ direct testimony, one logically
infers that the destinations of the additional crude oil volumes that would be enabled by
Joint Petitioners’ proposed capacity expansion would be transported to and refined by
Midwest and Gulf Coast refineries. According to the Joint Petition, “Crude petroleum
transported by the Dakota Access Pipeline can be transferred to other pipelines at Patoka
for shipment to other Midwestern refineries.” (Joint Petition, ¶ 11) Joint Petitioners then
referenced transport to Gulf Coast refineries, stating, “Crude petroleum … can be
transferred to the ETCO Pipeline at Patoka for shipment to Nederland, Texas, and the
12 “It has sometimes been suggested that these types of economic benefits to Illinois may not occur because, the argument goes, the crude oil to be carried by the Flanagan South Pipeline will somehow be ‘diverted’ or intended for export. Mr. Felmy, testifying for Applicant, says that such arguments ‘have no basis in fact.’” (internal citation omitted). Id.
54
Gulf Coast refinery region.” (Id.) Nowhere in the Joint Petition is there any indication that
the incremental crude oil volumes would end up anywhere other than Midwest and Gulf
Coast refineries, and certainly no hint of exporting any of the crude exists. Similarly, Joint
Petitioners’ lead witness Glenn Emery described the refinery regions Joint Petitioners’
pipelines can access in his direct testimony, stating:
Additionally, crude petroleum transported by the Dakota Access Pipeline from the Bakken/Three Forks region to Patoka can be transferred to other pipelines at Patoka for shipment to other Midwestern refineries; and crude petroleum transported to Patoka via other pipelines can be transferred to the ETCO Pipeline at Patoka for shipment to Nederland, Texas, and the Gulf Coast refinery region. (emphasis added) (Dakota Access-ETCO Ex. 1.0 at 4, lines 78-82)
Again, Mr. Emery implies that the proposed capacity expansion is needed to enable
transportation of more crude oil to U.S. refineries for processing, providing no hint of
exportation of any of the incremental crude volumes.
Mr. Emery also reiterated a factor Joint Petitioners have emphasized, that “[t]he
increased demand for crude petroleum transportation services on the Dakota Access and
ETCO Pipelines has been driven primarily by increased crude oil production from the
Williston Basin production area, including the Bakken/Three Forks region.” (Id., lines 143-
145) In other words, according to Joint Petitioners, because the supply of crude oil has
increased, as long as someone is willing to take it from its production area and ship it,
utilizing Joint Petitioners’ pipelines to do so, that should be sufficient to satisfy this
Commission. But that is not sufficient; establishing public need requires more. The
sources of the demand for the oil by those who will refine or otherwise use it, and not
simply those who will ship it, are relevant and material to the determination of need. As
the Commission held in Lakehead, “the general concept of analyzing the appropriate
55
market and other providers in that market, and not just the pipeline itself, should be a
guiding principle in determining public need.” (Lakehead, 1997 PUC LEXIS, at *34)
In his rebuttal testimony (Dakota Access-ETCO Ex. 1.2), Mr. Emery continued to
advance Joint Petitioners’ strong implication that the incremental crude oil would be
shipped to and processed by Midwest and Gulf Coast refineries. In referencing Mr.
Rahbar-Daniels testimony in Docket No. 14-0754, he echoed “that Midwest refineries to
which crude oil delivered by the Dakota Access pipeline from the Bakken region to Patoka
could be delivered (on other pipelines) included four refineries in Illinois (which is all of
the refineries in Illinois), the BP refinery in Whiting, Indiana, and refineries in Lima and
Canton, Ohio.” (Id., lines 72-76) (internal citation omitted) Further echoing Mr. Rahbar-
Daniels, Mr. Emery testified that “the ETCO pipeline would enable supplies of crude oil
from the Bakken region to be transported directly to the substantial Gulf Coast refinery
complex ….” (Id., lines 76-78) If most of the incremental crude oil volumes are destined
for export, rather than to be refined or processed by domestic customers, it is
understandable that Joint Petitioners would not want that fact known. To the knowledge
of SOIL-SC-WK, no common carrier pipeline company has ever been granted a PUA
Section 15-401 Certificate or other approval from this Commission where the product or
products to be transported are destined for overseas foreign markets. As previously
discussed above, in Docket No. 06-0470, Enbridge sought a Certificate for two new
liquids pipelines in Illinois. While one transported crude oil into an Illinois storage facility,
the other transported a refined product, liquid hydrocarbons (diluents), into Canada. The
diluents, however, were sourced in part from Illinois-area refineries. That proceeding
56
certainly does not establish precedent for a finding of public need based on the exporting
of crude oil, especially oil originating out of state and merely being shipped through Illinois.
Intervenor William Klingele noted the lack of information from Joint Petitioners as
to the ultimate destinations of the additional volumes that the proposed increase in
pumping capacity would enable. He stated he saw no evidence as to how much if any of
the additional oil will be delivered to and processed by refineries in Illinois, or anywhere
in the U.S. It appeared to Mr. Klingele that most of the additional volumes will be
exported. He found it strange that, in contrast to the evidence as to the destinations of
the oil Joint Petitioners offered in the original pipeline Certificate dockets (14-0754 and
14-0755), they offered no similar public need-related evidence in this proceeding.
Moreover, they have resisted attempts to elicit information about destinations for the
additional volumes. (Klingele Ex. 1.0, lines 298-311)
Mr. Stuckey made similar observations in his direct testimony. He stated that it is
not known that the public in Illinois or the Midwest will benefit from the proposal. He noted
that Joint Petitioners refused in discovery to identify any Illinois refineries that would
receive crude oil from the proposed incremental capacity. (SOIL-SC Ex. 1.0, lines 174-
182) Mr. Stuckey then testified that in another discovery request, Joint Petitioners
acknowledged that the incremental crude volumes could be exported from the U.S. for
refining or conversion elsewhere. (Id., lines 182-184; SOIL-SC Ex. 1.5)
Mr. Emery finally acknowledged near the end of his rebuttal testimony that at least
some of the incremental crude volumes enabled by Joint Petitioners’ proposed capacity
expansion plan would be exported:
57
Q. Do you acknowledge that some of the increased amount of crude oil that the Dakota Access and ETCO pipelines will be able to deliver to Nederland, Texas, with the additional pumping capacity will be exported?
A. As I have stated, and as the Petitioners have stated in response to data requests, the Petitioners transport crude oil placed on their pipelines by shippers to the destination points of the Patoka, Illinois, and Nederland, Texas, terminals, and do not control or necessarily know the ultimate destinations or uses of the oil. … However, as Petitioners’ witnesses Dr. Makholm and Mr. Caruso explain, this transition to and position as an exporter is a good thing, not a bad thing.
(Dakota Access-ETCO Ex. 1.2, lines 239-253) Mr. Emery added that “there is a market demand for additional exports of U.S.-produced
crude oil, to which Petitioners’ parent company is responding with plans for additional
transportation facilities. (Id., lines 280-282)
As it became more evident that much if not most of the incremental crude oil
volumes would be exported rather than refined in the U.S., Joint Petitioners added expert
testimony attempting to defend and justify crude oil exports as being consistent with the
interests of our country. As explained hereinabove, however, in no common carrier by
pipeline docket of which SOIL-SC-WK are aware has this Commission based a finding of
public need on the exporting of the liquid product(s) carried by the pipeline.
Despite Joint Petitioners’ lack of candor regarding the destination of the
incremental crude oil they propose to transport, compelling evidence exists that their
primary parent, Energy Transfer, plans to export the crude. To begin with, Mr. Stuckey
relates that the Gulf Coast, where the ETCO Pipeline ends, was the departure point for
more than 90% of U.S. crude oil exports. The EIA attributes the export increase in part
to the increase in domestic production. According to the EIA, the increased production is
mostly of light, sweet crude oils, but U.S. Gulf Coast refineries are configured mostly to
process heavy, sour crude oils. This increasing production and mismatch between crude
58
oil type and refinery configuration causes more of U.S. crude oil production to be
exported. (SOIL-SC Ex. 1.14) Coincidentally, the type of crude oil shipped by Joint
Petitioners is light, sweet crude oil. (SOIL-SC Ex. 1.0, lines 248-249)
Joint Petitioners’ interest in expanding their transportation capacity to the Gulf
Coast coincides with their primary parent’s plans to expand on their existing crude oil
export capacity from Texas. Energy Transfer is in discussions with potential shippers to
build an export facility in Texas capable of handling supertankers, which can transport
about 2 million barrels of crude oil. (SOIL-SC Ex. 1.15) In addition, during Energy
Transfer’s August 2019 earning call, Thomas Long, Energy Transfer’s Chief Financial
Officer, stated:
But from Energy Transfer's standpoint our focus is finding a home for our liquids. And if that means China it means China, if it means other parts of the world and that's what we're doing. So we certainly have expanded out to other areas. But we remain in negotiations with several – a number of Chinese companies. (SOIL-SC Ex. 1.16, at 29)
Mr. Long’s reference to China is consistent with Mr. Emery’s acknowledgement that
Energy Transfer recently opened an office in Beijing, the capital of China. (Tr. at 402-403)
In addition, in December of 2019, Energy Transfer closed on its acquisition of
SemGroup (Tr. at 402), another pipeline company with refinery, storage, and export
facilities in Houston, Texas. According to Energy Transfer’s September 2019 press
release announcing the acquisition, SemGroup will further expand on Energy Transfer’s
crude oil export capabilities. (SOIL-SC Exhibit 1.17) The December 2019 press release
announcing the completion of the acquisition reiterated the enhancement of Energy
Transfer’s export capabilities, noting that SemGroup’s Houston Fuel Oil Terminal has five
deep-water ship docks and seven barge docks. (SOIL-SC Cross Ex. 4)
59
In light of Joint Petitioners’ inability to provide evidence of domestic use and
compelling evidence that the additional throughput Joint Petitioners propose to transport
will be exported, the Commission should find that Joint Petitioners have not demonstrated
a public need for their capacity optimization plan.13
G. The Public Burdens Outweigh the Private Benefits
1. Balancing Costs and Benefits is Appropriate and Necessary
Concomitant with the question of need for a project like Joint Petitioners is the
question of what benefit is to be gained by implementing such a project. For if a project
is truly needed, there must be some benefit to be gained by it. Moreover, the benefit must
be to the public, rather than to one or more private entities. Furthermore, it is not enough
for Joint Petitioners to simply identify one or two benefits to meet their burden of
establishing need. As SOIL-SC witness Peter Christensen explained, an evaluation of
the benefits of the project to the public “must consider a range of potential impacts and it
is reasonable to assume that the expansion will be beneficial if and only if the prospective
benefits exceed the costs.” (SOIL-SC Ex. 7.0, lines 39-41) To consider only benefits
without contemplating burdens or costs is shortsighted and may very well result in net
harm to the public. Fortunately, the Commission has expressed support for considering
both benefits and burdens to the public associated with projects brought before it. In the
aforementioned Lakehead proceeding, Docket No. 96-0145, the Commission considered
a pipeline project under Section 15-401 of the PUA. In its Order denying the requested
Certificate, the Commission found that, “[t]he benefits and burdens to the public resulting
13 Notably, Staff did not address whether the desire to export the Bakken crude is sufficient to demonstrate a public need.
60
from the proposed project are relevant when addressing the public convenience and
necessity.” (1997 Ill. PUC Lexis 255, at *38)
SOIL-SC-WK recognize that, as an administrative body, the Commission is not
required to abide by the referenced finding in Docket No. 96-0145, but logic validates the
wisdom in doing so. Mr. Stuckey offers a simple and apt analogy to demonstrate why
broader examination of benefits and costs consistent with the Commission’s earlier
conclusion remain appropriate and reasonable, both in the context of evaluating the public
convenience and necessity under Section 15-401 and evaluating whether changes are
necessary and ought reasonably to be made or are necessary and should be erected to
promote the convenience of the public under Section 8-503. Consider, for example, a
decision about whether to use asbestos as building insulation. Most buildings need some
form of insulation. Asbestos has beneficial insulation qualities. Asbestos would therefore
seem to fit a need and provide a benefit. Any rational evaluation, fortunately, does not
end there. Although unknown when its use first began, science now recognizes that
asbestos is dangerous to human health. Asbestos is still used in limited circumstances,
but it is now widely regarded as a substance to be avoided. (SOIL-SC Ex. 4.0, lines 745-
752) In the situation at hand, assuming the Commission recognizes a need exists to ship
an additional 530,000 bpd despite the deficiencies in the forecasts and the apparent lack
of shipper interest discussed elsewhere in this Initial Brief, SOIL-SC-WK aver that the
Commission should balance any marginal benefit associated with shipping an additional
530,000 bpd against the negative impacts of climate change resulting from the
consumption of that crude oil, the increased risk of spills due to the reasons outlined by
SOIL-SC witness Kuprewicz, and greater risk imposed on landowners without additional
61
compensation. (SOIL-SC Ex. 4.0, lines 745-757) Like asbestos, science now recognizes
the harm inherent in continued fossil fuel use and such negative attributes must be
weighed against the benefits claimed by Joint Petitioners.
In support of their claim of need, Joint Petitioners have the burden of proving that
their proposal benefits the public. Not surprisingly, Joint Petitioners do not acknowledge
any burdens or costs associated with the capacity optimization plan. To do so would
further weaken their claims of need and make meeting their burden in this docket more
difficult. Joint Petitioners’ witness Jeff Makholm even argues in his prepared testimony
that it is not appropriate to balance costs and benefits. He denies there being any
distortions or market imperfections that warrant such balancing. (Dakota Access-ETCO
Ex. 6.2, lines 441-496) Contrary to the Commission’s Order in Docket No. 96-0145, Dr.
Makholm argues in his written testimony that regulators let the competitive market and
“private profitability calculations” determine the “desirability” of additional pipeline projects
to the transport market. (Id., lines 478-482) Perhaps realizing the imprudence of denying
in his prepared testimony the need to balance costs and benefits, however, on cross-
examination Dr. Makholm testified that the Commission “is weighing costs and benefits
of approving in the public’s interest the optimization project.” (Tr. at 540) In trying to
explain himself, Dr. Makholm attempts to distinguish SOIL-SC witness Peter
Christensen’s discussion of the need for a cost-benefit analysis from what he
characterizes as the Commission’s customary balancing of costs and benefits. (Id.) To
be clear, Dr. Makholm does not deny that a cost-benefit analysis can be conducted, he
simply indicates that the vague analysis he references has a different purpose. (Id.)
62
Notably, among the vagaries of his testimony on cross-examination, Dr. Makholm does
not identify any costs or burdens associated with Joint Petitioners’ proposal.
In demonstrating that benefits exceed costs, it is incumbent upon Joint Petitioners
to provide evidence that the benefits that they outline will exceed the costs associated
with potential damages. As Dr. Christensen avers, proceeding without such an attempt
to evaluate and compare the costs and benefits associated with the proposed expansion
poses undue risk to Illinois residents and the public at large. (SOIL-SC Ex. 7.0, lines 54-
58) While Joint Petitioners attribute a handful of benefits to their proposal, which will be
discussed further below, Dr. Christensen observes that there has been no serious attempt
to evaluate whether the proposed expansion will produce positive net benefits. (Id., lines
61-63)
In furtherance of the effort to deflect attention from the negative impacts of the
proposal, Dr. Makholm accuses SOIL-SC-WK of wanting the Commission to change its
focus from the transportation of crude oil to the relationship between the oil industry and
climate change. (Dakota Access-ETCO Ex. 6.2, lines 253-259) To the extent that the
Commission focused exclusively on transportation above all else in past common carrier
dockets, SOIL-SC-WK are not asking the Commission to find that it was wrong to do so.
Rather, SOIL-SC-WK are asking the Commission to find that the category of burdens to
weigh against benefits is broader today than it was in the past. The world now recognizes
burdens associated with climate change that were previously largely unrecognized. If
“traditional criteria” for considering public need, as relied upon by Dr. Makholm to justify
disregarding science (Dakota Access-ETCO Ex. 6.2, lines 273-274), is as sacrosanct as
he suggests, those afflicted with COVID-19 would be treated with leeches and exiled to
63
COVID colonies. The Commission is not barred from broadening its public need
considerations and, in fact, the appellate court has found that the Commission has the
discretion to do so. In affirming the Commission’s evaluation of public need in Lakehead
and denial of a Certificate, the court found that the legislatures “failure to provide a
statutory definition of public need at any time strongly suggests that it intended to allow
the Commission to exercise a flexible approach toward these matters.” (296 Ill. App. 3d
942, *954)
Consistent with the Commission’s earlier finding in Docket No. 96-0145 (1997 Ill.
PUC Lexis 255, at *38) that the benefits and burdens to the public are relevant, the
Commission must balance any benefits of Joint Petitioners’ proposal against the
associated burdens. The Commission need not and should not limit itself to the types of
burdens considered in prior dockets.
2. Purported Benefits
When identifying the benefits of their proposal, Joint Petitioners offer vague
references to serving the needs of shippers (Dakota Access-ETCO Ex. 1.5), enhancing
U.S. energy security (Id.), providing additional crude for domestic refineries (Dakota
Access-ETCO Ex. 1.2, lines 159-162), safety and cost advantages over railroad and truck
transportation (Dakota Access-ETCO Ex.1.0, lines 172-177), and royalties, jobs, and a
“general benefit” for the people whose jobs make crude oil exports possible. (Dakota
Access-ETCO Ex. 6.0, lines 259-261). At no point do Joint Petitioners make any attempt
to even generally quantify the claimed benefits or otherwise rank the claimed benefits.14
14 Dr. Makholm offers a per barrel cost comparison of transportation methods, but not does profess to know how much of a benefit is attributable to any sector of the public. (Dakota Access-ETCO Ex. 6.2, Table 1)
64
When asked to identify the beneficiaries of their proposal, in other words, who they
consider to be the public benefitting from nearly doubling the throughput on the pipelines,
Joint Petitioners list first shippers seeking to transport crude oil and processors of crude
oil such as refineries and petrochemical manufacturers. The remainder of their list
consists of the general public as consumers of refined petroleum products and those
located along alternative road and rail routes where crude may pass or those wishing to
use trucks and/or railroads to ship goods. (Dakota Access-ETCO Ex. 1.4, at 2) At no
point do Joint Petitioners describe in any detail how the general public (those not directly
involved in the oil industry) will experience improvements or gains as a result of the
capacity optimization plan.15
The amorphous and illusory benefits cited by Joint Petitioners are insufficient to
demonstrate a need for the capacity optimization plan, particularly when compared to the
burdens associated with Joint Petitioners’ plan. But before addressing the burdens, it is
useful to evaluate the alleged benefits more thoroughly. With regard to serving the needs
of shippers, as discussed earlier, Joint Petitioners’ 2018 open season resulted in only six
shippers seeking transportation service, five of which committed to only a relatively small
portion of the proposed expansion. (Confidential SOIL-SC Cross Ex. 9) As of the time of
the evidentiary hearing, the open season initiated in July 2019 remained open with no
commitments resulting therefrom and no set closing date.16 (Tr. at 392) Moreover, with
15 In making its recommendation in this docket, Staff relied solely on information provided by Joint Petitioners and conducted no independent analysis or investigation and identified no other benefits other than those referenced by Joint Petitioners (Tr. at 773) 16 Incidentally, Joint Petitioners indicated in their November 7, 2019 Response to SOIL-SC’s Motion to Compel that the 2019 open season would close on December 17, 2019. (Response, at 10, footnote 13) Joint Petitioners subsequently extended the open season without explanation. On cross examination, Joint Petitioners’ witness Glenn Emery testified, “There has never been a defined end close date for the open season.” (Tr. at 392) Clearly, either Joint Petitioners’ verified Response or Joint Petitioner’ sworn testimony
65
the previously discussed short-term (through 2023) and incomplete production forecasts
relied upon by Joint Petitioners, it is questionable whether the full capacity expansion will
ever be committed to. Furthermore, the impact of COVID-19 on the oil industry makes
the failure of Joint Petitioners’ current open season all the more likely. Surprisingly, Joint
Petitioners’ primary economics witness claimed at the hearing not to be aware of the
pandemic’s impact on the industry. While he testified that he tracks oil prices on an
ongoing basis (Id., at 504) and is aware of COVID-19 (Id., at 507), Dr. Makholm denies
having read any analysis of potential impacts of the ongoing pandemic on global oil
demand. (Id., at 533)
With regard to Joint Petitioners’ claim that their project will enhance U.S. energy
security and provide additional crude for domestic refineries, it is difficult to see how that
is possible since, as noted above, Joint Petitioners have repeatedly pointed out that they
do not know where the crude they transport ends up and it has been established that
PADD II and PADD III refineries are operating at near 100% capacity (at least under the
level of demand prior to the COVID-19 pandemic). In addition, many domestic refineries
rely on imports of their prefer’red crude grade, not the light sweet crude from the Williston
Basin. (SOIL-SC Ex. 4.0, lines 469-472, lines 676-678) Dr. Makholm’s argument that the
expanded capacity will aid in the transportation of fuel during a national crisis (Dakota
Access-ETCO Ex. 6.2, lines 311-317) fails to validate Joint Petitioners’ claim of benefit
since sufficient transportation capacity from the Willison Basin already exists to satisfy
domestic needs. Moreover, since, as explained above, the goal of Joint Petitioners’
is inaccurate. This and other direct contradictions have caused SOIL-SC-WK to question many of Joint Petitioners’ statements.
66
primary parent appears to be to export the light, sweet Bakken crude overseas, it is not
clear how doing so enhances U.S. energy security.
In terms of safety advantages of pipelines over truck or railroad transportation, it
has never been SOIL-SC-WK’s contention that any particular form of crude oil
transportation is 100% safe or accident free. The important point to consider in the
context of safety is what is actually being measured in the statistics cited by the parties.
Dr. Makholm cites studies to argue that there are fewer spill incidents for pipeline
transportation of crude oil than for rail transportation. (Dakota Access-ETCO Ex. 6.2, lines
222-225) But as SOIL-SC witness David Hughes observes, the Congressional Research
Service (“CRS”) has recognized that “railroads consistently spill less crude oil per ton-
mile transported than other modes of land transportation.” (SOIL-SC Ex. 8.0, lines 78-
81) The CRS reports that rail oil spillage rates are less than one-third that of pipeline per
ton-mile. (Id., at 82-83) The decision for the Commission to make is whether it considers
larger less frequent pipeline releases preferable to smaller more frequent rail releases,
bearing in mind that overall less oil is spilled by railroads. SOIL-SC-WK submit that
regardless of the Commission’s decision on this issue, Joint Petitioners have still failed to
show that any benefits of their proposal outweigh the associated burdens. With regard
to the general per barrel cost of pipeline transportation compared to rail transportation,
Joint Petitioners fail to recognize that the flexibility of the U.S. rail network offers access
to markets not served by pipelines, which SOIL-SC-WK contend offset any general
benefit attributable to Dr. Makholm’s generic cost comparison.17 (Id., at 75-78)
17 Staff witness Brett Seagle references the testimony of Joint Petitioners’ witness Glenn Emery for his statement that transportation of crude oil by railcars and trucks presents safety issues not presented by pipeline transportation. (Staff Ex. 1.0, lines 166-168) Under cross-examination, Mr. Seagle admits that he conducted no analysis or investigation of his own to confirm Mr. Emery’s opinion and simply relied on
67
The last category of benefits offered by Joint Petitioners (royalties, jobs, and a
“general benefit” to people involved in exports) lacks sufficient specificity to know to what
extent such alleged benefits exist. SOIL-SC-WK do not deny that exports of crude oil will
support some jobs and involve the payment of some amount of royalties. (SOIL-SC Ex.
4.0, lines 733-734) But any benefits attributable to such have certainly not been quantified
in any way by any party in this proceeding. Joint Petitioners’ general reliance on an
undefined number of jobs and an unspecified financial gain to the handful receiving
royalties can be accorded little weight as a benefit.
More telling than the nature of the benefits Joint Petitioners identify are the
beneficiaries Joint Petitioners identify when evaluating the public need for the capacity
optimization plan. The members of the public that Joint Petitioners identify as benefiting
from their proposal fall into two groups: (1) the direct beneficiaries consisting of the
shippers and processors of the additional crude oil Joint Petitioners seek to transport, and
(2) members of the general public that use petroleum products and/or use the roads and
rail systems that would otherwise be used to transport the additional crude if Joint
Petitioners’ request is denied. Considering the second group first, there is no evidence
of any measurable benefit to the general public—a point which Joint Petitioners appear
to concede. Notably, when asked whether Illinois citizens will experience any change in
the price of refined petroleum products as a result of the capacity optimization plan, Joint
Petitioners essentially acknowledge that they cannot assure any change in consumer
prices relating to their proposal, since consumer prices are impacted by multiple factors.
common sense to conclude that transporting oil underground must be safer than transporting oil on an interstate. (Tr. at 773) This is consistent with the level of Staff’s review throughout this proceeding. Notably, there is no evidence that Staff conducted any independent analysis of the safety of the pipelines if the capacity optimization plan is implemented.
68
(SOIL-SC Ex. 7.2) SOIL-SC witness Peter Christensen agrees with this assessment. In
the absence of any compelling rationale for why a relatively small expansion in the global
context would affect the price of gasoline or other refined products, he concludes that any
benefits to U.S. consumers in term of price effects will be negligible. (SOIL-SC Ex. 7.0,
lines 91-95)
With regard to the direct beneficiaries in the first group, the record is clear that this
group is limited in number, with the only known members of that group being the six
shippers listed in confidential SOIL-SC Cross Ex. 9. Whether there are in fact any
domestic refiners or processors of the crude oil is unknown since, as previously noted,
Joint Petitioners are steadfast in their denial of knowing where any of the transported
crude ends up. SOIL-SC-WK find it difficult to believe Joint Petitioners’ schedulers and
the operators at ET’s Nederland terminal, the largest above-ground crude oil storage
facility in the U.S., do not have some idea of where the oil they handle is going, even if it
is simply knowing whether the oil will be sent to a crude carrier for export. (SOIL-SC Ex.
4.0, lines 336-342)
There is, however, another group of beneficiaries that Joint Petitioners omit from
their list of beneficiaries of their capacity optimization plan—Joint Petitioners themselves
and their owners. Joint Petitioners’ neglect to mention their own interest in the proposal.
But as Dr. Makholm indicates, the Commission should rest assured that this group is
looking out for its own interests. As mentioned earlier, Dr. Makholm testifies that “private
profitability calculations” underlie pipeline companies’ decisions. (Dakota Access-ETCO
Ex. 1.2, lines 480-482) He even suggests that regulators approve pipeline projects
without any other consideration: “If pipeline companies see, and show, that there are
69
sufficient buyers for their transport services to give reasonable assurance that those new
pipelines will be adequately used, then regulators approve them.” (Id., lines 482-484) On
cross examination Dr. Makholm further suggests that Joint Petitioners’ decision to invest
in the project should be sufficient rebuttal to SOIL-SC witness Hughes’ evaluation of the
need for additional Bakken region take-away capacity. (Tr. at 536)
3. Burdens of Joint Petitioners’ Proposal Having determined that the benefits identified by Joint Petitioners are essentially
limited to themselves and six shippers, it is appropriate to consider the burdens identified
by SOIL-SC-WK (since Joint Petitioners, IBEW, LIUNA, and Staff recognized no burdens
or costs associated with capacity optimization plan). The burdens to address include the
increased risk of releases as well as the deleterious effects of climate change. Because
the technical aspects of Joint Petitioners’ proposal will be addressed in greater detail in a
latter section of this Initial Brief, it is sufficient for purposes of this section to generally
describe the concerns related to releases raised by SOIL-SC witness Richard Kuprewicz.
a. Increased Risk of Releases
As an initial matter, Mr. Kuprewicz noted that the crude oil flow velocity under Joint
Petitioners’ capacity optimization plan will exceed 15 feet/second. While there is no rule
against such an extreme velocity, he expressed significant concern related to the
possibility of surge overpressure. Surge is the change in pressure in liquid pipelines
caused by a major change in flow, such as a pump shutdown/startup or inadvertent
remotely operated mainline valve closure. Mr. Kuprewicz noted that inadvertent remotely
operated mainline valve closure is not an uncommon occurrence on a hazardous liquid
pipeline. Surge pressure increases occur within large diameter liquid hydrocarbon
70
pipelines in microseconds and can move up and down many miles along a pipeline
system at slightly under one mile per second. (SOIL-SC Ex. 2.0, lines 152-161) When
surge overpressure occurs, the result can easily be a rupture of the pipeline. Joint
Petitioners’ surge analysis offered as confidential Dakota Access-ETCO Ex. 7.3, once
finally provided,18 reflects ***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx CONFIDENTIAL*** (Dakota Access-
ETCO Ex. 7.3, at 23, 24, 31, 32, 39, 40, 64, and 70) Mr. Kuprewicz does not consider
such systems failsafe and cautions the Commission against assuming that pipeline
operations will always go as planned. Notably, on March 25, 2020, the U.S. District Court
for the District of Columbia issued an opinion criticizing the U.S. Army Corps of Engineers’
(“USACE”) evaluation of DA’s worst-case discharge on the same pipeline under
consideration in this docket. In that case, the court found that assuming the DA Pipeline
people and systems will function as expected was wrong. (Standing Rock Sioux Tribe v.
U.S. Army Corps of Engineers, No. 16-1534, at 31-32)
Mr. Kuprewicz also raised concerns regarding rupture at a point along the ETCO
Pipeline unrelated to surge. Briefly, when refurbishing the natural gas pipeline south of
Patoka, Illinois to transport crude oil, ETCO replaced a roughly 30-mile segment with new
pipe having a maximum operating pressure (“MOP”) of 1,440 pounds per square inch
gauge (“psig”). At the end of that new segment, the old pipe has a MOP of 900 psig.
(SOIL-SC Ex. 5.0, 231-241) In the event that crude oil leaving the Patoka pump station
18 As with many discovery questions posed by SOIL-SC, Joint Petitioners objected to providing information related to its surge protection efforts and refused to provide meaningful answers. (SOIL-SC Ex. 2.5) Not until after SOIL-SC submitted its written direct testimony identifying safety concerns did Joint Petitioners relent and provide some of the surge related information sought by SOIL-SC, such as that provided in/with Dakota Access-ETCO Ex. 7.0.
71
at a pressure higher than 900 psig does not loose enough pressure by the time it arrives
at the older ETCO pipe segment (having a MOP of 900 psig), SOIL-SC-WK are concerned
that the older pipe will not tolerate the higher pressure and rupture. As reflected in the
confidential surge analysis, there ***CONFIDENTIAL xxxxxxxxxxxxxxx
CONFIDENTIAL*** at the point where the MOP drops from 1,440 psig to 900 psig to
protect against overpressure. (Dakota Access-ETCO Ex. 7.3, at 49, 52, and 57) This risk
of rupture and release poses another burden on the public unaccounted for by Joint
Petitioners.
The threat of catastrophic release is also present where corrosion exists because
it can weaken a pipe, making it more susceptible to surge overpressure. Mr. Kuprewicz
expressed concern about a cluster of corrosion anomalies identified along the ETCO
Pipeline during a 2019 inline inspection (“ILI”). While not an immediate concern, the threat
level could rise in the future if not adequately addressed. (SOIL-SC Ex. 5.0, lines 269-
276) Unfortunately for the public, Joint Petitioners do not plan on evaluating the corrosion
Mr. Kuprewicz references. According to Joint Petitioners, the cluster of corrosion
anomalies Mr. Kuprewicz discusses is not actionable under integrity management
regulations of the U.S. Department of Transportation Pipeline and Hazardous Materials
Safety Administration (“PHMSA”). (Dakota Access-ETCO Ex. 8.2, lines 470-478) As
someone who was involved in the development of PHMSA’s integrity management
regulations (SOIL-SC Ex. 2..0, lines 18-25; SOIL-SC Ex. 2.1) and in light of the
characteristics of the coal tar coating on the subject pipe, Mr. Kuprewicz believes
verification digs are warranted. (SOIL-SC Ex. 5.0, lines 254-284) But according to the
response of Joint Petitioners’ witness John Godfrey to data request SOIL-SC 9.036, Joint
72
Petitioners have not and do not plan to conduct a field verification dig of the corrosion
cluster. (Confidential SOIL-SC Cross Ex. 1; March 6, 2020 Transcript at 363-364) For
the handful of verification digs that did occur following the 2019 ILI, Mr. Godfrey was not
aware of what conditions spurred ETCO to conduct verification digs at those locations
(Id., at 365), so it is not known how those anomalies compare to the corrosion cluster
noted by Mr. Kuprewicz.
Corrosion is also a concern and imposes a risk and burden on the public because
it can lead to smaller leaks that are more difficult to detect. The frequency of such smaller
releases is apparent from examining confidential SOIL-SC Exs. 4.10 and 4.11. SOIL-SC
Ex. 4.10 identifies in response to a Staff data request pipeline leaks or losses of structural
integrity from 2017 through May 2019. SOIL-SC Ex. 4.11 identifies in response to a SOIL
data request pipeline leaks or losses of structural integrity from 2012 through 2014. Note
that the data request in SOIL-SC Ex. 4.11 sought information regarding leaks and losses
of structural integrity from 2010 onward, but Joint Petitioners provided only three years of
information. Excluding losses of structural integrity caused by third parties, the more
recent list in SOIL-SC Ex. 4.10 reflected ***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx CONFIDENTIAL*** The list for the period of
2012 through 2014 in SOIL-SC Ex. 4.11 did not include any losses of structural integrity
due to a third party. That list reflected ***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
73
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx CONFIDENTIAL***
The significance of corrosion leading to pinhole leaks is apparent when one
realizes how much crude oil can escape from a pinhole leak. Such a scenario is all the
more disturbing when one realizes that Joint Petitioners freely acknowledge that their leak
detection system cannot detect pinhole leaks. SOIL-SC Ex 4.13 contains Joint Petitioners
response to data request SOIL-SC 2.023. Joint Petitioners admit that they cannot detect
leaks up to 1% of the transported volume on the pipeline. At a flow rate of 1,100,000 bpd,
in one hour 458 barrels of crude oil can escape undetected. Shockingly, Joint Petitioners
do not recognize this as a concern or risk despite the frequency of pinhole leaks reflected
in SOIL-SC Exs. 4.10 and 4.11. In fact, Joint Petitioners’ witness Todd Stamm
characterizes pinhole leaks as “uncommon.” (SOIL-SC Ex. 4.13) This is yet another
example of Joint Petitioners presenting conflicting information on important issues in this
docket.
While Joint Petitioners may not be concerned about releases, landowner William
Klingele is. Mr. Klingele is an intervenor in this docket who owns 385 acres of farmland
adjacent to the DA Pipeline route in Brown County, Illinois. (Klingele Ex. 1.0, lines 10-12)
He has lived with the risk of a crude oil release on the adjacent land spreading onto his
property since the pipelines became operational. In light of the undisputed increase in
flow velocity, Mr. Klingele is troubled by the greater associated risks and larger spill
volumes that may occur in the event of a release. (Id., lines 104-106, 110-112) He notes
that crude oil releases, even relatively small releases, do not stay confined to the
particular location along a pipeline. This is due to the fact that the spilled oil tends to rise
74
to the surface and contaminate a large area of valuable topsoil. In the context of his own
property and the field drainage system which runs through the DA Pipeline easement, he
is concerned that a release of crude oil will adversely affect, if not disable, the integrated
drainage system on his farmland, thereby inhibiting water drainage on his property. An
October 30, 2019 oil pipeline spill on another pipeline in North Dakota is illustrative of oil
tending to go to the surface. (Klingele Ex. 2.0, lines 131-135) The impacted area,
depicted below, was reported as 1,500 long and 15 feet wide. (Klingele Ex. 2.1, at 1)
(Klingele Ex. 2.1, at 1)
Mr. Klingele is not comfortable with the increased burden Joint Petitioners’ proposal
subject him and his property too, particularly in light of the insufficient demonstration of
need and public benefit made by Joint Petitioners.
b. Exacerbation of Climate Change The burden and risk associated with Joint Petitioners’ capacity optimization plan,
however, are not limited to releases of crude oil directly jeopardizing lives and property.
A decision by the Commission to allow Joint Petitioners to implement their proposal and
75
pump up to 1,100,000 bpd will also expose Illinois, as well as the nation and world, to
greater harm from the effects of climate change. The phenomenon of climate change is
generally recognized by science, as are its causes and impacts on the Earth. To be clear,
the negative impacts of climate change are not just a matter of more severe weather. For
example, Moody’s Investors Service recognizes that local government debt, particularly
in Illinois, will be adversely affected as heat stress becomes a greater issue facing local
governments. (See SOIL-SC Ex. 1.2)
Interestingly, Joint Petitioners do not acknowledge environmental degradation as
a cost associated with facilitating the consumption of nearly twice the amount of crude oil.
Moreover, they also turn a blind eye to the effects that the transition away from fossil fuels
may have on their plans. SOIL requested information from Joint Petitioners on how their
operations impact climate change and how climate change may impact their operations.
Joint Petitioners refused to answer and in their supplemental response to data request
SOIL 1.099 characterized the term “climate change” as “undefined, vague, and
ambiguous.” They further claimed that “there is no reason to believe that transportation
of crude oil will have any impacts on climate change.” Oddly, it is not clear how they know
that the transportation of crude oil will have no impacts on the climate if in the same
response they claim to not know what “climate change” means.19 In related data requests
SOIL 1.102 and 1.103, Joint Petitioners object to being asked how they factored into their
analysis for shipping capacity the possible curtailment of crude oil usage due to a carbon
tax and other government or regulatory disincentives for fossil fuel use. They do admit,
however, that they “did not explicitly take into account any potential reduction in petroleum
19 This is another example of Joint Petitioners’ self-serving inconsistent statements that cast into doubt their other claims in this proceeding.
76
usage due to ‘government and other actions.’” These data requests have been admitted
into the record as SOIL-SC Exhibit 1.3. As discussed above in the context of production
forecasts, Joint Petitioners’ witness Laura Olive also acknowledges that she did not
perform an analysis of how efforts to mitigate climate change may impact demand for
fossil fuels. (SOIL-SC Cross Ex. 14, at 1) During cross examination, it also became
painfully obvious that Joint Petitioners’ witness Glenn Emery did not want to admit that
the efforts Illinois has taken to move away from carbon-based energy sources is aimed
at mitigating the effects of climate change.20 (See March 6, 2020 Transcript at 429-432)
To put the potential emissions at stake in context, renowned climate scientist and
former Director of the Goddard Institute for Space Studies of the National Aeronautics
and Space Administration (“NASA”), James Hansen, calculates that the additional crude
at issue, once burned as intended, will emit ~ 97 mmt CO2-eq/year. This is roughly equal
to the emissions from fifteen 1,000-megawatt coal plants or 20 million cars. (SOIL-SC Ex.
3.0, lines 321-324) Using Dr. Hansen’s calculation and a well-established central
estimate for the social cost of carbon of $41.50 per ton, Dr. Christensen calculates that
$4.03 billion in annual damages would result worldwide from full implementation of Joint
Petitioners’ capacity optimization plan.21 Such damages include impacts to agricultural
yields, direct human health impacts, infrastructure and mortality impacts from sea level
rise and increasingly frequent storms, etc. (SOIL-SC Ex. 7.0, lines 177-183)
20 Staff witness Brett Seagle acknowledges that pollution “could possibly be” an externality associated with pipelines (Tr. at 776), but there is no evidence in the record that Staff gave any consideration to the negative impacts of pollution or climate change on the public. 21 Joint Petitioners’ witness David Harrison offers a social cost of carbon at the U.S. national level of $6.23 per ton and at the Illinois level of $0.27 per ton. (Dakota Access-ETCO Ex. 9.2, lines 691-693, 705-706) This results in annual damages of $604,310,000 to the United States and $26,190,000 to Illinois from the consumption of the crude Joint Petitioners seek to bring to market.
77
Joint Petitioners’ witness David Harrison criticizes both Dr. Hansen’s calculation
and Dr. Christensen’s calculation. He argues that denial of the Joint Petition will not mean
that the crude that would otherwise be transported by Joint Petitioners will not be
transported by another and consumed. He points out (contrary to Joint Petitioners’
argument that additional capacity is needed) that there is enough capacity in the existing
railroad and pipeline systems to transport the additional crude oil from the Williston Basin.
(Dakota Access-ETCO Ex. 9.0, lines 194-202) With regard to Dr. Christensen, Dr.
Harrison complains that Dr. Christensen’s source for the social cost of carbon is too
technical (Dakota Access-ETCO Ex. 9.2, lines 579-583) and contains too many
uncertainties to be relied upon. (Id., lines 718-721) Noticeably absent from Dr. Harrison’s
testimony, or from the testimony of any of Joint Petitioners’ witnesses, is an alternative
emission’s calculation or any attempt to value the negative consequences of those
emissions. This absence is significant because when SOIL asked Joint Petitioners earlier
in this proceeding how much additional carbon dioxide and other greenhouse gases
would be emitted by the additional crude oil at issue, Joint Petitioners stated that they
“have not made the requested calculations and object to being required to perform the
calculations specified by SOIL.” (Dakota Access-ETCO Ex. 1.3, at 1) Joint Petitioners
should not be able to object to a request that they calculate emissions and also object
when someone else performs the calculations they refuse to. Had Joint Petitioners
desired to present their own calculations, they were free to do so.
Dr. Harrison also criticizes SOIL-SC-WK’s concern with the climate impact of Joint
Petitioners’ proposal on the basis that there are better ways to mitigate climate change
then by denying pipeline projects. (Dakota Access-ETCO Ex. 9.0, lines 106-123) He
78
prefers market based environmental policies and characterizes the denial of the Joint
Petition as an ad hoc means of addressing climate change. (Dakota Access-ETCO Ex.
9.2, lines 184-186) Dr. Harrison’s position, however, does not comport with reality or
recognize the seriousness of the climate situation.
To be clear, SOIL-SC-WK’s primary position in this regard is that Joint Petitioners
have not adequately demonstrated that there will be sufficient crude available to
implement the proposed capacity optimization plan. If despite the realities of the
economically available crude in the Bakken region and competing transportation options,
enough crude does exist to fully implement Joint Petitioners’ proposal, SOIL-SC-WK
acknowledge that the granting of the Joint Petition would not definitively result in the
emitting of an additional 97 mmt CO2-eq/year. Moreover, SOIL-SC-WK are not arguing
that the social cost of implementing the capacity optimization plan will definitely total $4.03
billion annually. As Dr. Hansen explains, the actual impact on global emissions ultimately
stemming from the Commission’s decision in this docket would be a function, at least in
part, of induced price changes, demand changes, supply adjustments, and offsetting
effects. (SOIL-SC Ex. 6.0, lines 45-47) Dr. Hansen avers that if the Joint Petition is
granted, global emissions will increase by some amount over and above what they would
be otherwise, and if the Joint Petition is denied, a reduction in overall emissions will occur.
(Id., lines 49-52) Even Dr. Harrison agreed under cross-examination that in the kind of
situation at hand, an increase in take-away capacity could lead to higher production. (Tr.
at 637-638)
Furthermore, uncertainty in estimates has been rejected by the U.S. Supreme
Court as a reason for an agency avoiding statutory responsibility. In Massachusetts v.
79
EPA, 549 U.S. 497, 127 S. Ct. 1438 (2007), the U.S. Supreme Court considered the
Environmental Protection Agency’s refusal to regulate greenhouse gas emissions from
new motor vehicles, in part because of the uncertainty surrounding climate change. The
Court disagreed with the agency and found, “Nor can EPA avoid its statutory obligation
by noting the uncertainty surrounding various features of climate change and concluding
that it would therefore be better not to regulate at this time.” (Id., at 534) Thus, to the
extent that uncertainty exists in the social cost of carbon resources relied upon by Dr.
Christensen, it does not negate the Commission’s ability to consider or rely on Dr.
Christensen’s testimony.
If the Joint Petition is approved, the exact extent of the emissions increase will
depend on the circumstances present when the capacity optimization is implemented.
To the extent of the increase in emissions upon granting the Joint Petition, the
Commission must weigh the effect of the worsened climate against the purported public
benefits referenced by Joint Petitioners and bear in mind overall that any increase in
emissions is unquestionably a step in the wrong direction in addressing the pending
climate disaster.
With regard to Dr. Harrison’s preference for market-based approaches to mitigate
climate change, SOIL-SC-WK have never asserted that denial of projects like Joint
Petitioners’ is the best way to address climate change. Rather, it is the absence of
alternatives that warrants the Commission’s consideration of and action on climate
change when deciding this matter. In other words, given the urgent nature of the climate
crises, a preference for an unavailable solution must not deter the Commission from
taking action when and how it can to mitigate the harm caused by climate change. Nor
80
should the Commission be misled by another example of Joint Petitioners’ inconsistent
statements on this matter. While Dr. Harrison testifies at one point that “effective and
cost-effective policies are available to reduce [greenhouse gas] emissions” (Dakota
Access-ETCO Ex. 9.0, line 420), he later acknowledges that none of his preferred market-
based approaches exist in Illinois or at the national level. (Tr. at 632) In light of the fact
that no market-based approach applies to Illinois, if the Commission agrees that carbon
dioxide emissions must be minimized without further delay, it is obvious that the
Commission has the responsibility to curb carbon emissions through its authority over
cases such as the pending proceeding.
Assuming the Commission accepts the science of climate change and concurs
with former NASA administrator Dr. Hansen that approval of Joint Petitioners’ proposal
will result in some increase in carbon dioxide emissions, it is appropriate to discuss the
impacts of climate change so that the burdens of facilitating greater crude oil consumption
can be evaluated. Dr. Hansen had studied climate change for decades. In recent years,
he has attempted to draw attention to the danger of passing climate tipping points --
irreversible climate impacts that could yield a different planet from the one on which
civilization developed. He avers that it is critical for regulators and policy makers at all
levels to dispute the presumption of fossil fuel interests that all fossil fuels ought to be
burned, with their combustion products discharged into the atmosphere. (SOIL-SC Ex.
3.0, lines 64-69) It is now clear, as the relevant scientific community has established for
some time, that high carbon dioxide emissions from fossil fuel burning have already
disrupted Earth’s climate system and that, unless we fundamentally alter business as
81
usual, the accumulation of atmospheric carbon dioxide will impose profound and
mounting risks of ecological, economic, and social collapse. (Id., lines 76-80)
Dr. Hansen incorporates into his testimony as SOIL-SC Ex. 3.3 a copy of Ice Melt,
Sea Level Rise and Superstorms: Evidence from Paleoclimate Data, Climate Modeling,
and Modern Observations that 2°C Global Warming is Highly Dangerous. This work was
published by Dr. Hansen in 2015 in conjunction with 16 colleagues and discusses multi-
meter sea level rise. Dr. Hansen and his fellow authors conclude that if carbon dioxide
emissions are allowed such that energy is continuously pumped at a high rate into the
ocean, then multi-meter sea level rise will become practically unavoidable, with
consequences that may threaten the very fabric of civilization. Thereafter, in 2017, Dr.
Hansen and 16 colleagues published Young People’s Burden: Requirement of Negative
CO2 Emissions, Earth Syst. Dynam. In Young People’s Burden, the authors establish
that restoring and securing a viable climate system on which our children and their
progeny necessarily depend now requires not only the phasing out of emissions—
including abandoning new major fossil fuel investment of which the Joint Petitioners’
proposal is a prime instance -- but also “negative emissions,” i.e., extraction of carbon
dioxide from the air. Young People’s Burden is included in the record as SOIL-SC Ex.
3.4.
Dr. Hansen concludes from his work that the present atmospheric carbon dioxide
level is already in the dangerous zone. Unless action is taken without delay, he testifies
that the consequences of climate change will become unbearable. (SOIL-SC Ex. 3.0,
lines 113-137) In the context of sea level rise, Dr. Hansen points out that ice mass losses
from Greenland, West Antarctica, and parts of East Antarctica are growing nonlinearly,
82
with doubling times so far this century of approximately 10 years. (Id., lines 142-144)
This prospect alone, he asserts, cries out for urgent national and international action to
constrain carbon pollution, considering that complete disintegration of the Totten glacier
in East Antarctica could raise sea levels by approximately 19-23 feet; that ice fronted by
the Cook glacier in East Antarctica could add 9-13 feet of sea rise; and that West Antarctic
ice fronted by Amundsen Sea glaciers have the potential to raise sea level an additional
9-13 feet. Much of the U.S. eastern seaboard, as well as low-lying areas of Europe, the
Indian sub-continent, and the Far East, would then be submerged. That order of sea level
rise would result in the loss of hundreds of historical coastal cities worldwide, with
incalculable economic consequences. It would also create hundreds of millions of global
warming refugees from highly populated low-lying areas, and thus likely cause or
exacerbate major international conflicts. The United States Department of Defense
identifies climate change as a threat to national security. (Id., lines 148-161)
For the impacts of climate change closer to home, Dr. Hansen references the
National Oceanic and Atmospheric Administration (“NOAA”) publication NOAA National
Centers For Environmental Information: State Climate Summaries. The Illinois summary,
which is available in SOIL-SC Exhibit 3.5, importantly denotes that continued climate
warming in the region is projected to yield substantially increased spring precipitation
rates in Illinois – far more than for the nation as a whole – particularly for the northern
two-thirds of the state. In addition, the NOAA review points out that “historically
unprecedented warming is projected during the 21st century,” though “less warming is
expected under a lower emissions future (the coldest years being about as warm as the
hottest year in the historical record …) and more warming under a higher emissions future
83
(the hottest years being about 10°F warmer than the hottest year in the historical record
…).” The NOAA study does not, however, consider the impact of in-migration to Illinois
of refugees from coastal regions submerged by the rising seas or other regions torn by
climate-linked strife. (Id., lines 166-181)
Dr. Hansen also speaks to ocean warming, acidification of the oceans, freshwater
insecurity, species extinction, and the expectation of increased global burdens from
infectious disease and premature death associated with climate change. (SOIL-SC Ex.
3.0, lines 201-202, 205-206, 214-219, 231-240) With specific regard to human health, he
relates that the availability of food, clean air, and clean water will lessen with climate
change, which will lead to increased malnutrition and consequent disorders, including
those related to child growth and development. Increased death, illness, and injuries
associated with chronic obstructive pulmonary disease, asthma, other respiratory
distress, heat waves, and storms will increase. (Id., lines 223-230) As extreme heat
events have become more common with climate change, he relays that their frequency
will increase further if fossil fuel emissions continue to be permitted, so that global
warming becomes locked in and rendered increasingly severe. (Id., lines 208-211)
While Dr. Hansen acknowledges the possibility that the Commission could approve
the proposed capacity expansion and decisions by other more progressive, responsible
authorities could offset the climate degradation fostered by the Commission, he doubts
that would be the outcome. More likely, the wrong decision may well work to demoralize
other authorities. (SOIL-SC Ex. 3.0, lines 312-315) The question for the Commission to
consider is whether it will pave the way for this intended expansion and continue with the
business as usual approach that led us to this climate crisis or whether the Commission,
84
by making the right choice, will exercise leadership that other authorities can emulate. If
it takes the latter path, the Commission’s decision and the decisions of those who emulate
the Commission’s leadership will function to mitigate the burdens and costs of climate
change from which Joint Petitioners seek to profit.
Since the Commission previously considered and granted in 2015 Joint Petitioners’
request to transport up to 570,000 bpd of crude oil, Illinois has taken several steps to
move away from fossil fuels. In 2016, Illinois adopted the Future Energy Jobs Act
(“FEJA”), Public Act 99-0906. In 2019, the Illinois legislature considered the Clean
Energy Jobs Act (“CEJA”) in Senate Bill 2132 and House Bill 3624. Both FEJA and the
proposed CEJA are evidence of the societal transition from fossil fuels to cleaner forms
of energy. Clearly, fossil fuels are losing their social license. If CEJA or similar legislation
is enacted, expansion of the capacity of Joint Petitioners’ pipelines will make achievement
of CEJA’s goals substantially more difficult and expensive for Illinois. The enactment of
Public Act 101-373 in 2019 enabled Illinois to create restrictions on greenhouse gas
emissions and address climate change. This too is evidence of society recognizing the
threat of climate change and, in particular, an example of Illinois recognizing that threat.
(SOIL-SC Ex. 1.0, lines 76-87) In addition, Executive Order 2019-6 sets forth clear
statements regarding climate change in relation to Illinois and provides direction for the
Commission’s consideration. Executive Order 2019-6, included in the record as SOIL-
SC Ex. 4.17, states in part:
… all residents of the State of Illinois deserve clean air, clean water, and a safe environment where their communities can thrive; and … the overwhelming consensus of scientists is clear: climate change is real, and must be addressed by public officials; and
85
… Illinois is home to forests, farms, prairies, rivers, lakes, and wetlands, and Lake Michigan, and these abundant natural resources must be protected and preserved for future generations; and … Illinoisans are experiencing the damaging effects of climate change, including increased temperatures, soil erosion, and pollution, which cause harm to the environment, economy and residents’ health; and … the State of Illinois acknowledges that it must take action immediately in order to prevent further impacts of climate change; … The State of Illinois shall commit to the principles of the Paris Climate Agreement. (emphasis added) The fact that Illinoisans favor policymakers taking action to address climate change
is apparent from an independent survey by the Center for State Policy and Leadership,
the Institute for Legal, Legislative, and Policy Studies, and the Survey Research Office at
the University of Illinois Springfield conducted in September of 2019. The survey
methodology, sample demographic data, and results are included in the record as SOIL-
SC Ex. 4.18. Among the multiple topics covered in the survey was the question, “How
much priority, if any, do you think dealing with global climate change should be given by
policymakers?” Of the 1,012 registered Illinois voters that participated in the survey, 44%
responded that dealing with global climate change should be given “top priority,” while
41% indicated that it should be given “some priority.” With an overwhelming majority of
respondents (85%) saying dealing with climate change should be given priority, it is clear
that public concern warrants the Commission’s consideration of climate change as it
determines whether to facilitate further climate degradation.
c. Takings Consideration In the 2015 Orders in Docket Nos. 14-0754 and 14-0755, the Commission granted
Joint Petitioners authority under Section 8-509 of the PUA to take private property by
eminent domain. (Docket No. 14-0754 Order at 52; Docket No. 14-0755 Order at 24) In
86
doing so, the Commission presumably considered the risk and burden of the project on
landowners, weighing the imposition associated with the proposal against the finding in
the dockets that the project was in the public interest. To be clear, the proposal at issue
in those dockets concerned transportation of up to 570,000 bpd of crude oil. In this
docket, as discussed elsewhere in this Initial Brief, the proposal to transport up to
1,100,000 bpd of crude oil at a higher velocity exposes property and landowners to
greater risk of releases and ruptures. In other words, the Commission granted
condemnation authority under one set of considerations that will change if Joint
Petitioners’ capacity optimization plan is implemented. Unfortunately for landowners,
Joint Petitioners already have the easements they want and it is not even known how
many landowners are aware of the greater risk they will be exposed to under the capacity
optimization plan.
SOIL-SC-WK acknowledge that there is no request for authority under 8-509
before the Commission in this docket. Nevertheless, the Commission should be
cognizant of how a decision approving the Joint Petition will impose a greater burden on
landowner’s property rights, effectively authorizing a second taking without additional
compensation.
4. Public versus Private
Alluded to earlier during the discussion of the benefits and costs of Joint
Petitioners’ proposal is the question of whether the alleged need is that of the public or of
a few individuals. In the past the Commission has recognized that “[w]hatever basis a
petitioner chooses for demonstrating a public need, the need must be for the public, not
for the few. And the Commission must weigh the evidence presented by the petitioner
87
that there exists a public need against the evidence other parties presented that no such
public need exists.” (Docket No 96-0145, 1997 Ill. PUC LEXIS 255, *35-36) The quoted
language comes from the Commission’s aforementioned Lakehead decision, wherein the
Commission rejected the ALJ’s recommendation to grant Lakehead its requested relief
and instead supported the extensive analysis of Staff concluding that Lakehead had not
met its burden. The Order denying Lakehead’s petition stated:
The Commission agrees with Staff that the public need, like the public convenience and necessity, "required to support an order of the Commission is that of the public and not of any individual or number of individuals". Roy v. Ill. Commerce Commission, 322 Ill. 452, 458 (1926). The public, as indicated by the court, is greater than a limited number of market players. While it may be in Lakehead's own best interest that the proposed pipeline be built, that does not establish a public need. (1997 Ill. PUC LEXIS 255, *34)
The Commission noted as well that “the general concept of analyzing the appropriate
market and other providers in that market, and not just the pipeline itself, should be a
guiding principle in determining public need.” (1997 Ill. PUC LEXIS 255, 34)
In discussing Lakehead’s showing of benefits, which is remarkably similar to Joint
Petitioners’ showing of benefits in the docket at hand, the Commission concluded:
We agree with Staff's analysis, in this case, that public need is based upon the demand for refined petroleum products and not only crude oil per se. Lakehead was unable to show positive price effects on the market for petroleum products, nor future public demand that would indicate the need for this proposed pipeline. (1997 Ill. PUC LEXIS 255, *37-38)
In the present docket, although Staff conducted no analysis, SOIL-SC-WK evaluated Joint
Petitioners’ claims of need and found them grossly wanting. Other than general
references to the public using petroleum products (see, for example, Dakota Access-
ETCO Ex. 4.0, lines 91-96), Joint Petitioners have failed to show any positive price effects
88
on the market for petroleum products. In fact, as reflected in SOIL-SC Ex. 7.2, Joint
Petitioners deny that implementation of their capacity optimization plan will have any
impact on prices the public pays for petroleum products. With regard to “future public
demand,” Joint Petitioners second expansion open season has essentially failed (Tr. at
392), SOIL-SC witness David Hughes explains why Bakken crude is unlikely to be
available to ship anyway (SOIL-SC Ex. 8.0, lines 99-106), and Joint Petitioners offer
nothing more than general expectations that refineries will increase capacity in the future
because they have in the past. (Dakota Access-ETCO Ex. 5.2, lines 46-49)
In language which is also prescient of the current situation, the Commission
discussed the handful of customers Lakehead intended to serve under its proposal. By
simply changing the reference to “Lakehead” to “Joint Petitioners” and number of
customers from three to six, the following language from the Commission’s Lakehead
Order could be used in an order in this proceeding:
The Commission has carefully reviewed the record in this case and has determined that Lakehead has not shown a public need for this proposed pipeline. The Commission is charged with protecting the interests of the public and must always weigh the interests of private companies with the public's interest. In this case a private company has asked the Commission to determine that its needs and the needs of three of its customers constitute a public need. It is difficult to reconcile that definition of public with the court's statement that "the convenience and necessity required to support an order of the commission is that of the public and not of any individual or number of individuals." Roy v. Ill. Commerce Commission, 322 Ill. 452, 458 (1926). We believe that the public is not and cannot be defined as a limited number of private interests. If we were to accept this definition, the role of the Commission under Article 15 would be merely to recognize that a private interest is fit, willing and able to build a pipeline and its customers want the product of that pipeline. This would require virtually no judgment on the part of the Commission and would relinquish the Commission's prudent control over the pipelines that wish to enter this state. (1997 Ill. PUC LEXIS 255, *55-56)
89
This language succinctly describes the Commission’s obligations and provides a
roadmap for evaluating the public need for Joint Petitioners’ proposal in this docket.
Amazingly, the similarities and applicability of the Commission’s analysis in
Lakehead continue. Mr. Hughes explains that existing take-away capacity from the
Bakken region exceeds the additional throughput Joint Petitioners claim is needed to
serve the public. (SOIL-SC Ex. 8.0, lines 66-76) The Commission considered the
availability of other transportation options in Lakehead as well and concluded that the
failure to consider other options was another shortcoming in the company’s arguments.
Again, by simply replacing “Lakehead” with “Joint Petitioners,” much of the following
language could be used in an order in this docket denying the Joint Petition:
We also cannot accept the argument that Lakehead's system is the only relevant system to address in determining public need. The Company did not do an analysis, economic or engineering, of the relevant supply sources of the market. The Company simply stated that demand is growing and it wanted to supply that demand. The Company failed to show any evidence that relevant supply sources (not just Lakehead's system) could not meet current and foreseeable future demand in this region. There is no evidence that future demand in the region dictates the necessity of a new pipeline other than speculative statements from the Company. Staff even attempted to do this analysis, in a more rigorous manner, and could not support the contention that a new pipeline was needed in this market to meet any alleged future capacity shortfalls. In fact, Lakehead's own witnesses from the refiners could not identify any sort of current or future capacity shortfall on any system except Lakehead's. Knowing this, one may ask why a company would invest such a sum of money to put in a pipeline. One possible explanation is the conquest of market share. While obtaining market share may be beneficial to the Company, it is not a public need, it is a private goal. (1997 Ill. PUC LEXIS 255, *56-57)
Like Lakehead, Joint Petitioners have simply stated their belief that demand is growing
and they want to supply that demand (Dakota Access-ETCO Ex. 1.0, lines 110-116), but
they have provided no analysis that current transportation options could not meet the
90
demand. Likewise, Staff has not offered any such analysis. Mr. Hughes is the only
witness who investigated whether current capacity is sufficient to meet future demand for
crude oil transportation. The conquest of market share, while beneficial to Joint
Petitioners, is not a public need, it is a private goal.
Not liking to be told “no” by the Commission, Lakehead appealed the
Commission’s Order in Docket No. 96-0145. The appellate court affirmed the
Commission in every respect. (Lakehead Pipeline Co., Ltd. Pshp. v. Ill. Commerce
Comm'n, 296 Ill. App. 3d 942 (1998)) (“Lakehead Pipeline”) With regard to who to
consider in determining public need, the appellate court stated:
For direction in determining what group should be considered when investigating public need, the Commission turned to the Supreme Court's decision in Roy v. Illinois Commerce Comm'n, 322 Ill. 452, 153 N.E. 648 (1926). In the context of discussing public necessity and convenience, the Roy court stated that the "convenience and necessity required to support an order of the commission is that of the public and not any individuals or number of individuals." Roy, 322 Ill. at 458, 153 N.E. at 648. The Commission adopted this same approach in this case, determining that the public is larger than a limited number of market players and the need of a few refiners does not in and of itself establish a public need. A public need, in the Commission's opinion, cannot be defined as involving only a limited number of private interests.
We can find no fault with this reasoning which takes into account the public as a whole. (Lakehead Pipeline, 296 Ill. App. 3d at 954-55)
The appellate court went on to state:
In the context of public need, it is appropriate to look at the larger group of the general public to see if it requires the service, not whether some components of the public are in fact using the service. Only by looking to the public at large can one determine whether there is an actual existing or expected popular need for the proposed service which should not be denied. This broader understanding of public has been consistently employed by our courts. Thompson v. Illinois Commerce Comm'n, 1 Ill. 2d 350, 115 N.E.2d 622 (1953); Illinois Highway Transportation Co. v. Illinois Commerce Comm'n, 404 Ill. 610, 90 N.E.2d 86 (1950); Illinois Central R.R. Co. v. Illinois Commerce Comm'n, 395 Ill. 303, 70 N.E.2d 64 (1946);
91
Chicago Rys. Co. v. Commerce Comm'n, 336 Ill. 51, 167 N.E. 840 (1929); West Suburban Transportation Co. v. Chicago and West Towns Ry. Co., 309 Ill. 87, 140 N.E. 56 (1923). (Lakehead Pipeline, 296 Ill. App. 3d 942, 955)
Clearly the Commission should consider in this docket who would actually benefit from
Joint Petitioners’ proposed capacity optimization plan. With only six shippers offering to
use a portion of the additional capacity Joint Petitioners seek to implement (and no
prospect for that number growing) and enough existing take-away capacity in the Bakken
region to transport substantially more crude than Joint Petitioners seek to transport, it is
easy for the Commission to conclude that the benefits of this proposal will go to a few
private companies, Joint Petitioners, and Joint Petitioners’ parents.
If any doubt remains as to the need for the proposed capacity expansion, Joint
Petitioners’ witness Makholm provided clarification under cross-examination. When
asked whether shippers “need” to ship crude oil from North Dakota to Texas, he corrected
counsel as follows:
[Counsel for SOIL-SC] So when--so when you look at the shipper's need-- [Dr. Makholm] Shipper's desire. [Counsel for SOIL-SC] --shipper's desires, you know, to ship oil from Williston Basin to markets, …. (Tr. at 515)
Joint Petitioners’ own witness recognizes that shippers do not “need” to use Joint
Petitioners’ pipelines, they “desire” to do so.
5. A Net Burden on the Public An objective evaluation of the alleged benefits and demonstrable burdens to the
public produces an outcome that clearly weights against the granting of the Joint Petition.
The limited number of beneficiaries (six shippers and Joint Petitioners and their parent
companies) seek profit for themselves while the externalized costs are borne by the public
92
at large, which by Joint Petitioners’ admission will see no measurable benefit. Such
private gain at the expense of the public conflicts with both the Commission’s and the
appellate court’s conclusions related to Lakehead.
H. Conclusion on Public Need The entire premise of Joint Petitioners’ claim of public need is that six shippers
accepted Joint Petitioners’ offer to transport crude oil. They provided no evidence of a
lack of transportation capacity in the market (other than their own). They provided no
evidence of any discernible benefit to any Illinoisans, let alone any American, other than
six shippers and themselves, and in fact appear to be focusing their efforts on serving
foreign needs for crude oil. The production forecasts relined upon by Joint Petitioners
are glaringly limited and incomplete. They ignore their own admitted inability to detect
leaks and resent any questioning of their safety measures related to surge overpressure.
Joint Petitioners refuse to acknowledge any cost or burden to the public. While the list
could continue, it is clear from these facts alone that Joint Petitioners have failed to meet
their burden of demonstrating public need. Joint Petitioners’ arguments, as well as Staff’s
support for the Joint Petition, conflict with years of past Commission orders and caselaw.
The only legally sustainable outcome is to conclude that Joint Petitioners have not
demonstrated a public need for the capacity optimization plan.
V. DESIGN, ENGINEERING, AND OPERATIONS A facility would not be necessary under Section 8-503 if it was unreliable or unsafe.
Similarly, under Section 15-401, an unreliable or unsafe facility or service would not be
needed by the public or required by the public convenience and necessity, and an
93
applicant would not be deemed fit and able to provide a service that was unreliable or
unsafe.
In their direct testimony, Joint Petitioners’ witnesses Frey and Stamm described
some of the design, engineering, operational, and safety aspects of the pipelines with the
addition of the proposed pumping facilities and increased throughput. (Dakota Access–
ETCO Ex. 2.0 (Frey) and Ex. 3.0 (Stamm)) Nothing in the record shows that when Joint
Petitioners designed and built the pipelines, and integrated the newly built portion of the
ETCO pipeline with the older natural gas pipeline, they contemplated any greater oil
throughput volume than 570,000 bpd. To reiterate, nothing in Docket Nos. 14-0754, 14-
0755, or 19-0673 indicates that the pipelines were designed with a near doubling of the
planned capacity in mind.
As Mr. Stamm described, the pipelines are and will continue to be monitored and
controlled remotely from a Control Center Console located in Houston, Texas. Mr. Stamm
stated further that operating and maintenance personnel will be stationed at or near the
proposed new pumping stations in Hancock County and Massac County, Illinois, and that
personnel are stationed at or near the Patoka, Illinois terminal. (Dakota Access-ETCO
Ex. 3.0, lines 64-79)
Mr. Stamm next described how he believes Joint Petitioners will be able to
transport greater crude oil volumes “within the specifications of the original as-built
design.” He represented that existing MOP will remain unchanged while using existing
operating controls, operating the existing pumping capacity, using drag reducing agent
(“DRA”) (to reduce friction loss), and adding and operating the additional pumping
capacity, both in Illinois and other states. Together, according to Joint Petitioners, these
94
items would support an increase in daily throughput from 570,000 bpd to 1,100,000 bpd.
(Dakota Access-ETCO Ex. 3.0, lines 80-99)
Staff witness Brett Seagle stated in his direct testimony that he reviewed the Joint
Petition, exhibits, Joint Petitioners’ direct testimony, and discovery responses. Based on
that review, Mr. Seagle concluded he saw no reason to oppose Joint Petitioners’ request.
(Staff Ex. 1.0, lines 41-50) He noted in support that, in response to a data request, Joint
Petitioners said that they performed hydraulic modeling to determine the optimum
pumping capacity, which he stated enabled them to avoid locating the pumping stations
in high consequence areas and environmentally or culturally sensitive areas. (Id., lines
174-178)
SOIL-SC presented the testimony of Richard Kuprewicz, the President of
Accufacts Inc., for the purpose of reviewing potential adverse effects of increasing the
crude oil flow capacity resulting from the addition of pumping stations and equipment and
introducing a DRA on the DA Pipeline and ETCO Pipeline within the state of Illinois. As
Mr. Kuprewicz stated, “Accufacts provides pipeline safety expertise in gas and liquid
pipeline investigation, auditing, risk management, siting, construction, design, operation,
maintenance, training, Supervisory Control and Data Acquisition, leak detection,
management review, emergency response, and regulatory development and
compliance.” (SOIL-SC Ex. 2.0, lines 7-11) Mr. Kuprewicz provides “independent
consulting services and expert advice on pipeline matters.” (Id., lines 312-13) He has
experience in helping develop PHMSA’s federal regulations for liquid and gas
transmission integrity management, as well as safety regulations for distribution pipelines.
With over 46 years of experience, Mr. Kuprewicz understands state and federal pipeline
95
safety regulation. He has been involved in many pipeline failure investigations. (Id. lines
18-35) Mr. Kuprewicz is experienced in providing pipeline-related expert testimony in
proceedings before regulatory bodies. (Id., line 46-65) Mr. Kuprewicz’ substantial
experience and credentials are directly relevant to Joint Petitioners’ proposed pipeline
modifications and uniquely qualify him to review and critique the proposed capacity
expansion project.
SOIL-SC-WK summarized portions of Mr. Kuprewicz’ testimony in Section
IV.G.3.a. of this Initial Brief (discussing the increased risk of releases as a burden of the
Joint Petitioners’ proposal). Some of the content of that section of the Initial Brief will
appear again this section, but given the importance of the subject of his testimony,
reiterating the evidence he presented is appropriate. SOIL-SC-WK will focus here on
those portions of Mr. Kuprewicz’ testimony that they deem to be most important.
A. Surge Overpressure After reviewing Joint Petitioners’ direct testimony and related information
pertaining to their proposal to increase their pipeline capacity to 1,100,000 bpd, Mr.
Kuprewicz expressed his major areas of concern. (Id., lines 94-108) Included in his list
of concerns were (i) not having been provided (despite being requested in discovery) a
pipeline system map showing approximate locations of pump stations and mainline
valves, and (ii) the high potential for surge over-pressures exceeding 110% of MOP at
what he termed the extremely high actual flow velocities resulting from the increased
capacity. (Id.) Mr. Kuprewicz calculated that the liquid flow velocity will exceed 15
feet/second, which he stated is extreme for crude oil pipelines, and which significantly
increases the risk of surge pressure increases. (Id., lines 150-155) He explained that
96
surge “is the change in pressure in liquid pipelines caused by a major change in flow,
such as a pump shutdown/startup or inadvertent remotely operated mainline valve
closure (a not uncommon occurrence on a hazardous liquid transmission pipeline). Surge
pressure increases occur within large diameter liquid hydrocarbon pipelines in
microseconds and can move up and down many miles along a pipeline system at slightly
under one mile per second.” (Id., lines 155-161)
Mr. Kuprewicz also expressed concerns about the DRA included in Joint
Petitioners’ plans, based on his considerable operational experience with DRA injection
on crude oil pipelines. He stated that, while the use of DRA can permit higher flow rates
for a given addition of pumping horsepower, it can further increase the risk of surge
resulting from the higher flow velocities. In addition, loss of DRA effectiveness can affect
surge pressures. (Id., lines 162-169)
Mr. Kuprewicz translated this increased flow velocity and surge overpressure risk
into the tangible, practical, adverse impacts such factors could have on the Illinois portion
of the pipelines. Two such impacts exist. First, the risks of pipeline rupture and oil spill
will increase significantly compared to the pipeline’s existing capacity (which was the
capacity described to the Commission in Docket Nos. 14-0754 and 14-0755). Second, in
the event of a rupture, the volume of oil released compared to a rupture occurring today
would be significantly greater. (Id., lines 377-388)
Mr. Kuprewicz noted that Joint Petitioners stated that as designed the pipelines’
mainline valves can be controlled, and will be operated, remotely. (Id., lines 190-191)
According to Mr. Kuprewicz, remotely operated mainline valving is subject to being
inadvertently closed and must be designed carefully to prevent overpressure. He urged
97
Joint Petitioners to provide sufficient mainline valve design detail to protect against
overpressure, such that it can be independently verified that, at the higher flow rate, surge
pressure will not exceed 110% MOP. Given the high liquid velocities, Mr. Kuprewicz does
not believe pump station relief valves are adequate to prevent surge overpressures on
the mainline pipelines, and that additional safety equipment is likely needed. (Id., lines
198-204)
In his rebuttal testimony (SOIL-SC Ex. 5.0), following the submission of Joint
Petitioners’ rebuttal testimony which included responses to Mr. Kuprewicz’s direct
testimony, Mr. Kuprewicz continued to have concerns regarding the design, operational,
and safety aspects of the proposed additional pumping facilities. The surge protection
system for this high flow rate, where surge is a very real risk, appears not to be failsafe
to prevent overpressure in excess of 110 % MOP. He stated that additional information
is needed from Fluid Flow Consultants (“FFC”), the entity hired to conduct the surge
analysis on the DA and ETCO pipelines. The missing information relates to whether the
***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx CONFIDENTIAL***
anywhere on the system. Joint Petitioners’ proposed configuration, under the FFC surge
analysis, only protects against surge overpressure as long as ***CONFIDENTIAL xxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx CONFIDENTIAL*** (Id., lines 58-
73) Mr. Kuprewicz is very concerned because he does not view this as failsafe. He states
further that the complexity/complications associated with communication (such as
satellite or cellular networks) is not failsafe. In addition, software programing in complex
SCADA systems is not considered a failsafe protection against surge overpressure, such
98
as are the mechanical SRVs proposed at the pump stations for some causes of surge.
(Id., lines 75-80) According to the Facility Response Plans (“FRPs”), communication
***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxx CONFIDENTIAL*** Continuing, Mr. Kuprewicz stated that the
surge reports are unclear whether any inadvertent mainline valve closure cannot generate
surge overpressure ***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxx. CONFIDENTIAL*** (Id., lines 80-114) He added that the surge analysis tables
(part of Dakota Access-ETCO Ex. 7.3) apparently attempting to address the 1,100,000
bpd cases with ***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxx CONFIDENTIAL*** are not clear. He suggested these critically
important protections and their ability to failsafe protect against surge overpressure,
especially mainline valve closure, need to be clarified by FFC. (Id., lines 114-119)
Mr. Kuprewicz observed that Joint Petitioners’ witness Dr. Hein indicated that he
conducted his surge analysis with the intent of limiting operating pressure due to surges
to 105% of MOP rather than to 110% of MOP as provided for in PHMSA regulations.
(Dakota Access-ETCO Ex. 7.0, lines 48-51). (Id., lines 120-125) He termed that a false
sense of assurance that surge risks have been accounted for. If the safety approaches
are not failsafe, overpressures can quickly far exceed 110% MOP to a pressure level that
99
would likely cause the pipeline to rupture. (Id., lines 125-131) “This is just one reason
that federal pipeline safety regulations (citation in testimony omitted) setting minimum
pipeline safety standards require that pipeline operating manuals address an abnormal
condition related to “unintended closure of valves or shutdowns.”’ (Id., lines 132-135)
Relying on a control room operator to fix the problem is insufficient, according to
Mr. Kuprewicz. The experience of being in a pipeline control room while a control center
operator tries and fails to stop a mainline valve that is unexpectantly closing on its own
makes it obvious why failsafe protection on a pipeline moving at high velocities is
necessary to prevent surge overpressure. (Id., lines 135-139)
Mr. Kuprewicz next commented on the valve design. “A ***CONFIDENTIAL xxxx
CONFIDENTIAL*** valve’s valve flow coefficient (“CV”) curve (flow value versus percent
stem travel, or valve opening) will show that ***CONFIDENTIAL xxxx CONFIDENTIAL***
valves can be especially susceptible to generating surge overpressure, especially on a
pipeline operating at excessively high actual flow velocities….” (Id., lines 141-147) Based
on his own analysis, Mr. Kuprewicz concluded that such a valve type can contribute to
surge overpressure “given this type of valve’s potential to dramatically reduce flow (i.e.
greater change in CV or flow) with minor changes in valve opening or travel.” (Id., lines
154-156)
Mr. Kuprewicz then commented further on surge potential. He stated that SRVs
are special fast acting overpressure protection devices that can actually contribute to
mainline surge overpressure. He stated that he has observed rapid overpressures in
mainline pipelines in microseconds if SRVs are not properly installed, designed,
calibrated, and maintained. Mr. Kuprewicz recommended that Joint Petitioners
100
incorporate into the relief valve installations the guidance contained in America Petroleum
Institute (“API”) Standards 520 and 521, as these standards help protect against improper
installation. (Id., lines 168-176)
Mr. Kuprewicz further addressed the potential adverse effects of injecting DRA into
the pipelines, which is a component of Joint Petitioners’ plans to increase oil volume
throughput. His experience with DRA in crude oil systems is that the material does not
take shear well and its effects can disappear quickly. If the DRA breaks down, a pipeline
may experience a large volume of crude oil slowing down very quickly. A fast change
from the high velocity Joint Petitioners plan to a significantly lower velocity can lead to a
dangerous situation. (Id., lines 177-193)
During the evidentiary hearings, SOIL-SC-WK counsel cross-examined several
Joint Petitioner witnesses who had provided testimony in rebuttal of Mr. Kuprewicz. The
cross exposed several important items of information about the design, engineering,
operations, and safety of the pipelines following, if approved, the proposed capacity
expansion plans. The following portion of this Initial Brief highlights portions of the cross-
examination, organized by Joint Petitioner witness.
Stamm
Mr. Stamm was asked about PHMSA’s role pertaining to Joint Petitioners’
proposal. He acknowledged that a PHMSA permit or approval is not required for the
project (Tr. at 215-16)
Frey
Mr. Frey admitted that (conservatively) setting the limit for the surge analysis at
105% MOP, instead of 110%, is meaningless if the safety features called for do not work.
101
(Tr. at 237) At Energy Transfer’s control center in Houston, a single operator is
responsible for monitoring the entire DA-ETCO pipeline, from North Dakota to Texas. (Tr.
at 240) The operator in Texas controls the equipment located along the pipeline in Illinois
remotely, via cellular communication, with satellite backup. (Tr. at 244) While mainline
valves have backup battery power for communications, commercial (utility) power is
required to actuate (open or close) a valve. (Tr. at 245) While a loss of communication is
“pretty rare,” it “can happen.” (Tr. at 245-46)
Mr. Frey was questioned about Mr. Kuprewicz’ frustration over Joint Petitioners
having failed to provide him with detailed pipeline maps showing certain facilities and
information by milepost. First, Mr. Frey acknowledged that the United States map Joint
Petitioners provided does not display sufficiently detailed distances and other information.
(Tr. at 251-54) Next, Mr. Frey was referred to the maps attached to his direct testimony
as Exhibits 2.2 and 2.3. He admitted that neither map designates mileposts. (Tr. at 254-
55) After attempting to describe how Mr. Kuprewicz may have been able to construct his
own milepost map from various other documents, Mr. Frey hesitatingly admitted, “We
have mapping, and we have our GIS system where we have the mileposts identified, and
we have the maps done electronically.” (Tr. at 257) When asked why, if he had the map,
he did not provide it, Mr. Frey testified, “It was available in a variety of locations including
elsewhere in the surge report.” The next question and answer followed. “Q. You just felt,
by spreading the information around, that was responsive enough? A. We felt like we had
provided the information that was requested.” (Tr. at 257)
***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
102
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx CONFIDENTIAL***
Hein
Dr. Hein founded FFC, and was commissioned by Joint Petitioners to perform a
surge analysis for the DA Pipeline and ETCO Pipeline. His report on the proposed
capacity expansion was provided as Dakota Access-ETCO Ex. 7.3. ***CONFIDENTIAL
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx CONFIDENTIAL*** Dr. Hein
acknowledged at the hearing that, for the pipelines to operate safely at the higher
proposed throughput levels, the additional safety equipment he recommended must be
installed and be working properly. (Tr. at 286) The PLC and SCADA systems used for
the pipeline’s communication and operation rely on software. (Tr. at 287-88) On his
Company’s web site, a sentence in red type reads, “If you have one of our older – more
than a year old – programs, you should upgrade as we have made many improvements,
103
added new features, fixed bugs, et cetera.” (Tr. at 289) Dr. Hein acknowledged that
software can have bugs, including PLC software. (Tr. at 290) ***CONFIDENTIAL xxxxzz
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxx CONFIDENTIAL*** (Tr. at 302)
***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx. CONFIDENTIAL***
104
B. Specpoint Break
Mr. Kuprewicz also expressed concerns over the pipeline “spec break” where a
newer portion of the ETCO Pipeline south of Patoka rated at 1,440 psig MOP joins the
older, repurposed natural gas segment of the ETCO Pipeline rated at 900 psig MOP. He
advises that the Commission should be sure that failsafe field installation equipment is in
place to prevent overpressure from the planned upgraded Patoka pump station. (Id., lines
372-377) Overall, Mr. Kuprewicz believes Joint Petitioners do not adequately appreciate
the risks associated with surge overpressure and the importance of failsafe protection.
***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxx CONFIDENTIAL*** (Tr. at 308-13)
Mr. Godfrey was asked about the portion of his testimony pertaining to spec break,
and FFC’s recommendations; specifically, how the decrease in pressure to 900 psig at
the spec break is accomplished. (Tr. at 357-58) In a non-steady state, or transient
condition, so long as the systems and protections function, the pressure should remain
below 900 psig at the spec break. (Tr. at 359-60)
105
C. The Questionable Record of Joint Petitioners’ Operator As discussed above in the context of the burden imposed on the public by the
increased risk of release associated with Joint Petitioners’ proposal, releases due to
corrosion should be of concern to the Commission. Monitoring, mitigating, and avoiding
releases due to corrosion are the responsibility of the operator of a pipeline. At paragraph
8 of the Joint Petition, Joint Petitioners identify the operator of their respective pipelines
as DAPL-ETCO Operations Management, LLC, an indirect subsidiary of Energy Transfer.
The significance of this is that it is not entirely accurate. According to Joint Petitioners’
FRPs, DAPL-ETCO Operations Management, LLC has appointed Sunoco Pipeline L.P.
(“Sunoco Pipeline”) as the operator of Joint Petitioners’ pipelines. (SOIL-SC Ex. 4.0, lines
523-525) Prior to obtaining the FRPs (which meant overcoming Joint Petitioners’ multiple
objections), Sunoco Pipeline’s involvement with Joint Petitioners’ pipelines was not
reflected in Joint Petitioners’ submissions.22
Sunoco Pipeline’s operation of Joint Petitioners’ pipelines should be of particular
concern to the Commission. Of the ***CONFIDENTIAL xxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
22 The obfuscation of the true operator of the pipelines is another example Joint Petitioners’ actions that cause SOIL-SC-WK to question many of Joint Petitioners’ statements in this docket.
106
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxx CONFIDENTIAL***
Joint Petitioners witness Todd Stamm defends the frequency of Sunoco Pipeline’s
appearance on the lists by pointing out that Sunoco Pipeline is the operator. (Dakota
Access-ETCO Ex. 3.5, lines 90-91) He asserts that under PHMSA reporting
requirements, unless there is a specifically known and identified entity that caused an
incident, the pipeline operator is always identified as the entity “who caused the leak or
loss of structural integrity.” (Id., lines 84-87) SOIL-SC-WK are well aware of this, which
is why they believe the Commission should be concerned. SOIL-SC-WK are not
suggesting that Sunoco Pipeline is responsible because it is actively causing corrosion.
Rather, because it is the operator’s responsibility to monitor for and work to prevent
pipeline failure due to corrosion, Sunoco Pipeline’s poor track record in this regard
warrants the Commission’s attention. Although the lists in SOIL-SC Exs. 4.10 and 4.11
do not reflect corrosion attributable incidents on Joint Petitioners’ pipelines at issue in this
docket, corrosion should not be expected on the segments constructed just four or five
years ago. But as noted above, SOIL-SC witness Kuprewicz noted corrosion on the older
ETCO Pipeline segments, which Sunoco Pipeline did not believe warranted concern.
Before allowing Joint Petitioners to nearly double throughput, however, the Commission
should give serious consideration to Sunoco Pipeline’s history as an operator.
Notably, when confronted with Sunoco Pipeline’s track record, Joint Petitioners
attempted to distance themselves from that history. Mr. Stamm acknowledged that
Energy Transfer became a general partner of Sunoco Logistics Partners, L.P. in 2012,
107
but characterized Energy Transfer and Sunoco as “independent, separately operated
companies until April 2017.” (Dakota Access-ETCO Ex. 3.5, lines 96-98) This description
is not accurate. As reflected in paragraph 5 of the verified March 13, 2020 Petition for
Interlocutory Review of SOIL and SC, the Sunoco family of companies became part of
the Energy Transfer family beginning in October 2012. On October 5, 2012, Energy
Transfer Partners, L.P. (“ETP”) and Sunoco, Inc. announced the successful completion
of their previously announced merger of a wholly owned subsidiary of ETP, with and into
Sunoco, Inc., with Sunoco, Inc. surviving the merger as a subsidiary of ETP. Sunoco
L.P.’s own website identifies 2012 as the year Energy Transfer acquired Sunoco, Inc. A
subsequent intracorporate merger occurred in April 2017 consolidating the ownership
structure. Joint Petitioners did not disagree with this description of the ownership in their
March 20, 2020 Answer to SOIL-SC’s March 13, 2020 Petition for Interlocutory Review.
Any attempt by Joint Petitioners to distance themselves from Sunoco Pipeline’s track
record is disingenuous.
Mr. Stamm also attempts to portray the pattern of leaks and failures as acceptable
consequences of Joint Petitioners’ enterprise. He downplays the incidents on SOIL-SC
Exs. 4.10 and 4.11. To hear Mr. Stamm testify, if a release of oil occurs on Joint
Petitioners’ property or only costs tens of thousands of dollars to remediate, it does not
count. (Dakota Access-ETCO Ex. 3.5, lines 100-114) In light of this view, the question
for Joint Petitioners is how bad does Sunoco Pipeline’s operations have to be before it is
a concern?
In addition, SOIL-SC-WK are not the only ones concerned about the operator’s
track record. In the March 25, 2020 Standing Rock Decision, among the reasons that the
108
court ordered the USACE to prepare an EIS is that the USACE failed to consider Sunoco
Pipeline’s safety record. The court observed that a “valid risk analysis would recognize
the history of the operator, but that didn't happen here.” (2020 U.S. Dist. LEXIS 51540,
*33) The court proceeded to state, “In this case, the operator's history did not inspire
confidence: ‘PHMSA data shows Sunoco has experienced 276 incidents resulting in over
$53 million in property damage from 2006-2016,’ which one expert described as ‘one of
the lower performing safety records of any operator in the industry for spills and releases.’
Holmstrom Decl., ¶ 9.” (2020 U.S. Dist. LEXIS 51540, *34) In determining whether
Sunoco Pipeline is up to the task of managing nearly twice the throughput on Joint
Petitioners’ pipelines, the Commission would be well within its bounds to consider Sunoco
Pipeline’s track record and should do so.23
D. Inadequate Leak Detection and Response Time SOIL-SC-WK discussed the inadequacy of Joint Petitioners’ leak detection system
above in the context of the balancing of costs and benefits to the public (or more
specifically, Joint Petitioners’ failure to consider any costs associated with its project).
Nevertheless, Joint Petitioners’ leak detection system warrants revisiting in the discussion
of Joint Petitioners’ operations. SOIL-SC witness Richard Kuprewicz expresses concern
over Joint Petitioners (in)ability to detect and respond to releases in a reasonable amount
of time. Given the higher volumes Joint Petitioners propose to transport and the higher
23 SOIL-SC-WK recognize that a majority of the Commission determined on April 1, 2020 not to allow cross-examination of Joint Petitioners’ witnesses on Sunoco Pipeline’s track record. The filings preceding that determination were made prior to the Standing Rock Decision. With the knowledge of the Standing Rock Decision, SOIL-SC-WK encourage the full Commission to reflect on the lack of a complete record in this matter concerning Sunoco Pipeline’s record.
109
velocities discussed above, it is important for the Commission to understand how
implementation of Joint Petitioners’ proposal would impact inevitable releases.
To begin with, Mr. Kuprewicz maintains that the Commission should understand
that Joint Petitioners’ leak detection system claim of being able to detect leaks is in all
probability unrealistic based on his extensive experience in investigating pipeline releases
and his working knowledge of pipeline release detection systems. He asserts that it is
challenging enough for “state of the art” release detection systems to remotely and timely
identify rupture releases, and almost impossible for such systems to reliably identify the
much harder to spot lower rate “leak” releases. Leak detection claims for small opening
releases (such as pitting or punctures), even on well-monitored systems, are often
overstated. The reality demonstrated time and time again, is that such remote leak
detection approaches are very difficult and challenging. Most leaks are not determined
by remote detection, but by field observations of hydrocarbon releases where the amount
of oil released can be considerable before its discovery. The 1% variation described in
SOIL-SC Ex. 4.13 does not reflect Mr. Kuprewicz’s experience and many others’
observations that while CPM systems may meet PHMSA’s regulations for leak detection,
meeting regulation and working reliably are two very different objectives. (SOIL-SC Ex.
2.0, lines 307-324)
As noted, Joint Petitioners openly acknowledge that they cannot detect leaks less
than 1% of the throughput on the pipelines. (SOIL-SC Ex. 4.13) This means, by Joint
Petitioners’ own calculation, that at a flow rate of 1,100,000 bpd, in one hour 458 barrels
of crude oil can escape undetected. Even at the current throughput of 570,000 bpd, Joint
Petitioners’ witness Todd Stamm acknowledges that 237.5 barrels could escape over one
110
hour without detection. (Dakota Access-ETCO Ex. 3.5, lines 43-46) With regard to
landowner intervenor William Klingele’s concern with leaks (see generally Klingele Exs.
2.0 and 2.1) and his observation that leaked oil can rise to the surface and contaminate
farmland, Mr. Stamm responds, “Whether leaked crude oil will rise to the surface, and if
so within what time period, in a leak at a particular location, will depend on a number of
site-specific conditions including soil and rock type and condition at the location, pipeline
burial depth, elevation, surface gradient, and other factors.” (Dakota Access-ETCO Ex.
3.5, lines 61-65) In other words, given Joint Petitioners’ admitted inability to detect “small”
leaks (ie: leaks that can release 457 barrels, or over 19,000 gallons, in one hour ), such
a leak could continue for hours (days?) undetected by Sunoco Pipeline or anyone at the
site if the crude does not rise to the surface due to the circumstances at the site of the
leak. Not in the least bit reassuring is Mr. Stamm’s offer that the probability of detecting
a small leak “will increase as the volume imbalances increase.” (Id., line 157) Joint
Petitioners have not indicated how much time need pass before a volume imbalance is
detectable. Joint Petitioners’ lack of concern over these undisputed facts is shocking. As
with Sunoco Pipeline’s operation track record, apparently this level of risk to others and
their property is acceptable to Joint Petitioners and their owners.
The Standing Rock court, however, did not agree. Rather than accept attempts to
gloss over the concerns with detecting both small and large leaks, the court could not find
that the USACE adequately disposed of those concerns. With regard to the claim that a
small leak would eventually be detected, the court observed:
Its further response that a less-than-1% leak would eventually be detected over an unspecified "period of time" after building up enough to cause a meter imbalance, id., was less than reassuring given that the amount of
111
undetected leaking oil could be as much as 6,000 barrels per day.24 See RAR 7683. Indeed, one of the experts noted that Sunoco had experienced a spill of 8,600 barrels on one of its pipelines when it had not recognized a leak even when there was an "imbalance indication[]" because that imbalance did not exceed "established normal operating tolerances." RAR 7491 (quoting PHMSA report of the incident). (2020 U.S. Dist. LEXIS 51540, *31
The USACE’s failure to consider Joint Petitioners’ leak detection system was another
reason that the court directed the preparation of an EIS and will consider whether to order
the shutdown of the DA Pipeline in the meantime.
Joint Petitioners’ admission that it cannot detect small leaks, which can continue
for an unknown amount of time, is inconsistent with the requirement that they be fit, willing,
and able to provide service and that the project is in the public interest or necessary to
promote the security or convenience of the public. The absence of evidence on Joint
Petitioners’ leak detection failure when the Commission granted Joint Petitioners authority
under Sections 15-401 and 8-503 in Docket Nos. 14-0754 and 14-0755 is not a bar to the
Commission considering that evidence now. Joint Petitioners’ admitted inability to protect
the public must not be overlooked and must be taken as seriously as it was in Standing
Rock.
Once a release is detected, whether by Joint Petitioners’ leak detection system or
by the public, Mr. Kuprewicz very much doubts that Joint Petitioners’ estimated response
time of a matter of minutes is realistic. (SOIL-SC Ex. 5.0, lines 363-365) SOIL-SC-WK
note that Joint Petitioners optimistically claim that they can respond to several abnormal
operating situations in a matter of minutes. Joint Petitioners’ Standard Operating
Procedures for Recognizing and Reacting to Abnormal Operations (“SOP”) identifies the
24 This calculation appears to be based on a throughput of 570,000 bpd.
112
steps to be taken when abnormal operations occur (ie: unintended valve closures,
unintended shutdown, increase or decrease of pressure or flow rate outside of normal
limits, loss of communications). The SOP has been admitted into the record as
confidential SOIL-SC Cross Ex. 2. Joint Petitioners’ witness John Godfrey discusses
situations in which a loss of communications occurs and asserts that the Sunoco Pipeline
operators are “trained to immediately bring the pipeline to a safe mode of operation.”
(Dakota Access-ETCO Ex. 8.2, lines 167-170) When questioned about the details of
doing so, both through discovery and under cross-examination, Mr. Godfrey refers to the
SOP and unavailable training documents and defers to Joint Petitioners’ operations
witness. In mentioning the SOP, he specifically refers to Section 7.4, which lists only
four steps if a loss of communications occurs using words like “evaluate” and “address
promptly.” Despite the lack of details on what exactly an operator does to bring the
pipeline back to an undefined “safe mode of operation,” Mr. Godfrey claims that an
operator can shut down an impacted pipeline segment in ***CONFIDENTIAL xxxxxxxx
CONFIDENTIAL*** minutes. (See confidential SOIL-SC Cross Ex. 3 and Tr. at 371-374)
Mr. Godfrey’s support for an operator being able to restore a “safe mode of operation”
does not reassure SOIL-SC-WK. General assurances based on general procedures are
in no way sufficient to demonstrate to the Commission that Joint Petitioners can protect
the public from abnormal conditions on the pipelines, particularly when there is no
explanation for Joint Petitioners’ rosy response times to problems, like surge
overpressure, that can occur in a fraction of second.
Because Joint Petitioners readily admit that they cannot detect “small” leaks
capable of releasing up to 458 barrels of crude in one hour and can offer only a
113
rudimentary explanation of their ability to respond to operating problems within minutes,
the Commission should not find that Joint Petitioners have met their burden to
demonstrate that their proposal is in the public interest under either Section 8-503 or
Section 15-401.
VI. OTHER
A. Interstate Commerce Act Compliance
1. Applicable Statutes and Case Law
SOIL-SC-WK contend that certain agreements and practices of Joint Petitioners
violate the Interstate Commerce Act (“ICA”) (49 App. U.S.C. § 1 et seq. (2020)). SOIL-
SC-WK have raised issues, for example, questioning the legality of at least some of Joint
Petitioners’ capacity contracts under the ICA, going back to the 2014 initial and expansion
open seasons.
The ICA dates back to 1887. An instructive article published in the Cornell Law
Review in 1940 contains an early historic description of the ICA, subsequent federal
statutes and other related legislative activity, decisions of the Interstate Commerce
Commission, and decisions of the United States Supreme Court and other federal courts.
Forrest R. Black, Oil Pipe Line Divorcement by Litigation and Legislation, 25 Cornell L.
Rev. 510 (1940) (“Black” or “Black article”). The ICA and its companion statute, the Elkins
Act of 1903 (49 App. U.S.C. §§41-43 (1903)), were both designed to prevent
discrimination and rebates, but were initially limited to rail and water carriers.
The ICA provides in pertinent part:
If any common carrier subject to the provisions of this chapter shall, directly or indirectly, by any special rate, rebate, drawback, or other device, charge demand, collect, or receive from any person or persons a greater or less compensation for any service rendered or to be rendered, in the
114
transportation of passengers or property, subject to the provisions of this chapter, than it charges, demands, collects, or receives from any other person or persons for doing for him or them a like and contemporaneous service in the transportation of a like kind of traffic under substantially similar circumstances and conditions, such common carrier shall be deemed guilty of unjust discrimination, which is prohibited and declared to be unlawful. (49 U.S.C. § 60502; 49 App. U.S.C. § 2 (1988))
Under the relevant portion of the Elkins Act:
[I]t shall be unlawful for any person, persons, or corporation to offer, grant, or give, or to solicit, accept, or receive any rebate, concession, or discrimination in respect to the transportation of any property in interstate or foreign commerce by any common carrier subject to said Act . . . whereby any such property shall by any device whatever be transported at a less rate than that named in the tariffs published and filed by such carrier, as is required by said Act to regulate commerce and the Acts amendatory thereof. (49 U.S.C. § 60502; 49 App. U.S.C. §§ 41(1), 43 (1988))
Courts have historically interpreted the ICA and Elkins Act broadly.
“More unequivocal language would be hard to imagine. It strikes at any and every
kind of rebate, no matter by whom or to whom given. Nowhere does the section say or
imply that rebates are unlawful only if they are given to or are for the benefit of a shipper.
It is a rebate, to whomever given, which the statutory language proscribes.” United States
v. Braverman, 373 U.S. 405, 406 (1963).
“The concessions are none the less illegal, if made for non-transportation services,
as long as they result in lowering directly or indirectly transportation costs to a shipper.
That other inducements may also have influenced the concessions is not important when
a materially effective purpose is the securing of traffic for an interstate carrier. Where
traffic is an object, and discriminatory advantage the means employed in attempting to
obtain or actually obtaining it, there is a violation of the section in respect to
transportation.” Union Pac. R.R. Co. v. United States, 313 U.S. 450, 464 (1941).
115
“The all-embracing prohibition against either directly or indirectly charging less
than the published rates shows that the purpose of the statute was to make the prohibition
applicable to every method of dealing by a carrier by which the forbidden result could be
brought about.” N.Y., New Haven & Hartford R.R. Co. v. Interstate Commerce Comm’n,
200 U.S. 361, 392 (1906) (“New Haven”).
As the Black article noted, the Hepburn Act of 1906, by virtue of the Pipe Line
Amendment, extended common carrier status to oil pipelines, thus bringing them under
the ICA and the Elkins Act. (Black article at 510-511) The Hepburn Act also included the
so-called Commodities Clause, prohibiting a railroad company from transporting any
commodity which it owns in whole or in part except for its own use. It thereby divorced
production and transportation for railroads but oil pipelines were spared from the
Commodities Clause. (Id. at 511; see United States v. South Buffalo Railway Co., 333
U.S. 771 (1948)).
The presence, or absence, of the Commodities Clause, is not determinative as to
discrimination or rebate issues. The Supreme Court made that determination in 1906 as
to railroads (New Haven, supra).
In its Order in the Magellan proceeding (although still subject to rehearing after
issuance of a tolling order25) (“Magellan” or the “Magellan Order”), FERC reiterated that
“[t]he fact that the filed tariff rate was paid by the Marketing Affiliate to its pipeline is not
relevant if the entire transaction includes either direct or indirect payments back to the
shipper because the ICA prohibits any and all means or devices that result either directly
or indirectly in a rebate from the filed tariff rate.” Magellan Midstream Partners, L.P., 161
25 Order Granting Rehearings for Further Consideration, Magellan Midstream Partners, L.P., Docket No. OR17-2-001 (Jan. 22, 2018), eLibrary No. 20180122-3021.
116
FERC ¶ 61,219, at 14 (2017), petition for rehearing pending (“Magellan” or the “Magellan
Order”)
SOIL-SC-WK have previously raised issues as to the legality under Magellan of
certain arrangements undertaken by Joint Petitioners. Such issues were raised in (i) the
Petition for Interlocutory Review filed December 9, 2019; (ii) the Verified Motion to
Supplement Petition for Interlocutory Review filed December 13, 2019; and (iii) the
Verified Amended Motion for Leave to Supplement Petition for Interlocutory Review filed
December 31, 2019.
Magellan concerned a petition for a declaratory order by Magellan Midstream
Partners, L.P. (“Magellan Midstream”) requesting a finding that Magellan Midstream’s
proposal to establish a marketing affiliate to buy, sell, and ship crude oil is compliant with
the ICA. Magellan Midstream subsidiaries and affiliates owned crude oil pipelines. In its
petition, Magellan Midstream stated that it wanted to establish a marketing affiliate to buy
and sell crude oil which it would ship on Magellan Midstream’s pipelines at the applicable
tariff rate. It wanted the marketing affiliate to be allowed to participate in open seasons
conducted by the pipeline affiliates. Magellan Midstream stated that the marketing
affiliate may incur a profit or a loss on the shipments, depending on how the tariff rate for
a shipment compares to the difference in price for the oil between the origin and
destination markets; but that a loss incurred by the marketing affiliate could still provide
an overall financial benefit to the integrated company. An overall profit would be realized
if the origin-destination price differential exceeds the variable cost of the shipment
(variable cost being less than the tariff rate). Magellan Midstream contended such
transactions would benefit the marketing affiliate by establishing shipping history on its
117
affiliated pipeline. Magellan Midstream also stated that its marketing affiliate may partially
assign rights acquired in an open season, or enter into similar arrangements with third
parties, at rates that diverge from the committed shipper rate contained in the applicable
TSA. (Magellan Order, ¶ 4, 5)
In arguing for its compliance with the ICA, Magellan Midstream stated that, unlike
railroads, oil pipelines are not prohibited by the ICA’s Commodities Clause from shipping
products in their own name on their own pipeline. Magellan Midstream emphasized that,
like other third-party shippers, its marketing affiliate would pay the filed tariff rates when
shipping crude oil on Magellan Midstream’s pipelines. It added that no producers or
marketers would be denied pipeline access, consistent with Magellan Midstream’s
common carrier obligations.
FERC denied Magellan Midstream’s request, stating that, “taken together the
transaction’s proposed by Magellan would violate various provisions of the ICA, primarily
the ICA’s prohibition on rebates.” (Id., ¶ 11) FERC stated that the ICA permits an oil
pipeline to create a marketing affiliate (which is common-place in the industry), for that
marketing affiliate to ship on its affiliate’s pipeline, and for marketing affiliates to
participate in open seasons. (Id., ¶ 12)
Beyond the relationship and activities described above, other activities can run
afoul of the ICA and the Elkins Act. FERC in Magellan noted that the ICA prohibits a
common carrier from granting special rates or rebates to any shipper. The ICA prohibits
a carrier from charging different rates for identical service. A carrier that receives different
compensation from one shipper than it receives from another for providing like and
contemporaneous service in transporting like kind traffic under substantially similar
118
circumstances and conditions is guilty of unlawful discrimination. FERC concluded its
description of the law by stating that any refund or remittance of a filed tariff rate is a
violation of the tariff. (Id., ¶ 13)
In holding that that transactions Magellan Midstream described would violate the
ICA, FERC concluded that the “fact that the filed tariff rate was paid by the [Magellan
Midstream affiliate] to its pipeline is not relevant if the entire transaction includes either
direct or indirect payments back to the shipper because the ICA prohibits any and all
means or devices that result either directly or indirectly in a rebate from the filed tariff
rate.” (Id., ¶ 14) (emphasis added) FERC noted at the outset of its order that Magellan
Midstream supported its request with the statement that “a number of its crude oil pipeline
competitors have similar marketing affiliates that buy and sell crude oil for the purpose of
shipping on their affiliates’ pipelines.” (Id., ¶ 1) (emphasis added)
In reaching its conclusions, FERC cited and relied upon, as precedent, several of
the older Supreme Court decisions in railroad cases. (Id., ¶ 14) FERC cited three cases
wherein the Court held the subject transactions violate the ICA’s prohibition against
rebates.
The first cited case was United States v. Union Stock Yards & Transit Co. of
Chicago, 226 U.S. 286 (1912). In that case a railroad operation based in Chicago
transported livestock in interstate commerce. The railroad entered into a contract with a
company in the cattle slaughtering business, agreeing to pay the company $50,000 if it
would build a plant adjacent to stock yards where the company would utilize the railroad
for transportation of the cattle and pay the regular transportation charges. The Court held
119
that the contract amounted to an undue advantage given to and unlawful discrimination
in favor of the slaughter company.
The next case cited in the Magellan Order was New Haven. In that case, the
Chesapeake & Ohio Railway purchased and transported coal under contract with the New
Haven Railroad. The delivered price to New Haven was $2.75/ton. The cost of coal to
Chesapeake was $2.47/ton. The published tariff for transportation was $1.45/ton,
resulting in a loss per ton of $1.17/ton. Chesapeake was a carrier, and most of the
transportation was on its rail line. Chesapeake bore the loss arising from the difference
between the contract price, the price of the coal at the mines, the published rate to an
interim site, and the cost of transporting the coal from there to the destination.
The issue presented was as follows: may a carrier in interstate commerce contract
to both sell and transport a commodity, when the contract price does not pay the cost of
purchase, the cost of delivery, and the published freight rates? (New Haven, 200 U.S. at
390-391) The railroad carrier stated that when a carrier sells an article which it has
purchased and transports it for delivery, it is both a dealer and a carrier. The railroad
carriers then contended that, when the price for the commodity is adequate to pay the
published freight rate and something over, the statutory requirement to adhere to the
published rates is complied with, because the price will be imputed to the freight rate, and
the loss, if any, attributed to the company in its capacity as dealer, and not as a carrier.
(Id. at 397) The Supreme Court disagreed. To hold otherwise would allow the carrier who
possesses the power, by the form in which he deals, to render the prohibitions of the
statute ineffective, since it implies the right of a carrier to shut off inquiry as to the real
result of a particular transaction on the published rates, and avoiding the prohibitions of
120
the statute. (Id.) The Court found that the coal company/carrier/seller bought and sold the
coal without reference to whether the net result to it would realize its published
[transportation] rates. (Id.) It is not a factor whether the carrier intended to violate the
statute, but instead whether the effect of the acts done violate those prohibitions. (Id. at
398)
The Court acknowledged that there is no express prohibition against a carrier
becoming a dealer in the commodities to be shipped in interstate commerce.26 It does
not matter that the practical effect of applying the prohibitions will be to render it difficult,
if not impossible, for a carrier to deal in commodities. That result does not relieve the
Court of its plain duty of enforcing the statutory provisions as they exist. (Id. at 399) The
Court held that the contracts in question, being contrary to public policy and in conflict
with the ICA, were void and unenforceable.
FERC in Magellan next cited Armour Packing Co. v. United States, 209 U.S. 56
(1908). Several packing houses had entered into a contract with a rail carrier to transport
product from Kansas City, Kansas to New York City at the carrier’s then tariff rate per
pound from June 17, 1905, until December 31, 1905. On August 6, the rail tariff was
amended and increased. Despite the increase, the packing house shippers insisted on
shipping their product pursuant to the lower rate contained in the contract. The packing
houses were prosecuted under the Elkins Act for obtaining from the rail carrier an unlawful
concession from the published and filed rate for a shipment made after the amended tariff
became effective. Each of the packing houses was convicted, and the circuit court of
appeals affirmed. The Supreme Court described the Elkins Act as making it unlawful for
26 The decision in this case was rendered several months prior to the effective date of the Hepburn Act’s enactment of the Commodities Clause.
121
any person “to offer, grant, solicit, give, or to accept or receive, any rebate, concession,
or discrimination in respect to transportation of property in interstate or foreign commerce,
whereby any such property shall, by any device whatever, be transported for a less rate
than that published and filed by such carriers, or whereby any other advantage is given
or discrimination practised.” (Id. at 71) The Court found that Congress’ purpose was for
all shippers to be treated alike, that the only rate charged for the same service, under the
same conditions, should be the rate lawfully established and published. The Court
continued, “It is not so much the particular form by which or the motive for which this
purpose was accomplished, but the intention was to prohibit any and all means that might
be resorted to to obtain or receive concessions and rebates from the fixed rates, duly
posted and published.” (Id. at 72) The Court affirmed the judgment of the circuit court of
appeals.
The last of the railroad cases cited by the Magellan Order was United States v.
Delaware, Lachawanna, and Western R.R. Co., 238 U.S. 516 (1915). The Supreme
Court in this case interpreted and applied the Commodities Clause of the Hepburn Act to
a situation in which an owner of coal and the carrier were not the same company, but
were affiliates. The facts were that a railroad company was also authorized to mine and
sell coal. In an effort to avoid violation of the Commodities Clause, the company devised
a plan by which it would sell the coal at the mine mouth, before transporting it. The
company formed a new corporation to serve as the purchaser of the coal. The new
corporation was nearly totally owned by the same stockholders as the railroad, and the
two companies shared many of the same officers and directors, and were located in the
same offices. The railroad company continued its coal mining business, and sold the coal
122
not needed for its own operations to the new coal company. The railroad company then
transported the coal it had sold to the new company to its destination. The coal company
paid the regular tariff rate for transportation. A government petition against both
companies alleged the two were practically one, and attacked the validity of the contract
between them. The government appealed from the district court’s dismissal of the
petition. The Supreme Court examined the details of the contract (Id. at 530-534) and
determined that, based on the contract terms (which the Court described in detail), along
with the relationship of the companies, the coal company was not independent. The Court
thus held the contract to be invalid, reversed the lower court decree, and directed the
lower court to enjoin the railroad from transporting any more coal sold under the subject
contract.
It is evident from the Magellan Order that FERC correctly views the ICA and Elkins
Act as equally applicable to common carrier oil pipe lines and to railroads. The Supreme
Court also decided other cases involving ways that parties attempted to get around the
ICA and Elkins Act proscriptions. In Union Pac. R.R. v. U.S., the Court held that the
railroad’s provision of certain financial and other services and support for a new food
terminal that would increase the railroad’s traffic, and revenue, amounted to illegal
rebates, concessions and discriminations under the ICA and Elkins Act. (313 U.S. at 450)
The Court found that the railroad’s motive was to divert produce traffic from other railroads
to its own. (Id. at 400-461) The Court described that, as general principles, the statutes
have been effective “to accomplish the destruction of discriminatory practices, whatever
their form. Violation of the commerce acts through receipt of advantages is to be tested
123
by actual results not by intention. Any and all means to accomplish the prohibited end
are banned.” (Id. at 461-462)
The Supreme Court encountered a situation in another case where an individual
who worked for a shipper had been charged with soliciting concessions and rebates
respecting shipments of the shipper’s goods by an interstate motor carrier. (United States
v. Braverman, 373 U.S. 405 (1963)) There was no allegation that the shipper benefitted
from the rebate. The district court had dismissed an indictment brought against the
individual under the Elkins Act because any alleged advantage or discrimination in favor
of the shipper was lacking. The Supreme Court reversed, stating that the Elkins Act
outlaws solicitations of rebates by anyone, without regard to who may benefit. (Id. at 406)
Quoting portions of the statute, the Court stated that the Elkins Act “aims in unmistakable
language at preserving published tariffs inviolate.” (Id.) The Court continued, stating that
the Elkins Act goes on:
to make it unlawful ‘for any person, persons, or corporation to offer, grant, or give, or to solicit, accept, or receive any rebate, concession, or discrimination’ as to interstate shipments of property ‘whereby any such property shall by any device whatever be transported at a less rate than that named in the tariffs published and filed by such carrier …’ (Id.)
The Court characterized the statutory prohibitions in its own descriptive manner:
More unequivocal language would be hard to imagine. It strikes at any and every kind of rebate, no matter by whom or to whom given. Nowhere does the section say or imply that rebates are unlawful only if they are given to or are for the benefit of a shipper. It is a rebate, to whomever given, which the statutory language proscribes. (Id.)
124
2. The Record Indicates Likely Violations
With the foregoing legal foundation in mind, SOIL-SC-WK will next review relevant
portions of the record and demonstrate how and why Energy Transfer and Joint
Petitioners have violated the ICA and the Elkins Act. SOIL-SC witness Richard Stuckey
provided testimony pertaining to the possibility of shippers affiliated with a pipeline
shipping at a loss. (SOIL-SC Ex. 4.0, lines 210-264) Mr. Stuckey compared crude oil
prices in the Bakken region to the prices at Nederland, Texas, during certain months, and
then factored in DA-ETCO tariff shipping rates. Based on these comparisons, Mr.
Stuckey found several instances of losses experienced by the shipper. (Id., lines 221-
256) The losses resulted from the crude price differential between Bakken and Nederland
during the same month being less than the tariff shipping cost. The situation Mr. Stuckey
described is similar to what Magellan Midstream described to FERC. As the case law
shows (e.g., New Haven; Magellan Order), in a transaction like that described by Mr.
Stuckey, under the ICA the law will presume that, for a shipper affiliated with the pipeline
carrier, the carrier effectively granted a discount in the transportation rate. Such a
transaction would be in violation of the ICA, including the prohibition against rebates and
discrimination.
In his surrebuttal testimony for Joint Petitioners (Dakota Access-ETCO Ex. 1.6),
Mr. Emery took issue with Mr. Stuckey’s testimony on this point. He labelled the analysis
and hypothetical transactions “incomplete and unrealistic.” (Id., lines 409-417) Further
on in his response to Mr. Stuckey, Mr. Emery termed “offensive to Petitioners” what he
contended were “unfounded and misleading implications” that Joint Petitioners’ affiliates
125
were engaging in illegal or otherwise inappropriate practices and thereby artificially
inflating demand for pipeline capacity. (Id., lines 448-454) On cross-examination, Mr.
Emery was shown a document that Joint Petitioners’ parent company Energy Transfer
filed in the FERC Magellan proceeding, filed by Energy Transfer attorney Andrew Ray.27
A portion of the Energy Transfer Magellan filing was read into the record. As an industry
shipping practice, “[t]here are many legitimate business reasons why the shipper, whether
affiliated with the pipeline or unaffiliated, would move product between two points when
the price differential between the origin and destination points is less than the applicable
tariff rate.” (Tr. at 446, lines 17-23) Continuing, in its FERC filing, Energy Transfer added,
“Energy Transfer is aware of unaffiliated third-party shippers transporting product on
[Energy Transfer] pipelines at times when the price differential is lower than the applicable
filed tariff rate. It would be discriminatory for an affiliated shipper to be prohibited from
engaging in the same transactions in which an unaffiliated shipper engages.” (Tr. at 447,
lines 1-8)
Mr. Emery’s attempt to discredit Mr. Stuckey as having performed “a seriously
flawed analysis” and discredit his description of hypothetical shipping transactions is
belied by his own company’s filing at FERC.28 Energy Transfer contended in its FERC
Magellan filing that affiliated shippers should be allowed to ship at times when the price
differential is lower than the applicable transportation tariff rate. Energy Transfer’s
advocacy for the kind of transaction Mr. Stuckey described, but which Mr. Emery
27 Energy Transfer’s filing in Magellan was not a response to Magellan Midstream’s petition initiating the proceeding, but followed and was in response to Magellan Midstream’s request for rehearing or clarification of FERC’s Order. 28 The conflict between Mr. Emery’s testimony and Energy Transfer’s statements at FERC represent yet another example of why SOIL-SC-WK question Joint Petitioners’ testimony and representations in this docket.
126
dismissed as unrealistic, is contrary to Mr. Emery’s claims that such transactions are
antithetical to the way business is conducted. Mr. Emery thereafter actually buttressed
the legitimacy of Mr. Stuckey’s hypothetical shipping transaction, when he acknowledged
there are times where the shipper incurs a loss for legitimate business reasons, such as
establishing a shipping history on the pipeline. (Tr. at 458) Mr. Emery also was asked on
cross about Energy Transfer’s 10-K report to the Securities and Exchange Commission
for the year 2018. Appearing in the regulatory risks portion of the 10-K report, and relating
to the Magellan Order, Mr. Emery read the following sentence into the record: “Depending
on how FERC responds [to requests for rehearing], it could have an impact on the rates
we are permitted to charge.” (Tr. at 464) Such a statement strongly suggests that the
FERC Order in Magellan, if not reversed or overturned, would require Energy Transfer to
change the way its pipeline business is conducted. If Energy Transfer was in fact
compliant with the Magellan Order, such a disclosure in its 10-K report would seem to be
unnecessary.
In his next, and last, round of written testimony, Mr. Stuckey testified in response
to additional discovery information the Commission had compelled Joint Petitioners to
provide. (SOIL-SC Ex. 9.0) The additional discovery information pertained to certain
shipper identities and alleged demand for transportation service.
The newly-provided discovery responses and documents shed more light on the
business relationship between Marathon Petroleum Company L.P. (“MLP”) and its parent
Marathon Petroleum Corporation (“Marathon”) on the one hand, and Energy Transfer and
Joint Petitioners on the other. As Mr. Stuckey testified, additional information about that
business relationship was sought because of the apparent tie between Marathon’s
127
purchase of an equity interest in the pipelines and MLP’s transportation volume
commitment on the pipelines as a shipper. (SOIL-SC Ex. 9.0, lines 37-42)
Mr. Stuckey testified further that a new discovery response from Joint Petitioners
disclosed that, in August 2016, MLP had entered into a ***CONFIDENTIAL xxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx. CONFIDENTIAL *** (Id., at 3, lines 50-59)
Mr. Stuckey noted that a similar discovery request was made in relation to Phillips 66, but
as of the date of Mr. Stuckey’s testimony, SOIL-SC had not received such requested
information from Joint Petitioners. (Id. at 4, lines 73-79) As he further explained,
however, public information pointed to Phillips 66 having entered into a similar
arrangement as the one by MLP. (Id. at 4-5, lines 80-112). Mr. Stuckey’s testimony as to
Phillips 66 likely having entered into a similar arrangement was confirmed by the
subsequent supplemental rebuttal testimony of Mr. Emery. (Dakota Access-ETCO Ex.
1.10, lines 70-79)
The relationship of the equity investments in Joint Petitioners’ pipelines by MarEn
Bakken and Phillips 66 to the commitments for capacity on the pipelines by, respectively,
Marathon (or an affiliate) and by Phillips 66 (or an affiliate), constitute examples of
transactions by which an affiliate of a shipper makes an equity investment in a pipeline
company (or its owner) tied to, or conditioned upon, the shipper making a commitment to
contract for capacity on the pipeline.
128
Joint Petitioners previously denied any tie existed between such equity
investments and shipping commitments. When confronted with such a possibility, they
argued that, “[t]here is nothing to see here” in the context of Marathon’s ownership interest
and the capacity commitment. (Joint Petitioner November 7, 2019, Response to October
24, 2019, Motion to Compel, at 16)
Prior to being compelled to respond SOIL-SC’s discovery requests, in response to
SOIL DR 1.057, Joint Petitioners stated, “…there have been no transactions where a
shipper has agreed to subscribe to capacity on Petitioners’ pipelines in an open season
in connection with an equity transaction. Petitioners further state that as common
carriers, they are prohibited from conditioning the award of pipeline capacity to a shipper
in an open season on the shipper committing to purchase an equity interest in Petitioners’
pipelines.” (emphasis added) But as the supplemental rebuttal testimony of Mr. Stuckey
and the precedent agreement demonstrate, such assertions by Joint Petitioners were
inaccurate or mistaken (and in either case misleading).
A logical way to reframe the capacity-for-equity arrangement is to focus on whether
it results in a more Magellan-like rebate. If Marathon, as the affiliated shipper, incurs a
loss on shipping at the August 2016 open season’s tariff rate, but the transaction is still
economically beneficial from Marathon’s perspective given its ownership stake in DA
(although it would not be beneficial for a non-affiliated shipper), it encompasses a rebate.
The overall transaction would be beneficial for Marathon, for example, if an open season
tariff price is less than the expected price differential for the delivered oil, but greater than
the variable cost of transportation, Marathon can still make a profit depending on how
129
much of DA’s profits on Marathon’s tariff rate payments (i.e., above the variable cost)
Marathon receives back through the dividend it receives through its ownership share.
As SOIL-SC-WK have described hereinabove, Courts have historically interpreted
the ICA and Elkins Act as prohibiting any sort of benefit to a shipper – “as long as they
result in lowering directly or indirectly transportation costs to a shipper” – that are not
spelled out in the tariff and available to all shippers. These cases support an interpretation
of the ICA as prohibiting a common carrier from providing any benefit to a shipper that is
not included in the filed rate. The facts and holding in Union Pac. R.R. Co. v. United
States, discussed supra, are instructive and bear reiterating. In that case, the railroad
company’s activities in cooperation with the City of Kansas City, Kansas to lure merchants
from an established railroad terminal in Kansas City, Missouri to a new terminal that
Kansas City, Kansas would construct and own. (313 U.S. at 452) Kansas City, Kansas
persuaded – with the railroad’s urging and support – the merchants to move to the new
terminal by offering “free rents, reduced rents, free refrigeration, cash payments and
rental credits purporting to be for the purpose of paying such produce dealers’ cost of
removal from Kansas City, Missouri.” (Id. at 458) The railroad, in turn, advanced funds
and waived certain bond covenants to enable Kansas City, Kansas to offer below market
terms to the merchants. (Id. at 467-468) Although the railroad had not directly provided
a benefit to the merchants and the terms of the leases were not related to the railroad,
the U.S. Supreme Court found that there was a “plan for securing traffic, developed
cooperatively by a carrier and others, [and] the purpose makes clear that the concessions
offered are in respect to transportation” and therefore the railroad had violated the Elkins
Act. (313 U.S. at 467)
130
FERC in Magellan reiterated that “[t]he fact that the filed tariff rate was paid by the
Marketing Affiliate to its pipeline is not relevant if the entire transaction includes either
direct or indirect payments back to the shipper because the ICA prohibits any and all
means or devices that result either directly or indirectly in a rebate from the filed tariff
rate.” (161 FERC ¶ 61, 219, at 14 (2017))
Joint Petitioners utilized a substantial portion of their last round of prepared written
testimony, which was termed “supplemental rebuttal,” in an attempt to rebut Mr. Stuckey’s
Supplemental Rebuttal and to defend against any possible claim that they or other Energy
Transfer affiliated entities have run afoul of the rebate, discrimination, and other
proscriptions of the ICA and the Elkins Act. Their evidence, however, falls short. Energy
Transfer (or at least its witnesses) concedes that the prohibition applies to a pipeline’s
relationship with its affiliate shipper.
Mr. Stuckey also described other new Joint Petitioner discovery responses
concerning credit ratings of and credit support for affiliated marketers shipping on Joint
Petitioners’ pipelines. (SOIL-SC Ex. 9.0, lines 115-118) To begin with, to assure
themselves of a shipper’s ability to pay, Joint Petitioners’ policy is to impose
creditworthiness requirements through their TSAs. (See Dakota Access-ETCO Ex. 1.10,
lines 208-216 (stating that Joint Petitioners’ TSAs have “have credit policies for shippers
that apply equally to all shippers, both affiliated shippers and unaffiliated shippers…”))
Specifically, Mr. Stuckey noted that Joint Petitioners’ TSAs require ***CONFIDENTIAL
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
131
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxx CONFIDENTIAL***
Energy Transfer has admitted that it has “received parent guarantees for credit
support on behalf of both affiliated and unaffiliated shippers.” (Id., lines 215-216) By
providing its wholly-owned, affiliate shippers with a parental guarantee, Energy Transfer
is providing a benefit (or rebate) – that is outside of DA’s filed rate – to affiliated shippers
that it is not providing unaffiliated shippers. Energy Transfer’s affiliates that are below
investment grade can ship on DA’s pipeline while avoiding letter of credit costs that may
be applicable to non-affiliated shippers. Such a guarantee may also be considered a
benefit outside of the filed rate prohibited by ICA Section 2.
Parental guarantees by pipelines (or pipeline owners) of affiliated shippers may be
commonplace in the oil pipeline industry, but, as FERC found in Magellan, that fact does
not make the practice legal. Energy Transfer (or at least its witnesses) has conceded that
the ICA – and by extension FERC – prohibits it from favoring its own shipping affiliates.
Joint Petitioners’ witness Jeff Makholm testifies:
Q. Does the federal regulation of interstate oil pipelines permit pipeline owners to favor affiliates, either in prices or terms of service? A. No. The bedrock principle of common carriage regulation, reflected in the Interstate Commerce Act is to prevent common carrier pipelines from engaging in unwarranted price discrimination or other operating practices that would abuse those affiliate relationships. [FERC] is highly attuned to relationships between crude oil pipelines and affiliated shippers and effectively prevents the use of those relationships to damage competition in oil markets. Such procedures reflect the longstanding way in which the FERC prevents undue favoritism or advantage in affiliated relationships that would run counter to the basic non-discrimination principles of common carriage as a form of regulation—as reflected in the Interstate Commerce Act. (Dakota Access-ETCO Ex. 6.5, lines 95-100, 109-112)
132
As an additional witness for their last round of prepared written testimony, Joint
Petitioners’ brought in a former FERC attorney, Derek Anderson, to address Joint
Petitioners’ compliance with the ICA. His role was limited to providing background legal
requirements under the ICA and, while stating he did not observe that Joint Petitioners
had violated the ICA, he acknowledged that he was not providing a legal opinion to that
effect, and his observations were based solely on a very few documents Joint Petitioners
had provided to him. Mr. Anderson also stated, “I believe Congress intended to protect
other shippers on the pipeline, who would be competitively and financially harmed if some
shippers (either affiliated or unaffiliated) were afforded more favorable treatment.”
(Dakota Access-ETCO Ex. 10.0, lines 86-88) On cross-examination, Mr. Anderson
acknowledged that similar prohibitions in the Elkins Act do not require a showing of
competitive harm to other, non-affiliated shippers. (March 9, 2020 Transcript at 492)
In the absence of an investment grade credit rating or similar arrangement, a
shipper—whether an affiliate or non-affiliate—must have some form of satisfactory
financial assurance to ship on Joint Petitioners’ pipelines. Financial assurances are
important for “oil pipelines like Dakota Access and ETCO . . . to obtain a reasonable
assurance that the pipelines will recover their costs.” (Dakota Access-ETCO Ex. 6.5,
lines 50-52) Mr. Emery explains further:
Q. Do Petitioners have credit policies for shippers that apply equally to all shippers, both affiliated shippers and unaffiliated shippers? A. Yes. Petitioners’ TSAs do not require credit support or enhancement for a shipper if the shipper has an investment grade credit rating. If the shipper does not have an investment grade credit rating, the shipper must provide credit enhancement, which may include a parent guaranty (if the parent providing the guaranty has an investment grade credit rating), letter of credit, or other satisfactory form of financial assurance. These
133
requirements are applied equally to all shippers. Petitioners have received parent guaranties for credit support on behalf of both affiliated and unaffiliated shippers.
(Dakota Access-ETCO Ex. 1.10, lines 208-216)
Energy Transfer has publicly admitted that it has “received parent guarantees for credit
support on behalf of both affiliated and unaffiliated shippers.” (Id., lines 215-216)
Extending to sub-investment-grade affiliated shippers a parental guarantee from Energy
Transfer—a part owner of DA—is the functional equivalent of waiving the financial
assurances requirement for its affiliated shipper because Energy Transfer’s only
assurance that it will be paid by its affiliated shipper is that it will be able to pay itself. A
self-guarantee is no guarantee at all. Energy Transfer is therefore seemingly incentivized
to favor its affiliated shippers by providing a parental guarantee that effectively waives its
financial assurance requirements so they are eligible to ship on the Joint Petitioners’
pipelines and, in turn, to discriminate against unaffiliated shippers by applying those
financial assurance requirements to them.
B. Section 8-101 of the PUA
The agreements and practices of Joint Petitioners that violate the ICA’s anti-
discrimination provisions also are violative of PUA Section 8-101 (made applicable to
common carrier pipelines by Section 15-101). Section 8-101 provides in pertinent part:
“Duties of public utilities; nondiscrimination. … A public utility shall, upon reasonable
notice, furnish to all persons who may apply therefor and be reasonably entitled thereto,
suitable facilities and service, without discrimination and without delay.” Non-affiliated
potential shippers are included in “all persons who may … be reasonably entitled …[to]
suitable facilities and service, without discrimination….” The above discussion of Joint
Petitioners’ discriminatory practices, to the extent they violate federal statutory non-
134
discrimination requirements in relation to non-affiliated shippers, would be equally
violative of Section 8-101.
C. Conclusion and Consequences
The United States Supreme Court held in New Haven that the contracts in violation
of the ICA are against public policy and void. A void contract is a “contract that is of no
legal effect, so that there is really no contract in existence at all.” (BLACK’S LAW
DICTIONARY 326 (7th ed. 1999)) The shipping contracts Joint Petitioners have entered
into with affiliated marketers that violate the federal statute therefore may not be
considered in determining the actual demand for capacity on the pipelines.
It is not just evidence of need for the additional capacity Joint Petitioners seek to
implement that is relevant. The additional capacity of 530,000 bpd builds on the initial
capacity of 570,000 bpd Joint Petitioners cite. If portions of the initial capacity are not
legitimate, the overall capacity Joint Petitioners seek to implement is not warranted and
the additional pumping capacity may not be necessary at all.
The Commission should not grant the Joint Petitioners’ requested relief if they,
together with their parent Energy Transfer, have violated other laws directly related to the
subject matter of their petition and, in addition, have violated the PUA’s own anti-
discrimination provisions applicable to common carrier pipelines. The Commission
regularly requires a public utility to satisfy other applicable laws and regulations (e.g.,
environmental, species, safety) as a condition of granting a certificate of public
convenience and necessity or other requested relief. SOIL-SC-WK acknowledge that it
is not customary for the Commission to require a common carrier oil pipeline company to
demonstrate compliance with the ICA as a condition of receiving approval for new pipeline
135
facilities. SOIL-SC-WK also recognize that it is not the Commission’s responsibility to
enforce the ICA. SOIL-SC-WK also are not aware of a proceeding in which a pipeline’s
activities or facilities have been challenged as violative of PUA Section 8-101. In this case,
however, SOIL-SC-WK have demonstrated potential, if not probable, ICA violations. The
fact that Joint Petitioners initially refused to disclose requested information and
documents that exposed possible violations, together with misstating significant facts
directly relevant to ICA-compliance, should heighten the Commission’s suspicion and
concern.
That being the case, SOIL-SC-WK do not deem it necessarily appropriate for the
Commission itself to investigate and determine for itself the extent to which Joint
Petitioners’ activities, together with its parent company, have violated the ICA and the
Elkins Act. Nor do SOIL-SC-WK necessarily deem it appropriate for the Commission to
undertake such investigation under PUA Section 8-101. But those potentially non-
discriminatory activities should not be ignored. SOIL-SC-WK believe it is appropriate
under the circumstances for the Commission to seek FERC’s findings and conclusions
on this matter. The Commission could either directly seek such determination itself, or
require Joint Petitioners to apply for and obtain a declaratory order from FERC, similar to
the approach Magellan Midstream utilized. Having been made aware of these facts, the
Commission must decide if it wishes to sanction activity potentially violative of the ICA
and Elkins Act by granting the Joint Petition without further inquiry.
VII. CONCLUSION Joint Petitioners’ request for a Commission order approving their proposed project
under PUA Section 8-503 should be denied for a number of reasons. They have failed to
136
seek applicable certificate authority under PUA Section 15-401; they have failed to show
a public need for the project; they have not adequately provided for a reasonably safe
pipeline with its nearly doubled throughput volumes; and they have likely violated federal
and state non-discrimination statutes.
Dated: April 23, 2020 Respectfully submitted,
Save Our Illinois Land, Sierra Club, and William Klingele
John D. Albers William M. Shay Shay Law, Ltd. 230 SW Adams Street, Suite 310 Peoria, Illinois 61602 (309) 494-6155 telephone (309) 494-6156 facsimile [email protected] [email protected] Save Our Illinois Land and Sierra Club Paul C. Blackburn Staff Attorney Honor the Earth 607 Main Avenue Callaway, MN 56521
137
STATE OF ILLINOIS
ILLINOIS COMMERCE COMMISSION Dakota Access, LLC and Energy Transfer Crude Oil Company, LLC
: : :
Joint Petition for an Order under Section 8-503 of the Public Utilities Act for authority to install additional pumping stations and pumping facilities on existing certificated pipelines in the State of Illinois.
: : : : :
19-0673
NOTICE OF FILING Please take notice that on April 23, 2020, the undersigned attorney caused the Initial Brief of Save Our Illinois Land, Sierra Club, and William Klingele in this matter to be filed via e-Docket with the Chief Clerk of the Illinois Commerce Commission in the above-captioned proceeding.
___________ John D. Albers Attorney for
Save Our Illinois Land, Sierra Club, and William Klingele
CERTIFICATE OF SERVICE The undersigned attorney hereby certifies that he has caused the Initial Brief of Save Our Illinois Land, Sierra Club, and William Klingele in Docket No. 19-0673 to be served on each of the persons on the Service List by e-mail on April 23, 2020.
_ John D. Albers Attorney for
Save Our Illinois Land, Sierra Club, and William Klingele
138
ICC Docket 19-0673 Service List
John D. Albers, Atty. for SOIL, Sierra Club & Landowner Klingele Shay Law, Ltd. 230 SW Adams St., Ste. 310 Peoria, IL 61602 [email protected]
Amy C. Antoniolli, Atty. for Applicants Schiff Hardin LLP 233 S. Wacker Dr., Ste. 6600 Chicago, IL 60606 [email protected]
Glennon P. Dolan, Administrative Law Judge Illinois Commerce Commission 160 North LaSalle, Suite C-800 Chicago, IL 60601-3104 [email protected]
Bret A. Dublinske, Atty. for Applicants Fredrikson & Byron, P.A. 505 E. Grand Ave., Ste. 200 Des Moines, IA 50309 [email protected]
Ryan C. Granholm, Atty. for Applicants Schiff Hardin LLP 233 S. Wacker Dr., Ste. 7100 Chicago, IL 60606 [email protected]
Matthew L. Harvey Office of General Counsel Illinois Commerce Commission 160 N. LaSalle St., Ste. C-800 Chicago, IL 60601-3104 [email protected]
Steve Hughart, Business Manager/Financial Secretary IBEW Local 702 106 N. Monroe St. West Frankfort, IL 62896 [email protected]
Bina R. Joshi, Atty. for Applicants Schiff Hardin LLP 233 S. Wacker Dr., Ste. 7100 Chicago, IL 60605 [email protected]
Owen E. MacBride, Atty. for Applicants Schiff Hardin LLP 233 S. Wacker Dr., Ste. 7100 Chicago, IL 60606 [email protected]
Denise B. Mathews, President Save Our Illinois Land 218 N. Oak Ave. Barlett, IL 60103 [email protected]
139
Jeff E. Naville Midwest Region Laborers' International Union of North America #1 N. Old State Capitol Plz., Ste. 525 Springfield, IL 62701 [email protected]
Elizabeth T. Pearlman Natural Resources Defense Council 20 N. Wacker Dr., Ste. 1600 Chicago, IL 60606 [email protected]
Keegan Pieper, Associate General Counsel Dakota Access, LLC Energy Transfer Crude Oil Company, LLC 1300 Main St. Houston, TX 77002 [email protected]
Brett Seagle, Case Manager Illinois Commerce Commission 527 E. Capitol Avenue Springfield, IL 62701 [email protected]
William M. Shay, Atty. for SOIL, Sierra Club & Landowner Klingele Shay Law, Ltd. 230 SW Adams St., Ste. 310 Peoria, IL 61602 [email protected]
Marcy A. Sherrill Office of General Counsel Illinois Commerce Commission 160 N. LaSalle St., Ste. C-800 Chicago, IL 60601 [email protected]
Patrick K. Shinners, Atty. for IBEW, Local 702 Schuchat Cook & Werner 1221 Locust St., 2nd Fl. St. Louis, MO 63103 [email protected]
Tanya L. Young, Paralegal Schuchat Cook & Werner 1221 Locust St., Ste. 250 St. Louis, MO 63103 [email protected]
Paul C. Blackburn Honor the Earth 4145 20th Avenue S Minneapolis, MN 55407 [email protected]